East Mar There are multiple construction crews working on the TDS fiber project. The White Construction crews are working in the area designated EA-2. They will start in the north portion of the area before moving south to the residential area.Their subcontractor will be working in the area designated BA-6 until that area is complete. ¯ City of Stevens Point Engineering Dept.- August 2019 0 250 500 Feet 0 250 500 Feet ¯ Construction Plan for August 26th- September 6th TDS Fiber Project EA-2 BA-6 Fiber Completed Current Fiber Work Current Project Area Future Fiber Work
Transcript
Page 1: TDS Fiber Project - Stevens Point

East Maria Dr

There are multiple construction crews working on the TDS fiberproject. The White Construction crews are working in the areadesignated EA-2. They will start in the north portion of the area

before moving south to the residential area.Their subcontractor willbe working in the area designated BA-6 until that area is complete.

¯City of Stevens Point Engineering Dept.- August 2019

0 250 500Feet

0 250 500Feet

¯

Construction Plan for August 26th- September 6th

TDS Fiber Project

EA-2BA-6

Fiber CompletedCurrent Fiber WorkCurrent Project Area

Future Fiber Work

Recommended