ENQUIRY NO. CORP4203 CLARIFICATION SESSION FOR THE DESIGN, MANUFACTURING, TESTING AND , SUPPLY OF SPLIT METERING POLE TOP BOXES AND READYBOARDS. Date: 05 February 2018 Venue: Ian McRae Boardroom EAL
Transcript

ENQUIRY NO. CORP4203

CLARIFICATION SESSION FOR

THE DESIGN, MANUFACTURING, TESTING AND ,

SUPPLY OF SPLIT METERING POLE TOP BOXES

AND READYBOARDS.

Date: 05 February 2018

Venue: Ian McRae Boardroom EAL

AGENDA FOR CORP4203

2

1 Registration - Tea/Coffee All 15 Minutes

2 Evacuation Procedure Venue Rep 5 Minutes

3 Introductions All 10 Minutes

4 Objective of the session –RFQ Process L Morife 5 Minutes

5 Commercial L Morife 15 Minutes

6 Quality

F Mogamisi 15 Minutes

7 Supplier Development & Localisation (SD & L) M Sabelo 20 Minutes

8 Technical J Maudu 40 Minutes

9 Closure L Morife 5 Minutes

Purpose of meeting

• The session will focus on addressing the content of CORP4203;

• Providing responses to the clarification requests submitted in

advance; and

• Providing forum for Q & A to clarifications required.

3

4

Timelines, RFQ Conditions & Returnables

Eskom Representative for CORP4203 : Portia Ramushu

E-mail : [email protected]

Landline : +27 11 516 7628 FAX +27 86 601 7138

All communication in writing to the Eskom rep

Timelines

Clarification meeting : 05 February 2018

Clarification Queries deadline : 5 working days prior to closing

Enquiry Closing Date and Time : 07 March 2018, Strictly 10:00am (SAST)

No late submissions accepted -not even by a second

Include your company return address + Company Stamp

(In case submission is late)

5

Timelines, RFQ Conditions & Returnables

Tender Addressed: Attention: Portia Ramushu

Confidential Enquiry no: CORP4203

Eskom Holdings SOC Limited

Eskom Megawatt Park

1 Maxwell Drive

Sunninghill

2157

Tender box Location: Tender Advice Centre (Retail Centre)

Eskom Megawatt Park

1 Maxwell Drive

Sunninghill

Tender box operating hours 07h00-17h00

Enquiry Costs: Free of Charge

RFQ Conditions

6

SD&L Mandate 1

Enquiry Submission

• an original,

• one (1) complete hard copy of the original,

• one (1) complete copy of tender on CD or USB,

The original, hard and soft copy of the tender must be clearly divided into the

following sections:

• Commercial (As per Commercial Tender Returnables)

• SD&L (As per SD&L Tender Returnables)

• Finance (As per Finance Tender Returnables)

• Technical (As per Technical Tender Returnables)

• Quality (As per Quality Tender Returnables)

RFQ Conditions

7

SD&L Mandate 1

It must be noted that a Supplier’s failure to provide the necessary

original and hard copies of the tender will disqualify the Supplier from

being evaluated.

All enquiry submissions must be in English

8

A six step evaluation process will be followed (i.e. basic compliance, mandatory

returnables, functionality (desk top & factory evaluation) & price & preference

(90/10) and objective criteria)

Step 1 - Basic Compliance

All tender submissions will be checked for overall compliance to the conditions of tender

and responsiveness.

Step 2 - Mandatory Returnables

All tenders will be evaluated for compliance to the mandatory requirements. Tenders

which do not comply will not be evaluated further.

Step 3 – Functionality

Evaluations

Functionality criteria Weightings

Technical 100%

Overall minimum threshold 86%

9

Step 4 Functionality (Technical)

Gate keeper Level 1: this initial part of the evaluations starts when submissions are

opened and assessed for the first time. It begins with the gate-keeper (Level 1) and

proceeds to level 2 (scoring method). Submissions that do not meet the level

gatekeepers is immediately disqualified.

Level 2 (Scoring method) – Tenderers need to achieve a minimum score of 86%

(technical evaluation) to be considered for factory evaluation.

Factory evaluation – Factory evaluations will be arranged with tenderers who have

achieved a minimum score as per above.

Step 5 - Price and Preference

Price points will be calculated out of 90 for price. A maximum of 10 points will be

allocated to the B-BBEE level contribution. The prices and preference points will be

added together to determine the highest scoring tenderer.

Evaluations

Evaluations continued

Step 6 – Objective criteria

Objective criteria in terms of section 2 (1) (d-f) of the PPPFA will be used in

awarding the contract to the tenderer which meets specific goals i.e. financial,

Quality, Legal, Commercial, Shipping & Supplier Development and Localisation.

Eskom reserves the right to award to multiple original equipment manufacturers

(OEM’s) who may not be the highest scoring/highest ranked supplier, in line with

Section (2) (1) (f) of the PPPFA.

Tenderers are required to submit plans with milestones for improving their BBBEE

contributor levels and migrating to more than 51% black ownership within a period

of twelve (12) months. Eskom reserves the right to revoke the contract if these

milestones are not achieved within 12 (twelve) months.

10

11

/

B-BBEE Score and Evaluations

B-BBEE Status Level of

Contributor

Number of Points

1 10

2 9

3 6

4 5

5 4

6 3

7 2

8 1

Non-compliant contributor 0

12

/

Returnables

Reference

Returnables from supplier

Mandatory

returnable

for

evaluation

Mandat

ory

returnab

le for

contract

award

Basic Compliance One (1) complete hard copy of the original tender

Annexure A

Acknowledgement Form

Additional Documents

required in event of

JV:-

Letter of intent to form a JV/consortium

Valid joint venture agreement confirming the rights and obligations of each

of the joint venture partners and their profit-sharing ratios.

Written confirmation that the joint venture will operate as a single business

entity (incorporated) for the duration of the contract (this may be included

as an obligation within the JV agreement)

* A trust, consortium or joint venture (including unincorporated consortia

and joint ventures) must submit a consolidated B-BBEE Status Level

Verification Certificate for every separate tender.

Details and confirmation of a single designated bank account in the name

of the JV and independent of the individual JV partners, as set out in the

joint venture agreement.

13

/

Returnables

Annexure B Tenderers Particulars

Annexure C Integrity Pact Declaration form

Annexure D CPA for local goods/services (if applicable)

Annexure E CPA(IG) for imported goods/services (if applicable)

Annexure H Confirmation of receipt of addenda to enquiry document

Annexure I (applicable for all

suppliers including Foreign

suppliers)

SBD 1- to be submitted with the tender at tender submission deadline

Annexure J SBD 6.1- Preference Points Claim Form in terms of PPPFA 2017

regulations

*B-BBEE Certificates Failure on the part of the supplier to submit a valid current certificate

for purposes of evaluation and scoring by the tender closing deadline

will not result in disqualification (if otherwise deemed to be responsive

and acceptable in all other aspects) but the tenderer will score zero on

B-BBEE for purposes of scoring and ranking

14

/

Returnables

Tax Clearance Certificates Foreign suppliers (who have answered yes to any of the

questions in the relevant section of SBD 1 and who have

not provided a CSD or SARS Efiling pin number as per

Annexure A, will need to provide a copy of a current valid

tax compliance certificate

Tax Questionnaire Evaluation questionnaire to determine whether a company,

close corporation (CC) or Trust is a personal service

provider for purposes of PAYE [only in the case of services

contracts]

Signed Sub-contracting

intent agreement

Tenderers must, where subcontracting is a pre-qualification

requirement, submit proof of signed subcontracting intent

agreement

Compliance with

Employment Equity Act

To the extent that the tenderer falls within the definition of a

“designated Employer” as contemplated in the Employment

Equity Act 55 of 1998, the tenderer is required to furnish the

Employer with proof of compliance with the Employment

Equity Act, including proof of submission of the Employment

Equity report to the Department of Labour. (South African

tenderers only)

15

/

Returnables

Financial statements Audited Financial Statements of the tenderer for the

previous two financial years, or to the extent that

such statements are not available, for the last year.

Tenderers must note that in the case of a joint

venture or special purpose vehicle (SPV) especially

formed for this tender, audited financial statements

for each participant in the JV / SPV is required. Start-

up enterprises formed within the last 12 months are

not required to send in statements, but if successful

with their tender will be required to send statements

for the first year when once available.

Shareholding Shareholding organogram /breakdown (for each

individual company/JV member) clearly identifying

percentages owned by individual shareholders (full

names & ID Numbers) and other entities (provide full

legal/trading name and respective identifying

registration/trust numbers)

NEC/FIDIC

Documentation

Completed NEC/FIDIC pricing schedule and contract

data.

Complete NEC document

16

/

Returnables

Technical returnables Pole top boxes

Type test reports/certificates (accredited facility)

Completed technical schedules B

Split meter pole top box construction drawings

Proof for MOV (surge arrester) that complies with SANS

1524-1-2

Dimensional data drawings

Ready boards

Type test reports/certificates (accredited facility)

Completed technical schedules B

Split meter ready board construction drawings

Dimensional data drawings

Sample of manufacturer’s abridged certificate of

compliance (COC) with NRCS number

A proof or certificate which shows that cable used to

connect socket outlet complies with SANS 1507

A proof or certificate which shows that ELU complies with

VC 8035 and SANS 767-1

17

/

Returnables Documents listed in quality criteria category 2.

Section A Option 1:

A.1 Product / Service Scoping on ISO certificate is defined and relevant

A.2 Certificate by Approved and Authorized certification authority

A.3 Certification Authority has Recognized International Accreditation

A.4 Validity (expiry date) of certificate

OR

Section B Option 2

A.1 Quality Manual /or Quality Method statement

A.2 Copy of Quality Policy signed by top management.

A.3 Procedure for Control of Documents

A.4 Procedure for Control of Records

A.5 Internal Audits Procedure

A.6 Procedures for Control of Nonconforming product or services

A.7 Corrective Action Procedure

A.8 Preventive Action Procedure.

18

/

Returnables

Quality Section B:

B.1 Copy of appointment letter & CV/ resume of a Quality

Representative for the project

B.2 Signed Organizational structure & Quality dept reporting

structure.

B.3 Copy of procedure for control of suppliers &

subcontractors

B.4 Copy of an internal management system audit report (with

NCR, corrective & preventive report)

B.6 Copy of Customer satisfaction surveys

B.8 Historical Information (list) of similar work performed <

2yrs

Section C:

NB!!!! draft Contract/Project Quality Plan has important QA

deliverables

Section E:

E.1 Form A is completed and signed

Due Diligence Financial statements etc that may be required for due diligence

purposes.

Supplier Development and

Localization

CSD Report

Supplier development and localization matrix

Questions ????