IAEA International Atomic Energy Agency Technologies & Management Systems that Work: Current Best Practice in Nuclear New Build John H. Moore Nuclear Power Division [email protected] Paris, France March 11, 2014 (OECD Workshop)
Transcript
Page 1: Technologies & Management Systems that Work: Current Best ...

IAEA International Atomic Energy Agency

Technologies & Management Systems

that Work: Current Best Practice in

Nuclear New Build

John H. Moore

Nuclear Power Division [email protected]

Paris, France March 11, 2014 (OECD Workshop)

Page 2: Technologies & Management Systems that Work: Current Best ...

IAEA International Atomic Energy Agency

Exciting Times!

Page 3: Technologies & Management Systems that Work: Current Best ...

IAEA

Barakah-Unit 1, UAE

• The United Arab Emirates is the first country to start the construction

of its first nuclear power plant in 27 years, since construction was

started on China's first plant in 1985.

July 20 2012

Concrete

pouring

after approval

of PSAR.

Unit 2 followed

May 2013.

Page 4: Technologies & Management Systems that Work: Current Best ...

IAEA

Sanmen, China

Jan 29, 2013

AP-1000

Containment

vessel top head

placement;

Sanmen, China

Page 5: Technologies & Management Systems that Work: Current Best ...

IAEA

VC Summer Unit 2, USA

March 10/11, 2013

First concrete pour

of a new NPP in

North America in

three decades.

• Followed closely followed by concrete pours at

Vogtle Unit 3 (and later by Summer 3 and Vogtle4)

Page 6: Technologies & Management Systems that Work: Current Best ...

IAEA

Other recent starts (2013 and 2014)

• Belarus;

• China (3);

• South Korea;

• Argentina.

Page 7: Technologies & Management Systems that Work: Current Best ...

IAEA

Current status

0

2

4

6

8

10

12

14

16

18

Construction Starts

0

10

20

30

40

50

60

70

80

Europe-Western

Europe-Central &East

Asia-Middle East &South

Asia-Far East

America-North

America-Latin

Under Construction

Source: IAEA PRIS 05-Mar-2014

Page 8: Technologies & Management Systems that Work: Current Best ...

IAEA

IAEA MANAGEMENT SYSTEM

GUIDANCE

Safety

Requirements Nuclear

Facility

Guidance

NPP

Guidance

Page 9: Technologies & Management Systems that Work: Current Best ...

IAEA

IAEA GS-G-3.5 Mgmt System for Nuclear Installations -

Appendix V Construction

“Things to do:”

• Define roles and

interfaces;

• Grade requirements based

on safety significance;

• Have well defined

processes;

• Define handover and

responsibility transfer

processes;

• Plan activities;

Page 10: Technologies & Management Systems that Work: Current Best ...

IAEA

IAEA GS-G-3.5 Mgmt System for Nuclear Installations -

Appendix V Construction

“Things to do”(continued):

• Have kick off meetings;

• Control design

information;

• Maintain cleanliness;

• Maintain control of

material;

• Prevent damage during

storage and handling;

• Verify construction work.

Page 11: Technologies & Management Systems that Work: Current Best ...

IAEA

Verification of Construction Work

Need to have:

• Methods/schedules for verification that

specify levels of inspection & verification

required;

• Suppliers must verify all procurement

requirements have been satisfied;

• Construction activities should follow

inspection and test plans (ITPs) approved by

organization (Owner);

Page 12: Technologies & Management Systems that Work: Current Best ...

IAEA

Verification of Construction Work

• ITPs should have appropriate hold / witness

points for owner to verify acceptability;

• Plan to be prepared to ensure design and

regulatory requirements met;

• Process required to verify construction

activities;

• Verification normally documented via check

sheets or similar means to record that SSCs

have been constructed and installed to

specified requirements.

Page 13: Technologies & Management Systems that Work: Current Best ...

IAEA

Example quality issues (Sanman, China)

• RCP impeller :

Irregularities welded

without documentation;

• Squib Valve :

Manufacturer used

components and sub-

contractor without

proper equipment

qualification.

Page 14: Technologies & Management Systems that Work: Current Best ...

IAEA

BEST PRACTICE

PUBLICATIONS

Page 15: Technologies & Management Systems that Work: Current Best ...

IAEA

Project Management in NPP Construction

• Construction management

• Preparatory phase;

• Construction phase (after concrete

pouring);

• Commissioning phase;

• Main issues and lessons learned

• Selection of local suppliers;

• Bulk material management;

• Worker turnover;

• Construction equipment;

• Massive movements of people and

material;

• Public perception;

• Construction phase closure activities;

• Country specific lessons learned

Page 16: Technologies & Management Systems that Work: Current Best ...

IAEA

Construction Technologies for New NPPs

• Goal: Achieving optimum construction schedule for future NPP construction projects.

• Content: • Comprehensive descriptions

of all construction methods;

• Advantages / disadvantages;

• Best practices;

• Lessons learned.

Page 17: Technologies & Management Systems that Work: Current Best ...

IAEA

Some sample beneficial technologies

• Early engineering / front end

planning;

• Site construction management

support systems

• Modularization and open

top construction;

• Advanced welding;

• 4 season construction.

Page 18: Technologies & Management Systems that Work: Current Best ...

IAEA

Early Engineering

Basic Design

Detailed Design

Construction

Construction Engineering

Previous Design Process

Front-Loaded Construction Engineering

Basic Design

Detailed Design

Construction

Construction Engineering

Requirements from Construction Engineering Inputs from Plant Design

(BOQ, Composite Design, etc.)

Source : From Hitachi construction experience

Reduce Site Manpower by 40%

Page 19: Technologies & Management Systems that Work: Current Best ...

IAEA

Issues with a Gen 3+ project

• 18000 design changes by end of 2013;

• Lead time for nuclear side design change

approvals from one month to six months;

• Engineering completion behind schedule;

• Insufficient support for regulatory review

from off-shore team.

Should improve for “nth of a kind”

Page 20: Technologies & Management Systems that Work: Current Best ...

IAEA

建設工程

3D-model linked to schedule

Site construction management support

Page 21: Technologies & Management Systems that Work: Current Best ...

IAEA

“6D” construction schedules

3D-model by construction area

Quantities based

on 3D-model

Assign labour

resource

Schedule loaded with quantities and resources

3D model + Quantities + Resources + Time = 6D database

• Develop detailed construction schedule by area based on quantities and labour resources;

• Simulate schedule with 3D-model.

Page 22: Technologies & Management Systems that Work: Current Best ...

IAEA

RPV

Upper Condenser Module RCCV Lower Liner Module

Lower Condensor Unit RPV Pedestal Module Base Mat Module HPU Module

Stator Upper Drywell Module RCCV Top Slab

(420 ton)

(410 ton) (460 ton) (260 ton)

630 ton) (270 ton)

(650 ton) (900 ton) (550 ton)

(270 ton)

Modularization

Page 23: Technologies & Management Systems that Work: Current Best ...

IAEA

Sep 27, 2010 Unit 1 CA01 lifting.

Page 24: Technologies & Management Systems that Work: Current Best ...

IAEA

Man P

ow

er

Construction Progress

(month)

Level-off

Manpower Peak

Based on previous ABWR (Conventional Method) (a

rb.)

Manpower Peak Reduction Effort

- Construction & Module Experience-

4

3

2

1

1 6 11 16 21 26 31 36 41 (month)

Manpower Distribution

Based on Latest ABWR

Page 25: Technologies & Management Systems that Work: Current Best ...

IAEA

Advanced Welding Techniques

• Quality welding is crucial and time consuming;

• Advanced Techniques • Metal Arc Welding;

• Gas Tungsten Arc Welding;

• Submerged Arc Welding;

• Automatic welding equipment is very effective; • Maintains high quality;

• Improves work environment in narrow spaces.

Page 26: Technologies & Management Systems that Work: Current Best ...

IAEA

Automatic Welding Machine

Automatic Welding Machine for RCCV Liner

Automatic Welding for Large Bore Piping

Automatic Welding for Small Bore Piping (CRD piping)

Page 27: Technologies & Management Systems that Work: Current Best ...

IAEA

Four season construction

• Provides “factory-like” environment for

construction during winter;

• Secures environment for:

• Welding;

• Concrete pouring & curing;

• Protection from equipment;

• Allows around the clock work.

Page 28: Technologies & Management Systems that Work: Current Best ...

IAEA

Improvement of Work Productivity

during winter

Buildings with the All-Weather Structure (Steel and Temporary cover)

Movable Temporary Roof

70

75

80

85

90

95

100

冬期稼働率[%]

個別養生耐候工法 全天候耐候工法

Four season construction

Page 29: Technologies & Management Systems that Work: Current Best ...

IAEA

CONSTRUCTION READINESS

REVIEW SERVICE

Page 30: Technologies & Management Systems that Work: Current Best ...

IAEA

IAEA REVIEW SERVICES

30

Milestone 1 Milestone 2

NPP site

review

mission

Phase 1 Phase 2 Phase 3

INIR

mission

Milestone 3

INIR

mission

NPP construction

review mission

Pre-

OSART

mission

SCART

mission

EPREV

mission

ISSAS

mission

IPPAS

mission

INSSERV

mission

Page 31: Technologies & Management Systems that Work: Current Best ...

IAEA

Construction Readiness Reviews

• Focus is on a specific NPP

construction project (new

build or refurbishment), not

the overall programme.

• Must have design chosen

and construction

preparations underway at a

very detailed level.

• Guidelines finalized and

published. Service available

now!

Page 32: Technologies & Management Systems that Work: Current Best ...

IAEA

INIR

mission

IAEA REVIEW SERVICES

32

Milestone 1 Milestone 2

NPP site

review

mission

Phase 1 (commit to

programme)

Phase 2 (invite bids)

Phase 3 (commission

and operate)

INIR

mission

Milestone 3

INIR

mission

NPP construction

review mission

Pre-

OSART

SCART

mission

EPREV

mission

ISSAS

mission

IPPAS

mission

INSSERV

mission

Stage 1

Construction

Preparation.

Stage 2

Construction

Execution.

Page 33: Technologies & Management Systems that Work: Current Best ...

IAEA

Construction readiness reviews

• Areas Reviewed: • Project Management;

• Engineering Readiness;

• Procurement / Material / Supply Chain Readiness;

• Quality Management and Records;

• Human Resources and Training;

• Construction Readiness;

• Construction Installation Completion Assurance;

• Targeted Reviews (as requested by customer).

Page 34: Technologies & Management Systems that Work: Current Best ...

IAEA

Project management area

• Scope control;

• Front end planning;

• Project scheduling;

• Estmating;

• Metrics;

• Alignment;

• Community support;

• Roles & responsibilities;

• Risk management;

• Project oversight;

• Contract &

procurement

strategies;

• Change control;

• Delay/suspension

provisions.

Page 35: Technologies & Management Systems that Work: Current Best ...

IAEA

Engineering readiness area

• Documentation;

• Feedback

incorporation;

• Design change

process;

• Planning;

• Configuration mgmt,

controlled docs &

records;

• Computer & cyber

security;

• Review of previous

work (if delayed

project);

• Eng. Programmes;

• Eng. quality (Ph2 review).

Page 36: Technologies & Management Systems that Work: Current Best ...

IAEA

Procurement / material / supply chain readiness

• Equip./material availability;

• Procurement procedures and plans;

• Packaging, warehousing, & transport;

• Material inspection;

• Risk management;

• Quality assurance / quality surveillance.

Page 37: Technologies & Management Systems that Work: Current Best ...

IAEA

Quality management and records

• Quality assurance & controls;

• Independent assessments;

• Non-conformance / corrective action

programmes;

• Construction experience;

• Quality surveillance and construction

inspection;

• Controlled documentation and records.

Page 38: Technologies & Management Systems that Work: Current Best ...

IAEA

Human resources and training

• Hiring, development, and training;

• Personnel qualification;

• Human performance;

• Health and safety training;

• Personnel availability;

• First line supervision and management.

Page 39: Technologies & Management Systems that Work: Current Best ...

IAEA

Construction readiness

• Site infrastructure

requirements;

• Regulatory requirements;

• Tools availability;

• Construction sequencing;

• Security and safeguards

requirements;

• Construction execution

plans and procedures;

• Safety management;

• Environmental

management;

• New construction

practices /

technologies.

Page 40: Technologies & Management Systems that Work: Current Best ...

IAEA

Construction completion assurance

• Process defined;

• Walkdown processes;

• Hold points;

• Open item tracking;

• Labelling and control of boundaries;

• Inaccessible items;

• Interim maintenance during construction.

Page 41: Technologies & Management Systems that Work: Current Best ...

IAEA

Targeted reviews (upon request)

• Completed activities and expenditures;

• Detailed as-experienced schedule review;

• Variance review;

• Significant events of interest;

• Corrective action review;

• Other areas.

Page 42: Technologies & Management Systems that Work: Current Best ...

IAEA

E-LEARNING

Page 43: Technologies & Management Systems that Work: Current Best ...

IAEA

Construction e-learning module

• Part of a series targeted at newcomer countries, at both

senior leader and project team member levels.

• Topics covered in Construction Module:

• What makes nuclear construction unique;

• Important considerations for projects and programmes;

• How to achieve excellence;

• Key site considerations.

• Now available !

Page 44: Technologies & Management Systems that Work: Current Best ...

IAEA

SOME LESSONS LEARNED

Page 45: Technologies & Management Systems that Work: Current Best ...

IAEA

Elements needed for successful NPP

• Health, environment and safety • Communicate with regulator and public as early as possible and as

much as possible;

• Quality • Quality surveillance of sub-contractors (engineering, construction

etc.) should start early;

• Cover both domestic and foreign vendors;

• Schedule • Level 2 for management; monitor at level 3;

• Ensure sufficient resources, support contractors;

• Financial • Risk funding needed. Only 25 % NPP projects in China were completed

with planned budget.

Page 46: Technologies & Management Systems that Work: Current Best ...

IAEA

Project management lessons

• Clearly define roles of Owner and EPC

contractor ;

• Set up PM organization early;

• Ensure Owner has appropriate contingency

funding and risk allocated for unforeseens;

• Perform surveillance of quality during

manufacturing;

• Need strong site centred PM for EPC and

Suppliers;

Page 47: Technologies & Management Systems that Work: Current Best ...

IAEA

Project management lessons (cont.’d)

• Off-site team should support fully, but not

manage site team;

• Include incentives for on/off site team;

• Authorized to proceed (ATP) for long lead

items equally important with first concrete

pour date (FCD); • Lead time typically 3 years between ATP and FCD in

recommended (China).

Page 48: Technologies & Management Systems that Work: Current Best ...

IAEA

Thank you for your attention!