16 NOVEMBER 2016
Tecon Salvador Expansion
p. 2
Terminal OverviewExpansions Timeline
2000Start of operations
2012Conclusion of 1st expansion
Capacity
263k TEUs
Quay Length(1)
450 meters
Total Area
74.000 m²
Quay Length(1)
617 meters
Total Area
118.000 m²
Capacity
925k TEUs
Quay Length(1)
1.040 meters
Total Area
216.000 m²
1 2 31 21
2017Future expansion site after
executive project completion
p. 3
Reasons to Expand
Opportune Environment
� The new regulatory framework reinforces the possibility of early
extension of port lease agreements, in exchange of an investment
plan;
� The Government recognizes the existence of logistics bottlenecks and
publicly fosters investment in infrastructure;
� The Government has created means to encourage the private sector to
develop port terminals;
Containership Size Increase
2018-20 TBD 22.0k 460m
2013 ULCS 18.0k 400m
2004New
Panamax12.5k 366m
1988Post
Panamax5.0k 285m
1980 Panamax 3.4k 250m
1970Fully
Cellular2.5k 215m
YEAR CLASS DESIGN TEU LENGTH
Cabotage Berth Unable to Accommodate Largest Vessels
Limited Quay Length Increases Vessel Waiting Time
!
p. 4
Expansion ProjectFinal Layout - Conceptual Engineering Project
Notes: (1) The investments presented on this slide were calculated based on december 2013 based on conceptual project
Phase 1: Phase 2: Phase 3:
Total Investment
R$ 255.4 million
Total Investment
R$ 28.7 million
Total Investment
R$ 114.4 million
p. 5
Expansion ProjectPhase 1
Phase Description
� 423m quay extension, with a total length
of 800m after expansion;
� Acquisition of 3 STSs (Ship-to-shore Gantry
Cranes), Super Post-Panamax type;
� Total gross investment of R$ 255.4 M;
� Phase construction expected to commence
in nine months after the Amendment
signature and complete by 24 months after
the commencement of the works.
p. 6
Expansion ProjectPhase 2
Phase Description
� Leveling and paving an existing 28.160 sqm
backyard area;
� Total gross investment of R$ 28.7M;
� Phase construction limit by 2030.
p. 7
Expansion ProjectPhase 3
Phase Description
� Landfill and paving of an additional 88.803
sqm backyard area;
� Total gross investment of R$ 114.4M;
� Capacity at the end of Phase 3: 925k TEUs.
� Phase construction limit by 2034