Amphibious Construction Battalion Two. The Final Link in the Sealift Chain. Maritime Prepositioning Force. Joint Logistics Over The Shore (JLOTS). BENIGN. CMPF. Chain of Command. CINCLANTFLT. COMNAVSURFLANT. COMPHIBGRUTWO. COMNAVBCHGRUTWO. ACB-2. BMU-2. ACU-2. ACU-4. Mission Areas. - PowerPoint PPT Presentation
Popular Tags:
27
The Final Link in the Sealift Chain Amphibious Construction Battalion Two
Transcript
Page 1: The Final Link in the Sealift Chain

The Final Link in the Sealift Chain

Amphibious Construction Battalion Two

Page 2: The Final Link in the Sealift Chain

Maritime Prepositioning Force

Joint Logistics Over The Shore (JLOTS)

Page 3: The Final Link in the Sealift Chain

BENIGN

Page 4: The Final Link in the Sealift Chain
Page 5: The Final Link in the Sealift Chain
Page 6: The Final Link in the Sealift Chain
Page 7: The Final Link in the Sealift Chain

CMPF

Page 8: The Final Link in the Sealift Chain
Page 9: The Final Link in the Sealift Chain
Page 10: The Final Link in the Sealift Chain
Page 11: The Final Link in the Sealift Chain
Page 12: The Final Link in the Sealift Chain
Page 13: The Final Link in the Sealift Chain
Page 14: The Final Link in the Sealift Chain
Page 15: The Final Link in the Sealift Chain
Page 16: The Final Link in the Sealift Chain

Chain of Command

COMNAVBCHGRUTWO

COMPHIBGRUTWO

COMNAVSURFLANT

CINCLANTFLT

ACB-2 ACU-2BMU-2 ACU-4

Page 17: The Final Link in the Sealift Chain

Mission Areas

• Causeway Ferry

• Roll On/Roll Off Discharge Facility (RRDF)

• Amphibious Assault Bulk Fuel/Water System (AABFS/AABWS)

• Offshore Petroleum Discharge System (OPDS)

• Elevated Causeway, Modular (ELCAS-M)

• Defensive Military Operations

• Camp Support

Page 18: The Final Link in the Sealift Chain

Barge Ferry System

• Side Loadable Warping Tug (SLWT)

• Causeway Section Powered (CSP)

• Causeway Section Non-Powered (CNSP)

Page 19: The Final Link in the Sealift Chain

MPS-1 Lighterage

• 4 SLWTs• 16 CSPs• 14 Intermediates• 16 Beach Ends• 8 LCM-8s

• For Dynamic Mix:

Instream: 8 rolling stock/hour

Pierside: 20/hour.

Page 20: The Final Link in the Sealift Chain

Roll On/Roll Off Discharge Facility (RRDF)

Page 21: The Final Link in the Sealift Chain

• 5,000 ft of 6” conduit (Fuel)• 10,000 ft of 4” conduit (Water)• Deploy from Barge Ferry or LCU• Install in 8 hours• 700Kgal/day

Amphibious Assault BulkFuel/Water System

Page 22: The Final Link in the Sealift Chain

Offshore Petroleum Discharge System (OPDS)

• Single Product 4 NM

• Dual Product 2 NM

• 1.2 Mgal/day

• First Fuel in 48 hrs.

• Total install in 7 days

• Water Depth 35-200 ft.

• Service Life 2 yrs.

Page 23: The Final Link in the Sealift Chain

Lighterage support w/ OPDS

• SLWT Lighterage support:

• 3 tow tugs• Converted lay repair

barge 1 SLWT • Dive boat - LCM 8

• OUB Lighterage support:

• 3 tow tugs - OUBs• Converted lay repair

barge 1 OUB • Dive boat - OUB

Page 24: The Final Link in the Sealift Chain

Elevated Causeway-Modular

- Up to 3000 ft length

- 20 FSW at MLW

- 7 Days to Erect

- UCT Site Survey

Page 25: The Final Link in the Sealift Chain

Defensive Military Operations

Page 26: The Final Link in the Sealift Chain

Camp Support

• Berthing Tents• Galley/Scullery• Laundry• Showers/Heads• Transportation• Beach Salvage• Water Purification• Medical/Admin

Page 27: The Final Link in the Sealift Chain

Recommended