+ All Categories
Home > Documents > Technical Specification_SIDCL.pdf

Technical Specification_SIDCL.pdf

Date post: 13-Apr-2018
Category:
Upload: rakesh-ranjan
View: 216 times
Download: 0 times
Share this document with a friend

of 194

Transcript
  • 7/26/2019 Technical Specification_SIDCL.pdf

    1/194

    17

    Chapter 7 TECHNICAL SPECIFICATIONS

    TABLE OF CONTENTS

    Preamble

    Section 100 General

    101 Introduction

    102 Definitions

    103 Materials and Test Standards

    104 Sieve designations

    105 Scope of Work

    106 Construction Equipment

    107 Contract Drawings

    108 Site Information

    109 Setting out

    110 Public Utilities

    111 Precautions for safeguarding the environment

    112 Arrangement for Traffic during construction

    113

    General rules for the measurement of works for payment

    114

    Scope of rates for different items of work

    115 Methodology and sequence of work

    116 Crushed stone aggregates

    117 Approval of materials

    118 Supply of quarry samples

    119 Use of surface by construction traffic

    120 Site Office for Engineer and other supervisory staff

    121 Field Laboratory

    122

    Site residential accommodation for Engineer and other supervisory staff123 Providing and maintaining Wireless Communication System / Mobile Phones

    124 Providing and maintaining Project Vehicle

    125 Deleted

    126 Deleted

    127 Deleted

    128 Tolerance

  • 7/26/2019 Technical Specification_SIDCL.pdf

    2/194

    18

    129 Temporary Buildings and Site Services

    130 Hoardings and Fencing

    131 Project Information signboards

    132 Reports and Documentation

    Section 200 Site Clearance

    201 Clearing and grubbing

    202 Dismantling culverts, bridges and other structures / pavements

    203 Other site Clearance matters

    Section 300 Earthwork, Erosion Control and drainage

    301 Excavation for roadway and drain

    302 Blasting operations

    303 Presplitting rock excavation slopes

    304 Excavations for structures

    305 Embankment construction

    306 Soil Erosion and sedimentation control

    307 Turfing with sods

    308 Seeding and mulching

    309 Surface/sub-surface drains

    310 Preparation and surface treatment of formation

    311 Works to be kept free of water

    312 Water Courses at Culvert

    313 Construction of rockfill embankment

    314 Granular Backfill

    315 Permeable Backfill

    Section 400 Sub-bases, Bases (Non-bituminous) and Shoulders

    401 Granular sub-base

    404 Water bound macadam sub-base/base

    405 Crushed cement concrete sub-base/base

    406 Wet mix macadam sub-base/base

    407 Shoulders, islands and median

  • 7/26/2019 Technical Specification_SIDCL.pdf

    3/194

    19

    408 Cement concrete kerb and kerb with channel

    409 Footpaths and separators

    410 Crusher-run macadam base

    Section 500 Bases and Surface Courses (Bituminous)

    501 General Requirements for Bituminous Pavement Layers

    502 Prime coat over granular base

    503 Tack coat

    504 Bituminous macadam

    505 Bituminous penetration macadam

    506 Built-up spray grout

    507 Dense bituminous macadam

    508 Semi-dense bituminous concrete

    509 Bituminous concrete

    510 Surface dressing

    511 Open graded premix carpet

    512 Mix seal surfacing

    513 Seal coat

    514 Supply of mineral aggregates for pavement courses

    515 Mastic Asphalt

    516 Slurry seal

    517 Recycling of bituminous pavement

    Section 800 Traffic signs. Marking & Other Road Appurtenances

    801 Traffic signs

    802 Overhead signs

    803 Road markings

    804 Hectometre/Kilometre stones

    805 Road delineators

    806 Boundary stones

    807 Fencing

    808 Tubular steel railing

    809 Concrete crash barrier

  • 7/26/2019 Technical Specification_SIDCL.pdf

    4/194

    20

    810 Metal beam crash barrier/ Box beam barrier

    811 Road traffic signals

    812 R.C. guard post

    Section 900 Quality Control for Road Works

    901 General

    902 Control of alignment level and surface regularity

    903 Quality control tests during construction

    Section 1000 Materials for Structures

    1001 General

    1002 Sources of materials

    1003 Bricks

    1004 Stones

    1005 Cast iron

    1006 Cement

    1007 Coarse aggregates

    1008 Sand/fine aggregates

    1009 Steel

    1010 Water

    1011 Timber

    1012

    Concrete admixtures

    1013 Reinforced concrete pipes

    1014 Storage of materials

    1015 Tests and standard of acceptance

    Section 1100 Pile foundations

    1101 Description

    1102 Sub-surface investigation

    1103 Types of piles

    1104 Materials

    1105 Test piles

    1106 Pre-cast concrete piles

  • 7/26/2019 Technical Specification_SIDCL.pdf

    5/194

    21

    1107 Cast in-situ concrete piles

    1108 Steel piles

    1109 Timber piles

    1110 Driving equipment

    1111

    Driving1112

    Raker (inclined) piles

    1113

    Pile tests

    1114 Pile caps

    1115 Bored cast-in-situ piles

    1116 Tolerances

    1117 Tests and standards of acceptance

    1118 Measurements for payment

    1119 Rate

    Section 1300 Brick Masonry

    1304 Cement mortar

    Section 1500 Formwork

    1501 Description

    1502 Materials

    1503 Design of formwork

    1504

    Workmanship

    1505 Formed surface and finish

    1506 Precautions

    1507 Preparation of formwork before concreting

    1508 Removal of formwork

    1509 Re-use of formwork

    1510

    Specialized formwork

    1511 Tests and standards of acceptance

    1512 Measurements for payment

    1513 Rate

    Section 1600 - Steel Reinforcement (untensioned)

  • 7/26/2019 Technical Specification_SIDCL.pdf

    6/194

    22

    1601 Description

    1602 General

    1603 Protection of the reinforcement

    1604 Bending of reinforcement

    1605

    Placing of reinforcement1606

    Bar splices

    1607

    Testing and acceptance

    1608 Measurements for payment

    1609 Rate

    Section 1700 - Structural concrete

    1701 Description

    1702 Materials

    1703 Grades of concrete

    1704 Proportioning of concrete

    1705 Admixtures

    1706 Size of coarse aggregates

    1707 Equipment

    1708 Mixing concrete

    1709 Transporting, placing and compaction of concrete

    1710 Construction joints

    1711 Concreting under water

    1712

    Adverse weather conditions

    1713 Protection and curing

    1714 Finishing

    1715 Tolerances

    1716 Tests and standards of acceptance

    1717 Measurements for payment

    1718

    Rate

    1719 Application of Loading

    1720 Use of Adhesives

    1721 Additional reference to IRC: SP-65

    Section 1800 Prestressing

  • 7/26/2019 Technical Specification_SIDCL.pdf

    7/194

    23

    1801 Description

    1802 Materials

    1803 Testing of Prestressing Steel and Anchorages

    1804 Workmanship

    1805

    Supervision1806

    Tensioning Equipment

    1807

    Post-Tensioning

    1808 Grouting of Prestressed Tendons

    1809 Pre- Tensioning

    1810 Safety Precautions during tensioning

    1811 Transportation and storage of units

    1812 Tolerances

    1813 Tests and standard of acceptance

    1814 Measurements for Payment

    1815 Rate

    1816 IRC : SP-65 2005

    Section 1900 Structural Steel

    1901 Description

    1902 General

    1903 Materials

    1904 Fabrication

    1905

    Erection

    1906 Painting

    1907 Tests and standards of acceptance

    1908 Measurements for payment

    1909 Rate

    1910 Other incidental bridge facilities

    Section 2000 Bearings

    2001 Description

    2002 General

    2003 Steel bearings

    2004 Special bearings

  • 7/26/2019 Technical Specification_SIDCL.pdf

    8/194

    24

    2005 Elastomeric bearings

    2006 Pot bearings

    2007 Inspection and testing

    2008 Tests and standards of acceptance

    2009 Measurements for payment2010 Rate

    Section 2200 Sub-structure

    2201 Description

    2202 Materials

    2203 General

    2204 Pier and abutments

    2205 Pier cap and abutment cap

    2206 Dirt/ballast wall, return wall and wing wall

    2207 Tests and standards of acceptance

    2208 Tolerances in concrete elements

    2209 Measurements for payment

    2210 Rate

  • 7/26/2019 Technical Specification_SIDCL.pdf

    9/194

    25

    Section 2300 Concrete superstructure

    2301 Description

    2302 Material

    2303

    General2304

    Reinforced concrete construction

    2305

    Prestressed concrete construction

    2306 Tolerances

    2307 Tests and standards of acceptance

    2308 Measurement for payment

    2309 Rate

    2310 Reference IRC: SP-65 -2005

    2311 Construction Requirement for Precast Segmental Superstructure

    Section 2400 Surface and sub-surface geotechnical exploration

    2401 General

    2402 Preliminary investigation

    2403 Detailed investigation

    2404 Exploration for bridge foundations resting on rock

    2405 Boring

    2406 Records of borings and trial pits

    2407 Method of Sampling

    2408

    Procedure for taking samples

    2409 Protection, handling and labeling of samples

    2410 Tests for exploration of shallow foundations of bridges

    2411 Test for exploration of deep foundation of bridges

    2412 Testing of material for guide bund and high embankment and its foundations

    2413 Measurement for payment

    2414

    Rate

    Section 2500 - River Training Works

    2504 Pitching / revetment on slopes

  • 7/26/2019 Technical Specification_SIDCL.pdf

    10/194

    26

    Section 2600 - Expansion joints

    2601 Description

    2602

    General2603

    Requirements

    2606

    Elastomeric slab seal expansion joint

    2607 Strip seal expansion joint

    2608 Tests and standards of acceptance

    2609 Measurement for payment

    2610 Rate

    Section 2700 Wearing coat and Appurtenances

    2701 Description

    2702 Wearing coat

    2703 Railings

    2704 Approach slab

    2705 Drainage spouts

    2706 Weep holes

    2707 Tests and standards of acceptance

    2708 Measurement for payment

    2709 Rate

    Section 2900 - Pipe culverts

    2901 Scope

    2902 Materials

    2903 Excavation for pipe

    2904 Bedding for pipe

    2905 Laying of pipe

    2906 Jointing

    2907 Backfilling

    2908 Headwall and other ancillary works

    2909 Opening to traffic

    2910 Measurements for payment

  • 7/26/2019 Technical Specification_SIDCL.pdf

    11/194

    27

    2911 Rate

    Section 3500 Protection and Necessary Diversions of Existing Dry Utilities

    3501 Scope3502 Measurement for payment

    Section 3800 Painting of bridge, Culvert, Post, Railing etc.

    3801 Painting of post, wheel guards, railing etc.

    3802 Painting of bridge and culvert

  • 7/26/2019 Technical Specification_SIDCL.pdf

    12/194

    28

    Preamble

    The work of Construction of R.C.C Bridge over River Kalnagini Branch Canal near

    Nrisingha Ashram of Swami Vivekananda & Sri Ramkrishna Gram Panchayat under

    Kakdwip Block in the district of South 24 Paraganas, West Bengal is to be

    constructed to the Specifications for Road and Bridge Works, Fourth Revision, Reprint of March

    2006 (MOSRT&H specifications) as supplemented by this Volume wherein some of the clauses

    of the MOSRT&H specification have been amended, modified, supplemented, substituted,

    deleted and where necessary new clauses added, in order to be better applicable to the

    Works. Therefore the MOSRT&H specifications, jointly read with this Volume, will

    govern the Works.

    In case there is contradiction between the provisions of MOSRT&H specifications and those

    detailed in this Volume, the latter shall prevail.

    The Clause numbers in MOSRT&H specifications have been followed in this Technical

    Specification and amendments, additions, deletions and other changes have been indicated by

    referring to the particular clause. Where new clauses have been added, new numbers have

    been given to Clauses or Sections. Where no amendment or change is mentioned, the original

    Clauses in MOSRT&H specification shall prevail.

    Where several types of construction or materials are specified in the MOSRT&H Specification,

    the Contractor shall refer to this Technical Specification and/or the other Contract Documents

    in applying the definitive types used for the Works.

    The contractors shall quote their contract price at item rate basis based on the rates of

    different items provided in the priced Bill of Quantities for whole cost of complying with

    provisions of contract comprising Instruction to Bidders, the General Conditions of Contract,

    the Technical Specifications and other related tender documents.

    The Contractors price is deemed to cover all the provisions under the clauses mentioned

    hereinafter. Other than what is included in item rate quoted price and BOQ item for running

    bills no other measurement of payment shall be done and shall be deemed to be incidental to

    the main works and no separate payment will be made for these provisions beyond the

    Contract price.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    13/194

    29

    SECTION 100 GENERAL

    101 Introduction

    This Clause shall remain unchanged as in MOSRT&H specification.

    102 Definitions

    Wherever the word drawing appears in this volume, it will mean General Arrangement Drawing

    and further detailed drawings for permanent works to be furnished by SIDCL.

    The following shall be added after at the end of the first paragraph:

    The associated definitions of contractual terms are given in Clause 1.1 of the General

    Conditions of Contract (Section 4 of Volume I of these Contract Documents).

    103 Materials and Test Standards

    The following shall be added after at the end of the first paragraph,-

    Appendix 1 of the MOSRT&H Specification gives the Indian and other standards referred to in

    the text of the specifications. Additional standards and testing procedures, as required, are

    specified in appropriate places in this Technical Specification.

    103.1 Substitution of foreign standards by Indian equivalent

    All products materials supplied by the Contractor shall conform to the Specification and shall

    be approved by the Engineer. Where specific manufacturers or brand names are mentioned in

    the Contract Documents, it shall be deemed that that product or similar approved is required.

    It shall not be deemed to indicate that the particular manufacturer is mandatory.

    Where any materials or equipment are specified, as being in accordance with non-Indian

    Standards it should be understood that these are automatically be substituted by such

    equivalent to IS or I.R.C. In case application of IS or I.R.C is found unsuitable from a technical

    point of view, the Employer will take appropriate measures based on the recommendation of

    the Engineer.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    14/194

    30

    103.2 Applicable edition of Standards

    In the Specification materials or tests specified as being in accordance with IS or I.R.C.,

    AASHTO or ASTM shall refer to the specifications or method of test prevailing till 28 days prior

    to the final date for the submission of Tenders, unless otherwise stated.

    104 Sieve Designations

    This shall remain unchanged as in MOSRT&H specification.

    105 Scope of Work

    105.1 This shall remain unchanged as in MOSRT&H specification upto sub cl. 105.4.The

    following shall be added after sub cl. 105.4

    105.5 Composition of Works

    The scope of work shall generally comprise of but not necessarily be limited to the following:

    (a) Construction of the Permanent Works, e.g. R.C.C prestressd bridge resting on piles and

    pile caps, piers, crossheads, Solid R.C.C. Wall type Abutment, Precast segmental Box

    girder, to the lines and levels as specified in the Drawings and Specification.

    (b) Design, provision and subsequent removal of all Temporary Works, staging/scaffolding,

    Casting bed, shuttering and Ancillary work required for the construction of the Permanent

    Works.

    (c) Design and provision of any ground treatment required for the construction of

    foundations and pipe culverts in poor soil strata where required.

    (d) Keeping the Site secure and maintaining of access to and from the Site, in order for the

    Works to be carried out in accordance with the Contract

    (e) Provision and delivery of all materials, Contractor's Equipment and manpower required to

    construct the Works

    (f) Removal and disposal at a suitable tip of arising from all construction activities. The

    transport provided shall be suitable for the nature of the arising and shall not leak or

    discharge any of its contents during transportation or during transfer from one means of

    transport to another.

    (g) Temporary and permanent reinstatement of roads and footpaths in accordance with

  • 7/26/2019 Technical Specification_SIDCL.pdf

    15/194

    31

    Drawings and Specification and the requirements at site.

    (h) Maintaining all times of a safe traffic movement around the Site in accordance with the

    Relevant Authorities.

    (i) Preparation of bar bending schedules for all reinforced concrete structures and all

    construction drawings including shop drawings for all structural steel work, ConstructionMethodology/ Method statement for Precast Segmental work, Construction methodology

    / Method statement for erection of precast Box segments including casting, curing

    stressing etc. The Contractor shall be responsible for checking the accuracy of bending

    dimensions shown on all bending schedules. These schedules are to be submitted to the

    Engineer for his approval.

    (j) Preparation of as-built drawings for the completed Works. These shall be submitted to

    the Engineer for his review and approval.

    105.6 Exclusions from the Contractor's Works

    The following works and services shall be excluded from the Contractor's scope of work:

    (a) Provision of right-of-way

    (b) Provision of initial base points/line(s) and bench mark(s) to be referred to for the

    contractor's setting out

    106 Construction Equipment

    This Clause shall remain unchanged as in MOSRT&H specification.

    107 Contract Drawings

    This Clause shall remain unchanged as in MOSRT&H specification.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    16/194

    32

    108 Site information

    108.1 Site Conditions

    The following shall be added to Clause 108.1The requirements of the Conditions of Contract Clause 11 and 12 shall take precedence.

    108.4 Quarry Charts

    Clause 108.4 of the MOSRT&H Specification shall be deleted and the following substituted in

    its place:

    No quarry information is provided under the contract. The Contractor is expected to make his

    own arrangements for the availability of all construction material and, rates shall be deemed to

    include any associated transportation and all other charges.

    109 Setting out

    109.1 Bench Marks

    Add the words subject to a minimum two in a project (work location) after the words four

    per km in the sixth line.

    The following shall be added after the Clause 109.1:

    Except where otherwise specified, all levels shall be in metres expressed to three places of

    decimals. All levels on Site shall be determined from the temporary benchmark provided at site

    with an arbitrary level of 100.000.

    This is to be linked with nearest reference bench marks of PW (Roads) or PWD.(Govt. of W.B)

    109.3 Manner of Setting Out

    Clause 109.3 of the MOSRT&H Specification shall be deleted and the following substituted in

    its place:-

    The Works shall be accurately set out and referenced to the satisfaction of the Engineer.

    Marking systems shall require the prior approval of the Engineer and full records of setting out

    and reference points shall be reported to the Engineer in formats to his approval. All setting

    out markings and reference points shall be maintained until their removal is approved by the

    Engineer.

    109.9 Precision of Instrumentation

    Clause 109.9 of the MOSRT&H Specification shall be deleted and the following substituted in

    its place:-

    The precision of surveying and measuring instrumentation shall be to the satisfaction of the

    Engineer.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    17/194

    33

    The following shall be added after clause 109.9:-

    109.10 Surveying Equipment for the Engineer's Use

    The Contractor shall furnish the Engineer for his exclusive use the following instruments,

    appliances, surveyor personnel and labour, and materials for the Engineer use in connection

    with the Works:(a) 1 Surveyor and 2 Surveying assistants

    (b) One set of Surveying equipment as listed below or equivalent, as will be approved by the

    Engineer. The equipment will be used by crew of 1 Surveyor and 2 surveying Assistants.

    Main Equipment:

    Total Station (Make: Nikon or Sokkia or Leica or Trimble) with following minimum

    specifications:

    Minimum display (least count) : 1second

    Angle measuring Accuracy : 2 seconds

    Distance Accuracy : + 2mm + 2ppm x D

    1 MB SRAM

    16 MB compact Flash Card

    Maximum distance measurement with single prism: 2.7km

    Auto Level of make and accuracy to be approved by the Engineer

    Accessories: Generally, these shall be of same make of the main equipment

    Wooden Tripod

    Program Card

    Card reader/Writer

    Triple prism set

    Prism Pole Tripod

    Telescope Prism Pole Set

    2 steel measuring tapes 50m long

    2 steel measuring rods (4m)

    2 nos Leveling Staff

    Survey stakes as required and

    Miscellaneous tools and consumables as required in surveying.

    All surveying instruments shall be supplied complete including tripods, staffs etc.

    109.11 Maintenance

    Such survey equipment shall be calibrated prior to use and periodically, and be repaired or

    replaced by the Contractor as required by the Engineer.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    18/194

    34

    109.12 Ownership

    The surveying equipment will be treated as the property of the Employer during the period of

    contract including extension period and will be returned to the Contractor on as is where is

    basis within thirty days (30) of the issuance of the Taking Over Certificate.

    109.13 Measurement for Payment

    The supply of surveying equipment and its maintenance and shall be measured for payment as

    follows:

    (1) no separate payment for provision of the equipment, including the demonstration,

    (2) by time related monthly items for the maintenance of the equipment including the

    demonstration.

    (The monthly payment should cover activity under item 1 above and item 3 hereunder)

    (3) no separate payment for removal of equipment,

    (4) by time related monthly items for supply of 1 Surveyor and 2 surveying assistants as a

    group to work with the equipments.

    109.14 Rates

    The Contract rates for time related monthly payment shall include all aspects of the

    procurement, delivery, maintenance and removal of the surveying equipment for the

    Engineers exclusive use. In other words, the scope is similar to monthly hire charges for the

    equipment in working condition. Prorate rate shall be applicable if the equipment is not fit for

    use for more than 3 calendar days in a particular month. Rate for Surveyors and surveying

    Assistants shall be per shift per month, in units of 1 Surveyor and 2 survey Assistants.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    19/194

    35

    110 Public utilities

    Sub Clause 110.1 of the MOSRT&H Specification is deleted entirely and the following

    substituted:

    Channelizing the request through SIDCL, the Contractor shall have to collect the information

    from the concerned authority(ies) and/or make one trial trenches at 150 metre interval or

    closer to confirm the exact location of utilities at site. Drawing scheduling the affected

    services like water pipes, sewers, cables, gas ducts etc. owned by various authorities

    including Public Undertakings and Local Authorities shall be prepared by the contractor and

    verified by the contractor for accuracy of the information prior to the commencement of any

    work close to those services. SIDCL will arrange for their shifting through the owning agencies.

    The Contractor shall be asked to render all assistance during the execution of the utility work,

    by suitably programming their main work at no extra cost to SIDCL and shall be treated as

    incidental to the work.

    The Contractor is therefore required to provide drawings showing the exact routes of all the

    dry utilities, and underground installation, as located by trial trenches and survey. The above

    incidental works shall have to be carried by the Contractor at his own cost.

    Sub Clauses 110.2 to 110.7 are unaltered from the MOSRT&H Specification.

    111 Precautions for Safeguarding the Environment

    This shall remain unchanged as in MOSRT&H specification

    112 Arrangements for Traffic during Construction

    Clause 112 of the MOSRT&H Specification is deleted entirely and the following substituted:

    112.1 General

    The Contractor shall carry out the Works in a manner creating least interference to the safe

    flow of traffic consistent with the execution of the Contract.

    The Contractors project planning shall include a traffic control plan for moving traffic through

    and around the construction zone in a manner that is conducive to the safety of the travelling

    public, pedestrians and workers.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    20/194

    36

    The traffic control plan shall include such items as , methods and devices for delineation and

    channelisation, signaling signing, application and removal of pavement markings, placement of

    devices; working area lighting, surveillance and inspection.

    The Contractor shall submit the Program for approval of the Engineer of the works associated

    with the sub-projects (Project Sections) which shall, in principle, be carried out in stages andsub stages covering various components of the works.

    The Contractor shall take prior approval of the Engineer, traffic police and other concerned

    authorities regarding traffic arrangement during construction.

    No two sequences of work will be taken simultaneously without the prior approval of the

    Engineer.

    The Contractor shall make the road or footpath available for public use after the completion of

    one section of work if blocked temporarily.

    The Contractor shall obtain the specific prior permission from traffic police and other

    concerned authorities for the transportation of all plant and material to and from the site,

    particularly on the public highway.

    The Contractor shall maintain two lanes available for traffic in each direction at all times except

    when a temporary reduction is approved by the Engineer and granted specific prior permission

    from traffic police and other concerned authorities. The existing drainages should not be

    affected by contractor's work.

    The minimum permissible traffic route widths shall be as follows:

    1 lane - 3.5m

    2 lane - 6.5m

    3 lane - 9.9m

    Further temporary reduction shall be allowed subject to the prior approval of the Engineer, the

    traffic police and other concerned authorities.

    Minimum 1.5m width of footpath of approved hard surfacing shall be kept free during

    construction period as a temporary measure, if they are allowed to occupy existing footpath

    space for any reason whatsoever for construction activities.

    112.2 Passage of Traffic along a part of the Existing Carriageway under

    improvement

    Shall remain same

    112.3 Passage of traffic along a temporary diversion

    Shall remain same

  • 7/26/2019 Technical Specification_SIDCL.pdf

    21/194

    37

    112. 5 Maintenance of Diversion and Traffic Control Devices

    Signs, lights, barriers and other traffic control devices of diversion roads shall be maintained in

    a satisfactory condition till such time as they are required as directed by the Engineer. The

    temporary traveled way shall be kept free of dust by frequent applications of water, if

    necessary.

    112. 6 Measurements for Payment and Rate

    Shall remain same

    113 General rules for the measurement of works for payment

    Clause 113 from the MOSRT&H Specification shall be deleted entirely and the following

    substituted in its place:-

    113.1 Method of Measurement

    All measurements for payment in the Bill of Quantities shall be made net based on the

    Drawings, or the actual work done approved by the Engineer. The contractors quoted price

    shall include this cost in the Item rate cost. The Bill of Quantities are for monthly/ periodical on

    account payments only and this cost will merge in the final amount. Detailed measurements

    are to be furnished by contractor to compare with as built drawings.

    114 Scope of rates for different items of work

    This shall remain unchanged as in MOSRT&H specification.

    115 Methodology and sequence of work.

    This shall remain unchanged as in MOSRT&H specification. The requirements of the Conditions

    of Contract shall take precedence.

    116 Crushed stone aggregates

    This shall remain unchanged as in MOSRT&H specification.

    117 Approval of materials

  • 7/26/2019 Technical Specification_SIDCL.pdf

    22/194

    38

    This shall remain unchanged as in MOSRT&H specification.

    118 Supply of quarry samples.

    This shall remain unchanged as in MOSRT&H specification.

    119 Use of surface by construction traffic.

    This shall remain unchanged as in MOSRT&H specification.

    120 Site office for Engineer and other supervisory staff.

    The sub-section is deleted entirely and the following is substituted:

    120.1 A temporary site office of 500 (five hundred) sqft carpet area with facility of toilet,

    electricity, water, reasonable furniture for the engineer and his representative,

    computer operator and other facilities as will be directed by the Engineer shall be

    handed over to the Engineer within 30 days after issue of work order for their use.

    They shall remain the property of the contractor and shall be returned to the

    contractor within thirty (30) days after issuing taking over certificate for the whole

    work.

    120.2 Payment will be made on the basis of B.O.Q. provision under preliminary subhead.

    121 Field laboratory

  • 7/26/2019 Technical Specification_SIDCL.pdf

    23/194

    39

    121.1 Scope

    This shall remain unchanged as in MOSRT&H specification

    121.2

    Description

    Clause 121.2 of MOSRT&H Specifications shall be deleted entirely and the following

    paragraphs substituted in its place:

    The area for the erection of the field laboratory will not be provided by the Employer, and the

    provision of such area shall be the responsibility of the Contractor. The field laboratory shall be

    for the exclusive use of this project and should not be shared with any other work even under

    another Government agency.

    The field laboratory shall preferably be located adjacent to the site and shall be provided with

    amenities like water supply, electric supply etc. as well as laboratory tables, cupboards, chairs,

    tables and other furniture as necessary.

    The floor space of the field laboratory shall be decided by the Contractor, subject to the

    approval of the Engineer. Office space shall be provided within the field laboratory for the use

    of the Engineer's Materials Engineer.

    The laboratory will be operated by the Contractor under the supervision of the Engineer.

    All other apparatus and materials necessary for tests required under the Contract shall be

    supplied by the Contractor and installed in the laboratory. Not later than 30 days after the

    receipt of the Letter of Acceptance, the Contractor shall submit for the Engineer's approval, a

    list of all equipment to be procured and details of suppliers.

    All equipment used for testing shall be of standard type and approved by the Engineer and

    properly housed by the Contractor. An adequate supply of water and electric power shall be

    provided at all time.

    Every designation of the Indian Standards or other foreign standard specifications shall refer to

    the versions of those specifications current 28 days prior to the final date for the submission of

    Tenders, except where otherwise stated.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    24/194

    40

    In any case where material or workmanship is specified by one of the above tests, and

    alternative test methods are allowed, the method used to determine compliance with the

    Specification will be at the absolute discretion of the Engineer.

    The Contractor shall provide laboratories fully equipped and furnished at locations approved bythe Engineer in order that the Engineer can control and supervise the material used for (i)

    concrete batching and / or (ii) bituminous pavements and operations of bituminous mixing

    plants. Only such laboratories can be at a remote place close to the plants at a remote area

    from pollution point of view.

    121.3 Laboratory equipment

    Clause 121.3 of the MOSRT&H Specification shall be deleted entirely and the following

    substituted in its place;-

    All necessary laboratory equipment shall be provided, maintained and operated by the

    Contractor for the sampling, transporting, storing, curing, preparation of samples and testing

    of all materials required for the Works.

    All laboratory equipment shall be to the approval of the Engineer.

    121.4 Ownership

    Clause 121.4 of the MOSRT&H Specification shall be deleted entirely and the following

    substituted in its place:

    The area for the erection of the laboratories will not be provided by the Employer, and the

    provision of such area shall be the responsibility of the Contractor. However where there is

    available space the Employer may give permission for the laboratories office to be erected

    within Such areas, at payment of ground rent, at rate to be decided by the employer.

    The laboratories and equipment as detailed in Sub-clause 121 above shall be provided by the

    Contractor for the use of the Employer and/or Engineer. They shall remain the property of the

    Contractor and shall be returned to the Contractor within thirty (30) days after issuing the

    Taking-Over Certificate.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    25/194

    41

    121.5 Maintenance

    Clause 121.5 of the MOSRT&H Specification shall be deleted entirely and the following

    substituted in its place; -

    The Contractor shall be responsible for all aspects of maintenance and operation of the

    laboratories, including all costs associated with purchase, delivery erection calibration of

    equipment, operation, including sampling, storage, curing and testing of materials, periodic re-

    calibration of equipment, supply of consumables, recording and submitting test results to the

    Engineer, and removal on completion of the Works.

    121.6 Measurements for Payment.

    This Sub-Clause is deleted entirely and the following substituted:

    The supply of laboratories together with equipment and furniture, their operation, removal

    after completion of works and their maintenance and charges for utilities shall be measured for

    payment on the principle of hire charges as follows:

    By time related monthly items for (1) supply and maintenance of Field Laboratory and

    equipment including final removal of Field Laboratory and equipment.

    121.7 Rates

    Payment will be made on the basis of B.O.Q. provision under preliminary subhead.

    Clause 122 Site Residential Accommodation for Engineer and Other

    Supervisory Staff

    DELETED

    Clause 123 Providing and maintaining Telecommunication System

    123.1 Scope

    The works shall cover the provision of three sets of mobile phones for the exclusive use of the

  • 7/26/2019 Technical Specification_SIDCL.pdf

    26/194

    42

    Engineer or his Representatives as also maintenance and payment of call charges per month.

    123.2

    Provision and Ownership

    The Contractor shall arrange to provide three sets of mobile phones for a period of 25 months

    with one battery, one spare battery and one battery charger per phone for the exclusive use of

    Engineer or his Representative and connection to a telephone network (BSNL or Similar). The

    mobile phones will remain the property of the Employer and shall be retained by the Engineer

    upon the completion of the contract.

    123.3 Approval

    The Nokia make or equivalent model of the phone and selection of the network and tariff to beused shall require the prior approval of the Engineer. International and long distance dialing

    facilities will not be provided.

    123.4 Maintenance

    The Contractor shall maintain the phones and carry out repair including provision of

    replacement of batteries, chargers or the telephone instrument itself if it cannot be repaired to

    provide uninterrupted service.

    123.5 Measurement for Payment

    Payment for the provision of mobile phones shall be by a unit rate per unit provided. Each unit

    shall be procured by initial outright purchase rather than obtained on a lease or similar basis.

    Phones procured by purchase at prices subsidized by subsequent line rental and call charge

    tariffs will not be acceptable. Each unit shall include the cost of provision of the phone, any

    initial lump sum connection fees or related initial charges and deposits. International dialing

    facilities shall not be required or provided. The phones provided shall have the facility to be

    restricted to local calls only.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    27/194

    43

    123.6 Rates

    The Contract unit rate shall include for the supply of mobile phones and shall be deemed to

    include all initial charges associated with the outright purchase of the phone, SIM card,

    battery, spare battery, battery charger, suitable protective case, security deposit and anyother items so that the phone is provided to the Engineer in an operating condition.

    The telephone monthly rental and call charges, voice mail etc. will also be included in the rate

    quoted by the Contractor. Payment in this regard will be made as per rate quoted in the BOQ.

    124 Providing and Maintaining Project Vehicle

    This Clause is unaltered from MOSRT&H Specification with following modification.

    Make of Car- Ambassador or similar (Hard top Jeep, Maruti Gypsy or Mahindra and Mahindra

    Jeep is not acceptable).

    Type of Car - Euro 3 Diesel Car (Petrol Car will not be accepted).

    124.5 Measurement for Payment

    This sub- clause is deleted and substituted by the following:

    The payment for providing and maintaining vehicles shall be on vehicle month basis. The

    rate of vehicle- month given in the BOQ shall be proportionately reduced for number of days

    in a month the contractor fails to place the vehicle to the Engineer or the Engineers

    representatives and/ or for the period of withdrawal as per sub-clause 124.4 irrespective of the

    fact whethervehicle was available or not.

    125 Supply of Colour Record Photographs and Albums

    Deleted

    126 Supply of Video Cassettes

    Deleted

    127 Provision of Copies of Indian Standards etc.

    Deleted

  • 7/26/2019 Technical Specification_SIDCL.pdf

    28/194

    44

    128 Tolerance

    All Works executed under the Contract shall be carried out in accordance with the tolerances

    given in the Specification and approved Drawings, and such other tolerances as are givenelsewhere.

    129 Temporary Buildings and Site Services

    129.1 Maintenance of the Contractor's temporary site buildings

    The Contractor shall not erect any structure permanent or temporary for any sort of use

    without the prior permission of the Engineer.

    The Contractor shall provide and maintain all necessary temporary buildings, ablutions, water

    closets, sheds, stores and storage areas, move as required during the construction of the

    Works, and remove the same from the Site on completion of the Works. No structure shall be

    erected or storage area laid out by the Contractor within the Site without the Engineer's

    consent, but such consent will not relieve the Contractor from his responsibility of siting

    temporary structures clear of the Works, utility access points and the like. A copy of the plan

    showing the extent and position of all offices, ablutions, water closets, sheds, stores and

    storage areas shall be given to the Engineer. Temporary buildings, ablutions, water closets,

    sheds, stores and storage areas shall be cleaned and maintained on a daily basis, to the

    satisfaction of the Engineer.

    129.2 Provision of Latrines

    The Contractor shall provide efficient and sanitary latrine accommodation (at location

    permitted by the Engineer) for the use of the employees on the Works and shall keep the

    whole of the Site and the latrines in a clean and sanitary condition to the satisfaction of the

    Engineer.

    129.3 Site Services

    The Contractor shall be responsible for providing at his own cost all Site services including for

    the Engineer's use as necessary and appropriate for the construction of the Works, which shall

  • 7/26/2019 Technical Specification_SIDCL.pdf

    29/194

    45

    include, but not necessarily be limited to:

    (a) electricity

    (b) water

    (c) site communication facilities, and

    (d) temporary drainage and sewage disposal.

    Such services shall be provided by the Contractor for use solely in connection with the proper

    execution of the Works. The Contractor shall be responsible for complying with all regulations

    of the Relevant Authorities concerned. The Contractor shall be responsible for the provision

    and maintenance of all installations associated with such services and the relation thereto and

    shall take all reasonable precautions to safeguard the safety and health of all persons and the

    security of the Site. The Engineer may demand the immediate disconnection or alteration of

    such installations or portions thereof as he considers to be prejudicial to safety, health or

    security. As soon as any or all of the Contractor's installations are no longer required for the

    execution of the Works they shall be entirely removed to the satisfaction of the Engineer.

    All installations shall comply fully with all appropriate statutory requirements. Pipes, tubes,

    ducts or cables crossing roads, footpaths, or right-of-way shall be ramped over, or recessed

    below the surface. Specific services shall comply with the following:

    129.4 Electricity

    The Contractor shall provide all necessary artificial lighting for use on the Works at night,

    closed underground work and wherever required.

    The Contractor shall provide all temporary cables, mains, sub-mains, wirings, fittings, etc. for

    the above, clear away and make good on completion and pay all fees and charges.

    129.5 Water

    An adequate supply of fresh water shall be provided at the Site, including provision to the

    satisfaction of the Relevant Authority of any storage tanks so that sufficient fresh water is

    always available for the execution of the works including during any periods of water

    restriction. A supply of safe drinking water shall be provided by the Contractor for his own

    work people and the Engineer.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    30/194

    46

    129.6 Temporary Drainage and Sewage Disposal

    Adequate provision shall be made for the discharge or disposal from the Site of all water,

    surplus fluid, sewage and waste products and the method of disposal shall be to the approvalof the Engineer and in accordance with the regulations of the Relevant Authorities. The Site

    shall be kept well drained and free from standing water. Where existing channels and gullies

    cannot be maintained, temporary drainage arrangements shall be provided at the Contractor's

    cost.

    129.7 Measurement and Payment

    Contractors quoted rates are deemed to cover all the provisions under clause 129 which are

    incidental to the work and no separate payment will be made for these provisions.

    130 Hoardings and Fencing

    This clause shall remain unchanged as in MOSRT&H specification.

    131 Project Information Signboards

    This clause shall remain unchanged as in MOSRT&H specification.

    132 Reports and Documentation

  • 7/26/2019 Technical Specification_SIDCL.pdf

    31/194

    47

    132.1 Initial Plans etc.

    The Contractor shall, within fifteen (15) days from receipt of the Letter of Acceptance, submit

    to the Engineer the following documents, data and/or schedules but not be limited to, for the

    Engineer's approval:

    (a) Execution plan covering organization chart, resume of all key personnel, mobilization of

    supervising force and other indirect staff, labor, construction equipment/vehicles,

    material procurement/purchasing plan, temporary work plan, overall construction

    programme, quality assurance plan, safety plan, subcontract plan, work sequence plan,

    etc.

    (b) Inspection and testing plan

    (c) Working drawings, and detail information on equipment

    Field laboratories

    (d) Cash flow schedule

    (e) Other document and information designated by the Engineer at issuing the Letter of

    Acceptance

    132.2 Regular Reports to the Engineer

    In addition to the reports and documentation specified in the Contract other than this Clause,

    the Contractor shall submit to the Engineer the following regularly:

    (a) Advance monthly construction programmes

    (b)

    Advance weekly construction programmes

    (c) Advance method statement

    (d) Submission of the line diagram along with the monthly bill showing the exact progress of

    the executed work for which the bill has been drawn.

    (e) Inspection applications and reports

    (f) Accident reports

    132.3 Regular Reviews

    Progress review meeting shall be held every week. In addition once each month during the

    progress of the Works or at such other intervals as may be required by the Engineer, the

    program is to be reviewed and updated by the Contractor taking into account the latest

    available information on activities completed, in progress and not yet started, which

  • 7/26/2019 Technical Specification_SIDCL.pdf

    32/194

    48

    information shall be agreed with the Engineer.

    Three (3) copies of the program arising from the review shall be submitted to the Engineer

    indicating the state of progress of the Works and the revisions necessary to achieve

    completion thereof and of individual Sections thereof by the dates specified and to achievecompletion of the whole of the Works by the required date.

    The monthly review shall also include, but not necessarily be limited to the provision by the

    Contractor of the following:

    (a) Description of the previous month's activities and progress

    (b) Discussion on critical activities and program with particular reference to action taken or

    which will be taken to rectify any program slippage

    (c) Any significant movement in labor numbers 01- equipment mobilization / demobilization

    (d) Photographic record of the construction site, in sufficient detail to show the progress of

    the major aspects of the Works

    (e) Project financial report including reconciliation of variations, claims and estimates of

    future claims

    (f) Project safety report

    The Contractor shall submit to the Engineer a daily return of Labour and Contractor's

    Equipment, i.e., the statement of the Contractor's Equipment, labour (by discipline) and staff

    on Site, major material items received, problems to be solved and as desired by the Engineer.

    132.4 Measurement for Payment

    The cost for these items of work shall be deemed to be included in the Contractor's unit rates.

    No separate payment shall be made for these provisions.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    33/194

    49

    SECTION 200 SITE CLEARANCE

    201 Clearing and Grubbing

    201.1 Scope

    Add the following paragraph to the MOSRT&H Specification.

    If any vegetation grows after clearing and grubbing before road construction work, the

    contractor shall repeat the work to the satisfaction of the Engineer without any extra cost. The

    scope of clearing and grubbing shall include all clearance of street furniture, utility apparatus

    etc. necessitated by the Works not specifically measured elsewhere.

    201.2 Preservation of Property / Amenities

    Add the following paragraph to the MOSRT&H Specification.

    The Engineer will establish the limits of work and designate all trees, shrubs, plants and other

    things to remain. The Contractor shall preserve all items designated to remain.

    201.3 Methods, Tools and Equipments

    This clause shall remain unchanged as in MOSRT&H specification.

    201.4 Disposal of Materials

    Clause 201.4 of the MOSRT&H Specification shall be deleted entirely and the following

    substituted:-

    All surplus materials arising from the Works (except those arising from private properties) shall

    be the property of the Contractor who shall be responsible for their disposal.

    201.5 Measurement for Payment

    Payment will be made on area basis in hectare regarding site clearance. Cutting of trees upto

    300mm in including removal of stumps and roots, and trimming of branches of trees extending

    above the roadways shall be considered incidental to the cleaning and grubbing operations,

    Removal of stumps left over after trees have been cut by any other agency shall also be

    considered incidental to the cleaning and grubbing operations.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    34/194

    50

    Cutting in including removal of stumps and roots of trees of girth above 300mm and backfilling

    to required compaction shall be measured in terms of number according to the sizes given

    below:-

    Above 300mm to 600mm

    Above 600mm to 900mmAbove 900mm to 1800mm

    Above 1800mm

    For the purpose, the girth shall be measured at a height of 1 meter above the ground or at the

    stump if the height of the stump is less than one meter from the ground.

    201.6 Rates

    The unit price for the work hereof will be deemed to include any precautions or special

    working methods necessary to avoid damage to adjacent items designated to remain. Any

    such damage shall be rectified by the contractor at his own cost.

    The Contract unit rate for the work shall be, payment in full for all labour, material, tools,

    equipment and incidental charges necessary to complete the work.

    201.7 Clearance of Sludges from the Manholes / Gully pits

    All the sludges from the Manhole / Gully pits within the limit of works shall have to be cleared

    as per direction of the engineer.

    201.8 Measurement for Payment

    No separate payment will be made.

    202 Dismantling Culverts, Bridges and Other Structures / Pavements

    Sub-Clauses 202.1 and 202.2 of the MOSRT&H Specifications are unaltered.

    202.3 Dismantling Pavements and Other Structures

    Add the following sub-paragraph in between the two sub-paragraphs of Sub-Clause 202.3 of

  • 7/26/2019 Technical Specification_SIDCL.pdf

    35/194

    51

    the MOSRT&H Specification.

    For careful scarifying of bituminous layers to specified level and grade, refer to Sub-Clause

    501.8.3.2.

    Add the following at the end of Sub-Clause 202.3 of the MOSRT&H Specification.

    The dismantling operations shall have to be conducted carefully, so as not to damage thematerials which are scheduled to be or may be reused with or without further treatment.

    202.5 Disposal of Materials

    Sub-Clause 202.5 of the MOSRT&H Specification is deleted and the following substituted:

    Unless specifically stated otherwise within the Contract Documents, all surplus materials arising

    from the Works (except those arising from private properties) shall be the property of the

    Contractor. The disposal of all surplus materials arising from the Works shall be the

    responsibility of the Contractor. The Contractor shall be deemed to have allowed in his rates

    for all cost associated with such disposal and any salvage value of any materials. Materials

    indicated within the Contract Documents as required for reuse shall be the property of the

    Employer.

    202.6 Measurements for Payment

    Delete the Sub-Clause 202.6 of MOSRT&H Specification entirely and substitute the following:

    Dismantling required for the Permanent Works will be measured for payment, while

    dismantling for haul roads, borrow areas and all the Temporary Works will not be measured

    for payment. The work of dismantling structures shall be paid for in units indicated below, by

    taking measurements before and after as applicable:

  • 7/26/2019 Technical Specification_SIDCL.pdf

    36/194

    52

    Work Item Unit of

    Measurement

    Brick/Stone masonry/concrete (plain and

    reinforced)

    cu.m

    Gullies No.

    Flexible and cement concrete pavements cu.m

    Road Pavement cu.m

    Footpath cu.m

    Steel structures tonne

    Timber structures cu.m

    Pipes, guard rails, kerbs, gutters and

    fencing

    lin m

    Pedestrian Barrier lin m

    Kerbs lin m

    Channel Blocks lin m

    Garden / Median Fencing lin.m

    202.7

    Rates

    The words within all lifts and upto a lead of 1000m shall be deleted from Sub-Clause 202.7

    of the MOSRT&H Specification.

    The following Clauses are added to the MOSRT&H Specification Section 200

    203 Other Site Clearance Matters

    203.1 Treatment of areas for Roadway Embankment

    In areas under roadway embankments, from which top soil or unsuitable materials are to be

    removed or which are designated to be compacted, all stumps and roots shall be removed to a

    depth of at atleast 50 cm below the original ground surface and at least 50 cm below the

    bottom of the lowest pavement layer.

    203.2 Protection of Areas Designated to Remain

  • 7/26/2019 Technical Specification_SIDCL.pdf

    37/194

    53

    In areas designated by the Engineer, the Contractor shall be responsible for the protection and

    routine maintenance of existing shrubs, trees and grassed areas. On completion of the Works

    these areas shall be returned to the Employer in the same condition as before and any

    damage due directly or indirectly to the Contractor's operations shall be made good at his owncost The Contractor may take photos for his recording of the original condition at the time of

    work commencement.

    203.3 Maintenance of Flows in Culverts to be demolished.

    Where the Works include the diversion of existing culverts and subsequent demolition of the

    existing sewers and similar services, demolition of such existing services shall not commence

    until authorised by the Engineer. Such authorization will be dependant upon availability of the

    alternative diversion where appropriate.

    203.4 Maintenance of Traffic Flow - Alternative Traffic Routes

    No road, bridge, tram track or other structure in use by traffic shall be removed until

    authorised by the Engineer. Such authorization will be dependant upon satisfactory alternative

    arrangements have been made to accommodate traffic where appropriate.

    203.5 Materials for Reuse

    Existing kerbs, channels, street furniture and other materials designated for dismantling and

    reuse by the contractor in his offer, shall be carefully removed and stockpiled for re-use in the

    Works, or shall be disposed of, as directed by the Engineer.

    Dismantling of existing items shall be undertaken in such a manner as to avoid damage to

    existing pavements and kerbs which are designated to remain.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    38/194

    54

    203.6 Measurement & Payment

    Reuse of material except kerbs shall not to be measured and paid and is deemed to be

    included in contract price.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    39/194

    55

    SECTION 300 Earthwork, Erosion control and Drainage

    Clause 301 Excavation for Roadway and Drains

    301.1

    Scope

    The following shall be added at the end of Clause 301.1:

    The scope of this clause does not include excavation of trenches for utilities and excavation for

    surface water drainage works, which are governed by Clause 3200 later in this volume.

    301.2 Classification of Excavated Material

    301.2.2 Authority for classification

    The existing clause shall be deleted and following substituted in its place:

    The Engineer shall be the sole authority for the classification of the soil in excavation and his

    decision shall be final and binding on the Contractor. Soil classification will not be decided on

    the basis of the means adopted i.e. use of explosives or hydraulic or pneumatic breakers in

    excavation, but by the Engineer who may authorize such use.

    301.3 Construction Operations

    301.3.1Setting out

    Delete the 2nd sentence of this MOSRT&H Sub-Clause beginning and ending with The

    Contractor shall. establishment of bench marksand substitute with the following:-

    The contractor shall set out the works and shall establish bench marks from the initial control

    points supplied by the Engineer.

    Sub-Clause 301.3.2 is unaltered from the MOSRT&H Specification.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    40/194

    56

    301.3.3 Excavation-General

    The following shall be added at the end of the third paragraph of this clause:

    Temporary shoring shall be provided by the Contractor to the sides of the excavation wherevernecessary to support the foundations of adjoining structures and road pavement and to

    prevent any ground movement. Where temporary supports are required they shall be

    designed, provided and removed such that no ground movement occurs on removal.

    The Contractor shall submit his proposals for support of excavations to the Engineer for

    approval prior to commencement of excavation.

    301.3.5 Rock Excavation - Rock

    DELETED

    301.3.6Marshy Excavation

    This clause shall remain unchanged as in MOSRT&H specification.

    301.3.11 Disposal of Excavated Materials

    The first paragraph shall be deleted and the following substituted:

    All materials arising from excavations required for reuse in the Works shall be the property of

    the Employer. No material shall be removed from Site without the permission of the Engineer.

    However, all surplus excavated materials shall be the property of the Contractor The material

    obtained from the excavation of roadway, shoulders, verges, drains, cross-drainage works etc,

    shall be used for filling up of (i) roadway embankment, (ii) the existing pits in the right-of-way

    and (iii) for landscaping of the road as directed by the Engineer, including leveling and

    spreading with all lifts and leads and no extra payment shall be made for the same.

    Where suitable for reuse, existing granular base and sub-base materials removed as part of

    the works shall be removed carefully and stockpiled and tested for re-use as granular sub-base

    or otherwise as directed by the Engineer.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    41/194

    57

    Delete the words upto 1000mfrom 3rdline of 2ndparagraph of this Sub-Clause.

    Delete the 3rdparagraph of this Sub-Clause and substitute the following:

    Unsuitable and surplus material not intended for use in Works shall be transported with all lifts

    and leads to dispose of as directed by the Engineer.

    301.3.12

    Backfilling

    This clause shall remain unchanged as in MOSRT&H specification.

    301.6 Preparation of Cut Formation

    This clause shall be deleted and the following clauses 301.6.1 to 301.6.3 substituted in its

    place:

    301.6.1 Preparation of Cut Formation in Soil Excavation

    Unsuitable materials found in the sub-grade shall be removed as directed by the Engineer and

    suitable fill material replaced, and compacted in accordance with the requirements of Clause

    305, to not less than 95 % of the MDD determined by IS: 2720 (Part 8). Material with a high

    moisture content shall be considered as unsuitable only on the basis of one or more of the

    conditions stipulated in Clause 305.2.1.1 for unsuitable material.

    Unsuitable materials shall be disposed of in accordance with Clause 301.3.11.

    The bearing capacity of the sub-grade material (i.e. the in-situ material below the underside of

    the granular base course) shall be tested in the laboratory in accordance with IS: 2720 (Part

    16) at 97 % of the MDD determined in accordance with IS2720 (Part 8) and soaked for four

    days. Where the CBR value is less than 10%, the sub-grade shall be strengthened by

    constructing a capping layer and sub-base layer as indicated on the Drawings. Where the CBR

    value is greater than 10 % but less than 30% the sub-grade shall be strengthened by

    constructing sub-base layer as indicated on the Drawings.

    Where indicated on the Drawings or directed by the Engineer, the sub-grade in soil

    excavations shall be protected by the capping layer immediately after completion of the

    preparatory works.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    42/194

    58

    The cut formation in soil excavation, which serves as a sub-grade, shall be prepared to receive

    the capping layer or sub-base immediately after completion of the excavation.

    Where a capping layer is to be constructed and the material in the sub-grade that lies within300 mm of the underside of the capping layer has a density less than 95% of the MDD

    determined in accordance with IS: 2720 (Part 8), the same shall be loosened and conditioned

    to bring the moisture content to within +2 %/ -3 % of the Optimum Moisture Content and

    compacted in layers in accordance with the requirements of Clause 305, to not less than 95%

    of the MDD determined by IS: 2720 (Part 8).

    Where no capping layer is required and the material in the sub-grade that lies within 500 mm

    of the underside of the sub-base has a density less than that specified in Table 300-2, the

    same shall be loosened and conditioned to bring the moisture content to within +2/-3 of the

    Optimum Moisture Content and compacted in layers in accordance with the requirements of

    Clause 305, to not less than 97% of the MDD determined by IS: 2720 (Part 8).

    If due to any reason (such as for example weather) the moisture content of the sub-grade

    material cannot be reduced as specified by aeration and exposure to the sun, compaction of

    the sub-grade shall be suspended and the Contractor shall submit alternative measures to the

    Engineer for approval.

    After satisfying the density requirements, the cut formation shall be prepared to receive the

    capping layer or sub-base in accordance with Clause 310 and 311.

    The finished cut formation shall comply with the surface tolerances described in Clause 902.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    43/194

    59

    301.6.2 Preparation of Cut formation in Rock

    DELETED

    301.6.3 The Capping Layer

    Material for the capping layer shall be suitable fill material complying with Clause 305.2 of the

    specification with a minimum CBR value of 15 % when tested in accordance with IS: 2720

    (Part 16) at 97 % of the MDD determined in accordance with IS: 2720 (Part 8) after soaking

    for four days.

    The capping layer shall be constructed to the lines and levels shown on the Drawings in

    accordance with Clause 305 of the Specification to not less than 97 % of the MDD determined

    in accordance with IS: 2720 (Part 8).

    The finished formation of the capping layer shall comply with the surface tolerances for sub-

    grade described in Clause 902.

    301.7 Finishing Operations

    Paragraph 3 of this clause shall be deleted.

    301.8 Measurements for Payment

    This clause shall remain as in MOSRT&H specification, unchanged.

    301.9 Rates

    This clause shall remain as in MOSRT&H specification, unchanged.

    The following shall be added after Clause 301.9.1 (vi):

    (vii) Working around existing utility appliances

    Delete the last sentence of the Sub-Clause 301.9.1, starting and ending with Provided,

    however, where.. vide Sub-Clause 303.5.

    301.9.2 Loosening and re-compacting

  • 7/26/2019 Technical Specification_SIDCL.pdf

    44/194

    60

    Clause 301.9.2 shall be deleted and the following substituted in its place:

    The Contract unit rate for loosening and re-compacting the loosened materials at sub-grade

    shall include full compensation for loosening to the specified depth, including breaking clods,spreading in layers, watering or drying the material as appropriate including removing the

    material to stockpile and backfilling where necessary, and compacting to the requirements.

    301.9.3

    Sub-Clause 301.9.3 is unaltered from the MOSRT&H Specification.

    301.9.5

    Replace the words but leads upto 1000m in 3rd and 4th lines by all leads.

    301.9.6 Unit Rates for Disposal of surplus earth

    Clause 301.9.6 shall be deleted and the following substituted in its place:

    All surplus materials arising from the Works shall be the property of the Contractor. All material

    required for reuse in the Works shall be the property of the Employer. The disposal of surplus

    excavated material shall be the responsibility of the Contractor. The Contractor shall be

    deemed to have allowed all cost associated with such disposal and any salvage value in the

    Contract Rates.

    This item of work shall not to be measured and paid separately and is deemed to be included

    in the contract price.

    Clause 302 Blasting Operations

    DELETED

    Clause 303 Pre-splitting Rock Excavation Slopes

    DELETED

  • 7/26/2019 Technical Specification_SIDCL.pdf

    45/194

    61

    Clause 304 Excavation for Structures

    304.3 Construction Operations

    304.3.2 Excavation

    Add "or road pavement" after "an adjoining structure" in the fifth line of the second paragraph.

    304.3.4 Preparation of Foundations

    The second sentence of the first paragraphs shall be deleted and the following substituted:

    Before the footing is constructed all disturbed material shall be fully compacted in accordance

    with Table 300.2 and the surface shall be lightly watered, if required, and rammed to compact

    the in situ material.

    304.3.7 Backfilling

    The first paragraph shall be deleted and the following substituted in its place:

    Backfilling shall be done with selected granular material after the concrete or masonry is fully

    set and carried out in such a way as not to cause undue thrust on any part of the structure. All

    space between foundation masonry or concrete and the sides of the excavation shall be filled

    to the original surface in layers not exceeding 150 mm compacted thickness. The compaction

    shall be done with the help of suitable equipment such as mechanical tamper, rammer,

    vibrating plate compactor etc., after necessary watering or drying so as to achieve a density

    not less than the field density before excavation or 90 % of the MDD determined by IS: 2720

    (Part 8).

  • 7/26/2019 Technical Specification_SIDCL.pdf

    46/194

    62

    304.4 Measurements for Payments

    This clause shall remain as in MOSRT&H specification, unchanged.

    304.5

    Rates

    This clause shall remain as in MOSRT&H specification, unchanged.

    Clause 305 Embankment Construction

    305.3 Construction Operations

    305.3.4 Compacting Ground Supporting Embankment / Sub-grade

    The first paragraph shall be deleted and the following substituted:

    Where necessary, the original ground shall be leveled to facilitate placement of the first layer

    of the embankment, scarified, mixed with water or dried as appropriate, and then compacted

    by rolling so as to achieve the minimum dry density as given in Table 300-2.

    The following shall be added at the end of the second paragraph:

    In cases where a capping layer is to be constructed and the difference between the sub-grade

    level and ground level is less than 300 mm and the relative compaction of the ground is less

    than 95 %of the MDD determined in accordance with IS: 2720 (Part 8) the ground shall be

    loosened up to a depth of 300 mm below the underside of the capping layer, scarified, mixed

    with water or dried as appropriate, and then compacted to achieve not less than 95% of the

    MDD determined in accordance with IS: 2720 (Part 8).

    305.7 Sub-grade Strength

    A new sub-clause 305.7.3 shall be added:

  • 7/26/2019 Technical Specification_SIDCL.pdf

    47/194

    63

    305.7.3

    Any imported fill material used as part of the preparation of the sub-grade formation shall

    have a minimum CBR value of 15 % after soaking for four days.

    305.8

    Measurements for Payment

    The first paragraph shall be deleted and the following substituted in its place:

    Earth embankment / sub-grade construction shall be measured separately net from the

    drawings by taking cross-sections at suitable intervals of the original surface before the work

    starts and computing the volume in cubic metres from cross-sections based upon the original

    ground profile and the theoretical finished profile by the method of average end areas.

    305.9 Rates

    This clause shall remain as in MOSRT&H specification, unchanged

    The following shall be added after item (xiii):

    (xiv) Working around existing utility appliances.

    Clause 306 Soil Erosion and Sedimentation Control

    DELETED

    Clause 307 Turfing with Sods

    This clause shall remain as in MOSRT&H specification, unchanged

    .

    Clause 308 Seeding and Mulching

    This clause shall remain as in MOSRT&H specification, unchanged.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    48/194

    64

    Clause 309 Surface / Sub-Surface Drains

    This clause shall remain as in MOSRT&H specification, unchanged

    Clause 310 Preparation and Surface Treatment of Formation

    The first sentence of the first paragraph shall be deleted and the following substituted:

    Preparation of surface treatment of the formation, that is top of the sub-grade or capping

    layer, shall be carried out only after completion of any specified sub-grade drainage and unless

    otherwise agreed by the Engineer immediately prior to laying the sub-base or the road base

    where no sub-base is required.

    No separate measurement for the provisions of the same shall be done as it is already

    considered in the relevant items.

    Clause 311 Works to be kept free of water

    This clause shall remain as in MOSRT&H specification, unchanged

    No separate measurement for the provisions of the same shall be done as it is already

    considered in the relevant items.

    Clause 312 Water Courses at Culverts

    This clause shall remain as in MOSRT&H specification, unchanged.

    Clause 313 Construction of Rockfill Embankment

    DELETED

    The following new Clauses 314 and 315 shall be added to the MOSRT&H Specification:-

    Clause 314 Granular Backfill

    314.1 Scope

  • 7/26/2019 Technical Specification_SIDCL.pdf

    49/194

    65

    This item shall consist of furnishing, placing and compaction granular backfill adjacent to

    structures. The areas in which this material is to be placed in the "Influence Zone" of certain

    structures and this will be shown on the Drawings.

    314.2 Material

    The material shall be well graded crushed or uncrushed gravel, stone, rock fill or natural sand

    or a well mixed combination of any of these. The grading requirements for the material are as

    follows-

    Maximum particle size 10 cm

    Passing 4.75mm sieve 25 to 90

    Passing 0.075mm sieve 0 to 10Plasticity index 10 % maximum

    314.3 Construction

    The granular backfill shall be placed in layers not exceeding 15 cm and compacted in

    accordance with Table 300-2.

    314.4 Method of Measurement

    The quantity of granular backfill to be measured and paid for, will be the number of cubic

    metres of suitable material supplied and compacted to the Engineer's satisfaction and in

    accordance with this Specification.

    The material is required to be placed when filling within the influence zone of certain

    structures and any material placed outside the specified zone will not be measured for

    payment.

    Any existing material within the influence zone, which is removed because of the Contractor's

    method of working, must be replaced by granular backfill at Contractor's expense. Where

    excavation within the influence zone is instructed under any Clause of these Specifications,

    then the backfilling will be carried out with granular backfill and the work will be measured for

  • 7/26/2019 Technical Specification_SIDCL.pdf

    50/194

    66

    payment under this clause.

    314.5 Rates

    The accepted quantities of granular backfill, measured as provided above, will be paid for atthe Contract unit price for the pay item as below. The price and payment will be full

    compensation for the work described in this Clause, including furnishing, hauling, placing and

    compacting the material.

    Work Item Unit of Measurement

    Granular backfill:

    a) Silver sand

    b)

    Coarse sand

    Cubic metre

    Cubic metre

    Clause 315 Permeable Backfill

    DELETED

    315.1 Scope

    This work shall consist of supplying and installing selected backfill material adjacent to

    structures in accordance with these Specifications and in locations as shown on the Drawings

    or instructed by the Engineer.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    51/194

    67

    315.2 Material

    The material shall be hard, clean, crushed rock or gravel complying with the following

    grading:-

    Sieve Size % passing by weight

    63mm 100

    37.5mm 85-100

    19mm 0-20

    9.5mm 0-5

    315.3 Construction

    The method of construction will be at the discretion of the Contractor, but details must be

    submitted for the Engineers approval before commencement of the work. All details of the

    permeable backfill shall be as shown on the Drawings and the degree of compaction shall be

    as instructed by the Engineer.

    315.4 Method of Measurement

    Unless this material is specified as included in another pay item, the quantity of permeable

    backfill to be measured and paid for will be the number of cubic metres of suitable material

    supplied, placed and compacted in accordance with the details shown on the Drawings. Any

    material placed beyond the dimensions shown on the Drawings will not be measured for

    payment.

    315.5 Rates

    The work measured as provided above will be paid for at the Contract price per unit of

    measurement for the item listed below, which price and payment will be full compensation for

    furnishing and placing all materials, and for all labour, equipment and other incidentals

    necessary to complete the work in accordance with the Drawings, specifications and as

    directed by the Engineer.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    52/194

    68

    Work Item Unit of Measurement

    Permeable backfill Cubic metre

    316

    Reinforced Earth Backfill

    DELETED

  • 7/26/2019 Technical Specification_SIDCL.pdf

    53/194

    69

    SECTION 400 Sub-bases, bases (non-bituminous) and shoulders

    Clause 401 Granular Sub-base

    The following amendments are made to Clause 401 of the MOSRT&H Specification:-

    401.1 Scope

    This clause shall remain as in MOSRT&H specification, unchanged.

    401.2 Materials

    401.2.1

    The third sentence of the first paragraph shall be deleted and the following substituted.

    The material shall be free from organic matter, clay balls or other deleterious materials and

    shall conform to one of the gradings given in Table 400-1. The minimum CBR value of the

    granular sub-base material when tested in accordance with IS: 2720 (Part 16) when

    compacted to 98 % of MDD determined in accordance with IS: 2720 (Part 8) and soaked for

    four days shall be 30 %.

    401.2.2 Physical Requirement

    The minimum CBR values from Table 400-1 and Table 400-2 shall be deleted and substituted

    with 30 % for each grading.

    401.4 Construction Operation

    401.4.1 Preparation of Subgrade

    This clause shall remain as in MOSRT&H specification, unchanged.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    54/194

    70

    401.4.2 Spreading and Compacting

    The second and third paragraphs shall be deleted and substituted by the following:

    When the sub-base consists of a combination of materials mentioned in Clause 401.2.1, mixingshall be done off site in an approved mixing plant of suitable capacity having provision for

    controlled addition of water.

    The following paragraph shall be added after the last paragraph:

    At all areas not accessible to the roller, the material shall be compacted thoroughly by

    approved mechanical tampers or compactors.

    401.5 Surface Finish and Quality Control of Work

    This clause shall remain as in MOSRT&H specification, unchanged.

    401.7 Measurement for Payment

    This clause shall remain as in MOSRT&H specification, unchanged.

    401.8 Rate

    The work measured as provided above will be paid for at the contract price per unit of

    measurement for the item listed below:

    Work Item Unit of Measurement

    Granular sub-base:

    a) Stone dust and medium sand

    b) Brick Bats and medium sand

    Cubic metre

    Cubic metre

    402 Lime treated soil for improved sub-grade / sub-base

    DELETED

  • 7/26/2019 Technical Specification_SIDCL.pdf

    55/194

    71

    403 Cement treated soil for sub-base / base

    DELETED

    404

    Water Bound Macadam Sub-base/base

    This clause shall remain as in MOSRT&H specification, unchanged

    405 Crushed Cement Concrete Sub-base/base

    DELETED

    406 Wet Mix Macadam Sub-base / Base

    406.1 This clause shall remain as in MOSRT&H specification, unchanged

    The following amendments are made to Clause 406 of the MOSRT&H Specification:-

    406.2 Materials

    406.2.1 Aggregates

    406.2.1.1 Physical Requirements

    The following shall be added to Table 400-10: "Physical Requirement of Coarse Aggregates

    for Wet MixMacadam for Sub-base / Base.

    In addition to the tests listed above, the coarse aggregates of Wet Mix Macadam Base shall

    comply with the following:

    Test Test Method Requirement

    3

    .

    Water absorption value IS: 2386 (Part 3) Less than 2%

    4

    .

    Sodium sulphate

    soundness

    IS:2386 (Part 5) Less than 12%

    The following shall be added after the last paragraph:

  • 7/26/2019 Technical Specification_SIDCL.pdf

    56/194

    72

    The California Bearing Ratio of the Wet Mix Macadam Base when tested in accordance with IS:

    2720 (Part 16) at 98 % of the MDD determined in accordance with IS: 2720 (Part 8) and

    soaked for four days shall not be less than 80 %.

    406.2.1.2 Grading Requirements

    The following shall be added after Table 400-11: "Grading Requirements of Aggregates for

    Wet Mix Macadam for Sub-base/Base":

    In addition to the grading requirements listed above, the coarse aggregates of Wet Mix

    Macadam Base shall comply with the following:

    The fraction of the aggregate passing the 2.36 mm sieve in Wet Mix Macadam Base shall

    consist of rock or gravel screenings and shall be free from loam, organic or other deleterious

    matter.

    406.3 Construction Operation

    Add the following amendment in this Clause:-

    406.3.2Provision of lateral confinement of aggregates

    Add the words or by kerbs/kerbs and channels and their foundations between the words

    shoulders and along in the 4th line of this Sub-Clause.

    406.4 Opening to Traffic

    This clause shall remain as in MOSRT&H specification, unchanged.

  • 7/26/2019 Technical Specification_SIDCL.pdf

    57/194

    73

    406.5 Surface Finish and Quality Control of Work

    This clause shall remain as in MOSRT&H specification, unchanged

    .

    406.6 Rectification of Surface Irregularity

    This clause shall remain as in MOSRT&H specification, unchanged.

    406.8 Measurement for Payment

    This clause shall remain as in MOSRT&H specification, unchanged.

    406.9 Rate

    This clause shall remain as in MOSRT&H specification, unchanged.

    Clause 407 Shoulder, Islands and Median

    This shall remain unchanged as in MOSRT&H Specification

    Clause 408 Cement Concrete Kerb and Kerb with Channel

    This clause shall be deleted in its entirety and substituted with the following:

    Clause 408 Cement Concrete Kerb / Natural Stone Kerb and Kerb with Channel

    408.1 Scope

    The work shall consist of constructing cement concrete kerbs, natural stone kerbs, concrete

    edgings and kerbs with concrete channel blocks along the footpaths and / or in the central

    median or separators in conformity with the lines and levels and dimensions as specified in the

    drawings. Where specified or indicated on the Drawings, the exposed up-stand face and top

    surface of the kerbs shall be painted alternately in black and white, or yellow.

    408.2 Cement Concrete Kerbs, Edgings and Channel Blocks

  • 7/26/2019 Technical Specification_SIDCL.pdf

    58/194

    74

    408.2.1 Materials

    Unless otherwise described in the Contract, concrete kerbs, edgings, quadrants and channel

    blocks shall be hydraulically pressed pre-cast blocks. During manufacture the kerbs/channel

    blocks shall be subjected to a pressure of not less than 7 MPa. The method of manufactureshall prevent the loss of the finer particles of cement during the pressing process.

    The method of manufacture and testing shall comply with the requirements of IS: 5758, as

    amended here below, and to the cross Clauses shown on the Drawings. All materials shall

    conform to the requirements of IS: 5758 and as specified herein.

    For all kerbs, and associated works specified in this clause, the cement shall be ordinary

    Portland cement conforming with Clause 1006 of the Specifications. Kerbs shall be

    manufactured using a concrete mixture containing not less than 350 kg of cement per cu.

    metre of mix. The concrete when tested in accordance with IS: 516 shall attain a 28 days

    compressive strength of not less than 30 MPa, determined on cubes specimens.

    The top edge and front face of individual pre-cast kerb, channel or edging units shall not

    deviate by more than 1 mm from the nominal profile when checked with a straight edge.

    The Contractor shall submit samples of the various types of concrete kerbs for testing and

    approval by the Engineer before commencing the work.

    Sand / cement mortar for bedding shall comply with Clause 1304 of the Specification, except

    as described below. Class 1 mortar shall be mixed in the proportions 1volume cement to 3

    volumes fine aggregate. Water added shall be the least amount which will yield a mix of

    suitable consistency for masonry work.

    408.2.2Construction Operations

    After preparation and compaction of the granular sub-base pavement layer, the surface shall

    be regulated under the line of the kerbs with additional sub-base material trimmed and

    compacted to the lines and levels shown in the Drawings to provide the platform for

    constructing the kerb or kerb and channel block foundation.

    Pre-cast concrete kerbs, edgings and channels shall be laid and bedded in a layer of Class 1

  • 7/26/2019 Technical Specification_SIDCL.pdf

    59/194

    75

    mortar not less than 10 mm and not more than 40 mm thick, on a foundation of concrete

    grade M 20. Kerbs shall be backed with grade M 20 concrete.

    Joints between kerb stones, other than expansion joints shall be of uniform width not greater

    than 4 mm and shall be filled with Class 1 mortar.

    Expansion joints shall be provided through the kerbs, kerb foundation and kerb backing at 9

    metre spacing along the kerb run. The joint filler shall be formed of 12 mm thick bitumen

    impregnated fibre-board complying with IS: 1838 (Part 1).

    Any unit of kerb, channel, edging and quadrant deviating more than 3 mm in 3 m from line

    and level shall be made good by lifting and relaying.

    408.2.3 Measurement

    Cement concrete kerbs, edgings and channel blocks shall be measured separately in linear

    metres for the complete item of work. No separate item will be made for kerb and/or channel

    foundations, concrete backing, joints or expansion joints.

    408.2.4 Rates

    The Contract unit rates for concrete kerbs, edgings, quadrants and channel blocks shall be

    payment in full compensation for furnishing all materials, labour, tools, equipment for

    construction and other incidental cost necessary to complete the work.

    408.3 Natural Stone Kerbs and Edgings

    DELETED

  • 7/26/2019 Technical Specification_SIDCL.pdf

    60/194

    76

    408.4 Kerb Painting

    408.4.1 Materials

    Where specified on the drawings kerbs shall be painted with quick-drying chlorinated


Recommended