East Maria Dr
There are multiple construction crews working on the TDS fiberproject. The White Construction crews are working in the areadesignated EA-2. They will start in the north portion of the area
before moving south to the residential area.Their subcontractor willbe working in the area designated BA-6 until that area is complete.
¯City of Stevens Point Engineering Dept.- August 2019
0 250 500Feet
0 250 500Feet
¯
Construction Plan for August 26th- September 6th
TDS Fiber Project
EA-2BA-6
Fiber CompletedCurrent Fiber WorkCurrent Project Area
Future Fiber Work