Date post: | 14-Apr-2015 |
Category: |
Documents |
Upload: | edgar-espinosa-cazarin |
View: | 43 times |
Download: | 5 times |
TRAINING REPORT AT
THE WELL
TEOTLECO 02
8 ½” STAGE
BY
ING EDGAR FERNAN ESPINOSA
CAZARIN
PEMEX ALIANZ II
PREPARED FOR
ING NATI JIMENEZ
ING MONSERRAT HERNANDEZ
2
Content
................................................................................................................................ 1
Introduction.............................................................................................................. 3
Scope ................................................................................................................... 3
Report Description ............................................................................................... 3
Mechanical state .................................................................................................. 4
Well Casing .......................................................................................................... 4
Drill String, Bit and Bottom Hole Assembly (BHA)................................................ 4
Annulus volume ................................................................................................... 5
Mud Pumps .......................................................................................................... 5
Mud Pits ............................................................................................................... 6
Reserves Tanks ................................................................................................... 6
Solid Control Equipment (SCE) ............................................................................ 7
Wellbore Antecedents ............................................................................................. 7
Drilling Operation ..................................................................................................... 8
DFG Simulations ................................................................................................... 10
Logistic .................................................................................................................. 10
Fluid Test............................................................................................................... 11
Inventory................................................................................................................ 13
List of Products ...................................................................................................... 14
Health Safety and Environment (HSE) .................................................................. 15
Conclusions and Recommendations ..................................................................... 15
3
Introduction
Scope
I had the opportunity to be in the first stage of this well, in that stage a 17.5
inch bit size was used to drill the first stage. This well has a slim design for this
reason the third stage will be drilled with a PDC 8 1/2” bit. The formation that will
be drilled is almost one hundred percent of shale, in a high pressure zone; a lost
pressure problem should not exist while the mud weigh condition been maintained
according to the program, notwithstanding other problem could happened as a
stuck pipe due to the well angle. Now I should take part of the operation, and give
my recommendations about mud treatment and also I should realize hydraulic
simulations in order to reach a good hole clean and maintain the mud in excellent
conditions
Report Description
The report will be present in the following form:
1. Those thinks that you should know at the first day at the Well:
Mechanical State
Mud Pits Capability
Revers Tanks Capability
Mud Mixing Equipment
Mud System
2. .Operations at the Well.
Well antecedents
Drilling Operations
Electrical Register
Cementing
3. Mud Engineer Roles
Logistic
Mud Test
Inventory
List of products
HSE
Conclusions and Recommendations
4
Mechanical state
Well Casing
In the table below appear the casing properties.
Type OD (in)
Weight (lbm/ft)
ID (in)
Shoe MD (ft)
Shoe TVD (ft)
Conductor Casing 20 129.33 18.750 164.05 164.05
Intermediate Casing 13.375 54.50 12.615 3281 3281
Conductor Casing 9.625 53.50 8.535 10335.15 10335.15
The well capacity in the casing and the open hole is in (lbb):
2 28.535 10335.15 8.5 1
825.8810
341.929
102 29 9lbb
Drill String, Bit and Bottom Hole Assembly (BHA)
The principal characteristical of drill string used in this stage were the
directional tools, all of these tools are very sophisticated and the mud should be in
good conditions with respect to the low solid rate concentration, according with the
mud weight used. Also the Solid control equipment might work in excellent
conditions due to the formations solid could damage the directional tools. A long
this stage the Well direction was built using the LWD and the mud motor, and the
bit used was a PDC bit.
Component Data Item #
Description OD (In)
ID (In)
Weight (lb/ft)
Top Connect
Serial Length (m)
Cumulative Length (m)
1 PDC Bit 8.5 3 230 P6-5/8”
REG 11806241 0.32 0.32
1 Mud
Motor 6 ½ 5.25 123.16
B6 5/8 REG
10469969 9.16 9.48
1 Stabilizer B6 5/8 REG
1 Pony
collar 8” 8 2.75 147.22
B6 5/8 REG
11460380 3.05 6.28
1 Stabilizer
8”x12” 8 2.8 150.13
B6 5/8 REG
11673574 2.68 15.01
1 Double
Pin 8 3.25 143.03
B6 5/8 REG
10469593 0.41 15.42
5
1
EWR-collar 8
(resistivity)
8 2 151 B6 5/8 REG
10469593 3.69 19.11
1
DGR Collar
(Gamma Ray)
8 2 142.7 - 285841 1.37 20.48
1 HCMI
Collar 8 (battery)
8 2 149.9 - 10909619 1.45 21.93
1 TM/DM Collar
8 3 147.22 B6 5/8 REG
10688002 4.6 26.53
1 CPV 7.875 3.25 137.72 B6 5/8 REG
SSFS-8014
0.74 27.27
5 Drill
Collar 8 2.25 157.4
6 5/8 REG
PEMEX 9.156 73.05
1 Sledgehammer 8”
8.125 2.75 132.58 6 5/8 REG
11652864 6.56 79.61
1 Combinat
ion 5 2.875 44.79
6 5/8 REG
PEMEX 9.52 81.99
12 DP HW
5” NC 50 5 3 53.6 NC 50 PEMEX 9.53 196.54
Length Total
196.54
The bit data appear in the next table
Bit Data
Bit Size (in) 8.5 Nozzles 6X20/32
Manufacturer HDBS FTA 1.841
Model FX65
Annulus volume
The volume in the annulus is in (lbb):
2 2 2 25 58.535 10335.15 8.5 134
542.181029 10
1.929
29lbb
Mud Pumps
At this well there are two triplex pumps, the piston on a triplex mud pump
work only on the forward stroke and generally short strokes.
6
Mud Pump
Pump Liner Diameter (in)
Length Liner (in)
Adjust pressure (psi
Model Type
Mud pump 1 6.5 14 4500 LEWCO 2214
TRIPLEX
Mud Pump 2 6.5 14 4500 National 14-P-220
TRIPLEX
The volume displacement for each pump is
26 12 0.95
1 0.1365 4116
mud pump lbb stk
Both pumps has the same configurations, and displacement the same volume
Mud Pits
In the Table below appear the mud pits and its capacity
Mud Pits
Pit Names Factor Max Capacity (lbb)
Minimum Capacity (lbb)
Suction Pit 0.165 166 75.47
Pill Pit 0.058 58.36 25.15
Mix Pit 0.274 275.47 50.31
Settling pit 0.203 254.6 -
Sand Trap - 94.3 -
The maximum volume in all the pits is 135 m3, is very important to know and be
care full with the mud moves among the pits if doesn´t have control of the volumes
could occurred a spill.
Reserves Tanks
The capacity of the reserves tanks is show in the next table
Reserve Tanks
Name Capacity (lbb) Material Supplier
Vertical Tank N° 1 50 Control Fluid HALLIBURTON
Elevate Tank 18 Light Fluid PEMEX
Silo N° 1 45 Barite HALLIBURTON
Silo N° 2 45 Barite HALLIBURTON
Silo N °2 45 Barite HALLIBURTON
7
Solid Control Equipment (SCE)
The Solid control is one of the most important aspects of mud System
control, since it has a direct bearing on drilling efficiency.
Solid Control Equipment
Style Equipment Centrifuge Alfa laval 1458 Centrifuge Alfa laval 1458 Shaker D-285 Shaker D-285 Shaker D-285 Mud Cleaner -
The flow used with this bit size is just 430 gpm, for that reason just was used two
shakers during this stage. The rest of the equipment was used only in special case,
when the mud weight was increased, situation that occurred in few times
Type of screens for each shaker used for this drilling stay
Type of mesh used along the stage
Day Interval Type of screen
04-01-13 3559-3497 120-120-100-80
05-01-13 3618-3559 120-120-100-80
06-01-13 3638-3618 120-120-140-170
08-01-13 3691-3638 120-120-140-170
09-01-13 3745-3691 120-120-140-170
10-01-13 3770-3745 120-120-140-170
16-01-13 3818-3770 120-120-140-170
17-01-13 3915-3818 120-120-140-170
18-01-13 3988-3915 120-120-140-170
19-01-13 4076-3988 120-120-140-170
20-01-13 4158-4076 120-120-140-170
21-01-13 4281-4158 120-120-140-170
22-01-13 4324-4281 120-120-140-170
Different arrays were used thought the stage, because the mud weight was
increasing according the deep.
Wellbore Antecedents
This well is located in the Teotleco field; the last well drilled by BAROID in
this field was the Teotleco 15. For the type of well design, this stage have been
drilled with 8.5 bit, the first stage was drilled with 17.5 in bit, and the second stage
was drilled with 12.25 in bit. In this stage the well angle was built with the
8
directional tools, (MWD and Mud motor), these tools send their signal through the
mud, for that reason the mud properties should be in adequate conditions, in order
to achieve a good signal and get more detailed results. This stage began in
10335.15 ft, and the footage when I came was 1138.5 ft, the stage just had seven
days.
Drilling Operation
Between slide drilled meter and rotate drilled the drilling operations was in
normal conditions. While the angle was build the ROP was less due to the drilling
was in slide form, in average 30 minutes per meter, otherwise when the meters
were with rotate the ROP was in average 5 minutes. These highs ROP needed a
good hole cleaned.
Following the process PM-MXS-HAL-BDF-400 for the execution of the service
order, the parameters that might be follow while the drilling operations are the
density, the mud pit volume, and the viscosity. Each 30 minutes these parameters
are measured. Any variations in the volume should be notified to the driller. This
could be indications of a loss circulation or a blowout.
The drilling parameters appear in the table below.
Drilling Parameters
Day Drilled meters
ROP m/h
Volume in the hole (m3)
Interval Volumen loss in SCE (m3)
Formation
04/01 62 8.5 2.26 3559 - 3497 5.94 100% Shale
05/01 59 12.1 2.15 3618 - 3559 6.98 100 % Shale
06/01 20 6.6 0.73 3638 - 3618 2 100% Shale
08/01 53 9.2 1.94 3691- 3638 10.54 100% Shale
09/01 55 7.4 12.2 3745 - 3691 11.20 10% Mud stone 90%
Shale
10/12 25 4.8 0.91 3770 - 3745 3 100% Shale
16/01 48 13.1 1.75 3818 - 3770 3.72 100% shale
17/01 97 13.3 3.55 3915 - 3818 9.66 100% shale
18/01 73 10 2.67 3988 - 3915 8.41 100% shale
19/01 88 12 3.22 4076 - 3988 7.77 100% shale
20/01 82 15.8 3.00 4158 - 4076 4 100 % shale
21/01 123 20.2 4.50 4281 - 4158 3.75 100% shale
22/01 43 15.7 1.57 4324 - 4281 0.96 100% shale
26/01 17 11.2 0.62 4341 - 4324 1.28 100% shale
28/01 8 26.2 0.29 4349 - 4341 0.50 100% shale
9
29/01 83 11.3 3.03 4432- 4349 4.58 100% shale
During the first drilling days, 273 meters were drilled, with good ROP and keeping
the angle and the course, drilling in slide form using the mud motor. But the well
angle according to the plan was 41 degree, in order to get a better angle
construction, and safety operations, the Kelly system was replaced by a TOP-
DRIVE system, this change took six day including the out trip and the in trip. Before
trip out started a viscous pill was pump for clean the entire hole. The high viscosity
pill helped to sweep all the cuttings deposited in the annulus and avoid a
resistance along the trip out.
As the table shows with the after the TOP DRIVE was installed, the ROP increase
almost in two times. But the cuttings load was higher that the Kelly.
The formation drilled is a high pressure zone. One characteristic of these fields is
the high rotary torque even rotary stopped, and drags through the trips. For this
reason a high density program was designed to reach a high ROP and avoid
problems. The density program is showed in the table below:
Fluid Density Program
Deep (m) Density (gr)
3150 1.95
3550 1.96
4000 1.97
4100 1.98
4200 1.99
4300 2.00
4400 2.01
4500 2.02
4600 2.03
4675 2.04
4750 2.05
5670 2.05
The density program was followed until 4281 m deep, where a pack pipe almost
occurred, with this event was decided increase the density in two points until 2.01
gr/cc. the other modifications in the program was at 4047 during the trip in, other
drag was observed and the program was changed one more time, the density was
raised one point until 2.02 gr/cc.
10
The problems with the directional tools make lost much time with tripping for check
the tools signals.
DFG Simulations
A long the Drilling the ECD was predicted using the DFG simulator. Also the
hole cleaned was simulated, and the maximum cuttings charge was simulated in
this software. Theses parameters are calculate while have been drilling.
As mud engineer we should give these recommendations to the driller in order to
avoid a lost circulation during the Run casing and during the cementing.
With the high weight has driven the ECD should be followed in order to avoid a lost
circulations of fracture the same. The fracture pressure is 2.23 gr/cc
Logistic
The logistic is very important, you should in contact with the supervisor and
him with the mud plant, in order to request the mud necessary due to the material o
some other thing than they should provide you. All off those requests are elaborate
with a format FO-MXS-HAL-BDF-200B-101
With the quantity of material used during this stage the logistic take a lot
importance. Also the Fluid requirements were more, this due to the volume
consumed during the stage are large, and the impregnation of the solid is a lot to.
An effective communication with the supervisor should be keep, in order to have de
adequate materials in time and form.
In this well one problem was that only has one vertical tanks, for this reason the
mud request
11
Fluid Test
The Fluid used during the stage was the INVERMUL system; INVERMUL
tight-emulsion systems provide high-temperature stability and tolerance to
contaminants. This system use high concentrations of emulsifiers and fluid-loss
agents for maximum emulsion stability and minimal filtrate loss.
The system presented a problem with the electrical stability, this is a factor very
important due to if this value is less than 700 V, could be a sign of have a weak
stability and the emulsion could break if a contamination occurred.
Firs to all is necessary establish what is the reason for the stability is too low? One
factor could be a contamination with water, or water-wet solids or even a high salt
concentration are factors that affect the electrical stability value.
To solve this problem all of those factors should be discard, the water relation was
kept in 85/15 or even 86/14, the water contain never was higher. The water-wet
solid was a problem due to the system was increased its weight adding barite,
(solids), a concentration of wettings should be kept. Finally the concentration of
emulsifier was low according to the laboratory analysis realize by the tech support.
The concentration recommended by the lab tech, was a 5 l/m3 of emulsifier per 5
l/m3 of wetting, and 5 kg/m3 of Lyme. According with the pilot tests the electrical
stability should reach values closer of 1200 V, enough high for ensure a stable
emulsion.
The total system circulation was 250 m3 the concentrations used to solve this
problem were:
( ) ( ⁄ ) (
)
The same calculus was realized to get the quantity of wetting used, and the
quantities of lime used.
With the addition of these concentrations the problem was solved, furthermore the
temperature along the drilling helped to improve this parameter.
The other parameter that was adjusted was the salinity, this due to the behavior of
the formation.
The concentration of cacl2 should be raised until 295000ppm according to the
hydrometer test.
12
( )
( ) ( )( )( )
( )( )( )
Desired weight % CaCl2: D%CaCl2
%purity CaCl2 %purity
CaCl2 (lb/bbl whole mud) to add=
[
]
[
] ( )( )
(
⁄) ⁄ ( ) (
)
In the table below appears the parameters in the minimum and maximum mud
weight used during the drilling
Fluid Test
Parameters Miminum Maximum
Density (gr/cc) 1.95 2.02
Funnel Viscosity (s) 78 82
Filtered (cc) 2.2 2.4
Filter Cake (mm) 1 1
Gels (lb/100 ft2) 18/29 24/35
Salinity 260000 295,000
% Solid 37 38
%Oil 53 52
%water 9 9
R O/W 85/15 85/15
Plastic Viscosity (cp)
48 51
Yield Point (lb/100 ft2) 29 31
Electrical stability (volts) 435 978
13
Lyme excess (Kg/m3) 19.21 20.32
Alkalinity (ml) 5.3 5.5
600/300 125/77 133/82
200/100 56/37 61/43
6/3 18/16 21/20
Inventory
One of the most important aspects of any business is inventory
management and the Drilling Fluid is not the exception, for that reason we should
keep ours inventory update every day, and have a perfect control about the
products that were using along the stage.
The List Below contain the product used during my period in this well, each
material is used according to the analysis that was realized to the mud, and in
order to hold the properties according to the target´s parameters
Inventory
Product Unit Begin received Sent Used Final
Barite 1 Tonne 128 86 99 115
BAROFIBRE COARSE
40 lbm bag
74 74
Calcium carbonate coarse (M100)
25 kg Bag
280 70 210
Calcium carbonate medium (M200)
25 kg Bag
105 140 35 210
CALCIUM CHLORIDE PEL
25 KG Bag
100 70 70 100
DURATONE 50 lbm Bag
75 50 25 100
EZ MUL 55 Gal Drum
6 16 14 8
INVERMUL NT 55 Gal Drum
8 12
LIME HYDRATED
25 Kg Bag
140 200 212 128
GELTONE V 55 Gal DRUM
57 25 2 30
STEALSEAL 400
50 kg Bag
122 122
14
List of Products
The list below contains the Baroid´s product used during the stay, with these
products an adequate treatment was given to the system
List Product
Product Name Function Description
BAROFIBRE COARSE Sweeping agent is a synthetic fiber and is suitable for use in all fluid types, vertical and horizontal wells, and is an ideal product for use during milling operations
DURATONE-HT Filtration control agent is a modified lignitic product which is the primary filtration control additive for INVERMUL. reduce HTHP Filtrate at temperatures reaching 500°F
EZ MUL Wetting agent Emulsifier is the primary emulsifier and oil-wetting agent for application in INTEGRADE® drilling fluid systems. When FORTI-MUL emulsifier is used with RHEMOD™ L viscosifier and ADAPTA® filtrate reducer, it aids in producing a stable invert emulsion system with low filtration rates
INVERMUL Emulsifier Primary emulsifier is designed for mineral oil and paraffin based drilling fluid systems. emulsifier helps stabilize emulsions, aid suspension properties, and reduce HPHT filtration
STEAL SEAL (100 AND 200)
Bridging Agent lost circulation material products are resilient, angular, dual-carbon based lost circulation materials. These unique
15
resilient graphitic carbon (RGC) products allow tightly packed particles, under compression in pores and micro fractures, to compress and then expand without being dislodged by changes in differential pressure.
Health Safety and Environment (HSE)
Each week a Health Safety and Environment tour is realized, identifying the
problems related with the safety problems. This part is as important as the same
operation, or even more. Baroid has a different process to spread towards us, and
our customers the HSE policies.
The different Formats elaborated to spread our HSE policies are:
FO-MXS-HAL-BDF-400D Security meeting
FO-MXS-HAL-BDF-400H Safety Tours
FO-MXS-HAL-BDF-231A check list charge an discharge
Additionally the AST format is elaborate to comply with PEMEX policies.
Conclusions and Recommendations
Through this stage the angle was buit, with it, the drilling operation was slowly, due
to much of the meters were slides, and per each slide meter the ROP raised until
45 minutes per meter drilled. A 47 angle was built by the directional operators,
using the mud motor and its directional tools.
The troubles relationship with the mud was the mentioned in along this report, the
stability problem, and in some drilling days, the pass of cuttings through the control
solid equipment, situation that was followed with the SCE operators. The
concentration of drilled solid always was in conditions, but the addition of barite
also was a factor for raise this parameter.
The addition of emulsifier in conjunction with wetting and lime help to stabilize the
emulsion. The concentration used was almost two time bigger that the lab tech, but
the fluid received had a low concentration of emulsifier and wetting, for that reason
should increase this concentration.
16
One problem maybe was the concentration of organophilic clays used for the mud
plant, due to this material usually has a better reaction when has contact with high
temperatures. My recommendation is request a mud with light rheological
parameters, in order to avoid high plastic viscosities when this material has a
reaction with the high temperatures in the wellbore.