Date post: | 28-Mar-2015 |
Category: |
Documents |
Upload: | sade-lepper |
View: | 222 times |
Download: | 4 times |
Tech
nolo
gies
1CH
P (V
A D
alla
s Ca
se S
tudy
)
Proprietary Information Of Energy 2013
Dallas VA Medical CenterA CHP Case StudyDesign Build Delivery of a Combined Heat and Power (CHP) Project for a Federal Client
Proprietary Information Of Energy 2013
Agenda
1. Introductions2. Project Overview3. Vision4. Construction Activities5. Challenges/Lessons Learned6. Q&A
Proprietary Information Of Energy 2013
Introductions
Mike McLaughlin, PEVice President of Engineering
Jeff GunlicksProject Manager
Proprietary Information Of Energy 2013
Project Overview
Dallas VA Medical Center• The referral center for VA North Texas Health Care System• A major teaching and medical research center.• An 84 acre campus less than 10 miles south of Dallas• Providing a wide range of medical specialties • Includes 544 beds and over 1 million sf of healthcare space
Proprietary Information Of Energy 2013
Project Scope• Add a 4.6 MW natural gas fired turbine to an existing
central energy plant.• Replace an existing steam boiler with a dual fuel fired Heat
Recovery Steam Generator (HRSG) to replace an existing steam boiler.
• Integrate electricity into the existing 11MW usage.
Existing Central Utility Plant
Turbine Yard
Electrical Support Building
Project Overview
Proprietary Information Of Energy 2013
What were the project goals?• Reducing operating costs and saving energy • Leveraging renewable energy and improve “Green” footprint• Energy Security
Why was CHP chosen? • Consistent demand for power and heat.• Integrated well with existing infrastructure• Improved energy independence
Where did the owner start? • Feasibility study that assessed the economical, technical and
funding options.• Investigation included Biodiesel, Landfill Gas and Biomass and
conventional (natural gas)
Project Vision
Proprietary Information Of Energy 2013
Power Plant Boiler Plant
45%Efficient
Traditional SystemPower Heat
Proprietary Information Of Energy 2013
Generator Heat Recovery
80%Efficient
Combined SystemPower Heat
Proprietary Information Of Energy 2013
Gas fired engines½ – 2.5 MW
Micro Turbines ½ - 1 MW
Gas Turbines5 – 50 MW
Heating Water180F-220F
Steam
25,000lbs/hr
400,000 lbs/hr
Power Heat
Combined Heat & Power
Dallas VA
Proprietary Information Of Energy 2013
Air Inlet Filter
Gas Turbine
Generator
Diverter Valve
Bypass Duct Heat Recovery
Steam Generator
Combined Heat & Power
Turbine Heat Recovery
Power Heat
Supplementary Burner
Proprietary Information Of Energy 2013
Supplementary Burner
Heat Recovery
Steam Generator
Combined Heat & Power
Heat Recovery
HeatHeat Recovery Steam GeneratorA custom piece of equipment design and fabricated to meet the project requirements• Essentially a large water tube boiler using
turbine exhaust heat as heat source
Actual Dallas VAMC HRSG during hydrostatic pressure test
Proprietary Information Of Energy 2013
Aug 2011: Proposal Submitted
Dec 2013: Target Turnover
Project Schedule
2011 2012 2013
DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR
CONTRACT SIGNED
PURCHASE TURBINE
PURHCAS
E HRSG
DRAWING
S COMPLET
E
DRAWING
S ISSUED
FOR
CONS
TRCTUION
CONSTTRUCTION
STARTS
TUBRINE DELIVERED
CONSTRUCTION
COMPLET
E
DESIGN CONSTRUCTION
Dec 2013: NG Pipeline Complete
Proprietary Information Of Energy 2013
CHP Construction
Considerations: • Access to site• Space for cranes to set up
TurbineEquipment Delivery & Rigging:
Proprietary Information Of Energy 2013
CHP ConstructionHRSGEquipment Delivery & Rigging:
Considerations: • Access to site• Space for cranes to set up• Size of doors in facility
Proprietary Information Of Energy 2013
CHP Construction
Considerations: • Access to site• Space for cranes to set up
NG CompressorEquipment Delivery & Rigging:
Proprietary Information Of Energy 2013
CHP ConstructionSite Construction:
Considerations: • Accessibility• Noise & Emissions• Proximity to Utilities
Proprietary Information Of Energy 2013
Inlet Air Chilling Coils
Generator and Turbine (Inside Enclosure)
Turbine exhaust
CHP ConstructionSite Construction:
Proprietary Information Of Energy 2013
Fuel Train
Exhaustfrom Turbine
Water Tube Boiler
Economizer
Steam ConnectionMain Stack
CHP ConstructionSite Construction:
Duct Burner
Proprietary Information Of Energy 2013
• Availability of Natural Gas will dictate size/cost of the Natural Gas Compressor.
• Turbine required 230 psig natural gas.
• Existing gas supply was 20 psig which would have required a 300 HP compressor.
• Government opted to contract for a dedicated 100-180 psig natural gas line which dropped NG Compressor to 100 HP saving significant energy
• Start up currently waiting on completion of NG line.
CHP ConstructionNatural Gas Supply:
Proprietary Information Of Energy 2013
1. Construction in an operating Central Energy Plant• Shut-downs/high risk operations: Hot tap, Electrical tie-ins
2. Working closely with the end-user throughout the duration of the project facilitated:
CHP ConstructionOther Considerations:
• Deliver the owner products that meet their needs (example: sight glass change out).
• Facility operators become familiar with equipment, and manufacturers representatives.
• RFI’s answered quickly with design-build delivery and access to end user.
• Extensive training at facility turnover for the operators.
Proprietary Information Of Energy 2013
3. Manufacturers Representatives are vital to the effort• Coordination is critical• Expertise is invaluable
4. Planning for Long Lead Items• Production of Shop Drawing• Payment Schedule and Financing
5. Allow for innovation and design flexibility (design-build):• Alternative Solutions within the contractual requirements• Improved performance with cost savings
CHP ConstructionOther Considerations:
Proprietary Information Of Energy 2013
SummaryBenefits:• Improved energy efficiency• Energy Independence• Opportunities to leverage renewable energy sources• Environmental Stewardship
Options:• Available for systems from ½ MW to 50+ MW• Heat is available as heating hot water or steam• Systems can utilize packaged or custom equipment
Unique Considerations:• Design to best match your application• Construction offers different challenges that traditional construction.• Financing and Utility Rebates are commonly available.
Select qualified partners to and contract delivery methods
Proprietary Information Of Energy 2013
Questions