TDC2/TCC2 WGstatus report in EATM
S. Evrard on behalf of the TDC2/TCC2 WG18.06.2013
1. WP breakdown2. TDC2/TCC2 Visit on June 4th
3. Next issues4. ENTM agenda
Work package breakdownActivity WPA WDP DIMR Collective dose
(mSv)Transport 15/01 OK
Vacuum 22/01 OK
Targets and collimators 29/01 OK
XTAX tables 05/02 OK OK 10.5
Cooling and Ventilation 06/02 OK
Civil Engineering 15/02
Magnets 26/02 OK
LV electricity 19/03 OK
Cabling 19/03
RP issues 02/04 OK
Beam instrumentation 09/04 OK
Survey
Visit on June 4th: TCSC dose rate measurement by means of Telerob
TCSC contact : 11 mSv/h
T4 measurement from RP – 4th June 2013
418th June 2013M. Calviani / E. Nowak - TCC2TDC2 WG meeting
Ratio D/U ~ 1.8
New CE issue: the mezzanine floor is not water tight
Cabling work: tough working conditions
Next actions, topics, issues• Laser scan of TA801 (Thursday 20/06) BE-ABP + DGS-RP• Survey Work package EN-MEF + BE-ABP• New dose rate measurement (Friday 21/06, TBC) EN-HE + DGS-RP• Tech. Spec. for:
– Underground IT network EN-MEF + IT-CS– Chilled pipe removal (asbestos ?) EN-CV– Dismantling works EN-MEF + DGS-RP
• TCSC and Target boxes and monitor storage in B.954 GS-IS• PVC insulation analysis TE-EPC + EN-MME• Mezzanine floor water tighness issue GS-SE + EN-CV• Risk analysis (cranes BA80, B954) EN-HE• Shielded containers for target boxes and monitors EN-STI + EN-MEF + DGS-RP• ENTM on July 2nd all WG members
ENTM agenda July 2nd
• Rationales for TDC2 Consolidation (S. Evrard)• Planned Activities (E. Harrouch)• ALARA Optimisation (S. Evrard)• Transport Issues (J-L Grenard)• Waste management (E. Harrouch)• Risk analysis (E. Harrouch)