Texas Artificial Reef Program 2015 Year in Review Texas Parks and Wildlife Department Artificial Reef Program J. Dale Shively 15 March 2016
Transcript
Page 1: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Texas Artificial Reef Program2015 Year in Review

Texas Parks and Wildlife DepartmentArtificial Reef Program

J. Dale Shively15 March 2016

Page 2: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in
Page 3: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Texas Artificial Reef Program by the Numbers

Over 4,800 Acres Permitted

Reef Sites: 77 Permitted / 10 Pending

149 Platform R2R Donations to Date Plus 12 Other Components

30 Platform R2R Donations in Progress

$25.2 Million Generated through Rigs-to-Reefs Program

Other Donations:

22 Vessels - Barges, Shrimp Boat, 2 Tugs, Tanker, Ships

> 7,000 Fabricated Materials - Concrete Reef Balls and Pyramids, Culvert, Utility Poles, Fly-Ash Blocks, Hatchery Troughs, MARAD Steel Buoy

700 Quarry Rock

Page 4: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Rigs-to-Reefs Program

Page 5: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in
Page 6: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

0

2

4

6

8

10

12

14

19

90

19

91

19

92

19

93

19

94

19

95

19

96

19

97

19

98

19

99

20

00

20

01

20

02

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Reefed Oil and Gas Platforms

Page 7: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Methods of Removal

• Topple in place

– Traditional method

– Rarely used anymore

Page 8: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Methods of Removal

• Tow– Most common– Used for

smaller structures

Page 9: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Methods of Removal

• Partial removal

– Preferred method for larger structures

Page 10: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

TPWD Oil & Gas Platform Removal Methods

Topple12%

Towed61%

Partial Removal27%

Page 11: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Sizes of Platforms in TPWD Program12-pile jacket

1%

3-pile jacket13%

4-pile jacket55%

6-pile jacket2%

8-pile jacket29%

Page 12: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Petroleum Structures in Texas Gulf

OCS Region Reef Sites Reefed Platforms

NORTH

High Island 40 81

Galveston 6 14

Brazos 5 9

Matagorda Island 5 11

Mustang Island 8 17

Padre North 4 3

Padre South 4 8

SOUTH

Page 13: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Reef Sites by Water DepthWater

Depth

(ft)

Reef Sites Structures

50 - 100 14 10

101 - 150 13 17

151 - 200 20 62

201 - 250 17 30

251 - 300 11 32

301+ 6 3

Page 14: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Quarry RocksConcrete Culverts

Reef Balls

Nearshore Reefs & Public Reefing Program

Bridges and Causeways

Reef Pyramids

Page 15: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Public Reef Development

Matagorda

Galveston

Proposed Nearshore Reefs

Boatmans / Lonestar

Matagorda

Lonestar / Boatmans

Matagorda

Big Man Reef

Sabine 2

Port Mansfield

Corpus Christi

Port O’Connor

Vancouver

Port Isabel

Rio Grande Valley

Sabine 1

Lonestar / Boatmans

Big Man Reef

Matagorda

Sabine 2

Page 16: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in
Page 17: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in
Page 18: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in
Page 19: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Freeport and Matagorda Nearshore Reefs

• NRDA (Natural Resource Damage Assessment) funded projects

• $5 million

• Contract awarded to Callan Marine

• Reefing slated for summer 2016

– Freeport Reef: 800 reef pyramids

– Matagorda Reef: 1,600 reef pyramids

• Production slow. ~ 100 pyramids completed to date

Page 20: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in
Page 21: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in
Page 22: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in
Page 23: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in
Page 24: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Ships-to-Reefs

• 1960s: 3 Barges

• 1970s: 12 Liberty Ships,

T2 Tanker – V.A. Fogg

• 1980s: Barge

• 1990s: Tugboat, Navy Barge

• 2000s: Tugboat, Hopper Barge, Shrimp Boat, 473’ Texas Clipper, 155’ MV Kinta S

Page 25: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

M/V SCM Fedra

Page 26: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Biological Monitoring Methods• Roving Fish Census

• Decompression diving

• Lionfish removal

• Water quality

• Video transects

• Vertical long lines

• Photo documentation

• Biological sampling

Page 27: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Monitoring Events and Contracts

UTRGV (2007 – present)• Padre South protraction region

• Diving surveys, biofouling, sidescan and multibeam surveys, economic impact study

TAMU - Corpus Christi (2011 – present)• Numerous platform sites in the Mustang and

Matagorda protraction regions

• Diving surveys, tagging surveys, vertical longline, remote operated vehicle surveys, etc

• Scuba diving socio-economic impact study

TAMU - Galveston (2011 - present)• Vancouver archeological survey

• Bottom surveys and bathymetry, biological monitoring, multibeam surveys

TAMU - College Station(2013-2014)• Socio-economic survey of anglers and boaters

USGS (2013-present)• Offshore water quality survey

• Nearshore AUV, water quality, substrate survey

Page 28: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Reaching Out . . .

• TAMUG: 2013 – 2014 survey of anglers and boaters using TPWD license system for boats ≥ 27ft

• TAMUCC: Diver survey completed 2015

Page 29: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

So How Important are Artificial Reefs in Texas?

• 2013-14 TAMU-College Station Survey of Licensed Boat (>26ft) Owners (7,000 boat owners)

– Reef users were white males, 57 years old, with annual income >$160,000

– 62% took a trip into GOM in last 12 months, 70% to fish on TPWD reefs

– Average trip cost = $1,652 per person

Page 30: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

So How Important are Artificial Reefs in Texas?

• 2014-15 TAMU-CC Survey (55 dive shops and 508 divers)

– Average Texas Diver is a male 34-44 years old, 4 yrBachelor’s degree, annual income of >$70,000, lives in Corpus Christi

– Average trip cost to dive Gulf only = $1,173

Page 31: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

So How Important are Artificial Reefs in Texas?

– Total coastal county economic impact from diving:

• Flower Gardens Banks National Marine Sanctuary only = $2.4m

• Gulf diving only = $2.5m

• Combined freshwater and saltwater diving in TX = $23m

Page 32: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

So How Important are Artificial Reefs in Texas?

– Conclusion:

– “I don’t know much about the artificial reef program”

– “The best diving in Texas is Mexico”

Page 33: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

TPWD Artificial Reef Program Partners

• Coastal Conservation Association

• Recreational Fishing Alliance

• Saltwater fisheries Enhancement Association

• Matagorda, Brazoria County Government

• Port Mansfield Reefing Community

• Reef-Man, LLC

• Cities of Corpus Christi and South Padre Island

• Friends of Rio Grande Valley Reef

Page 34: Texas Artificial Reef Program 2015 Year in Revie Artificial Reef...12-pile jacket 1% 3-pile jacket 13% 4-pile jacket 55% 6-pile jacket 2% 8-pile jacket 29% Petroleum Structures in

Public Outreach & Information

www.facebook.com/TexasParksAndWildlifeArtificialReefProgram

tpwd.texas.gov/landwater/water/habitats/artificial_reef/

Direct link to Interactive map-tpwd.texas.gov/artificialreefs