TENTATIVE FIVE YEAR WORK PROGRAM FISCAL YEARS 2021-2025 FLORIDA DEPARTMENT OF TRANSPORTATION - DISTRICT ONE MANATEE COUNTY MANATEE OPERATIONS
Transcript
Page 1: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

TENTATIVE FIVE YEAR WORK PROGRAMFISCAL YEARS 2021-2025

FLORIDA DEPARTMENT OF TRANSPORTATION - DISTRICT ONE

MANATEE COUNTY MANATEE OPERATIONS

Page 2: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1TENTATIVE WORK PROGRAM REPORT

JULY 1, 2020 THROUGH JUNE 30, 2025DRAFT

The Department will provide a safe, interconnected statewide transportation system for Florida’s citizens and visitors that ensures the mobility of people and goods, while enhancing economic prosperity and sustaining the quality of our environment.

PHASE ADM - Administration • CAP - Capitol Improvement • CS - Construction • DSB - Design Build • ENV - Enviromental • INC - Contract Incentives • LAR - Local Government Reimbursement • MNT - Bridge/Rdway/Contract Maint CODES • MSC - Miscellaneous • OPS - Operations • PE - Prelim Engineering • PDE - Project Dev and Enviro • PLN - Planning • RES - Research • ROW - Right of Way • RRU - Railroad Utilities

Page: 1

MISSION STATEMENT

Brian RickCommunications SpecialistDistrict One Headquarters801 North Broadway AvenueBartow, FL 33830(863) 519-2828Email: [email protected]

Jesten AbrahamCommunity LiaisonDistrict One Headquarters801 North Broadway AvenueBartow, FL 33830(863) 519-2769Email: [email protected]

For additional information, please visit our website at www.swflroads.com

MANATEE COUNTY

Page 3: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

ACCM ADVANCE CONSTRUCTION (CM)

ACFP AC FREIGHT PROG (NFP)

ACNP ADVANCE CONSTRUCTION NHPP

ACSA ADVANCE CONSTRUCTION (SA)

ACSN ADVANCE CONSTRUCTION (SN)

ACSS ADVANCE CONSTRUCTION (SS,HSP)

ACSU ADVANCE CONSTRUCTION (SU)

ACTA ADVANCE CONSTRUCTION TALT

ACTU ADVANCE CONSTRUCTION TALU

BNDS BOND - STATE

BRRP STATE BRIDGE REPAIR & REHAB

CM CONGESTION MITIGATION - AQ

D UNRESTRICTED STATE PRIMARY

DDR DISTRICT DEDICATED REVENUE

DIH STATE IN-HOUSE PRODUCT SUPPORT

DITS STATEWIDE ITS - STATE 100%.

DPTO STATE - PTO

DS STATE PRIMARY HIGHWAYS & PTO

DSB1 SKYWAY

DU STATE PRIMARY/FEDERAL REIMB

EM20 GAA EARMARKS FY 2020

FTA FEDERAL TRANSIT ADMINISTRATION

FTAT FHWA TRANSFER TO FTA (NON-BUD)

GFSU GF STPBG >200 (URBAN)

HSP SAFETY (HIWAY SAFETY PROGRAM)

LF LOCAL FUNDS

LFRF LOCAL FUND REIMBURSABLE-FUTURE

NFP NATIONAL FREIGHT PROGRAM

NHRE NAT HWY PERFORM - RESURFACING

PORT SEAPORTS

CURRENTLY REPORTED ACTIVE FUND CODES

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 2 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 4: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

SA STP, ANY AREA

SN STP, MANDATORY NON-URBAN <= 5K

SR2S SAFE ROUTES - INFRASTRUCTURE

SU STP, URBAN AREAS > 200K

TALT TRANSPORTATION ALTS- ANY AREA

TALU TRANSPORTATION ALTS- >200K

TM01 SUNSHINE SKYWAY

TSM TRANSPORT SYSTEMS MANAGEMENT

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 3 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 5: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FLP: INTERMODAL

FPN : 4442511 Project/Location : PORT MANATEE INTERMODAL CARGO YARD IMPROVMENTS

Desc: SEAPORT CAPACITY PROJECT Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CAP DDR $0 $0 $0 $2,284,982 $2,362,668CAP LF $0 $0 $0 $2,293,027 $2,370,946Project Total: $0 $0 $0 $4,578,009 $4,733,614

FLP: INTERMODAL TOTAL 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

$0 $0 $0 $4,578,009 $4,733,614

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 4 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 6: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FLP: TRANSIT

FPN : 4101411 Project/Location : MANATEE COUNTY STATE TRANSIT BLOCK GRANT OPERATING ASSISTANCE

Desc: OPERATING FOR FIXED ROUTE Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

OPS DDR $0 $0 $696,765 $0 $0OPS DPTO $1,066,326 $1,119,642 $478,859 $1,234,405 $1,243,663OPS LF $1,066,326 $1,119,642 $1,175,624 $1,234,405 $1,243,663Project Total: $2,132,652 $2,239,284 $2,351,248 $2,468,810 $2,487,326

FPN : 4101481 Project/Location : MANATEE COUNTY FTA SECTION 5307 CAPITAL ASSISTANCE

Desc: CAPITAL FOR FIXED ROUTE Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CAP FTA $3,307,531 $3,434,752 $3,498,891 $3,624,727 $3,630,171CAP LF $826,883 $858,688 $874,723 $906,182 $907,543Project Total: $4,134,414 $4,293,440 $4,373,614 $4,530,909 $4,537,714

FPN : 4101482 Project/Location : MANATEE COUNTY FTA SECTION 5307 OPERATING ASSISTANCE

Desc: OPERATING FOR FIXED ROUTE Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

OPS FTA $500,000 $500,000 $500,000 $500,000 $500,000OPS LF $500,000 $500,000 $500,000 $500,000 $500,000Project Total: $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000

FPN : 4108951 Project/Location : MANATEE COUNTY AREA TRANSIT - OPERATING ASSISTANCE - CORRIDOR

Desc: URBAN CORRIDOR IMPROVEMENTS Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

OPS DDR $262,085 $269,383 $813,451 $0 $0OPS DPTO $575,779 $544,068 $0 $813,451 $807,359OPS LF $837,864 $813,451 $813,451 $813,451 $807,359Project Total: $1,675,728 $1,626,902 $1,626,902 $1,626,902 $1,614,718

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 5 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 7: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FPN : 4345172 Project/Location : MANATEE CO./SAR-BRADENTON UZA FTA SECTION 5339 CAPITAL ASSISTANCE

Desc: CAPITAL FOR FIXED ROUTE Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CAP FTA $416,326 $389,591 $399,487 $547,277 $493,210CAP LF $104,081 $97,398 $99,872 $136,819 $123,303Project Total: $520,407 $486,989 $499,359 $684,096 $616,513

FPN : 4390351 Project/Location : MANATEE COUNTY AREA TRANSIT (MCAT) BUS PURCHASES

Desc: PURCHASE VEHICLES/EQUIPMENT Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CAP FTAT $1,780,000 $0 $0 $0 $0CAP SU $1,780,000 $0 $0 $0 $0Project Total: $3,560,000 $0 $0 $0 $0

FLP: TRANSIT TOTAL 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

$13,023,201 $9,646,615 $9,851,123 $10,310,717 $10,256,271

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 6 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 8: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

HIGHWAYS

FPN : 4380861 Project/Location : 13TH AVENUE WEST AT US 301/US 41

Desc: ADD RIGHT TURN LANE(S) Project Length : 0.010 Begin Mile Post : 0.000 End Mile Post: 0.010Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST LF $20,520 $0 $0 $0 $0CST SU $668,157 $0 $0 $0 $0ENV SU $50,000 $0 $0 $0 $0Project Total: $738,677 $0 $0 $0 $0

FPN : 4313503 Project/Location : 15TH ST E / 301 BLVD E FROM 56TH AVE DR E TO N OF 52ND AVE

Desc: ADD LANES & RECONSTRUCT Project Length : 0.530 Begin Mile Post : 4.305 End Mile Post: 4.835Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST SU $0 $0 $0 $7,333,488 $0ROW SU $0 $2,760,497 $0 $0 $0Project Total: $0 $2,760,497 $0 $7,333,488 $0

FPN : 4313504 Project/Location : 15TH ST E / 301 BLVD E FROM 60TH AVE DR E TO 56TH AVE DR E

Desc: ADD LANES & RECONSTRUCT Project Length : 0.560 Begin Mile Post : 3.745 End Mile Post: 4.305Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST SU $0 $0 $0 $0 $6,248,767ROW SU $0 $0 $1,536,060 $0 $0Project Total: $0 $0 $1,536,060 $0 $6,248,767

FPN : 4313505 Project/Location : 15TH ST E / 301 BLVD E FROM S OF 63RD AVE TO 60TH AVE DR E

Desc: ADD LANES & RECONSTRUCT Project Length : 0.418 Begin Mile Post : 3.327 End Mile Post: 3.745Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

ROW SU $0 $0 $4,356,644 $0 $0Project Total: $0 $0 $4,356,644 $0 $0

FPN : 4351132 Project/Location : 63RD AVE E AT 33RD STREET E

Desc: ADD LEFT TURN LANE(S) Project Length : 0.470 Begin Mile Post : 1.530 End Mile Post: 2.000Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST SU $1,001,000 $0 $0 $0 $0Project Total: $1,001,000 $0 $0 $0 $0

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 7 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 9: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FPN : 4466741 Project/Location : 63RD AVE E FROM 17TH STREET EAST TO 19TH STREET EAST

Desc: RAIL SAFETY PROJECT Project Length : 0.124 Begin Mile Post : 0.195 End Mile Post: 0.319Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

RRU RHH $100,000 $0 $0 $0 $0Project Total: $100,000 $0 $0 $0 $0

FPN : 4466811 Project/Location : BRADENTON BEACH COMPLETE STREETS IMPROVEMENTS

Desc: PD&E/EMO STUDY Project Length : 2.956 Begin Mile Post : 4.910 End Mile Post: 7.866Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

PDE SU $0 $0 $0 $0 $1,251,000Project Total: $0 $0 $0 $0 $1,251,000

FPN : 4136391 Project/Location : BRADENTON TRAFFIC SIGNALS REIMBURSEMENT

Desc: TRAFFIC SIGNALS Project Length : 0.790 Begin Mile Post : 6.559 End Mile Post: 7.349Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

OPS DDR $229,645 $241,687 $254,246 $261,873 $269,729Project Total: $229,645 $241,687 $254,246 $261,873 $269,729

FPN : 4426301 Project/Location : DESOTO BRIDGE FROM 21ST AVE W TO US 19 BRIDGE #130053

Desc: PD&E/EMO STUDY Project Length : 7.584 Begin Mile Post : 0.000 End Mile Post: 6.500Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

PDE DDR $0 $0 $1,500,000 $0 $0PDE DIH $0 $0 $70,000 $0 $0Project Total: $0 $0 $1,570,000 $0 $0

FPN : 4404401 Project/Location : ELLENTON GILLETTE RD (CR 683) FROM MEMPHIS RD TO MENDOZA RD

Desc: SIDEWALK Project Length : 1.229 Begin Mile Post : 0.497 End Mile Post: 1.726Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

PE TALU $0 $71,000 $0 $0 $0Project Total: $0 $71,000 $0 $0 $0

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 8 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 10: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FPN : 4379601 Project/Location : H.E. BOYD BRIDGE NB

Desc: BRIDGE-REPAIR/REHABILITATION Project Length : 0.063 Begin Mile Post : 7.454 End Mile Post: 7.517Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DIH $0 $0 $5,405 $0 $0CST BRRP $0 $0 $2,214,138 $0 $0PE BRRP $0 $150,000 $0 $0 $0PE DIH $0 $5,000 $0 $0 $0

Project Total: $0 $155,000 $2,219,543 $0 $0

FPN : 4419851 Project/Location : I-75 (SR 93) AT MOCCASIN WALLOW ROAD INTERCHANGE

Desc: LANDSCAPING Project Length : 2.685 Begin Mile Post : 15.721 End Mile Post: 17.153Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DDR $1,385,100 $0 $0 $0 $0CST DIH $10,260 $0 $0 $0 $0Project Total: $1,395,360 $0 $0 $0 $0

FPN : 4420971 Project/Location : I-75 (SR 93) ADMS FROM SARASOTA COUNTY LINE TO I-275

Desc: DYNAMIC MESSAGE SIGN Project Length : 14.977 Begin Mile Post : 0.000 End Mile Post: 14.108Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DDR $0 $0 $520,716 $0 $0CST DIH $0 $0 $5,405 $0 $0CST DITS $0 $0 $1,621,500 $0 $0PE DITS $0 $0 $125,000 $0 $0PE DIH $0 $5,000 $0 $0 $0PE DDR $0 $300,000 $0 $0 $0

Project Total: $0 $305,000 $2,272,621 $0 $0

FPN : 4389951 Project/Location : I-75 (SR 93) AT SR 64

Desc: LANDSCAPING Project Length : 0.807 Begin Mile Post : 6.908 End Mile Post: 7.715Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DDR $1,051,650 $0 $0 $0 $0CST DIH $10,260 $0 $0 $0 $0Project Total: $1,061,910 $0 $0 $0 $0

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 9 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 11: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FPN : 2010325 Project/Location : I-75 (SR 93) AT US 301 INTERCHANGE

Desc: INTERCHANGE - ADD LANES Project Length : 1.150 Begin Mile Post : 10.250 End Mile Post: 11.400Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST ACSA $240,329 $0 $0 $0 $0CST CM $1,284,263 $0 $0 $0 $0CST DDR $2,536,126 $0 $0 $0 $0CST SA $102,346 $0 $0 $0 $0CST ACNP $152,192,212 $0 $0 $0 $0INC DDR $0 $0 $4,000,000 $0 $0PE ACNP $1,631,652 $0 $0 $0 $0

ROW ACNP $5,500,313 $0 $0 $0 $0RRU LF $500,000 $0 $0 $0 $0RRU STED $766,000 $0 $0 $0 $0Project Total: $164,753,241 $0 $4,000,000 $0 $0

FPN : 2010328 Project/Location : I-75 (SR 93) AT SR 70

Desc: LANDSCAPING Project Length : 0.759 Begin Mile Post : 3.337 End Mile Post: 4.096Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DDR $0 $0 $0 $2,251,130 $0CST DIH $0 $0 $0 $66,660 $0Project Total: $0 $0 $0 $2,317,790 $0

FPN : 2010322 Project/Location : I-75 AT SR 70 INTERCHANGE

Desc: INTERCHANGE - ADD LANES Project Length : 0.759 Begin Mile Post : 3.337 End Mile Post: 4.096Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

INC DDR $3,500,000 $0 $0 $0 $0Project Total: $3,500,000 $0 $0 $0 $0

FPN : 4350382 Project/Location : MANATEE COUNTY SCOUR COUNTERMEASURE AT VARIOUS LOCATIONS

Desc: BRIDGE-REPAIR/REHABILITATION Project Length : 1.278 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DIH $0 $42,120 $0 $0 $0CST BRRP $0 $2,991,284 $0 $0 $0PE BRRP $200,000 $0 $0 $0 $0

Project Total: $200,000 $3,033,404 $0 $0 $0

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 10 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 12: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FPN : 4126731 Project/Location : MANATEE COUNTY TRAFFIC SIGNALS REIMBURSEMENT

Desc: TRAFFIC SIGNALS Project Length : 5.519 Begin Mile Post : 0.560 End Mile Post: 6.079Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

OPS DDR $0 $600,299 $623,615 $642,324 $661,593OPS DITS $577,811 $0 $0 $0 $0Project Total: $577,811 $600,299 $623,615 $642,324 $661,593

FPN : 4414791 Project/Location : MANATEE ELEMENTARY

Desc: SIDEWALK Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST SR2T $0 $0 $735,100 $0 $0Project Total: $0 $0 $735,100 $0 $0

FPN : 4442731 Project/Location : MANATEE HIGH SCHOOL - SRTS

Desc: SIDEWALK Project Length : 0.413 Begin Mile Post : 0.535 End Mile Post: 0.948Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST SA $1,000 $0 $0 $0 $0CST SR2T $340,745 $0 $0 $0 $0Project Total: $341,745 $0 $0 $0 $0

FPN : 4467001 Project/Location : MANATEE MPO IDENTIFIED OPERATIONAL IMPROVEMENTS - FUNDING

Desc: FUNDING ACTION Project Length : Begin Mile Post : End Mile Post: Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST SU $13,606 $802,924 $1,934,569 $934,709 $1,126,199CST TALU $0 $5,169 $398,925 $5,203 $398,529Project Total: $13,606 $808,093 $2,333,494 $939,912 $1,524,728

FPN : 4371061 Project/Location : MANATEE/SARASOTA TMC OPS FUND COUNTY WIDE

Desc: OTHER ITS Project Length : 0.001 Begin Mile Post : 0.000 End Mile Post: 0.001Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

OPS DS $429,000 $429,000 $429,000 $429,000 $0Project Total: $429,000 $429,000 $429,000 $429,000 $0

FPN : 4136421 Project/Location : PALMETTO TRAFFIC SIGNALS REIMBURSEMENT

Desc: TRAFFIC SIGNALS Project Length : 0.751 Begin Mile Post : 0.505 End Mile Post: 1.256Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

OPS DDR $72,545 $79,874 $87,578 $90,206 $92,912Project Total: $72,545 $79,874 $87,578 $90,206 $92,912

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 11 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 13: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FPN : 4464501 Project/Location : PINERY POINT FROM US 41 TO REEDER RD

Desc: PD&E/EMO STUDY Project Length : 0.687 Begin Mile Post : 0.000 End Mile Post: 0.687Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

PDE ACSA $50,000 $0 $0 $0 $0Project Total: $50,000 $0 $0 $0 $0

FPN : 4389921 Project/Location : SOUTHERN PARKWAY WEST FROM 43RD STREET WEST TO 26TH STREET WEST

Desc: SIDEWALK Project Length : 0.001 Begin Mile Post : 0.000 End Mile Post: 0.001Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST LF $0 $0 $0 $13,332 $0CST SU $0 $0 $0 $557,147 $0CST TALU $0 $0 $0 $595,241 $0Project Total: $0 $0 $0 $1,165,720 $0

FPN : 4415341 Project/Location : SR 43 (US 301) FROM 60TH AVENUE TO ERIE ROAD

Desc: RESURFACING Project Length : 1.893 Begin Mile Post : 4.548 End Mile Post: 6.441Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DIH $0 $26,811 $0 $0 $0CST DS $0 $2,185,799 $0 $0 $0CST DDR $0 $2,429,700 $0 $0 $0ENV DDR $20,000 $50,000 $0 $0 $0Project Total: $20,000 $4,692,310 $0 $0 $0

FPN : 4444401 Project/Location : SR 45 (US BUS 41) FROM 17TH STREET TO BAYSHORE ROAD

Desc: RESURFACING Project Length : 0.778 Begin Mile Post : 0.527 End Mile Post: 1.305Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST ACSS $474,616 $0 $0 $0 $0CST DDR $938,393 $0 $0 $0 $0CST SA $1,928,761 $0 $0 $0 $0Project Total: $3,341,770 $0 $0 $0 $0

FPN : 4446121 Project/Location : SR 45 (US 41) EDWARDS DRIVE TO MAGELLAN DRIVE

Desc: RESURFACING Project Length : 2.081 Begin Mile Post : 0.007 End Mile Post: 2.088Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DDR $0 $0 $770,785 $0 $0CST DIH $0 $0 $1,081 $0 $0CST SA $0 $0 $3,246,836 $0 $0Project Total: $0 $0 $4,018,702 $0 $0

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 12 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 14: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FPN : 4335921 Project/Location : SR 45 (US 41) FROM 69TH AVE (BAY DRIVE) TO CORTEZ ROAD

Desc: SIDEWALK Project Length : 3.032 Begin Mile Post : 2.252 End Mile Post: 5.284Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST SU $4,127,822 $0 $0 $0 $0CST TALU $3,580 $0 $0 $0 $0CST ACSU $183,027 $0 $0 $0 $0CST DDR $408,758 $0 $0 $0 $0ENV DDR $100,000 $0 $0 $0 $0ROW DDR $0 $1,443,090 $0 $0 $0ROW DSB1 $2,728,054 $0 $0 $0 $0RRU LF $400,000 $0 $0 $0 $0RRU SA $200,000 $0 $0 $0 $0Project Total: $8,151,241 $1,443,090 $0 $0 $0

FPN : 4335923 Project/Location : SR 45 (US 41) LIGHTING RETROFIT

Desc: LIGHTING Project Length : 1.247 Begin Mile Post : 3.019 End Mile Post: 4.266Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST ACSS $237,260 $0 $0 $0 $0Project Total: $237,260 $0 $0 $0 $0

FPN : 4449041 Project/Location : SR 45 (USB 41) 8TH AVE W PEDESTRIAN MIDBLOCK CROSSING

Desc: MISCELLANEOUS CONSTRUCTION Project Length : 0.188 Begin Mile Post : 0.041 End Mile Post: 0.229Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST SU $0 $0 $0 $1,111 $0CST TALU $0 $0 $0 $192,147 $0PE TALU $0 $25,000 $0 $0 $0

Project Total: $0 $25,000 $0 $193,258 $0

FPN : 4443081 Project/Location : SR 55 (US 301/US 41) OVER MANATEE RIVER - HERNANDO DESOTO BR # 130053

Desc: BRIDGE-REPAIR/REHABILITATION Project Length : 0.420 Begin Mile Post : 2.618 End Mile Post: 3.038Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST BRRP $0 $1,135,557 $0 $0 $0CST DIH $0 $108,180 $0 $0 $0ENV DDR $0 $100,000 $0 $0 $0PE DIH $10,000 $0 $0 $0 $0PE BRRP $171,226 $0 $0 $0 $0

Project Total: $181,226 $1,343,737 $0 $0 $0

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 13 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 15: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FPN : 4450431 Project/Location : SR 55 FROM NB REST AREA TO SKYWAY FISHING PIER

Desc: RESURFACING Project Length : 1.284 Begin Mile Post : 0.000 End Mile Post: 1.284Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DDR $0 $0 $1,342,613 $0 $0CST DIH $0 $0 $198,548 $0 $0Project Total: $0 $0 $1,541,161 $0 $0

FPN : 4415351 Project/Location : SR 64 (6TH AVE) FROM 10TH ST WEST TO 10TH ST EAST

Desc: RESURFACING Project Length : 1.122 Begin Mile Post : 0.000 End Mile Post: 1.122Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST SA $0 $1,513,373 $0 $0 $0CST DDR $0 $104,642 $0 $0 $0CST DIH $0 $1,053 $0 $0 $0CST DS $0 $1,115,967 $0 $0 $0ENV DS $30,000 $60,000 $0 $0 $0Project Total: $30,000 $2,795,035 $0 $0 $0

FPN : 4415511 Project/Location : SR 64 (MANATEE AVE) FROM 43RD ST W TO 15TH ST W (SR 64)

Desc: RESURFACING Project Length : 1.729 Begin Mile Post : 6.576 End Mile Post: 8.305Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DDR $0 $2,567,683 $0 $0 $0CST DIH $0 $1,053 $0 $0 $0CST DS $0 $471,942 $0 $0 $0CST SA $0 $926,410 $0 $0 $0ENV DS $40,000 $0 $0 $0 $0ENV DDR $0 $100,000 $0 $0 $0Project Total: $40,000 $4,067,088 $0 $0 $0

FPN : 4081853 Project/Location : SR 64 (MANATEE AVE) FROM SR 789 TO PERICO BAY BLVD

Desc: BRIDGE REPLACEMENT Project Length : 1.936 Begin Mile Post : 0.216 End Mile Post: 2.152Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

ENV DDR $0 $25,000 $425,000 $0 $0PE LF $100,000 $0 $0 $0 $0

Project Total: $100,000 $25,000 $425,000 $0 $0

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 14 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 16: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FPN : 1960226 Project/Location : SR 64 AT LORRAINE ROAD

Desc: INTERSECTION IMPROVEMENT Project Length : 0.020 Begin Mile Post : 11.383 End Mile Post: 11.403Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST LF $0 $0 $0 $43,051 $0CST DIH $0 $0 $0 $31,188 $0CST DDR $0 $0 $0 $4,023,776 $0ENV DDR $0 $0 $0 $50,000 $0ROW DDR $54,045 $309,844 $0 $0 $0ROW DIH $48,000 $0 $0 $0 $0RRU LF $0 $0 $0 $775,000 $0Project Total: $102,045 $309,844 $0 $4,923,015 $0

FPN : 4402371 Project/Location : SR 64 OVER SARASOTA PASS ANNA MARIA DRAW BRIDGE # 130054

Desc: BRIDGE-REPAIR/REHABILITATION Project Length : 0.592 Begin Mile Post : 0.698 End Mile Post: 1.290Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST BRRP $0 $0 $0 $886,391 $0CST DIH $0 $0 $0 $11,110 $0ENV BRRP $0 $0 $65,000 $0 $0PE BRRP $0 $0 $71,000 $0 $0PE DIH $0 $0 $10,000 $0 $0

Project Total: $0 $0 $146,000 $897,501 $0

FPN : 1960228 Project/Location : SR 64 ROUNDABOUT @ GREYHAWK BLVD

Desc: LANDSCAPING Project Length : 0.500 Begin Mile Post : 9.840 End Mile Post: 10.340Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DDR $0 $220,000 $0 $0 $0CST DIH $0 $5,265 $0 $0 $0PE DIH $5,000 $0 $0 $0 $0

Project Total: $5,000 $225,265 $0 $0 $0

FPN : 4442101 Project/Location : SR 683 (US 301) AT 51ST AVENUE EAST

Desc: INTERSECTION IMPROVEMENT Project Length : 0.500 Begin Mile Post : 4.067 End Mile Post: 4.567Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST ACSS $0 $0 $534,889 $0 $0CST SA $0 $0 $1,081 $0 $0PE SA $10,000 $0 $0 $0 $0PE ACSS $295,000 $0 $0 $0 $0

Project Total: $305,000 $0 $535,970 $0 $0

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 15 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 17: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FPN : 4442111 Project/Location : SR 683 (US 301) AT 63RD AVE E

Desc: INTERSECTION IMPROVEMENT Project Length : 0.500 Begin Mile Post : 2.561 End Mile Post: 3.061Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST ACSS $0 $0 $1,035,976 $0 $0CST DDR $0 $0 $47,177 $0 $0CST SA $0 $0 $1,081 $0 $0PE SA $10,000 $0 $0 $0 $0PE ACSS $320,000 $0 $0 $0 $0

Project Total: $330,000 $0 $1,084,234 $0 $0

FPN : 4451441 Project/Location : SR 683 (US 301) FROM S OF 25TH CT E TO S OF 13TH AVE E

Desc: RESURFACING Project Length : 7.516 Begin Mile Post : 0.392 End Mile Post: 7.908Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DDR $0 $0 $1,670,206 $0 $0CST DIH $0 $0 $1,081 $0 $0CST DS $0 $0 $8,711,966 $0 $0CST SA $0 $0 $5,116,324 $0 $0RRU DDR $0 $50,000 $0 $0 $0Project Total: $0 $50,000 $15,499,577 $0 $0

FPN : 4406881 Project/Location : SR 684 (CORTEZ RD) FROM 86TH/PALMA SOLA BLVD TO CAPE VISTA DR

Desc: ADD LEFT TURN LANE(S) Project Length : 2.412 Begin Mile Post : 3.049 End Mile Post: 5.461Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DIH $0 $1,053 $0 $0 $0CST ACSS $0 $419,296 $0 $0 $0CST DDR $0 $13,914 $0 $0 $0ENV DDR $20,000 $50,000 $0 $0 $0Project Total: $20,000 $484,263 $0 $0 $0

FPN : 4302042 Project/Location : SR 684 FROM SR 789 (GULF DRIVE) TO 123RD STREET W

Desc: REPLACE MOVABLE SPAN BRIDGE Project Length : 0.900 Begin Mile Post : 0.000 End Mile Post: 0.900Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

PE LF $100,000 $0 $0 $0 $0ROW DIH $12,360 $0 $0 $23,640 $0ROW DSB1 $3,814,118 $0 $0 $980,957 $3,118,709Project Total: $3,926,478 $0 $0 $1,004,597 $3,118,709

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 16 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 18: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FPN : 4447771 Project/Location : SR 70 FROM W OF CURTIS ROAD TO COUNTY LINE ROAD

Desc: RESURFACING Project Length : 2.463 Begin Mile Post : 37.003 End Mile Post: 39.466Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DDR $0 $2,336,450 $0 $0 $0CST DIH $0 $1,053 $0 $0 $0Project Total: $0 $2,337,503 $0 $0 $0

FPN : 4145062 Project/Location : SR 70 FROM LORRAINE RD TO CR 675/WATERBURY ROAD

Desc: PD&E/EMO STUDY Project Length : 6.091 Begin Mile Post : 9.476 End Mile Post: 15.567Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

ENV DDR $1,420,000 $0 $0 $0 $0ENV DS $0 $0 $50,000 $0 $0ROW DSB1 $136,990 $0 $0 $0 $0ROW DDR $8,013,463 $0 $0 $0 $0ROW DIH $120,000 $0 $0 $0 $0Project Total: $9,690,453 $0 $50,000 $0 $0

FPN : 4145067 Project/Location : SR 70 FROM LORRAINE ROAD TO BOURNSIDE BLVD

Desc: ADD LANES & RECONSTRUCT Project Length : 3.561 Begin Mile Post : 9.476 End Mile Post: 12.338Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DDR $0 $0 $21,097,577 $0 $0CST DIH $0 $0 $1,081 $0 $0CST LF $0 $0 $81,075 $0 $0CST SIB1 $0 $0 $24,342,682 $0 $0RRU LF $0 $0 $750,000 $0 $0Project Total: $0 $0 $46,272,415 $0 $0

FPN : 4463481 Project/Location : SR 789 (GULF DR N) FROM N OF 9TH ST TO AVE C

Desc: DRAINAGE IMPROVEMENTS Project Length : 0.457 Begin Mile Post : 6.816 End Mile Post: 7.273Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DDR $115,980 $0 $0 $0 $0CST DIH $1,026 $0 $0 $0 $0Project Total: $117,006 $0 $0 $0 $0

FPN : 4365513 Project/Location : SR684(CORTEZ RD) FROM E OF 123RD ST WEST TO 119TH ST WEST

Desc: LANDSCAPING Project Length : 0.458 Begin Mile Post : 0.839 End Mile Post: 1.297Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DDR $430,916 $0 $0 $0 $0Project Total: $430,916 $0 $0 $0 $0

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 17 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 19: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

FPN : 4401551 Project/Location : US 41 FROM EDWARDS DRIVE TO PEARL AVENUE

Desc: PD&E/EMO STUDY Project Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

PDE SU $0 $800,000 $0 $0 $0Project Total: $0 $800,000 $0 $0 $0

FPN : 4466851 Project/Location : US 41 UPGRADE ATSPM COMPATIBILITY DESIGN-BUILD

Desc: TRAFFIC CONTROL DEVICES/SYSTEMProject Length : 0.000 Begin Mile Post : 0.000 End Mile Post: 0.000Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST DITS $0 $0 $0 $1,782,917 $0CST DIH $0 $0 $0 $1,111 $0PE DIH $0 $0 $1,000 $0 $0PE DITS $0 $0 $100,000 $100,000 $0

Project Total: $0 $0 $101,000 $1,884,028 $0

HIGHWAYS TOTAL 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

$201,492,935 $27,081,989 $90,091,960 $22,082,712 $13,167,438

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 18 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT

Page 20: TENTATIVE FIVE YEAR WORK PROGRAM FISCAL ...swflroads.com/WorkProgram/2019/documents/Manatee.pdfFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT JULY

MISCELLANEOUS

FPN : 4440491 Project/Location : US 41 FROM 63RD AVE W TO 53RD AVE W

Desc: TRAFFIC OPS IMPROVEMENT Project Length : 1.270 Begin Mile Post : 3.007 End Mile Post: 4.277Comments :

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

CST ACSS $764,432 $0 $0 $0 $0CST DDR $30,043 $0 $0 $0 $0CST SA $1,026 $0 $0 $0 $0Project Total: $795,501 $0 $0 $0 $0

MISCELLANEOUS TOTAL 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025

$795,501 $0 $0 $0 $0

MANATEE COUNTY TOTALS

Phase Fund 2020/ 2021 2021/ 2022 2022/ 2023 2023/ 2024 2024/ 2025 Total

COUNTY Total : $215,311,637 $36,728,604 $99,943,083 $36,971,438 $28,157,323 $417,112,085

PHASE CODES

ADM – Administration ● CAP – Capitol Improvement ● CS – Construction ● DSB – Design Build ● ENV – Environmental ● INC – Contract Incentives ● LAR – Local Government Reimbursement ● MNT – Bridge/Rdway/Contract Maint ● MSC – Miscellaneous ● OPS – Operations ● PE – Prelim Engineering ● PDE – Project Dev and Enviro ● PLN – Planning ● RES – Research ● ROW – Right of Way ● RRU – Railroad Utilities

Page: 19 Run Date:10/11/2019 SnapShot Date: 10/7/2019

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT - 1 TENTATIVE WORK PROGRAM REPORT

July 1, 2020 Through June 30, 2025 MANATEE COUNTY

DRAFT


Recommended