Date post: | 25-Dec-2015 |
Category: |
Documents |
Upload: | rodger-moore |
View: | 213 times |
Download: | 1 times |
Testing and Development Activities of Meter-Base Switches for DER Applications
Power Systems 2005 Conference, Clemson University March 9-11 2005
Panel Session on Interconnection:
Doeg RodriguezDoeg Rodriguez Tom KeyTom KeyUniv. of Puerto RicoUniv. of Puerto Rico EPRI SolutionsEPRI SolutionsMayagüez, PRMayagüez, PR Knoxville, TNKnoxville, [email protected] [email protected](787) 505-7783 (865) 218-8082
2 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Update on EPRI Meter-BaseSwitch Developments
Evaluation of Global Power Products “Generlink” (previously PEPCO Technologies)
Physical Inspection of the unit (inside and outside)
Transfer, Protection and Time Tests
Adding Paralleling Functions….”GridGateway”
Programmable Protection Settings
Future for AMR, Communications and Dispatching
3 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Generlink Unit Tests
Revenue Meter collar
Specially designed plug - prevents accidental disconnection or operation
4 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Top side view
Compatible with 4-jaw ringed/ring-less bases
CT’s on Utility side
Load circuit breakers on generator side
Generlink Plug
5 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Side view
Weather-tight cap
Meter base ring
Indicator LEDS
Utility Availability
Internal Fault
Overload
Generator as preferred source
6 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Bottom view
Blades for meter base
Neutral bond for generator
Meter base ring
7 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Switching Components
Interlocking relays
200 A rated busbars
200 A rated utility relay
30 A rated generator relay
Integral protection functions
8 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Test Setup
The “House”
PT and CT monitoring points
Weather-head
Meterbase
Circuit Panel
9 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Test Setup (Cont.)
Service Entrance
150 FT 4/0 AWG
50 kVA Transformer 480/240/120
10 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Test Setup (Cont.)
Standby source
25 kVA Transformer
480/240/120 V
Heater loads (×2)
4300 W (240V)
5200 W (240V)
120 V loads (×2)
40 W bulbs
11 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
State Diagram / Singleline
Generator is preferred source
Allows for scheduled maintenance and test runs
Transfer is break-before-make
Relay operation is fully interlocked
12 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Tests
Three types
A. Transfer Tests (16 tests)
Voltage Magnitude & Ramp tests
B. Protection Tests (5 tests)
Overload
C. Time Trial Tests (4 tests)
Transfer Time tests
13 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
A. Transfer Tests
Type of tests
Loss of Phase (only one 120V leg)
Under and Over-voltage events
Loss of utility
Paralleling
Designation Action Protocol Case Type Case
A0 Energize one leg gen. circuit while in utility mode Loss of line Single Line Gen. Energization
A1 Energize one leg gen. circuit while in utility mode Loss of line Single Line Gen. Energization
A2 Energize one leg gen. circuit while in gen. mode Loss of line Single Line Gen. EnergizationA3 Disconnect one leg gen. while serving load Loss of line Single Line Gen. Dropout
A4Disconnect one leg gen. while serving load/ Decrease voltage on remaining phase until transfer
Loss of lineSingle Line Gen. Dropout / Undervoltage Magnitude
A5Energize one leg utility, while in gen. mode / Gen. serving load
Loss of line Single Line Utility Energization
A6Energize one leg utility, while in gen. mode / Gen. un-energized
Loss of line Single Line Utility Energization
A6BEnergize one leg utility, while in utility mode / Gen. un-energized
Loss of line Single Line Utility Energization
A7BIncrease utility voltage from zero on both legs simulatenously until transfer
Voltage Disturbance Utility Pickup Voltage Magnitude
A8BIncrease gen. voltage on both legs simultaneously until transfer
Voltage DisturbanceGenerator Pickup Voltage Magnitude
A9BDecrease utility voltage on both legs simultaneously until transfer / Generator Offline
Voltage Disturbance Utility Undervoltage Magnitude
A10Decrease gen. voltage on both legs simultaneously until transfer
Voltage Disturbance Generator Undervoltage Magnitude
A11 De-energize utiltiy and energize gen. Loss of Utility Utility OutageA15 Energize Generator / utility serving load Paralleling ParallelingA17 Energize utility / Gen. serving load Reconnection Utility ReturnA18 Energize utility and de-energize gen Reconnection Utility ReturnA20 Increase voltage on utility source until transfer Voltage Disturbance Utility Overvoltage Magnitude
A21 Increase voltage on generator source until transfer Voltage Disturbance Generator Overvoltage Magnitude
Source Transfer tests
15 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
B. Protection Tests
Overload temperature trip
Tested onboard generator side load breakers
Inrush compatibility
Verified load breaker coordination with sudden current increase
Overloaded transfer test
Verified GL did not transfer to generator on overload
16 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Protection Tests (Cont.)
Designation Action Protocol Case Type Case
B1 Run above rated load on generator mode until trip Protection Overload Time
B2Energize generator with overload and utility offline; Utility Relay closed
Protection Overload Generator Blackstart A
B2BEnergize generator with overload and utility offline; Utility Relay open.
Protection Overload Generator Blackstart B
B3Transfer to generator while carrying a load above rated for generator mode
Protection Overload Transfer
B4Sudden, momentary, increase of load from rated to overload
Protection Inrush Test
Protection tests
17 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Time Trials
Transfer time from Utility to Standby
Standby Source: 25 kVA Transformer
Standby Source: 5 kW Gas Generator
Transfer time from Standby to Utility
Standby Source: 25 kVA Transformer
Standby Source: 5 kW Gas Generator
18 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Time Trials Results
Utility to 25 kVA Transformer
• Orange Unit = 14.2 Cycles (top)
• Blue Unit = 15.2 Cycles (right)
Orange Unit: Util to Gen - Xfmr
0
50
100
150
200
250
100 120 140 160 180 200 220 240 260 280 300
Time (in cycles)
Vol
tage
(in
RM
S V
olts
)
0
5
10
15
20
25
30
35
40
45
50
Cu
rren
t (i
n R
MS
Am
ps)
Vsource Vgen Vload Isource Igen Iload
Blue Unit: Util to Gen - Xfmr
0
50
100
150
200
250
300
100 120 140 160 180 200 220 240 260 280 300
Time (in cycles)
Vol
tage
(in
RM
S V
olts
)
0
5
10
15
20
25
30
35
40
45
50
Cu
rren
t (i
n R
MS
Am
ps)
Vsource Vgen Vload Isource Igen Iload
19 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Time Trials Results
Utility to 5kW Generator
• Orange Unit = 14.0 Cycles (top)
• Blue Unit = 14.8 Cycles (right)
Orange Unit: Util to Gen. - Honda
0
50
100
150
200
250
300
100 120 140 160 180 200 220 240 260 280 300
Time (in cycles)
Vol
tage
(in
RM
S V
olts
)
0
5
10
15
20
25
30
35
40
45
50
Cu
rren
t (i
n R
MS
Am
ps)
Vsource Vgen Vload Isource Igen Iload
Blue Unit: Util to Gen. - Honda
0
50
100
150
200
250
300
100 150 200 250 300 350 400
Time (in cycles)
Vol
tage
(in
RM
S V
olts
)
0
5
10
15
20
25
30
35
40
45
50
Cu
rren
t (i
n R
MS
Am
ps)
Vsource Vgen Vload Isource Igen Iload
20 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Time Trials Results
25 kVA Transformer to Utility
• Orange Unit = 75.5 Cycles (top)
• Blue Unit = 76.7 Cycles (right)
Orange Unit: Gen to Util Xfmr
0
50
100
150
200
250
150 170 190 210 230 250 270 290 310 330 350
Time (in cycles)
Vol
tage
(in
RM
S V
olts
)
0
5
10
15
20
25
30
35
40
45
50
Cu
rren
t (i
n R
MS
Am
ps)
Vsource Vgen Vload Isource Igen Iload
Blue Unit: Gen to Util - Xfmr
0
50
100
150
200
250
0 50 100 150 200 250 300 350
Time (in cycles)
Vol
tage
(in
RM
S V
olts
)
0
5
10
15
20
25
30
35
40
45
50
Cu
rren
t (i
n R
MS
Am
ps)
Vsource Vgen Vload Isource Igen Iload
21 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Time Trials Results
5 kW Generator to Utility
• Orange Unit = 75.0 Cycles (top)
• Blue Unit = 75.9 Cycles (right)
Orange Unit: Gen. to Util - Honda
0
50
100
150
200
250
300
100 120 140 160 180 200 220 240 260 280 300
Time (in cycles)
Vol
tage
(in
RM
S V
olts
)
0
5
10
15
20
25
30
35
40
45
50
Cu
rren
t (i
n R
MS
Am
ps)
Vsource Vgen Vload Isource Igen Iload
Blue Unit: Gen. to Util - Honda
0
50
100
150
200
250
300
100 120 140 160 180 200 220 240 260 280 300
Time (in cycles)
Vol
tage
(in
RM
S V
olts
)
0
5
10
15
20
25
30
35
40
45
50
Cu
rren
t (i
n R
MS
Am
ps)
Vsource Vgen Vload Isource Igen Iload
22 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Utility
House
Meter
DG
GenerLink™
Basic GenerLink
23 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Basic GridGateway
Utility
House
Meter
DG
GridGateway™CT
CT
200 A
30 A
GridGateway™
FCG
ICE
Disconnect SwitchDisconnect Switch
Internal Relay Internal Relay Interface Board Interface Board
Optional External Optional External Generator RelayGenerator Relay
Surge Protection Surge Protection BoardBoard
ConnectorConnectorfor Generatorfor Generator
What It Is
A device that provides a gateway connection with programmable protection for on-site generation systems operating in parallel with the grid or operating as an island
Benefits
Represents DG Interconnection Agreement btw end-user & utility
Utility adjustable protection parameters
Ability to periodically test and validate these parameters
Future utility communications and monitoring capability
7
GridGateway Development
Any DER
ConnectorConnectorfor Generatorfor Generator
Programmable Programmable Control Board Control Board
25 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
GridGateway Related Interface and Controls
Local Loads
GridGatewayGridGateway
DGDG
Reference
V/I Sense
V/ISense
Sense
Utility
GridGatewayGridGateway
DGDG
30A DG 30A DG RelayRelay
Relay Settings
Monitoring & Control
Sense
Sense
V
Trip/ Close
Trip/Close
200A Utility Relay200A Utility Relay
Meter
26 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Example Programmable Trip Settings
(GridGateway to have 18 programmable protective functions)
The primary functions of the device are to provide protection for the utility from incorrect operation of the DR and to provide a means for safely interconnecting a synchronized DR to the Utility/Residence circuit.
27 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Set up and Functional Control Responsibilities
• The GG handles any normal switching or paralleling functions, e.g. transfer, MBB or BBM, etc.
• Utility will use the laptop communication port and set up based on the application and input form end user. If end user changes the DG or Application utility reconfigures.
• End user has control to select "utility preferred" or "generator preferred," and can lockout either source via local circuit breakers.
• Eventually control wiring will be required between the GG and the DG for voltage regulator and governor control following standards for parallel interconnection.
• Potential for external supervisory control via GG, such as generator dispatch or load shedding is consideredin the logical design.
28 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
GridGateway Applications
0. Basic manual transferBasic manual transfer – starts with primary source closed, as default configuration for troubleshooting the unit (no protective functions)
1. Open transition transferOpen transition transfer - follows the Generlink functionality (break-before-make operation)
2. Closed transition transferClosed transition transfer - momentary paralleling in the range of 1 to 5 seconds for uninterrupted transfer applications (make-before-break operation)
3. Parallel operation rotatingParallel operation rotating generator - GG executes parallel connection, future synchronizing
4. Parallel operation inverterParallel operation inverter generator - GG allows inverter to synchronize and execute parallel connection
29 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Application State Diagram
No Connection Operating State
Load on DG Operating State
Paralleled DG and Utility Operating State
Load on Utility Operating State
2. Close DG Relay
1. Close Utility Relay
7. Open Utility Relay
6. Open Utility Relay
5. Open DG Relay
4. Close Utility Relay
3. Close DG Relay
8. Open DG Relay
P,QAMR
Applications 0 through 4,Monitoring & Firewall Functions
DG
Utility
L.M
Digital I/O lines (Future) for price signals, demand response, dispatching, etc5 outputs for
future load management
IO
Future governor regulator control
Microswitch for selection of preferred source
Relay
Relay
Communication interface for remote meter-reading, load control, etc
Metering Chip
Residential Load
CT
CT for DG power measurement
GUI (Utility-access only) for Configuration, setup
and Debugging
Future
Current
Gateway Functions and Features
GUI Tree
33 Copyright © 2005 EPRI Solutions, Inc. All rights reserved.
Residential Test Set up
• 200 A/240V Service and Various DG
• Residential Load Simulator
• Controllable 12kW Class D Amplifier for Simulation of utility and DG sources