The Great Western Electrification Programme -
Collaborating for Success
Tuesday 10th September INCOSE – Railway Interest Group
Nassar Majothi – Parsons Brinckerhoff
Joe Silmon – Atkins
• What is the GWEP? • The Atkins / Parsons Brinkerhoff Team – LDO • The integration challenges • SE Tools and techniques
Overview
The Route London and Bristol, including Newbury and Oxford, by 2016 and to Cardiff by 2017
New trains Enabling the route for the new fleet of Intercity Express Trains
Capacity More seats and faster journeys Environment Reduction in emissions, carbon and local
environmental impact Economic growth
Stimulate economic growth across the region by better connecting towns and cities
Reduce costs Higher overall reliability, lower operations and maintenance costs
Programme Goals
1. High Output Plant System – Construction Technology
2. New Product Technology – Series 1, FEDs. IPC, RATS
3. 3 new Grid Supplies
4. Circa 50 Local Auto Transformer/Switchgear Sites
5. 22,000 OLE Support Structures
6. 1000 Km of Wiring
7. 150 Structures to gauge clear (reconstructions, track lowers, jacking; awnings, tunnels, demolisions)
Programme Scope
Programme Scope – Innovation
The GWEP Route
Dec 2017 Sept 2015
1. Network Rail Investment Projects – The Client 2. Network Rail Route & EPDG 3. Amey – The Construction Contractor 4. Atkins & Parsons Brinckerhoff – The Lead
Design Organisation 5. Other Designers 6. Furrer & Frey – Series 1 Development 7. Windhoff – High Output Train
The Delivery Team
What is a Lead Design Organisation?
The LDO responsibility for systems integration
The LDO shall... enable the co-ordination and integration of engineering, designs, construction and commissioning produced by the LDO and others and to provide on going site design/engineering support and validation of the works during implementation and commissioning through to Entry into Service (EIS).
The LDO responsibility matrix
1. Market forces
2. Breadth of skills required
3. Size of team
4. Efficiencies
5. Innovation
6. Multi-discipline Approach
Why a JV and the drive for collaboration
Systems Integration
Design Integration
Design Integration
Design Integration
EDMS / CAD Management System
Document Control
Project, Design & Engineering Processes
PM, Project Controls & Schedule Management
Design Integration
Construction Integration
Operational Integration
Approach to Systems Integration
GRIP 4
GRIP 5
GRIP 3
GRI
P 6
GRIP 2
GRIP 1
LDO – Picks up design and integration (inc V&V) at start of GRIP 4
EIS – Entire GW Route – Complete
EIS – Route Section 3
GRI
P 7
EIS – Route Section – Staged
Great WesternElectrificationProgramme
Test
ing
& Co
mm
issio
ning
EIS
Application Design
In Service Monitoring
Inspection, Test & Comission Requirements
Route Section Design Requirements
System Requirements (PRS, Strategies & AIPs)
Operational and Performance Requirements (Client Functional)
Cons
truct
ion
Series 1
Series 1 – T&C
Series 1 – SRP Certificate
Series 1 – Approved Product Catalogue
Series 1 – Requirements
Series 1 – Product Development
Series 1 – Specification
Intergated Protection &
Control
Fixed Earth Devices
Products and Technology Development – GRIP 7/8 > Feed into GWEP GRIP4
Products and Technology Development: Series 1, IPC & FEDS, T&C on RS3 – V&V needed
Other NR GW Project & Programmes: Delivery for GWEP – V&V needed
External Project & Programmes: Delivery for GWEP – V&V needed
GRIP 8
NR Corporate / Route NR GWEP Lead Design
Organisation
High Output Construction Contractor
Conventional Construction Contractor
Other Design Organisations
The Challenge of Multiple V’s
CROSSRAIL WEST
Fixed Telecoms Network
Design stage
GRIP4-8Discipline/function
Systems & AssuranceOriginator
Checker
Reviewer
AuthoriserDateRevision
Title
LDO TECHNICAL INTERFACE MANAGEMENT - PROGRAMME LEVEL BOUNDARY DIAGRAM (DRAFT)
Number
[Atkins & Parsons Brinckerhoff]
Western Mainline Signalling Renewals (WMSR)
Western Building and Civils
Electrification Plant Design Group(EPDG)
National SCADA
National Traffic Management/ Regional
operating centres
Bristol+ Oxford Redevelopment
NETWORK RAIL INFRASTRUCTURE PROJECTSNETWORK RAIL (NR)
GREAT WESTERN ELECTRICIFICATION PROJECT
The purpose of diagram is to identify and visualise the organisational and programme interfaces to be considered by the LDO within its interface scope of work.
Cross Country
First Great Western
Heathrow Express
TRAIN OPERATING COMPANY (TOC)
FREIGHT OPERATING COMPANY
REGULATORY BODIESHealth Safety
Executive (HSE) HIGHWAYS
Highways Agency
ELECTRICAL UTILITIES, GAS,WATER &TELECOMS
Gas Company?
BT & other telecoms
companies?
Water Company?
DB Schenker
GB Railfreight
DirectRail Services
LOCAL RESIDENTS AND COUNCILS
NETWORK RAIL GREAT WESTERN ROUTE
Route Maintenance and Renewals (Track)
NETWORK RAIL WALES ROUTE
Country Land Owners
Association
Arriva Trains Wales
Environment Agency
British Transport
Police
National Grid
Department for Transport
Councils including Basingstoke and Deane, Reading, Bath & North East Somerset, Bristol City, Gloucestershire County, Hampshire County, Oxford City, Oxfordshire County, Reading Borough, Somerset County, South Gloucestershire County, Surrey County, Swindon West Berkshire , Wiltshire, Windsor and Maidenhead Royal.
XXXX - Refers to Stakeholder
XXXX
HMRI
Office of Rail Regulation (ORR)
Scottish & Southern Energy Other DNOs
ERTMS /European Train Control System(ETCS)
Programme
Colas
XXXX-Refers to Great WesternElectrification Programmeinternal structure
- Refers to Workstream or programme
Legend
Operations(Route Control & Signalling
Control)
Purpose:
Amey
AGILITY TRAINS
Station Renewals and Upgrades
NOTE THAT THIS DRAWING
English Heritage
Intercity Express Programme (IEP)
(Network Rail)
W12 Gauging Enhancement Programme
Filton Bank 4-Tracking
GW
EP
/PIF/3100
GWEP/PIF/0100
GWEP/PIF/2300
GW
EP
/PIF/2700
GWEP/PIF/3000 GWEP/PIF/3200
GWEP/PIF/1800
GWEP/PIF/1400
GWEP/PIF/1100
GWEP/PIF/1300
ERTMS - European Rail Traffic Management SystemDNOs - Distribution Network Operators
GWEP/PIF/1600
GWEP/PIF/1700
GWEP/PIF/1500
GW
EP
/PIF/2900
GW
EP
/PIF/2800
Electric Spine ElectrificationIEP Depot/stabling
Construction programme
New IEP Trains
Oxford Station Redevelopment
GWEP/PIF/1000
GWEP/PIF/0200 GWEP/PIF/0800
Welsh Government
GWEP/PIF/1200
GWEP/PIF/0700
Arriva Crosscountry
Port Talbot West Re-signalling
Electrification Development Programmes *
*- Electrification Development Programmes includes Thames Valley Lines, Reading to Basingstoke, Cardiff to Swansea,
GWEP/PIF/1900
GWEP/PIF/2100
GWEP/PIF/2200
Integrated Protection and
Control
GWEP/PIF/2400
GWEP/PIF/2500
Fixed Earthing Devices
TECHNOLOGY AND PRODUCT DEVELOPMENT
Rail for London (including future Crossrail TOC)
Track Renewals
GWEP/PIF/0300
Series 1 - Electrification Design Development review
Series 1
Electrification Alliance
IEP and Electrification works
(Associated NR infrastructure works)
Route Clearance Structures
Railways Heritage Trust
Crossrail on Network Works
NR Crossrail Infrastructure Paddington- Maidenhead
Route Maintenance and Renewals (Track)
XXXX - Further investigation required
- Her Majesty's Railway InspectorateHMRI
Newport / Cardiff Area Signalling Renewals(CASR
and NASR )
RASR (Electrification +
Resignalling)
RASR - Reading Area Stations Renewals
Natural England
South West Trains
Freightliner Heavy Haul
FreightlinerIntermodal
Track AlignmentPaddington - Cardiff
Operations(Route Control & Signalling
Control)
Electrification Plant Design Group(EPDG)
GWEP/PIF/2000
GWEP/PIF/2600
GWEP/PIF/0400
GW
EP
/PIF/0500
Network Rail Central/Corporate
Engineering
Network Rail Environment and
SustainabilityROSR
GWEP/PIF/0600
GWEP/PIF/0900
3 Position Load Break Switch
A Complex Set of Programme Interfaces
A Complex Set of Programme Interfaces
Maintenance
Signalling
Reading
Electrification
IEP
Electrification
Crossrail West
IEP
Electrification
Electrification
IEP
Sign
allin
g
Elec
trifi
catio
n Signalling Signalling
Signalling Wales Western
Track Renewals
7 Day Railway
National Stations Improvement Programme
Other Enhancements
CASR NASR
IEP Depot Filton Bank IEP Depot
North Pole
Kensal Green
Swindon to Kemble
CRL Depot OOC
HS2 Didcot
Melksham
Imperial Park
Oxford Re-modelling
Bristol TM Re-modelling
ERTMS
Engineering Challenges
Case A: LDO undertakes all design work for the route section
Case C: LDO undertakes no design work, all design is done by other organisations. LDO retains integration accountability.
LDO CEMNR DPE
LDO Project Manager
LDO Discipline
A CRE
LDO Discipline
B CRE
Others Org Discipline
C CRE
NR Discipline
A PE
NR Discipline
B PE
LDO Discipline
C PE
Others Org CEM
Others Org CEM
NR DPE
Others Org Discipline
A CRE
Others Org Discipline
B CRE
Others Org Discipline
C CRE
NR Discipline
A PE
NR Discipline
B PE
LDO Discipline
C PE
LDO CEM
LDO CEMNR DPE
NR Contract Project
Manager(s)
LDO Project Manager
LDO Discipline
A CRE
LDO Discipline
B CRE
LDO Org Discipline
C CRE
NR Discipline
A PE
NR Discipline
B PE
LDO Discipline
C PE
Case B: Design work is shared between the LDO and other organisations. LDO retains integration accountability.
Others Org CEM
Others Org CEM
NR Discipline
B PE
LDO CEM
Others Org CEM
Formal Engineering Flow and Information Exchange
Formal Contractual Communication and Documentation Flow
Engineering Information Exchange
Network Rail
Lead Design Organisation
Others Design Organisations
NR Contract Project
Manager(s)
Other Orgs Project
Manager(s)
NR Contract Project
Manager(s)
Other Orgs Project
Manager(s)
Governance Challenges
SYSTEMS ENGINEERING TECHNIQUES
Requirements management – guiding principles
Requirements drive the design Provide requirements to designers at the start – reduce retrospective verification
GRIP3 design contains numerous requirements
Huge value in Approved in Principle designs
Requirements are not confined to the PRS, they are defined and refined by design GRIP4 and GRIP5 designers write new requirements that are relevant to the next stage
Requirements relate to the system in different ways Need to ensure each design package only sees the applicable requirements
Avoidance of unnecessary work Reject non-value-adding requirements
Rich traceability Record and justify how requirements were evolved through the life-cycle
20
Challenge 1: a distributed system
RequirementMinimise environmental
impacttype a)
RequirementW10 structure gauge
type b)
RequirementNo impact piling near
Mr X’s housetype c)
PhysicalOLE Production Unit GW/00
PhysicalOLE Production Unit GW/01
PhysicalOLE Structure
GW/00/01
PhysicalOLE Structure
GW/00/02
PhysicalOLE Structure
GW/01/01
Each of these links must be independently verified for full technical assurance
traces to
traces to
traces to
Multi-level applicability of requirements Requirement
Type a) requirementAll elements
traces toPhysical
T00 Generic design element
PhysicalT03 OLE Structure
PhysicalGW/00/01 structure
is a
is a
RequirementType b) requirementAll elements of type
RequirementType c) requirement
location specific
traces to
traces to
Inferred applicability of requirements
• Inference: If A →B and B→C then A→C
• If the requirement applies to OLE structures, and GW/00/01 is an OLE structure, then the requirement applies to GW/00/01.
PhysicalT03 OLE Structure
PhysicalGW/00/01 structure
is a
RequirementType b) requirementAll elements of type
traces to
Inferred trace
Requirements that apply to each element
• Now three logical conditions are brought together to infer the traceability
• Useful for global requirements and aspirations e.g. environmental impact
• Use sparingly to avoid overloading designers!
RequirementType a) requirement
All elementstraces to
PhysicalT00 Generic design
element
PhysicalT03 OLE Structure
PhysicalGW/00/01 structure
is a
is a
Inferred trace
Challenge 2: Multiple requirements sources
• 65 requirements source documents from GRIP3
• ~5000 requirements
• Definition of specialist requirements ongoing
Requirements management & traceability
CLI
EN
T
STA
KE
HO
LDE
R
SA
FETY
RA
M
EM
C
ER
GO
NO
MIC
S
EN
VIR
ON
ME
NT
INTE
RFA
CE
DE
SIG
N
Design progression & change management
Verification and validation
Acceptance
Challenge 3: Evolution of assurance through the life-cycle
Integrating requirements with design
27
Project RequirementSpecification
GRIP3 output document
GRIP6 Inspection, testing &
Integration reports
GRIP4 coordinated requirement specification
GRIP4 output document
GRIP5 output document
GRIP7 Commissioning
reports
Traceability by Network Rail requirements
manager
Sponsor & Client
requirements
Traceability by LDO capture and
analysis
Traceability by LDO capture and
analysis
Traceability by LDO design teams
Owned and traced by LDO design
teams
e.g. Approved in Principle designs, EMC strategy, etc.
e.g. Form 001
Leaf-level requirements
RequirementOriginating
requirement 1
RequirementOriginating
requirement 2
RequirementOriginating
requirement 3
RequirementDerived requirement
4
RequirementDerived requirement
5
supersedessupersedes
RequirementDerived requirement
6
supersedes
DocumentProject specification
traces to traces to traces to
Set of leaf-level requirements
A simple rich traceability metamodel
Satisfaction argument
Requirement [TRAK]a requirement
Requirement [TRAK]a requirement
Document [TRAK]a document
satisfies
traces toIssue (UML)
argument of necessity
Change (UML)argument of sufficiency
arises from
resolves
implementsPhysical [TRAK]
a physical[TRAK]
traces to
Document [TRAK]a document
documented by
addresses
Direct traceability Rich traceability
Audit trail
“Pilot’s manual” instruction flowcharts
• Guide to contents of detailed documents
• Indicate involvement of multiple actors
• Easy to test logic
XLS
XLS
Syst
ems
and
assu
ranc
e te
am
Scrip
tSC
R00
3
Design team
1.1
Capture derived requirements
Design phase n baseline
Start of design phase n+1
Scrip
tSC
R00
1 1.2
Import requirements to database
XLSHS2 originating requirements baseline
Man
ual
1.3
Create traceable requirements structure
1.4
Review structure
Scrip
tSC
R00
2 1.5Flow inherited applicability to
individual elements
1.6
Generate element verification templates
XLSCompleted
capture sheets
XLSElement verification sheets
Enterprise Architect
Simplified architecture framework
31
traces to{interface req}
is configured with
interfaces with
VP03: Geographical
asset hierarchy
VP06: Element classification
VP04:Functional
model
VP05: System
interfaces
Requirementa requirement
Documenta document
supersedes
traces to
Satisfaction Argumentreason for changing/refining requirement
traces to
traces to
SystemGeographical area
PhysicalAsset [specific]
is configured with
is configured with
is configured with
SystemRoute
is a
SystemRailway system/
subsystemis configured with
SystemContext
SystemEnvironment/
external system
is configured with
is configured with
is configured with
interfaces with
traces to
traces to{global req}
traces to{area/section req}
traces to{localised/site req}
traces to{discipline/asset type req}
interfaces with
VP01: Requirement
capture
VP02: Requirement tracing, refinement
and applicability
VP07: Asset checklist
verify
Collaborative tools for SE • NR DOORS environment (via Citrix):
– Client reporting of V&V
– Mirroring of developed traceability downstream of PRS
– Mastering of traceability upstream of PRS (Client & Sponsor requirements)
• LDO Enterprise Architect environment (on the cloud, eventually...)
– Mastering of traceability downstream of PRS (GRIP3 and GRIP4 output requirements)
– System architecture / Interface modelling
– Safety risk assessment (WIP)
32
Interface Management
Route Section Interface Registers
Master technical interface registers
Top level technical interface register
System Architecture input
Programme Boundary
Programme Interface register
I/F Reqs & ICDs
Interface Management
Interface Reference Number
Interface Description Responsible Discipline From To Technical
ComplexityInternal/E
xternal Schedule Sum Total
GWEP/TIF/0101 Structural load bearing of OLE for design of OLE support structures. OLE Overhead Line Equipment (Catenary) OLE Supporting Structures 1 2 1 4
GWEP/TIF/0102 Physical clearance between OLE supporting structure and catenary. OLE Overhead Line Equipment (Catenary) OLE Supporting Structures 1 1 1 3
GWEP/TIF/0103 OLE catenary interface between the FEDs and motorised switches. OLE Overhead Line Equipment (Catenary) Distribution-Power Supply 1 1 2 4
GWEP/TIF/0104Physical location coordination of OLE cables and cable route with respect to telecoms cables and equipment.
OLE Overhead Line Equipment (Catenary) Telecoms System 1 1 1 3
GWEP/TIF/0105 Physical location coordination of OLE cables and cable route with respect to telecoms equipment. OLE Overhead Line Equipment (Catenary) Telecoms System 1 1 1 3
GWEP/TIF/0106Position of signals with respect to OLE (coordination of signalling scheme planning with respect to OLE layouts).
OLE OLE Layout Signalling System 1 2 2 5
GWEP/TIF/0107 Interface of Traction distribution equipment with SCADA for monitoring. OLE Distribution-Power Supply SCADA 2 2 2 6
GWEP/TIF/0108
Compatibility of OLE earthing and bonding with Earthing and Bonding of other disciplines earthing and bonding(inline with overall earthing and bonding strategy).
OLE Overhead Line Equipment (Catenary) and OLE Supporting Structures Earthing & Bonding 2 2 1 5
GWEP/TIF/0109 Electromagnetic Compatibility of OLE with respect to other discipline subsystems.(Internal) OLE Overhead Line Equipment (Catenary)
and OLE Supporting StructuresElectromagnetic Compatibility (EMC) 2 1 1 4
GWEP/TIF/0110 Electromagnetic Compatibility of OLE with respect to other discipline subsystems.(Third party) OLE Overhead Line Equipment (Catenary)
and OLE Supporting StructuresElectromagnetic Compatibility (EMC) 2 2 1 5
GWEP/TIF/0111 Heights and staggers of the OLE Catenary with respect to track structures. OLE Overhead Line Equipment (Catenary) Track Structures (formation and
drainage) 1 1 2 4
A receptive environment to SE • “You guys are so crucial”
• “If you meet any resistance, let me know straight away”
– LDO Project Director (a civil engineer)
• “We have a golden window to achieve a requirements-led design”
– LDO Engineering Director (a mechanical engineer)
• “Oh yeah, we’ve done requirements capture before. No problem”
– Discipline leads (several)
• “and of course, we’ll be producing a verification report for the design”
– Route Section design manager (a mechanical engineer)
35
Work in progress...
1.Reliability, Availability & Maintainability 2.Testing & Commissioning Planning 3.Entry Into Service Planning 4.Safety Assurance & Safety Case Development 5.Operational & Maintenance Development
Conclusions
1.GWEP has set off with a systems engineering – the challenge is to embed it and keep it going
2.Systems Integration / engineering is a core responsibility for the LDO and is facilitating wider collaboration
3.Team approach working jointly with NR and all partners
4.Collaboration is a necessity for good systems engineering on major programmes