Date post: | 13-Apr-2018 |
Category: |
Documents |
Upload: | rakesh-ranjan |
View: | 216 times |
Download: | 0 times |
of 194
7/26/2019 Technical Specification_SIDCL.pdf
1/194
17
Chapter 7 TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
Preamble
Section 100 General
101 Introduction
102 Definitions
103 Materials and Test Standards
104 Sieve designations
105 Scope of Work
106 Construction Equipment
107 Contract Drawings
108 Site Information
109 Setting out
110 Public Utilities
111 Precautions for safeguarding the environment
112 Arrangement for Traffic during construction
113
General rules for the measurement of works for payment
114
Scope of rates for different items of work
115 Methodology and sequence of work
116 Crushed stone aggregates
117 Approval of materials
118 Supply of quarry samples
119 Use of surface by construction traffic
120 Site Office for Engineer and other supervisory staff
121 Field Laboratory
122
Site residential accommodation for Engineer and other supervisory staff123 Providing and maintaining Wireless Communication System / Mobile Phones
124 Providing and maintaining Project Vehicle
125 Deleted
126 Deleted
127 Deleted
128 Tolerance
7/26/2019 Technical Specification_SIDCL.pdf
2/194
18
129 Temporary Buildings and Site Services
130 Hoardings and Fencing
131 Project Information signboards
132 Reports and Documentation
Section 200 Site Clearance
201 Clearing and grubbing
202 Dismantling culverts, bridges and other structures / pavements
203 Other site Clearance matters
Section 300 Earthwork, Erosion Control and drainage
301 Excavation for roadway and drain
302 Blasting operations
303 Presplitting rock excavation slopes
304 Excavations for structures
305 Embankment construction
306 Soil Erosion and sedimentation control
307 Turfing with sods
308 Seeding and mulching
309 Surface/sub-surface drains
310 Preparation and surface treatment of formation
311 Works to be kept free of water
312 Water Courses at Culvert
313 Construction of rockfill embankment
314 Granular Backfill
315 Permeable Backfill
Section 400 Sub-bases, Bases (Non-bituminous) and Shoulders
401 Granular sub-base
404 Water bound macadam sub-base/base
405 Crushed cement concrete sub-base/base
406 Wet mix macadam sub-base/base
407 Shoulders, islands and median
7/26/2019 Technical Specification_SIDCL.pdf
3/194
19
408 Cement concrete kerb and kerb with channel
409 Footpaths and separators
410 Crusher-run macadam base
Section 500 Bases and Surface Courses (Bituminous)
501 General Requirements for Bituminous Pavement Layers
502 Prime coat over granular base
503 Tack coat
504 Bituminous macadam
505 Bituminous penetration macadam
506 Built-up spray grout
507 Dense bituminous macadam
508 Semi-dense bituminous concrete
509 Bituminous concrete
510 Surface dressing
511 Open graded premix carpet
512 Mix seal surfacing
513 Seal coat
514 Supply of mineral aggregates for pavement courses
515 Mastic Asphalt
516 Slurry seal
517 Recycling of bituminous pavement
Section 800 Traffic signs. Marking & Other Road Appurtenances
801 Traffic signs
802 Overhead signs
803 Road markings
804 Hectometre/Kilometre stones
805 Road delineators
806 Boundary stones
807 Fencing
808 Tubular steel railing
809 Concrete crash barrier
7/26/2019 Technical Specification_SIDCL.pdf
4/194
20
810 Metal beam crash barrier/ Box beam barrier
811 Road traffic signals
812 R.C. guard post
Section 900 Quality Control for Road Works
901 General
902 Control of alignment level and surface regularity
903 Quality control tests during construction
Section 1000 Materials for Structures
1001 General
1002 Sources of materials
1003 Bricks
1004 Stones
1005 Cast iron
1006 Cement
1007 Coarse aggregates
1008 Sand/fine aggregates
1009 Steel
1010 Water
1011 Timber
1012
Concrete admixtures
1013 Reinforced concrete pipes
1014 Storage of materials
1015 Tests and standard of acceptance
Section 1100 Pile foundations
1101 Description
1102 Sub-surface investigation
1103 Types of piles
1104 Materials
1105 Test piles
1106 Pre-cast concrete piles
7/26/2019 Technical Specification_SIDCL.pdf
5/194
21
1107 Cast in-situ concrete piles
1108 Steel piles
1109 Timber piles
1110 Driving equipment
1111
Driving1112
Raker (inclined) piles
1113
Pile tests
1114 Pile caps
1115 Bored cast-in-situ piles
1116 Tolerances
1117 Tests and standards of acceptance
1118 Measurements for payment
1119 Rate
Section 1300 Brick Masonry
1304 Cement mortar
Section 1500 Formwork
1501 Description
1502 Materials
1503 Design of formwork
1504
Workmanship
1505 Formed surface and finish
1506 Precautions
1507 Preparation of formwork before concreting
1508 Removal of formwork
1509 Re-use of formwork
1510
Specialized formwork
1511 Tests and standards of acceptance
1512 Measurements for payment
1513 Rate
Section 1600 - Steel Reinforcement (untensioned)
7/26/2019 Technical Specification_SIDCL.pdf
6/194
22
1601 Description
1602 General
1603 Protection of the reinforcement
1604 Bending of reinforcement
1605
Placing of reinforcement1606
Bar splices
1607
Testing and acceptance
1608 Measurements for payment
1609 Rate
Section 1700 - Structural concrete
1701 Description
1702 Materials
1703 Grades of concrete
1704 Proportioning of concrete
1705 Admixtures
1706 Size of coarse aggregates
1707 Equipment
1708 Mixing concrete
1709 Transporting, placing and compaction of concrete
1710 Construction joints
1711 Concreting under water
1712
Adverse weather conditions
1713 Protection and curing
1714 Finishing
1715 Tolerances
1716 Tests and standards of acceptance
1717 Measurements for payment
1718
Rate
1719 Application of Loading
1720 Use of Adhesives
1721 Additional reference to IRC: SP-65
Section 1800 Prestressing
7/26/2019 Technical Specification_SIDCL.pdf
7/194
23
1801 Description
1802 Materials
1803 Testing of Prestressing Steel and Anchorages
1804 Workmanship
1805
Supervision1806
Tensioning Equipment
1807
Post-Tensioning
1808 Grouting of Prestressed Tendons
1809 Pre- Tensioning
1810 Safety Precautions during tensioning
1811 Transportation and storage of units
1812 Tolerances
1813 Tests and standard of acceptance
1814 Measurements for Payment
1815 Rate
1816 IRC : SP-65 2005
Section 1900 Structural Steel
1901 Description
1902 General
1903 Materials
1904 Fabrication
1905
Erection
1906 Painting
1907 Tests and standards of acceptance
1908 Measurements for payment
1909 Rate
1910 Other incidental bridge facilities
Section 2000 Bearings
2001 Description
2002 General
2003 Steel bearings
2004 Special bearings
7/26/2019 Technical Specification_SIDCL.pdf
8/194
24
2005 Elastomeric bearings
2006 Pot bearings
2007 Inspection and testing
2008 Tests and standards of acceptance
2009 Measurements for payment2010 Rate
Section 2200 Sub-structure
2201 Description
2202 Materials
2203 General
2204 Pier and abutments
2205 Pier cap and abutment cap
2206 Dirt/ballast wall, return wall and wing wall
2207 Tests and standards of acceptance
2208 Tolerances in concrete elements
2209 Measurements for payment
2210 Rate
7/26/2019 Technical Specification_SIDCL.pdf
9/194
25
Section 2300 Concrete superstructure
2301 Description
2302 Material
2303
General2304
Reinforced concrete construction
2305
Prestressed concrete construction
2306 Tolerances
2307 Tests and standards of acceptance
2308 Measurement for payment
2309 Rate
2310 Reference IRC: SP-65 -2005
2311 Construction Requirement for Precast Segmental Superstructure
Section 2400 Surface and sub-surface geotechnical exploration
2401 General
2402 Preliminary investigation
2403 Detailed investigation
2404 Exploration for bridge foundations resting on rock
2405 Boring
2406 Records of borings and trial pits
2407 Method of Sampling
2408
Procedure for taking samples
2409 Protection, handling and labeling of samples
2410 Tests for exploration of shallow foundations of bridges
2411 Test for exploration of deep foundation of bridges
2412 Testing of material for guide bund and high embankment and its foundations
2413 Measurement for payment
2414
Rate
Section 2500 - River Training Works
2504 Pitching / revetment on slopes
7/26/2019 Technical Specification_SIDCL.pdf
10/194
26
Section 2600 - Expansion joints
2601 Description
2602
General2603
Requirements
2606
Elastomeric slab seal expansion joint
2607 Strip seal expansion joint
2608 Tests and standards of acceptance
2609 Measurement for payment
2610 Rate
Section 2700 Wearing coat and Appurtenances
2701 Description
2702 Wearing coat
2703 Railings
2704 Approach slab
2705 Drainage spouts
2706 Weep holes
2707 Tests and standards of acceptance
2708 Measurement for payment
2709 Rate
Section 2900 - Pipe culverts
2901 Scope
2902 Materials
2903 Excavation for pipe
2904 Bedding for pipe
2905 Laying of pipe
2906 Jointing
2907 Backfilling
2908 Headwall and other ancillary works
2909 Opening to traffic
2910 Measurements for payment
7/26/2019 Technical Specification_SIDCL.pdf
11/194
27
2911 Rate
Section 3500 Protection and Necessary Diversions of Existing Dry Utilities
3501 Scope3502 Measurement for payment
Section 3800 Painting of bridge, Culvert, Post, Railing etc.
3801 Painting of post, wheel guards, railing etc.
3802 Painting of bridge and culvert
7/26/2019 Technical Specification_SIDCL.pdf
12/194
28
Preamble
The work of Construction of R.C.C Bridge over River Kalnagini Branch Canal near
Nrisingha Ashram of Swami Vivekananda & Sri Ramkrishna Gram Panchayat under
Kakdwip Block in the district of South 24 Paraganas, West Bengal is to be
constructed to the Specifications for Road and Bridge Works, Fourth Revision, Reprint of March
2006 (MOSRT&H specifications) as supplemented by this Volume wherein some of the clauses
of the MOSRT&H specification have been amended, modified, supplemented, substituted,
deleted and where necessary new clauses added, in order to be better applicable to the
Works. Therefore the MOSRT&H specifications, jointly read with this Volume, will
govern the Works.
In case there is contradiction between the provisions of MOSRT&H specifications and those
detailed in this Volume, the latter shall prevail.
The Clause numbers in MOSRT&H specifications have been followed in this Technical
Specification and amendments, additions, deletions and other changes have been indicated by
referring to the particular clause. Where new clauses have been added, new numbers have
been given to Clauses or Sections. Where no amendment or change is mentioned, the original
Clauses in MOSRT&H specification shall prevail.
Where several types of construction or materials are specified in the MOSRT&H Specification,
the Contractor shall refer to this Technical Specification and/or the other Contract Documents
in applying the definitive types used for the Works.
The contractors shall quote their contract price at item rate basis based on the rates of
different items provided in the priced Bill of Quantities for whole cost of complying with
provisions of contract comprising Instruction to Bidders, the General Conditions of Contract,
the Technical Specifications and other related tender documents.
The Contractors price is deemed to cover all the provisions under the clauses mentioned
hereinafter. Other than what is included in item rate quoted price and BOQ item for running
bills no other measurement of payment shall be done and shall be deemed to be incidental to
the main works and no separate payment will be made for these provisions beyond the
Contract price.
7/26/2019 Technical Specification_SIDCL.pdf
13/194
29
SECTION 100 GENERAL
101 Introduction
This Clause shall remain unchanged as in MOSRT&H specification.
102 Definitions
Wherever the word drawing appears in this volume, it will mean General Arrangement Drawing
and further detailed drawings for permanent works to be furnished by SIDCL.
The following shall be added after at the end of the first paragraph:
The associated definitions of contractual terms are given in Clause 1.1 of the General
Conditions of Contract (Section 4 of Volume I of these Contract Documents).
103 Materials and Test Standards
The following shall be added after at the end of the first paragraph,-
Appendix 1 of the MOSRT&H Specification gives the Indian and other standards referred to in
the text of the specifications. Additional standards and testing procedures, as required, are
specified in appropriate places in this Technical Specification.
103.1 Substitution of foreign standards by Indian equivalent
All products materials supplied by the Contractor shall conform to the Specification and shall
be approved by the Engineer. Where specific manufacturers or brand names are mentioned in
the Contract Documents, it shall be deemed that that product or similar approved is required.
It shall not be deemed to indicate that the particular manufacturer is mandatory.
Where any materials or equipment are specified, as being in accordance with non-Indian
Standards it should be understood that these are automatically be substituted by such
equivalent to IS or I.R.C. In case application of IS or I.R.C is found unsuitable from a technical
point of view, the Employer will take appropriate measures based on the recommendation of
the Engineer.
7/26/2019 Technical Specification_SIDCL.pdf
14/194
30
103.2 Applicable edition of Standards
In the Specification materials or tests specified as being in accordance with IS or I.R.C.,
AASHTO or ASTM shall refer to the specifications or method of test prevailing till 28 days prior
to the final date for the submission of Tenders, unless otherwise stated.
104 Sieve Designations
This shall remain unchanged as in MOSRT&H specification.
105 Scope of Work
105.1 This shall remain unchanged as in MOSRT&H specification upto sub cl. 105.4.The
following shall be added after sub cl. 105.4
105.5 Composition of Works
The scope of work shall generally comprise of but not necessarily be limited to the following:
(a) Construction of the Permanent Works, e.g. R.C.C prestressd bridge resting on piles and
pile caps, piers, crossheads, Solid R.C.C. Wall type Abutment, Precast segmental Box
girder, to the lines and levels as specified in the Drawings and Specification.
(b) Design, provision and subsequent removal of all Temporary Works, staging/scaffolding,
Casting bed, shuttering and Ancillary work required for the construction of the Permanent
Works.
(c) Design and provision of any ground treatment required for the construction of
foundations and pipe culverts in poor soil strata where required.
(d) Keeping the Site secure and maintaining of access to and from the Site, in order for the
Works to be carried out in accordance with the Contract
(e) Provision and delivery of all materials, Contractor's Equipment and manpower required to
construct the Works
(f) Removal and disposal at a suitable tip of arising from all construction activities. The
transport provided shall be suitable for the nature of the arising and shall not leak or
discharge any of its contents during transportation or during transfer from one means of
transport to another.
(g) Temporary and permanent reinstatement of roads and footpaths in accordance with
7/26/2019 Technical Specification_SIDCL.pdf
15/194
31
Drawings and Specification and the requirements at site.
(h) Maintaining all times of a safe traffic movement around the Site in accordance with the
Relevant Authorities.
(i) Preparation of bar bending schedules for all reinforced concrete structures and all
construction drawings including shop drawings for all structural steel work, ConstructionMethodology/ Method statement for Precast Segmental work, Construction methodology
/ Method statement for erection of precast Box segments including casting, curing
stressing etc. The Contractor shall be responsible for checking the accuracy of bending
dimensions shown on all bending schedules. These schedules are to be submitted to the
Engineer for his approval.
(j) Preparation of as-built drawings for the completed Works. These shall be submitted to
the Engineer for his review and approval.
105.6 Exclusions from the Contractor's Works
The following works and services shall be excluded from the Contractor's scope of work:
(a) Provision of right-of-way
(b) Provision of initial base points/line(s) and bench mark(s) to be referred to for the
contractor's setting out
106 Construction Equipment
This Clause shall remain unchanged as in MOSRT&H specification.
107 Contract Drawings
This Clause shall remain unchanged as in MOSRT&H specification.
7/26/2019 Technical Specification_SIDCL.pdf
16/194
32
108 Site information
108.1 Site Conditions
The following shall be added to Clause 108.1The requirements of the Conditions of Contract Clause 11 and 12 shall take precedence.
108.4 Quarry Charts
Clause 108.4 of the MOSRT&H Specification shall be deleted and the following substituted in
its place:
No quarry information is provided under the contract. The Contractor is expected to make his
own arrangements for the availability of all construction material and, rates shall be deemed to
include any associated transportation and all other charges.
109 Setting out
109.1 Bench Marks
Add the words subject to a minimum two in a project (work location) after the words four
per km in the sixth line.
The following shall be added after the Clause 109.1:
Except where otherwise specified, all levels shall be in metres expressed to three places of
decimals. All levels on Site shall be determined from the temporary benchmark provided at site
with an arbitrary level of 100.000.
This is to be linked with nearest reference bench marks of PW (Roads) or PWD.(Govt. of W.B)
109.3 Manner of Setting Out
Clause 109.3 of the MOSRT&H Specification shall be deleted and the following substituted in
its place:-
The Works shall be accurately set out and referenced to the satisfaction of the Engineer.
Marking systems shall require the prior approval of the Engineer and full records of setting out
and reference points shall be reported to the Engineer in formats to his approval. All setting
out markings and reference points shall be maintained until their removal is approved by the
Engineer.
109.9 Precision of Instrumentation
Clause 109.9 of the MOSRT&H Specification shall be deleted and the following substituted in
its place:-
The precision of surveying and measuring instrumentation shall be to the satisfaction of the
Engineer.
7/26/2019 Technical Specification_SIDCL.pdf
17/194
33
The following shall be added after clause 109.9:-
109.10 Surveying Equipment for the Engineer's Use
The Contractor shall furnish the Engineer for his exclusive use the following instruments,
appliances, surveyor personnel and labour, and materials for the Engineer use in connection
with the Works:(a) 1 Surveyor and 2 Surveying assistants
(b) One set of Surveying equipment as listed below or equivalent, as will be approved by the
Engineer. The equipment will be used by crew of 1 Surveyor and 2 surveying Assistants.
Main Equipment:
Total Station (Make: Nikon or Sokkia or Leica or Trimble) with following minimum
specifications:
Minimum display (least count) : 1second
Angle measuring Accuracy : 2 seconds
Distance Accuracy : + 2mm + 2ppm x D
1 MB SRAM
16 MB compact Flash Card
Maximum distance measurement with single prism: 2.7km
Auto Level of make and accuracy to be approved by the Engineer
Accessories: Generally, these shall be of same make of the main equipment
Wooden Tripod
Program Card
Card reader/Writer
Triple prism set
Prism Pole Tripod
Telescope Prism Pole Set
2 steel measuring tapes 50m long
2 steel measuring rods (4m)
2 nos Leveling Staff
Survey stakes as required and
Miscellaneous tools and consumables as required in surveying.
All surveying instruments shall be supplied complete including tripods, staffs etc.
109.11 Maintenance
Such survey equipment shall be calibrated prior to use and periodically, and be repaired or
replaced by the Contractor as required by the Engineer.
7/26/2019 Technical Specification_SIDCL.pdf
18/194
34
109.12 Ownership
The surveying equipment will be treated as the property of the Employer during the period of
contract including extension period and will be returned to the Contractor on as is where is
basis within thirty days (30) of the issuance of the Taking Over Certificate.
109.13 Measurement for Payment
The supply of surveying equipment and its maintenance and shall be measured for payment as
follows:
(1) no separate payment for provision of the equipment, including the demonstration,
(2) by time related monthly items for the maintenance of the equipment including the
demonstration.
(The monthly payment should cover activity under item 1 above and item 3 hereunder)
(3) no separate payment for removal of equipment,
(4) by time related monthly items for supply of 1 Surveyor and 2 surveying assistants as a
group to work with the equipments.
109.14 Rates
The Contract rates for time related monthly payment shall include all aspects of the
procurement, delivery, maintenance and removal of the surveying equipment for the
Engineers exclusive use. In other words, the scope is similar to monthly hire charges for the
equipment in working condition. Prorate rate shall be applicable if the equipment is not fit for
use for more than 3 calendar days in a particular month. Rate for Surveyors and surveying
Assistants shall be per shift per month, in units of 1 Surveyor and 2 survey Assistants.
7/26/2019 Technical Specification_SIDCL.pdf
19/194
35
110 Public utilities
Sub Clause 110.1 of the MOSRT&H Specification is deleted entirely and the following
substituted:
Channelizing the request through SIDCL, the Contractor shall have to collect the information
from the concerned authority(ies) and/or make one trial trenches at 150 metre interval or
closer to confirm the exact location of utilities at site. Drawing scheduling the affected
services like water pipes, sewers, cables, gas ducts etc. owned by various authorities
including Public Undertakings and Local Authorities shall be prepared by the contractor and
verified by the contractor for accuracy of the information prior to the commencement of any
work close to those services. SIDCL will arrange for their shifting through the owning agencies.
The Contractor shall be asked to render all assistance during the execution of the utility work,
by suitably programming their main work at no extra cost to SIDCL and shall be treated as
incidental to the work.
The Contractor is therefore required to provide drawings showing the exact routes of all the
dry utilities, and underground installation, as located by trial trenches and survey. The above
incidental works shall have to be carried by the Contractor at his own cost.
Sub Clauses 110.2 to 110.7 are unaltered from the MOSRT&H Specification.
111 Precautions for Safeguarding the Environment
This shall remain unchanged as in MOSRT&H specification
112 Arrangements for Traffic during Construction
Clause 112 of the MOSRT&H Specification is deleted entirely and the following substituted:
112.1 General
The Contractor shall carry out the Works in a manner creating least interference to the safe
flow of traffic consistent with the execution of the Contract.
The Contractors project planning shall include a traffic control plan for moving traffic through
and around the construction zone in a manner that is conducive to the safety of the travelling
public, pedestrians and workers.
7/26/2019 Technical Specification_SIDCL.pdf
20/194
36
The traffic control plan shall include such items as , methods and devices for delineation and
channelisation, signaling signing, application and removal of pavement markings, placement of
devices; working area lighting, surveillance and inspection.
The Contractor shall submit the Program for approval of the Engineer of the works associated
with the sub-projects (Project Sections) which shall, in principle, be carried out in stages andsub stages covering various components of the works.
The Contractor shall take prior approval of the Engineer, traffic police and other concerned
authorities regarding traffic arrangement during construction.
No two sequences of work will be taken simultaneously without the prior approval of the
Engineer.
The Contractor shall make the road or footpath available for public use after the completion of
one section of work if blocked temporarily.
The Contractor shall obtain the specific prior permission from traffic police and other
concerned authorities for the transportation of all plant and material to and from the site,
particularly on the public highway.
The Contractor shall maintain two lanes available for traffic in each direction at all times except
when a temporary reduction is approved by the Engineer and granted specific prior permission
from traffic police and other concerned authorities. The existing drainages should not be
affected by contractor's work.
The minimum permissible traffic route widths shall be as follows:
1 lane - 3.5m
2 lane - 6.5m
3 lane - 9.9m
Further temporary reduction shall be allowed subject to the prior approval of the Engineer, the
traffic police and other concerned authorities.
Minimum 1.5m width of footpath of approved hard surfacing shall be kept free during
construction period as a temporary measure, if they are allowed to occupy existing footpath
space for any reason whatsoever for construction activities.
112.2 Passage of Traffic along a part of the Existing Carriageway under
improvement
Shall remain same
112.3 Passage of traffic along a temporary diversion
Shall remain same
7/26/2019 Technical Specification_SIDCL.pdf
21/194
37
112. 5 Maintenance of Diversion and Traffic Control Devices
Signs, lights, barriers and other traffic control devices of diversion roads shall be maintained in
a satisfactory condition till such time as they are required as directed by the Engineer. The
temporary traveled way shall be kept free of dust by frequent applications of water, if
necessary.
112. 6 Measurements for Payment and Rate
Shall remain same
113 General rules for the measurement of works for payment
Clause 113 from the MOSRT&H Specification shall be deleted entirely and the following
substituted in its place:-
113.1 Method of Measurement
All measurements for payment in the Bill of Quantities shall be made net based on the
Drawings, or the actual work done approved by the Engineer. The contractors quoted price
shall include this cost in the Item rate cost. The Bill of Quantities are for monthly/ periodical on
account payments only and this cost will merge in the final amount. Detailed measurements
are to be furnished by contractor to compare with as built drawings.
114 Scope of rates for different items of work
This shall remain unchanged as in MOSRT&H specification.
115 Methodology and sequence of work.
This shall remain unchanged as in MOSRT&H specification. The requirements of the Conditions
of Contract shall take precedence.
116 Crushed stone aggregates
This shall remain unchanged as in MOSRT&H specification.
117 Approval of materials
7/26/2019 Technical Specification_SIDCL.pdf
22/194
38
This shall remain unchanged as in MOSRT&H specification.
118 Supply of quarry samples.
This shall remain unchanged as in MOSRT&H specification.
119 Use of surface by construction traffic.
This shall remain unchanged as in MOSRT&H specification.
120 Site office for Engineer and other supervisory staff.
The sub-section is deleted entirely and the following is substituted:
120.1 A temporary site office of 500 (five hundred) sqft carpet area with facility of toilet,
electricity, water, reasonable furniture for the engineer and his representative,
computer operator and other facilities as will be directed by the Engineer shall be
handed over to the Engineer within 30 days after issue of work order for their use.
They shall remain the property of the contractor and shall be returned to the
contractor within thirty (30) days after issuing taking over certificate for the whole
work.
120.2 Payment will be made on the basis of B.O.Q. provision under preliminary subhead.
121 Field laboratory
7/26/2019 Technical Specification_SIDCL.pdf
23/194
39
121.1 Scope
This shall remain unchanged as in MOSRT&H specification
121.2
Description
Clause 121.2 of MOSRT&H Specifications shall be deleted entirely and the following
paragraphs substituted in its place:
The area for the erection of the field laboratory will not be provided by the Employer, and the
provision of such area shall be the responsibility of the Contractor. The field laboratory shall be
for the exclusive use of this project and should not be shared with any other work even under
another Government agency.
The field laboratory shall preferably be located adjacent to the site and shall be provided with
amenities like water supply, electric supply etc. as well as laboratory tables, cupboards, chairs,
tables and other furniture as necessary.
The floor space of the field laboratory shall be decided by the Contractor, subject to the
approval of the Engineer. Office space shall be provided within the field laboratory for the use
of the Engineer's Materials Engineer.
The laboratory will be operated by the Contractor under the supervision of the Engineer.
All other apparatus and materials necessary for tests required under the Contract shall be
supplied by the Contractor and installed in the laboratory. Not later than 30 days after the
receipt of the Letter of Acceptance, the Contractor shall submit for the Engineer's approval, a
list of all equipment to be procured and details of suppliers.
All equipment used for testing shall be of standard type and approved by the Engineer and
properly housed by the Contractor. An adequate supply of water and electric power shall be
provided at all time.
Every designation of the Indian Standards or other foreign standard specifications shall refer to
the versions of those specifications current 28 days prior to the final date for the submission of
Tenders, except where otherwise stated.
7/26/2019 Technical Specification_SIDCL.pdf
24/194
40
In any case where material or workmanship is specified by one of the above tests, and
alternative test methods are allowed, the method used to determine compliance with the
Specification will be at the absolute discretion of the Engineer.
The Contractor shall provide laboratories fully equipped and furnished at locations approved bythe Engineer in order that the Engineer can control and supervise the material used for (i)
concrete batching and / or (ii) bituminous pavements and operations of bituminous mixing
plants. Only such laboratories can be at a remote place close to the plants at a remote area
from pollution point of view.
121.3 Laboratory equipment
Clause 121.3 of the MOSRT&H Specification shall be deleted entirely and the following
substituted in its place;-
All necessary laboratory equipment shall be provided, maintained and operated by the
Contractor for the sampling, transporting, storing, curing, preparation of samples and testing
of all materials required for the Works.
All laboratory equipment shall be to the approval of the Engineer.
121.4 Ownership
Clause 121.4 of the MOSRT&H Specification shall be deleted entirely and the following
substituted in its place:
The area for the erection of the laboratories will not be provided by the Employer, and the
provision of such area shall be the responsibility of the Contractor. However where there is
available space the Employer may give permission for the laboratories office to be erected
within Such areas, at payment of ground rent, at rate to be decided by the employer.
The laboratories and equipment as detailed in Sub-clause 121 above shall be provided by the
Contractor for the use of the Employer and/or Engineer. They shall remain the property of the
Contractor and shall be returned to the Contractor within thirty (30) days after issuing the
Taking-Over Certificate.
7/26/2019 Technical Specification_SIDCL.pdf
25/194
41
121.5 Maintenance
Clause 121.5 of the MOSRT&H Specification shall be deleted entirely and the following
substituted in its place; -
The Contractor shall be responsible for all aspects of maintenance and operation of the
laboratories, including all costs associated with purchase, delivery erection calibration of
equipment, operation, including sampling, storage, curing and testing of materials, periodic re-
calibration of equipment, supply of consumables, recording and submitting test results to the
Engineer, and removal on completion of the Works.
121.6 Measurements for Payment.
This Sub-Clause is deleted entirely and the following substituted:
The supply of laboratories together with equipment and furniture, their operation, removal
after completion of works and their maintenance and charges for utilities shall be measured for
payment on the principle of hire charges as follows:
By time related monthly items for (1) supply and maintenance of Field Laboratory and
equipment including final removal of Field Laboratory and equipment.
121.7 Rates
Payment will be made on the basis of B.O.Q. provision under preliminary subhead.
Clause 122 Site Residential Accommodation for Engineer and Other
Supervisory Staff
DELETED
Clause 123 Providing and maintaining Telecommunication System
123.1 Scope
The works shall cover the provision of three sets of mobile phones for the exclusive use of the
7/26/2019 Technical Specification_SIDCL.pdf
26/194
42
Engineer or his Representatives as also maintenance and payment of call charges per month.
123.2
Provision and Ownership
The Contractor shall arrange to provide three sets of mobile phones for a period of 25 months
with one battery, one spare battery and one battery charger per phone for the exclusive use of
Engineer or his Representative and connection to a telephone network (BSNL or Similar). The
mobile phones will remain the property of the Employer and shall be retained by the Engineer
upon the completion of the contract.
123.3 Approval
The Nokia make or equivalent model of the phone and selection of the network and tariff to beused shall require the prior approval of the Engineer. International and long distance dialing
facilities will not be provided.
123.4 Maintenance
The Contractor shall maintain the phones and carry out repair including provision of
replacement of batteries, chargers or the telephone instrument itself if it cannot be repaired to
provide uninterrupted service.
123.5 Measurement for Payment
Payment for the provision of mobile phones shall be by a unit rate per unit provided. Each unit
shall be procured by initial outright purchase rather than obtained on a lease or similar basis.
Phones procured by purchase at prices subsidized by subsequent line rental and call charge
tariffs will not be acceptable. Each unit shall include the cost of provision of the phone, any
initial lump sum connection fees or related initial charges and deposits. International dialing
facilities shall not be required or provided. The phones provided shall have the facility to be
restricted to local calls only.
7/26/2019 Technical Specification_SIDCL.pdf
27/194
43
123.6 Rates
The Contract unit rate shall include for the supply of mobile phones and shall be deemed to
include all initial charges associated with the outright purchase of the phone, SIM card,
battery, spare battery, battery charger, suitable protective case, security deposit and anyother items so that the phone is provided to the Engineer in an operating condition.
The telephone monthly rental and call charges, voice mail etc. will also be included in the rate
quoted by the Contractor. Payment in this regard will be made as per rate quoted in the BOQ.
124 Providing and Maintaining Project Vehicle
This Clause is unaltered from MOSRT&H Specification with following modification.
Make of Car- Ambassador or similar (Hard top Jeep, Maruti Gypsy or Mahindra and Mahindra
Jeep is not acceptable).
Type of Car - Euro 3 Diesel Car (Petrol Car will not be accepted).
124.5 Measurement for Payment
This sub- clause is deleted and substituted by the following:
The payment for providing and maintaining vehicles shall be on vehicle month basis. The
rate of vehicle- month given in the BOQ shall be proportionately reduced for number of days
in a month the contractor fails to place the vehicle to the Engineer or the Engineers
representatives and/ or for the period of withdrawal as per sub-clause 124.4 irrespective of the
fact whethervehicle was available or not.
125 Supply of Colour Record Photographs and Albums
Deleted
126 Supply of Video Cassettes
Deleted
127 Provision of Copies of Indian Standards etc.
Deleted
7/26/2019 Technical Specification_SIDCL.pdf
28/194
44
128 Tolerance
All Works executed under the Contract shall be carried out in accordance with the tolerances
given in the Specification and approved Drawings, and such other tolerances as are givenelsewhere.
129 Temporary Buildings and Site Services
129.1 Maintenance of the Contractor's temporary site buildings
The Contractor shall not erect any structure permanent or temporary for any sort of use
without the prior permission of the Engineer.
The Contractor shall provide and maintain all necessary temporary buildings, ablutions, water
closets, sheds, stores and storage areas, move as required during the construction of the
Works, and remove the same from the Site on completion of the Works. No structure shall be
erected or storage area laid out by the Contractor within the Site without the Engineer's
consent, but such consent will not relieve the Contractor from his responsibility of siting
temporary structures clear of the Works, utility access points and the like. A copy of the plan
showing the extent and position of all offices, ablutions, water closets, sheds, stores and
storage areas shall be given to the Engineer. Temporary buildings, ablutions, water closets,
sheds, stores and storage areas shall be cleaned and maintained on a daily basis, to the
satisfaction of the Engineer.
129.2 Provision of Latrines
The Contractor shall provide efficient and sanitary latrine accommodation (at location
permitted by the Engineer) for the use of the employees on the Works and shall keep the
whole of the Site and the latrines in a clean and sanitary condition to the satisfaction of the
Engineer.
129.3 Site Services
The Contractor shall be responsible for providing at his own cost all Site services including for
the Engineer's use as necessary and appropriate for the construction of the Works, which shall
7/26/2019 Technical Specification_SIDCL.pdf
29/194
45
include, but not necessarily be limited to:
(a) electricity
(b) water
(c) site communication facilities, and
(d) temporary drainage and sewage disposal.
Such services shall be provided by the Contractor for use solely in connection with the proper
execution of the Works. The Contractor shall be responsible for complying with all regulations
of the Relevant Authorities concerned. The Contractor shall be responsible for the provision
and maintenance of all installations associated with such services and the relation thereto and
shall take all reasonable precautions to safeguard the safety and health of all persons and the
security of the Site. The Engineer may demand the immediate disconnection or alteration of
such installations or portions thereof as he considers to be prejudicial to safety, health or
security. As soon as any or all of the Contractor's installations are no longer required for the
execution of the Works they shall be entirely removed to the satisfaction of the Engineer.
All installations shall comply fully with all appropriate statutory requirements. Pipes, tubes,
ducts or cables crossing roads, footpaths, or right-of-way shall be ramped over, or recessed
below the surface. Specific services shall comply with the following:
129.4 Electricity
The Contractor shall provide all necessary artificial lighting for use on the Works at night,
closed underground work and wherever required.
The Contractor shall provide all temporary cables, mains, sub-mains, wirings, fittings, etc. for
the above, clear away and make good on completion and pay all fees and charges.
129.5 Water
An adequate supply of fresh water shall be provided at the Site, including provision to the
satisfaction of the Relevant Authority of any storage tanks so that sufficient fresh water is
always available for the execution of the works including during any periods of water
restriction. A supply of safe drinking water shall be provided by the Contractor for his own
work people and the Engineer.
7/26/2019 Technical Specification_SIDCL.pdf
30/194
46
129.6 Temporary Drainage and Sewage Disposal
Adequate provision shall be made for the discharge or disposal from the Site of all water,
surplus fluid, sewage and waste products and the method of disposal shall be to the approvalof the Engineer and in accordance with the regulations of the Relevant Authorities. The Site
shall be kept well drained and free from standing water. Where existing channels and gullies
cannot be maintained, temporary drainage arrangements shall be provided at the Contractor's
cost.
129.7 Measurement and Payment
Contractors quoted rates are deemed to cover all the provisions under clause 129 which are
incidental to the work and no separate payment will be made for these provisions.
130 Hoardings and Fencing
This clause shall remain unchanged as in MOSRT&H specification.
131 Project Information Signboards
This clause shall remain unchanged as in MOSRT&H specification.
132 Reports and Documentation
7/26/2019 Technical Specification_SIDCL.pdf
31/194
47
132.1 Initial Plans etc.
The Contractor shall, within fifteen (15) days from receipt of the Letter of Acceptance, submit
to the Engineer the following documents, data and/or schedules but not be limited to, for the
Engineer's approval:
(a) Execution plan covering organization chart, resume of all key personnel, mobilization of
supervising force and other indirect staff, labor, construction equipment/vehicles,
material procurement/purchasing plan, temporary work plan, overall construction
programme, quality assurance plan, safety plan, subcontract plan, work sequence plan,
etc.
(b) Inspection and testing plan
(c) Working drawings, and detail information on equipment
Field laboratories
(d) Cash flow schedule
(e) Other document and information designated by the Engineer at issuing the Letter of
Acceptance
132.2 Regular Reports to the Engineer
In addition to the reports and documentation specified in the Contract other than this Clause,
the Contractor shall submit to the Engineer the following regularly:
(a) Advance monthly construction programmes
(b)
Advance weekly construction programmes
(c) Advance method statement
(d) Submission of the line diagram along with the monthly bill showing the exact progress of
the executed work for which the bill has been drawn.
(e) Inspection applications and reports
(f) Accident reports
132.3 Regular Reviews
Progress review meeting shall be held every week. In addition once each month during the
progress of the Works or at such other intervals as may be required by the Engineer, the
program is to be reviewed and updated by the Contractor taking into account the latest
available information on activities completed, in progress and not yet started, which
7/26/2019 Technical Specification_SIDCL.pdf
32/194
48
information shall be agreed with the Engineer.
Three (3) copies of the program arising from the review shall be submitted to the Engineer
indicating the state of progress of the Works and the revisions necessary to achieve
completion thereof and of individual Sections thereof by the dates specified and to achievecompletion of the whole of the Works by the required date.
The monthly review shall also include, but not necessarily be limited to the provision by the
Contractor of the following:
(a) Description of the previous month's activities and progress
(b) Discussion on critical activities and program with particular reference to action taken or
which will be taken to rectify any program slippage
(c) Any significant movement in labor numbers 01- equipment mobilization / demobilization
(d) Photographic record of the construction site, in sufficient detail to show the progress of
the major aspects of the Works
(e) Project financial report including reconciliation of variations, claims and estimates of
future claims
(f) Project safety report
The Contractor shall submit to the Engineer a daily return of Labour and Contractor's
Equipment, i.e., the statement of the Contractor's Equipment, labour (by discipline) and staff
on Site, major material items received, problems to be solved and as desired by the Engineer.
132.4 Measurement for Payment
The cost for these items of work shall be deemed to be included in the Contractor's unit rates.
No separate payment shall be made for these provisions.
7/26/2019 Technical Specification_SIDCL.pdf
33/194
49
SECTION 200 SITE CLEARANCE
201 Clearing and Grubbing
201.1 Scope
Add the following paragraph to the MOSRT&H Specification.
If any vegetation grows after clearing and grubbing before road construction work, the
contractor shall repeat the work to the satisfaction of the Engineer without any extra cost. The
scope of clearing and grubbing shall include all clearance of street furniture, utility apparatus
etc. necessitated by the Works not specifically measured elsewhere.
201.2 Preservation of Property / Amenities
Add the following paragraph to the MOSRT&H Specification.
The Engineer will establish the limits of work and designate all trees, shrubs, plants and other
things to remain. The Contractor shall preserve all items designated to remain.
201.3 Methods, Tools and Equipments
This clause shall remain unchanged as in MOSRT&H specification.
201.4 Disposal of Materials
Clause 201.4 of the MOSRT&H Specification shall be deleted entirely and the following
substituted:-
All surplus materials arising from the Works (except those arising from private properties) shall
be the property of the Contractor who shall be responsible for their disposal.
201.5 Measurement for Payment
Payment will be made on area basis in hectare regarding site clearance. Cutting of trees upto
300mm in including removal of stumps and roots, and trimming of branches of trees extending
above the roadways shall be considered incidental to the cleaning and grubbing operations,
Removal of stumps left over after trees have been cut by any other agency shall also be
considered incidental to the cleaning and grubbing operations.
7/26/2019 Technical Specification_SIDCL.pdf
34/194
50
Cutting in including removal of stumps and roots of trees of girth above 300mm and backfilling
to required compaction shall be measured in terms of number according to the sizes given
below:-
Above 300mm to 600mm
Above 600mm to 900mmAbove 900mm to 1800mm
Above 1800mm
For the purpose, the girth shall be measured at a height of 1 meter above the ground or at the
stump if the height of the stump is less than one meter from the ground.
201.6 Rates
The unit price for the work hereof will be deemed to include any precautions or special
working methods necessary to avoid damage to adjacent items designated to remain. Any
such damage shall be rectified by the contractor at his own cost.
The Contract unit rate for the work shall be, payment in full for all labour, material, tools,
equipment and incidental charges necessary to complete the work.
201.7 Clearance of Sludges from the Manholes / Gully pits
All the sludges from the Manhole / Gully pits within the limit of works shall have to be cleared
as per direction of the engineer.
201.8 Measurement for Payment
No separate payment will be made.
202 Dismantling Culverts, Bridges and Other Structures / Pavements
Sub-Clauses 202.1 and 202.2 of the MOSRT&H Specifications are unaltered.
202.3 Dismantling Pavements and Other Structures
Add the following sub-paragraph in between the two sub-paragraphs of Sub-Clause 202.3 of
7/26/2019 Technical Specification_SIDCL.pdf
35/194
51
the MOSRT&H Specification.
For careful scarifying of bituminous layers to specified level and grade, refer to Sub-Clause
501.8.3.2.
Add the following at the end of Sub-Clause 202.3 of the MOSRT&H Specification.
The dismantling operations shall have to be conducted carefully, so as not to damage thematerials which are scheduled to be or may be reused with or without further treatment.
202.5 Disposal of Materials
Sub-Clause 202.5 of the MOSRT&H Specification is deleted and the following substituted:
Unless specifically stated otherwise within the Contract Documents, all surplus materials arising
from the Works (except those arising from private properties) shall be the property of the
Contractor. The disposal of all surplus materials arising from the Works shall be the
responsibility of the Contractor. The Contractor shall be deemed to have allowed in his rates
for all cost associated with such disposal and any salvage value of any materials. Materials
indicated within the Contract Documents as required for reuse shall be the property of the
Employer.
202.6 Measurements for Payment
Delete the Sub-Clause 202.6 of MOSRT&H Specification entirely and substitute the following:
Dismantling required for the Permanent Works will be measured for payment, while
dismantling for haul roads, borrow areas and all the Temporary Works will not be measured
for payment. The work of dismantling structures shall be paid for in units indicated below, by
taking measurements before and after as applicable:
7/26/2019 Technical Specification_SIDCL.pdf
36/194
52
Work Item Unit of
Measurement
Brick/Stone masonry/concrete (plain and
reinforced)
cu.m
Gullies No.
Flexible and cement concrete pavements cu.m
Road Pavement cu.m
Footpath cu.m
Steel structures tonne
Timber structures cu.m
Pipes, guard rails, kerbs, gutters and
fencing
lin m
Pedestrian Barrier lin m
Kerbs lin m
Channel Blocks lin m
Garden / Median Fencing lin.m
202.7
Rates
The words within all lifts and upto a lead of 1000m shall be deleted from Sub-Clause 202.7
of the MOSRT&H Specification.
The following Clauses are added to the MOSRT&H Specification Section 200
203 Other Site Clearance Matters
203.1 Treatment of areas for Roadway Embankment
In areas under roadway embankments, from which top soil or unsuitable materials are to be
removed or which are designated to be compacted, all stumps and roots shall be removed to a
depth of at atleast 50 cm below the original ground surface and at least 50 cm below the
bottom of the lowest pavement layer.
203.2 Protection of Areas Designated to Remain
7/26/2019 Technical Specification_SIDCL.pdf
37/194
53
In areas designated by the Engineer, the Contractor shall be responsible for the protection and
routine maintenance of existing shrubs, trees and grassed areas. On completion of the Works
these areas shall be returned to the Employer in the same condition as before and any
damage due directly or indirectly to the Contractor's operations shall be made good at his owncost The Contractor may take photos for his recording of the original condition at the time of
work commencement.
203.3 Maintenance of Flows in Culverts to be demolished.
Where the Works include the diversion of existing culverts and subsequent demolition of the
existing sewers and similar services, demolition of such existing services shall not commence
until authorised by the Engineer. Such authorization will be dependant upon availability of the
alternative diversion where appropriate.
203.4 Maintenance of Traffic Flow - Alternative Traffic Routes
No road, bridge, tram track or other structure in use by traffic shall be removed until
authorised by the Engineer. Such authorization will be dependant upon satisfactory alternative
arrangements have been made to accommodate traffic where appropriate.
203.5 Materials for Reuse
Existing kerbs, channels, street furniture and other materials designated for dismantling and
reuse by the contractor in his offer, shall be carefully removed and stockpiled for re-use in the
Works, or shall be disposed of, as directed by the Engineer.
Dismantling of existing items shall be undertaken in such a manner as to avoid damage to
existing pavements and kerbs which are designated to remain.
7/26/2019 Technical Specification_SIDCL.pdf
38/194
54
203.6 Measurement & Payment
Reuse of material except kerbs shall not to be measured and paid and is deemed to be
included in contract price.
7/26/2019 Technical Specification_SIDCL.pdf
39/194
55
SECTION 300 Earthwork, Erosion control and Drainage
Clause 301 Excavation for Roadway and Drains
301.1
Scope
The following shall be added at the end of Clause 301.1:
The scope of this clause does not include excavation of trenches for utilities and excavation for
surface water drainage works, which are governed by Clause 3200 later in this volume.
301.2 Classification of Excavated Material
301.2.2 Authority for classification
The existing clause shall be deleted and following substituted in its place:
The Engineer shall be the sole authority for the classification of the soil in excavation and his
decision shall be final and binding on the Contractor. Soil classification will not be decided on
the basis of the means adopted i.e. use of explosives or hydraulic or pneumatic breakers in
excavation, but by the Engineer who may authorize such use.
301.3 Construction Operations
301.3.1Setting out
Delete the 2nd sentence of this MOSRT&H Sub-Clause beginning and ending with The
Contractor shall. establishment of bench marksand substitute with the following:-
The contractor shall set out the works and shall establish bench marks from the initial control
points supplied by the Engineer.
Sub-Clause 301.3.2 is unaltered from the MOSRT&H Specification.
7/26/2019 Technical Specification_SIDCL.pdf
40/194
56
301.3.3 Excavation-General
The following shall be added at the end of the third paragraph of this clause:
Temporary shoring shall be provided by the Contractor to the sides of the excavation wherevernecessary to support the foundations of adjoining structures and road pavement and to
prevent any ground movement. Where temporary supports are required they shall be
designed, provided and removed such that no ground movement occurs on removal.
The Contractor shall submit his proposals for support of excavations to the Engineer for
approval prior to commencement of excavation.
301.3.5 Rock Excavation - Rock
DELETED
301.3.6Marshy Excavation
This clause shall remain unchanged as in MOSRT&H specification.
301.3.11 Disposal of Excavated Materials
The first paragraph shall be deleted and the following substituted:
All materials arising from excavations required for reuse in the Works shall be the property of
the Employer. No material shall be removed from Site without the permission of the Engineer.
However, all surplus excavated materials shall be the property of the Contractor The material
obtained from the excavation of roadway, shoulders, verges, drains, cross-drainage works etc,
shall be used for filling up of (i) roadway embankment, (ii) the existing pits in the right-of-way
and (iii) for landscaping of the road as directed by the Engineer, including leveling and
spreading with all lifts and leads and no extra payment shall be made for the same.
Where suitable for reuse, existing granular base and sub-base materials removed as part of
the works shall be removed carefully and stockpiled and tested for re-use as granular sub-base
or otherwise as directed by the Engineer.
7/26/2019 Technical Specification_SIDCL.pdf
41/194
57
Delete the words upto 1000mfrom 3rdline of 2ndparagraph of this Sub-Clause.
Delete the 3rdparagraph of this Sub-Clause and substitute the following:
Unsuitable and surplus material not intended for use in Works shall be transported with all lifts
and leads to dispose of as directed by the Engineer.
301.3.12
Backfilling
This clause shall remain unchanged as in MOSRT&H specification.
301.6 Preparation of Cut Formation
This clause shall be deleted and the following clauses 301.6.1 to 301.6.3 substituted in its
place:
301.6.1 Preparation of Cut Formation in Soil Excavation
Unsuitable materials found in the sub-grade shall be removed as directed by the Engineer and
suitable fill material replaced, and compacted in accordance with the requirements of Clause
305, to not less than 95 % of the MDD determined by IS: 2720 (Part 8). Material with a high
moisture content shall be considered as unsuitable only on the basis of one or more of the
conditions stipulated in Clause 305.2.1.1 for unsuitable material.
Unsuitable materials shall be disposed of in accordance with Clause 301.3.11.
The bearing capacity of the sub-grade material (i.e. the in-situ material below the underside of
the granular base course) shall be tested in the laboratory in accordance with IS: 2720 (Part
16) at 97 % of the MDD determined in accordance with IS2720 (Part 8) and soaked for four
days. Where the CBR value is less than 10%, the sub-grade shall be strengthened by
constructing a capping layer and sub-base layer as indicated on the Drawings. Where the CBR
value is greater than 10 % but less than 30% the sub-grade shall be strengthened by
constructing sub-base layer as indicated on the Drawings.
Where indicated on the Drawings or directed by the Engineer, the sub-grade in soil
excavations shall be protected by the capping layer immediately after completion of the
preparatory works.
7/26/2019 Technical Specification_SIDCL.pdf
42/194
58
The cut formation in soil excavation, which serves as a sub-grade, shall be prepared to receive
the capping layer or sub-base immediately after completion of the excavation.
Where a capping layer is to be constructed and the material in the sub-grade that lies within300 mm of the underside of the capping layer has a density less than 95% of the MDD
determined in accordance with IS: 2720 (Part 8), the same shall be loosened and conditioned
to bring the moisture content to within +2 %/ -3 % of the Optimum Moisture Content and
compacted in layers in accordance with the requirements of Clause 305, to not less than 95%
of the MDD determined by IS: 2720 (Part 8).
Where no capping layer is required and the material in the sub-grade that lies within 500 mm
of the underside of the sub-base has a density less than that specified in Table 300-2, the
same shall be loosened and conditioned to bring the moisture content to within +2/-3 of the
Optimum Moisture Content and compacted in layers in accordance with the requirements of
Clause 305, to not less than 97% of the MDD determined by IS: 2720 (Part 8).
If due to any reason (such as for example weather) the moisture content of the sub-grade
material cannot be reduced as specified by aeration and exposure to the sun, compaction of
the sub-grade shall be suspended and the Contractor shall submit alternative measures to the
Engineer for approval.
After satisfying the density requirements, the cut formation shall be prepared to receive the
capping layer or sub-base in accordance with Clause 310 and 311.
The finished cut formation shall comply with the surface tolerances described in Clause 902.
7/26/2019 Technical Specification_SIDCL.pdf
43/194
59
301.6.2 Preparation of Cut formation in Rock
DELETED
301.6.3 The Capping Layer
Material for the capping layer shall be suitable fill material complying with Clause 305.2 of the
specification with a minimum CBR value of 15 % when tested in accordance with IS: 2720
(Part 16) at 97 % of the MDD determined in accordance with IS: 2720 (Part 8) after soaking
for four days.
The capping layer shall be constructed to the lines and levels shown on the Drawings in
accordance with Clause 305 of the Specification to not less than 97 % of the MDD determined
in accordance with IS: 2720 (Part 8).
The finished formation of the capping layer shall comply with the surface tolerances for sub-
grade described in Clause 902.
301.7 Finishing Operations
Paragraph 3 of this clause shall be deleted.
301.8 Measurements for Payment
This clause shall remain as in MOSRT&H specification, unchanged.
301.9 Rates
This clause shall remain as in MOSRT&H specification, unchanged.
The following shall be added after Clause 301.9.1 (vi):
(vii) Working around existing utility appliances
Delete the last sentence of the Sub-Clause 301.9.1, starting and ending with Provided,
however, where.. vide Sub-Clause 303.5.
301.9.2 Loosening and re-compacting
7/26/2019 Technical Specification_SIDCL.pdf
44/194
60
Clause 301.9.2 shall be deleted and the following substituted in its place:
The Contract unit rate for loosening and re-compacting the loosened materials at sub-grade
shall include full compensation for loosening to the specified depth, including breaking clods,spreading in layers, watering or drying the material as appropriate including removing the
material to stockpile and backfilling where necessary, and compacting to the requirements.
301.9.3
Sub-Clause 301.9.3 is unaltered from the MOSRT&H Specification.
301.9.5
Replace the words but leads upto 1000m in 3rd and 4th lines by all leads.
301.9.6 Unit Rates for Disposal of surplus earth
Clause 301.9.6 shall be deleted and the following substituted in its place:
All surplus materials arising from the Works shall be the property of the Contractor. All material
required for reuse in the Works shall be the property of the Employer. The disposal of surplus
excavated material shall be the responsibility of the Contractor. The Contractor shall be
deemed to have allowed all cost associated with such disposal and any salvage value in the
Contract Rates.
This item of work shall not to be measured and paid separately and is deemed to be included
in the contract price.
Clause 302 Blasting Operations
DELETED
Clause 303 Pre-splitting Rock Excavation Slopes
DELETED
7/26/2019 Technical Specification_SIDCL.pdf
45/194
61
Clause 304 Excavation for Structures
304.3 Construction Operations
304.3.2 Excavation
Add "or road pavement" after "an adjoining structure" in the fifth line of the second paragraph.
304.3.4 Preparation of Foundations
The second sentence of the first paragraphs shall be deleted and the following substituted:
Before the footing is constructed all disturbed material shall be fully compacted in accordance
with Table 300.2 and the surface shall be lightly watered, if required, and rammed to compact
the in situ material.
304.3.7 Backfilling
The first paragraph shall be deleted and the following substituted in its place:
Backfilling shall be done with selected granular material after the concrete or masonry is fully
set and carried out in such a way as not to cause undue thrust on any part of the structure. All
space between foundation masonry or concrete and the sides of the excavation shall be filled
to the original surface in layers not exceeding 150 mm compacted thickness. The compaction
shall be done with the help of suitable equipment such as mechanical tamper, rammer,
vibrating plate compactor etc., after necessary watering or drying so as to achieve a density
not less than the field density before excavation or 90 % of the MDD determined by IS: 2720
(Part 8).
7/26/2019 Technical Specification_SIDCL.pdf
46/194
62
304.4 Measurements for Payments
This clause shall remain as in MOSRT&H specification, unchanged.
304.5
Rates
This clause shall remain as in MOSRT&H specification, unchanged.
Clause 305 Embankment Construction
305.3 Construction Operations
305.3.4 Compacting Ground Supporting Embankment / Sub-grade
The first paragraph shall be deleted and the following substituted:
Where necessary, the original ground shall be leveled to facilitate placement of the first layer
of the embankment, scarified, mixed with water or dried as appropriate, and then compacted
by rolling so as to achieve the minimum dry density as given in Table 300-2.
The following shall be added at the end of the second paragraph:
In cases where a capping layer is to be constructed and the difference between the sub-grade
level and ground level is less than 300 mm and the relative compaction of the ground is less
than 95 %of the MDD determined in accordance with IS: 2720 (Part 8) the ground shall be
loosened up to a depth of 300 mm below the underside of the capping layer, scarified, mixed
with water or dried as appropriate, and then compacted to achieve not less than 95% of the
MDD determined in accordance with IS: 2720 (Part 8).
305.7 Sub-grade Strength
A new sub-clause 305.7.3 shall be added:
7/26/2019 Technical Specification_SIDCL.pdf
47/194
63
305.7.3
Any imported fill material used as part of the preparation of the sub-grade formation shall
have a minimum CBR value of 15 % after soaking for four days.
305.8
Measurements for Payment
The first paragraph shall be deleted and the following substituted in its place:
Earth embankment / sub-grade construction shall be measured separately net from the
drawings by taking cross-sections at suitable intervals of the original surface before the work
starts and computing the volume in cubic metres from cross-sections based upon the original
ground profile and the theoretical finished profile by the method of average end areas.
305.9 Rates
This clause shall remain as in MOSRT&H specification, unchanged
The following shall be added after item (xiii):
(xiv) Working around existing utility appliances.
Clause 306 Soil Erosion and Sedimentation Control
DELETED
Clause 307 Turfing with Sods
This clause shall remain as in MOSRT&H specification, unchanged
.
Clause 308 Seeding and Mulching
This clause shall remain as in MOSRT&H specification, unchanged.
7/26/2019 Technical Specification_SIDCL.pdf
48/194
64
Clause 309 Surface / Sub-Surface Drains
This clause shall remain as in MOSRT&H specification, unchanged
Clause 310 Preparation and Surface Treatment of Formation
The first sentence of the first paragraph shall be deleted and the following substituted:
Preparation of surface treatment of the formation, that is top of the sub-grade or capping
layer, shall be carried out only after completion of any specified sub-grade drainage and unless
otherwise agreed by the Engineer immediately prior to laying the sub-base or the road base
where no sub-base is required.
No separate measurement for the provisions of the same shall be done as it is already
considered in the relevant items.
Clause 311 Works to be kept free of water
This clause shall remain as in MOSRT&H specification, unchanged
No separate measurement for the provisions of the same shall be done as it is already
considered in the relevant items.
Clause 312 Water Courses at Culverts
This clause shall remain as in MOSRT&H specification, unchanged.
Clause 313 Construction of Rockfill Embankment
DELETED
The following new Clauses 314 and 315 shall be added to the MOSRT&H Specification:-
Clause 314 Granular Backfill
314.1 Scope
7/26/2019 Technical Specification_SIDCL.pdf
49/194
65
This item shall consist of furnishing, placing and compaction granular backfill adjacent to
structures. The areas in which this material is to be placed in the "Influence Zone" of certain
structures and this will be shown on the Drawings.
314.2 Material
The material shall be well graded crushed or uncrushed gravel, stone, rock fill or natural sand
or a well mixed combination of any of these. The grading requirements for the material are as
follows-
Maximum particle size 10 cm
Passing 4.75mm sieve 25 to 90
Passing 0.075mm sieve 0 to 10Plasticity index 10 % maximum
314.3 Construction
The granular backfill shall be placed in layers not exceeding 15 cm and compacted in
accordance with Table 300-2.
314.4 Method of Measurement
The quantity of granular backfill to be measured and paid for, will be the number of cubic
metres of suitable material supplied and compacted to the Engineer's satisfaction and in
accordance with this Specification.
The material is required to be placed when filling within the influence zone of certain
structures and any material placed outside the specified zone will not be measured for
payment.
Any existing material within the influence zone, which is removed because of the Contractor's
method of working, must be replaced by granular backfill at Contractor's expense. Where
excavation within the influence zone is instructed under any Clause of these Specifications,
then the backfilling will be carried out with granular backfill and the work will be measured for
7/26/2019 Technical Specification_SIDCL.pdf
50/194
66
payment under this clause.
314.5 Rates
The accepted quantities of granular backfill, measured as provided above, will be paid for atthe Contract unit price for the pay item as below. The price and payment will be full
compensation for the work described in this Clause, including furnishing, hauling, placing and
compacting the material.
Work Item Unit of Measurement
Granular backfill:
a) Silver sand
b)
Coarse sand
Cubic metre
Cubic metre
Clause 315 Permeable Backfill
DELETED
315.1 Scope
This work shall consist of supplying and installing selected backfill material adjacent to
structures in accordance with these Specifications and in locations as shown on the Drawings
or instructed by the Engineer.
7/26/2019 Technical Specification_SIDCL.pdf
51/194
67
315.2 Material
The material shall be hard, clean, crushed rock or gravel complying with the following
grading:-
Sieve Size % passing by weight
63mm 100
37.5mm 85-100
19mm 0-20
9.5mm 0-5
315.3 Construction
The method of construction will be at the discretion of the Contractor, but details must be
submitted for the Engineers approval before commencement of the work. All details of the
permeable backfill shall be as shown on the Drawings and the degree of compaction shall be
as instructed by the Engineer.
315.4 Method of Measurement
Unless this material is specified as included in another pay item, the quantity of permeable
backfill to be measured and paid for will be the number of cubic metres of suitable material
supplied, placed and compacted in accordance with the details shown on the Drawings. Any
material placed beyond the dimensions shown on the Drawings will not be measured for
payment.
315.5 Rates
The work measured as provided above will be paid for at the Contract price per unit of
measurement for the item listed below, which price and payment will be full compensation for
furnishing and placing all materials, and for all labour, equipment and other incidentals
necessary to complete the work in accordance with the Drawings, specifications and as
directed by the Engineer.
7/26/2019 Technical Specification_SIDCL.pdf
52/194
68
Work Item Unit of Measurement
Permeable backfill Cubic metre
316
Reinforced Earth Backfill
DELETED
7/26/2019 Technical Specification_SIDCL.pdf
53/194
69
SECTION 400 Sub-bases, bases (non-bituminous) and shoulders
Clause 401 Granular Sub-base
The following amendments are made to Clause 401 of the MOSRT&H Specification:-
401.1 Scope
This clause shall remain as in MOSRT&H specification, unchanged.
401.2 Materials
401.2.1
The third sentence of the first paragraph shall be deleted and the following substituted.
The material shall be free from organic matter, clay balls or other deleterious materials and
shall conform to one of the gradings given in Table 400-1. The minimum CBR value of the
granular sub-base material when tested in accordance with IS: 2720 (Part 16) when
compacted to 98 % of MDD determined in accordance with IS: 2720 (Part 8) and soaked for
four days shall be 30 %.
401.2.2 Physical Requirement
The minimum CBR values from Table 400-1 and Table 400-2 shall be deleted and substituted
with 30 % for each grading.
401.4 Construction Operation
401.4.1 Preparation of Subgrade
This clause shall remain as in MOSRT&H specification, unchanged.
7/26/2019 Technical Specification_SIDCL.pdf
54/194
70
401.4.2 Spreading and Compacting
The second and third paragraphs shall be deleted and substituted by the following:
When the sub-base consists of a combination of materials mentioned in Clause 401.2.1, mixingshall be done off site in an approved mixing plant of suitable capacity having provision for
controlled addition of water.
The following paragraph shall be added after the last paragraph:
At all areas not accessible to the roller, the material shall be compacted thoroughly by
approved mechanical tampers or compactors.
401.5 Surface Finish and Quality Control of Work
This clause shall remain as in MOSRT&H specification, unchanged.
401.7 Measurement for Payment
This clause shall remain as in MOSRT&H specification, unchanged.
401.8 Rate
The work measured as provided above will be paid for at the contract price per unit of
measurement for the item listed below:
Work Item Unit of Measurement
Granular sub-base:
a) Stone dust and medium sand
b) Brick Bats and medium sand
Cubic metre
Cubic metre
402 Lime treated soil for improved sub-grade / sub-base
DELETED
7/26/2019 Technical Specification_SIDCL.pdf
55/194
71
403 Cement treated soil for sub-base / base
DELETED
404
Water Bound Macadam Sub-base/base
This clause shall remain as in MOSRT&H specification, unchanged
405 Crushed Cement Concrete Sub-base/base
DELETED
406 Wet Mix Macadam Sub-base / Base
406.1 This clause shall remain as in MOSRT&H specification, unchanged
The following amendments are made to Clause 406 of the MOSRT&H Specification:-
406.2 Materials
406.2.1 Aggregates
406.2.1.1 Physical Requirements
The following shall be added to Table 400-10: "Physical Requirement of Coarse Aggregates
for Wet MixMacadam for Sub-base / Base.
In addition to the tests listed above, the coarse aggregates of Wet Mix Macadam Base shall
comply with the following:
Test Test Method Requirement
3
.
Water absorption value IS: 2386 (Part 3) Less than 2%
4
.
Sodium sulphate
soundness
IS:2386 (Part 5) Less than 12%
The following shall be added after the last paragraph:
7/26/2019 Technical Specification_SIDCL.pdf
56/194
72
The California Bearing Ratio of the Wet Mix Macadam Base when tested in accordance with IS:
2720 (Part 16) at 98 % of the MDD determined in accordance with IS: 2720 (Part 8) and
soaked for four days shall not be less than 80 %.
406.2.1.2 Grading Requirements
The following shall be added after Table 400-11: "Grading Requirements of Aggregates for
Wet Mix Macadam for Sub-base/Base":
In addition to the grading requirements listed above, the coarse aggregates of Wet Mix
Macadam Base shall comply with the following:
The fraction of the aggregate passing the 2.36 mm sieve in Wet Mix Macadam Base shall
consist of rock or gravel screenings and shall be free from loam, organic or other deleterious
matter.
406.3 Construction Operation
Add the following amendment in this Clause:-
406.3.2Provision of lateral confinement of aggregates
Add the words or by kerbs/kerbs and channels and their foundations between the words
shoulders and along in the 4th line of this Sub-Clause.
406.4 Opening to Traffic
This clause shall remain as in MOSRT&H specification, unchanged.
7/26/2019 Technical Specification_SIDCL.pdf
57/194
73
406.5 Surface Finish and Quality Control of Work
This clause shall remain as in MOSRT&H specification, unchanged
.
406.6 Rectification of Surface Irregularity
This clause shall remain as in MOSRT&H specification, unchanged.
406.8 Measurement for Payment
This clause shall remain as in MOSRT&H specification, unchanged.
406.9 Rate
This clause shall remain as in MOSRT&H specification, unchanged.
Clause 407 Shoulder, Islands and Median
This shall remain unchanged as in MOSRT&H Specification
Clause 408 Cement Concrete Kerb and Kerb with Channel
This clause shall be deleted in its entirety and substituted with the following:
Clause 408 Cement Concrete Kerb / Natural Stone Kerb and Kerb with Channel
408.1 Scope
The work shall consist of constructing cement concrete kerbs, natural stone kerbs, concrete
edgings and kerbs with concrete channel blocks along the footpaths and / or in the central
median or separators in conformity with the lines and levels and dimensions as specified in the
drawings. Where specified or indicated on the Drawings, the exposed up-stand face and top
surface of the kerbs shall be painted alternately in black and white, or yellow.
408.2 Cement Concrete Kerbs, Edgings and Channel Blocks
7/26/2019 Technical Specification_SIDCL.pdf
58/194
74
408.2.1 Materials
Unless otherwise described in the Contract, concrete kerbs, edgings, quadrants and channel
blocks shall be hydraulically pressed pre-cast blocks. During manufacture the kerbs/channel
blocks shall be subjected to a pressure of not less than 7 MPa. The method of manufactureshall prevent the loss of the finer particles of cement during the pressing process.
The method of manufacture and testing shall comply with the requirements of IS: 5758, as
amended here below, and to the cross Clauses shown on the Drawings. All materials shall
conform to the requirements of IS: 5758 and as specified herein.
For all kerbs, and associated works specified in this clause, the cement shall be ordinary
Portland cement conforming with Clause 1006 of the Specifications. Kerbs shall be
manufactured using a concrete mixture containing not less than 350 kg of cement per cu.
metre of mix. The concrete when tested in accordance with IS: 516 shall attain a 28 days
compressive strength of not less than 30 MPa, determined on cubes specimens.
The top edge and front face of individual pre-cast kerb, channel or edging units shall not
deviate by more than 1 mm from the nominal profile when checked with a straight edge.
The Contractor shall submit samples of the various types of concrete kerbs for testing and
approval by the Engineer before commencing the work.
Sand / cement mortar for bedding shall comply with Clause 1304 of the Specification, except
as described below. Class 1 mortar shall be mixed in the proportions 1volume cement to 3
volumes fine aggregate. Water added shall be the least amount which will yield a mix of
suitable consistency for masonry work.
408.2.2Construction Operations
After preparation and compaction of the granular sub-base pavement layer, the surface shall
be regulated under the line of the kerbs with additional sub-base material trimmed and
compacted to the lines and levels shown in the Drawings to provide the platform for
constructing the kerb or kerb and channel block foundation.
Pre-cast concrete kerbs, edgings and channels shall be laid and bedded in a layer of Class 1
7/26/2019 Technical Specification_SIDCL.pdf
59/194
75
mortar not less than 10 mm and not more than 40 mm thick, on a foundation of concrete
grade M 20. Kerbs shall be backed with grade M 20 concrete.
Joints between kerb stones, other than expansion joints shall be of uniform width not greater
than 4 mm and shall be filled with Class 1 mortar.
Expansion joints shall be provided through the kerbs, kerb foundation and kerb backing at 9
metre spacing along the kerb run. The joint filler shall be formed of 12 mm thick bitumen
impregnated fibre-board complying with IS: 1838 (Part 1).
Any unit of kerb, channel, edging and quadrant deviating more than 3 mm in 3 m from line
and level shall be made good by lifting and relaying.
408.2.3 Measurement
Cement concrete kerbs, edgings and channel blocks shall be measured separately in linear
metres for the complete item of work. No separate item will be made for kerb and/or channel
foundations, concrete backing, joints or expansion joints.
408.2.4 Rates
The Contract unit rates for concrete kerbs, edgings, quadrants and channel blocks shall be
payment in full compensation for furnishing all materials, labour, tools, equipment for
construction and other incidental cost necessary to complete the work.
408.3 Natural Stone Kerbs and Edgings
DELETED
7/26/2019 Technical Specification_SIDCL.pdf
60/194
76
408.4 Kerb Painting
408.4.1 Materials
Where specified on the drawings kerbs shall be painted with quick-drying chlorinated