Date post: | 22-Dec-2015 |
Category: |
Documents |
Upload: | lee-morton |
View: | 215 times |
Download: | 0 times |
TeamMembers
Architect:
Angela RibasUC Berkeley
Engineer:
Matthias NieblingBauhaus-University Weimar, Germany
Construction Manager:
Kevin CoyneStanford University
Product Manager:
Torsten SchluesselburgFH Aargau, Switzerland
Owner: David SteinbachWeimar, Germany
CEE 222 - Computer Integrated AEC (2002)
Team members of theTeam members of the
Location
CEE 222 - Computer Integrated AEC (2002)
• BAY AREA / CITY OF SAN FRANCISCO
• UNIVERSITY OF SAN FRANCISCO
• MAIN CAMPUS AT FULTON STREET
CAMPUS LOCATION CAMPUS LOCATION
SURROUNDING:
• GOLDEN GATE PARK
•RESIDENTIAL NEIGHBORHOOD
•HILL AREA
(HUGE GREEN AREA)
CEE 222 - Computer Integrated AEC (2002)
SITE MAP
SURROUNDING SURROUNDING BUILDINGSBUILDINGS
Textures
SURROUNDING SURROUNDING BUILDINGSBUILDINGS
CEE 222 - Computer Integrated AEC (2002)
SITE SITE
PANORAMIC VIEW
SITE MAP
•FLAT GROUND
•FACING FULTON STREET
N
Building location
A_First concept
CEE 222 - Computer Integrated AEC (2002)
FIRST ARCHITECTURAL CONCEPTFIRST ARCHITECTURAL CONCEPT
FOREST “AN OPEN AND FRIENDLY
SPACE WHERE PEOPLE CAN
INTERACT”
CORE VIEW
Concept
CEE 222 - Computer Integrated AEC (2002)
FIRST ARCHITECTURAL CONCEPT
FIRST FLOOR PLAN Plan
FIRST ARCHITECTURAL CONCEPT
CEE 222 - Computer Integrated AEC (2002)
FIRST ARCHITECTURAL CONCEPT
BASEMENT
FIRST ARCHITECTURAL CONCEPT
Plan
CEE 222 - Computer Integrated AEC (2002)
FIRST ARCHITECTURAL CONCEPT
SECOND FLOOR
FIRST ARCHITECTURAL CONCEPT
Plan
CEE 222 - Computer Integrated AEC (2002)
FIRST ARCHITECTURAL CONCEPT
THIRD FLOOR
FIRST ARCHITECTURAL CONCEPT
Plan
CEE 222 - Computer Integrated AEC (2002)
FIRST ARCHITECTURAL CONCEPT
SECTION AA
A A
B B
C
C
SectionsSECTION CCSECTION BB
N
FIRST ARCHITECTURAL CONCEPT
CEE 222 - Computer Integrated AEC (2002)
FIRST ARCHITECTURAL CONCEPT
SOUTH FACADE
NORTH FACADE
SOUTH FACADE
EAST FACADE
NORTH FACADE
N
WEST FACADE Elevations
TOP VIEW
FIRST ARCHITECTURAL CONCEPT
Loading assumptions
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEMSTRUCTURAL SYSTEM
Load Assumptions
LIVE LOADS:
• Storage 125 psf 6.00 kN/m²• First floor corridors / Stairs / Lobbies 100 psf 4.79 kN/m²• Corridors above first floor 80 psf 3.83 kN/m²
• Classrooms 40 psf 1.92 kN/m²
• Auditorium, Offices 50 psf 2.40 kN/m²
• RAIN LOAD 30 psf 1.44 kN/m²
DEAD LOADS:
• Finishes, Lights 10 psf 0.48 kN/m²• HVAC installation (ducts, etc) 5 psf 0.24 kN/m²
• Partition walls 20 psf 0.96 kN/m²
LATERAL LOADS:
• Wind load 13 psf 0.64 kN/m²
Concrete Walls
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEMSTRUCTURAL SYSTEM
Concrete walls
Structural elements
Concrete walls: 12“
Typical element sizes:
Girders
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEMSTRUCTURAL SYSTEM
Girders
Concrete walls
Structural elements
Possible sections of a column
typical column / girder connection
16“
15“
2 former Solutions
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEMSTRUCTURAL SYSTEM
Solution 1
Solution 2
•Composite floor deck
•Bays of 30 x 30 ft
•Advantage: only 4 columns needed
•Steel Frame Structure
•Spans of 15 ft (concrete elements) and
30 ft (steel frames)
•Advantage: slab can be thin (reduction of dead loads)
Girders
Concrete walls
Former solutions
Typical element sizes
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEMSTRUCTURAL SYSTEM
Girders
Secondary
Beams
Concrete wallsMost economic compromise:takes the advantages of both structural solutions
• only 4 columns• reduced slab thickness
Typical element sizes:
• Slab: Composite floor deck, total height: 4 ¾“• Secondary beams: 8“ (HEA 200)
• Small Girders: 12“ (HEB 280)
• Large Girders: 15“ (HEB 360)
•Concrete walls: 12“
Columns (in basement): ø 16“ with a steel thickness of 1/3“
Typical element sizes
Gravity Load Path1Gravity Load Path1
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEMSTRUCTURAL SYSTEM
Girders
Secondary
Beams
Concrete walls
Gravity Load Path
Gravity Load Path2Girders
Secondary
Beams
Concrete walls
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEMSTRUCTURAL SYSTEM
Gravity Load Path
Gravity Load Path3
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEMSTRUCTURAL SYSTEM
Girders
Secondary
Beams
Concrete walls
Gravity Load Path
Gravity Load Path4
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEMSTRUCTURAL SYSTEM
Girders
Secondary
Beams
Concrete walls
Gravity Load Path
Gravity Load Path5
STRUCTURAL SYSTEMSTRUCTURAL SYSTEMCEE 222 - Computer Integrated AEC (2002)
Gravity Load Path
Foundation MainBuilding
STRUCTURAL SYSTEMSTRUCTURAL SYSTEMCEE 222 - Computer Integrated AEC (2002)
Foundation – Main Building
Column loadsLine loads
Foundation will be:• a ground plate with a height of 15“
• at the positions of concentrated loads (columns): strengthening of the ground plate up to 24“
Foundation Auditoroium
STRUCTURAL SYSTEMSTRUCTURAL SYSTEMCEE 222 - Computer Integrated AEC (2002)
Foundation - Auditorium
Foundation will be:
• the floor of the auditorium is declined.
• using a stepping instead of declination -> horizontal loads (out of gravity loads) are avoided
Line loads
• a ground plate with a height of 15“
• at the positions of concentrated loads (columns): strengthening of the ground plate up to 24“
Lateral Load Path LeftSymmetrical plan:
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEMSTRUCTURAL SYSTEM
Concrete walls
• no additional moment occurs
Lateral Load Paths
Lateral Load Path Right
S
M
(M=N·e)
e
N
N
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEMSTRUCTURAL SYSTEM
Concrete wallsAsymmetrical plan:
• additional moment• can be compensatet by
two normal forces N
Lateral Load Paths
Outside Wall
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEMSTRUCTURAL SYSTEM
Outside concrete walls:
• do not act as a slab because of number of openings• it is necessary to build a moment resisting
frame structure
• high amount of reinforcement is needed
Lateral Load Paths
A1_C_Slide1
CEE 222 - Computer Integrated AEC (2002)
Existing Buildings
Site Access (Fulton)
Project Office
Material Laydown & Storage
Building Perimeter
Site Perimeter
Crane
Site plan
CONSTRUCTION SITE PLANCONSTRUCTION SITE PLAN
A1_C_Slide2
CEE 222 - Computer Integrated AEC (2002)
EXCAVATION:
• 18’ Hard Strata Excavation – No retaining wall necessary
FOUNDATION:
• Poured Reinforced Concrete Mat Slab w/ Column Footings
SUPERSTRUCTURE A:
• Reinforced Concrete Moment Frame
• Cast-in-Place Reinforced Concrete Shear Walls
• Cast-in-Place Composite Concrete/Steel Floor System
SUPERSTRUCTURE B:
• Steel Moment Frame
• Cast-in-Place Composite Concrete/Steel Floor System
EXTERIOR FACADE:
• Concrete and Glass Curtain Wall System
CONCEPT #1: CONSTRUCTIONCONCEPT #1: CONSTRUCTION
Materials and Methods
A1_C_Slide3
CEE 222 - Computer Integrated AEC (2002)
Sitework $33,423.00Substructure $18,667.00Foundations $313,856.00Superstructure $773,670.00Exterior Façade $801,820.00Interiors $454,850.00Finishes $132,658.00Bldg. Specialties $481,540.00MEP $2,047,950.00Subtotal $5,058,434.00
Contingency 10% $505,844.00Gen. Cond. 10% $505,844.00Subtotal $1,011,688.00
CONCEPT #1: COST
Sitework $33,423.00Substructure $18,667.00Foundations $313,856.00Superstructure $625,789.00Exterior Façade $801,820.00Interiors $454,850.00Finishes $132,658.00Bldg. Specialties $481,540.00MEP $2,047,950.00Subtotal $4,910,553.00
Contingency 10% $491,055.30Gen. Cond. 10% $491,055.30Subtotal $982,110.60
Structural Solution #1: Structural Solution #2:
• Concrete Moment Frame
• Concrete Shear Walls
• Steel Moment Frame
• Concrete Shear Walls
Total Cost = $6,070,122 Per S.F. = $164.06
CONCEPT #1: COST
Total Cost = $5,892,664 Per S.F. = $159.26
A1_C_Slide2
CEE 222 - Computer Integrated AEC (2002)
CONCEPT #1: SCHEDULECONCEPT #1: SCHEDULEID Task Name Duration
1 Site Work 8 wks
2 Substructure 8 wks
3 Foundation 6 wks
4 Milestone #1 - Foundation 1 day?
5 SuperStructure 16 wks
6 Milestone #2 - Frame 1 day?
7 Exterior Façade 8 wks
8 MEP 12 wks
9 Interior 10 wks
10 Milestone #3 - Move-In 1 day?
3/1
6/21
9/30
8/309/69/139/209/2710/410/1110/1810/2511/111/811/1511/2211/2912/612/1312/2012/271/31/101/171/241/312/72/142/212/283/63/133/203/274/34/104/174/245/1 5/85/155/225/296/56/126/196/267/37/107/177/247/318/78/14August September October November December January February March April May June July August
ID Task Name
1 Site Work
2 Substructure
3 Foundation
4 Milestone #1 - Foundation
5 SuperStructure
6 Milestone #2 - Frame
7 Exterior Façade
8 MEP
9 Interior
10 Milestone #3 - Move-In
3/1
5/10
9/30
7/57/127/197/268/2 8/98/168/238/309/69/139/209/2710/410/1110/1810/2511/111/811/1511/2211/2912/612/1312/2012/271/31/101/171/241/312/72/142/212/283/63/133/203/274/34/104/174/245/1 5/85/155/225/296/56/126/196/267/37/10July August September October November December January February March April May June July
Start: 9/20/2015 – End: 7/7/2016
Conceptual Schedules
Start: 9/20/2015 – End: 7/7/2016
Schedule Duration = 9 months
Schedule Duration = 9 months
MILESTONE #1: 3/01/16 – Foundation Complete MILESTONE #2: 5/10/16 – Shell Complete MILESTONE #3: 9/30/16 – Move-In
A_Second concept
CEE 222 - Computer Integrated AEC (2002)
SECOND ARCHITECTURAL CONCEPTSECOND ARCHITECTURAL CONCEPT
CONCEPTUAL IDEAS
• Plaza
• Suspended box
• Open auditorium below
• Bridge idea for suspension
• Owner requested round forms
•“The bridge curve”
• access and circulation issues Progress
• “The crane” - A / E idea
• Suspended auditorium
• very expensive
CEE 222 - Computer Integrated AEC (2002)
SECOND ARCHITECTURAL CONCEPT
PLAZA “A PLAZA
SURROUNDED BY WATER”
SECOND ARCHITECTURAL CONCEPT
Concept
CEE 222 - Computer Integrated AEC (2002)
SECOND ARCHITECTURAL CONCEPT
FIRST FLOOR PLAN
SECOND ARCHITECTURAL CONCEPT
Plan
CEE 222 - Computer Integrated AEC (2002)
SECOND ARCHITECTURAL CONCEPT
BASEMENT PLAN
SECOND ARCHITECTURAL CONCEPT
Plan
CEE 222 - Computer Integrated AEC (2002)
SECOND ARCHITECTURAL CONCEPT
SECOND FLOOR PLAN
SECOND ARCHITECTURAL CONCEPT
Plan
CEE 222 - Computer Integrated AEC (2002)
SECOND ARCHITECTURAL CONCEPT
THIRD FLOOR PLAN
SECOND ARCHITECTURAL CONCEPT
Plan
CEE 222 - Computer Integrated AEC (2002)
SECOND ARCHITECTURAL CONCEPTSECOND ARCHITECTURAL CONCEPT
SOUTH / NORTH FACADEEAST / WEST FACADE
SECTION AA
S / N FACADE
E / W FACADE
N
AA
TOP VIEW
Section / Elevations
A2_E_SOLUTION1
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #1STRUCTURAL SYSTEM #1
Architectural sketch
Engineering model
• Width: 100 ft
• Length: 145 ft
Constraints
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #1STRUCTURAL SYSTEM #1
Solution 1• the whole building is based on 4 large columns at the corners• an additional 4 columns in the core • as well as concrete walls in the core
(Elevators, Restrooms)
Gravital Structure
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #1STRUCTURAL SYSTEM #1
In each slab there will be 4 large girders• to collect gravity loads and transport them to theframework and the core columns
Girders
• Additionally, secondary beams will be usedto reduce the span of the slab
Secondary
Beams
Gravity Structure
Framework
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #1STRUCTURAL SYSTEM #1
Realizing the large span by a huge framework:• to collect gravity loads and transport lateral loads• to reduce deformation of the slabs
Girders
Secondary
Beams
Gravity Structure
Element sizesFramework
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #1STRUCTURAL SYSTEM #1Typical Element sizes:
Girders
Secondary
Beams
• Slab: Composite floor deck, total height: 4 ¾“ (Span ~11ft)• Secondary beams: 8“ (HEA 200)
• Core Columns: 20“ x 20“
• Large Girders: 24 1/2“ (HEM 600)
• Small Girders: 14“ (HEB 340)
• Outside Columns: 40“ x 40“ (Assumption)
Typical element sizes
GravityLoadPath
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #1STRUCTURAL SYSTEM #1
• from secondary beams to the girders• from girders to the outside framework and the inner core
Forces are transported:
• by vertical elements into the ground
Gravity Load Path
Lateral Structure
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #1STRUCTURAL SYSTEM #1
Stiffening the inside of the box by EBF‘s (eccentric braced frames):• Advantage – in case of an earthquake, EBF‘s can absorb some of energy
Lateral Resisting Structure
• Note – detailed calculations will need to be completed to determine the feasibility of this solution(due to massive framework)
LateralLoadPath_Left
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #1STRUCTURAL SYSTEM #1
Symmetrical plan:
• no additional moments occur
Lateral Load Paths
LateralLoadPath_Top
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #1STRUCTURAL SYSTEM #1
Symmetrical plan:
• no additional moments occur
Lateral Load Paths
Foundation Columns
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #1STRUCTURAL SYSTEM #1Foundation of the columns is critical because of seismic issues:
• the outside columns must be able to rock -> base isolation system
• the core columns are supposed to be thinner and more ductile, allowing for deformation in case of an earthquake
• these two columns areconnected to the wall of the
auditorium
Foundation
FoundationBasement
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #1STRUCTURAL SYSTEM #1Foundation of the basement:
• will be a ground plate
• in the core, a strengthening of the ground plate becomes necessary (columns)
Foundation
A2_E_SOLUTION2
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #2STRUCTURAL SYSTEM #2
Solution 2• additional columns are used to reduce the span• the building becomes more economical
InsideElements
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #2STRUCTURAL SYSTEM #2
Stiffening inside of the box by EBF‘s (eccentric braced frames)
Lateral Resisting Structure
OutsideElements
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #2STRUCTURAL SYSTEM #2
Stiffening also the outside of the box by EBF‘s:
• with this structural solution there are shorter spans of about 30 ft.• EBF‘s can absorb energy in case of an earthquake• Columns are not stressed with the entire earthquake energy
Lateral Resisting Structure
LoadPaths and Foundation
CEE 222 - Computer Integrated AEC (2002)
STRUCTURAL SYSTEM #2STRUCTURAL SYSTEM #2
Load paths and foundation are similar to the first structural solution
A2_C_Slide1A1_C_Slide2
CEE 222 - Computer Integrated AEC (2002)
CONCEPT #2: CONSTRUCTIONEXCAVATION:
• 18’ Hard Strata Excavation – No retaining wall necessary
FOUNDATION A:
• Concrete Slab and Base Isolation System
FOUNDATION B:
• Poured Reinforced Concrete Mat Slab w/ Column Footings
SUPERSTRUCTURE A:
• Exterior Steel Truss System
• Interior Steel Eccentrically Braced Frame (EBF) System
• Cast-in-Place Composite Concrete/Steel Floor System
SUPERSTRUCTURE B:
• Exterior/Interior Steel EBF System
• Cast-in-Place Composite Concrete/Steel Floor System
EXTERIOR FACADE:
• Concrete and Glass Curtain Wall System
CONCEPT #2: CONSTRUCTION
Materials and Methods
A1_C_Slide3A2_C_Slide2
CEE 222 - Computer Integrated AEC (2002)
CONCEPT #2: COST
Sitework $33,423.00Substructure $22,234.00Foundations $345,000.00Base Isolation $617,500.00Superstructure $610,000.00Exterior Façade $750,000.00Interiors $467,000.00Finishes $145,000.00Bldg. Specialties $475,000.00MEP $2,112,000.00Subtotal $5,577,157.00
Contingency 12% $669,258.84Gen. Cond. 10% $557,715.70Subtotal $1,226,974.54
Sitework $33,423.00Substructure $22,234.00Foundations $345,000.00Superstructure $550,000.00Exterior Façade $750,000.00Interiors $467,000.00Finishes $145,000.00Bldg. Specialties $475,000.00MEP $2,112,000.00Subtotal $4,899,657.00
Contingency 12% $587,958.84Gen. Cond. 10% $489,965.70Subtotal $1,077,924.54
Structural Solution #1: Structural Solution #2:
• Steel Truss/EBF system
• Base Isolation System
• Exterior/Interior EBF system
Total Cost = $6,804,132 Per S.F. = $183.90
Total Cost = $5,977,581 Per S.F. = $161.56
CONCEPT #2: COST
A1_C_Slide2
CEE 222 - Computer Integrated AEC (2002)
CONCEPT #2: SCHEDULE
ID Task Name
1 Site Work
2 Substructure
3 Foundation
4 Milestone #1 - Foundation
5 SuperStructure
6 Milestone #2 - Frame
7 Exterior Façade
8 MEP
9 Interior
10 Milestone #3 - Move-In
3/29
6/21
9/30
8/98/168/238/309/69/139/209/2710/410/1110/1810/2511/111/811/1511/2211/2912/612/1312/2012/271/31/101/171/241/312/72/142/212/283/63/133/203/274/34/104/174/245/1 5/85/155/225/296/56/126/196/267/37/107/177/247/318/78/14August September October November December January February March April May June July August
Schedule Duration = 9.5 months
ID
1
2
3
4
5
6
7
8
9
10
2/2
4/12
9/30
8/98/168/238/309/69/139/209/2710/410/1110/1810/2511/111/811/1511/2211/2912/612/1312/2012/271/31/101/171/241/312/72/142/212/283/63/133/203/274/34/104/174/245/15/85/155/225/296/56/126/196/267/37/107/177/247/318/78/148/218/289/49/119/189/2510/210/9August September October November December January February March April May June July August September October
Schedule Duration = 8 months
CONCEPT #2: SCHEDULE
Conceptual Schedules
MILESTONE #1: 3/29/16 – Foundation Complete MILESTONE #2: 6/21/16 – Shell Complete MILESTONE #3: 9/30/16 – Move-In
Start: 9/20/2015 – End: 7/17/2016
Start: 9/20/2015 – End: 5/21/2016
Decision_Forest
CEE 222 - Computer Integrated AEC (2002)
DECISION MATRIXDECISION MATRIX
Costs:
$5.9 MilCONS: •More conventional design
•Only one main access•Relatively simple box - structure
A
E
C
•Daylight / Green area inside•No extended footprint•Owners preference
•Large glass facade•Interesting retractable roof
A
E
C
PROS:
FOREST
•Steel is efficient and cost effective
•Retractable roof / Glass facade costly
•Straightforward construction sequencing
Decision_Plaza
CEE 222 - Computer Integrated AEC (2002)
DECISION MATRIX
Costs:
$6.8 MilCONS:A
E
C
A
E
C
PROS:
PLAZA
•More unusual design•Two accesses•Daylight inside
•Extended footprint•Space on first floor wasted
•A lot of details must be solved
•Again: interesting structure with A LOT of details
•Open ground floor
•Interesting structure (large spans)
•Base Isolation System costly
•EBF system is cost andschedule efficient
DECISION MATRIX
Matrix
CEE 222 - Computer Integrated AEC (2002)
DECISION MATRIX
Costs:
•Daylight / Green area inside
$5.9 Mil $6.8 Mil
PROS:
CONS:
•No extended footprint•Owners preference
•More conventional design•Only one main access
•Large glass facade•Interesting retractable roof
•Relatively simple box - structure
•More unusual design•Two accesses•Daylight inside
•Extended footprint•Space on first floor wasted
•Interesting structure (large spans)•A lot of details must be solved
•Again: interesting structure
•Open ground floor
with a lot of details
Comparison
•EBF system is cost and
•Base Isolation System costly
•Steel is efficient and cost•Straightforward construction
•Retractable roof/Glass facade
effective.
sequencing
schedule efficient
costly
DECISION MATRIX
Lessons Learned
CEE 222 - Computer Integrated AEC (2002)
LESSONS LEARNEDLESSONS LEARNED
New media needs further development to work properly every time
• We encountered problems, especially in using Netmeeting
The phone line we have as backup is used every time in present meetings
• The data archival is very important but also complicated
Necessity of keeping track of the different versions of a document
Developing a tool to easily gather and manage data
Further Collaboration
CEE 222 - Computer Integrated AEC (2002)
FURTHER COLLABORATIONFURTHER COLLABORATION
The discussion forum should be used more often
We used it at the beginning of the project quite often but recently we „fell back“ to Emails
We should announce team-meetings (with all the members) once a week
The notification mechanism should be improved
Discussing with everybody (other disciplines) brings an improved learning experience
Importance of knowing if an email, attachment arrived and was useful