+ All Categories
Home > Documents > The Festival Walk - City University of Hong...

The Festival Walk - City University of Hong...

Date post: 23-Jul-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
78
Raymond Wong 1 Construction of a Semi-Buried Building – A Super-sized Shopping Mall : The Festival Walk Presented by Raymond Wong Wai Man, Division of Building Science & Technology, City University of Hong Kong
Transcript
Page 1: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 1

Construction of a Semi-Buried Building –A Super-sized Shopping Mall :

The Festival Walk

Presented by

Raymond Wong Wai Man,Division of Building Science & Technology,

City University of Hong Kong

Page 2: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 2

General InformationSite area – 21000 sq m (overall measure 290m x 80m)geological features- Tat Chee Avenue (+35m) on one longitudinal

sides and the Kowloon Canton Railway (+20m) on the other, a level diff. of about 15m exist.

- rockhead range between +25m to -35m. - Mass Transit Railway tunnels cutting across

site at +8m - deepest basement down to -3m (36m below

Tat Chee Av.)

Page 3: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 3

Block Plan

Site

25m roadway

Railway track

N

(Tat Chee Avenue)

Page 4: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 4

Building Section along Tat Chee Road

Page 5: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 5

Diaphragm Wall

Page 6: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 6

Typical Section cutting through MTR tunnels

Page 7: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 7

Site Formation andDiaphragm Wall Construction

Sub-divided into 7 stages from level +35m down to +20m.

Diaphragm wall and bored pile foundation construction work at the same time.

Two rows of temporary ground anchor were installed at Diap. Wall along Tat Chee Avenue Av as lateral support to cut during site formation excavation.

Page 8: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 8

Diaphragm Wall

Boring MachineTemporary Ramp

Preliminary Site Formation

Page 9: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 9

Tat Chee Av

Row of anchor as lateral retrain to diaphragm wall

Page 10: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 10

KCR Rail track Tat Chee Av. Hand-dug caisson in progress (bored pile)

Site at the up-hill portion had been formed down to +20m (level to the KCR Rail track level)

Page 11: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 11

Site formation close to its completion

Page 12: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 12

Site Formation andDiaphragm (cont.)

2m thick Diap. Wall constructed using traditional grab/chisel and reverse circulation trench cutting (hydrofraise) methods, both using bentonite slurry as a stabilizing agent.Removal of soil maintained at 2 exit-points arrangement as far as possibleLater stage of site formation merged with the main contract.

Page 13: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 13

Using a trench cutting machine (hydrofraise) to form the diaphragm wall panel

Page 14: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 14

Detail of the cutting drums of the hydrofraise(trench cutting machine)

Page 15: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 15

Forming the diaphragm wall panel using grabs (clamshell)

Page 16: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 16

Bored Pile Foundation

Total about 165 piles ranging from 1.8, 2.65 and 3.25m dia.3.25m dia piles were done by hand-dug method.Excavation done by steel grab/chisel and reverse circulation drilling method, both using steel casing as excavation support.With steel stanchion anchored into the pile as support to basement structure constructed in top-down arrangement.

Page 17: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 17

MTR Kwun Tong Line Tunnels

Bored Piles Layout

Page 18: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 18

Forming the bored pile using grab

Protective steel casing

Page 19: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 19

Forming the bored pile using Reversed Circulation Drill

Page 20: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 20

Stages of construction

Page 21: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 21

Stages of construction – from site formation to completion of superstructure

Diaphragm wall MTR TunnelsExcavation start at this point

Ground anchor to serve as lateral support during excavation

2.5m dia bored pile

Site formation stages

Page 22: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 22

Commencement of Top-down Basement ConstructionBasement excavation

below the ground slab

Upper floor slab and basement excavation and construction work at the same time

Excavation to form the vehicular ramp

Page 23: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 23

Work Flow direction

Completed vehicular ramp in advance to facilitate the removal of excavated spoil

Basement excavation and construction

Superstructure

Page 24: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 24

Atrium space

Page 25: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 25

Topping out of the entire structure

Page 26: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 26

Construction of Basement4-level full basement and 3-level semi-basement.Full basement constructed in top-down method.Construction generally arranged in a 6-phased manner, each with appropriate sub-sectioning depending to local layout. Spoil removal:1st stage, maintain a exit point to road level on the down-slope side of site; 2nd stage, use the newly constructed vehicle ramp (permanent structure) at the up-slope side.

Page 27: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 27

Steel stanchions to be inserted into bores piles as temporary support during the top-down construction of the basement structure (encased to become column later)

Steel stanchions

Page 28: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 28

Anchor plate at head of stanchion

Floor slab formwork for basement at +22m

Connecting the stanchion to the basement slab

Page 29: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 29

Exit point

Provision of temporary ramp to exit point at down-slopel location

Page 30: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 30

Basement underneath to be formed by top-down method

Vehicular ramp leading to basement carpark used as temporary access for removal of spoil during site formation and basement excavation

Page 31: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 31

Forming an entrance into he basement for carrying

out of excavation

Page 32: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 32

Progressing stage of superstructure & basement construction (1)

Page 33: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 33

Progressing stage of superstructure & basement construction (2)

Page 34: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 34

Progressing stage of superstructure & basement construction (3)

Page 35: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 35Progressing stage of superstructure & basement construction (4)

Page 36: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 36

Progressing stage of superstructure & basement construction (5)

Page 37: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 37

Principle of top-down method: Construct the ground slab first (in this case slab between full and semi-basement at +20m). Provide an entrance to the basement to facilitate downward excavation (between portion 2 & 3 at the first start). Excavate downward until the proceeding slab being cast. Repeat the excavation and basement slab casting horizontally and vertically until the entire basement finished. Cast/encase other vertical elements (staircase, ramps or columns) at time appropriate.

Page 38: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 38

Forming the first basement slab at +20m

Page 39: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 39

Steel columns erected in the bored pile helps to support the ground slab at the beginning of the top-down basement construction

Page 40: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 40

Formwork for the lower basement slab being erected

Excavation in progress

Upper basement slab already cast

Excavation and casting the basement slab in a top-down manner

Page 41: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 41

Steel columns support the ground slab at the beginning stage

Page 42: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 42

Excavation along Tat CheeAvenue where rockheadlocated close to ground

Page 43: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 43

Rock cutting carried out under the steel shore

Page 44: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 44

The Main Structure

Traditional timber panel formwork was used.Majority of structure in span ranging from 8.5m to 16m, some post-tensioned beams up to 35m and 48m.Strength of concrete in 40 (in-situ) and 45 (post-tensioned).Phasing and sectioning arrangement somewhat similar to basement construction, but more complicated due to the layout of the shopping mall.

Page 45: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 45

Portion 1

Portion 2

Portion 3

Portion 4

Portion 5

Portion 6

Construction of the superstructure in complicated phases

Page 46: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 46

Superstructure constructed using traditional manual timber formwork

Page 47: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 47

Construction of the superstructure at its final stage (observe the complicated sectioning arrangement of formwork)

Page 48: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 48

series

Page 49: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 49

Steel fixing for the superstructure structure

Page 50: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 50

Elevation along Tat Chee Avenue

Office block48m span post-tensioned girder beams

Skating rink below

Page 51: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 51

Main Structure : Other features

- existence of large volume atrium spaces (120m x 35m high, 80m x 40)

- ice skating ring measures 46m (span) x 70m x 30m high)

- fully glazed sky light (180m x 22m for mall, 30m x 35m for office)

- Glass wall total 3500 sq m.

Page 52: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 52

Isolated “Island” sub-divided by the “River” & “canyon”

The “River”

The “canyon”

Complicated spacing arrangement within the superstructure

Page 53: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 53

Page 54: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 54

The “River”taking shape

Escalator spanning below two levels of the shopping mall

Page 55: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 55

Steel frame that formed the skeleton of the skylight of “River”and “Canyon”

Intermediate frames

Main frame

Page 56: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 56

Installing the glazing panels for the skylignt

Page 57: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 57

Office block

Roof plan showing layout of “River” & “Canyon”

Page 58: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 58

Isometric view of the Festival Walk superstructure

Page 59: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 59Glass wall that form the “Canyon”

Page 60: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 60

Forming the glass wall at end-side of Canyon

Page 61: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 61

Cladding the glass wall of the “Canyon”

Page 62: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 62

GI grille (A/C compressors behind

Powder coated metal panels

Marble slab

Page 63: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 63

Difficulties encountered in the project

Very large scale of works – site formation, volume of excavation, large layout, huge amount of formwork and concrete, interior space that fitting out works required etc.

Very deep excavation and the required support.Works in close proximity with MTR facilities and tunnels.

Difficult phasing and sectioning arrangement.Relatively tight schedule.Very high headroom and difficult accessible interior spaces sub-divided by the atrium.

Page 64: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 64

Complicated teething arrangement between interface of phased sections (1)

Steel stanchion to support basement slab

1.2m thick slab (MTR tunnel tubes below)

Page 65: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 65

Complicated teething arrangement between interface of phased sections (2)

Page 66: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 66

Bored-piles as protection to pedestrian shaft

Working close to the MTR pedestrian facilities – in-situ bored piles were constructed to protect during excavation

Page 67: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 67

Protecting the MTR pedestrian facilities

Steel strut supporting pedestrian shaft to partially completed basement structure

Page 68: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 68

MTR pedestrian and ventilation shaft

Structural steel strut frame to stabilize the shaft

Squeezing difficultly into the ground to form the basement structure when working close to the MTR facilities

Page 69: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 69

Cut into rockhead to extend diap. wall further downward

Diap. wall being concreted

Underpinning to extend diaphragm wall panels further down into the rockhead

Page 70: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 70

Vast volume within the atrium add difficulty in the carrying out of superstructure and interior works

Page 71: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 71

Finishing the atrium formed within the “River”

Page 72: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 72

The “River” and the skylight

Page 73: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 73

The 48m-span interior space at the skating rink and food-stall area

Page 74: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 74

Finishing the skating rink

Page 75: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 75

Finishing the 20m-high, 48m-span Skating Ring

Page 76: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 76

Construction of a series of linking bridge in structural steel within the atrium space of the Skating Rink

Page 77: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 77

The vast interior space within the long-span atrium area (skating rink)

Page 78: The Festival Walk - City University of Hong Kongpersonal.cityu.edu.hk/bswmwong/photo_lib/pdf/Fest... · Raymond Wong 16 Bored Pile Foundation Total about 165 piles ranging from 1.8,

Raymond Wong 78

End of presentation


Recommended