X. Wu, Cyclotrons 2010, 09/09/2010, Slide 1
The Accelerator System for ReA3 – the New Re-accelerated RIBs Facility at MSU
XiaoyuXiaoyu WuWuNational Superconducting Cyclotron LaboratoryNational Superconducting Cyclotron Laboratory
Michigan State UniversityMichigan State Universityon behalf of the NSCL ReA3 teamon behalf of the NSCL ReA3 team
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 2
Acknowledgements
• Accelerator R&D – O. Kester– F. Marti– M. Doleans– C. Compton– W. Hartung– L. Popielarski– J. Popielarski– J. Wlodarczak– Q. Zhao– C. Benatti– G. Perdikakis
• Mechanical Engineering– D. Lawton– J. Ottarson– M. Johnson– J. Wenstrom
• Nuclear Physics– D. Bazin– G. Bollen– S. Schwarz– J. Yurkon– F. Montes
• Facility/Operation– D. Sanderson– A. Zeller– S. Chouhan– J. Bierwagen– S. Bricker– N. Verhanovitz– M. Portillo– J. Delauter– P. Miller– G. Machicoane– D. Cole
• Electronics– J. Vincent– K. Davidson– N. Usher– K. Holland
• Special thanks to B. Laxdal and colleagues from TRIUMF
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 3
Production of RIBs by Projectile Fragmentation at NSCL
ReA3
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 4
NSCL Present Facility Layout
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 5
Facility for Rare Isotope Beams (FRIB)
•>200 MeV/u for all ions •400kW •Superconducting driver linac•Three-stage fragmentation separator•Successfully passed DOE CD-1 review•To be completed in ~2018
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 6
ReA3 Connections to CCF and FRIB
• ReA3 will be operated as a radioactive beam reaccelerator for the Coupled Cyclotron Facility in the coming years
• ReA3 will be operated as a radioactive beam reaccelerator for FRIB once the FRIB driver linac is operational and replaces the coupled cyclotrons
• ReA3 shares similar technology as the FRIB driver linac– Low energy beam lines for ion beams– RFQ– SRF linac
• ReA3 will provide valuable experience to FRIB for tuning strategies, particularly for SRF linac phasing strategy and development of beam tuning applications
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 7
Modern ion linac:• LEBT with multi-harmonic buncher• Radio frequency quadrupole (RFQ) • Superconducting RF linac• HEBT with rebuncher
Higher energies for lighter ionsMinimum energy spread 1keVMinimum pulse length 1 ns
12 keV/u
238U 0.3 – 3 MeV/u48Ca 0.3 – 6 MeV/u
600 keV/u
ReA3 platform
EBIT charge breeder
RFQ
SRF-linac
HEBT
LEBTQ/A-Separator
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 8
SRF
EBITQ/A
RFQ
ReA3 platform
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 9
ReA3 hardwareEBIT Charge Breeder
Q/A Separator
LEBT RFQ
SC Linac
HEBT
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 10
ReA3 ReA3 –– EBIT charge breederEBIT charge breeder
• Unique features:– Continuous injection of ions
» high capture rate– Variable extraction duty cycle
» μs pulse to quasi-continuous– Short breeding time (<10 ms)– High efficiency
> 50% in a single charge state
EBIT installation will be completed in October,Simulations are performed to optimize performance,Injection tests end of 2010!
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 11
Achromatic Q/A-separatorB
eam
fro
mEB
IT
Energy collimationslit
Mass separationslit
Resolvingpower > 100
Resolvingpower > 100
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 12
Low energy beam transport (LEBT)
Stable Ion Source(4He1+)
Multi-harmonic buncher
Triple-Bender
E-Quads
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 13
Beam Diagnostics (LEBT)Bunch length
monitor
RFQ
Faraday cupCaF viewer
45 deg. slit
MCP viewer
Attenuators
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 14
Emittance Scans
• RFQ transverse acceptance >– εn = 1.0 π-mm-mrad– εg = 200 π-mm-mrad (@ RFQ input energy of 12 keV/u )
• Desired twiss parameters α = 0.6 and β = 0.06 m– Measured beam emittances fit into RFQ transverse acceptance
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 15
RT 4RT 4--rod RFQrod RFQ
tuningplate
stemrods(milled fromCu profiles)
New design:Al-tank (no copper plating required)Simple adjustment of tuning plates,no alignment requiredHigh power operation
New design:Al-tank (no copper plating required)Simple adjustment of tuning plates,no alignment requiredHigh power operation
RFQ installed in beam line,Conditioning started,Beam tests in September 2010!
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 16
ReA3 SRF-cryomodules
ReA3 -• 3 ReA3 Cryomodules• 15 cavities• 2 cavity types (QWR)
– Beta=0.041 & 0.085– Same as FRIB design
• 8 solenoids– Same as used in FRIB
First two cryomodulescompleted,third in progressto be completed Q2FY2011
re-buncher β = 0.041 module β = 0.085 module
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 17
SRF-LINAC infrastructure
Clean rooms
Lead shield
diagnostic boxes
C.K. Gelbke, 9/15/2010, Slide 18
Building cryomodules!
Vacuum Vessel ReA3 design
Thermal Shield
CryogenicDistribution System
Cold-massReA3 Cryomodule
Clean room assemblyClean room assembly
of cold mass required!of cold mass required!
Performance tests of cavitiesPerformance tests of cavities
and solenoids.and solenoids.
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 19
ReA3 – QWRs testing β o
pt=
0.0
41
β opt
=0
.08
5
0 10 20 30 40 50 60Ep (MV/m)
108
109
1010
Q0
SC236 (BB)SC240 (Ja)SC241 (Ch)SC237 (Fr)SC243 (Dr)SC245 (Nm)SC244 (PH)
ReA3 FRIB
3180110-002
0 8 16 24 32 40 48Ep (MV/m)
108
109
1010
Q0
Generation1st (RIA)2nd (SC247 Jk)
ReA3 FRIB
3180710-022
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 20
ReA3 High Energy Beam Transport (HEBT)
Beam dynamics design completedMechanical design ofS-bend completedMagnets in productionCompleted end of 2010
Beam dynamics design completedMechanical design ofS-bend completedMagnets in productionCompleted end of 2010
ReA3 Platform
Beam dynamics design completed
Design of Re-bunchercryomodule started
Completed end of 2011
Beam dynamics design completed
Design of Re-bunchercryomodule started
Completed end of 2011
β=0.041 QWRRe-buncher
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 21
ReA3 Facility Layout
ReA3 Platform
SC Linac
EBIT
Q/A SeparatorLEBT+RFQ
HEBT
ReA3 Experimental Hall
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 22
Strong interests using ReA3 RIBs for nuclear astrophysics experiments
AT-TPCANSENSeGACAESAR
JENSASECAR
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 23
ReA3 Beam Simulations
0 5 10 15 20 25 30 35 40 45 500
1
2
3
4Energy
Z (m)
Ek
(MeV
/u)
0 5 10 15 20 25 30 35 40 45 500
10
20
30
40Beam Envelope
Z (m)
Rm
ax (m
m)
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 24
ReA3 Beam Simulations
0 5 10 15 20 25 30 35 40 45 500
0.1
0.2
0.3
0.4Longitudinal rms emittance
Z (m)
Erm
s(z)
(pi k
eV/u
-ns)
0 5 10 15 20 25 30 35 40 45 500
1
2
3
4Longitudinal 99.5% emittance
Z (m)
E99
5(z)
(pi k
eV/u
-ns)
0 5 10 15 20 25 30 35 40 45 500
0.1
0.2
0.3
0.4Transverse rms emittances
Z (m)
Erm
s(x/
y) (p
i mm
-mra
d)
Erms(x)Erms(y)
0 5 10 15 20 25 30 35 40 45 500
0.5
1
1.5
2Transverse 99.5% emittances
Z (m)
E99
5(x/
y) (p
i mm
-mra
d)
E995(x)E995(y)
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 25
ReA3 Beam Simulations
-10 -5 0 5 100
200
400
600
800
1000Horizontal plane
X (mm)
N
-10 -5 0 5 100
200
400
600
800
1000Vertical plane
Y (mm)
N
-1 -0.5 0 0.5 10
500
1000
1500
2000Bunch length
Time (ns)
N
-2 -1 0 1 20
500
1000
1500
2000Energy spread
dEk (keV/u)
N
-10 -5 0 5 10-10
-5
0
5
10Horizontal Phase Space
X (mm)
Px
(mra
d)
-10 -5 0 5 10-10
-5
0
5
10Vertical Phase Space
Y (mm)
Py
(mra
d)
-10 -5 0 5 10-10
-5
0
5
10Real Space
X (mm)
Y (m
rad)
-40 -20 0 20 40-0.4
-0.2
0
0.2
0.4Longitudinal Phase Space
Phase ([email protected])
DW
/W (%
)
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 26
ReA3 to ReA6 Upgrade
β=0.041QWRRe-buncher
β=0.085 QWRRe-buncher
β=0.085 QWRAcceleratingCryomodule
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 27
ReA6 Facility Layout
HEBT
ReA3 Platform
EBITSC Linac
LEBT+RFQQ/A Separator
ReA3 Experimental Hall
HEBT
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 28
ReA3 SRF LINACon platform
ReA6 to ReA12 Upgrade
β=0.085 QWRRe-buncher
β=0.085 QWR AcceleratingCryomodule
ReA6 ReA12
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 29
Re-Accelerator Energy Increase with Additional Cryomodules
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 30
NSCL Pre-FRIB (2016) Facility Layout
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 31
Fast, Stopped, and Re-accelerated RIBsat NSCL with FRIB
RIBs from FRIB
X. Wu, Cyclotrons 2010, 09/09/2010, Slide 32
Summary ReA3 status
Test of EBIT electron beam system done, magnet commissioned,assembly ongoing first operation October
Q/A-separator beam commissioning completed
LEBT beam commissioning is presently performed
RFQ tuning completed, conditioning ongoing, firstbeam tests in early September 2010
SRF-linac:− re-buncher rf-tests completed, first beam tests in conjunction with
RFQ beam commissioning− β = 0.041 module installed, hardware tests are being performed− β = 0.085 under constructionAccelerated stable beams end of 2010
Reaccelerated beams in 2011