June 9th, 2008TPTF
Texas Nodal Program:Market Readiness Metrics Update
Mike Beck
2Texas Nodal Program UpdateJune 9th, 2008 2
Agenda
• Status Update– ERCOT Staff Readiness– Market Participants– EDS
• Cycle 4 Survey Update
• Action Items from May 22nd TPTF Meeting
• Metric Revisions/Interpretations
• Appendix (see separate file)
3Texas Nodal Program UpdateJune 9th, 2008 3
Status Update
There have been positive and negative changes since the last meeting:
ERCOT Staff Readiness: green amber (–)
Market Participant Readiness: red amber (+)
UPDATE CLOSER
TO THE DATE
4Texas Nodal Program UpdateJune 9th, 2008 4
Status Update: ERCOT Staff Readiness
• Engagement (green)• New survey results came out at the end
of May - ERCOT remains fully engaged
• Training (amber)• completion target is August 31, 2008• 3 departments in the IT division are
behind scheduled training levels
• Process (green)• updated weekly• completion target is August 31, 2008
• Staffing (amber)• RAG rule based on June 1st date
(requires >95% staffing for green status – ERCOT is currently ~92% staffed)
• recruitment is ongoing
• Testing (green)• no recent developments
ERCOT Staff readiness status is AMBER
5Texas Nodal Program UpdateJune 9th, 2008 5
Status Update: Market Participants
• Engagement (>95% green)• will be updated June 12th when Cycle 4 Survey
is scored
• Connectivity (>95% green)• no change
• Registration and Qualification (amber)• MP10 (Resource Mapping)
• ~12 resource entities still need to submit initial data (as of 5pm 6/3/08)
• MP11 (RARF Submissions)• ~99.5% of MWs have been reported
(as of 5pm 6/3/08)• Both MP10 and MP11 are amber based on new
interpretations of the metrics (see next slides)
• Telemetry (green)• no change
• Training (>95% green)• will be updated June 12th when Cycle 4 Survey
is scored
• Trials Participation (>95% green)• no change
Market Participant readiness status is AMBER, driven by MP10 and MP11
6Texas Nodal Program UpdateJune 9th, 2008 6
Market Participants: MP10 Metric Interpretation
MP10 (Mapping of Resources to Resource Nodes and Resources to EPS Meters) has been interpreted as Amber based on a review of completion dates and the RAG rules for Target 1
Target 1 Target 2
Criteria Feb. – March 2008 goal:
100% Resource to Node/EPS meter mapping; QSEs to ensure REs provide email acceptance of mapping
June – July 2008 Goal:
100% Resource to Node/EPS meter mapping; QSEs to ensure REs certify acceptance of mapping
Completion Date EDS 2 Release 4 completion(Network Model Verification)
168 Hour-Test Start less 45 days(was July 15 – date will change)
RAG Rules Green: Complete
Amber: Not complete, <1 mo. past target
Red: Not complete, >1 mo. past target
Green: Complete
Amber: Not complete, <1 mo. past target
Red: Not complete, >1 mo. past target
Status Approx. 12 REs have not submittedApprox. 21 REs need to modify data
N/A (still on Target 1)
Interpretation AmberEDS 2 Release 4 is not yet complete, therefore no one can be red
N/A (still on Target 1)
7Texas Nodal Program UpdateJune 9th, 2008 7
Market Participants: MP11 Metric Interpretation
MP11 (Registration Activities) has been interpreted as Amber based on a new interpretation of the RAG rules and the fact that submitted RARFs represent close to 100% of MWs in the market
Sept 2007 and Nov 2007 Targets
April 2008 Target
Criteria No longer relevant • Individual REs will be measured on successful completion of RARFs• Market will be measured by % received• As of May 1 all incomplete forms will be considered red
Completion Date No longer relevant EDS Trial Participation Milestone plus 14 days
RAG Rules No longer relevant MPs
Green: All forms received
Amber: Incomplete form
Red: Failure to submit documentation
Market Segment
Green: Meeting criteria
Amber: Within 10% of criteria
Red: Not meeting criteria
Status No longer relevant RARFs received represent 99.5% of the modeled MWs
Interpretation --- Since essentially 100% of the MWs are represented in submitted RARFs status is reported as amber
8Texas Nodal Program UpdateJune 9th, 2008 8
Status Update: Wall of Shame
The following Resource Entities are RED for MP11 (Registration Activities), meaning they have not submitted a completed RARF at this time
• Texas Big Spring (Gen.)
• Post Wind Farm (Gen.)
• Capricorn Ridge Wind (Gen.)
• Capricorn Ridge Wind II (Gen.)
• Eagle Energy Partners (Load)
• Bass Enterprises Production (Load)
9Texas Nodal Program UpdateJune 9th, 2008 9
Status Update: EDS
• EDS 1 (green) no changes
• EDS 2 (red) monitoring telemetry data from MPs to ensure data is of the quality needed for the state estimator
to converge within the TAC approved tolerances progress made with EMO12 (Network Operations Model and SE Performance)
Initially there were 338 unobservable buses - now there are only 80continuing to work with TSPs to fix remaining issues
• EDS 3 (amber) successfully completed EMO6 (QSE Response to Dispatch)
• EDS 4 (red) waiting on EMS 5 delivery to proceed with EMO3 (Verify Outage Evaluation System Functionality) working with MPs to connect to new hardware to satisfy N2.2 (ERCOT Telemetry/ICCP System Failover)
EDS status remains unchanged since the last meeting
10Texas Nodal Program UpdateJune 9th, 2008 10
Cycle 4 Survey Update
• Updates to the Cycle 4 Survey can be submitted using the excel form found on the metrics website (same process as previous surveys)
• ERCOT Account Managers will continue their outreach efforts to MPs who were non-responsive to the Cycle 4 Survey or who reported negative answers
• Cycle 4 Survey Data will be reported on the scorecards on June 12th
• Metrics MP1 (engagement), MP12 (EDS 3 related training), MP13 (EDS 4 related training), and MP19 (LSE engagement) will be impacted by this survey
– Limited response so far; may impact overall MP status at next TPTF meeting
Survey Monkey has closed for the Cycle 4 Self-Reported Survey
11Texas Nodal Program UpdateJune 9th, 2008 11
Action Items
• Communication with QSEs– Red Status: updates done on a consistent schedule, email for Wall of Shame only– Wall of Shame: email prior to publication, chance to remedy/contact us (complete)
• Resource Entities– Wall of Shame: as shown for MP11; not linked to QSEs– Access to RE data/forms: ERCOT cannot intervene, but MPs can solicit
• MP11– Scoring (Market Segment) Interpretation: previously described– QSE Exclusion from EDS Testing (i.e., LFC): only the non-responsive REs will be excluded– RARF Data Review Plan: Dana to discuss later today
• MP10 – Reporting: Dana to discuss later today
• EDW – Extracts Delay: Delay is 5 weeks due to limited testing space
At the last TPTF meeting there were several items we committed to research and to report on, including:
12Texas Nodal Program UpdateJune 9th, 2008 12
Metric Revisions and Interpretations
Reasons for revisions include the following:
• Inaccurate Target Completion Dates
– E7, E10, E11…
• Metric Categorization
– CRR2, CRR4…
• RAG Rules
– MP14, MP15, MP16…
• Phase 2, Further Testing
– MP10, MP11…
Anticipated nodal program schedule modifications provide the opportunity to review all metrics to ensure a consistent application of status criteria
13Texas Nodal Program UpdateJune 9th, 2008 13
Questions ?