+ All Categories
Home > Documents > THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS...

THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS...

Date post: 03-Feb-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
46
THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS TRACKING FOR INVENTORY MANAGEMENT PROCESS IN CONSTRUCTION PROJECTS SITI RADZIAH BINTI LIWAN A project report submitted in partial fulfilment of the requirement for the award of the Degree of Master of Technology Management. Faculty of Technology Management and Business Universiti Tun Hussein Onn Malaysia August 2015
Transcript
Page 1: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS TRACKING FOR

INVENTORY MANAGEMENT PROCESS IN CONSTRUCTION PROJECTS

SITI RADZIAH BINTI LIWAN

A project report submitted in partial

fulfilment of the requirement for the award of the

Degree of Master of Technology Management.

Faculty of Technology Management and Business

Universiti Tun Hussein Onn Malaysia

August 2015

Page 2: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

iv

ABSTRACT

Inventory management is important especially in construction projects because

materials and components constitute 50-60% of the total project cost. While

inventory management has increased concerned among various parties within the

project, materials tracking for inventory management also act the same way. Material

tracking could provide timely information on materials availability and enables real-

time on-site measurement of the project performance which is important for

inventory management. However, material tracking practices in construction projects

has been using manual method and it has many drawbacks. Although the application

of advanced technology is needed as it has ability to assist materials tracking,

however; there is still lack of materials tracking framework for inventory

management process in construction projects. Therefore, the research aims to fill in

this gap by developing an on-site material tracking framework for improving

inventory management processes in Malaysian construction projects. In this research,

potential implementation of RFID technology for materials tracking and the existing

material tracking practices in construction projects were identified. Literature review

and case studies approach were conducted to obtain data of the research. Ten case

studies was undertaken to investigate inventory management process and material

tracking practices in Malaysia construction projects. The data analysis involves both

within case analysis and cross-case analysis. The findings conclude by developing an

on-site material tracking framework for inventory management process which

consists of seven components namely; manufacturing, materials delivery, materials

arrival, materials storage, materials use, on-site control centre and report generation.

The framework would be beneficial for contractors having intention to adopt RFID

technology to assist and facilitate materials tracking particularly at the site storage

area.

Page 3: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

v

ABSTRAK

Pengurusan inventori penting terutamanya di dalam projek pembinaan kerana bahan

dan komponen pembinaan menyumbang sebanyak 50-60% daripada kos keseluruhan

projek. Pengurusaan inventori telah menarik perhatian pelbagai pihak yang terlibat di

dalam projek pembinaan begitu juga dengan pengesanan bahan untuk pengurusan

inventori. Pengesanan bahan dapat memberikan maklumat terkini mengenai bahan

binaan dan membolehkan prestasi projek diukur mengikut keadaan semasa di tapak

pembinaan di mana ini adalah penting untuk pengurusan inventori.

Walaubagaimanapun, kaedah pengesanan bahan yang digunapakai di dalam projek-

projek pembinaan adalah menggunakan kaedah manual di mana ia mempunyai

banyak kelemahan. Walaupun pengunaan teknologi amat diperlukan untuk

membantu pengesanan bahan binaan, tetapi; kerangka kerja pengesanan bahan untuk

tujuan pengurusan inventori di tapak pembinaan masih lagi kurang. Oleh itu, kajian

ini bertujuan untuk membangunkan satu kerangka kerja pengesanan bahan untuk

membantu memperbaiki proses pengurusan inventori di dalam projek pembinaan di

Malaysia. Di dalam kajian ini, potensi penggunaan teknologi RFID untuk

pengesanan bahan serta kaedah pengesanan bahan yang digunapakai di dalam projek

pembinaan dikenalpasti. Kaedah literatur dan kajian kes digunakan untuk

mendapatkan maklumat penyelidikan. Sebanyak sepuluh kajian kes dijalankan untuk

mengetahui proses pengurusan inventori dan kaedah pengesan bahan binaan yang

digunakan di dalam projek pembinaan di Malaysia. Analisis data kajian melibatkan

analisis kes secara individu dan analisis kes secara bersilang. Dapatan kajian ini

disimpulkan dengan membangunkan satu kerangka kerja pengesanan bahan binaan

untuk membantu proses pengurusan inventori di mana ianya terdiri daripada tujuh

komponen iaitu; proses pengeluaran, penghantaran, penerimaan bahan, penyimpanan

bahan, pengeluaran, pusat kawalan (di tapak pembinaan) dan penjanaan laporan.

Kerangka kerja ini amat berguna bagi kontraktor yang mempunyai keinginan untuk

mengaplikasikan teknologi RFID untuk membantu dan mempercepatkan proses

pengesanan bahan binaan terutamanya di kawasan stor binaan.

Page 4: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

vi

CONTENTS

TITLE i

DECLARATION ii

ACKNOWLEDGEMENT iii

ABSTRACT iv

CONTENTS vi

LIST OF TABLES xi

LIST OF FIGURES xii

LIST OF SYMBOLS AND ABBREVIATIONS xiii

CHAPTER 1 INTRODUCTION 1

1.1 Research Background 1

1.2 Problem Statement 3

1.3 Research Questions 5

1.4 Aim and Objectives 5

1.5 Scope of the Research 5

1.6 Research Methodology 6

1.7 Significance of the Research 9

1.8 Structure of the Thesis 9

1.9 Summary 10

CHAPTER 2 MATERIALS TRACKING FOR INVENTORY 11

MANAGEMENT PROCESS

2.1 Introduction 11

2.2 Inventory 11

2.2.1 Definitions of Inventory 12

Page 5: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

vii

2.2.2 The Importance of Inventory 12

2.3 Inventory Management Processes 14

2.3.1 Planning 14

2.3.2 Purchasing 15

2.3.3 Materials Delivery 15

2.3.4 Storage 16

2.3.5 Materials Issue 16

2.4 Inventory Management in Construction Projects 17

2.5 Inventory Management Problems 18

2.6 Material Tacking for Inventory Management 21

2.6.1 The Importance of Material Tracking 21

2.6.2 Current Approaches of Materials Tracking 22

2.6.3 Materials Tracking Technology 24

2.6.3.1 Bar-coding 24

2.6.3.2 Radio Frequency Identification (RFID) 26

2.6.3.3 Global Positioning System (GPS) 28

2.6.4 Benefits of ICT for Materials Tracking 29

2.7 RFID Technology for Materials Tracking 31

2.7.1 RFID Technology Application 31

2.7.2 RFID Components 33

2.7.2.1 RFID Tags 33

2.7.2.2 RFID Readers 35

2.7.3 The Advantages of RFID Technology 36

2.7.4 RFID for Materials Tracking in Construction 38

Projects

2.7.5 Issues in RFID Implementation 39

2.7.5.1 Costs 40

2.7.5.2 Standardisation 40

2.7.6 Current RFID Situations in Malaysia 41

2.8 Potential Implementation of RFID for Materials 42

Tracking in Malaysian Construction Projects

2.9 Several Materials Tracking Framework 44

2.9.1 Automated Project Schedule and Inventory 44

Monitoring Framework

Page 6: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

viii

2.9.2 Real-time Materials Tracking Framework 46

2.9.3 Ubiquitous Tracking and Locating of 48

Construction Resources using GPS, GIS and RFID

2.9.4 RFID-facilitated Construction Materials 49

Management (RFID-CMM) Framework

2.9.5 Integrating RFID, GPS and GPRS for 51

Real-time Data Collection

2.9.6 Information Lifecycle Management Framework 53

for Material Control on Construction Sites

2.10 Discussion of Materials Tracking Framework 54

2.11 Theoretical Framework for On-Site Materials Tracking 55

2.12 Summary 59

CHAPTER 3 RESEARCH METHODOLOGY 60

3.1 Introduction 60

3.2 Introduction to Research 60

3.3 Research Philosophy 62

3.4 Research Approaches 63

3.4.1 Quantitative Research 63

3.4.2 Qualitative Research 66

3.4.2.1 Case Studies 68

3.5 Research Strategy Decision 70

3.5.1 Selection of Research Methodology 71

3.5.2 Selection of Multiple Case Studies and 71

Interview Techniques

3.5.2.1 Multiple Case Studies 72

3.5.2.2 Interview Technique 75

3.6 The Methods Adopted for this Research 76

3.6.1 Literature Review 78

3.6.2 Case Studies 80

3.6.2.1 Selection of Respondents 84

3.6.3 Framework Development 85

3.7 Summary 87

Page 7: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

ix

CHAPTER 4 DATA ANALYSIS AND FINDINGS 88

4.1 Introduction 88

4.2 Objectives of Case Studies 88

4.3 Case Studies Projects 89

4.3.1 Case A: Agricultural Complex Development 90

4.3.2 Case B: School Development Project 94

4.3.3 Case C: Residential Development Project 97

4.3.4 Case D: Hypermarket Development Project 100

4.3.5 Case E: Condominium Development 103

4.3.6 Case F: Residential Development Project 107

4.3.7 Case G: Public Infrastructure Development 110

4.3.8 Case H: Residential Development Project 113

4.3.9 Case I: Public Institution Development 116

4.3.10 Case J: Public Secondary School 120

Development

4.4 Key Findings form Case Studies 124

4.4.1 Inventory Management Process 129

4.4.2 Problems in Materials Tracking 133

4.4.3 Materials Tracking Technology for Inventory 135

Management

4.4.4 Improving Materials Tracking for Inventory 140

Management

4.4.5 Integration of Inventory Management and 142

Resource Modelling

4.5 Requirement for Real-Time Materials Tracking 145

for Inventory Management Framework

4.6 Summary 147

CHAPTER 5 ON-SITE MATERIALS TRACKING 148

FRAMEWORK FOR INVENTORY MANAGEMENT

5.1 Introduction 148

5.2 On-Site Materials Tracking Framework for 148

Inventory Management- Components

Page 8: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

x

5.3 On-Site Materials Tracking Framework 152

5.4 Key Components 153

5.4.1 Manufacturing 153

5.4.2 Materials Delivery 154

5.4.3 Materials Arrival 155

5.4.4 Storage Area 156

5.4.4.1 Materials Storage 156

5.4.4.2 Materials Use 157

5.4.5 On-site Control Centre 159

5.4.6 Report Generation 160

5.5 Summary 161

CHAPTER 6 CONCLUSIONS AND RECOMMENDATIONS 163

6.1 Introduction 163

6.2 Summary 163

6.3 Conclusions 166

6.4 Research Contributions 168

6.5 Limitations of the Research 169

6.6 Recommendations for Future Research 169

6.6.1 Recommendations for Researchers 170

6.6.2 Recommendations for Industry Practitioners 171

6.7 Concluding Remarks 171

REFERENCES 172

APPENDICES 181

Page 9: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

xi

LIST OF TABLES

1.1 Research Objectives and Chapter Outcome 5

2.1 Summary of Inventory Management in Construction Projects 18

2.2 Inventory Management Problems in Construction Projects 19

2.3 Application of RFID Technology in Construction 27

2.4 Active versus Passive RFID Tags 34

2.5 RFID Tags Common Frequencies and their Uses 34

2.6 Summary of Materials Tracking Framework 57

3.1 Selection of Research Methodologies 61

3.2 Qualitative versus Quantitative Research 64

3.3 Comparison of Qualitative and Quantitative Data 67

3.4 Relevant Situation for Different Research Strategies 70

3.5 Project and Respondent Background 80

4.1 Project and Respondent Background 90

4.2 Summary of Cross-case Analysis 126

4.3 Inventory Management Process 129

4.4 Problems in Materials Tracking 134

4.5 The Application of Technology for Materials Tracking 136

4.6 Factors Improving Current Material Tracking Practices 140

4.7 The Integration Process 143

Page 10: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

xii

LIST OF FIGURES

1.1 The Research Process Flow Chart 7

2.1 Bar-coding Label 24

2.2 Typical RFID-based System 31

2.3 Active and Passive RFID Tags 33

2.4 Handheld Reader 35

2.5 Materials Tracking using RFID Reader 39

2.6 Automated Project Schedule and Inventory Monitoring 45

Process

2.7 Real-time Materials Tracking Framework 46

2.8 Automatic Data Collection System 48

2.9 RFID-facilitated CMM System 50

2.10 Automatic Data Collection using RFID, GPS and GPRS 52

2.11 A Conceptual ILM Framework for Material Control 53

2.12 Theoretical Framework for On-Site Materials Tracking 58

3.1 Selection of Research Methodology 62

3.2 Quantitative Research Process 65

3.3 Qualitative Research Process 66

3.4 Basic Types of Designs for Case Studies 73

3.5 Case Study Method 74

3.6 The Overall Research Process 77

5.1 On-Site Materials Tracking Framework for 151

Inventory Management

5.2 Materials Storage Process 156

5.3 Materials Use Process 158

5.4 On-Site Control Centre Process 160

5.5 Report Transmission Process 161

Page 11: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

xiii

LIST OF SYMBOLS AND ABBREVIATIONS

ADC Automatic Data Collection

AutoCAD Automated Computer Aided Design

Auto-ID Automatic Identification

BIM Building Information Modelling

BQ Bill of Quantities

C-aIS Context-aware Information System

CCTV Closed-Circuit Television Camera

CIDB Construction Industry Development Board

DO Delivery Order

E-mail Electronic Mail

GIS Geographic Information System

GHz Giga Heartz

GPS Global Positioning System

GPRS General Packet Radio System

GSM Global System for Mobile Communications

HQ Head Quarter

IBS Industrialised Building System

ICT Information and Communication Technology

ILM Information Lifecycle Management

ISO International Organisation for Standardisation

JIT Just-In-Time

kb kilo byte

kHz kilo Heartz

LADAR Laser Detection and Ranging

LAN Local Area Network

m metre

MHz Mega Heartz

MRO Materials Requisition Order

MS Materials Storage

MU Materials Use

Page 12: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

xiv

O&M Operation and Maintenance

PDA Personal Digital Assistant

PO Purchasing Order

QS Quantity Surveyor

RF Radio Frequency

RFID Radio Frequency Identification

RFID-CMM RFID-Facilitated Construction Materials Management

UHF Ultra High Frequency

UWB Ultra-Wide Bands

Page 13: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

xv

LIST OF APENDICES

APPENDIX TITLE PAGE

A Sample of Interview Questions 182

B Sample of Interview Transcript 187

C List of Publications 195

Page 14: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

CHAPTER 1

INTRODUCTION

This chapter presents the context of the research study. Firstly, it starts with brief

introduction to the research background and problem statement that brings to the

research interest in this study area. Secondly, this chapter states the aim and

objectives of the research and the methodology adopted in order to achieve the

research objectives. Finally, the chapter present the structure of the thesis.

1.1 Research Background The demand for construction development is increasing from day to day parallel with

increasing in the growth of population. A lot of development has been carried out

which comprise of the housing development, infrastructure, industry, institutions,

health care and others to fulfil the demand. In project development, materials are

among the important elements to be taken into consideration as they are the building

blocks that make up a project meanwhile material also constitute large amount of the

project costs (Lu et al., 2011). Previous research identified that material cost

comprise of 50-60% from the total project costs (Nasir, 2008; El-Ghazali et al.,

2011). Therefore, inventory which is part of materials also contribute significant

amount to the above percentage.

Inventory in general could be defined as the company’s raw materials, work

in process, supplies used in operations and finished goods which were used to ensure

smooth running of the business (Muller, 2011; Sahari et al., 2012). However, in

construction settings; inventory was referred as materials or components on hand;

which was kept by contractors for the smooth functioning of construction processes.

Inventory is also known as the stock of materials or components kept at the storage

Page 15: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

2

for future use in construction process. Adequate amount of inventory is crucial to

ensure the smoothness of construction processes and to maintain a healthy cash flow

for contractors (Lu et al., 2011). However, inadequate amount of inventory results in

job stoppage due to materials required for conducting construction works could not

be specified at time they are needed.

The management of inventory in construction projects is important where

significant amount of money was invested in every single activity. It involves the

management of materials or components as they were unloaded to the site storage

upon arrival at the project site. Several processes which considered important in

inventory management are materials planning, purchasing, materials delivery,

materials storage, and materials issue (Waters, 2003). Despite great demand for

managing inventory, however; there are several problems which bound existing

inventory management practices in construction projects. Those problems are:

materials shortage (Ali et al., 2010), over ordering and double handling of inventory,

missing materials; unavailability of storage space (Donyavi & Flanagan, 2009), and

incomplete and lack of up-to-date information regarding on-site stock (Navon &

Berkovich, 2006).

As inventory management has increase in importance, materials tracking for

inventory management also have received great attention. Material tracking for

inventory management process has become everyone’s concern as construction

materials usually come in bulk without proper identification and difficult to be

traced. Hence, material’s tracking is important as it could ensure that materials are

available at the right time, in the right place and at the right quantity at time are

needed to carry out construction work (Song, 2005). However, in construction

projects; the tracking of inventory along the supply chain and tracking their locations

at jobsites are among important problems related to construction materials (Song,

2005; Navon & Berkovich, 2006; Nasir, 2008). Thus, this research focuses on

material tracking practices for inventory management process in construction

projects particularly at the storage area.

Page 16: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

3

1.2 Problem Statement Existing material tracking practices for inventory management in construction

projects has several limitations. Material tracking practices relies on manual method

of collecting and recording data related to tracking activities which is labour

intensive (Ergen & Akinci, 2007). Sardroud et al. (2010) asserts that the data

collected using manual method could be questioned as it depends on workers skill

and level of productivity at time the data is taken during materials tracking. In

addition, received materials is often improperly recorded or not recorded at all (Ala-

Risku et al., 2010).

Navon and Berkovich (2006) has highlighted several limitations of manual

material tracking which are labour intensive, inaccurate and subjected to error-prone

which further leads to waste and surplus of materials, schedule delays, decrease in

productivity, and lack of up-to-date information regarding the status of materials.

Sardroud et al., (2010) also agreed that manual method of material tracking are

labour intensive and data collected is unreliable as they depend on workers

motivations and skills to track the materials during its arrival and at the storage area.

Moreover, the data collected through manual materials tracking are usually

kept and transferred in paper-based format which is difficult to be traced and

accessed in future. Hence, some information is being unavailable to the parties who

need access to them in a timely manner for decision making process (Sardroud et al.,

2010). Demiralp et al. (2012) also stated that manual material tracking practices are

time consuming, results in late deliveries, lead to mislocated components and

incorrect installations. Meanwhile, Grau et al. (2009) addressed several limitations of

material tracking in which it has raised difficulties among labour craft in accessing

the required material and components at time of materials consumption. Thus, this

provides less assurance for materials future identification.

Research conducted based on Malaysian construction projects have found

that construction projects suffered from several inventory management problems

such as improper planning and shortage of materials (Sambasivan & Yau, 2007). Ali

et al. (2010) also found that material shortage is the inventory management related

problems that contribute to delay among construction projects in the Klang Valley,

Malaysia. Hence, Ibrahim et al. (2010) added that surplus of materials are among

factors that contribute to project delay in Malaysian construction projects. The

Page 17: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

4

inventory management related problems that occur in Malaysian construction

projects is contributed by the inexistence of appropriate material tracking practices

for inventory management process.

However, the advancement in Information and Communication Technology

(ICT) provided an opportunity to improve material tracking practices for inventory

management process in construction projects. Previous researchers have introduced

technology to overcome the drawbacks of existing material tracking practices (Chen

& Li, 2006; Moselhi & El-Omari, 2006; Grau et al., 2009; Sardroud et al., 2010).

Technologies such as bar-coding, Radio Frequency Identification (RFID), Global

Positioning System (GPS), wireless technology and others has ability to facilitate

materials tracking for the purpose of inventory management and materials control.

Regarding to Moselhi and El-Omari (2006), bar-coding, RFID and other wireless

technology could improve the speed and accuracy of data acquisition in construction

projects in a cost effective manner.

Bar-coding technology has been used in materials tracking to provide instant

and up-to-date information on quantities of materials and equipments exchanged

between the store keepers and the working groups (Chen & Li, 2006). In contrast,

RFID technology could provide unique identification and real-time information

(Sarac et al., 2010) in construction projects. As ICT implementation offers great

advantage in terms of material tracking especially in the construction industry

abroad, therefore; ICT is expected to be adopted in Malaysian construction projects

to overcome inventory management related problems especially in the area of

materials tracking.

However, a framework is needed for successful adoption of technology for

materials tracking in construction projects. Although previous researchers such as

Gajamani and Varghese (2007), Kasim (2008), Sardroud et al. (2010), Ren et al.

(2011), Sardroud (2012) and Lee et al. (2013) have developed several materials

tracking framework, however; this framework does not focused on materials tracking

for inventory management at the storage area. Yet; there is still lack of example of

material tracking framework for inventory management processes in construction

projects particularly focusing at the storage area. Therefore, this research is intended

to develop an on-site material tracking framework for inventory management process

which act as guidance for contractors in order to successfully adopting technology

for materials tracking in construction projects.

Page 18: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

5

1.3 Research Questions Based on the problem statement, several research questions have been posed which

comprise:

(i) What is the potential implementation of RFID technology for material

tracking in Malaysian construction projects?

(ii) How does material tracking for inventory management process is practised

among Malaysian construction projects?

(iii) How to improve the on-site material tracking for inventory management

process in Malaysian construction projects?

1.4 Aim and Objectives This study aims to improve on-site materials tracking for inventory management

process in construction projects particularly at the storage area. Towards reaching the

aim of the research, the following objectives have been formulated as reflected in

Table 1.1.

Table 1.1: Research Objectives and Chapter Outcome

No. Objective Outcome

1. To study potential implementation of RFID technology for materials tracking in Malaysian construction projects

Chapter 2

2 To investigate existing material tracking practices for inventory management process in Malaysian construction projects.

Chapter 4

3 To develop an on-site materials tracking framework for improving inventory management processes in Malaysian construction projects.

Chapter 5

1.5 Scope of the Research The research focuses on developing an on-site materials tracking framework for

inventory management process in construction projects particularly at the site storage

area. The target population for this research is main contractors registered with

Construction Industry Development Board (CIDB) Grade 7 (G7) or registered with

Contractor Service Centre (PKK) Grade A. G7 contractors are selected as they has

unlimited tendering capacity (Construction Industry Development Board, 2013)

Page 19: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

6

therefore has experience in developing multi-million construction projects and has

high capability for using technology in their projects. However, the samples of this

research is only two hundred and thirty six (236) which consist of main contractors

specialised in building construction which located in three different states namely;

Johor, Selangor and Negeri Sembilan (CIDB, 2012). Those states are selected since

they are moving forward among other states in terms of having progressively

expanding in the volume of new construction development (Construction Industry

Development Board, 2012). Case study research was adopted as a research strategy

while semi-structured interview was used to gather data about the research.

Respondent of the research are related personnel having experience or involved

directly in inventory management and overall site management such as the project

manager, the site engineer and the site supervisor. The data obtained from semi-

structured interviews was analysed using matrix table and thus, presented as ‘within

case’ and ‘cross-case’ reports.

1.6 Research Methodology In achieving the aim and the research objectives, several research methods were

adopted. This includes literature review, case studies and development of the on-site

materials tracking framework for inventory management. Figure 1.1 shows the

method adopted for this research with the respective output from each activity.

Discussions in detail on the methodology adopted throughout the research were

presented in Chapter 3.

(a) Literature Review Literature related to the research was achieved from sources such as books, journal

articles, proceeding papers and online data sources such as webpage of firms,

governments, semi-government organizations and catalogues. Literature review in

this research starts with reviewing existing literature on RFID technology in material

tracking for inventory management in construction projects. This takes into account

the implementation of RFID for materials tracking either locally or internationally.

Upon reviewing the literature, the research problems were established concurrently.

Page 20: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

7

Literature Review

- Reviewing existing literature on RFID technology in material tracking for inventory management in construction projects.

Research contexts in RFID technology implementation for materials tracking and the successful RFID adoption in construction projects

Case Studies (Interviews)

- Investigates existing material tracking practices for inventory management in construction projects.

The inventory management processes, materials tracking problems, materials tracking technology for inventory management, improving materials tracking for inventory management and the integration of inventory management and resource modelling

Framework Development

- Develop on-site materials tracking framework for inventory management.

Research Method Activities Output

The outputs generated from the review are the research contexts in RFID technology

implementation for materials tracking and the successful RFID implementation in

construction projects.

Figure 1.1: The Research Process Flow Chart

(b) Case Studies: Interviews The case study approach was undertaken to gain primary data for this research. The

case or unit of analysis involved ten construction projects in order to investigate

existing material tracking for inventory management process within each case.

Construction projects participate in the research are selected due to several criteria.

Such criteria include the projects must be constructed by main contractors registered

On-site materials tracking framework for inventory management at the storage area

Page 21: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

8

with Construction Industry Development Board (CIDB) Grade 7 (G7) or registered

with Contractor Service Centre (PKK) Grade A.

The case studies involved face-to-face semi-structured interviews in which

the respondents are selected based on purposive sampling. According to Oliver

(2006), purposive sampling is a type of sampling in which the decisions regarding

the individuals to be participated in the research are determined by the researcher

based upon variety of criteria which required by him or her. Hence, respondents for

this research are selected based on their experience and involvement in inventory

management and the overall site management such as the project manager, the site

engineer or the site supervisor.

A list of predetermined and standardised questions was also prepared for the

interview which acts as the interview guideline. This is important as according to

Cavana et al. (2001), the semi-structured interview need to be carefully ordered and

worded in a detailed interview schedule. Finding from case studies reveal the

inventory management processes undertaken in each project, key problems related to

materials tracking, implementation of technology for materials tracking, several

approaches to improve materials tracking and the integration of inventory

management and resource modelling.

The identification of material tracking problems from each case study enables

the researcher to propose the adoption of ICT, particularly RFID technology to

overcome material tracking related problems within construction projects. However,

the decision to adopt RFID technology was made based on results from literature

review which reveals the advantages of RFID technology for materials tracking.

RFID implementation enables the material to be scanned automatically (Ozumba &

Shakantu, 2008; Sardroud, 2012), reduce labour hours in scanning materials, could

track work-in progress, improves antitheft protection and better inventory

management (Mehrjerdi, 2011).

(c) Framework Development The development of the on-site materials tracking framework for inventory

management process carried out from both literature review and case studies

findings. It starts with the identification of material tracking components and its

Page 22: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

9

element obtained from previous literature. The on-site materials tracking framework

was developed based on the suitability of each component and elements with the

actual material tracking practices for inventory management process carried out on-

site. Several questions were designed for the interviews to enable the researcher to

identify suitable components and important elements for the framework. The

developed framework is important to successfully adopting technology in materials

tracking for inventory management process in Malaysian construction projects.

1.7 Significance of the Research This research is expected to contribute to the body of knowledge and study by:

identifying the current status of RFID implementation for material tracking in

Malaysian construction projects,

exploring inventory management processes and identifying existing problems

related to material tracking in Malaysian construction projects, and

propose new on-site material tracking framework for inventory management

by improving the existing framework.

1.8 Structure of the Thesis The thesis is structured into six chapters respectively. The content of each chapter are

as follows:

Chapter 1 briefly introduces the content of the research. It explains the research

background, problems that bring into the research initiative, the aim and objectives;

and the methodology used in the research.

Chapter 2 reviews the literature related to the research. It focuses on the material

tracking practices for inventory management processes in construction sites. The

chapter also review the current ICT implementation to facilitate materials tracking in

construction projects.

Page 23: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

10

Chapter 3 reviews the overall methodology in business research and the method

adopted to carry out this research project. This chapter also provide justification for

the adoption of the specific research method.

Chapter 4 explains the findings from the case studies undertaken for the research.

The findings were used to reveal the material tracking problems and the use of ICT

to improve current material tracking practices in construction projects.

Chapter 5 focuses on development of on-site materials tracking framework. In this

chapter, each component of the on-site materials tracking framework were discussed

in details and their integration with RFID were discussed.

Chapter 6 presents the summary and conclusions for the thesis. This chapter

discusses the research findings, conclusions, contributions and several limitations of

the research. In addition, this chapter also provides some recommendations for future

research.

1.9 Summary This chapter outlined several problems in materials tracking for inventory

management and justify the importance to conduct the research. Several problems

have been identified regarding materials tracking for the inventory management in

construction projects. The manual method of material tracking use in construction

projects are labour intensive and rely greatly on paper-based reports which is

difficult in term of traceability. This chapter also outlined the aim and the research

objectives; together with the research methodology and structure of the thesis. The

next chapter explained the literature undertaken for this research.

Page 24: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

CHAPTER 2

MATERIALS TRACKING FOR INVENTORY MANAGEMENT PROCESS

2.1 Introduction This chapter reviews inventory management and material tracking technologies for

inventory management process in construction projects. Firstly, it describes the

inventory management as a whole which consist of definition, the process, the

importance and problems in inventory management; and the application of

information and communication technology (ICT) in managing inventory. Secondly,

it explains the need for material tracking and existing material tracking practices in

construction projects. Thirdly, it describes the material tracking technology and its

benefits for material tracking. Finally, the chapter demonstrated the use of RFID for

material tracking and issues of deployment.

2.2 Inventory Adequate amount or level of inventory is important in every business to ensure

business processes for example the manufacturing of goods could be carried out

successfully. Research conducted by Lu et al. (2011) has found that, materials

(including inventory) constitute a great portion from the total costs in construction

projects. However, in order to have better understanding on inventory; it is important

to go through their definitions and why inventory is so important.

Page 25: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

12

2.2.1 Definitions of Inventory In general, inventory could be defined as the company’s raw materials; work in

process, supplies used in operations, and finished goods (Muller, 2011; Sahari et al.,

2012). Inventory is the amount of raw materials, fuels, lubricants, spare parts and

semi-processed material to be stocked for the smooth functioning of the plant

(Chitale & Gupta, 2006). According to Maré (2006), inventory were use to mean

several different things, such as;

the company’s or firms raw materials;

work in process;

components/sub-assemblies;

finished goods;

maintenance, repair and operational supplies; and

transportation inventory (movement inventory).

In construction projects, inventory refers to materials or components on hand;

which is kept by construction firms or projects as stock for the smooth functioning of

construction process. In addition, inventory in construction also could be referred to

as the amount of materials or components on the storage area. Regardless their

definitions, it is important for businesses to manage inventory for their survival.

Adequate amount of inventory helps company to fulfil customer need and demands,

and vice versa; the company may incurred loss in profit margins. Therefore, there is

a need for effective and efficient inventory management processes in construction

projects. As according to Navon and Berkovich (2005), the main benefits arises from

efficient materials management or inventory management are increased productivity,

avoidance of delays, reduction of labour working hours and reduction in materials

cost. Thus, effective and efficient inventory management processes is needed to help

improve overall inventory management in construction projects.

2.2.2 The Importance of Inventory Why businesses need inventory or why inventory is so important? Why do

businesses keep inventory in their organisations? As in just-in-time (JIT)

Page 26: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

13

manufacturing concept, keeping a stock or inventory is considered as a waste.

However, according to Muller (2011) there are several reasons for holding inventory

in organisations. Such reasons are:

Predictability

In order to engage in capacity planning and production scheduling,

organisations need to control the inventory quantity (raw materials, parts, and

sub-assemblies) they had processed at a given time. This is important as

inventory will act as a buffer as what you need from what you want.

Fluctuations in demand

Inventory on hand acts as a protection against undesirable market conditions.

Inventory of finished goods is important in protecting companies from an

increase in customers demand.

Unreliability of supply

Inventory will provide organisations with a protection from unreliable

suppliers and in scarce conditions where it is difficult to ensure a steady

supply of materials and items.

Price protection

Buying and keeping large quantities of inventory at appropriate time helps

avoid the impact of cost inflation.

Quantity discounts

Buying large amount of items such as buying in bulk is much susceptible to

quantity discounts as compared to buying in smaller quantities.

Lower ordering costs

Buying large quantity of several items, but in less frequent will result in

lower ordering costs. This are differed with buying a small quantities of an

item, but in much frequent.

Keeping or having adequate level of inventory is important for every

business. This is due to inventory carries large amount of hidden cost (Sahari et al.,

2012) such as the cost of equipment to handle them, warehouse, deterioration or

damage if any, and other related costs. In construction projects, adequate amount of

inventory (materials, equipments, tools, etc.) is important to ensure that all

construction works could be carried out according to schedule. Apart from adequate

Page 27: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

14

amount of inventory, the management of inventory itself is an important concern in

construction projects. Therefore, current material tracking practices used in

managing inventory in construction projects has successfully captured a great

concern among contractors and clients.

2.3 Inventory Management Processes In general, inventory management is specifically responsible for the management of

inventory as they arrive at the construction site, their storage and the disposal of

inventory wastes. According to Waters (2003), inventory management is so entwined

with activities in logistics which responsible for all aspects of the movement and

storage of materials in a supply chain. Inventory management in construction

projects consists of five main processes. Those processes were discussed in the

following sub-sections.

2.3.1 Planning Planning is the initial process and could be considered as the most important process

in inventory management. Materials planning involve determining the need for

materials to carry out production process and other related works. During planning, if

material is estimated wrongly; the stock level will become too high and generate

other hidden costs. However if the stock level is too low, it may lead to another

problems which related to the distribution (Heck, 2009).

In construction, appropriate planning for materials is important and must be

done concurrently with engineering, construction and other project plans (Kasim,

2011). The author also identifies the process in planning which includes quantifying,

ordering and scheduling. Materials planning in construction involve activities such as

determine the type of materials which to be used in construction works, its quantities,

and specifications in order to carry out construction works. Material planning in

construction projects has significant contribution in increasing work productivity,

increase profit and facilitating the timely completion of construction projects.

Page 28: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

15

2.3.2 Purchasing Procurement or purchasing could be defined as the purchase of materials and

services from other organisations in order to support the firm’s operations (Kasim,

2011). The person in charge for procuring materials or the purchasing department in

case of large construction firms need to ensure that the right materials in the right

quantities are purchased from suppliers or manufacturers. Such person also needs to

verify the release dates at which the material is needed and to clearly specify those

delivery dates and the location of delivery to the supplier (Al-Shorafa, 2009).

The purchasing and planning process are interrelated. This is due to, before

the buying process; the advance planning is required in order to determine the

amount of inventory needed for each time period (Hedrick et al., 2013). After the

need for materials was identified, decisions regarding the buying needs need to be

done which include whether to buy or not and in what quantities. Before the

purchasing order were issued to suppliers or manufacturers, it is important to

highlight the exact time in which the materials are going to be used and for which

activities. This is important to ensure materials availability to carry out construction

works.

2.3.3 Materials Delivery Usually, materials are delivered to the project sites during the construction phase.

However, in several instances the delivery of materials to the jobsites may not be

feasible due to storage or access limitations (Al-Shorafa, 2009).This means that

construction materials cannot be delivered to the project sites due to unavailability of

the site storage space. Sometimes, the locations of the project site from the main road

or main area contribute difficulties for manufacturers and suppliers to delivered or

shipped construction materials.

In such cases, construction materials were delivered or shipped to other

locations such as the contractor’s warehouse, a prefabrication shop or the

subcontractor storage area (Al-Shorafa, 2009). In situations where construction

materials are delivered successfully to the site, workers usually the site supervisor’s

need to checked the delivered materials upon their receipt. The site supervisor need

Page 29: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

16

to check the delivered material in terms of its quantity and specifications and

compared the information with the purchase order (Heck, 2009). At this time, the

materials which required for further storage are segregated or separated from

materials which required to be used for immediate construction activities.

2.3.4 Storage Materials were added to the stock after checking during materials delivery. The

amount or quantities of materials added to the stock need to be recorded in the store

database (whether using paper-based or registered in the system) for further use by

the store keeper in managing the site storage area (Heck, 2009). Adequate

information on materials identification at the storage area is important to enable

workers to easily retrieve the materials. In addition, proper management at the site

storage area is also important to ensure that materials are available at time they are

needed, thus; avoiding problems related to the unavailability or lack of materials

such as double handling and inadequate site storage.

2.3.5 Materials Issue According to Heck (2009), materials or goods were issued for two reasons; each of

which would depend on its environment. In a warehouse, items or goods were issued

to fulfil an order placed by clients. However, in a production environment; items are

retrieved from stock as they are required for production of goods (Heck, 2009).

Construction materials were issued from the site storage or the unloading area; to the

workers to carry out construction works. Materials which were taken out from the

storage were recorded in the store database. However, materials that were taken

directly from the unloading area upon their received need to be deducted directly

from the inventory lists.

Materials issuance needs high degree of supervision from the person in

charge of the site storage area. If it was undertaken without proper supervision,

materials flow may be not recorded at all; or even worse the materials were taken out

in excessive amount which contribute to wastage. Hence, materials issuance is

Page 30: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

17

important to control the flow of materials in and out from the site storage and in

construction projects.

2.4 Inventory Management in Construction Projects In traditional settings, inventories of raw materials, work-in-process and finished

goods were kept as a buffer against the possibility of running out of needed items

(Sahari et al., 2012). However, large inventories consume valuable resources and

generate hidden costs. Adequate inventory level is important for businesses to keep

up competing in the market conditions while operating the business smoothly. On the

other hand, high inventory level could burden the companies as inventories carried

out hidden costs.

Inventory management is one of the most important operations management

responsibilities as inventory involves great deal of capital and the delivery of goods

from manufacturers to the suppliers and customers (Chitale & Gupta, 2006).

Therefore, the management of inventory is important as it has great impact on the

overall business functions. In construction project, materials and equipments may

constitute more than 60% of the total project cost (Donyavi & Flanagan, 2009; Patel

& Vyas, 2011), hence; make the management of materials and inventory as crucial.

In addition, Tersine (1994) asserts that the management of inventory is a

common problem to all organisations in any economic sector. Like other sectors such

as manufacturing, automotive, electronics and others; construction industry also

suffered from poor inventory management especially during construction phase. In

Malaysia, inventory management related factors such as materials shortage and

equipment and tools shortages are among factors that contribute delay to the

construction projects (Sambasivan & Yau, 2007; Alaghbari et al., 2007; Ali et al.,

2010). Therefore, the project management team need to take superior attention on

inventory management in construction projects to ensure materials availability during

conducting the construction works.

Page 31: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

18

Table 2.1: Summary of Inventory Management in Construction Projects

No. Author Year Key Elements

Materials Inventory Inventory

Management Construction

Project 1 Tersine 1994 2 Chitale & Gupta 2006 3 Alaghbari et al. 2007

4 Sambasivan & Yau

2007

5 Donyavi et al. 2009 6 Ali et al. 2010 7 Patel & Vyas 2011 8 Sahari et al. 2012

Table 2.1 summarised several researches that has been carried out regarding

the inventory management in construction projects. From the table, it is clear that the

inventory management in construction projects has received a great concern among

researchers. Therefore, inventory in construction projects need to be managed

properly or vice versa it can causes schedule and project delays which in turn

contribute to the project failure. The next section discusses on the inventory

management problems in construction sites.

2.5 Inventory Management Problems Existing inventory management in construction projects are susceptible to various

problems. Table 2.2 has summarises several inventory management problems which

occur in construction projects abroad and in Malaysia. From the table, Donyavi and

Flanagan (2009) have found out common problems related to inventory management

in construction projects. In their study; failure to order on time, wrong delivery time,

over ordering, wrong materials or error in direction requiring rework, double

handling and theft of materials are common inventory management problems in

construction sites. Inventory management in construction projects also suffered from

inadequate site storage space (Kasim, 2010). Due to inadequate site storage space,

delivered materials were leave scattered everywhere around the construction area,

thus; increase difficulties for materials traceability.

In another research, Sardroud (2012) has identified several major problems

related to inventory management in construction projects. Those problems are:

materials required but not purchased, wrong time for delivery of materials, lack of

Page 32: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

19

complete and up-to-date information regarding the site stocks; missing or surplus of

materials; inadequate site storage space; and waste of working hours searching for

materials and in tracking them. Similar to the other inventory management problems,

these problems also results in the decrease of labour productivity, schedule delays

and increase the project costs.

Table 2.2: Inventory Management Problems in Construction Projects

No. Author Year Inventory Management Problems Construction Projects Overseas

1. Jang & Skibniewski 2008

- Manual material tracking in which it is labour intensive, inaccurate & subjected to error, wastage, surplus materials, schedule delay, decrease in productivity and lack of timely information regarding materials.

2. Donyavi & Flanagan 2009

- Failure to order materials on time - Wrong delivery time - Over ordering - Wrong materials or error in directions requiring rework - Double handling - Theft

3. Kasim 2010 - Inadequate site storage space

4. El-Ghazali et al. 2011

- Manual material tracking in which it is labour intensive, inaccurate & subjected to error, wastage, surplus materials, schedule delay, decrease in productivity and lack of timely information regarding materials.

5. Sardroud 2012

- Required materials are not purchased - Wrong delivery time - Late of timely information regarding on-site stock - Materials missing and surplus of materials - Inadequate storage space - Waste of man-hours searching for materials and in tracking them

Construction Projects in Malaysia

1. Sambasivan & Yau 2007 - Shortage of materials - Equipment and tool shortage

2. Alaghbari et al. 2007 - Shortage of materials - Equipment and tool shortage

3. Ali et al. 2010 - Shortage of materials - Equipment and tool shortage

4. Ibrahim 2010 - Surplus of materials - Late delivery of materials - Improper planning

5. Hamzah et al. 2012 - Shortage of materials - Equipment and tool shortage

In addition, inventory management in construction also suffers from

traditional-manual material tracking practices (Jang & Skibniewski, 2008; El-Ghazali

et al., 2011). According to Sardroud et al. (2010), manual material tracking relies on

workers efficiency to track and identify materials in construction jobsites. This

method is labour intensive, inaccurate and subjected to error-prone, which further

leads to waste and surplus of materials, schedule delays, decrease in productivity,

Page 33: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

20

and lack of up-to-date information regarding the status of materials. Data collected

using manual method is also unreliable as it depends on workers initiative to collect

data regarding materials.

In Malaysia, shortage of materials and equipment and tool shortages are

among the common problems related to inventory management in construction

projects (Sambasivan & Yau, 2007; Alaghbari et al., 2007; Ali et al., 2010; Hamzah

et al., 2012) besides other factors such as surplus of materials (Ibrahim, 2010), late

delivery of materials and improper planning. On the other hand, shortage of materials

is also among the major factors that contribute delays of construction projects in the

Klang Valley, Malaysia (Ali et al., 2010). However, little research has been carried

out regarding the problems faced by Malaysian construction industry related to

inventory management in construction projects (Ibrahim, 2010).

In case of material shortage, materials required to carry out specified jobs are

unavailable when needed, thus; result in delay of construction works, wasting of

labour hours and equipments and increase the total project cost (Ali et al., 2010).

From the above study, it is expected that inventory management problems which

occur among Malaysian construction projects are contributed by the inexistence of

proper material tracking system for the purpose of managing inventory in

construction projects. Song (2005) has highlighted the importance of proper material

tracking in which it provides timely information on materials availability. Timely

information on materials is important for the site manager to make proper planning

on construction works based on materials availability and to make decision regarding

the purchasing of materials. Hence, materials shortage, surplus of materials and other

inventory management problems could be avoided.

The above literature revealed several inventory management problems which

occur in construction projects including existing problems in Malaysia. Therefore, it

could be concluded that effective material tracking practices is required in managing

inventory. Fail to manage inventory results in schedule delays, increase labour

working hours, decrease productivity and increase the production costs. Hence, this

research intended to highlight the importance of material tracking practices for

inventory management processes in construction projects.

Page 34: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

21

2.6 Material Tracking for Inventory Management Material tracking in construction projects is not an easy task (Navon & Berkovich,

2006). This is due to construction projects involve large amount of materials to fulfil

the demand of construction activities. Thus, it is important for the project

management to be able to trace every construction materials to make sure

construction works could be carried out in line with the availability of resources

(construction materials).

2.6.1 The Importance of Material Tracking The term material tracking could be defined as the process of collecting and

managing information related to present or real-time location of a products or items

(Shamsuzzoha & Helo, 2011). Material tracking in construction project is crucial as

materials constitute large portion of the total project costs. According to Green

(2005), material tracking in construction projects is important because of several

reasons; (i) to know exactly the location of materials, so workers do not have to

waste their time searching for materials, (ii) to make sure jobs and orders are not held

up because of lack of materials, (iii) to track the quality and cost of each container of

material in order to make sure that the correct materials are received according to

purchase orders, (iv) to make sure the manufacturers have shipped the right materials

to the customer; and (v) the need for traceability.

Material tracking system helps to identify the position of the shipment and

informed the customer about the products or items location in well advance. Vice

versa, it is impossible to find out delivered items and to track lost or stolen item

without material tracking system (Shamsuzzoha & Helo, 2011). In another research,

Song (2005) stated that materials’ tracking in construction projects is important

because of two reasons. Firstly, materials tracking could provide timely information

on materials availability to enhance crew-level work planning and improve labour

productivity. Secondly, materials tracking enable real-time on-site measurement of

project performance indicators that provide the project management with feedback

information for project control. In construction projects, both timely information on

Page 35: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

22

material and real-time on-site measurement of project performance is important for

the project management to make decision regarding the project.

Construction environment also demanding high materials traceability where

materials need to be at predetermined locations at time they are needed (Song, 2005).

This is important primarily to facilitate materials consumption during construction

works. At the storage area, material tracking were used to know the specific quantity

of every item within the storage. This is important in order to have correct

information regarding materials in stock while at the same time making new

purchase order if the inventory level is low. Therefore, materials tracking play an

important role for the purpose of inventory management processes in construction

projects. Fail to track materials means failed to manage inventory which could affect

on the overall project performance.

2.6.2 Current Approaches of Materials Tracking According to Sardroud et al. (2010), current material tracking practices in

construction projects rely greatly on manual data collection process. Manual data

collection is inefficient and ineffective as the data collected is not reliable and

accurate. In construction project, accurate and timely information is primary concern

among various parties in the project in order to increase the project control.

However, Grau et al. (2009) has demonstrated current method of material tracking

which were used to tracked pre-fabricated components such as structural steel and

pipe spools in construction jobsites.

In their research, structural steel and pipe spools were first unloaded and

stored in the lay down yard upon their arrival at the construction site. Then, the

delivery information (i.e. delivery date and truck number) was hand-marked to the

components. The piece mark of each received components and their grid location in

lay down yard was manually recorded by workers in paper-based format. Later, this

information was manually keyed into an electronic materials management system for

future use. At the lay down yard, there are possibilities where those components may

be moved to different grids at different times. To have updated inventory

information, workers need to records the new grid location of the components in

every possible movement. Therefore, manual material tracking is very labour

Page 36: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

23

intensive and involve excessive paper-based as workers are required to record the

location of the components in every possible movement before installation process.

Not much research has been conducted regarding material tracking in

Malaysian construction projects. Kasim et al. (2013) found that existing material

tracking practices among four construction projects in Malaysia was undertaken

manually which has several drawback. Liwan et al. (2013) also revealed that

Malaysian contractors rely on manual material tracking practices which is

susceptible to several drawbacks. In addition, the CIDB master plan for occupational

safety and health 2004 (CIDB Master Plan OSHA 2004) also highlighted that one of

the problems facing by the Malaysian construction industry is low productivity

which contribute by the low technology usage. It also show that Malaysian

construction industry is lag far behind other industries in embracing technology and

therefore; the overall project management were carried out manually including

materials tracking.

Several case studies have been conducted to explore material tracking

practices in Malaysian construction projects. It is found that each material was

calculated manually one-by-one by the personnel in charge upon its arrival at the

project site with referred to the Delivery Order (DO) (Liwan et al., 2013). Every time

materials were delivered to the construction site, the site supervisor need to manually

check and tracked the materials to ensure it is according to the DO (Kasim et al.,

2013). This is to ensure that the types, quantity, quality and specifications of

materials arrived at the site is according to the DO. However, Malaysian construction

projects also suffered from manual material tracking related problems. Kasim et al.

(2013) reported that manual material tracking practices are labour intensive, lack of

up-to-date information regarding materials and involved excessive paper-based

recording and reporting. In addition, manual method of materials tracking also

involved excessive paper-based recording, lack of timely information on materials,

inadequate storage space, theft and others (Liwan et al., 2013).

Sardroud et al. (2010) has stated several drawbacks of manual material

tracking in which it is labour intensive, inefficient and data collected using these

methods are unreliable as they depend on workers motivations and skills to collect

data on materials. In addition, data collected through manual method are usually kept

and transferred in paper-based format, which is difficult to be reached in term of its

accessibility and traceability. Current material tracking practices also time

Page 37: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

24

consuming, results in late deliveries, lead to mislocated components and incorrect

installations (Demiralp et al., 2012). Although current material tracking practices has

many drawbacks, however; the advancement in ICT could be manipulated to

improve current practices. Several technologies could be adopted to assist and

improve material tracking in construction projects. Brief explanations on those

technologies were explained on the next section.

2.6.3 Materials Tracking Technology The implementation of technology in everyday’s life has ability to assist human

works while at the same time improving their life quality. Hence, the implementation

of technology particularly for material tracking in construction projects is expected to

facilitate and improve existing material tracking practices. From previous research,

there are several technologies which were used for material tracking. Explanations

on each technology were made as follows.

2.6.3.1 Bar-coding Bar-coding have been successfully positioned itself against other identification

systems over the past two decades. Bar-coding is a binary code comprising of bars

and gaps arranged together in parallel configuration. The bars and gaps were

arranged according to a predetermined pattern and represent data elements that refer

to an associated symbol (Finkenzeller, 2010). Figure 2.1 depicts the example of bar-

coding label which available in the market.

Figure 2.1: Bar-coding Label

Page 38: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

REFERENCES

Abdul Kareem, H. I. & Abu Bakar, A. H. (2011). Identifying IT Benefits for

Malaysian Construction Companies. Journal of Information Technology in

Construction (ITcon), vol. 16, pp. 477-492.

Alaghbari, W., A. Kadir, M. R., Salim, A. & Ernawati (2007). The Significant

Factors Causing Delay of Building Construction Projects in Malaysia.

Journal of Engineering, Construction and Architectural Management, vol.

14(2), pp. 192-206.

Ala-Risku, T. & Karkkainen, M. (2006). Material Delivery Problems in Construction

Projects: A Possible Solution. International Journal of Production

Economics, vol. 104, pp. 19-29.

Ali, A. S., Smith, A. & Pitt, M. (2010). Contractors’ Perception of Factors

Contributing to ProjectDelay: Case Studies of Commercial Projects in Klang

Valley, Malaysia. Journal of Design and Built Environment, vol. 7. pp. 43- 57.

Al-Shorafa, A. A. (2009). A Framework for Construction Materials Supply Chain

Process in the Local Construction Industry. Islamic University of Gaza:

Master Thesis.

Banks, J., Hanny, D., Pachano, M. A. & Thompson, L. G. (2007). RFID Applied.

New Jersey: John Wiley & Sons.

Brilakis, I. Park, M. W. & Jog, G. (2011) Automated Vision Tracking of Project

Related Entities. Journal of Advanced Engineering Informatics, vol. 25, pp.

713-724.

Bryman, A. & Bell, E. (2007). Business Research Methods. 2nd ed. New York:

Oxford University Press.

Caldas, C. H., Torrent, D. G. & Haas, C. T. (2004). Integration of Automated Data

Collection Technologies for Real-time Field Materials Management. Proc. of

the 21st Int. Symposium on Automation and Robotics in Construction. Jeju,

Korea.

Cavana, R. Y., Delahaye, B. L. & Sekaran, U. (2001). Applied Business Research:

Qualitative and Quantitative Methods. Australia: John Wiley & Sons.

Page 39: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

173

Chitale, A. K. & Gupta, R. C. (2006). Materials Management: Text and Cases. New

Delhi: Prentice-Hall.

Chen, K. M., Chen, J. C. & Cox, R. A. (2012). Real Time Facility Performance

Monitoring System using RFID Technology. Journal of Assembly

Automation, vol. 32(2), pp. 185-196.

Construction Industry Development Board, CIDB (2012). Dafter Projek Pembinaan

Mengikut Nama Kontraktor: Januari hingga Disember 2012. Retrieved

December 18, 2012 from http://www.cidb.gov.my.

Construction Industry Development Board, CIDB (2013). CIDB Master Plan for

Occupational Safety and Health (CIDB Master Plan OSHA 2004).Retrieved

July 6, 2014 from http://www.cidb.gov.my.

Construction Industry Development Board, CIDB (2014). Retrieved July 6, 2014

from http://www.cidb.gov.my.

Construction Industry Development Board, CIDB (2014). CIDB News: Newsletter

for the Construction Industry Development Board, Issue 01 (April 2014).

Cooper, D. R. & Schindler, P. S. (2008). Business Research Methods. 10th ed.

United States: McGrawHill.

Demiralp, G., Guven, G. & Ergen, E. (2012). Analyzing the Benefits of RFID

Technology for Cost Sharing in Construction Supply Chains: A Case Study

on Prefabricated Precast Components. Journal of Automation in

Construction, vol. 24, pp. 120-129.

Donyavi, S. & Flanagan, R. (2009). The Impact of Effective Material Management

on Construction Site Performance for Small and Medium Sized Construction

Enterprises. Proc. of the 25th Annual ARCOM Conference, Nottingham, UK.

Dul, J. & Hak, T. (2008). Case Study Methodology in Business Research. USA:

Elsevier.

Dziadak, K., Kumar, B. & Sommerville (2006). RFID in the Built Environment:

Buried Asset Location Systems. Journal of Intelligent Computing in

Engineering and Architecture, No. 4200, pp. 153-162.

El-Ghazali, Y., Lafebvre, E. & Lafebvre, L. A. (2011). RFID-Enabled Materials

Management in the Industrial Construction Supply Chain. Proc. of the 5th

WSEAS International Conference on Communications and Information

Technology, pp. 79-84.

Page 40: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

174

El-Omari, S. (2008). Automated Data Acquisition and Control of Construction

Projects. Concordia University: PhD Thesis.

Eriksson, P. & Kovalainen, A. (2008). Qualitative Methods in Business Research.

London: Sage Publications.

Ergen, E. & Akinci, B. (2007). An Overview of Approaches for Utilizing RFID in

Construction Industry. IEEE Xplore Digital Library.

Fathi, M. S., Anumba, C. Carrillo, P. & Zakiyudin, M. H. (2009). Real Time Mobile

Information System for Construction Programme Management. Proc. of the

2nd Construction Industry Research Achievement International

Conference (CIRAIC2009).

Finkenzeller, K. (2010). RFID Handbook: Fundamentals and Applications in

Contactless Smart Cards, Radio Frequency Identification and Near-Field

Communication. London: John Wiley and Sons.

Fellows, R. & Liu, A. (1999). Research Methods for Construction. Oxford:

Blackwell Science Ltd.

Gajamani, G. K. & Varghese, K. (2007). Automated Project Schedule and Inventory

Monitoring using RFID. 24th International Symposium on Automation &

Roborics in Construction (ISARC 2007), Madras.

Garfinkel, S. & Rosenberg, B. (2006). RFID Applications, Security, and Privacy.

Pearson Education, Inc.

Ghauri, P. & Gronhaug, K. (2005). Research Methods in Business Studies: A

Practical Guide. 3rd ed. Prentice Hall Europe.

Gill, J. & Johnson, P. (1997). Research Methods for Managers: 2nd Edition.

London: Paul Chapman.

Goodrum, P. M., McLaren, M. A. & Durfee, A. (2006). The Application of Active

Radio Frequency Identification Technology for Tool Tracking on

Construction Jobsites. Journal of Automation in Construction, 15, pp. 292-

302.

Grau, D., Caldas, C. H., Haas, C. T., Goodrum, P. M. & Gong, J. (2009). Assesing

the Impact of Materials Tracking Technologies on Construction Craft

Productivity. Journal of Automation in Construction, 18, pp. 903-911.

Green, P. (2005). Material Tracking Handbook. Millbury: BellHawk® Systems

Corporation.

Page 41: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

175

Greener, S. (2008). EBooks: Business Research Methods. Dr. Sue Greeber & Ventus

Publishing ApS.

Hair, J. F. J., Babin, B., Money, A. H. & Samouel, P. (2003). Essentials of Business

Research Methods. United States: Leyh Publishing.

Hakim, C. (2000). Research Design: Successful Designs for Social and Economic

Research. 2nd ed. London: Routledge.

Heck, V. G. (2009). Inventory Management: Introducing a Framework to Assess

Operational Performance. Delft University of Technology: Master Thesis.

Hedrick, F. D., Barnes, F. C., Davis, E. W., Whybark, D. C. & Krieger, M. (2013).

Inventory Management. Retrieved May 29, 2013 from

http://www.sbaonline.sba.gov/idc/groups/public/documents/sba_homepage/p

ub_mp22.pdf

Hunt, V. D., Puglia, A.& Puglia, M. (2007). RFID A Guide to Radio Frequency

Identification. New Jersey: John Wiley & Sons.

Ibrahim, A. R., Roy, M. H., Ahmed, Z. & Imtiaz, G. (2010). An Investigation of the

Status of the Malaysian Construction Industry. Benchmarking: An

International Journal, vol. 17, pp. 294-308.

Idrus, A., Utomo, C. & Mubarak, I. H. (2008). Applicability of Computer Tools in

Malaysia’s Construction Industry. Proc. of International Conference on

Project Management (ICoPM), 18-20 November 2008, Selangor.

Jaafar, M., Abdul Aziz, A. R., Ramayah, T. & Saad, B. (2007). Integrating

Information Technology in the construction industry: Technology Readiness

Assessment of Malaysian Contractors. Int. Journal of Project Management,

vol. 25, pp. 115-120.

Jang, W. S. (2007). Embedded System for Construction Material Tracking using

Combination of Radio Frequency and Ultrasound Signal. University of

Maryland: PhD Thesis.

Jang, W. S. & Skibniewski, M. J. (2008). A Wireless Network System for

Automated Tracking of Construction Materials on Project Sites. Journal of

Civil Engineering & Management, 14(1), pp. 11-19.

Kasim, N. B., Anumba, C. J. & Dainty, A. R. J. (2005). Improving Materials

Management Practices on Fast-track Construction Projects. 21st Annual

ARCOM Conference, vol. 2, 793-802.

Page 42: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

176

Kasim, N. B. (2008). Improving Materials Management on Construction Projects.

Loughborough University: PhD Thesis.

Kasim, N. B. (2010). Towards a Framework for ICT-Enabled Materials Management

in Complex Projects. Journal of Techno-Social.

Kasim, N. B. & Ang, S. E. P. (2010). The Awareness of ICT Implementation for

Materials Management in Construction Projects. Int. Journal of Computer

and Communication Technology, vol. 2(1).

Kasim, N. B. (2011). ICT Implementation for Materials Management in Construction

Projects. Journal of Construction Engineering and Project Management, vol.

1 (2011).

Kasim, N., Liwan, S. R., Shamsuddin, A. & Zainal, R. (2013). Improving Materials

Tracking Practices for Inventory Management in Construction Projects. Proc.

ofTheSecond International Conference on Sustainable Infrastructure and

Built Environment, Bandung, 19-20 November 2013.

Kim, C., Ju, Y. & Kim, J. H. (2009). Resource Management in Civil Construction

Using RFID Technologies. The 26th International Symposium on Automation

and Robotics in Construction (ISARC 2009).

Lancaster, G. (2005). Research Methods in Management: A concise Introduction to

Research in Management and Business Consultancy. Oxford: Elsevier.

Lee, J. H., Song, J. H., Oh, K. S. & Gu, N. (2013). Information Lifecycle

Management with RFID for Material Control on Construction Sites. Journal

of Advanced Engineering Informatics, vol. 27, pp. 108-119.

Li, S., Godon, D. & Visich. J. K. (2010). An Exploratory Study of RFID

Implementation in the Supply Chain. Journal of Management Research, vol.

33(10), pp. 1005-1015.

Liwan, S. R., Kasim, N. & Zainal, R. (2013). Materials Tracking Practices for

Inventory Management in Construction Projects. Proc. of 1st Faculty of

Technology Management and Business (1st FPTP) Colloquium, Universiti

Tun Hussein Onn, Malaysia.

Lu, W., Huang, G. Q. & Li, H. (2011). Scenarios for Applying RFID Technology in

Construction Project Management. Journal of Automation in Construction,

20, pp. 101-106.

Malhotra, N. K., Hall, J., Shaw, M., & Oppenheim, P. (2006). Marketing Research:

An Applied Orientation. 3rd ed. Sydney: Pearson Education.

Page 43: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

177

Maré, S. E. (2006). Improvement of the Materials Management Function in a Shared

Service Centre. University of Pretoria: Master Thesis.

Mehrjerdi, Y. Z. (2008). RFID-enabled System: A Brief Review. Journal of

Assembly Automation, vol. 28(3), pp. 235-245.

Mehrjerdi, Y. Z. (2010). Coupling RFID with Supply Chain to Enhance Productivity.

Handbook of Business Strategy,vol. 11(2), pp. 107-123.

Mehrjerdi, Y. Z. (2011). RFID and Its Benefits: A Multiple Case Analysis. Journal

of Assembly Automation, vol. 31(3), pp. 251-262.

Mohd Tobi, S. U. (2013). Research Methodological Cage: Understanding the

Qualitative Viewpoint. Kuala Lumpur: Aras Publisher.

Molnar, M., Andersson, R. & Ekholm, A. (2007). Benefits of ICT in the

Construction Industry- Characterization of the Present Situation in House-

Building Processes. Proceedings of the W78 Conference, Maribor.

Moselhi, O. & El-Omari, S. (2006). Integrating Bar Coding and RFID To Automate

Data Collection From Construction Sites. Joint Int. Conf. on Computing and

Decision Making in Civil and Building Engineering. Montreal: Concordia

University. pp. 1734- 1741.

Muller. M. (2003). Essentials of Inventory Management. 1st ed. New York: American

Management Association (AMA).

Muller. M. (2011). Essentials of Inventory Management. 2nd ed. New York:

American Management Association (AMA).

Nasir, H. (2008). A Model for Automated Construction Materials Tracking.

University of Waterloo: Master Thesis.

Nasr, E., Shehab, T. & Vlad, A. (2013). Tracking Systems in Construction:

Applications and Comparisons. 49th ASC Annual International

Conference Proceedings.

Navon, R. & Berkovich, O. (2005). An Automated Model for Materials Management

and Control. Journal of Construction Management and Economics, 24, pp.

635-646.

Neuman, W. L. (2003). Social Research Methods: Qualitative and Quantitative

Approaches. New York: Allyn and Bacon.

Norman, A. A., Md. Nasir, M. H. N. & Azmi, M. (2008). The Users Perceptions and

Opportunities in Malaysia in Introducing RFID System for Halal Food

Page 44: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

178

Tracking. WSEAS Transactions on Information Science and Applications, vol.

5.

Oliver, P. (2006). Purposive Sampling. Retrieved February 24, 2015 from

http://srmo.sagepub.com/view/the-sage-dictionary-of-social-research

methods/n162.xml

Ozumba, A. O. U. and Shakantu, W. M. (2008). Improving Site Management

Process Through ICT.

Papageorgiou, C. (2000). Technology Adoption, Human Capital, and Growth

Theory. Department of Economics, Louisiana State University, LA.

Patel, K. V. & Vyas, C. M. (2011). Construction Materials Management on Project

Sites. National Conference on Recent Trends in Engineering & Technology,

Gujarat.

Polonsky, M. J. & Waller, D. S. (2011). Designing and Managing a Research

Project: A Business Student Guide. 2nd ed. London: SAGE Publications.

Razavi, S. N.; Montaser, A. & Moselhi, O. (2012). RFID Deployment Protocols for

Indoor Construction. Journal of Construction Innovation, vol. 12(2), pp.

239-258.

Ren, Z., Anumba, C. J. & Tah, J. (2011). RFID-facilitated Construction Materials

Management (RFID-CMM). A Case Study of Water-supply Project. Journal

of Advanced Engineering Informatics, vol. 25, pp. 198-207.

Ritchie, J.; Lewis, J.; McNaughton, N., C. & Ormston, R. (2013). Qualitative

Research Practice: A Guide for Social Science Students & Researchers.

London: Sage Publications Ltd.

Rivera, J. L. P. (2004). A Framework for a Decision Support Model for a Supply

Chain Management in the Construction Industry. Virginia Polytechnic

Institute: PhD Thesis.

Robson, C. (2002). Real World Research. USA: Blackwell.

Sahari, S., Tinggi, M. & Kadri, N. (2012). Inventory Management in Malaysian

Construction Firms: Impact on Performance. SIU Journal of Management,

vol. 2(1).

Sarac, A., Absi, N. & Dauzere-Peres, S. (2010). A Literature Review on the Impact

of RFID Technologies on Supply Chain Management. Int. Journal of

Production Economics, vol. 128, pp. 77-95.

Page 45: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

179

Sambasivan, M. and Yau, W. S. (2007). Causes and Effects of Delays in Malaysian

Construction Industry. International Journal of Project Management, 25,

pp. 517-526.

Sardroud, J. M., Limbachiya, M. C. & Saremi, A. A. (2010). Ubiquitous Tracking

and Locating of Construction Resource Using GIS and RFID. 6th GIS

Conference and Exhibition (GIS 88), Tehran.

Sardroud, J. M. (2012). Influence of Technology on Automated Management of

Construction Materials and Components. Journal of Scientis Iranica A, vol.

19(3), pp. 381-392.

Saunders, M., Lewis, P. & Thornhill, A. (2007). Research Methods for Business

Students. 4th ed. United Kingdom: Prentice Hall.

Saygin, C. & Natarajan, B. (2010). RFID-based Baggage-handling System Design.

Technical Paper Retrieved from Journal of Emerald. vol. 30(4).

Shamsuzzoha, A. H. M. & Helo, P. (2011). Real-time Tracking and Tracing System:

Potentials for the Logistics Network. Proceedings of the 2011 International

Conference on Industrial Engineering and Operations Management, Kuala

Lumpur.

Song, J. (2005). Tracking the Location of Materials on Construction Projects.

University of Texas: PhD Thesis.

Straub, E. T. (2009). Understanding Technology Adoption: Theory and Future

Directions for Informal Learning. Journal Review of Educational Research,

vol. 79 (2), pp. 625-649.

Strauss, A. & Corbin, J. (1990). Basics of Qualitative Research: Grounded Theory

Procedures and Techniques. Newbury Park: Sage Publications.

Sulaiman, S., Umar, A. U., Tang, S. H. & Fatchurrohman, N. (2012). Application of

Radio Frequency Identification (RFID) in Manufacturing in Malaysia. Int.

Journal of Procedia Engineering, vol. 50, pp. 697-706.

Swanborn, P. (2010). Case Study Research: What, Why and How? London: Sage

Publications.

Takim, R. (2005). A Framework for Successful Construction Project Performance.

Glasgow Caledonian University: PhD Thesis.

Teijlingen, E. R. V. & Hundley, V. (2001). Social Research Update, Department of

Sociology, University of Surrey.

Page 46: THE FRAMEWORK OF IMPROVING ON-SITE MATERIALS …eprints.uthm.edu.my/id/eprint/8010/1/SITI_RADZIAH_BINTI_LIWAN.pdfbinaan dan membolehkan prestasi projek diukur mengikut keadaan semasa

180

Tersine, R. J. (1994). Principles of Inventory and Materials Management. 4th ed.

New Jersey: PTR Prentice Hall.

Thornhill, A., Saunders, M. & Lewis, P. (2007). Research Methods for Business

Students. 4th ed. Oxford: Prentice Hall.

Wan Hamid, W. H. & Hong, L. C. (2008). Development and Implementation of

Radio-Frequency Identification (RFID) Technology for Inventory

Management System: A Case Study. Jurnal Mekanikal, no. 27, pp. 51-68.

Waters, D. (2003). Inventory Control and Management. 2nd ed. Chichester: John

Wiley.

Wilson, J. (2010). Essentials of Business Research: A Guide to Doing Your Research

Project. London: Sage Publications.

Wing, R. (2006). RFID Applications in Construction and Facilities Management.

Journal of ITcon, vol. 11, pp. 711-721.

Wu, D. L., Ng, W. W. Y., Yeung, D. S. & Ding, H. L. (2009). A Brief Survey on

Current RFID Applications. Proc. of the Eighth Int. Conf. on Machine

Learning and Cybernetics. Baoding: University of Technology Guangzhou,

China. pp. 2330-2335.

Yin, R. K. (2009). Case Study Research Design & Methods. 4th ed. United Kingdom:

Sage Publications.

Yoon, W. J., Chung, S. H. & Lee, S. J. (2008). Implementation and Performance

Evaluation of An Active RFID System for Fast Tag Collection. Journal of

Computer Communications, vol. 31, pp. 4107-4116.

Young, D. A. (2009). Modelling the Impact of Automated Materials Locating and

Tracking Technology on the Construction Supply Network. University of

Waterloo: Master Thesis.

Zakaria, M. Z. (2013). The Malaysian RFID Scenario. Retrieved May 29, 2013 from

Zikmund, W. G. (2003). Business Research Methods. 7th ed. United States:

Thomson.


Recommended