Capital Improvement Program 1 TDP Meeting Friday, February 12, 2016
Transcript
Page 1: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Capital Improvement Program

1

TDP MeetingFriday, February 12, 2016

Page 2: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Capital Improvement Program

2

Transportation Department Vision & Mission Statement:

City of Tampa BudgetAvailable Online:

http://www.tampagov.net/budget

Page 3: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Capital Improvement Program

3

Page 4: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Capital Improvement Program

4

Page 5: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Capital Improvement Program

5

Cass St. & Tyler St. Two‐Way Conversion:

Project converts Cass and Tyler streets to two‐way, restoring the street grid in downtown and transforming Cass into a central spine throughout the city as outlined in the InVisionTampa Center City plan.  The project includes the downtown portion of the East‐West Green Spine cycle track from the bridge to Nebraska Ave.  The project also requires coordination with the Intown/Framework Group, LLC development for interim improvements west of Ashley Dr.  The developer is to design/construct roadway improvements west of Ashley Dr.  

PhaseCass St./Tyler St. 

Two‐Way ConversionDesign & Permitting Nov‐13 Nov‐14

Bid Aug‐14 Dec‐14Construction Jan‐15 Jul‐16Closeout Jul‐16 Aug‐16

Page 6: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Capital Improvement Program

6

Downtown Traffic Modeling

Downtown Tampa in the future is expected to have a significant influx of traffic during the AM and PM peak hours due to an increase in the number of access points, specifically from the I‐275 and I‐4 Express Lanes. These new access points are expected to cause traffic pattern changes internally along the local Downtown Tampa street network. 

Category Name PO# Contract # Amount

Phase 1 American Cons. WO #1; WA #2 $83,702

Page 7: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Capital Improvement Program

7

Green Spine• 3.4 mile urban trail/cycle track along Cass Street, Nuccio Parkway and 15th Street • Part of the InVision Tampa Center City Plan to provide a pedestrian and bicycle access 

between N. Hyde Park, Downtown and Ybor City• Provides a safe and accessible bicycle connection to the Tampa Riverwalk• Downtown segment is part of Tyler Street and Cass Street Two‐Way conversion project

Phase Firm CostFundin

gSchedule

Start FinishConcept Dev. ICON $59,985 City July 2015 Feb 2016

Design Procurement

Mar 2016 July 2016

Design (est.) TBD $300,000 City July 2016 Dec 2017Construction 

(est.)TBD

$1,900,000

TBD

TBD TBDCEI (est.) City $150,000 TBD

Unknowns $350,000City/TB

D

Page 8: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Capital Improvement Program

8

Streetcar Extension and Modernization StudyIn December 2014, the Hillsborough Area Regional Transit Authority (HART) completed a study to explore the general feasibility of constructing a streetcar extension through downtown Tampa to the Marion Transit Center.  The study also identified improvements required to upgrade the existing system to accommodate modern street or light rail transit vehicles. Based on the results of the feasibility study and the Streetcars’s potential to serve the influx of resident and business commuters in the downtown and Channelside areas, the City of Tampa and the Florida Department of Transportation have partnered to leverage funding resources to further explore the extension and modernization of the streetcar system by performing an Alternatives Analysis Study.  This level of analysis will recommend a preferred corridor that can be carried into a Project Development & Environmental (PD&E) Study.

Phase Firm Amount Funding ScheduleStart Finish

Alternative Analysis 

Study/PD&E Study

TBD $1.25 M FDOT & City of Tampa

Spring 2016

TBD

Design Phase TBD $24 M (est.)

TBDTBD TBD

Right‐of‐Way Phase

TBD TBD TBD

Construction  TBD $121 M (est.)

TBD TBD TBD

Page 9: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Capital Improvement Program

9

Downtown Train Horn Quiet Zone

In 2005 the Federal Railroad Administration issued a rule exception for local agencies or communities to establish quiet zones at railroad crossings, which waive the railroad horn sounding requirement if full‐width crossing gates, flashing lights and other safety devices are installed.  

This project consists of preparation of an engineering study to determine the feasibility and cost to implement train horn quiet zones within the City.   The study area includes InterbayDistrict, Central Business District, and Ybor City.  Study will also include public involvement with property owners and area stakeholders.

Phase Agency Cost FundingSchedule

Start Finish

Design CSX $135,000FDOT Grant 

& Downtown CRA 

Nov 2015April2016

Construction CSX/City $2,570,221June 2016 Nov 2017

TOTAL $2,705, 221

Page 10: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Capital Improvement Program

10

• Laurel St. Bridge Rehabilitation

The Laurel Street Bridge is a 1926 historic steel structure single‐span bascule bridge that is an important crossing over navigable waters of the Hillsborough River in downtown Tampa.  This rehabilitation, which will extend the bridge’s useful life by 10 – 15 years.

Phase Firm Amount Funding ScheduleStart Finish

Design

KCA

$91,585

LOGT

Feb 2004 Feb 2007Stimulus Funding Mod. $24,760 Aug 2010 Oct 2010Plans Update/Post‐

Dsgn$49,802

June 2014

Feb 2015

Steel Member Inspection

$34,954 Jan 2015 Feb 2017

Bid Phase ‐ ‐ April 2015 July 2015

ConstructionRoyal Bridge, 

Inc. $3,246,79

0Aug 2015

Feb 2017Coating Inspection GPI $49,570Welding Inspection Ardaman $27,090

CEI In‐House (CAD) $112,800OH (Constr.) In‐House (CAD) $260,000

Page 11: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Impact Fees

11

Transportation Impact Fees‐ The City of Tampa Ordinance 9362A, passed in 1986, imposes an impact fee on land development in the city. Fees are based upon the type of development and  the development capacity.

Revenue collected must be used for roadway CAPACITY projects within the development district.

Page 12: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Impact Fees

12

Downtown is in Impact Fee District #1 

(Central Business District)

Page 13: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Impact Fees

13

ResidentalSingle Family Detached

Under 1500 S.F. du $7161500 - 2499 du $9552500 - S.F.& Over du $1,127

Single Family Semi-Detached du $726Mobile Home du $447Multi-Family

1-2 Stories du $4853 Stories And Over du $373

ACLF/Retirement Home du $250LodgingHotel/Motel room $1,874IndustrialGeneral Light Industrial 1000 s.f. $1,882General Heavy Industrial 1000 s.f. $513Warehouse 1000 s.f. $1,676Mini Warehouse 1000 s.f. $958

Utilities employee $239MedicalNursing Home bed $659Hospital bed $5,271OfficeUnder 100,000 S.F. 1000 s.f. $6,056100,000' -199,999 S.F. 1000 s.f. $4,892200,000 S.F. And Over 1000 s.f. $3,729Research Facility 1000 s.f. $1,813

RetailConvenience 1000 s.f. $4,024

Under 50,000 S.F. 1000 s.f. $2,85350,000 -99,999 S.F. 1000 s.f. $3,339100,000-199,999 S.F. 1000 s.f. $3,586200,000-299,999 S.F. 1000 s.f. $3,766300,000-399,999S.F. 1000 s.f. $3,883400,000-999,999 S.F. 1000 s.f. $3,6881,000,000 S.F. & Over 1000 s.f. $3,528Wholesale 1000 s.f. $693

Furniture 1000 s.f. $72Hardware/Paint Store 1000 s.f. $1,922

RestaurauntRestauraunt 1000 s.f. $2,143Fast Food With Drive Thru 1000 s.f. $3,784Services Bank 1000 s.f. $7,009Bank With Drive Thru 1000 s.f. $7,963Savings & Loans 1000 s.f. $2,530Insurance 1000 s.f. $3,934Day Care Center 1000 s.f. $2,566Service Station/Car Wash 1000 s.f. $20,335

Page 14: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Impact Fees

14

Recreation

General Recreationparking space $436

Golf Courseparking space $2,257

Marina slip $1,278Racquet Club/Health Club 1000 s.f. $1,009InstitutionalElementary School student $335Jr. High/Middle School student $335High School student $469Junior Technical College student $536College student $805Church 1000 s.f. $904General Aviation flight $1,415Civic Center 1000 s.f. $11,558

Page 15: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Impact Fees

15

Downtown ATISAdvanced Traveler Information System

The Tampa downtown area hosts an increasing number of sporting events, festivals, concerts and conventions year round at major venues including the Tampa Bay Times Forum, the Tampa Convention Center, The Straz Center for the Performing Arts and Curtis Hixon Park.   The vision for Tampa downtown is to create a multi‐use area which fosters businesses, residences, restaurants and major event venues.   It will be necessary to provide efficient traffic management for inbound and outbound traffic for all events. This ATIS will include static and dynamic message signs (DMS) installed at strategic locations.

FUNDING PLAN

Local Option Gas Tax

$334,337 $77,383 $470,272 $881,992

Impact Fee $316,000 $315,417

Total Funding $392,800 $470,272 $0 $0 $0 $0 $863,072

Project was shelved due to advances in technology.  The City now has a contract with Waze.  We provide information about street closures and special events directly to them.

Page 16: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Multimodal Fees

16

Multi‐modal Transportation Impact Fees are collected similar to impact fees. 

However, revenues can be spent on projects other than roadway capacity, such as:

• Pedestrian• Sidewalks

• Bicycle• Bike Lanes

• Complete Streets• Transit

• Vehicles• Bus stops, Shelters• Road network

Page 17: TDP Meeting Friday, February 12, 2016€¦ · Concept Dev. ICON $59,985 City July 2015 Feb 2016 Design Procurement Mar 2016 July 2016 Design (est.) TBD $300,000 City July 2016 Dec

Thank You! Questions?

17