+ All Categories
Home > Documents > The Basic Reliability Calculations

The Basic Reliability Calculations

Date post: 02-Apr-2018
Category:
Upload: abdulyunus-amir
View: 223 times
Download: 0 times
Share this document with a friend

of 30

Transcript
  • 7/27/2019 The Basic Reliability Calculations

    1/30

    Definition

    Reliability is a general quality of an object an ability toperform a desired function, sustaining the values of rated

    operational indicators in given limits and time according to

    given technical conditions.

    Reliability is probability that an activity of an appliance ingiven time and given operation conditions will be adequate

    to its purpose.

    EIA (Electronic Industry Association, USA)

    The Basic Reliability Calculations

  • 7/27/2019 The Basic Reliability Calculations

    2/30

    Reliability Calculations

    1. Reliability of single parts of networks in the time of

    production of project documentation

    2. Reliability of already operated networks

    3. Reliability in the area of control of electric power

    system operation

  • 7/27/2019 The Basic Reliability Calculations

    3/30

    failure rate [ year-1]

    mean time of failure [ h ]

    probability of failure-free run R [ - ]

    probability of failure Q [ - ]

    mean time between failures tS [ h ]

    Restored x Notrestored objects

    Mean time between failures x Mean time to failure

    Numerical Representation of Reliability

    (Classical - reliability of elements)

  • 7/27/2019 The Basic Reliability Calculations

    4/30

    Global Indices of Reliability

    Outage rate - SAIFIaverage system outage rate

    (number of outages/year/consumer)

    Total time of all outages - SAIDIaverage system outage time

    (min/year/consumer)

    Time of one outage - CAIDIaverage outage time at a customer

    (min/outage)

    (Reliability of electric energy supply)

  • 7/27/2019 The Basic Reliability Calculations

    5/30

    Bathtub curve

    I II III t

    Early failure

    period Constant failure rate periodWear-out failure

    period

  • 7/27/2019 The Basic Reliability Calculations

    6/30

    The relation between the function of reliability and

    failure rate is:

    For failure rate it is valid:

  • 7/27/2019 The Basic Reliability Calculations

    7/30

    Division of Probability of FailureExponential division

    Exponential rule of failure

  • 7/27/2019 The Basic Reliability Calculations

    8/30

    Poissons division

    Weibulls deal

    If k = 0, there is probability of no failure, therefore probability of failure-freerunning.

  • 7/27/2019 The Basic Reliability Calculations

    9/30

    Obtaining of input values for reliability calculations

    Calculation of Reliability in Electricity

    Industry

    A priori reliability determination of reliability quantities from data of a producer.

    Empirical reliabilitymonitoring of failures in electricity industry.

    The empirical method is mostly used for obtaining the input values for reliabilitycalculations, because an application of a priori reliability method requires different

    attitude to every element of electricity system.

  • 7/27/2019 The Basic Reliability Calculations

    10/30

    Analysis of Distribution Network Failure Databases

    Exclusive outage databases had been on the rise since 1975 in theformer Czechoslovakia.

    Unfortunately, database building stopped in1990 because of politicaland social changes.

    Thanks to the expert group CIRED Czech distributors opted forunified monitoring of global reliability indices and the reliability ofselected pieces of equipment in 1999 again.

    Data for the reliability computation is centrally processed andanalyzed at the VSB - Technical University of Ostrava since the year2000.

    Collected data are often heterogeneous. It is necessary to solve the storage, indexing, and also transformation

    of such data.

    We need to create a common relational scheme for the storage of the

    data, a new relation makes the querying and analysis possible.

  • 7/27/2019 The Basic Reliability Calculations

    11/30

    Database range

    Region1 Region2 Region3 Region4 Region5 Region6 Region7 Region82000 - - - 1 - 12 - - 1 - 12 1 - 12

    2001 1 - 12 - 1 - 12 1 - 12 - 1 - 12 1 - 12 1 - 12

    2002 1 - 12 - 1 - 12 1 - 12 - 1 - 12 1 - 12 1 - 12

    2003 1 - 12 - 1 - 12 1 - 12 - 1 - 12 1 - 12 1 - 12

    2004 1 - 12 - 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12

    2005 - - 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12

    2006 - 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12 1 - 122007 - 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12

    2008 - 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12

    2009 - 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12 1 - 12

  • 7/27/2019 The Basic Reliability Calculations

    12/30

  • 7/27/2019 The Basic Reliability Calculations

    13/30

  • 7/27/2019 The Basic Reliability Calculations

    14/30

    Heterogeneous Data

    We developed a common relational schema.

    Order Attribute Description

    1 Distribution company Unique number of a distributor

    2 Outage identification Unique number of an outage

    3 Outage type Accidental, planned or forced

    4 Distribution point Type of substation: single, double busbar substation, . . .

    5 Distribution area Specification of the location

    6 Network type Insulated system, resonant grounded neutral system, . ..

    7 Network voltage 0.4 kV, 22 kV, . . .8 Equipment voltage 0.4 kV, 22 kV, . . .

    9 Original outage identification Unique number of the outage cause

    10 Outage cause Foreign influences, causes before starting operation, . . .

    11 Equipment type Overhead line, underground line, . . .

    12 Failed equipment Specific equipment: conductor, switch, pole, fuse, . . .

    13 Type of equipment Further specification: wooden pole, steel pole, . . .

    14 Amount of failed equipment

    15 Short circuit type One-line-to-ground fault, ground fault, line-to-line grounded fault, . . .

    16 Producer Siemens, ABB, . . .

    17 Production year Production year of the equipment

    18 Outage start time

    19 First manipulation Failure limitation start time20 End of manipulations Failure limitation time

    21 End of outage Supply renewal time for all consumers

    22 End of equipment failure Equipment reparation end time

    23 Time of dead earth

    24 Unsupplied power at the outage start

    25 Unsupplied power at the end of manipulations

    26 Unsupplied distribution transformers at the outage start

    27 Unsupplied distribution transformers at the end of manipulations

    28 Unsupplied customers at the outage start

    29 Unsupplied customers at the end of manipulations

    30 Number of unsupplied customers multiplied by time of their outage

    31 Failure type With or without equipment fail

  • 7/27/2019 The Basic Reliability Calculations

    15/30

    Failure rate

    (year-1)

    N = number of failures (-) Z = number of elements of the given type

    in the network (-)

    P = the considered period (year)

    Results

    PZ

    N

  • 7/27/2019 The Basic Reliability Calculations

    16/30

    Mean duration of the failure

    (h)

    N = number of failures (-) ti = the considered period (h)

    Results

    N

    t

    N

    i

    i

    1

  • 7/27/2019 The Basic Reliability Calculations

    17/30

    Results

    The value tendency of reliability indices of the22 kV cable

    Cable 22 kV

    0

    1

    2

    3

    4

    5

    6

    7

    200020012002 20032004 200520062007 20082009 Total

    Meantime

    torepair(h)

    0

    0.01

    0.02

    0.03

    0.04

    0.05

    0.06

    0.07

    0.08

    0.09

    0.1

    Failurerate(year-1)

    (h)

    (year

    -1

    )

  • 7/27/2019 The Basic Reliability Calculations

    18/30

    Results

    Comparison with methodology EZ 22/80

    EZ

    22/80

    22 kV cable (year

    -1)

    14.5 5.480 ( 215 4.034

    22 kV overhead line (year-1

    ) 14 3.018 (h) 3 4.163

    110 kV overhead line (year-1

    ) 5.2 0.370 (h) 3.5 3.992

    MV/LV transformer (year-1

    ) 0.03 0.007 (h) 2500 4.315

    110 kV/MV transformer (year-1

    ) 0.04 0.059 ( 1300 0.480

    22 kV circuit breaker (year-1

    ) 0.015 0.016 ( 30 64.179

    110 kV circuit breaker (year-1

    ) 0.01 0.052 ( 100 47.425

    Equipment 2000 - 2009

  • 7/27/2019 The Basic Reliability Calculations

    19/30

    Results

    Division of failures according to their causes

    1

    2

    3

    4

    8

    9

    Causes before starting operation

    Operation and maintenance causes

    Foreign influences

    Forced outage

    Cause not explainedOther causes

  • 7/27/2019 The Basic Reliability Calculations

    20/30

    The Main Calculation Methods of

    Reliability

    Method of reliabilty schemes

    Department of electrical power engineering

    Markovs processes

    Simulative methods

  • 7/27/2019 The Basic Reliability Calculations

    21/30

    - make-up of reliability diagram,

    - assignment of relevant reliability quantities to single elements,

    - simplification of reliability diagram towards one element,

    Advantages:

    - considered systems do not have to really exist as yet,

    - procedure of solving is well-arranged and not exacting concerningmathematics,

    - mathematical procedure does not require iterative calculation,

    - accuracy of results depends only on the accuracy of input parameters

    of calculation.

    Disadvantages:

    - it is impossible to pursue power balance of network,

    - T type bay can be modelled only approximately.

    Method of Reliability Schemes

  • 7/27/2019 The Basic Reliability Calculations

    22/30

    Probability of failure-free run:

    Rule of Multiplication of Probabilities :

    P(A) probability of occurrence ofA

    P(B) probability of occurrence ofB

    Series systems

    A failure of one element leads to a failure of a system.

  • 7/27/2019 The Basic Reliability Calculations

    23/30

    A failure of a system occurs when all elements have a failure

    Probability of a failure:

    Probability of failure-free run:

    Parallel Systems

  • 7/27/2019 The Basic Reliability Calculations

    24/30

    Simplified

    Probability of failure-free run:

  • 7/27/2019 The Basic Reliability Calculations

    25/30

  • 7/27/2019 The Basic Reliability Calculations

    26/30

    Mean times of outages of a two-elements system:

    Series connection of elements

    For this circuit with two elements it holds:

    P ... Failure rate [year-1]

    U ... Maintenance rate [year-1]

    ... Outage rate (maintenance + repair) [year-1]

  • 7/27/2019 The Basic Reliability Calculations

    27/30

    Maintenance outage cannot occur at this connection, because at the failure of one

    element maintenance of another element will not begin.

    Parallel connection of elements hot reserve

    Failure rate:

    Mean time of failure:

  • 7/27/2019 The Basic Reliability Calculations

    28/30

    Parallel circuit of elements cold reserve

    . Manipulation time [h]

  • 7/27/2019 The Basic Reliability Calculations

    29/30

    Simulation Methods of Calculation of Reliability

    It is necessary to know the intensity of outages and mean time of outages of all the

    elements of a system.Simulation - numerical method which resides in experimenting with mathematical

    models of real systems on numerical computers.

    Advantages:

    - considered systems do not have to really exist as yet,

    - considered systems can be too complicated for using analytical methods,

    - simulation makes possible study of behaviour of systems in real, accelerated, or

    retarded time. The second possibility is the most important in this case,

    because the processes of outage of elements and their re-introduction into

    operation are very slow. It would be very inefficient to study them in any othertime but accelerated.

    - with simulation it is possible to verify results obtained by other independant

    processes,

    - possibility of modelling T type bays- simple power balance of a diagram is carried out, outage is always simulated at

    overloaded elements.

  • 7/27/2019 The Basic Reliability Calculations

    30/30

    - construction of a useful simulation model is very time-consuming. Mostly

    several variants of a model are needed.

    - simulation is a numerical method, so a solution of certain problem cannot be

    generally transferred on analogous problems.

    - the results obtained from stochastic simulation models are values of

    accidental quantities, and it would be very computer time-consuming if their

    accuracy should be increased

    - precision of results depends on the number of iterations,

    - the needed number of iterations depends on the extent of the solved

    network and on the required precision.

    Disadvantages of simulation methods:


Recommended