The Effects of Inflation in EngineeringEconomic Studies
February 18, 2004
2/18/04 Nuclear Energy Economics and Policy Analysis
2
Source: Bradford DeLong, http://www.j-bradford-delong.net/Econ_Articles/woodstock/woodstock4.html
2/18/04 Nuclear Energy Economics and Policy Analysis
3
Producer Price Index -- All Manufacturing (1992-2002)
2/18/04 Nuclear Energy Economics and Policy Analysis
7
Price trends in turbines and turbine generator sets
Source: US Bureau of Labor Statistics
2/18/04 Nuclear Energy Economics and Policy Analysis
8
Producer price index for computers and work stations
Source: BLS
2/18/04 Nuclear Energy Economics and Policy Analysis
9
Treatment of inflation in investment analysis
• Two alternatives:– Estimate cash flows in actual (‘nominal’ or
‘current’) dollars, and use ‘market’ (‘nominal’) interest rates
– Estimate cash flows in terms of the purchasing power of the dollars of some base year (i.e., in ‘constant dollars’) and use real interest rates
2/18/04 Nuclear Energy Economics and Policy Analysis
10
†
Relationship between future worth of construction project at time of completion and ‘overnight cost’ in dollars of construction start year:
1) Uniform rate of expenditure (in constant dollars)
eyTe -xT ˘È1 -Exact expression : F = IONexT Í ˙
Î (x - y)T ˚
È Approximate expression : F = ION Í1+
x + y T
˘ ˙
Î 2 ˚
2. Sine - wave construction expenditure profile (constant dollars) :
È ˘ Í ˙ Í ˙ Í ˙
˙Exact expression : F = I Í e yt + exT
onÍ Ï ¸˙ Í Ô ( x - y )2 Ô˙
ÌÍ2 1+ 2
˝˙ Í Ô p Ô˙( T ) ˛˚Î Ó
È Ê x + y ̂ ˘ Approximate expression : F ª I 1+ Á ˜T˙onÍ
Î Ë 2 ¯ ˚
2/18/04 Nuclear Energy Economics and Policy Analysis
11
Effect of construction lead time on future worth of plant, F
0.00
1.00
2.00
3.00
4.00
5.00
6.00
2 4 6 8 10 12 14
Construction lead time, T (yrs)
F/
ION
y=0.02,x=0.06
y=0.02,x=0.06(approx)
y=0.04;x=0.08;
y=0.04;x=0.08 (approx)
y=0.1;x=0.14
y=0.1;x=0.14 (approx)
Uniform rate of expenditure assumed (in constant dollars)
y= escalation rate
x= interest rate
2/18/04 Nuclear Energy Economics and Policy Analysis
12
Interpretation of alternative capital cost measures
Ion: The ‘overnight cost’ of the project, expressed in dollars of the year ofconstruction start. This is what the plant would cost if there were noinflation and no interest charges on capital, i.e., if the plant were built‘overnight’. It consists of the direct costs of labor, materials,equipment, engineering and design, etc.
F: The future worth of the project at the construction completion date. Thisis the amount of money that, if paid to the constructor at the completionof the project, would be just sufficient to cover all costs incurred duringconstruction, i.e., both the direct costs and the interest accruing onfunds borrowed (or equity invested) during construction. In the dayswhen power plants were constructed by regulated electric utilities, thiswas also often referred to as the ratebase cost.
F-Ion: The ‘time-related’ costs of the project.
2/18/04 Nuclear Energy Economics and Policy Analysis
13
Energy Information Administration. "An Analysis of Nuclear Power Plant Operating Costs." DOE/EIA-0511 (Washington,DC,1988).
2/18/04 Nuclear Energy Economics and Policy Analysis
14
Costs in 1982 constant dollars
2/18/04 Nuclear Energy Economics and 15Policy Analysis
Energy Information Administration. "An Analysis of Nuclear Power Plant Operating Costs." DOE/EIA-0511 (Washington,DC,1988).
Overnight costs given in dollars of year of construction start.
2/18/04 Nuclear Energy Economics and 16 Policy Analysis
Energy Information Administration. "An Analysis of Nuclear Power Plant Operating Costs." DOE/EIA-0511 (Washington,DC,1988).
2/18/04 Nuclear Energy Economics and Policy Analysis
17 Energy Information Administration. "An Analysis of Nuclear Power Plant Operating Costs." DOE/EIA-0511 (Washington,DC,1988).
2/18/04 Nuclear Energy Economics and Policy Analysis
18 Energy Information Administration. "An Analysis of Nuclear Power Plant Operating Costs." DOE/EIA-0511 (Washington,DC,1988).
Nuclear Energy Economics andPolicy Analysis
Predicted construction costs for future nuclear power plants
Source: MIT Nuclear Study
2/18/04 19
Deutsch, John, Ernest Moniz et al. "The Future of Nuclear Power: An Interdisciplinary MIT Study." Massachusetts Institute of Technology, 2003 (ISBN 0-615-12420-8). Available at http://web.mit.edu/nuclearpower/. p. 138.
Deutsch, John, Ernest Moniz et al. "The Future of Nuclear Power: An Interdisciplinary MIT Study." Massachusetts Institute of Technology, 2003 (ISBN 0-615-12420-8). Available at http://web.mit.edu/nuclearpower/. p. 137.
Predicted construction costs for future nuclear power plants(contd.)
2/18/04 Nuclear Energy Economics and Policy Analysis
20
Deutsch, John, Ernest Moniz et al. "The Future of Nuclear Power: An Interdisciplinary MIT Study." Massachusetts Institute of Technology, 2003 (ISBN 0-615-12420-8). Available at http://web.mit.edu/nuclearpower/. p. 137.