+ All Categories
Home > Documents > The Filling Procedure - KKT Chillers, Inc. · 4/6/2016 Filling Procedure/ TSG Manager AF 4...

The Filling Procedure - KKT Chillers, Inc. · 4/6/2016 Filling Procedure/ TSG Manager AF 4...

Date post: 30-Jul-2018
Category:
Upload: trandat
View: 213 times
Download: 0 times
Share this document with a friend
37
The Filling Procedure Model(s): ECO Series
Transcript

The Filling Procedure

Model(s):

ECO Series

4/6/2016 Filling Procedure/ TSG Manager AF 2

What is needed!

1. Pump

2. 3 water hoses with metric adapters (found on the chiller pump)

3. Glycol (Premixed 37% of KKT Protect)

4. Hand tools

5. Pressure gauge

6. Chiller key

4/6/2016 Filling Procedure/ TSG Manager AF 3

Method of Filling

What is “The Push-Through Method”?

It is the most effective method for purging air out of the closed water loop

system. The trap air will travel throughout the system and make its way back to

the chiller by means of an external pump.

The external pump is used to push through the chiller, IFP, and MRI system. In

a form of a bypass at the chiller, a bucket is ran inline of the external pump to

collect the purged glycol to be recirculated into the system.

4/6/2016 Filling Procedure/ TSG Manager AF 4

Connecting to the Chiller

1. Remove the pump compartment panel.

2. Connect the discharge port of the pump to the drain valve of the chiller via

hose.

3. Connect inlet port of the pump to the glycol bucket via hose.

4. Connect a hose from the drain valve before the filter ball valve to the

glycol bucket.

5. Verify connections

4/6/2016 Filling Procedure/ TSG Manager AF 5

Step 1

Remove pump compartment panel.

Chiller key needed

4/6/2016 Filling Procedure/ TSG Manager AF 6

Step 2

Connect discharge port of the pump to

the drain valve of the chiller via hose.

4/6/2016 Filling Procedure/ TSG Manager AF 7

Step 3

Connect inlet port of the pump to the glycol bucket via hose.

4/6/2016 Filling Procedure/ TSG Manager AF 8

Step 4

Connect a hose from the drain valve before the filter ball valve to the glycol

bucket.

4/6/2016 Filling Procedure/ TSG Manager AF 9

Step 5

Verify connections

4/6/2016 Filling Procedure/ TSG Manager AF 10

Steps before filling

1. Verify the chiller is powered off!

2. Remove fuses from the“17F1” pump fused breaker!

3. Verify IFP is powered off!

4. Verify filter ball valve to the chiller is closed!

5. Verify all valves to the IFP are open.

6. Verify air bleeders are open.

7. Verify pipe run and check for any bypass loops installed on the contractors

piping from the chiller to the IFP. (If installed, close the valve)

8. Verify chiller height from scanner.

9. Verify expansion tank nitrogen pressure.

4/6/2016 Filling Procedure/ TSG Manager AF 11

Step 1

Verify the chiller is powered off!

4Q1 should be on the “0” position

4/6/2016 Filling Procedure/ TSG Manager AF 12

Step 2

Remove fuses from the“17F1” pump fused breaker!

4/6/2016 Filling Procedure/ TSG Manager AF 13

Step 3

Verify IFP is powered off!

4F1 should be on the “0ff” position

4/6/2016 Filling Procedure/ TSG Manager AF 14

Step 4

Verify filter ball valve is closed!

Valve handle should be pointing upwards

4/6/2016 Filling Procedure/ TSG Manager AF 15

Step 5

Verify all valves to the IFP are open.

4/6/2016 Filling Procedure/ TSG Manager AF 16

Step 6

Verify all air bleeders are open.

IFP, Chiller, and Water Loop

4/6/2016 Filling Procedure/ TSG Manager AF 17

Step 7

Verify pipe run and check for any bypass loops installed on the contractors

piping from the chiller to the IFP.

(If installed, close the valve)

Ball valve handle should be positioned away from flow

4/6/2016 Filling Procedure/ TSG Manager AF 18

Step 8

Verify chiller height from scanner.

Important factor in determining IFP static fill

4/6/2016 Filling Procedure/ TSG Manager AF 19

Step 9

Verify expansion tank nitrogen pressure!

The reserve and operating tank should be pressurized at 0.6 Bar.

Remove cap and check with a pressure gauge.

4/6/2016 Filling Procedure/ TSG Manager AF 20

Filling the System

1. Power on the chiller!

2. Power on the IFP!

3. Verify that the 3 way valve at the IFP is open.

4. Power on external filling pump and open the drain valves. Perform “The

Push-Through Method”.

5. Fill the system to static on the IFP.

6. After desired pressure, close the drain valves and power off the external

pump.

4/6/2016 Filling Procedure/ TSG Manager AF 21

Step 1

Power on the chiller!

“4Q1” should be on the “I” position.

“17F1” should have the fuses removed!

Powering on the chiller will ensure the chiller sends a signal to the IFP to activate the 3 way valve

to the open position. This makes it easier to purge the system while performing “The Push-Through

Method”.

4/6/2016 Filling Procedure/ TSG Manager AF 22

Step 2

Power on the IFP!

4F1 should be on the “ON” position

4/6/2016 Filling Procedure/ TSG Manager AF 23

Step 3

Verify that the 3 way valve at the IFP is open.

Position should be at “9”

4/6/2016 Filling Procedure/ TSG Manager AF 24

Step 4

Power on the external filling pump and open the drain valves.

Perform “The Push-Through Method”.

Allow the external pump to run for 5-10 minutes. Inspect the amount of air pouring out the hose. If

a great amount of air remains pouring out, allow more time to circulate the external pump.

It is important not to fully open both drain valves while performing “The Push-Through Method”,

glycol may over-fill the glycol bucket.

4/6/2016 Filling Procedure/ TSG Manager AF 25

Step 5

Fill the system to static on the IFP.

Chiller higher than the IFP panel → 1.7–1.9bar, Read at the IFP

Limitation: 10m above IFP

Chiller lower than the IFP panel or on the same level → 1.1–1.5bar, Read at the IFP

Limitation: 30m below IFP

4/6/2016 Filling Procedure/ TSG Manager AF 26

Step 6

After desired pressure, close the drain valves

and power off the external pump.

4/6/2016 Filling Procedure/ TSG Manager AF 27

Running the Pump, Venting the Air

1. Power off the chiller!

2. Add the fuses to the“17F1” pump fused breaker!

3. Close all air vents!

4. Power on the chiller!

5. Pump will begin to run. Allow the pump to run for 15-30 minutes

6. Power off the chiller!

7. Open all air vents, purge the remaining air.

8. Clean the strainers!

9. Power on the chiller!

10. Verify operation!

4/6/2016 Filling Procedure/ TSG Manager AF 28

Step 1

Powered off the chiller!

4Q1 should be on the “0” position

4/6/2016 Filling Procedure/ TSG Manager AF 29

Step 2

Add the fuses to the“17F1” pump fused breaker!

4/6/2016 Filling Procedure/ TSG Manager AF 30

Step 3

Close all air vents!

IFP, Chiller, and Water Loop

4/6/2016 Filling Procedure/ TSG Manager AF 31

Step 4

Power on the chiller!

4Q1 should be on the “I” position

4/6/2016 Filling Procedure/ TSG Manager AF 32

Step 5

Pump will begin to run. Allow the pump to run for 15-30 minutes.

4/6/2016 Filling Procedure/ TSG Manager AF 33

Step 6

Powered off the chiller!

4Q1 should be on the “0” position

4/6/2016 Filling Procedure/ TSG Manager AF 34

Step 7

Open all air vents, purge the remaining air.

If the pressure on the manometers drops. Repeat Steps 4-6 of “Filling the

System”

4/6/2016 Filling Procedure/ TSG Manager AF 35

Step 8

Clean the strainers!

Clean the filter strainer before the next-to last pass. The filter ball valve allows

you to clean the strainers with minimal loss of glycol. Please be sure to clean

the strainers at the IFP and chiller!

4/6/2016 Filling Procedure/ TSG Manager AF 36

Step 9

Power on the chiller!

4Q1 should be on the “I” position

4/6/2016 Filling Procedure/ TSG Manager AF 37

Step 10

Verify Operation!

Pressure at the pump:

1.1-1.5 bar.

IFP Pressure differential:

(Day Mode) 3-4 Bar

(Night Mode) 1.4 Bar


Recommended