+ All Categories
Home > Documents > The Basics of OEE (2)

The Basics of OEE (2)

Date post: 10-Feb-2018
Category:
Upload: guillerminagalleg2
View: 216 times
Download: 0 times
Share this document with a friend

of 30

Transcript
  • 7/22/2019 The Basics of OEE (2)

    1/30

    The Basics of OEEOverall Equipment Effectiveness

    10.29.09

  • 7/22/2019 The Basics of OEE (2)

    2/30

    What is OEE?

    Best practices way to monitor and improveeffectiveness of manufacturing processes

    Breaks productivity loss down into threemain categories

    Results in metrics that can be monitoredand use for improvement

  • 7/22/2019 The Basics of OEE (2)

    3/30

    What is OEE?

    OEE Factors

    Availability

    Performance

    Quality

    Losses

    Six major causes for effectiveness losses

  • 7/22/2019 The Basics of OEE (2)

    4/30

    Starting Point

    Total Plant Operating Time = Total hours available to run

  • 7/22/2019 The Basics of OEE (2)

    5/30

    Starting Point

    Total Plant Operating Time = Total hours available to run

    -No intention of running i. e. breaks, lunch, schedule maintenance

  • 7/22/2019 The Basics of OEE (2)

    6/30

    Starting Point

    Total Plant Operating Time = Total hours available to run

    Planned Production Time=Total hours- breaks, scheduled downtime Planned Shutdown

    -No intention of running i. e. breaks, lunch, schedule maintenance

  • 7/22/2019 The Basics of OEE (2)

    7/30

    Starting Point

    Total Plant Operating Time = Total hours available to run

    Planned Production Time=Total hours- breaks, scheduled downtime Planned Shutdown

    -No intention of running i. e. breaks, lunch, schedule maintenance

    -Equipment failures, material shortages, changeovers

  • 7/22/2019 The Basics of OEE (2)

    8/30

    Starting Point

    Total Plant Operating Time = Total hours available to run

    Operating Time=Planned Prod. Time-waiting on fabric, changeovers Downtime Loss

    Planned Production Time=Total hours- breaks, scheduled downtime Planned Shutdown

    -No intention of running i. e. breaks, lunch, schedule maintenance

    -Equipment failures, material shortages, changeovers

  • 7/22/2019 The Basics of OEE (2)

    9/30

    Starting Point

    Total Plant Operating Time = Total hours available to run

    Operating Time=Planned Prod. Time-waiting on fabric, changeovers Downtime Loss

    Planned Production Time=Total hours- breaks, scheduled downtime Planned Shutdown

    -No intention of running i. e. breaks, lunch, schedule maintenance

    -Equipment failures, material shortages, changeovers

    -Machine wear, poor incoming quality, operator inefficiency

  • 7/22/2019 The Basics of OEE (2)

    10/30

    Starting Point

    Total Plant Operating Time = Total hours available to run

    Net operating Time =Oper. Time-small stops, inability to run at spec Speed Loss

    Operating Time=Planned Prod. Time-waiting on fabric, changeovers Downtime Loss

    Planned Production Time=Total hours- breaks, scheduled downtime Planned Shutdown

    -No intention of running i. e. breaks, lunch, schedule maintenance

    -Equipment failures, material shortages, changeovers

    -Machine wear, poor incoming quality, operator inefficiency

  • 7/22/2019 The Basics of OEE (2)

    11/30

    Starting Point

    Total Plant Operating Time = Total hours available to run

    Net operating Time =Oper. Time-small stops, inability to run at spec Speed Loss

    Operating Time=Planned Prod. Time-waiting on fabric, changeovers Downtime Loss

    Planned Production Time=Total hours- breaks, scheduled downtime Planned Shutdown

    -No intention of running i. e. breaks, lunch, schedule maintenance

    -Equipment failures, material shortages, changeovers

    -Machine wear, poor incoming quality, operator inefficiency

    -Product that does not meet quality standards including rework

  • 7/22/2019 The Basics of OEE (2)

    12/30

    Starting Point

    Total Plant Operating Time = Total hours available to run

    Net operating Time =Oper. Time-small stops, inability to run at spec Speed Loss

    Fully Productive Time Quality Loss

    Operating Time=Planned Prod. Time-waiting on fabric, changeovers Downtime Loss

    Planned Production Time=Total hours- breaks, scheduled downtime Planned Shutdown

    -No intention of running i. e. breaks, lunch, schedule maintenance

    -Equipment failures, material shortages, changeovers

    -Machine wear, poor incoming quality, operator inefficiency

    -Product that does not meet quality standards including rework

  • 7/22/2019 The Basics of OEE (2)

    13/30

    Another Way to Look at It

  • 7/22/2019 The Basics of OEE (2)

    14/30

    Another Way to Look at It

  • 7/22/2019 The Basics of OEE (2)

    15/30

    Another Way to Look at It

  • 7/22/2019 The Basics of OEE (2)

    16/30

    Another Way to Look at It

  • 7/22/2019 The Basics of OEE (2)

    17/30

    Another Way to Look at It

  • 7/22/2019 The Basics of OEE (2)

    18/30

    Another Way to Look at It

  • 7/22/2019 The Basics of OEE (2)

    19/30

    Yet Another Way to Look at It

    Total Plant Operating Time / Total Time Available to Run

  • 7/22/2019 The Basics of OEE (2)

    20/30

    Yet Another Way to Look at It

    Total Plant Operating Time / Total Time Available to Run

    Planned Production TimePlanned

    Shutdown

  • 7/22/2019 The Basics of OEE (2)

    21/30

    Yet Another Way to Look at It

    Total Plant Operating Time / Total Time Available to Run

    Planned Production TimePlanned

    Shutdown

    Operating TimePlanned

    ShutdownDowntime

    Loss

  • 7/22/2019 The Basics of OEE (2)

    22/30

    Yet Another Way to Look at It

    Total Plant Operating Time / Total Time Available to Run

    Planned Production TimePlanned

    Shutdown

    Operating TimePlanned

    ShutdownDowntime

    Loss

    Net Operating TimePlanned

    ShutdownDowntime

    LossSpeedLoss

  • 7/22/2019 The Basics of OEE (2)

    23/30

    Yet Another Way to Look at It

    Total Plant Operating Time / Total Time Available to Run

    Planned Production TimePlanned

    Shutdown

    Operating TimePlanned

    ShutdownDowntime

    Loss

    Net Operating TimePlanned

    ShutdownDowntime

    LossSpeedLoss

    Fully Productive TimePlanned

    ShutdownDowntime

    LossSpeedLoss

    QualityLoss

  • 7/22/2019 The Basics of OEE (2)

    24/30

    Six Big Losses

    OEE LossCategory Six Big LossCategory Example Comment

    Down Time Loss

    Breakdowns ToolingUnplanned Maintenance

    General breakdowns

    Threshold between breakdownand small stop

    Setup andAdjustments

    Set up / changeover

    Material shortages

    Operator shortage

    Major adjustments

    Warm up time

    Addressed through set up timereduction

    Speed Loss

    Small Stops MisfeedsCleaning checking

    Blocked delivery

    Blocked sensor

    Typically stops under 5 minutesand no maintenance

    Reduced Speed Rough runningUnder capacity

    Equipment wear

    Operator inefficiency

    Any factor contributing torunning at less than ideal speed

    Quality Loss

    Startup Rejects ScrapRework

    Rejects due to startup, warm-up,adjustments

    Production Rejects ScrapRework

    Rejects while steady stateproduction

  • 7/22/2019 The Basics of OEE (2)

    25/30

    Starting Point

    OEE Loss OEE Factor

    PlannedShutdown

    Not part of OEE calculation

    Down TimeLoss

    Availability =Operating Time

    Planned Production time

    Speed Loss Performance =Net Operating Time

    Operating Time

    Quality Loss Quality =Good product

    Total Product

  • 7/22/2019 The Basics of OEE (2)

    26/30

    World Class OEE

    OEE Factor World Class Metric

    Availability 90.0%

    Performance 95.0%

    Quality 99.9%

    OEE 85.0%

  • 7/22/2019 The Basics of OEE (2)

    27/30

    Calculating OEE

    Availability =

    Performance =

    Performance =

    Quality=

    OEE =

    Operating TimePlanned Production Time

    Ideal Cycle TimeOperating Time / Total Pieces

    Total Pieces / Operating TimeIdeal Run Rate

    Good Pieces

    Total Pieces

    Availability x Performance x Quality

  • 7/22/2019 The Basics of OEE (2)

    28/30

    Example Calculation

    Shift Length 8 hours = 480 minutes

    Short Breaks 2 @ 15 minutes

    Meal Breaks 1 @ 30 minutes Down Time 47 minutes

    Ideal Run Rate 19 meters / minute

    Total Yards 7,000 meters / shift Rejections 157 meters

  • 7/22/2019 The Basics of OEE (2)

    29/30

    Example Calculation

    Planned Production Time

    Shift Length breaks = 480-60=420 minutes

    Operating Time

    Planned Production Time Downtime

    = 420-47 = 373 minutes

    Good Product

    Total meters rejection Meters

    = 7000-157 = 6930 Meters

  • 7/22/2019 The Basics of OEE (2)

    30/30

    Example Calculation

    Availability = = =Operating Time

    Planned Production Time373 minutes420 minutes 0.8881

    or88.81%

    Performance = =Total Yardage / Operating TimeIdeal Run Rate

    7000/373 minutes19 meters / minute

    0.9877 or 98.77%=

    Quality = = =Good yardageTotal yardage

    6930 meters7087 meters

    0.9778 or 97.78%

    OEE = =

    = 0.8577 or 85.77%

    0.8881 x 0.9877 x 0.9778Availability x performance x quality


Recommended