29th October 2015Global Street Design Program – NACTO, Austin
THE CROSSWALK LAB(an initiative of Centre for Green
Mobility)
The Crosswalk LabTraffic Junction management through improved design
Traffic Police Municipal Corporation
Vijay CrossingNarol Crossing
Traffic Management, Signaling Plan & Design
PUBLIC CONNECT | The Crosswalk Lab
The Crosswalk LabTraffic Junction management through improved design
STUDY AREA DEFINING
SURVEYS
ANALYSIS
STREET AUDIT:
PERCEPTION STUDYMEASUREMENT FOR DRAWING
TRAFFIC :
PEAK HOUR VEDIOGRAPHYUNDERSTANDING OF TRAFFIC
BEHAVIOURSIGNAL PHASING
PREPARATION OF DRAWINGVOLUME COUNT ANALYSIS
SIGNAL PHASING
DEMONSTRATION & COLLECTING EVIDENCE
PROPOSAL TO MUNICIPAL CORPORATION
PUBLIC CONNECT | TCL – Vijay Crossing
Feedback before the experimentShopkeepers, Pedestrians and Motorists
What we have needs to change
What we have is alright
PUBLIC CONNECT | TCL – Vijay Crossing
High number of pedestrians
PUBLIC CONNECT | TCL – Vijay Crossing
Issues
Parking at intersection and footpathConflict between traffic, pedestrians and parked vehiclesNo safe crossing path for pedestriansHigh speed of turning vehiclesHigh incidence of wrong turning vehicles
Left lane: 8 mC- 2400 PCUD- 166 PCU6.9% Used
Left lane: 8 mC- 2400 PCUD- 187 PCU7.9 % Used
PUBLIC CONNECT | TCL – Vijay Crossing
PUBLIC CONNECT | TCL – Vijay Crossing
Towa
rds U
NIVE
RSIT
Y
Towards DRIVE-INTo
ward
s DAR
PAN
towards COMMERCE
Phase 1 50 sec
Phase 3 50 sec
Phase 4 50 sec
Existing signal cycle: 200 sec
Phase 2 50 sec
PUBLIC CONNECT | TCL – Vijay Crossing
Towa
rds U
NIVE
RSIT
Y
Towards DRIVE-IN
Towa
rds D
ARPA
N
towards COMMERCE
Phase 1 45 secPhase 2 15 sec
Phase 3 40 sec
Phase 4 15 sec
254
8 P
CU/h
r
1200 PCU/hr
500
PCU
/hr
500 PCU/hr
Proposed signal cycle: 115 secReduction by
20seconds in each arm
Phase 2 15 sec
PUBLIC CONNECT | TCL – Vijay Crossing
Maximum speed at left turn:50 kmphMaximum speed at right turn: 20
kmphMaximum speed at straight: 40 kmph
PUBLIC CONNECT | TCL – Vijay Crossing
No lane discipline
Wide open left turnsUnguided road space
8 m
Too wide carriage way
Delay in junction clearance
8 m
PUBLIC CONNECT | TCL – Vijay Crossing
No sight distance for pedestriansLeft turn with high speed
Unsafe pedestrians
PUBLIC CONNECT | TCL – Vijay Crossing
Unsafe pedestriansIsland covered by greenery
Mix of trafficUnrestrictive u turn
No refuge while crossing at junction – median too far – too narrow
PUBLIC CONNECT | TCL – Vijay Crossing
PUBLIC CONNECT | TCL – Vijay Crossing
PUBLIC CONNECT | TCL – Vijay Crossing
PUBLIC CONNECT | TCL – Vijay Crossing
Improving SAFETY while crossing the road
Safe left turns
Improving SAFETY while crossing the road
Speed reduced by 60%
Improving SAFETY while crossing the road
A space to wait while crossingImproved and constrained turning – notice the police standing in the refuge
Junction Re-design
Existing Situation – No clear space for cyclists and pedestrians which is blocked by parked vehicles
Junction Re-design
New Situation – Space created for cyclists and pedestrians by aligning parking away from edge.
Junction Re-design
New Situation – Space created for cyclists and pedestrians by aligning parking away from edge.
Improving SAFETY while crossing the road
A space to wait while crossing
A space to wait while crossing
PUBLIC CONNECT | TCL – Vijay Crossing
A space to wait while crossingReduction in wrong side - No extra space
PUBLIC CONNECT | TCL – Vijay Crossing
DAY 0Implementation
Improving SAFETY while crossing the road
Day 1Slow left turns
Improving SAFETY while crossing the road
Day 1Slow U turns
Improving SAFETY while crossing the road
Day 1Parking getting organized
Improving SAFETY while crossing the road
Day 2
Improving SAFETY while crossing the road
Day 1More walking space,But parking persists
Day 2
Improving SAFETY while crossing the road
Day 1Refuge helps
Day 3
Improving SAFETY while crossing the road
Day Parking back to its original position
Day 3
Improving SAFETY while crossing the road
Day Much talking to people helps
Day 3
Improving SAFETY while crossing the road
Day Parking getting organized again
Day 4Talking talking and more talking to peopleTo get them to understand new parking space
Improving SAFETY while crossing the road
Day 5Much discipline observed
Improving SAFETY while crossing the road
Day 5
Improving SAFETY while crossing the road
Observed managed parking
Issues on street (Shopkeepers)
IMPACT
Do you feel street safe? (pedestrians)
IMPACT
THE IMPACT
Geometric Design of Junction
Pedestrian safety at the junction. High IncreaseSafety for cyclists at the junction. Little IncreaseHigh turning speeds. Reduced by 60%High incidence of wrong lane driving (opposite currents). Reduced by 90%Large wait time at junctions. Decrease by 35%Managing traffic. Easy
PUBLIC CONNECT | TCL – Vijay Crossing