Framework
for
Testing
Controlled copy Testing Framework
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 2 of 22
Table of Contents
1.0 Introduction 4
2.0 Definitions and Acronyms 5
2.1 Acronyms 5
2.2 Definitions 5
3.0 Purpose 6
What is not the intended use for the Framework? 6What then defines the process for the projects? 6How should the Framework be used? 6
4.0 Organization of the Framework 7
4.1 Section A – Process Disciplines 7
4.2 Section B – Standard PSPH 7
5.0 Section A - Process Disciplines 9
5.1 Test Requirements Study 9
5.1.1 Test Requirements Study (AWR) 9Scoping 9Requirements Gathering 9Identification of Estimation Methodology 9Estimation 9Business Process Understanding 10Application Understanding 10Tools Understanding 10Customer Testing Process Understanding 11Infrastructure requirements Understanding 11Customer Performance Baseline Collection 11Traceability matrix for Test Requirements 11Knowledge Transition to Offshore 12
5.2 Test Strategy 12
5.2.1 Test Strategy (AWR) 12Tool Evaluation and Selection (in case of automated testing) 12Testing Tools Installation (in case of automated testing) 12Proof Of Concept (in case of automated testing) 12Test Strategy formulation 13
5.2.2 Test Planning (AWR) 13Test Planning 13Receive requests from Customer 14Revisit Test Strategy 14
5.3 Test Design 15
5.3.1 Test Environment Setup (AWR) 15Test Environment Setup 15
5.3.2 Test Design (AWR) 15Test Design 15Test Data Preparation / Customization / Sampling / Manipulation 16
Controlled copy Testing Framework
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 3 of 22
5.4 Test Execution 17
5.4.1 Test Execution (AWR) 17Pilot Execution of Test cases 17Test Execution 17
5.5 Delivery 18
5.5.1 Delivery (AWR) 18Delivery 18Verification by Onsite team 18
5.6 Acceptance Testing 19
5.6.1 Acceptance Testing (AWR) 19Acceptance Test Plan 19Acceptance Test Procedure 19Assist in UAT Data Preparation 19Acceptance Testing 19Acceptance Sign – Off 20
6.0 Section B – Process Handbook (ETVX) 21
7.0 Section C – Measurements Applicable 22
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 4 of 22
Controlled copy Testing Framework
1.0 Introduction
This handbook describes the Cognizant Testing framework and applies to Projects executed by Cognizant delivery team as part of
1. Standalone projects taken up for any new/existing customer.
2. ODC engagement with existing customers,
This framework is organized as follows:
SECTION A – TESTING WORKFLOW
SECTION B – STAGES OF TESTING
ANNEXURES
Section A – Testing Workflow
The testing workflow refers to the logical group of tasks performed during the testing process. Logical grouping aims at grouping tasks that fulfill a common objective like System testing, Delivery etc.
A similar workflow exists for the Project Management process, which happens in parallel / overlaps with the testing workflow. (Refer to the Delivery Management Framework for more details)
Section B –Testing Process (ETVX Model/ OSSP)
Tasks in Testing workflow and Project Management workflow are fitted into the different stages of Testing operational model
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 5 of 22
Controlled copy Testing Framework
2.0 Definitions and Acronyms
2.1 Acronyms
NFR Non functional requirement
RFP Request For Proposal
SOW Statement of work
AWR Activity, Work Product, Responsibility
ODC Offshore Development Center
POC Proof of Concept
2.2 Definitions
ROLE The roles depicted here identify the skill background of the people doing the tasks. A Project team member could be playing more than one role. It is suggested that projects do a mapping of the roles to the team members accordingly
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 6 of 22
Controlled copy Testing Framework
3.0 Purpose
The primary purpose of this framework is to describe the testing related practices that are applicable to projects executed by Cognizant.
Where special guidelines are available, they have been referenced in the framework. It is recommended that such guidelines be read and understood entirely to have a complete understanding of the Testing Framework.
The practices that are mandatory for all projects and the practices that are optional for the projects are listed in separate boxes throughout the framework. An explanation of the legends is provided below:
What is not the intended use for the Framework?
The Framework cannot be considered to be the PSPH for the project. Understanding this is important, as the framework is not organized by Stages. It is rather organized by process disciplines. The Section B of the Framework contains references to PSPH, which defines the process to be adopted by the projects.
What then defines the process for the projects?
The Section B of the Framework contains references to PSPH, which defines the process to be adopted by the projects.
How should the Framework be used?
1. The Framework provides the basis on which all Operational life-cycle models are defined.
2. Additional operational life-cycle models needs to be arrived at using the Framework as the basis.
3. The Framework splits each of the tasks in the PSPH into further activities thus explaining how a task needs to be performed. Further references are provided to Testing guidelines that describe the Inputs, Outputs, and Tools & Techniques to be performed for each of these tasks.
Mandatory / Optional Discussions
Guidelines
Notes
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 7 of 22
Controlled copy Testing Framework
4.0 Organization of the Framework
This framework is organized as follows:
SECTION A – Standard Cognizant Process Disciplines
SECTION B – Standard PSPH for QSM defined Operational Life-cycle models
SECTION C – Measurements Applicable. This provides a reference to the DM Framework where Metrics Plan and Guidelines have been consolidated across Solution Offerings
4.1 Section A – Process Disciplines
This refers to the logical groups of tasks performed during the testing process. Tasks from a logical group could be split across several stages and the process discipline provides an approach to view information from a logical view.
If the project wished to understand the total effort spent on Acceptance Testing (for all the activities done as part of Acceptance Testing), it may not be possible only using stages as the plan for Acceptance Testing is done upfront in the project.
During the start of the project, the tasks are mapped to the chronological stages in the projects while the Process Discipline mapping is fixed, abstracted but available for reporting purposes.
4.2 Section B – Standard PSPH
Here the stages of Application development life cycle are depicted.
Framework
Standard Cognizant Process
Disciplines
Standard Cognizant PSPH
Tasks
Activities
Stages
Tasks
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 8 of 22
Controlled copy Testing Framework
Tasks from the various Process Disciplines are fitted into the different stages depending on the life-cycle model chosen for the project
Advantage of distinguishing Process Disciplines And Stages
1. Tasks can be looked upon as components, which can be plugged and played into different Stages of the project. The work products are tied to the tasks and the entry criteria and exit criteria of the stages would vary depending on how the tasks are interweaved.
2. Organizing tasks by process discipline and stages also helps in slicing and dicing project metrics and help in comparing one versus the other.
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 9 of 22
Controlled copy Testing Framework
5.0 Section A - Process Disciplines
5.1 Test Requirements Study
5.1.1 Test Requirements Study (AWR)
Scoping
Activity Work Products Responsibility
Define scope of testing (In Scope and Out of Scope)
Test Requirements Document
Account Manager / Senior Business Analysts
Identification of Estimation Methodology
Activity Work Products Responsibility
Evaluate Estimation methodologies
Estimation SheetProject Manager / Project Leader
Define Estimation methodology for testing
Estimation SheetProject Manager / Project Leader
Estimation
Activity Work Products Responsibility
Estimate for the total volume of work
Estimation Sheet (If Test Case Estimation: Test Case Estimation Document)
Project Leader
Requirements Gathering
Activity Work products Responsibility
Requirement gathering discussions and clarifications
Discussion notes /
CRAD
Business Analysts, Project Manager / Project Leader
Study of system Requirements Test Requirements
Document
Business Analysts, Project Manager / Project Leader
Documentation of software requirements and sign-off
Business Analysts, Project Manager / Project Leader
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 10 of 22
Controlled copy Testing Framework
Business Process Understanding
Activity Work products Responsibility
Understand and document the Application process
Testing KT Document Project Leader
Understand and document Technical aspects of the application
Testing KT Document Project Leader
Identify and define the customer performance baselines of the existing system
Customer Performance Baseline
Project Leader
Application Understanding
Activity Work products Responsibility
Understand the applications to be tested
Testing KT document Project Leader
Understand and document the interfaces to the application, if any
Testing KT document Project Leader
Understand the functionality impacts on other external interfaces
Testing KT document Project Leader
Tools Understanding
Activity Work products Responsibility
Understand if there are any tools used for testing in client’s place
Testing KT Document Project Leader
Understand the test script coding guidelines of the tool, if any
Testing KT Document Project Leader
Obtain Test Script Coding Guidelines and User Manual if any
Testing KT Document Project Leader
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 11 of 22
Controlled copy Testing Framework
Customer Testing Process Understanding
Activity Work products Responsibility
Understand and document the testing strategies used
Testing KT Document Project Leader
Understand and document the testing techniques used
Testing KT Document Project Leader
Understand and document the various outputs of the testing process (like Test Results, Test Cases etc.)
Testing KT Document Project Leader
Understand the gaps in the existing Test Process
Testing KT Document Project Leader
Infrastructure requirements Understanding
Activity Work products Responsibility
Understand and document the hardware / software environment that the application is running
Testing KT document Project Leader
Identify if there are any connectivity to be established
Testing KT document Project Leader
Customer Performance Baseline Collection
Activity Work products Responsibility
Identify if there are any Customer Performance Baselines set
Customer Performance Baseline
Project Leader
Traceability matrix for Test Requirements
Activity Work products Responsibility
List down the test requirements to trace it throughout the testing life cycle
Requirements Traceability matrix
Project Leader
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 12 of 22
Controlled copy Testing Framework
Knowledge Transition to Offshore
Activity Work Products Responsibility
KT of application systems, existing test process, infrastructure setup etc. to Offshore
- Project Leader
5.2 Test Strategy
5.2.1 Test Strategy (AWR)
Tool Evaluation and Selection (in case of automated testing)
Activity Work products Responsibility
Identify tools to be evaluated Test Tools Evaluation and Selection Report
Team Leads
Identify various evaluation parameters
Team Leads
Evaluate tools on the various parameters
Team members / Team Leads
Report findings Team members
Review findings Test Tools Evaluation and Selection review report
Team Leads
Finalize tool to be used Test Tools Evaluation and Selection Report
Team Leads
Testing Tools Installation (in case of automated testing)
Activity Work products Responsibility
Installation, Setup and customization of tools that are finalized for testing
Tools ready to use Project Leader / Team Leads
Proof Of Concept (in case of automated testing)
Activity Work products Responsibility
Refer Black-Box testing questionnaire and Performance testing questionnaire for evaluating various tools on Black-Box testing and Performance testing
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 13 of 22
Controlled copy Testing Framework
Proof of Concept in case of automated testing
Proof Of Concept Document Team Leads
Test Strategy formulation
Activity Work Product Responsibility
Determine the types of testing to be performed (Eg: Unit / Integration / System testing, Load Testing, Link Testing, Performance Testing etc.)
Test Strategy / Approach Document
Project Leader / Team Leads
Define testing methodology (Eg: Top-Down / Bottom-Up)
Define the risks involved and assumptions made in the project
Identify testing tools, if applicable (This section can be filled once the testing tool is finalized)
Define the testing approach / methodology to be followed in case of automated testing
5.2.2 Test Planning (AWR)
Test Planning
Activity Work products Responsibility
Types of Testing to be done are identified
Test StrategyProject Leader / Team Leads
The tasks for Test Planning are identified
Test Plan Project Leader / Team Leads
Test schedule is defined Project Leader / Team
1. Refer Test Strategy Guidelines for various types of testing that could be performed and various testing techniques
2. Refer Manual Testing Guidelines and Automated Testing Guidelines for the difference in the testing process
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 14 of 22
Controlled copy Testing Framework
Leads
Specific responsibilities are assigned to team members along with clear-cut deadlines
Project Leader / Team Leads
Preparatory activities are identified (Eg: acquiring special testing utility, hiring and training engineers etc.)
Project Leader / Team Leads
Test items are identifiedProject Leader / Team Leads
Additional needs, if any, are identified
Project Leader / Team Leads
Review Test Plan Test Plan review report Team Leads
Log Test Requests
Test Request Sheet and Tracking Sheet
Team members
Identify the Deadlines (Start Date and End Date) for the Test Request
Update Requirements Traceability matrix
Updated Requirements Traceability matrix
Team members
Receive requests from Customer
Activity Work products Responsibility
Receive requests from Customer
Test Request and Tracking Sheet
Team Leads / Team members
Revisit Test Strategy
Activity Work products Responsibility
Identify if Test Planning has brought in any changes to
Updated Test Strategy Project Leader
Requirements could come in two ways
1. Upfront Defined requirements
2. Adhoc requests which needs to be tracked
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 15 of 22
Controlled copy Testing Framework
the Test Strategy
5.3 Test Design
5.3.1 Test Environment Setup (AWR)
Test Environment Setup
Activity Work products Responsibility
Manual Testing
Setup System / Integration / Unit Test environment as applicable
Updated Test Strategy document
Team members
Setup System / Integration databases
Team Leads / Test DBA
Run scripts and populate the databases
Populated System / Integration database
Team Leads
Review System / Integration / Unit test environment
Test Environment review report
Team Leads
Automated Testing
Setting up the automated testing environment
Automated test bed Team Leads / Team members
5.3.2 Test Design (AWR)
Test Design
Activity Work products Responsibility
Manual Testing
Identify the type of testing Test Procedure with test cases
Team Leads/ Team members
Identify the scope of testing Team Leads/ Team members
Identify the pre-requisites for testing
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 16 of 22
Controlled copy Testing Framework
Identify the test scenarios for generating the test cases
Generate test cases based on the type and scope of testing
Define execution and verification procedures
Finalize environment data requirements
Build test suites, test drivers as needed for testing
Test Suites / Test Drivers
Team members
Review Test DesignTest Procedure review report
Team Leads
Update Requirements Traceability Matrix to include test specifications
Updated Requirements Traceability Matrix
Team members
Automated Testing
Prepare Test Scripts Test Scripts / Test Procedure
Team Leads / Team members
Review Test Scripts Reviewed Test Scripts Team Leads / Team members
Test Data Preparation / Customization / Sampling / Manipulation
Activity Work products Responsibility
Manual Testing
Prepare necessary test data for System / Integration / Unit Testing
Test environment ready with Test Data
Team members
Validate test dataTest environment ready with validated Test Data
Team Leads
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 17 of 22
Controlled copy Testing Framework
5.4 Test Execution
5.4.1 Test Execution (AWR)
Pilot Execution of Test cases
Activity Work products Responsibility
Manual Testing
Perform Pilot RunTest Logs Team members
Log Results
Analyze Results Pilot Run Results Report Project Leader / Client
Define Corrective action, if necessary
- Project Leader
Revisit Test Strategy, if necessary
Updated Test Strategy document
Project Leader
Test Execution
Activity Work products Responsibility
Identify the type of testing to be done -
Identify number of test runs from the test plan. -Team members / Team Leads
In every test run, Run test cases as per the test procedure and records results.
Test logs /As run logs (in case of Automated Testing)
If a test run fails altogether, because of an abortive functionality, then record the failure of the run as a whole (E.g. RUN N: ABORT M)
Record of disruption of Cycle completion in the test logs /As run logs (in case of Automated Testing)
Team members
Once the abortive failure is corrected, restart the Test Run and repeat for all the planned Test Runs
Test logs /As run logs (in case of Automated Testing)
Team members
Update Requirements Traceability Matrix to include test results
Updated Requirements Traceability Matrix
Team members
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 18 of 22
Controlled copy Testing Framework
5.5 Delivery
5.5.1 Delivery (AWR)
Delivery
Activity Work products ResponsibilityZip / Pack the testing documents (typically Test Plans, Test Procedures / Test Cases and Test Logs) for the tested module / requirements
Zipped file containing Test Plans / Test Procedures / Test Logs for the tested module
Project Leader / Team Leads
Prepare summary report for testing Summary ReportProject Leader / Team Leads
Verification by Onsite team
Activity Work products Responsibility
Deliverables verification by Onsite team
Verification mail from Onsite co-ordinator
Onsite Co-ordinator
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 19 of 22
Controlled copy Testing Framework
5.6 Acceptance Testing
5.6.1 Acceptance Testing (AWR)
Acceptance Test Plan
Activity Work products Responsibility
Plan for Acceptance Testing Acceptance Test Plan Customer and Cognizant
Acceptance Test Procedure
Activity Work products Responsibility
Determine Acceptance CriteriaTest Requirements Document
Customer and Cognizant
Identify Acceptance test scenarios Acceptance Test
Procedure
Customer and Cognizant
Define Acceptance Test Cases Customer and Cognizant
Assist in UAT Data Preparation
Activity Work products Responsibility
Prepare Acceptance Test DataAcceptance testing environment ready with test data
Customer and Cognizant
Acceptance Testing
Activity Work products Responsibility
Review and communicate any changes to the acceptance test plan
Updated Acceptance test plan
Client / Cognizant (S)
Get the acceptance test cases and review the same
Acceptance test cases Cognizant Delivery Manager
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 20 of 22
Controlled copy Testing Framework
Support during acceptance testing
Issue Resolution, Test logs from the client
Onsite coordinator / Delivery manager
Acceptance Sign – Off
Activity Work products Responsibility
Get Acceptance sign-off from customer
Formal mail from Client Customer
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 21 of 22
Controlled copy Testing Framework
6.0 Section B – Process Handbook (ETVX)
Testing Project Software Process HandBook
Release ID: QFTS-FW.doc / 1.01 / 05.03.2004 C3: Protected Page 22 of 22
Controlled copy Testing Framework
7.0 Section C – Measurements Applicable
Metrics Plan for Testing