+ All Categories
Home > Documents > Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Date post: 25-Feb-2016
Category:
Upload: jela
View: 26 times
Download: 0 times
Share this document with a friend
Description:
Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project. Dallas Horseshoe Project Overview. Margaret McDermott Bridges. Proposed Construction. Upgrade roadway geometry Replace I-30 and I-35E bridges over Trinity River Construct additional lanes - PowerPoint PPT Presentation
Popular Tags:
20
Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project
Transcript
Page 1: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Texas Transportation Commission Meeting

November 15, 2012

Item 3.

Dallas Horseshoe Project

Page 2: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Dallas Horseshoe Project Overview

Margaret McDermott

Bridges

Proposed Construction

• Upgrade roadway geometry• Replace I-30 and I-35E bridges

over Trinity River• Construct additional lanes• Construct Margaret McDermott

Bridges

Page 3: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

3

Purpose and Need

Margaret McDermott

Bridges

Proposed ConstructionRanked the 7th most congested

roadway in Texas in 2011 –Weekday volume exceeds 460,000

Page 4: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Margaret McDermott

Bridges

Proposed Construction

4

Purpose and Need

Bridge Deterioration

Page 5: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Horseshoe Project Configuration

(Eastbound at Jefferson Street)

Existing

Proposed

Plus the Calatrava-designed Margaret McDermott Bicycle/Pedestrian Bridges

Proposed Lanes

Existing LanesRampCollector-DistributorFrontage Road General Purpose Lanes HOV Lanes

Page 6: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Margaret McDermott Bridges

Page 7: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Dallas Horseshoe Project Funding

$100,755,000 PROP 12 P2 PE/ROW$ 87,104,000 PROP 12 P2 TMA$400,500,000 PROP 12 P2 Bridge$ 10,000,000 PROP 12 P1$ 13,300,000 PROP 14$ 21,450,000 SH 121 Regional Toll Revenue$106,375,987 Cat 10 HPS/DEMO Earmarks$ 75,000,000 Cat 6 Federal Bridge$ 4,450,000 Cat 7 STP-MM $818,934,987 Total Funding

Page 8: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Procurement History

• December 9, 2011 – RFQ released

• January 9, 2012 – Industry Workshop

• March 29, 2012 – Three firms shortlisted

• July 3, 2012 – Final RFP issued to shortlisted firms

• May 23 – August 17, 2012 – One-on-One meetings

• September 25, 2012 – Technical Proposals received

• October 8, 2012 – Financial Proposals received

Page 9: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Shortlisted ProposersDallas Horseshoe Solutions:Equity Members

• Granite Construction Company • CH2M Hill Engineers, Inc. • Traylor Bros., Inc.

Non-equity Members• Infrastructure Corporation of America• Excelsis, Inc.• Pavetex Engineering and Testing, Inc.• Kimley-Horn & Associates, Inc.• Cobb Fendley & Associates, Inc.

• Alliance Geotechnical Engineering• Structural Engineering Associates• Landtech Consultants, Inc.• Summit Engineering, Inc.• VAK Construction Engineering

Services, LLC

Page 10: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Shortlisted ProposersNorthGate Horseshoe Constructors JV:Equity Members

• Kiewit Infrastructure Group Inc. • Zachry Construction Corporation

Non-equity Members• Parsons Transportation Group, Inc.• Lamb-Star Engineering, L.P.• Kiewit Offshore Services, Ltd.• Halff Associates, Inc.• Civil Associates, Inc.• Terracon Consultants, Inc.• HVJ Associates, Inc.• The Transtec Group, Inc.• Hayden Consultants, Inc.

• IEA, Inc.• Mandy Vassigh Engineering, Inc.• Maldonado-Burkett Intelligent

Transportation Systems, LLP• e. Construct USA, LLC• CP&Y, Inc.• Delcan• VRX, Inc.• SRLS Texas, LLC

Page 11: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Shortlisted ProposersPegasus Link Constructors:Equity Members

• Fluor Enterprises, Inc. • Balfour Beatty Infrastructure, Inc.

Non-equity Members• Parsons Brinckerhoff, Inc.• Transfield Services North America,

Transportation Infrastructure• AECOM Technical Services, Inc.• American Bridge Company• Raba Kistner Infrastructure, Inc.• Kleinfelder Central, Inc.• K-Strategies Group LLC• Pinnacle Consulting Management

Group, Inc.• STL Engineers

• MBK Engineers• Surveying and Mapping, Inc.• Maldonado-Burkett Intelligent

Transportation Systems, LLP• Rios Engineering, LLC• EJES, Incorporated• IEA, Inc.• Aguirre & Fields, LP• David Mason & Associates of Texas,

LLC• AMEC Environment & Infrastructure,

Inc.

Page 12: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Evaluation of Proposals

• TxDOT implemented a pre-established and rigorous evaluation procedure to select the proposal that offers the best value

• Separate pass/fail, technical and financial evaluations• Evaluation subcommittees provided scoring

recommendations to Evaluation Selection Recommendation Committee (ESRC)

• ESRC provided scoring recommendations to Project Steering Committee

Page 13: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Best Value scoring based on price, schedule, and technical factors:

Component Point ValuePrice 70(includes discount for early completion)

Technical Solutions 15Project Management Plan 12Quality Management Plan 3Total 100

Scoring of Proposals

Page 14: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

14

Results

Detailed Evaluationswere completed

resulting in……….

Page 15: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Results (cont.)

Pegasus Link Constructors• Fluor Enterprises, Inc. • Balfour Beatty Infrastructure, Inc.

is recommended to the Texas Transportation Commission as providing the best value

Page 16: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

16

Results (cont.)• Pegasus Link Constructors ……………91.72 pts

• Fluor Enterprises, Inc. • Balfour Beatty Infrastructure, Inc.

• Dallas Horseshoe Solutions …….……86.50 pts• Granite Construction Company • CH2M Hill Engineers, Inc. • Traylor Bros., Inc.

• NorthGate Horseshoe ….……………...83.14 pts• Kiewit Infrastructure Group Inc. • Zachry Construction Corporation

Page 17: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

• Design & Construction $718,741,351

• Capital Maintenance (years 1-5) $ 11,641,090• Capital Maintenance (years 6-15) $ 23,208,005 Total Contract $753,590,446

17

Best Value Price

Page 18: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Estimated Best Value

• Design-Build $738.8M $718.8M• Row/Utilities/Etc. $ 79.2M $ 79.2M

$818.0M $798.0M

18

Page 19: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Next Steps

• Negotiate final terms of DBA and CMA• FHWA concurrence with award• Execution of the DBA and CMA• Start construction in early 2013• Complete construction in approximately

4 years

Page 20: Texas Transportation Commission Meeting November 15, 2012 Item 3. Dallas Horseshoe Project

Questions

Staff recommends and requests your approval of this minute order.


Recommended