+ All Categories
Home > Documents > Technical Report 2011 Electricity Networks

Technical Report 2011 Electricity Networks

Date post: 04-Jun-2018
Category:
Upload: ranasherdil
View: 218 times
Download: 0 times
Share this document with a friend

of 14

Transcript
  • 8/14/2019 Technical Report 2011 Electricity Networks

    1/14

    2011

    Annualtec

    hnicalrepo

    rtElect

    ricitynetw

    orks

  • 8/14/2019 Technical Report 2011 Electricity Networks

    2/142

    1.

    2.

    3.

    Content

    Introduction

    The transmission network

    The distribution network

    Health and safety (H&S)

  • 8/14/2019 Technical Report 2011 Electricity Networks

    3/143 Regulation & Supervision Bureau | Technical Report 2011 - Electricity Networks

    Since 1998 the Abu Dhabi electricity sector has been divided into its threeconstituent services: production, transmission and distribution. The single buyer

    (ADWEC) purchases all electricity produced from the various power plants,

    and then supplies distribution companies at a cost determined by an annually

    reviewed bulk supply tariff (BST).

    The electrical system in the Emirate is operated by three network

    companies: a transmission company (the Abu Dhabi Transmission and

    Dispatch Company, TRANSCO); and two distribution companies (Al AinDistribution Company, AADC; and Abu Dhabi Distribution Company,

    ADDC), both of which carry out supply-related activities.

    This report presents an overview of the performance of these

    companies and the quality of their services during 2011.

    Introduction

  • 8/14/2019 Technical Report 2011 Electricity Networks

    4/144 Regulation & Supervision Bureau | Technical Report 2011 - Electricity Networks

    1. The transmission networkThe transmission network delivers large volumes of electricity from production companies to

    users, including the distribution companies.

    The sole transmission licensee in the Emirate of Abu Dhabi is TRANSCO.

    TRANSCO generates revenue from users via connection fees and a Transmission Use of System(TUoS) tariff that is reviewed annually by the Bureau.

    Measuring performanceThe technical performance of the electricity transmission system in Abu Dhabi Emirate compares

    favourably with others worldwide. It is quantified using two primary performance measurements:

    system unavailability and energy lost.

    System unavailability

    Transmission system unavailability represents the total time during which the transmission systemis out of service, expressed as a percentage of the total circuit hours in the year.

    System unavailability decreased in 2011, compared to 2010. Data analysis indicates that reduced

    construction outages were the main cause of improved system availability.

    TRANSCO incidents and energy lost

    Nine transmission system incidents occurred in 2011, resulting in the loss of 427

    MWh - an increase of approximately 390 MWh on the previous year (see Figure 2).

    All nine incidents were investigated by the Bureau. The most severe of these

    occurred at the Shahama East (SHME) grid station, the Capital Garden (CPGR)

    substation and Shamkha mobile.

    Figure 1:Transmission system unavailability

    0.0%2009 2010 2011

    0.2%

    1.2%

    0.4%

    1.4%

    0.6%

    1.6%

    0.8%

    1.8%

    1.0%

    2.0%

    Maintenance Construction Users Faults

  • 8/14/2019 Technical Report 2011 Electricity Networks

    5/145 Regulation & Supervision Bureau | Technical Report 2011 - Electricity Networks

    A major incident occurred at the 220/33 kV Shahama East grid station on 22 August 2011.

    Transformer T202 tripped due to mal-operation of restricted earth fault protection, resulting in

    the loss of 146MWh.

    A second major incident occurred at the 132/11 kV Capital Garden substation on 21 September

    2011. It was caused by an internal software error during a database update and resulted in the

    loss of 94 MWh.

    The third major incident occurred at the 220/33 kV Shamkha mobile transformer at Shamkha

    on 19 October 2011, and involved a trip of the 220 kV WathbaShahama 2 circuit. This incident

    resulted in a loss of 89 MWh.

    A further six minor incidents occurred at Shamkha mobile 220/33 kV, MOS1 132/11 kV,

    KhaznaWathba mobile 220/33 kV, Central 220/33 kV, and Mushrif 132/11 kV.

    The number of transmission system incidents was five more than in the previous year, and

    the total energy lost as a result showed a significant increase over 2010.

    Distribution companies - anomalous incidents and energy lost

    An incident is considered anomalous when a fault on the distribution network

    results in an outage and loss of demand on the TRANSCO network. During

    2011, seven anomalous incidents caused supply interruptions on TRANSCOs

    assets. These incidents, which are not included in the performance data shown in

    Figure 2, resulted in a total loss of 188 MWh.

    Figures 3 and 4 show the trend in anomalous incidents for AADC and ADDC in

    which the distribution system failed to isolate the faults, causing the transmission

    assets to trip.

    Figure 2:Transmission system incidents

    02009 2010 2011

    50

    100

    150

    200

    250

    300

    400

    350

    450

    500

    EnergylostMWh

    Numberofincidents

    Energy lost Number of incidents

    0

    1

    2

    3

    4

    5

    7

    6

    8

    9

    10

  • 8/14/2019 Technical Report 2011 Electricity Networks

    6/146 Regulation & Supervision Bureau | Technical Report 2011 - Electricity Networks

    The Bureau and network companies are currently examining the issue of anomalous incidents

    with a view to improving performance.

    Additional transmission developments

    Major transmission system developments

    The following major transmission system expansion activities were carried outduring 2011:

    Commissioning of 132/22 kV substations on Reem Island.

    Commissioning of 132/22 kV substations on Saadiyat Island.

    Commissioning of the Raha B 132/22 kV, and Green Head, Mushrif, Souq and

    Danat 132/11 kV substations.

    Commissioning of two 220/33 kV transformers at Bab.

    Commissioning of a 220/33 kV substation at ELXR.

    Commissioning of a 220/33 kV substation at ICAD.

    New 220 kV cable from AAPS to DHMG.

    New 400 kV cable from Saadiyat to ADST grid.

    Commissioning of Shuweihat 2 (S2) power plant.

    Figure 3:Distribution companies - anomalous incidents

    02006 2007 2008 20102009 2011

    1

    2

    3

    4

    5

    6

    7

    8

    9

    Incidents

    Year

    10

    ADDC AADC

    Figure 4:Energy lost through anomalous incidents

    02006 2007 2008 20102009 2011

    50

    100

    150

    200

    250

    300

    350

    400

    MWh

    Year

    ADDC AADC

  • 8/14/2019 Technical Report 2011 Electricity Networks

    7/147 Regulation & Supervision Bureau | Technical Report 2011 - Electricity Networks

    Emirates National Grid

    The Emirates National Grid, which allows power exchanges between Abu Dhabi, Sharjah, Dubai

    and the Northern Emirates, is undergoing further expansion. During 2011 a 400 kV double-

    circuit overhead line between Shweihan and Fujairah grid was commissioned. This increased the

    cross-border transmission capability between Abu Dhabi and the Northern Emirates.

    Commissioning of the GCC interconnection

    Commissioning of the 400 kV double-circuit overhead line from Sila to the Shuweihat grid

    station was completed, and the UAE transmission system was synchronised with that of

    the GCCIA.

    The 220 kV double-circuit transmission line from the Al Oha 220 kV substation in Al Ain

    to the Mahada 220 kV substation in Oman was completed, allowing the UAE and Omansystems to be synchronised.

    The GCC interconnection will improve system security, provide support during emergencies,

    reduce generation reserve requirements, and support the development of a common

    GCC electricity market.

    TRANSCO seven-year planning statement review

    The Bureau reviewed and provided feedback on TRANSCOs seven-year planning

    statement, released in 2011. Following discussions with the Bureau, TRANSCOincorporated an enhanced strategic plan that provides a long-term view of the

    system to 2030. The plan will be updated annually in conjunction with the seven-

    year planning statement.

    WESTERN REGION

    AL AIN REGION

    Ras al Khaimah

    Dhaid

    MadinatZayed

    ADNOCSila

    Shahama

    ShweihanUmm AlNar

    Wagen

    Arad

    Wathba

    Musaffah

    Sanaiya

    Al Ain PowerStation

    Samha

    Taweelah

    Electricity system expansion

    Umm El Oush

    Hayer

    Al Foah

    Dahma

    Al AinSouthwest

    DEWAWarsan

    Umm Al Quwain

    AjmanSharjah

    Qidfa(Fujairah)

    DUBAI

    Abu Dhabi

    SaadiyatReem

    Asab

    Liwa

    Bu Hasa

    Bab

    Ghaythy

    Ruwais

    Mirfa

    Shuweihat

    Interconnectionto Oman (Wasit)

    220 kV Lines

    400 kV Lines

    Under construction

    Power Stations

    Figure 5:Transmission system

  • 8/14/2019 Technical Report 2011 Electricity Networks

    8/148 Regulation & Supervision Bureau | Technical Report 2011 - Electricity Networks

    2. The distribution networkThe distribution system comprises the final stage in the delivery of electricity to end-users. As

    of 31 December 2011, the total number of customers connected to the two networks was

    281,966 (ADDC)1and 123,318 (AADC)2.

    Peak demand load in 2011 was 4,260 MW for ADDC3and 1,940 MW for AADC4. ADDC recorded

    a growth in peak demand of 9.5% in 2011 over 2010, while AADC experienced a 7.8% rise over thesame period (see Figures 6 and 7).

    Figure 6:ADDC maximum demand5

    Figure 7:AADC maximum demand6

    1 ADDC, Technical Assessment of the Price Control Return Relating to 2011 Financial Year, Final

    Report, April 2012.

    2 AADC, Technical Assessment of the Price Control Return Relating to 2011 Financial Year, Final

    Report, April 2012.3 ADDC, 5 Year Electricity Planning Statement 20132017, June 2012.

    4 AADC, 5 Year Electricity Planning Statement 20132017, June 2012.

    5 ADDC 5 Year Electricity Planning Statement , op. cit.

    6 AADC 5 Year Electricity Planning Statement , op. cit.

    02006

    2,794

    2007

    3,099

    2008

    3,339

    2009

    3,693

    20112010

    4,260

    3,889

    500

    1,000

    1,500

    2,000

    2,500

    3,000

    3,500

    4,000

    4,500

    MW

    02006

    1,400

    2007

    1,521

    2008

    1,562

    2009

    1,683

    20112010

    1,940

    1,799

    500

    1,000

    1,500

    2,000

    MW

  • 8/14/2019 Technical Report 2011 Electricity Networks

    9/149 Regulation & Supervision Bureau | Technical Report 2011 - Electricity Networks

    Distribution network assets data7

    Quality of supplyEnsuring quality of supply for end-users requires high performance in all three elements of the

    network: generation, transmission and distribution. However, distribution is by far the most significant

    of these in determining quality of supply.

    Since the introduction of performance indicators in 2006, the Bureau has closely monitored the

    network performance of AADC and ADDC. The Bureau requires that an independent audit of

    annual performance data be carried out by a technical assessor each year.

    After reviewing the findings of the 2011 audit, the Bureau noted some improvements in

    ADDCs monitoring performance.

    AADCs data quality has improved, but many of the recommendations made in the 2010

    technical assessment audit have not yet been implemented.

    The Bureau utilises two key performance indicators (KPIs) to determine the performance

    and reliability of the ADDC and AADC distribution systems:

    The System Average Interruption Duration Index (SAIDI), calculated from the

    total number of customer minutes lost (CML) in any one year, divided by the total

    number of connected customers (at year-end).

    The System Average Interruption Frequency Index (SAIFI), calculated from the

    total number of customer Interruptions (CI) in any one year, divided by the total

    number of connected customers (at year-end).

    The distribution companies record customer interruptions and calculate KPIs

    according to specific procedures developed by the Bureau.

    7 Ibid.; and ADDC 5 Year Electricity Planning Statement , op. cit .

    ADDC DISTRIBUTION SYSTEM No. of

    units

    Capacity

    (MVA)

    132/22 kV primary SS 12 3,840

    132/11 kV primary SS 33 5,080

    33/11 kV primary SS 231 6,610

    22/0.4 kV distribution SS 122 376

    11/0.4 kV distribution SS 13,779 17,287

    ADDC CABLE /

    OVERHEAD LINE

    SYSTEM

    Length (km)

    33 kV 5,747

    22 kV 274

    11 kV 13,020

    0.4 kV 11,546

    AADC CABLE /

    OVERHEAD LINE

    SYSTEM

    Length (km)

    33 kV 3,529

    11 kV 9,259

    0.4 kV 9,945

    AADC DISTRIBUTION SYSTEM No. of

    units

    Capacity

    (MVA)

    33/11 kV primary SS 150 5,120

    11/0.4 kV distribution SS 14,583 8,025

  • 8/14/2019 Technical Report 2011 Electricity Networks

    10/1410 Regulation & Supervision Bureau | Technical Report 2011 - Electricity Networks

    ADDC performance

    ADDCs SAIDI and SAIFI KPIs are shown in Figures 8 and 9.

    Figure 8:AADC System Average Interruption Duration Index (SAIDI)8

    Figure 9:ADDC System Average Interruption Frequency Index (SAIFI)9

    Note: An adjustment was made to the 2006-2008 SAIDI/SAIFI figures to facilitate comparison with the2009 figures, owing to a change in ADDCs customer interruption reporting methodology in 2009.

    The improvement in ADDCs SAIDI/SAIFI values between 2010 and 2011 was

    mainly a result of less planned outages being required during the upgrading and

    replacement of the 11 kV distribution switchgears in the central region. The

    cancellation of the substation AMR works also contributed to this reduction.

    Furthermore, the Eastern and Western Regions experienced fewer cable and

    overhead line faults, and a significant increase in their numbers of customers.

    8 ADDC, Technical Assessment , op. cit.

    9 Ibid.

    02006

    184.6

    2007

    157.6

    2008

    173.7

    2009

    185.9

    20112010

    107.0

    205.3

    20

    40

    60

    80

    100

    120

    140

    160

    200

    180

    220

    240

    SAIDI

    02006

    1.77

    2007

    1.58

    2008

    1.65

    2009

    1.74

    20112010

    1.71

    1.99

    0.5

    1.0

    1.5

    2.5

    2.0SAIFI

  • 8/14/2019 Technical Report 2011 Electricity Networks

    11/1411 Regulation & Supervision Bureau | Technical Report 2011 - Electricity Networks

    AADC performance

    Figures 10 and 11 show AADCs SAIDI and SAIFI KPIs.

    Figure 10:AADC System Average Interruption Duration Index (SAIDI)10

    Figure 11:AADC System Average Interruption Frequency Index (SAIFI)11

    The improvement in AADCs SAIDI/SAIFI values in 2011 was mainly due to the

    installation of overhead line auto-reclosers and sectionalisers in 20082009,

    new primary 33/11 kV substations being added in the City Region, and the

    undergrounding of a number of overhead lines.

    Both companies are introducing the capability to control their systems remotely and

    restore power during severe weather events, and the Bureau has recommended

    targeted investment programmes for regions that have suffered consistently poor

    performance.

    Related events

    10 AADC Technical Assessment op. cit .

    11 Ibid.

    02006

    265.8

    2007

    165

    2008

    220.7

    2009

    261.34

    20112010

    134.65

    186.86

    20

    40

    60

    80

    100

    120

    140

    160

    200

    180

    220

    240

    260

    280

    300

    SAIDI

    02006

    3.6

    2007

    2.63

    2008

    2.76

    2009

    2.78

    20112010

    1.45

    1.92

    0.5

    1.0

    1.5

    4.0

    2.5

    3.0

    3.5

    2.0SAIFI

  • 8/14/2019 Technical Report 2011 Electricity Networks

    12/1412 Regulation & Supervision Bureau | Technical Report 2011 - Electricity Networks

    Related events

    Electricity wiring regulations training

    Two nominated companies continue to provide regular training courses on electricity wiring

    regulations for private contractors. The five-day course, based on a programme developed by

    the Bureau, includes both theoretical and practical elements, as well as a final examination.

    The Bureau maintains a list of registered engineers who have successfully completed the

    course (169 passed in 2011), which is available on its website. The aim of this training initiative

    is to improve the skill levels of electrical contractors in Abu Dhabi, as well as to streamline

    procedures for the approval and testing of wiring in new buildings.

    Asset risk management review

    The rapid development and associated demand growth within Abu Dhabi Emirate in recent years has led

    the network companies to invest heavily in network assets. In order to maximise the benefits of this activity,

    and to avoid future acute operation and maintenance issues, it is vital that assets and associated risks are

    managed effectively.

    An important aspect of this is the process of determining and assessing the network companies

    current asset risk management performance against international best practice in order to identify

    any areas for improvement.

    Towards the end of 2011, the Bureau appointed an external consultant to review the companies and

    assess their asset risk management performance. The review will be complete by Q3 2012 and a

    programme developed to implement the resulting recommendations.

    AADC and ADDC five-year planning statement reviews

    Each year the Bureau reviews and comments on the five-year planning statements

    produced by each of the distribution companies. The parties then discuss the observations

    of the Bureau in order to improve the quality and format of their statements.

    Connection process improvements

    During Q3 of 2011, the Bureau collaborated with ADDC to review the companys

    existing electricity connection process, with the aim of reducing the overall time required

    for connection.

    KPIs were selected at various stages of the process, and their results monitored by both

    parties. Wherever a KPI highlighted a significant delay, ADDC and the Bureau worked

    together to understand the cause and develop appropriate action plans.

    Emergency load reduction plans

    During 2011, the Bureau set up a working group and carried out a review of

    TRANSCO, AADC and ADDC emergency planning.

  • 8/14/2019 Technical Report 2011 Electricity Networks

    13/1413 Regulation & Supervision Bureau | Technical Report 2011 - Electricity Networks

    The review led to significant developments in the AADC and ADDC emergency load reductionplans, which will improve the management of emergencies in which load shedding is a requirement.

    As a result, measures are now in place to determine demand prioritisation and minimise the

    effects of load reduction on consumers, whilst maintaining the security of the power system.

    Reem Island mega development

    At the request of the Government, the Bureau cooperated with Bunya and ADDC to facilitate

    the asset transfer of electricity and water network infrastructure to Reem Island.

    Reem Island is considered a mega development, in which the developer builds the infrastructure to the

    Distribution Companys standards and specifications, and the assets are transferred upon completion.

    3. Health and safety (H&S)

    H&S performance: electricity and waterThe table below summarises the health and safety performance of the electricity and water networks

    operated by TRANSCO, AADC and ADDC during 2011.

    During Q3 of 2011, a review of AADC and ADDC H&S management and operational

    systems and processes was completed. The review was conducted by an external consultant

    at the request of the Bureau, and follows the successful completion of a similar appraisal of

    TRANSCO in 2010.

    The Bureau will use the data from these reviews to achieve significant improvements in

    H&S performance, working with network companies to implement action plans for thispurpose. The Bureau also organised best practice workshops for the beginning of 2012

    to share the lessons learnt from the process with the rest of the sector.

    Following on from the work carried out in 2010 to establish the Bureaus internal

    Environment, Health and Safety Management System (EHSMS), the AD EHSMS

    Centre completed its review of the system and gave its approval during Q1 of

    2011; the Bureau began to implement the system thereafter.

    During the latter part of 2011, the Bureau was appointed Sector Regulatory

    Authority (SRA) for the Wastewater Sector, and began working closely with the

    AD EHSMS Centre and other entities to develop codes of practice for the sector.

    LICENSEE Total man hours

    worked Fatalities

    Lost time

    injuries (LTI) Minor injuries

    AADC 22,397,728 0 2 0

    ADDC 13,278,754 0 4 6

    TRANSCO 17,497,060 0 4 156

    Total 53,173,542 0 10 162

    Figure 12:Health and safety performance, 2011

  • 8/14/2019 Technical Report 2011 Electricity Networks

    14/14

    Abbreviations and Acronyms:

    AADC Al Ain Distribution Company

    ADDC Abu Dhabi Distribution Company

    ADWEC Abu Dhabi Water and Electricity Company

    BST bulk supply tariff

    CML customer minutes lost

    CI customer interruption

    EHSMS Environment, Health & Safety Management System

    FAPCO Fujairah Asia Power Company

    GCC Gulf Cooperation Council

    GCCIA GCC Interconnection Authority

    H&S health and safety

    KPI key performance indicator

    HV high voltage

    kV kilovolt

    MVA megavolt ampere

    MWh megawatt hour

    SAIDI System Average Interruption Duration Index

    SAIFI System Average Interruption Frequency Index

    TRANSCO Transmission and Despatch Company

    TUoS transmission use-of-system


Recommended