+ All Categories
Home > Documents > Technip #Yemen #LNG March 2011 Web

Technip #Yemen #LNG March 2011 Web

Date post: 06-Apr-2018
Category:
Upload: yemen-exposed
View: 224 times
Download: 0 times
Share this document with a friend

of 6

Transcript
  • 8/3/2019 Technip #Yemen #LNG March 2011 Web

    1/6

    Building Yemens first LNG plant

    Yemen LNG

    Our projects

  • 8/3/2019 Technip #Yemen #LNG March 2011 Web

    2/6

    Establishing Yemen LNG as an international

    Liquefied Natural Gas supplier

    In August 2005, the Yemen LNG project was launched. It is the

    single largest investment project in the industrial history of

    Yemen, for a total value of almost 4.5 billion dollars.

    The project involved:

    A 320-km long pipeline from the Marib gas field, in CentralYemen, to the coast.

    A 2-train liquefied natural gas plant in Balhaf, on the Gulf of Aden, 200 km South-West from

    Al-Mukalla.

    Train 1 has been in operation since October 2009

    with the first LNG carrier loaded early November,

    whereas Train 2 came on stream in March 2010.

    The Balhaf site, on the Southern coast of Yemen,

    was chosen for the LNG facility because it offers

    a natural harbour, protected from the monsoon's

    wind gusts and sea swells.

    It is also a strategic location at the crossroads of

    international maritime routes. The output from

    the plants requires the movement of 100 LNG

    carriers per year, to deliver the LNG to Asian,European and American markets.

    The monetisation of Yemens naturalresources has been the countrys

    focus since the 1990s.

    In September 2005, Yemgas,

    the Technip-led Joint Ventureequally shared between

    Technip, JGC and KBR was

    awarded the engineering,

    procurement and

    construction contract for the

    2-train LNG plant including

    utilities and offsites.Client: Yemen LNG Company Ltd (YLNG) withpartners: Total (Project Leader with 39.62%), Hunt Oil

    (17.22%), Yemen Gas Company (16.73%), SK Corporation(9.55%), Korea Gas Corporation (6%), Hyundai

    Corporation (5.88%) and Yemens General Authority for

    Social Security & Pensions (5%)

    LNG plant Contractor: Yemgas, a Technip-led joint

    venture equally shared between Technip / JGC / KBR

    Lump sum turnkey contract awarded in September

    2005

    Global LNG production capacity of 6.7 Mtpa

    Steady production since November 2009 (train 1) and

    March 2010 (train 2)

    Yemen LNG

    Yemen

    Arabian

    Sea

    Saudi

    Arabia

    A challenge for the Technip-led

    joint venture

  • 8/3/2019 Technip #Yemen #LNG March 2011 Web

    3/6

    Yemgas project scope

    This project confirms Technip among

    the first tier of EPC contractors in LNG

    In 2009 and 2010, through the delivery of projects

    including Yemen, Technip will have delivered 57 million

    tonnes per year of LNG capacity to its clients, including

    the worlds largest LNG trains in Qatar.

    Underpinning this achievement meant

    meeting a fantastic challenge made possible

    by the commitment of the Technip-led

    joint venture over several years.

    It all started in the 1990s when Technip and its partners carried out the FEED studies for the project. In September 2005,

    Yemgas signed the Engineering, Procurement and Construction contract with Yemen LNG Company Ltd for the LNG

    plant:

    Engineering, procurement, construction, commissioning and start-up of 2 liquefaction trains with a total capacity of 6.7

    million tonnes of liquefied natural gas per year.

    Air Products C3/MR process, with the refrigerant compressors in Split MR configuration to maximise production from

    the two GE Frame 7 gas turbine drivers.

    2 full containment storage tanks of 140,000 m3 each.An 800-m long jetty.

    Overall construction supervision of the entire facilities / utilities.

    Large-scale infrastructure requirements.

    Technip will have been involved in

    adding around one third to theworlds LNG production capacity.

    Supported by outstanding Project

    Management skills and a strong

    organisation, Technip is capable of

    managing several of these gigantic

    grassroots projects simultaneously,

    even in remote locations where

    infrastructure is not completely

    adapted and most of the material

    needs for the project have to be

    brought in.

    The Yemen LNG contract is one

    example of Technips leadingposition among the first tier of EPC

    contractors in LNG:

    FEED studies

    LNG train detailed engineering

    Utilities / Facilities construction

    supervision

    Joint Venture leadership

  • 8/3/2019 Technip #Yemen #LNG March 2011 Web

    4/6

    The project recorded

    periods of up to 15 million

    hours without Lost Time

    Injury (LTI).

    A massive HSE training programme

    was central to achieving this result.

    The site HSE Departments mission

    was to work on the process of

    improving peoples behaviour as

    the main way to improve overall

    project HSE statistics. Various

    training modules were provided

    both in English and Arabic to

    maintain constant safety

    awareness:Site HSE induction

    Defensive driving

    Confined space entry

    Working at heights

    Commissioning & start-up

    safety

    The team

    The know-how developed by the Technip Security

    division over recent years on other projects allowed

    a site-specific programme to be successfully

    deployed at Balhaf with several innovative measures.

    The quality of the programme has since been

    recognised by many external parties.

    Outstanding Security

    Security of Personnel consisting of a Meet & Greet procedure, a

    Travellers booklet, accommodation audits and inspections, Security andCultural induction programs on site.

    Physical security measures (original concepts developed by Technip)

    Security Operations Room aiming at centralising all Security-related

    communications.

    Quick Response Team (QRT) consisting of a permanent Security Patrol

    inside the site.

    Main Gate, a pivotal access point in a project site where all personnel,

    equipment, materials and goods transit.

    Security toolbox

    Balhafs Security Master Plan detailing the responsibilities of each

    stakeholder. Established prior to opening the construction site.

    Appointment of permanent Subcontractor Security correspondents

    within the camps/worksites.

    Security Instruction book for operational support.

    Cultural and religious inductions within the Awareness Program.

    In March 2008, at the peak of construction, some 9,200 people from

    72 nationalities were working on the construction of the liquefaction plant.

    The Yemgas management team was just over 200 strong from 35 nationalities.

    140 out of the 208 Technip staff Balhaf April 2009

    HSE performance

    Yemen LNG

  • 8/3/2019 Technip #Yemen #LNG March 2011 Web

    5/6

    The projects main challenges

    To make the Yemen LNG project the success that is,

    Technip had to overcome several challenges over the 4 years

    between contract award and start up:

    Major success factors

    Construction market tightness in 2005. At the time of the project launch, several other LNG projects were underway

    worldwide, reducing the availability of skilled labour, construction materials and equipment and making it more

    difficult to predict costs and schedule.

    Technology-intensive and large-size plant in a remote location. Each train is using the Air Products C3/MR process.

    Large-scale infrastructure which required building:

    a harbour to receive industrial equipment from 60 shipments

    an airport for employee transfer

    a city to accommodate 10,000 people during construction phase and 700 permanent staff during operations

    Security: building such a high-technology industrial project in a location like Balhaf represented a challenge due to the

    remoteness of the site, its shorefront on the Gulf of Aden and the duration of the construction phase (4 years).

    Ensuring the security of personnel (whether Client, staff, contractors, visitors or Government bodies) and of the

    facilities (plants, harbour and vessels, airport, and equipment) was at the forefront of Technips concerns.

    Careful planning with a good quality FEED and early realisation of the scale of the challenges.

    The selection of proven technologies, equipment and partners from the global LNG supply chain.

    First rate project management and allocation of appropriate resources in conventional and less conventional project

    management domains.

    Pre-negotiated contracts for site preparation and certain critical equipment items that were assigned to Yemgas at EPC

    contract award.

    A spirit of co-operation: enthusiasm, dedication and hard work of a diverse multicultural workforce.

    The support of Yemeni authorities and local population.

  • 8/3/2019 Technip #Yemen #LNG March 2011 Web

    6/6

    Purchases in YemenMost of the plant technical items (pressure vessels, machinery, columns etc.) were

    imported due to local unavailability. However, Technip through its Yemgas joint

    venture implemented at very early project stages a procurement policy to favour

    local supply of goods and services available in Yemen such as: office stationery

    and furniture, computers and printers, site consumables, office cabins, air

    conditioning units, vehicles, safety equipments, telecommunications etc.

    Local subcontractors

    One of the Yemgas objectives was to ensure that the local business community

    took part to the realisation of the project. In this way, several million dollars wereallocated to local companies who had the opportunity to discover and develop

    modern industrial techniques and management.

    Camp landscaping and irrigation system for both Client and Contractor camps.

    Water management: the Balhaf site produces its own water (except drinking

    water).

    Waste recycling: Yemgas contracted a local company for site domestic and

    vehicle wastes.

    Waste donations such as timber, steel and cables.

    Recruitment of Yemenis

    Providing employment to local communities has been a main objective andachievement. Over the life of the project, it is estimated that almost 13,000

    Yemenis have come and obtained a position within the team: office and field

    positions requiring technical and English language skills, engineers, industrial

    relationships, labour, supervisory positions in civil and piping works etc.

    Knowledge transfer

    In order to share the experience of industrial projects among the Yemenis present

    on site and give them marketable skills, Technip through its Yemgas joint venture

    organised a wide training campaign in different fields: HSE, quality management,

    English, camps and catering etc.

    HEADQUARTERSTechnip89 avenue de la Grande Arme75773 Paris Cedex 16FrancePhone: +33 (0)1 47 78 24 00

    LNG / GTL Product LinePhil Hagyard, SVPPhone: +33 (0)1 47 78 27 17Email: [email protected]

    This document is the property of Technip and is not intended to be a binding contractual document.Any information contained herein shall not result in any binding obligation on the part of Technip, orany of its affiliates, and is provided for information purposes only.Technip - Group Communications - March 2011 - Photo credits: Technip

    Sustainable Development actions

    www.technip.com


Recommended