  • TD Help forShutdown 2012Preliminary, will be updatedApril 18, 2012

  • Who~23 People from TD divided up to an equivalent of 12 people (FTE) spread out over the yearThis means we will be spread out through the year long shutdown~ people assigned as of 4/18/12 More people (probably most) should be assigned by Friday

  • Who & What* This is length of work on this list so far. It is NOT the length people will be involved in the shutdown. The percentage listed under FTE is for the shutdown (11 to 12 months)

    Crew 210.6*Weeks of workRemove 6 cooling tanks 1005Remove 129 add spool bake8Strip 32 line Remove lambertson4Set up and bake 3208MIRR40 Gap clearing move20Bake 210 to 2198Leader: Brad TennisFTED. Kelley 100%D. Assell 100%W. Robatzek (?)50%L. Kaminskas100%

  • What (lots of what)* Note: 86.8 is a TOTAL length of the work. It will be broken up and done in parallel. It is not an implied extension of the shutdown

    Crew 486.8*Weeks of workMI RF work160Remove 2.5 MHZ cavities15Remove 5MHZ Rf Cavities1Remove Barrier Bucket Cavity1Make hole for Cavity 4A us end5Make hole for Cavity 15A us end5Install 4 A2Install 15A2Build and install 40 foot filler3Rebuild 6 cavities160520 Vacuum large elliptical tube2540 C magnet replacement25Add spool to kicker area3MI 103 Ipm Work2Misc vac leak5Mi8 Multiwire 45Electron cloud 1032Electron Gun at MI622Replace Microwave absorber at 6021Install Carbon coated tube2Main Injector Corrosion repair4??4

  • Who & What* Note: 86.8 is a TOTAL length of the work. It will be broken up and done in parallel. It is not an implied extension of the shutdown

    Leader: John FeatherstoneFTEI. Samayavong 04363N80%James Karambis (C) 02560C50%George Steuer (C) 09702C50%

    Crew 4 (continued)86.8*Weeks of work

  • Who & What* This is length of work on this list so far. It is NOT the length people will be involved in the shutdown. The percentage listed under FTE is for the shutdown (11 to 12 months)

    Crew 632*Weeks of workDelivery, staging, fabrication at MI60160Leader: Henry GuslerFTEW. Ostrom 100%

  • Who & What* This is length of work on this list so far. It is NOT the length people will be involved in the shutdown. The percentage listed under FTE is for the shutdown (11 to 12 months)

    Crew 716*Weeks of workInjection Line MI 8 and MI 1060Assist with RR 3020Leader: Michael Rauchmiller (Rocky)FTEMark Chlebek (1st qtr.)25%Jeff Wittenkeller (1st & 3rd qtr.)50%Marco Battistoni (2nd qtr.)25%Glenn Smith (2nd & 4th qtr.)50%

  • Who (Friday?)

    FTEChris Baker (2nd qtr.)25%Nathan Bremer (4th qtr.)25%Brent Stone (1st & 3rd qtr.)50%D. Plant 40%S. Sorenson10%Rick Espinoza (1st & 3rd qtr.)50%D. Howard 40%S. Sanchez10%J. Greskoviak50%B. Niels 100%S. Hobson20%

  • WhoDave Augustine (ALL)Ext: 4451Pager (630) [email protected] McCormickExt: 3691Pager (630) [email protected] Kiemschies (TD)Ext: 3925Cell (630) [email protected] GattusoExt: 6331Pager (708) [email protected]://www-cons.fnal.gov/

  • WhoCrew 4John FeatherstoneExt: 5605Pager (630) [email protected] 6Henry GuslerExt: 2675Pager (630) [email protected] 2Brad TennisExt: 2807Pager (630) [email protected] 7Michael Rauchmiller (Rocky)Ext: 3011Pager (360) [email protected]

  • WhereMI/RR for most work but all accelerators in access (eventually)There WILL be permanent shutdown keys (i.e. keys that you dont have to turn in at the end of the day) for mostLeaders will organize (more information later).Otherwise (however) keys will come from the MCR

  • Location of the MCR

  • Layout of MCR

  • LOTO (will be job lock boxes)

  • WhenBeam off Sunday April 29th at MidnightRadiation surveys begin Monday morningMost enclosures will be available for access Tuesday May 1st.

    But what about us?Depends on where you are going. Depends on how long you were allocated for (i.e. the job might start day 1 but you might not start until month 3Cons schedule can be seen here:http://www-cons.fnal.gov/install.pdf

  • WhyNOvA jobs will have NOvA task numbers (425)Will try to minimize the tasks numbersStill working on approval process. It doesnt sound like youll have to hand a sheet to anyone. Will probably just be an extra approval needed (local leader & real boss)

  • Good Luck!Stay Safe!This presentation can be found at:http://tdserver1.fnal.gov/AcceleratorSupport/Shutdown_2012/