The Basics of Microsoft Project
André Sanz
…or how to avoid using Excel to manage a project schedule..!
Step 2: Defining basic Project information & Loading Project
AgendaThe Basics of Microsoft Project
Creating & Assigning a Project calendar Defining basic Project information Loading Project resources Creating a top-level WBS (Summary Tasks) Loading each top-level WBS (Subtasks) Task Types, Durations & Predecessors Filtering & Reports
Defining Basic Project Information
Defining Basic Project InformationThe Basics of Microsoft Project
1
2
3Select your Project start date (Default Calendar should be set from prior step)
Select OK when finished
Select Project tab, then Project Information
4
4
Then Select File > Save and save
your Project Schedule
Loading Project Resources
Loading Project ResourcesThe Basics of Microsoft Project
1
2
45
6
3
From the Task tab, select the View drop-down
From the View drop-down, select the Resource SheetSelect the
Resources tab, Add Resources and select the Address Book
Loading Project ResourcesThe Basics of Microsoft Project
Search in the Global Address Book for those you’re looking to add to your project.
Select Add
Once the list is complete, select OK
Loading Project ResourcesThe Basics of Microsoft Project
Be sure the update the resource initials (important as you add resources, and your resource list gets larger)
Update the base calendar (created earlier) used by each resource so non-working time is reflected properly for all resources
Repeat as needed to add additional resources at any time
1
2
3