The Benefits of Building The Benefits of Building CommissioningCommissioning
Carl N. Lawson
Hanson Professional Services Inc.
Rapid City South DakotaRapid City South Dakota
ASHRAE
We are told never to cross a bridge until it is finished.
In this business we cross bridges every day that have not been finished.
And we will continue to do so.
What is the Total Building Commissioning Process (TBCxP)?
A Quality Process to VERIFY and DOCUMENT
that building systems and assemblies
meet the needs of
BUILDING OWNERS and OCCUPANTS.
What is TBCxP?What is TBCxP?
Owner orientated
Team Responsibility
Continuous improvement
Lower cost, more profits
Consistent delivery of construction projects
So, why are we here and what
does TBCxP have to offer?
Essential Concept of TBCxPEssential Concept of TBCxP It takes the uncertainty out of the delivery
of a constructed projects
Does as well as any other approach, but at a lower cost
Has means to use statistical tools based upon probability distribution of outcome or based upon random estimate of expected outcome distribution
Has an element of continuous improvement
Transfers knowledge from planning to operations
Goals of TBCxP Document owner’s goals and
requirements
Keep project team focused on owner’s goals
Prevent or eliminate problems inexpensively
Lower overall costs for the owner
Increase profits for project team by decreasing costs
TBCxP Best PracticeTBCxP Best Practice
Cost effective
Owner’s Project Requirement orientated
Team (commissioning process team)
Quality tools used
Orientated on delivery of the constructed project for: owner, occupants, and O&M
What Each Team Member WantsWhat Each Team Member WantsARCHITECTS
Design the next wonder of the world
Fewer change orders
Fewer RFI’s
Contractor to build it like it is designed
No site visits
Do the engineer’s inspections
No attorneys involved
What Each Team Member WantsWhat Each Team Member Wants
ENGINEERS
Design that is not VE’d to death
Fewer change orders
Fewer RFI’s
Contractor to install it like it is designed
No inspections
Do their own CA
No legal hassle
Paid on time
What Each Team Member Wants What Each Team Member Wants
SUB-CONTRACTORS
Design he can change (for he believes his design is better)
A/E should stay off the job site
Work at his own pace
Get paid in a timely manner
Holds supplier’s money since he has not been paid by the GC
Get off the job quickly
Hope he gets his retainage
What Each Team Member WantsWhat Each Team Member WantsGC/CM A design that works To VE the daylights out of it A/E should stay off the site Do it his way Paid 30% mobilization fee Paid monthly on time Hold subcontractor’s payment as long
as he can Get off the job and hope he gets his
retainage
What Each Team Member WantsWhat Each Team Member WantsOWNER
Project that is pretty, functions well and all systems work
Project is complete, on time and within budget
No change orders
No RFI’s
Low interest construction loan
Makes excuses about paying designers and contractors on time
Hopes the building and systems work as anticipated.
What Each Team Member WantsWhat Each Team Member Wants
Manufacturers
Equipment and system approval
Ship equipment early
Warranty to start when equipment leaves factory
Why can’t I submit on this project?
Take their time in completing project
Paid without penalty
ENERGIZED
SYSTEM
STATICSYSTEM
HUMAN SYSTEM
The Three Systems of BuildingsThe Three Systems of Buildings
STATIC SYSTEM: (THE FRAME AND ENVELOPE)ENERGIZED SYSTEM: (THE BUILDING SERVICES)HUMAN SYSTEM: (THE TENANTS AND OCCUPANTS)
OWNER
CONTR
ACTO
R
Building RelationshipsBuilding Relationships
A/E
COMMISSIONING AUTHORITY
Role of the Commissioning AuthorityRole of the Commissioning Authority Determine what the owner really wants
Work with design team to implement a Basis of Design (BOD) document and Owner’s Project Requirements (OPR) document
Develop a plan to implement the BOD and OPR into the construction documents
Verify the right systems are being installed
Verify the operation of the systems
Document the entire project
Price vs. CostPrice vs. Cost
Price is something you pay one time
Cost is what it takes to operate
PRICE
QUALITY
SPEED
Pick any Two
Benefits and Cost Savings Potential vs. Cost to Implement or Change
Benefits and Cost Savings Potential vs. Cost to Implement or Change
Concept Design Construction Acceptance Occupancy
Benefits and Cost Savings
Cost to Change
Phases
Commissioning ConsultantCommissioning ConsultantDefinition of “Consultant” – someone called in to share the blame.
The Blame Game…Dr. John Parker
Lawyer – Have we left anything out?
Surgeon – Have we left anything in?
Engineer – Is there anything left?
What is CommissioningWhat is Commissioning
Commissioning is a process to verify that the owner has received what they contracted for during the programming and design phases and during the construction phase. It also gives them a comfortable feeling of knowing someone is looking out for them throughout the project and the 1st year of occupancy
It also verifies that the architects and engineers have received the systems they designed and approved
The Principal Goal of CommissioningThe Principal Goal of Commissioning
The Principal Goal of the Commissioning Process is:
The identification and correction of problems as early in the process as possible.
Top 10 Deficiencies Discovered by Commissioning New & Existing Buildings
Top 10 Deficiencies Discovered by Commissioning New & Existing Buildings
Incorrect scheduling of HVAC and Lighting equipment
Incorrect heating and cooling Sequence of Operation
Incorrect Calibration of Sensors and Instrumentation
Lack of control strategies for optimum comfort and efficient operation
Malfunctioning air and water side economizers
Top 10 Deficiencies Discovered by Commissioning New & Existing Buildings (cont.)
Top 10 Deficiencies Discovered by Commissioning New & Existing Buildings (cont.)
Under-utilized computer-based control systems
Short cycling of HVAC equipment leading to premature failure
Lack of design intent and building documentation
Lack of training for building operators or service contractors on complex systems
Missing specified and pair-for equipment economizers
What Commissioning is NOTWhat Commissioning is NOT
Test and Balance
Start-up
Plan Review
Design
Contract Administration
Inspection
When Should Commissioning Begin??When Should Commissioning Begin??
Near the end of the Construction Phase?
When MEP systems installation begin?
When construction begins?
When design is complete?
When CD’s are started?
When DD’s are Started?
When SD’s are started?
Prior to beginning design?
It is mandatory to commission all LEED projects to a specified level
Some states have mandated that state owned or leased buildings be commissioned
US FEDERAL GSA has mandated that GSA buildings be commissioned
More and more hospitals are now requiring commissioning
Commissioning is a standard in Canada
Commissioning – Where it is goingCommissioning – Where it is going
Why Required?Why Required?
Low quality construction- construction deficiencies
Complex systems – difficult to test
Integrated systems – do cause problems
ASHRAE Guideline 0-2006ASHRAE Guideline 0-2006
Describes the commissioning process that will ensure HVAC systems perform in conformity with design intent and owner’s project requirements
Phases of CommissioningPhases of Commissioning
Pre-Design
Design
Construction
Occupancy
Project Turnover
Warranty
How does the CxA meet his Responsibilities?How does the CxA meet his Responsibilities?
Conduct a OPR Charrette with the owner and design team.
Create and publish the OPR.
Review each step in the process to ensure compliance with the OPR.
Conduct regular meetings with the Cx Team to ensure communications are free flowing.
Document the entire process for the benefit of the owner and his staff.
Systems CommissioningSystems Commissioning
Verifies operation of components under various conditions
Verifies interaction between systems and subsystems
Documents performance of systems to design criteria
Instructs building personnel on proper operation of systems
Ongoing after building occupancy as requirements change
Cost Savings from Building CommissioningCost Savings from Building Commissioning
Energy Savings of 20 to 50%
Maintenance savings of 15 to 50%
Reduction in claims from 2 to 20%
Reduction of in-house overtime costs
Reduction of trouble-shooting costs
Who are the PlayersWho are the Players
Architect
Engineers
Owner’s Representative
Construction Manager
Mechanical Contractor
Electrical Contractor
Controls Sub-Contractor
Others as deemed necessary
ResponsibilitiesResponsibilities
ARCHITECT/ENGINEER
Be a team player
Design the project with owner’s thoughts and requirements in mind
Be willing to make changes
Attend and participate in the commissioning meetings
Attend and participate in the owners project requirement meeting
Responsibilities (Cont.)Responsibilities (Cont.)
With the assistance of the CxA develop the basis of design document
Answer RFI’s in a timely manner
Answer change orders in a timely manner
Attend and participate in the VE process
Responsibilities (Cont.)Responsibilities (Cont.)
OWNER’S REPRESENTATIVE
Make decisions in a timely manner
Attend and participate in owners project requirement meeting
Attend and participate in commissioning meetings
Must own commissioning authority’s contract
Approve the owners project requirement document
Approve the commissioning plan
Responsibilities (Cont.)Responsibilities (Cont.)
CONSTRUCTION MANAGER
Manage the project
Coordinate sub-contractors work
Attend and participate in the commissioning meetings
Attend and participate in the owner’s project requirement meeting
Attend and participate in the VE process
Have coordination drawings developed
Responsibilities (Cont.)Responsibilities (Cont.)
MEP CONTRACTORS
Install their respective work
Complete the various checklist
Be part of the commissioning team
Attend and participate in the owners project requirement meeting
Attend and participate in the commissioning meetings
Attend and participate in the VE process
Be a team player
Responsibilities (Cont.)Responsibilities (Cont.)
COMMISSIONING AUTHORITY
Manage the commissioning process
Develop the commissioning plan
Develop the commissioning specifications
Work with all the other team members
Develop the owner’s project requirement document
With the assistance of the engineer develop the basis of design
Verify mold and mildew concerns
Responsibilities (Cont.)Responsibilities (Cont.)
COMMISSIONING AUTHORITY
Conduct the commissioning meetings
Review the project in a timely manner
Review the submittals for compliance
Review the warranties for the record
Review the checklist
Perform the FPT
Turn building over to the owner
Not responsible for the design
CxA Responsibities During DesignCxA Responsibities During Design
Review the SD documents and issue comments to the design team
Review the DD documents and issue comments to the design team
Review the CD documents and issue comments to the design team
Work with the VE process
To Correct Major ProblemsTo Correct Major Problems
The contract for the commissioning work should be awarded in the programming phase
The commissioning contract should be professional services directly contracted with the owner
Other contractual arrangements may and will lead to conflicts of interest
Common Technical DisagreementsCommon Technical Disagreements
Commissioning projects may experience difficulties if the design team does not take an active part in recommending an adequate solution to a found deficiency
It is not the responsibility of the CxA to dictate a design correction or change to solve a problem
Conflict ResolutionConflict Resolution Responsibilities of the design team
must be clearly defined by the commissioning plan
Design team required services and adequate fees also must be included in their contract
It is important that the commissioning authority and design team maintain a close relationship throughout the project
Common Technical DisagreementsCommon Technical Disagreements
Cx contract was not awarded until construction bids were received and awarded
The Cx contract is a subcontract under the mechanical contractor
O & M ManualsO & M Manuals
Should be received within 60 days after approved submittals have been returned
Review with owner and give comments back to contractor for compliance
Use this as your training Bible
Be careful what you get in the O & M
You do not need installation material
TrainingTraining
Factory witness testing on major pieces of equipment
Get factory training out of way up front
Training should be in a classroom setting and also at the respective piece of equipment
Use factory trainers not the local sales rep
Documentation RequiredDocumentation Required
Owners Project Requirement Document
Commissioning Plan Basis of Design Contract Documents TAB Report Draft of the Final Commissioning
Report Warranties O & M Manuals
Documentation Required (Cont.)Documentation Required (Cont.) Approved Change Orders
AS-Built Drawings
All testing data verification and documentation.
Sequence of Operation
Minutes of Meetings
Local jurisdictional inspection documentation and records
Benefits of the Commissioning ProcessBenefits of the Commissioning Process
If the Commissioning Authority/Team for your project cannot clearly document that their fee has been recovered, you are not
properly implementing the Commissioning Process
Project State Cost Project Cx Fee CxP Savings
Hospital IN $70 M Completed $744,000 $340,000
Hospital Ohio $80 M Completed $856,000 $375,000
PET Scan Facility NC $2.1 M Completed $25,000 $40,000
ABMT NC $4.8 M Completed $36,500 $100,000
Tissue Culture Lab NC $3.5 M Completed $35,000 $75,000
Hospital NC $45 M Completed $325,000 $900,000
Vivarium NC $28 M Completed $280,000 $500,000
Prison TX $40 M Completed $225,000 $400,000
CIEMAS NC $105 M Completed $1,200,000 $3,000,000
Center for Human Genetics
NC $42.5 M Completed $322,000 $1,680,000
ExampleExample Costs
$50M Laboratory Project
MEP Systems = $27M
MEP Cx Costs = 21/2 % = $675K
Savings CO reduction = $1.5M
Construction Costs = $2M
Energy Savings = $750K
Legal Costs = $500K
Early Occupancy = 45 days @ $10K/day = $450K
NET SAVINGS = $5,200,000
ROI = 1422.5%
Benefits of CommissioningBenefits of Commissioning Project on time Establish & maintain energy and
maintenance budgets Change orders are greatly reduced Claims are greatly reduced Punch list is non-existent Operators have correct training Enforce Start-Up Requirements Reduce Post-Occupancy Corrective
Work
Benefits of Commissioning (Cont.)Benefits of Commissioning (Cont.) Absenteeism has diminished Users have been able to take ownership Lasting professional relationships have
been developed Buildings and systems are operating as
owner predicted Minimize Effects of Design Defects Improve Indoor Environment and
Employee Production Reduce Energy and Operating Cost Increase Value through Better Quality
construction
Owner’s CommentsOwner’s Comments Kept politics out of project
Worth the money
Will definitely continue the process on other projects
Project was on time & budget
Systems are working as requested
Occupancy is stable
Training was a major factor in the process
Maintenance is manageable and understands the systems
Coil Damaged Beyond Repair Coil Damaged Beyond Repair
Water & Oil - OSHA ViolationWater & Oil - OSHA Violation
Corrosion Inside & OutCorrosion Inside & Out
Inside ATS for 330kw Generator #1: Improper installation requires hand operation.
Inside ATS for 330kw Generator #1: Improper installation requires hand operation.
Water Line MisplacedWater Line Misplaced
Variable Frequency Drives installed w/o air spaceVariable Frequency Drives installed w/o air space
Remember
Commissioning is
A
Quality Process
QuestionsQuestions
Thank You