Copyright UCT The Implementation of Operational Excellence Program at Phoenix Beverages Limited A research report presented to in partial fulfilment of the requirements for the Masters of Business Administration Degree by L.Hugues Rivet 11 th December 2009 Supervisor: Dr. Hamieda Parker
Transcript
Page 1: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

The Implementation of Operational Excellence Program

at Phoenix Beverages Limited

A research report presented to

in partial fulfilment

of the requirements for the

Masters of Business Administration Degree

by

L.Hugues Rivet

11th December 2009

Supervisor: Dr. Hamieda Parker

Page 2: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

2

Acknowledgement

I would like to thank my supervisor, Dr. Hamieda Parker for her guidance and support

throughout this research report. Her prompt and valuable feedback at the different stages of

the research has been very helpful to me.

I am also very grateful to my company, Phoenix Beverages Limited for their financial support and

particularly to my team in the Supply Chain department for their contribution in this research report.

Special thanks also goes to my family, my wife Sonia, sons Lucas and Mahé for their ongoing moral

support. Thanks also to my brother Jean Marc for his guidance and to my dad Pierre for helping me

putting everything together.

Plagiarism Statement

1. I know that plagiarism is wrong. Plagiarism is to use another’s work and pretend that it is one’s

own.

2. I have used a recognized convention for citation and referencing. Each significant contribution

and quotation from the works of other people has been attributed, cited and referenced.

3. I certify that this submission is all my own work.

4. I have not allowed and will not allow anyone to copy this research report with the intention of

passing it off as his or her own work.

Page 3: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

3

Abstract

Operational Excellence (OE) is a program developed by the Coca-Cola Company to improve efficiencies

along their Supply Chain. This Action Research paper has been written on three projects implemented

simultaneously within the first phase of this OE program at Phoenix Beverages Limited (PBL), Mauritius.

These three projects are within a total of nineteen and are focused in the warehouse operations of the

company. The research shows quantitatively how real improvements in efficiencies have been achieved

through the implementation of lean principles and the use of Six Sigma problem solving methodology.

The paper also captures, through a survey with participants in the OE program, how present were the

key success factors needed in the implementation of such an operational management program. The

results highlight the benefits employees and managers experienced in working in teams and the

challenges of implementing the various tools proposed within the Six-Sigma DMAIC problem solving

methodology.

Key words: Operational Excellence, Lean, Six Sigma, Waste, Warehousing

Page 4: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

4

Table of Contents

Acknowledgement ............................................................................................................................ 2

Plagiarism Statement........................................................................................................................ 2

Abstract............................................................................................................................................ 3

List of figures, table and equation...................................................................................................... 7

1. Introduction .............................................................................................................................. 8

1.1 Research Area and Problem ...........................................................................................................8

1.2 Research Environment...................................................................................................................8

1.2.1 Phoenix Beverages Limited Company ......................................................................................8

1.2.2 OE program .................................................................................................................... 10

1.2.3 OE diagnostic, Opportunities identification and projects selection.................................. 11

1.3 Research Questions and Scope............................................................................................... 14

1.4 Research Assumptions ................................................................................................................. 15

1.5 Research Ethics............................................................................................................................ 15

2. Literature Review .....................................................................................................................17

2.1 Discussion.................................................................................................................................... 17

2.1.1 Lean ...................................................................................................................................... 17

2.1.2 Six Sigma............................................................................................................................... 23

2.1.3 Lean and Six Sigma Integration.............................................................................................. 25

2.1.4 Performance measures: ........................................................................................................ 26

2.1.5 Success factors, challenges and key benefits. ........................................................................ 27

2.2 Critique of the Literature........................................................................................................ 30

2.3 Conclusion ................................................................................................................................... 31

3. Research Methodology.................................................................................................................32

3.1 Research Approach & Strategy..................................................................................................... 32

3.2 Research Design, Data Collection Methods and Research Instruments......................................... 33

3.3 Sampling...................................................................................................................................... 34

3.4 Research Criteria.......................................................................................................................... 35

3.5 Data Analysis Methods ................................................................................................................ 35

3.6 Limitations................................................................................................................................... 36

4. The DMAIC projects and Green Belt Training.................................................................................37

4.1 Project 1 - Optimize Full Pick operations. ..................................................................................... 38

Page 5: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

5

4.2 Project 2 - Optimize Picking operations. ....................................................................................... 40

4.3 Project 3 - Optimise Sorting operations........................................................................................ 44

5. Two sample T test on the Outcome (Y) indicators..........................................................................53

5.1 Testing Y1p1 : % of pallet staged in Project 1. .............................................................................. 53

5.2 Testing Y1p2 : Picking rate in Project 2. ........................................................................................ 54

5.3 Testing Y2p2 : % loads outside in Project 2................................................................................... 54

5.4 Testing Y1p3 : sorting rate in Project 1. ........................................................................................ 55

6. Survey findings- OE implementation at PBL...................................................................................56

6.1 Section A: Leadership, Management support and commitment: .................................................. 58

6.2 Section B: Communication: .......................................................................................................... 58

6.3 Section C: Group / Team Problem solving: ................................................................................... 58

6.4 Section D: Worker empowerment and involvement:.................................................................... 59

6.5 Section E: Training, Tool and Time: .............................................................................................. 59

6.6 Section F: Key learnings, what went well and what went wrong:.................................................. 60

7. Discussion of Results ....................................................................................................................61

7.1 Results of quantitative part.......................................................................................................... 61

7.2 Results of Survey.......................................................................................................................... 62

7.3 Contribution to the literature....................................................................................................... 62

7.4 Implication for managers ............................................................................................................. 62

8. Conclusion ...................................................................................................................................63

9. Future research............................................................................................................................64

10. References: ................................................................................................................................65

Appendix 1: Value Stream Maps (Full Products and Empties) ............................................................69

Appendix 2: Action research Journal.................................................................................................70

Appendix 3: Online Survey Questionnaire........................................................................................77

Appendix 4: Y indicators...................................................................................................................80

Appendix 5: Answers to open ended questions.................................................................................83

Page 6: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

6

Glossary of Terms

Term Definition

OE Operational Excellence – Operational excellence is a Coca-Cola strategy to

achieve transformational results using one common language, tool and

processes

PBL Phoenix Beverages Limited- the company under study

JIT Just in Time

TQM Total quality management

AR Action Research - a research methodology where the researcher is also an

active participant of the project being implemented.

VSM Value Stream Map – A map of all the essential actions/steps (both value added

and non-value added) required to bring a product or service to a customer. It

shows material and information flows as a product makes its way through the

value stream.

DMAIC (Define- Measure- Analyse- Improve and Control) Six Sigma structured

methodology for problem solving

SKU Stock Keeping Units

LSS organisations Lean Six Sigma organisations, companies following both lean and Six-Sigma

management systems.

WMS Warehouse Management System

Page 7: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

7

List of figures, table and equation

Figure 1 - Karlsson Lean Model ........................................................................... 18

Figure 2 - A conceptual Model for improving the efficiency of warehousing operations .....................1

Figure 3 – Old/New process of Full Pick Operations ............................................................................1

Figure 4 – Process flow picking operations ........................................................................................1

Figure 5 - Cause and effect diagram Picking operations ................................................................ 43

Figure 6 - Process / Sub process Map - sorting operations ................................................................ 45

Figure 7 - Sorting process Map ..........................................................................................................1

Figure 8 – Volume by bottle types .................................................................................................1

Figure 9 - Cause and Effect diagram ................................................................................................ 49

Figure 10 - Pre-sorting Index .......................................................................................................... 50

Figure 11 - The Conveyor Table .................................................................................................... 51

Figure 12 - Simplified Process Flow .................................................................................................. 52

Figure 13 - t distribution curve............................................................................................................... 53

Table 1 - Survey results ................................................................................................................ 57

Equation 1- two sample T test with unequal variances .......................................................................... 53

Page 8: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

8

1. Introduction

1.1 Research Area and Problem

Phoenix Beverages Limited (PBL), a total beverage company in Mauritius, has engaged in early 2009 in

an operation management program of the Coca-Cola Company, called Operational Excellence (OE). This

program has been effectively implemented in various other Coca-Cola locations around the world and

its implementation at PBL, Mauritius, would be the first in the East and Central African division.

This paper will evaluate the implementation of the OE program at PBL with a special emphasis on the

warehousing activities of the company. In a first stage, this explorative research will be conducted on

three projects being implemented simultaneously at PBL’s warehouse. These projects form part of a

total of nineteen projects that have been identified and selected by a team of employees during the

diagnostic phase of the OE program. A second section of the research will evaluate the conditions in

which the OE program in general has been implemented at PBL.

These nineteen projects form only the first phase of the OE program at PBL and other phases will follow

in the future. The results of this research could thus serve as an evaluation of that first phase of the

program and could help in the design of the future ones within this program. It could also be used in the

future implementation of the same program at other Coca-Cola Bottlers around the world.

The projects developed in the warehouse operations all have for aim to reduce the cost of operations.

This initiative falls in line with PBL strategic initiative of driving down cost throughout its supply chain in

order to consolidate its leading position in the beverage market in Mauritius. As the paper was being

written, a new brewery was starting its operations in the Mauritian market.

1.2 Research Environment

1.2.1 Phoenix Beverages Limited Company

The company: PBL is a ‘Total Beverage provider’, by far the biggest in the Mauritian beverage market,

that produces/ brews, sells and distributes beer (99% market share), carbonated soft drinks (65%

market share) and table water (55% market share). The company is also involved in the import and

commercialization of wines mainly from France and South Africa. The company employs over 1100

employees working on four different sites namely the brewery, the soft drink plant, the commercial unit

and the head office. The company is divided into eight departments namely Brewery operations, Soft

Page 9: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

9

drink operations, Human Resources, Finance and Administration, IT, Technical, Commercial and Supply

Chain.

PBL was incorporated in 2001 after a merger of two companies, MBL (previously the brewery) and PCM

(previously the Coca-Cola plant). PBL is also opening this year a new brewery in Madagascar.

PBL Facilities: The brewery has a brewing capacity of around 550,000 hl p.a and three packaging lines;

two glass returnable lines and one canning line. The majority of production is for the local market but

PBL is developing rapidly its export market, mainly in Reunion Island where its market share has grown

from less than 2% to more than 10% during the last three years. PBL also export beer to Australia, UK,

Indonesia and some countries in Africa.

The soft drink plant (LIMO) produces all Coca-Cola carbonated soft drinks and table water, five

packaging lines, one for returnable glass bottles, two PET Lines, one bottled water line and another one

for water jars. The total capacity of production lines is around 850,000 hlts p.a. PBL also does some

contract manufacturing under license from Coca-Cola for some countries in the region, for instance in

produces coke in glass for Reunion Island and bottled water for Mayotte.

The Commercial Unit (CU): PBL has one small warehouse on each production site. The one on the

brewery site is a bonded warehouse under customs supervision. All products for the local market are

transferred on a daily basis to the Commercial Unit which is on another site. The warehouse of the

Commercial Unit is 10,000 square meters and has a holding capacity of around 4500 pallets equivalent

to some 350,000 cases of drinks. All PBL delivery trucks are dispatched daily from this unique

distribution centre. PBL has a fleet of around 60 delivery vehicles and uses from 10 to 15 further vehicles

from contractors daily depending of the sales volume

PBL also has its Head office which is located on the brewery’s site, its own garage for repair and

maintenance of its vehicle fleet and a workshop for all refrigeration equipment like coolers, water

dispensers, draught beer and carbonated soft drink dispensers.

As stated previously, this research will have a special emphasis on PBL’s warehousing operations. The

warehousing operations at PBL includes the storage and movement of finished goods as from the end of

the production lines until the goods leave the company’s distribution centre for delivery to customers.

Warehousing can be broken into three sub-processes which are: Forwarding; the transfer of goods from

production sites to the Commercial Unit, Storage and Load Preparation for distribution. These

Page 10: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

10

operations play a crucial role in PBL’s supply chain as logistics and distribution is a major competitive

advantage for the company. PBL benefits from considerable economies of scale in the commercialization

of their products and their portfolio allows the company to provide an attractive commercial offer. The

ordering / planning / preparation and distribution process is a highly synchronized one. All orders

(around 1200 daily) are taken one day prior to delivery, are processed, prepared (picked) and loaded

onto trucks on the same day.

Also critical at PBL is the reverse logistic of empty glass bottles and other returnable packaging

containers like beer kegs, soft drink and CO2 tanks. Over half of PBL’s volume is sold in returnable glass

and the collection of these empty bottles and crates from customers, sorting and return to the

production facilities is an essential and critical operation at PBL’s. The supply of glass worldwide being

under strain and due to its relative small demand in glass, it is a real challenge for PBL to source out the

needed glass bottles to run its business.

1.2.2 OE program

The Coca-Cola Company claims to have the worldwide biggest supply chain. OE is an initiative to ensure

the company becomes also the best supply chain in the world. OE is a Coca-Cola strategy to achieve

transformational results using one common language, tool and processes. It is their umbrella for

numerous improvement initiatives and aims to answer the question of ‘How’ to become green and lean

and develop their high potential talent. OE is basically an adapted toolbox of the best fit from Six Sigma

and lean management for the beverage industry.

OE is defined as the continuous Improvement through a structured and systematic approach, which

improves operating margins of a business by focusing on the elimination of waste and the reduction in

variation through standardized work. Taken from the lean jargon, OE defines waste as; “Those system

elements the customers would rather not pay for”

The OE principles are Value, Value Added Activities, Customer, Waste, Continuous Improvement and

Respect for People. OE uses the acronym ‘DOWNTIME’ to define the 8 types of waste namely: Defects,

Overproduction, Waiting, Not embracing change, Transportation, Inventory, Motion and Excess

production.

Page 11: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

11

OE starts with a diagnostic exercise which prioritizes opportunities to focus the work on the important

few. The diagnostic is jointly performed by the OE core team and the local leaders to

• Provide a detailed data based analysis of the value stream

• Help the organization to understand their current state and a range of opportunities to progress

along the journey to OE ,and

• Deliver a prioritized and resourced list of projects supporting the business strategy, project

implementation plans, resources and KPI targets and current state of the site based on multi-

dimensional maturity assessment.

Following the diagnostic, there are different waves of project implementation. In each wave, a series of

selected projects are implemented following the Six Sigma Define-Measure-Analyse- Improve- Control

(DMAIC) structured methodology of problem solving. The OE program is designed to be run

continuously in the operations.

1.2.3 OE diagnostic, Opportunities identification and projects selection.

The OE diagnostic phase had as purpose to identify opportunities in order to improve the operations at

all levels at Phoenix Beverages Limited. This exercise was coordinated by a core team of Coca-Cola

experts in the OE program and performed by eight different cross functional teams composed of forty

five PBL employees and managers. Each team was allocated with a specific area of the PBL operation.

The diagnostic phase started with training on the eight kinds of waste and each group was given a

template to fill in the waste identification in their respective area of study.

Each group had to present two days later a list of all the waste identified in their area. The following day,

all participants were trained on Value Stream Mapping (VSM), Value added / Non- Value added analysis

and process mapping. The two VSM’s obtained in the warehouse section are in Appendix 1. These tools

are later used by each team to analyse their operations and identify improvement opportunities that

could bring a positive financial impact to the company.

All opportunities identified were presented in a given format and the potential financial impact was

calculated with the help of company’s finance department. At the end of the OE diagnostic phase which

ran for two weeks, each team presented their opportunities to the management of the company, a total

of over 60 opportunities were identified by the eight teams. The OE steering committee, composed of

Page 12: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

12

senior managers and Coca-Cola representative, sat two days later to select the nineteen projects from

the list to be implemented in OE phase one. Within these, three were in the warehouse section namely;

‘Optimise full-pick operations’, ‘Optimise picking operations’ and ‘Optimise sorting operations’.

These opportunities were developed around a common objective, the ‘motto’ of department; “Move

less - Move smart”. For each project, one or more outcome indicator(s) would be tracked over time to

measure the efficiency of the process. The outcome indicators would be in the format ‘Yxpn’ where x is

the indicator number (one project could have more than two outcome indicators) and ‘pn’ represents

the project number. For instance Y1p1 would stand for the 1st

indicator of project 1.

Project 1 (p1): Optimise full-pick operations:

As loads are prepared in the warehouse for delivery, the pallets are stacked in a ‘staging’ location which

is inside the warehouse just next to the loading bays where delivery vehicles are loaded. Around 70% of

these prepared pallets are mixed pallets containing two or more Stock Keeping Units (SKUs). These

mixed pallets are prepared by a team of pickers who themselves move their completed pallets to the

staging lanes. The other 30% of pallets are full pallets, only one SKU. These are taken from the storage

location to the staging location by forklift. The truck load, which is normally composed of eight to ten

pallets, ‘mixed’ or ‘full’ is then checked and later loaded on the delivery vehicle as the latter enters the

warehouse. During the diagnostic phase, the team identified that this double handling of the full pallets

(from storage to staging and from staging to truck) could be eliminated. There is a possibility for these

full pallets to be transferred from the storage location directly on the truck, just in time when the latter

enters the warehouse. This project would save considerable forklift movement (on average 300 and 400

pallets daily) and will also imply a reduction in the amount of staging lanes needed (estimated to around

19%).

The outcome indicator for this project is Y1p1: ‘% of full pallet staged’ and the lower would be that

indicator, the more efficient would be the process.

Project 2 (p2): Optimise picking operations:

Picking operations, which is the preparation of the mixed pallets (two or more SKUs), starts daily at

13:00 and finishes around 22:00. A single team of 20 pickers works at PBL’s warehouse. As orders from

clients are received the distribution planning is done and loads details are sent to the warehouse. The

picking documents are then printed and given out to pickers for pallet preparation. It was observed

Page 13: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

13

during the diagnostic exercise that there was a high amount of idle time for these pickers as they were

working faster than the upstream processes (order entry and distribution planning). The documents

were received in big batches and once a batch was received, there was a rush in the picking area

creating congestion with 20 pickers working simultaneously. Several products are damaged during that

operation and must be repacked. The forklift responsible for the replenishment of the pick faces could

also not follow the pickers’ pace.

Another problem noted was the lack of staging lanes inside the warehouse. Some of the loads had to be

staged outside the warehouse involving a lot of extra transportation. The same pallets had to be later

brought back inside the warehouse for loading the trucks. The quality of products being stored outside is

also affected by being exposed to direct sunlight and rain. Among the loads being prepared for the next

day’s delivery, some would be leaving the warehouse early the next morning but others would only be

leaving the next day in the afternoon during the second trip. The opportunity identified was to reduce

idle time and staging of loads outside the warehouse. This would create a picking operation that would

work much more in a flow, rather than in large batches.

Two outcome indicators were selected for this project, namely; Y1p2: Picking rate (in Cases per hour)

and Y2p2: % of loads being staged outside warehouse. A higher Y1p2 and lower Y2p2 would indicate a

more efficient picking process.

Project 3 (p3): Optimise Sorting Operations:

As stated before, half of PBL’s sales are done in returnable glass bottles. PBL uses 19 different types of

bottles. As the empty bottles are returned to the company, the different bottles must be sorted at the

warehouse before being sent back to the two different production sites. The sorting of these empties is

very time, labour and space intensive as it is a completely manual operation. All unsorted pallets are

unloaded from the delivery vehicles as they enter the warehouse yard and placed in the sorting area. A

group of workers, called sorters, sort these bottles; put them in the appropriate cases which are then

palletised. The pallets are later taken off the sorting area and brought to a staging location before being

sent to production plants on trailers. The diagnostic team identified several opportunities in

restructuring the sorting process that could lead to considerable gain in efficiencies and be linked to a

reduction of the costs involved in the process.

The outcome indicator for this project is Y1p3: Sorting rate calculated in bottles per min

Page 14: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

14

1.3 Research Questions and Scope

The central question of this research will be to test the effectiveness of the lean and Six Sigma tools and

methodology used in the OE Program in the improvement of the warehouse operations at PBL. The

question is formulated as such:

Can the lean and Six Sigma tools and methodology used in the Operational Excellence Program (OE) at

PBL bring a significant improvement in its warehouse operations?

The hypothesis that will thus be tested throughout the research will thus be:

The use of lean and Six Sigma tools and methodology can significantly improve PBL’s warehouse

operations.

The outcome indicators as described in the previous section will be tracked down over the time of the

project. Two data sets of these outcome indicators will be taken, one before the ‘improve’ stage of the

project and one after. The mean value and standard deviation of the two data sets will then be

compared to determine if the indicators have significantly improved.

In the second part of the research, the participants in the OE program will be surveyed to evaluate the

conditions created at PBL for the OE program to be successful. A literature review will first be done on

the success factors necessary for a successful implementation of an Operational Management initiative

like the one implemented at PBL. From this review, a set of variables will be extracted and used as a

base for the survey questionnaire design. This section of the research will also capture the main

challenges and the key learning’s of the employees and management during the implementation

process.

The second main question of the research is thus:

At what level were the key success factors, necessary for a successful implementation, present during

the initial phase of the OE program at PBL?

Furthermore, two sub questions that will be answered in that section of the research report are:

What are the challenges faced by PBL in implementing the OE program at PBL?

What are the key learning points in the implementing the OE program at PBL?

Page 15: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

15

This research can have a significance importance for the future implementation stages of the

programme at PBL. There will also be the possibility for the report to share with other bottlers around

the world, thus providing them a good insight of the OE programme in action.

The scope of the first, quantitative section of the research is limited to the three warehousing projects.

On the other hand, for the survey section of the research covers the totality (19) of the projects selected

for the first phase of OE at PBL.

1.4 Research Assumptions

The first phase of implementation of the project was scheduled to run between June and September

2009. The fact that an external consultant had been contracted to support PBL in this implementation

also reinforced these deadlines. There was however a risk of the timing being moved for a major reason

that could compromise the research but fortunately the OE phase one was successfully closed at the

end of September.

The human factor and reluctance to change from employees constituted the biggest risk of the program.

For instance, a high percentage (around 30%) of the warehouse employee’s remuneration is in terms of

overtime. Improving efficiencies in operations aim to reduce cost via reducing these overtime payments.

During the implementation of these projects, considerable care would be given to the way the benefits

of better efficiency are exposed to the labour force. Fortunately, the warehouse functions with several

casual employees that are employed during several months in the year. Improvement in the processes

could be translated into employing less casual labour while insignificantly affecting full time employees.

Furthermore, as the company is expanding and the workforce is ageing PBL might not need to replace

them with the improvement in operations. A series of communication meetings has been organised with

workers in order to get their buy-in for the project implementation. The principle that has been agreed

in the company is that workers will be reallocated should a process be improved and require fewer

workers.

1.5 Research Ethics

The research subject was approved by both PBL’s Chief Executive Officer of the company and a

representative of the OE program coordinator from the Coca-Cola Company. It was unfortunately not

Page 16: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

16

possible to obtain any documentation from the Coca-Cola corporate office on past OE implementations

for confidentiality reasons.

As the OE program has been developed by Coca-Cola for the company to gain a competitive edge on the

competitors, considerable care should be given to the confidentiality aspect of this research paper. The

publication of the research paper to other bottlers will still have to be considered with the CEO after the

final write up.

Considerable care was also taken during the progress of the projects for all participants to be aware of

my double role of researcher and team leader. This was stressed in all meetings.

Page 17: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

17

2. Literature Review

This section will review the literature on lean and Six Sigma and their application in various operations

from different industries. In the lean section, special emphasis will be put on waste reduction and value

stream mapping as these were the key tools used throughout the development of the OE program. A

review of using these tools in warehousing operations is also done in that section. Both lean and Six

Sigma management systems are discussed separately first before a brief review of their

complementarities and how they can be integrated together in what is called lean sigma, or lean Six

Sigma management system. There is also a review of the literature on the various performance

measures used in operations management. These are particularly important in determining what needs

to be measured and what would be the best indicators to be used for each of the projects under study.

For the second part of the study, a review of literature is done on the important factors and challenges

faced by companies when implementing such operation management initiatives. The objective of this

section is to identify a set of variables from the literature that will be measured at PBL during the

implementation of OE. From these variables, a series of questions will be derived to set up the survey.

2.1 Discussion

2.1.1 Lean

The concept of lean management can be traced back to the Toyota production system (TPS), a

manufacturing philosophy pioneered by the Japanese engineers Taiichi Ohna and Shigeo Shingo (Inman,

1999). According to Hines et al (2004) lean is constantly evolving and its definition would only be a ‘still’

image of a ‘moving target’ that could be valid only at certain point in time. Petterson (2009) suggests

that this could be the explanation for the apparent differences in the definition of lean by various

authors on the subject in the literature and that these differences could be problematic on a practical

level when an organisation aims to implement the concept. Petterson (2009) reviewed available

literature on lean and compared this management concept with TQM. He comes to the conclusion that

at the philosophical level, both lean and TQM have many ideas in common, particularly concerning

continuous improvement and the system perspective approach. However he identified significant

differences between the two concepts at operational level and in their fundamental values, especially

regarding humanistic values. Petterson (2009) did not support the conclusion from Shah and Ward

(2003) that TQM and other bundles are part of lean. Karlsson et al (1996), also identified this lack of

Page 18: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

18

precise definition of what lean production is and developed a model that operationalises the different

principles in lean production, with a focus on the manufacturing part of the company. The development

of this model was developed from available theory on lean principles and is presented in Fig 1 below:

Figure 1 - Karlsson Lean Model source: Karlsson et al (1996)

Karlsson et al (1996) stressed the point that lean should be seen as a direction rather than as a state to

be reached after a certain time. They therefore argue that the focus lies in the change of the

determinants and not in their actual value. Similarly, Hayes et al (1994) proposed that we need to

measure progress made in an effort to become lean. They put much emphasis on the word ‘progress’

since lean can be seen as an intended direction and not as a state or as an answer to a specific problem.

Page 19: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

19

Lee-Mortimer (2006), in his study on a UK-based electronic product manufacturing operation

demonstrates the high benefits brought by lean. On effect the plant is helped to move from a batch and

queue production system to creating flow through the whole plant reducing WIP and lead time and

improving productivity, without compromising previous gains from the highly effective continuous

improvement program. He explains how these changes have been achieved by the creation of work cells

and the challenges faced by the necessity to break these ‘islands of excellence’ core processes in order

to achieve this transition from batch and queue to a flow production system.

Gunasekaran et al (1999) proposed a conceptual model to improve the efficiency of warehousing

operations. Their model is discussed from two perspectives, ‘Just-in-time’ (JIT) and Total Quality

Management (TQM). While JIT looks at reducing inventory levels and buffers, creating demand pull and

dealing with suppliers’ reliability, TQM focuses on the long term commitment against war on waste,

continuous improvement, training and ergonomics. Their model is graphically represented in figure 2

below:

Gunasekaran et al (1999) state that the proper approach to JIT implies co-operation between suppliers /

clients to make sure inventory is not just transferred from one location to another, but that it is rather

minimised throughout the supply chain. The demand pull system definition of JIT implies that planning

begins with the final stage and works backwards through every process up to the suppliers of primary

Figure 2 - A conceptual Model for improving the efficiency of warehousing operations Source : Gunsekaran et al , 1999

Page 20: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

20

raw material. For JIT to function, essential criteria are necessary like accurate forecasting, proper

communication and trust among partners, efficient communication channels, long term contracts with

suppliers for them to ‘play the game’ and removing non-value activities throughout the supply chain

(Gunasekaran et al, 1999).

TQM is a management approach centred on quality which needs the involvement of all organisation

members and aiming at long term success through customer satisfaction and benefits to all stakeholders

of the organisation (Gunasekaran et al, 1999). They also found that the processing of information plays a

vital role in warehousing activities and that the information flow is often separated from the physical

flow, resulting in buffers and delay in the process. They thus recommend a greater emphasis on the

information flow. While they agree that in general JIT bring considerable benefits in the running of a

warehouse, there are some constraints as this policy requires more transportation, thus traffic and

other associated problems may arise when safety stock is not held for certain products (Gunasekaran et

al, 1999).

Machinery Inc, a leading European manufacturer of food processing machines and equipment failed in

their first attempt to introduce lean management in 1997 (Sherrer-Rathje et al, 2009). They attributed

this failure to the lack of senior management commitment due to the bottom-up approach used in that

implementation. In 2006 however, a second attempt at introducing lean was initiated in order to match

demand and reduce production costs. This time Machinery Inc chose to do a pilot implementation in

one business unit only where all efforts had been concentrated. The project was then ‘sold’ to the rest

of the company when the implementation in this business unit had proved itself worthwhile.

Lean management has been successful in several industries apart from just manufacturing. Several

successful implementations of lean practices exist as for instance the OLA project, a reengineering

action based on lean thinking principles for hospital care, within six public hospitals in Florence, Italy

(Gemmi et al, 2009). In this project, when applying lean principles to reengineer their processes, they

achieved up to 10% reduction of average length of stay in surgery, up to 18% reduction in overall

preparatory permanence in hospital and up to 85% reduction of total out-of-ward days for surgery.

Waste

Waste (‘muda’ in Japanese) as defined by Fujio Cho, former Toyota President is “anything other than the

minimum amount of equipment, materials, parts, and workers (working time) which are absolutely

Page 21: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

21

essential to production” (Jacobs and Chase, 2008, p226). In shorter terms, it can be defined as any

activity that does not create value or for which the customer will not be prepared to pay for.

Taiichi Ohno, late Toyota executive categorized waste into seven types, namely overproduction, waiting,

transportation, inventory, processing, motion and defects. Womack and Jones (1991) argue that waste

is everywhere, visible to even the casual observer on an average day in an average organisation. They

themselves added an eighth category of waste which is the design of goods and services which do not

meet the needs of customers. They defined the lean philosophy as the ‘antidote’ to Muda (Womack and

Jones, 1997).

According to Slack et al (2006), one of the most significant parts of the lean philosophy is its focus on the

elimination of all forms of waste. In their model, they propose four methods of eliminating waste;

streamlined flow, match demand exactly, increase process flexibility and reduce the effects of

variability. A series of techniques and tools like ‘Pull controls’ or ‘Kanbans cards’ are used as support for

waste elimination.

Emiliani (1998) argues that the tracking of all form of waste is a continuous, never-ending process and

that it is regarded as one of the few things that non-production workers can do to add value to

products. In his paper ‘Lean Behaviour’ (1998), Emiliani interestingly defined another type of waste he

called ‘behavioural waste’ which refers to the tremendous amount of waste that normally exists in intra-

and interpersonal relationships. He explains the destructive effect that ‘fat behaviours’ (as opposed to

lean behaviours) can have on lean initiatives in the organization and the power of communication in the

creation of value.

Emiliani (1998) explains that batch and queue production methods are the intuitive way people think,

seeking for economical lot sizes, minimizing set up and change over times. These production methods

drive along in their process a large amount of waste. Similarly, he adds that ‘fat behaviours’ are also

intuitive and almost invisible to the people in the organization because their own mindset constitutes

the base of this mental model.

Karlsson et al (1996) argue that inventory; apart from being itself wasteful, also hides other problems,

preventing their solution. He adds that inventory should not be removed as such but it is rather the

reasons for the existence of inventory that should be removed.

Page 22: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

22

Value Stream Mapping

Value stream mapping (VSM) is a tool created by the lean production movement for redesigning the

productive system (Lasa et al, 2008). It has for purpose to help researchers or practitioners to identify

waste in individual value streams and find solutions for the elimination of these wastes (Hines and Nick,

1997). While VSM is mainly focused on the analysis and improvement of manufacturing environments

with disconnected flow lines (Rother and Shook, 1998), it can also be used in non manufacturing

operations and services.

Rother and Shook (1998) identified five phases in the use of VSM, namely; the selection of a product

family, drawing the current state mapping, the future state mapping, defining the working plan and

achieving the working plan. Lean thinkers provide some guidelines to assist in the drawing of the future

state map (Rother and Shook, 1998; Marchwinski and Shook, 2003). Some of these are:

• Production rate must be dictated by demand, ‘Takt’ time dictates that rate

• There should be continuous flow in-between the different work centres where possible, or else

to employ pull systems should be used.

• Only one process should command the production of the different parts, called the pacemaker

process. This process scheduling will deal with the maximization of production levelling on mix

and volume.

Lasa et al (2008), used a case study to assess the effectiveness of the VSM technique for the redesigning

of productive systems. They found the technique highly effective for the described purpose and

achieved a reduction in the lead time for the production of plastic parts being studied, from 26 to 22

days, within the first six months following the VSM exercise.

Hines et al (1998) pointed out several limitations of the value stream mapping process and introduce

value stream management as “a new strategic and operational approach to the data capture, analysis,

planning and implementation of effective change within the core cross–functional or cross-company

processes required to achieve a truly lean enterprise”(Hines et al, 1998, p 25). The authors claim that

Value Stream Management also includes various education and policy deployment stages which provide

a far better framework for pursuing company or supply chain development.

Luyster and Shuker (2002) emphasized that value stream management is about putting people first,

reducing the speed and effort required of workers and not making people work faster or harder. They

Page 23: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

23

identified the following four critical behaviours when performing value stream management; making a

true commitment, thoroughly understanding customer demands, accurately illustrating the current

position, and effective communication.

Arnheiter et al, (2005) identified a series of key misconceptions around lean management, the first of

which is that lean is associated with laying off employees, while the term ‘lean’ itself, especially when

associated with the term ‘mean’, might show that lean companies should, according to Emiliani (2001)

make every effort to re-assign and re-train employees in value-adding activities. Another misconception

is that lean is applicable only in manufacturing and to Japan only. Literature shows very successful lean

implementation outside Japan and in non-manufacturing industry. A last misconception discussed by

Arnheiter et al is that lean is applicable to certain specific environments only where the lot size of one

could be attained.

2.1.2 Six Sigma

“Six Sigma was founded by Motorola Corporation and subsequently adopted by many US companies,

including GE and Allied Signal” (Arnheiter et al, 2005, p 5). Many argue that Six Sigma is a repackage of

old quality management practices, principles and tools / techniques (Clifford, 2001: McManus, 1999). Six

Sigma takes from TQM the concept that everyone in the organisation is responsible for quality, the focus

on customer satisfaction and the significant investment in education and training. (Arnheiter et al,

2005). On the other hand, several other researchers recognise the Six Sigma approach as an emergent

structure for quality management that helps organisations to control process improvement activities

more rigorously (Schroeder et al, 2008). Schroeder et al (2008) recognised several distinctive features of

Six Sigma from traditional TQM approaches, as follows:

• Unique focus on financial and business results

• A distinctive use of structured methods for process improvement

• Use of specific metrics is new with Six Sigma

• Use of significant number of full time specialists inside the organisation

In their study to define Six Sigma and from the literature, Schroeder et al (2008) suggest and retain the

following four relevant constructs or element of their Six Sigma definition:

Page 24: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

24

• Parallel-meso structure: Like quality cycles as an example of parallel structure (e,g., Adler et al,

1999; Lawler, 1996), The Six Sigma approach creates in parallel to the organisation hierarchy,

another structure for the management of projects comprising of champions, black and green

belts. This structure is defined as a parallel-meso structure (Schroeder et al, 2008), integrating

both the micro and macro levels of analysis. This contrast with the traditional quality circle

structure where members of these teams have little authority and power to implement their

ideas and many suggestions are not implemented Lawler (1996). “Various mechanisms in Six

Sigma, such as strategic project selection and leadership engagement help achieve multilevel

integration” (Schroeder et al, 2008, p 540).

• Improvement specialists: many Six Sigma organisations employ full time ‘Black Belts’ whose

main responsibilities are to act as instructors and to provide technical assistance and mentoring

(Slater, 1999). The parallel-meso structure as defined above is also supported by green belts

who are employees that receive a basic training on Six Sigma methodology and tools. The black

belt normally reports to the project sponsor, known as the champion, who ensures the

availability of critical resources to the team.

• Structured method: Six Sigma uses a structured method which is patterned after the PDCA cycle

(Shewhart, 1931, 1939), called DMAIC (Define, Measure, Analyse. Improve and Control). This

structured method fosters emphasis on going to the root cause of the problem and allows the

use of a common methodology and framework for problem solving throughout the organisation

• Performance metrics: Performance metrics used in the Six Sigma methodology is twofold, first in

the customer-oriented metrics and secondly the financial metrics. Understanding the true

customer need is at the root of Six Sigma. “A fundamental aspect of Six Sigma methodology is

identification of critical–to-customer (CTQ) characteristics that are vital to customer

satisfaction” (Evans and Lindsay, 2005, p. 184). According to Smith et al (2002), a financial

analyst on a Six Sigma project will help to translate the performance of the team into dollars and

cents.

Arnheiter et al, (2005) discussed some misconceptions that are traditionally associated with Six Sigma,

the first being that the Six Sigma methodology is ‘the new flavour of the month’ (Arnheiter et al, 2005, p

12). Other misconceptions is that the absolute value of 3.4 defects per million opportunities is an

absolute goal and that Six-Sigma is a quality focus program only whereas it relates in reality to the entire

customer value equation.

Page 25: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

25

2.1.3 Lean and Six Sigma Integration

With disparate roots but similar goals, Lean and Six Sigma have both proven to be effective on their

own. Arnheiter et al, (2005) explain that companies embracing either of these management systems

face after some time diminishing returns. They can also experience some possible gains for lean

companies to apply Six Sigma systems and vice versa. Sheridan (2000) used the term Lean Sigma to

describe a management system that combines these two systems. Arnheiter et al (2005) use the term

Lean Six Sigma (LSS) organisation to describe an entity that integrates the two systems.

Arnheiter et al (2005) proposed that lean organizations should make use of more data in decision

making and use of methodologies that promote a more scientific approach to quality. Similarly, they

propose that Six Sigma organizations should include training in lean management methods that

eliminates all kinds of waste, reducing set up times and mapping the value stream.

Arnheiter et al (2005) suggested that Lean Six Sigma organizations would capitalize on the strengths of

both lean and Six Sigma management systems by including the three primary tenets of lean

management:

• Incorporate the philosophy that aims at maximizing the value added content of all operations

• Constantly evaluate incentive systems in place

• Incorporate a management decision-making process that bases every decision on its relative

impact on the customer

And the three primary ones from Six Sigma which are:

• Provide data driven methodologies in all decision making

• Promote methodologies that strive to minimize variation of quality characteristics

• Design and implement a companywide and structured education and training regimen.

Dahlgaard et al (2006) showed from their perspective that the lean production philosophy and the Six

Sigma steps are essentially the same and that both have developed from the same root, the Japanese

TQM practices. They argue that the concepts and tools of lean production and Six Sigma quality should

not be seen as alternatives to TQM but rather as a collection of concepts and tools which support the

overall principles and aims of TQM.

Page 26: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

26

2.1.4 Performance measures:

Taj (2008) argues that to stay competitive, enterprises should try to make their manufacturing facilities

more efficient and lean. He adds that traditionally, managers have relied heavily on accounting metrics

to determine efficiency but those metrics alone are inadequate for managing a lean manufacturing

operation. A profit and loss statement for instance is a result of a long chain of decisions that may go

back for years or even decades. Managing a lean factory requires key information that reflects what is

happening upstream in these chains of events.

Ahlstrom and Karlsson (1996) state that it is not always easy to justify the implementation of lean

production program due to some decrease in productivity indicators calculated from traditional

management accounting systems. They claim that there is a need for some intermediate indicators to

assess the changes taking place and the effort to introduce lean production. Sanchez et al (2001),

following the work of Ahlstrom and Karlsson (1996) introduced a check list of 36 ‘lean indicators’ broken

into six different indicator groups and tested their use a sample of manufacturing firms. Their study

concludes that sixty percent of the lean indicators were used by more than half of the surveyed

companies and that 17 percent were used by more than 75 percent of the companies. As expected, they

found that large companies significantly use more of these indicators than small and medium ones.

Gunasekaran et al (2001) found a need to study the measures and metrics used in supply chain

management because of a lack of balanced approach between financial and non-financial performance

measures. They also identified a lack of distinction between metrics at strategic, tactical and operational

levels. According to Kaplan and Norton, while some managers concentrate on financial measures, others

concentrate on operational measures and these inequalities does not lead to metrics that can represent

a clear picture of the organisation performance.

Maskell (1991) suggested that while financial measures are important for strategic decisions and

external reporting, non-financial operational measures are often more suitable for the day to day

control of the operations. Gunasekan et al also warned about the important choice to be made when

choosing the right number of metrics to be used and state that performance measurement can be

better addressed using a good few metrics rather than a large number of them.

Cavinato (1992) state that since logistics cut across functional boundaries, one should be careful during

decision making as the cost in one area can have an impact in other areas. When measuring the

Page 27: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

27

performance of logistics operations using financial measures, one should be careful to consider the cost

implication in all areas and use a trade-off based on a logistic-oriented cost accounting system that will

identify the cost associated with each unique activity as well as the influence on the other linked

activities (Gunasekaran et al, 2001). Lee and Billington (1992) argue that for effective performance

measurement, supply chain metrics must be linked to customer satisfaction. Gunasekaran et al (2001)

proposed to measure customer satisfaction and service by using as metrics flexibility, customer query

time and the post transaction measures of customer service.

In their study on supply chain performance metrics, Gunasekaran et al (2001) concluded that there is a

shift from the traditional cost accounting methods. New techniques take into account the cost of

individual activities in the supply chain and the impact of these activities on other functions such as

customer service, asset utilisation, productivity and quality.

Deming (1986, 1994) and others have stressed on the importance of understanding customers’ present

and future demands when designing products and services. Evans and Lindsay (2005) claim that a

fundamental aspect of Six Sigma methodology is the identification of the critical-to-quality (CTQ)

characteristics that are vital to customer satisfaction. Linderman et al (2003) support that argument by

adding that customer requirements help establishes project improvement goals and direct improvement

efforts of Six Sigma teams. According to Smith (2002), the use of financial metrics to quantify the

process improvement of the Six Sigma projects is also essential throughout the project different phases

and also upon completion of the project, for up to a year to make sure the benefits are realised.

2.1.5 Success factors, challenges and key benefits.

For many years, the main emphasis in the strategic manufacturing literature has been on the

formulation side of strategies (Grundy, 1998; Al-Ghamdi, 1998). The issue of implementation has

received less attention although the implementation of strategic initiatives has frequently been

considered to be the graveyard of strategy (Grundy, 1998). Grundy (1998) points out that strategic

management should move from a 90:10 concern with strategy formulation relative to implementation

to at least a 50:50 concern with each. Otherwise, no matter how good the strategic decisions are,

companies would not benefit from them (Al-Ghamdi, 1998). Beer et al (1990) also reinforce that idea by

attributing much of the shortcomings in the strategy area to failures in the implementation process

rather than in the formulation of the strategy itself. Van Der Merwe (2002) argued that strategies do not

Page 28: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

28

fail when they are being analysed or when the objectives are being set but during implementation and,

more particularly, due to the lack of proper project management.

Minarro- Viseras et al (2005) studied the various Key Success Factors (KSF) essential for the proper

implementation of strategic manufacturing initiatives. They found that the highest number of KSFs was

found under the project management element of the people category. The results of their study

demonstrate the importance of recruiting the right individual who is able to positively influence the

ultimate success of the SMI implementation project (Minarro- Viseras et al; 2005). Their results also

show that in the manufacturing environment, the successful implementation of the project require full,

continuous and visible support from the senior management. Senior management must be behind the

project, the project manager and the project team and everyone in the organization must be aware of

that (Minarro- Viseras et al; 2005). Another key finding in their studies is that the implementation

success comes more critically from the human or people side of project management as opposed to

organization and systems related factors.

Achanga et al (2006) identified leadership and management as the most critical success factor for lean

implementation within SMEs. They state that strong leadership and management allows a vision and

strategy while permitting a flexible organizational structure to facilitate the change process. Leadership

and management support is also critical for the provision of resources, foster the learning environment

and permits for the company to acquire new ideas and technologies. Achanga et al (2006) also identified

other critical success factors namely the financial capabilities, skills and expertise and organizational

culture.

Antony and Banuelas (2002) studied the key ingredients for the effective implementation of Six Sigma

programs. They identified a total of eleven critical success factors from the literature and went to see

how the organizations in the UK prioritise these key ingredients. They found the top three most

important ingredients to be respectively; managing involvement and commitment, understanding the

Six Sigma methodology and linking the program to a business strategy.

Bhasin et al (2006) examined the underlying reasons surrounding the low rates of successful

implementation of lean initiatives. They found that for a successful implementation of lean initiatives,

not only it is necessary to implement most of the technical tools but that an organisation’s culture needs

transforming too. They advocate that lean has a major strategic significance through its implementation

process and that viewing lean as a set of tactics rather than embracing it as a philosophy is highly

Page 29: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

29

responsible for the number of failures in lean initiatives. Bhasin et al (2006) stressed that whilst lean is

concerned with the reduction of waste at all levels, it is also about bringing change in the corporate

culture. They identified a list of cultural requirements necessary for successful lean implementation,

these being:

• Ensure that decisions are taken at lowest level in organisation

• Have a clear vision of the desired state

• Ensure that that there is a strategy of change whereby the organisation communicates how the

goals will be achieved.

• Assign responsibilities within a pilot programme and ultimately within whole organisation

• Develop supplier relationship based on mutual trust and commitment

• Nurture a learning environment

• Systematically and continuously focus on the customer

• Promote lean leadership at all levels observed by a number of lean metrics at all levels

• Maintain the challenge of existing processes

• Maximise stability in a changing environment.

• Assess the fraction of an organisation’s employees operating under lean conditions

• Observe the proportion of organisation’s departments pursuing lean

• Lean requires a long term commitment.

Boyer and Sovilla (2003) argue that top management should not only demonstrate commitment and

leadership but that they must also work to create interest in the implementation and ensure changes

are communicated to everyone in the organisation. A lack of investment from their part may also affect

the success of the project in a less visible ways as employees will experience discouragement if they do

not perceive top management’s total dedication’s in the implementation of the initiative (Boyer and

Sovilla, 2003).

Worley and Doolen (2006) studied the role of communication and management support in a lean

manufacturing implementation of an electronics manufacturing company in the northwestern USA. They

found that failures attributed to management support shared some common characteristics, namely:

• Executive management must provide more information on lean and the reason for

implementing

• More resources must be allocated to the lean initiative in terms of time and material

Page 30: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

30

• Employees need to be able to see the progress of results

• Management must create a plan so that the entire organisation moves towards a common goal.

They also found that while lean initiative was initially implemented as a customer’s request, more

success was realised at an employee’s perspective by creating better relationships between

management and employees on the manufacturing floor.

Worley and Doolen (2006) in the same study also found evidence that lean implementation had a

positive impact on the communication lines between management and employees. It was further

expected that this would extend to inter-departmental communication with the progress in the lean

implementation.

Boyer (1996) tested and confirmed the positive relationship between a company’s commitment to lean

production and its commitment to supporting investment in infrastructure. This research was done with

companies in the metalworking industry. He studied four infrastructural investments namely; quality

leadership, the use of small groups or team for problem solving, training and worker empowerment.

Dahlgaard et al (2006), found that in lean and Six Sigma implementation, there tends to be a large focus

on the tools and techniques used and at the same time too little focus on how to build the right

company culture, where basic human needs are understood and respected.

2.2 Critique of the Literature

The literature on Lean and Six Sigma as reviewed in the previous section is mainly based on surveys

capturing the perceptions about the effectiveness of these methods when applied in companies. The

literature on the subject is mainly focused on manufacturing operations. Literature on operations

management in warehousing operations is very rare. Apart from the conceptual model developed by

Gunasekaran et al (1999), the researcher during the review of the literature did not found any other

study in that specific field. This research aims to bring a very practical and concrete study of the

implementation of an operational management program, with hard figures to breach that gap.

Warehousing is by its nature a ‘non-value added activity’ and in the extreme case of Just-in-time should

be totally eliminated. The implementation of lean principles and Six Sigma methodology in a

warehousing operation is interesting as there is a big scope for cost reduction.

Page 31: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

31

2.3 Conclusion

Throughout the literature review, it is acknowledged that Lean and Six Sigma systems used separately or

together can bring improvement to any operation. These methodologies have to be adapted to the

business environment and their success relies heavily on the philosophy behind the systems and the

capacity of the organisation to adapt its culture to fit those methods. We saw that implementation of

Lean and Six Sigma is a ‘way of working’ rather than a project with a defined scope. These management

systems are described as journeys rather than destinations and that the absolute target should be set

with respect to the customer. The application of Lean and Six Sigma goes beyond manufacturing and the

principles and tools are being applied more and more in the service industry. The principles of Lean and

Six Sigma will be used in the research for the design and implementation of the different projects

through the action research methodology.

The importance of performance measures to track the progress of Lean and Six Sigma projects and the

importance of both the financial and non financial performance measures were also discussed. We must

be careful about the use of traditional performance measures as these could indicate some drop in

productivity when implementing lean initiatives, hence the importance of intermediate indicators. The

literature review allows an insight in determining the performance measures that will be used to track

down the progress of the projects being implemented and ultimately determine if these projects have

been successful or not.

In the last part of that section, , through a review of the critical success factors and challenges of

implementing lean and Six Sigma initiatives in the literature, we have identified a list of variables which

will be used in the development of the questionnaire to be used for the survey section of the research.

The variables identified are: quality leadership and management support and commitment,

communication, group/team problem solving, worker empowerment, training tools and time.

Page 32: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

32

3. Research Methodology

3.1 Research Approach & Strategy

The research will first use a deductive research approach to test the effectiveness of applying lean and

Six Sigma concepts in the warehouse operations of Phoenix Beverages Limited. In the first part of the

research, a quantitative strategy will be used to test the hypothesis. As outlined in the first section of

this paper, the comparison of the outcome indicators prior and post project implementation will aim at

determining the progress, if any, realised during the course of the project.

The second part of the research will use a more inductive approach using a survey approach to evaluate

the presence of success factors at PBL during the OE program. This section will also aim at capturing the

challenges and key learning points experienced by PBL’s employees and management during the

program. The main target of this section is to come out with a set of recommendations that could be

useful for the future phases of implementation of this program and / or the implementation on other

sites.

Westbrook (1994) says that while POM (Production and Operation Management) research has been

traditionally based on modelling techniques, there is a need to do research which will be of practical

value to managers and that will be integrated instead of being focused on sub-system techniques. This

raised the question of research method in this particular field. He further adds that since the POM field

is an area in need of a broader conceptual basis, the theory-building potential of action research should

make it a major method in the future.

An ‘Action Research’ Methodology will be used in the writing of this paper. Goughlan and Coghlan

(2002, p 220) defined Action Research (AR) as “an approach to research that both aims at taking action

and creating knowledge or theory about that action”. They claim that the core characteristic of Action

research is that it is a participative and integrative method where the researcher himself is both an

observer and a participant in the specific project he is researching. They added that Action Research is

about action ‘in’ research rather that action ‘on’ research, that it is concurrent with action and

participative. In the case of this paper, the researcher is an active participant in the projects under study

and a member of the senior management of the company. The OE projects are being implemented

between June and August 2009, which coincide with the writing of the research.

Page 33: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

33

3.2 Research Design, Data Collection Methods and Research Instruments

In the quantitative section of the research where the effectiveness of the lean and Six Sigma tools and

methodology are tested in PBL’s warehouse operations, a comparative research design will be used to

evaluate the different projects being implemented in the warehouse operations. In this section, the data

collected through the implementation of the different projects will be used to evaluate their relative

success. The performance measures that have been set up to track down the effectiveness of each

process will be kept beyond the project and be used as the KPI for the respective process.

Particular attention will be given to possibility of experiencing the ‘Hawthorne effect’ during the first

few weeks when the observations will be made, which could be a treat to the internal validity of the

research. Bryman and Bell (2007) described the effect of the experimenter or the fact of being studied

on the subject is commonly referred to as the “Hawthorne effect’ following the works of Hawthorne of

the Western Electric Company in the USA during the late 1920s and early 1930s.

As suggested by Coughlan P. and Coghlan D. (2002), an Action Research Journal has been kept

throughout the conduct of the research for the researcher to note the observations and learning points

at each stage of the implementation process. The journal used throughout the research can be found in

Appendix 2. The Six Sigma DMAIC (Define-Measure-Analyse-Improve-Control) methodology is used in

the implementation process of the OE projects and each of these five steps uses a set of Lean and Six

Sigma tools. According to Schroeder et al (2008, p 542), “the DMAIC method is consistent with the

problem-solving steps of the PDCA model and places more emphasis on integrating specific tools into

each step of the method”.

In the second, survey part of the research, a survey with the participants in the different OE projects will

be done to analyse the level of key success factors present, the challenges and key learning points of the

various actors of the first phase implementation of the OE project. In order to design the questions for

the survey, a study of the literature was done to identify the various factors necessary for a successful

implementation of an operation management initiative. From that study of the literature, which can be

found in section 3.1.5 above, a set of variables were determined which would each form a section of the

survey.

Page 34: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

34

The variables identified are:

• Leadership, management support and commitment

• Communication

• Group / team problem solving

• Worker empowerment and involvement

• Training, tools and time

The survey questions were then developed around these variables with a series of four to six questions

per section. A last section of the survey was added to capture the key learning’s, what went well and

what went wrong during the program implementation. The survey questionnaire developed has been

done using the GSB online survey tool and is accessible through the link (see appendix 3):

http://gsblive.uct.ac.za/projects/ssurvey/TakeSurvey.asp?PageNumber=1&SurveyID=9MMm73KI2o4K12

The survey has been designed to be self completed but some respondents needed help as they had no

access to the internet. The researcher took necessary precautions so that appropriate support was given

to respondents while limiting the risk of putting a bias by those helping. This constituted a definite risk

to the internal validity of the research. The respondents were guaranteed that the answers would stay

anonymous and confidential. This questionnaire was tested by four of the researcher’s direct reports

before implementation.

3.3 Sampling

In the first part of the research, the outcome indicators as described before are tracked over a period of

four months. Two sample sets are taken for each of the four outcome indicators. The first sets of records

comprise of the first 30 records on and after 1 June 2009. The second sets are the last thirty records on

or prior to 30September 2009.

The survey questionnaire was sent to the whole population of OE participant, a total of 37 employees

and managers. A minimum target of 30 responses for the survey was expected in order to have an

appropriate sample size of respondents: 27 were finally obtained. The challenge in the design of the

questionnaire resides in keeping the right balance between convenience and the richness of information

to be collected. The language barrier was also a problem in some cases where the employees are not

very conversant with the English language. Particular attention was given to that point when writing up

Page 35: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

35

the questions. Four direct subordinates of the researcher helped those without internet access to

answer the questionnaire.

3.4 Research Criteria

The outcome indicators have been developed to track down the progress of the projects. Particular care

has been taken in the determination of these outcome indicators as getting these wrong could lead to a

complete failure of the project. These outcome indicators were validated by the process owners, the

line managers and the Six Sigma Black Belt facilitating the implementation process, thus ensuring

reliability and validity. Furthermore, the outcome indicators will be in all cases calculated from hard data

thus limiting the risk of inter-observer inconsistency.

The findings from the survey part of the research could be helpful for PBL in the future implementation

phases of the OE program as this is meant to be a long term project, if not a new way of operating. The

research, even if very specific to PBL’s context and culture, could also be helpful for other bottlers going

through the implementation of the OE program. Detailed information about the context of operation

will be given to ensure the research covers a fair about of external validity and reliability so that findings

could be applied in other locations.

3.5 Data Analysis Methods

A two sample T-tests (unequal variance) is used to compare the two sets of outcome indicators and

determine if a significant progress is recorded in each of the processes under study. These tests are one

sided tests as the purpose of the hypothesis is to determine if there has been an improvement in the

process. The T-tests are run with a confidence level of 95%.

For the Survey section of the research, a single ‘Likert’ scale (strongly agree- 5, Agree – 4, Neutral – 3,

disagree- 2, totally disagree – 1) will be used for all closed ended questions. For each question, a score

from 1 to 5 will be calculated from the response. Ultimately, a mean and standard deviation is obtained

per section of the survey from the score of the individual questions. Coding is applied to the answers to

the open ended questions which compliment the results of the closed ended questions.

Page 36: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

36

3.6 Limitations

The projects are being implemented and evaluated within a period of four months only which is very

short to be properly evaluated. There is first a serious risk of experiencing the ‘Hawthorne effect’ as

described in section 4.2 of the paper. It must also be considered that PBL will be at the start of a learning

curve. More long term benefits that could be realised by PBL following the implementation of these

projects would not captured during the course of this study. It is also important to consider that PBL’s

operations are very seasonal due to the intrinsic nature of their business, that is, sales of beverages. A

short term analysis of the operations therefore might not capture appropriately the scale of

transformation in the processes.

The description of the context and different factors influencing the outcome indicators, are described as

far as possible so that the findings of the research could be put in context. In one particular project, p3 -

Optimise the sorting process, the outcome indicator has also been heavily influenced by the rainy

season. Also in the same project, operations were significantly affected by another important project

that ran in parallel, the light weight project that is discussed further.

The small population of participants in the OE project constitute a limitation to the survey part of the

research. There is also a risk, despite precautions taken, that the respondents do not feel secure enough

to talk freely about their experience in the OE program.

For both the quantitative and survey part of the research, a second reading of the Y indicators and

redoing the survey with participants on the second phase of the OE programme after a period of around

6 months would have brought considerable value to the study

Page 37: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

37

4. The DMAIC projects and Green Belt Training.

The projects were to be run in parallel with a ‘Green Belt Six Sigma’ Training. During that training, the

participants were introduced to the different tools within the DMAIC methodology. Team leaders and

project champions of the various projects were concerned by this ‘Green belt training’. The training

started with the first two steps of DMAIC, namely ‘Define’ and ‘Measure’, beginning of June 2009 and

the teams were requested to complete these two steps by the end of the month. After being reviewed,

the training was continued on the two next steps, ‘Analyze’ and ‘Measure’ that were due for end of July

2009. Similarly, the training on ‘Control’ was scheduled for beginning of August after review of ‘Analyse’

and ‘Measure’. The projects were closed at the end of August 2009.

The projects were classified into two groups, ‘Track 1’ projects were the ones with a pretty clear and

direct implementation, basically a project where the solution was obvious and which could be

completed within three to four weeks. The other group of projects would be classified as ‘Track 3’

projects; these would require a detailed and thorough study of each of the DMAIC step as described

above, using several tools to solve the problem at its root cause and implement sustainable solutions for

fixing the problem. These ‘Track 3’ projects would need three months of implementation. Our first

project under study, p1- Optimize Full Pick operations, has been classified as a ‘Track 1’ project whereas

the two other projects under study; p2 and p3 are ‘Track 3’ projects. While the ‘Track 1’ projects would

use a ‘DMAIC Quick Wins One Pager’, which is a single Excel sheet, and a few supporting slides to

document the five different steps, the ‘Track 3’ projects would need to update a complete ‘Storyboard’

with all tools used, data analysis, photos and findings and any other details that were used during the

implementation of the project. These storyboards are in PowerPoint format and around 10 slides per

step per project. A brief of each of the three projects under study has already been given in section 1.2.3

of this paper.

The next section will summarise the 5 DMAIC steps for each of the three projects under study with a

brief description of the tools used. Most importantly, this section reveals the findings and outcomes in

each of these steps. The following section will then analyses the sets of outcome indicators obtained,

before and after the implementation and a comparison of these data sets will be done in order to test

the hypothesis as described in section 1.3.

Page 38: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

38

4.1 Project 1 - Optimize Full Pick operations.

Define: In this first step, we had to define the important aspects of the project in order for everyone to

be clear about the scope of the project. We identified that there was a double handing of full pallets

which were taken from the storage area of the warehouse to the staging lanes and at a later stage,

these same pallets were taken from the staging lanes to be loaded on delivery trucks as they enter the

warehouse to be replenished. This operation was performed daily on all full pallets going out to the

trade. We identified the customer to be the distribution team and we talked to them about their CTQs

(Critical to quality) characteristics. These were: correct loading in terms of quantity per item but also

proper staking of the products in the racks for quick access while delivering, quick turnaround for

second trips loading, loads properly secured on trucks and fresh products available on trucks (proper

stock rotation and expiry date management). We then identified the various stakeholders that were

concerned by this process, first the forklift drivers who move the pallets, the checkers who are

responsible for checking the loads before these are loaded on delivery vehicles and the inventory

controller who prepares all the paper work and looks after the inventory at the warehouse.

Measure: In this step, we wanted to quantify the problem. The full pallets represent, on average

throughout the year, 31% of all pallets going out of the warehouse. Over 90% of these full pallets

consisted of the top four SKU’s (Stock Keeping Units) of the company. On a daily basis, this represents

between 300 and 400 pallets a day. The operation of ‘Full Picks’ which consisted of moving the full

pallets from the storage area to the staging lanes, was performed by two forklift drivers on a full time

basis. This ‘Full Pick’ operation was actually automatically controlled by the Warehouse Management

System (WMS) which sends a task for a pallet to be picked on the RF (Radio Frequency) terminal of the

forklift driver, indicating the pallet to be picked, its address location (Storage area) and destination

address (staging lane). Once the task is completed and validated by the forklift driver, the WMS allocates

another task to him. This task takes from 1.5 to 2 minutes per pallet. The second part of the process is

the loading of the full and the mixed pallets (those with two or more SKU’s) on the delivery vehicle. This

operation is much more rapid (about 30 seconds) as the loading bays are very close to the staging lanes.

The loading operation is done by a separate team of forklift drivers.

We also identified some idle time of forklift drivers during the loading operation, in between the loading

of the pallets, due to these being secured on the trucks by a team of helpers. In order for all the team

Page 39: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

39

members to be clear about the process, a process flow for the actual ‘Full Pick’ and ‘Loading’ operations

was drawn.

Analyze: Our initial thought was to eliminate completely the ‘Full Pick’ operation as described above.

The team of loading forklift drivers would take the full pallets directly for the storage location and load

them on the delivery vehicles as these are inside the warehouse, just- in- time. This would impact on

making the loading process a little bit longer, as the forklift drivers would have to fetch the full pallet in

the storage location, which are further than the staging lanes. Overall there would be an increase the

efficiency of the combined processes. In the analyze step, we had to segregate the first and second

delivery trips loading to fine tune our solution. For the first trip loading which was done at night, on the

eve of delivery, we could afford to delay the loading operation slightly without any significant impact on

the service given to distribution department but on the other hand, as per our client’s CTQ’s, this delay

in loading for the second trips would have an impact on truck turnaround time and would affect them

significantly.

Improve: Before any implementation, a pilot test was performed with a sample of full pallets just for

one day. The result was positive and all employees were convinced that the change could be applied.

The change to Just in Time full picks was thus applied, but to the full pallets of the first trips only. These

represent around 60 to 70 % of total full pallets of the day. The Warehouse Management System (WMS)

system configuration had to be slightly changed to cater for this transition. All full pick tasks for first

trips, instead of going on the forklifts RF guns, had to be confirmed manually in advance and a list of

these given to the fork lift drivers responsible for loading the delivery truck, to enable them to perform

the tasks when the trucks are there. A further synchronization was needed with the inbound

department as while these full pick tasks have been completed on the system, the latter recognizes the

space to be freed and allocate inbound goods in those locations whereas the pallets were still there.

Another change that had to be brought was for the checking of the loads. Previously these were done

on the staging lanes before the loading of the trucks. With the arrival of the full pallet at the last minute

only now, the checker has to check the load which has been loaded on the truck already. This is, in fact,

more convenient as it allows a better utilization of the staging lanes with more loads being staged in the

same lane than previously.

Control: In the control stage, a new detailed process flow was done with details of each process step. All

employees in the Administration Department and fork-lift drivers have been trained in the new way of

working. The change was relatively a smooth one with some minor problems on the first few days,

Page 40: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

40

when for instance a full pallet scheduled for one load went on another. The two forklift drivers who

were previously allocated to the ‘Full Pick’ task have been reallocated to other tasks in the warehouse,

thus significantly helping in improving the other operations, namely the receiving of products which is a

relatively slow operation and had to be improved. The figures below compare the old and the new

processes.

Old Process New Process

4.2 Project 2 - Optimize Picking operations.

Waving

Full Pallets Mixed Pallets (out of scope)

RF Full pick

Staging

Loading on truck

Checking

Is Full pallet for 1st trip?

Manual complete task on system

Figure 3 – Old/New process of Full Pick Operations source: Optimise Full Pick Operation storyboard, PBL, 2009

Page 41: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

41

Define: Similarly to the previous project, the client of the process is the Distribution department and the

suppliers are the production facilities. The first step of the project was thus to go and talk to the client

and identify their CTQ’s (Critical to Quality characteristics) in terms of picking. For recall, we refer to

picking as the preparation of mixed pallets, pallets containing two or more different items. The mixed

pallets represent 69% of all pallets on average, the difference being full pallets as seen previously. The

requirements for the clients were in terms of quality, quantity and timing. They required the right

quantity of each item, properly stacked on the pallets, for each to be available at any one time during

delivery, and these pallets should be ready on time. Most critical in terms of timing was the second trips

loads necessary to attain a proper lorry turnaround time in order to be able to deliver second trips. The

other steps in the define stage consisted of doing a process / sub process analysis, in order to segregate

all sub processes of the picking process. Following was the input / output and a stake holder analysis for

the process.

The Input / output analysis would be helpful in the next stage to identify exactly what would be needed

to be measured. The stakeholder analysis was essential for us to keep a track on everyone who could

eventually be affected by any change in the process, for us to be careful about the implication on that

particular stakeholder. Also this would be helpful for our future communication plan. The biggest

opportunity we identified in this project was to reduce or even eliminate the using of outside staging

lanes as we identified a lot of double handling of mixed pallets in that. The pickers who were completing

the mixed pallets would leave these near the warehouse door (as their equipment cannot transport

these pallets outside), forklift drivers would take them and put in the outside staging lanes. Later, at the

moment of loading, another forklift would take back the pallet from outside to be loaded on the truck

inside the warehouse. This was done because there were not enough staging lanes inside the

warehouse for all loads for the day. Staging products outside was also having an effect on the quality of

the products, these being exposed to direct sunlight. We also identified a lot of idle time within the

pickers teams. Out output indicators for this project would thus be the picking rate (in terms of cases

per hour per man) and a second one would be the percentage of loads staged outside the warehouse.

Measure: In the measure stage, we first did a process flow diagram, see fig 4 below, and identified the

different indicators that would need to be measured. We identified three input indicators which are

respectively; the dispatching delays, the absenteeism of pickers and number of mixed pallets. We refer

to dispatching at PBL as the load planning, where all orders received for the day are grouped together to

form loads that would each go on a delivery truck. The picking process was effectively highly affected by

Page 42: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

42

the delay in that planning, this being the immediate upstream process. This ‘dispatching’ was itself

affected by the delay in order taking. We named these three input indicators X1, X2 and X3 respectively.

We thus started measuring daily all these input and output indicators. This data set would be analysed

in the next step of the DMAIC process.

Process flow: Picking process:

Analyse: This step has for objective to determine the root causes of the problem. This is a critical step

which, if not done properly, can put at risk the entire project, as the focus could be put on the wrong

areas. This step started with a brainstorming of the different causes that was causing the problem. It

Figure 4 – Process flow picking operations source: Optimize Picking Operation storyboard, PBL

Page 43: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

43

was important at this sub step to let everything out and this brainstorming was done at all levels of the

hierarchy, from senior management, down to the floor employee doing the process. After some

elimination in the list, the brainstormed causes, were regrouped into six pre-defined categories, known

as the ‘5M and 1E’, which are Man, Machine, Method, Material, Measurement and Environment. Finally

a Cause and Effect diagram was populated see figure below,

Cause and Effect diagram:

Figure 5 - Cause and effect diagram Picking operations source: Optimize Picking Operation storyboard, PBL

After confirmation with data, the main root causes of the problems were identified to be the lack of

synchronisation between the different parties involved in the process, namely the telesales department,

distribution planning and warehouse administration but mainly that the loads were being processed in

too big batches.

Improve: That stage also started with a brainstorming where all potential solutions to solve the problem

were discussed and latter evaluated in terms of effectiveness, ease to implement and cost of

implementing. The risk involved in implementing these solutions would be evaluated using a FMEA

Page 44: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

44

(Failure Mode and Effect Analysis). The selected solutions were finally to reschedule slightly the working

hours of the pickers team, making them come one hour later than before, in order to reduce the idle

time, re-routing of some clients who were causing big delays in the load planning process and preparing

loads in smaller batches and better synchronisation with the loading of trucks, so that these staging

lanes could be used more effectively. These solutions allowed each staging lane inside the warehouse to

be used several times, reducing the needs to use the outside staging lanes. The first project of

optimising the full picks operations also considerably helped the picking operation in the sense that it

reduced the number of staging lanes needed as some loads with several full pallets could use half of a

lane only for the few mixed pallets to be staged.

Control: The operators and workers were trained and standard operating procedures were written in

order for the implemented solutions to be sustained over time. What was interesting in that project is

that as from the very start, in the diagnostic phase, one particular solution had been identified which

was to break the teams of pickers into two small pickers teams. The first team would work in the

evenings to prepare the first trip loads in the next morning and the other team would come in the

morning in order to prepare the second trips loads. This solution had been evaluated as risky for the

business as the second trips loads might not be ready on time and cause disruption in the warehouse.

This solution would have a lot of implications also on the workers current working hours that would

have to be renegotiated with them. Finally with the selected solutions, the target of significantly

reducing outside staging was achieved at minimum cost and disruption in the warehouse operations and

working hours. This example proved that going through the detailed DMAIC steps and getting down to

the real root causes is indeed very effective.

4.3 Project 3 - Optimise Sorting operations.

Page 45: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

45

Define: Unlike the two previous projects where the supplier of the processes was, in both cases,

production and client was the distribution department, in the sorting process, this relationship is simply

reversed. Sorting is the main reverse logistic operation of the company where all returnable packaging

(half of PBL’s sales volume is in returnable package) are brought back by distribution, sorted at the

warehouse before being sent back to production and serve as ‘raw material’ for future production.

Scarcity and price of glass on the world market makes this reverse logistic an essential and critical

component PBL’s business. All secondary packaging used for returnable products which is essentially

glass bottles inside plastic crates, will be referred as empties in the course of this paper. Empties are

very space consuming and are stocked in the yard of the various different sites of the company.

Production department needs accurate stock of empties available by location in order to plan their

production batches and sizes. Also they need these empties to be correctly sorted which mean that each

case should contain the only one type of bottle it should have. Another requirement is also to have the

cases properly stacked on pallets ready for production. When drawing the process/ sub process map for

the sorting operation, see fig 6, we found useful to include an upstream sub process we called ‘Pre-

sorting’ which is not directly in the process but has a very high influence on it. Pre-sorting is the

preliminary sorting of the empties by the delivery teams of distribution trucks.

Figure 6 - Process / Sub process Map - sorting operations source: Optimize Sorting Operation storyboard, PBL

PBL uses a total of 19 different types of bottles which are classified in four categories; brewery’s 65cl,

brewery’s 33cl, Limo 1lt and Limo 30cl bottles. The output indicator that would allow us to track the

performance of the process would be the ‘sorting rate’ which is calculated by bottles sorted per minute

Page 46: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

46

per employee. A stakeholder analysis was performed, like for the previous projects, in order for us to

check all those that would be concerned with any change in the process.

Measure: We started the measure stage with a detail process map of the sorting operation. This map

allowed us to differentiate between the value added and non-value added activities in the process, and

determine the various measurement points in the process. We thus identified three important input

indicators that would be track over time as these have a significant influence on the sorting operation.

The first input indicator X1 would be the number of trips being performed by distribution for the day. For

the second indicator, it was useful for us to develop what we called a ‘pre-sorting’ index to somehow

quantify the quality of sorting that has been performed by the distribution team before the pallets of

empties are unloaded at the warehouse. For this indicator, we sampled the pallets unloaded and

categorise them into type 1, type or type3 pallet according to how much they are sorted (type 1 has less

than 3 cases unsorted, type 2 has between 3 and 10 cases unsorted and pallets having over 10 unsorted

cases are defined as type 3 pallets. The pre-sorting indicator X2 is then calculated using the formula:

X2= 1 x %type 1 + 0.5 x %type 2 + 0 x %type3.

The higher would be the pre-sorting indicator X2; the better would be the pre-sorting quality.

The third indicator X3 would track the category of employee, casual or full time employee. This would be

very useful as casual employees are paid following a piece rate system, whereas the full time employees

are remunerated on a hourly basis. This difference in remuneration system has a considerable impact of

the employee’s performance, the casual employees being much more productive than the full time

ones.

Page 47: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

47

Sorting process Map:

We also found useful at this stage to do some stratification of data in order to differentiate between the

different types of bottles used by PBL. We did a ‘Pareto analysis’ on the average monthly volume of

bottles used at PBL and obtained the following:

Figure 7 - Sorting process Map source: Optimize Sorting Operation storyboard, PBL

Page 48: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

48

This exercise sheds light on an important aspect of the process. We were actually dealing with all

empties in the same way; all empties pallets were unloaded to the same sorting area. The initial idea

that came to us was that we could have different treatment for different pallets depending on the type

of bottles these contained. At the end of the measure stage, we were settled on all indicators we would

have to track for the projects, these would be also forming our KPI’s in the future for the sorting

process.

Analyse: In the analyse stage, we wanted to start with a brainstorming in order to determine the root

causes of the problem with the sorting operations. Two brainstorming sessions were organized, the first

one with management and supervisors, and the second one with supervisors and the employees

involved directly in the sorting process. We thought that a single brainstorming could not be very fruitful

as the employees would express themselves when they would be face to face with top managers.

Following the brainstorming sessions, we eliminated some of the ideas that we thought would be

outside the scope of the project and group the rest of these ideas into pre-defined categories and that

led us to populate a cause and effect diagram as shown below.

Figure 8 – Volume by bottle types source: Optimize Sorting Operation storyboard, PBL

Page 49: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

49

Figure 9 - Cause and Effect diagram source: Optimize Sorting Operation storyboard, PBL

The red circles in the figure represent what we selected on the main root causes that we would action

on. The next step was to validate these root causes with data where possible. Finally, a 5-why analysis

on these root causes allowed us to go down to the lowest level of the root causes. We completed these

steps with four main areas we decided we would focus on, these are: The remunerations system for the

full time employees, the enforcement of pre-sorting process with the distribution team by enforcing the

check at the gate, the ergonomic aspect of the sorting and the different treatment that would be given

to different types of pallets at the unloading bay.

Improve: This stage started with a solution matrix where again we brainstormed on the different

solutions that could be applied to improve sorting operations in the warehouse. The first root cause we

tackled was the poor pre-sorting and we did that by communicating with the distribution employees and

enforcing the check at the gates to make sure the crates being returned were being sorted correctly. We

used the pre-sorting index developed (as described in measure stage) to track down any improvement

and we effectively experienced a big change on a week over the previous, as demonstrated in the

following chart (fig 10)

Page 50: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

50

Figure 10 - Pre-sorting Index source: Optimize Sorting Operation storyboard, PBL

The second change we did was a creation of a ‘Fast Track’ sorting area for type 1 pallets. These pallets,

instead of being transported to the sorting area and go through the normal sorting process, were to be

brought to a special dedicated area between the unloading bays and the staging lanes and sorted by two

dedicated employees, while still being on the forklifts. These pallets have very few unsorted crates and

these get sorted very quickly and in a flow. This ‘fast track’ would considerably reduce the forklift driving

time, to and from the sorting area. The third solution implemented was one to deal with the ergonomics

of the workers performing the sorting operation. We realised that each sorter was doing three distinct

operations, de-palletising of the palettes of unsorted crates, sorting of the individual crates and re-

palletising the sorted crates. The sorters had to perform a lot of movements, working at different

heights and move several crates manually from one pallet to another. Our solution consisted of creating

a simple ‘Sorting table’ with two old crate conveyors from the production lines where the sorting of

crates would be performed. Instead of each employee doing the three sub operations in sorting, they

would be put in groups of three and perform the operations in a flow, each one performing one of

these. At the start of the conveyor, employee 1 would thus be loading the conveyor with unsorted

crates which would be sorted by employee 2. Once the crates are sorted, employee 3 put these on

pallets.

Page 51: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

51

Figure 11 - The Conveyor Table source: Optimize Sorting Operation storyboard, PBL

A FMEA (Failure Mode and Effect Analysis) was also performed during the improve stage in order to

evaluate the potential risks of failures of the solution being implemented.

Control: we wrapped up the projects by the control stage where we gave necessary training to all

employees and re-wrote all standard operating procedures for the new process. The simplified process

flow that follows show the changes applied in the sorting operations.

Page 52: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

52

Figure 12 - Simplified Process Flow source: Optimize Sorting Operation storyboard, PBL

A more detailed process flow has also been done and serves as the standard operating procedure (SOP)

for the sorting process at the warehouse. During the project, one major event which influenced the

sorting process was the introduction of the new single serve soft drink bottles in the lightweight project.

The lightweight project is a Coca-Cola project where the glass bottles used for packaging soft drinks are

changed to lightweight bottles in order to reduce use of glass and thus the cost in the manufacture of

the bottles. During the course of the project, a new Coke and Sprite 300ml bottle was introduced in

replacement of the old ones (weight of 305grms instead of 380grms) while the Coke light 300ml bottle

was replaced by a 250ml bottle. These changes had a significant impact on the operations as the old

bottles had to be sorted and removed from the circuit to be destroyed or packed for export. The Coke

and Coke Light bottles being the same bottles with just two different prints made the sorting process

much more difficult and time consuming and this affected considerably the outcome indicator. We also

noted big variances in our outcome indicators over days, due to the weather. The sorting of empties

being done in the open air is significantly affected by rain and operations have to be slowed or even

stopped at times.

Page 53: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

53

5. Two sample T test on the Outcome (Y) indicators.

A two sample t test will be used to test if there is a significant difference between the two set of sample

means for each of the y indicator. The standard deviation also being different for these samples, the

‘unspooled test’ will be used, thus using the formula below to calculate the t statistic:

( )

2

2

2

1

2

1

21221

n

s

n

s

differenceedhypothesisxxt nn

+

−−=

−+

Equation 1- two sample T test with unequal variances

As all sample size is 30 for all Y indicators, the degree of freedom that will be used generally will be 58

(30+30-2). A one-sided t-test will be done on each pair of sample at a confidence level of 0.05, therefore

a t-critical value of 1.68 will be used(by looking in the t table at d.f = 58 and α = 0.05). That means that

the null hypothesis will be rejected if we obtain a t value > 1.68

Figure 13 - t distribution curve (shaded area represent the rejection area)

The four outcome (Y) indicators for the three projects are in Appendix xx

5.1 Testing Y1p1 : % of pallet staged in Project 1.

The first Y indicator to be tested is Y1p1, the % of full pallet staged in project 1. For recall, a drop of this

indicator indicates an improvement in performance; therefore we draw the null and alternate

hypothesis as below.

Ho: μ1 = μ2

Page 54: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

54

Ha: μ1 > μ2

μ1 = 95% d1= 14%

μ2 = 57% d2= 10%

t 58 = (95-57) / √(142/30-10

2/30)

t = 21.3

Therefore the null hypothesis can be rejected as t = 21.3 is greater than the critical value of 1.68.

This means that the Y1p1 has significantly improved.

5.2 Testing Y1p2 : Picking rate in Project 2.

For recall, an increase in this indicator indicates an improvement in performance; therefore we draw the

null and alternate hypothesis as below.

Ho: μ1 = μ2

Ha: μ2 > μ1

μ1 = 303 d1= 30

μ2 = 305 d2= 26

t 58 = (305-303) / √(302/30-262/30)

t = 0.73

Therefore the null hypothesis cannot be rejected as t = 0.73 is not greater than the critical value of 1.68.

This means that the Y1p2 has not significantly improved.

5.3 Testing Y2p2 : % loads outside in Project 2.

For recall, a drop of this indicator indicates an improvement in performance; therefore we draw the null

and alternate hypothesis as below.

Page 55: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

55

Ho: μ2 = μ1

Ha: μ2 > μ1

μ1 = 32% d1= 10%

μ2 = 0% d2= 0%

t 58 = (32-0) / √(102/30-0

2/30)

t = 17.58

Therefore the null hypothesis can be rejected as t = 17.58 is greater than the critical value of 1.68.

This means that the Y2p2 has significantly improved.

5.4 Testing Y1p3 : sorting rate in Project 1.

For recall, an increase in this indicator indicates an improvement in performance; therefore we draw the

null and alternate hypothesis as below.

Ho: μ2 = μ1

Ha: μ2 > μ1

μ1 = 82.5 d1= 13.6

μ2 = 65.7 d2= 9.3

As μ1 is greater than μ2, we have to accept the null hypothesis meaning that the Y indicator Y1p3 has

not improved.

Page 56: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

56

6. Survey findings- OE implementation at PBL

The purpose of the survey part of the research is to find out how much the key ingredients to the

success implementation of the OE program were present at PBL. The questionnaire was developed from

a literature review on the key success factors necessary for such operational improvement programs

and a set of variables were taken out to form questions. The questionnaire was sent to all participants of

the program, a total of 37 PBL managers and staff, from which 27 responses were obtained, thus a

positive response rate of 73%. Due to confidentiality and to stay completely anonymous, the answers to

this survey were not linked to any specific project. The questionnaire was divided into 6 sections, each

of the first 5 sections containing a series of questions specific to one of the variables and the last section

dedicated to key learning and general comments about the program.

For the close-ended questions, a score was developed for each question according to the answers. This

score ranges from 1 to 5 and the bigger the value, the more the respondents agree about the respective

statement asked. Finally a score is calculated for each of the first five sections the questionnaire, each

question carrying equal weight in the calculation of this average.

The answers to these closed ended questions and the calculated scores are represented in table 1 below

whereas the answers to the open ended questions are to be found in appendix 5. The results of both

these set of questions are analyzed in the different sections below.

Page 57: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

57

Table 1 - Survey results source OE survey PBL 2009

Page 58: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

58

6.1 Section A: Leadership, Management support and commitment:

This section scored 3.8 over a maximum of 5 points. Each question carries more or less an equal score

but with some minor differences with the access to information and resources pulling down the

average, whereas management support and commitment and leadership pulling it up. The answers from

the open ended question were various and confirmed the results of the close ended questions. While

the respondents in general liked the commitment and presence of management, there are some

complaints about the limited access to information and resources, especially from the finance

department.

6.2 Section B: Communication:

This section scored an average of 4 points, once again very balanced among the various questions with a

preference on the communication among the team members and between the teams and the OE

coordinator. It is to be noted here that PBL employed a full time OE coordinator for the program and

that was a strong signal from management in showing its dedication to the program. Lagging somehow

behind in that section is the communication between the teams and management. Another question

that was asked in that section was to see if the OE program helped in creating a better communication

in the company. 54% strongly agreed and 12% agreed with the statement that the program did

effectively helped in increasing communication in the company, 7% were neutral and 2% disagreed. The

answer to this specific question was not part of the score of the section as it is outside the scope of the

survey but the researcher was interested to get the perception of respondents on this point. The

answers to the open ended question once again confirm the results obtained and the difference in the

score of the closed ended questions. Several respondents requested more communication meeting,

especially between the staff level and management while recognizing in general that the OE program

was a very good opportunity for them to voice out what they always thought that was not working well

in the company, thing they never had the opportunity to do before.

6.3 Section C: Group / Team Problem solving:

This section got the highest score of 4.1 among all other sections. This is not very surprising knowing

that the OE program was a great first formal opportunity for people to work in teams and that generally

this is not very common in the company. The question that really pulled down the average in this

Page 59: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

59

section was about the number of people in the team; only 3 respondents strongly agreed that there

were enough team members in their teams. It is important to point out once more that there was a total

of 19 projects being run simultaneously at PBL and that the teams were relatively limited in terms of

team members due to the unavailability of resources. A very high score of 4.4 for the first question of

this section shows that most respondents enjoyed working in their teams. The answers to the open

ended question revealed that the respondents had an enriching experience working in teams but

requested some better balance of the teams according to the different competencies and backgrounds

of the employees.

6.4 Section D: Worker empowerment and involvement:

A score of 3.8 was obtained in this section with an equal weight for each question except for the one

asking if the employees participated actively in the brainstorming sessions which pulled up the average

with a score of 4. This shows that the OE program was a great opportunity to get all employees

throughout the hierarchy of the company to participate and get together in solving the daily operational

problems faced at PBL. The main comment emerging from the open ended part of this section was

about the fact that the employees were not well aware of the OE program and thus could not

participate effectively in brainstorming sessions. The fact that this practice was new at PBL, more effort

could have been made to sellthe program to employees at all levels of the hierarchy. Probably some fear

about loss of jobs also played an effect in the willingness of employees to participate in the program.

Nothing was clearly communicated on this particularly sensitive subject even if it was informally agreed

that any saving of manpower would be reallocated to other more productive tasks and that the OE

program would not cause any lay-offs in the company. On the other hand, it was clear that any gain in

productivity would affect the amount of working hours needed and consequently the overtime

remuneration of employees which forms an important section of employees package at PBL.

6.5 Section E: Training, Tool and Time:

This section obtained the lowest score (3.5) among all others due to the very low score obtained in the

last two questions, the one about if the participants felt they had enough time for the projects (2.9) and

the one on the period of implementation of the program (3.0). The open part confirmed that the

respondents required more time for the projects.Somecomplained about the complexity of some of the

tools and the limited time they had to digest these and use for their project. For information, the project

Page 60: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

60

ran for a total of three months, each month starting with two day training on one or two of the DMAIC

steps and being followed by a review of the update of the projects’ previous steps. The teams would

then have the rest of the month to work and complete the one or two steps required. While most

appreciated the appropriateness of the tools and training given, some found them bulky and requested

translation in French (all training and tools were in English). Nothing was said about the timing of the

program in the open ended question, I personally felt that this had been perfect for the first phase of

that project as it was during the winter (lowest) season and the operations were relatively not on strain,

even if it made things more difficult to effectively obtain substantiate savings during these low periods

(e.g. reducing overtime in a period where structurally there is no much need for overtime anyway).

6.6 Section F: Key learning points, what went well and what went wrong:

This section contained four open ended questions and the purpose was to capture the key learning

points and also the general appreciation of the OE program participants.

When asked about the key learning points, the learning experience came up in several of the answers,

learning the new tools and problem solving methodologies. Several answers also mentioned the value

creation, reduction of waste and working more productively and efficiently. These results are very

encouraging as these key learning points form the essence of Six Sigma and lean, problem solving

methodology and value creation respectively.

Team spirit was the highlight in the answers of the second question of this section. The mention of

correct team work was in 6 of the 19 answers received for this question. Also was well appreciated the

management commitment and involvement in the project, which was very beneficial for participants,

“Management had time to hear us” says it all. Looking at things differently, challenging the way to do

things were also mentioned in the answers to this question

On the ‘What went wrong’ question, several respondents mentioned time issues like in the section E.

Lack of available resources also came up in that section. Some respondents also mentioned the lack of

communication issues among management and employees and the difficulties of getting through the

entire set of tool effectively, mainly the language barrier issue as discussed previously.

Lastly the respondents were asked for tips that would be useful for the future implementation stages of

the OE program. Following the previous answers from the previous sections, it was not surprising to see

Page 61: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

61

in that one a request for more time for implementing the project. Also other things that were lacking

were in the list of requests for future implementation, such as have better access to financial

information, improve communication challenge and better awareness of the OE program for all the

employees in the organization.

7. Discussion of Results

7.1 Results of quantitative part

Two of the four Y indicators showed a significant improvement in the operations and a third one showed

improvements but these were not significant enough. The forth Y indicator did not show any increase in

the process performance and that could be explained by the different reasons as discussed previously. It

can safely be said that the implementation of the Operations Excellence program has been successful at

the warehouse operations at PBL. These improvements in the processes will definitely with time be

transformed into real resource and cost savings for the company.

Also, the program provided a unique opportunity for employees and management to work together in

cross departmental teams, armed with solid lean principles and a structured Six-Sigma DMAIC problem

solving methodology. As the researcher and an active participant within the projects, I experienced a

real opportunity in challenging ourselves in the way we operate and using the tools provided during the

projects to really identify the root causes of the problems and to apply appropriate and sustainable

solutions to our problems.

I also realised that several of the problems we solved during the projects were not new or newly

identified problems. Most of these problems already existed but we were used to living with them. The

program was a unique opportunity for us to tackle these problems at their roots and apply long term,

sustainable solutions to them.

Page 62: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

62

7.2 Results of Survey

The results of the survey shed light on several benefits and threats of the program at PBL. Employees

and managers appreciated solving problems within teams and recognized the benefits of applying a

structured problem solving methodology to process improvement within their work environment. These

results will serve as a constructive and objective feedback for the future stages of implementation of the

OE program at PBL or at other Coca-Cola bottlers.

7.3 Contribution to the literature

Operations management literature does not contain a lot on process improvement in warehousing

operations and this research paper aimed at contributing to close that gap of the literature. The

research had a big focus on certain specific processes within PBL warehouse operations and

demonstrated how these processes could be improved using lean principles and Six-Sigma problem

solving methodology. The findings of this research are based on hard figures from the quantitative

section of the research rather than just an analysis of the perception of participants through surveys.

This brings value and credibility to the study and could provide certain guidelines for replication on

other warehousing sites. These Y indicators will serve as Key Performance Indicators for their respective

process at PBL warehouse.

7.4 Implication for managers

This paper gives managers some simple but concrete examples of how using lean principles and the

DMAIC methodology can help in bringing significant and sustainable improvement in processes. It

proposes examples showing how these tools are applied in a warehousing context and how these

contribute to achieving real process improvement. Managers at various levels of the hierarchy can draw

from this study some very practical tips that could be helpful for them when starting any process

improvement initiative. The survey part of the research could also be useful and provide some

guidelines to planning when one is to enter into a process improvement initiative. DMAIC could seem

heavy and lengthy but is definitely a very efficient structured problem solving methodology.

Page 63: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

63

8. Conclusion

The central question of the research paper was:

Can the lean and Six Sigma tools and methodology used in the Operational Excellence Program (OE) at

PBL bring a significant improvement in its warehouse operations?

And the hypothesis to be tested was:

The use of lean and Six Sigma tools and methodology can significantly improve PBL’s warehouse

operations.

With the results obtained from the research and the analysis of the Y indicators in chapter 6, we can

with confidence accept the hypothesis that the use of lean and Six Sigma tool and methodology brought

significant improvement in PBL’s warehouse operations. Among the three projects under study, two

showed real improvement achieved, whereas good reasons explain the non-improvement of the third

one.

The survey part of the research was a good opportunity for the participants in the first phase of the OE

program to give their feedback about their experience. The compiled results will be helpful in the future

phases of implementation at PBL or in other companies.

Page 64: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

64

9. Future research

One of the important limitations of that study is that it was not possible it, due to the time limit, to test

for the sustainability of the solutions applied over time. Also, as specified in the research, PBL’s activities

are highly seasonal and the Y indicators have been measured over only four months. There is a scope for

a follow up of these processes and to test the sustainability of the solutions through a future study of

the Y indicators over time and particularly over the peak period of November / December. A follow up of

the sorting project will also be interesting once the ‘Light weighting’ transition stage is over.

The same survey questionnaire could also be applied to the second population of participants, those

involved in the second phase of the OE program which started in October 2009 and is due to end in

February 2010.

Finally, a long run study about the real sustainable changes the OE program brought to the way PBL

operates will be interesting in a few years. It would be interesting to see if the program was for PBL just

another one bringing some short term benefits or, like it claims to be, one bringing “continuous

improvement through a structured and systematic approach, which improves operating margins of a

business by focusing on the elimination of waste and the reduction in variation through standardized

work.” (OE presentation, 2009, slide 2)

Page 65: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

65

10. References:

• Ahlstrom P. and Karlsson, C, 1996, “Change processes towards lean production: the role of the

management accounting system”, international Journal of Operations & Production

Management, Vol 16 No 11, pp. 42-46

• Al-Ghamdi, S.M, 1998, “Obstacles to the successful implementation of strategic decisions: The

British experience”, European Business Review, Vol 98 No 6, pp. 322-327

• Antony Jiju and Banuelas Ricardo, 2002, “Key ingredients for the effective implementation of Six

Sigma program”, Measuring Business Excellence Vol 6 No 4, pp 20-27

• Arnheiter Edward D. and Maleyeff John, 2005, “The integration of lean management and Six

Sigma”, The TQM magazine, Vol 17 No 1, pp. 5 – 18.

• Bhasin Sanjay and Burcher Peter, 2006, “Lean viewed as a Philodophy”, Journal of

Manufacturing Technology Management, Vol 17 No 1 pp. 56-72

• Boyer K. Kenneth, 1996, “An assessment of managerial commitment to lean production”,

International journal of Operations & Production Management, Vol 16 No. 9, pp. 48-59

• Boyer M. and Sovilla L, 2003, “How to identify and remove the barriers for a successful lean

implementation”, Journal of Ship Production, Vol 19 No 2, pp. 116-20

• Bryman Alan and Bell Emma, 2007, Business Research Methods second edition, Oxford

University Press. Oxford.

• Clifford, L., 2001, “Why you can safely ignore Six Sigma”. Fortune No. 143 Vol. 2, pp. 140.

• Coca-Cola Operation Excellence Executive summary presentation, Feb 2009

• Coughlan P. and Coghlan D, 2002, “Action Research for Operations management” International

journal of Operations & Production Management, Vol 22 No. 2pp 220-240

• Dahlgaard Jens J. and Dahlgaard-Park Su Mi, 2006, “Lean Production, Six Sigma quality, TQM and

company culture”, The TQM Magazine Vol.18 No 3, pp. 263-281

• Deming, W.E. ,1986, “Out of the Crisis”, MIT Press, Cambridge, MA.

• Deming, W.E., 1994, “The New Economics for Industry”, Education, Government 2nd ed. MIT

Press, Cambridge, MA.

• Emiliani M.L, 1998, “Lean Behaviors” , Journal Management decision, Vol 36 issue 9 pp 615 –

631

• Emiliani, M.L. ,2001, “Redefining the focus of investment analysts”, The TQM Magazine, Vol. 13

Page 66: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

66

• Evans, J.R., Lindsay, W.M. ,2005, The Management and Control of Quality, 6th ed. South-

Western, Mason, OH.

• Gemmi Fabrizio and Mechi Maria Teresa , 2009, ‘The Ola Project, a reengineering action based

on lean thinking principles for hospital care, within six public hospitals in Florence, Italy’

Presented to the International Forum on Quality and Safety in Health Care, 17-30 March 2007

on Berlin

• Grundy, T, 1998, “Strategy Implementation and Project Management” International Journal of

project Management, Vol .16 No 1, pp. 43-50

• Gunasekaran A., Marri H.B. and Menci F. ,1999, “Improving the effectiveness of warehousing

operations: a case study”, Industrial Management & Data systems 99/8, pp. 328 - 339

• Gunasekaran A., Patel C. and Tirtiroglu E. ,2001, “Performance measures and metrics in a supply

chain environment”, International journal of Operations and Production Management, Vol 21

No. 1 / 2 pp. 71-87

• Hayes, R. H and Pisano, G.P. ,1994, “Beyond world-class: the new manufacturing strategy”,

Harvard Business Review, January / February , pp. 77-86

• Hines Peter and Nick Rich, “The seven Value Steam Mapping tool”, International journal of

Operations and production management, Vol 17, No 1 (1997), pp 46-64.

• Hines Peter, Nick Rich, John Bicheno, David Brunt, David Taylor, Chris Butterworth and James

Sullivan, 1998, “Value Stream Management”, The international journal of logistic Management,

Vol 9, No 1, pp 25 – 42

• Hines, P., Holweg, M and Rich, N., 2004, “Learning to evolve: a review of the contemporary lean

thinking”, International journal of Operations & Production Management, Vol. 24 No 10, pp.

994-1011.

• Ibon Serrano Lasa, Carlos Ochoa Laburu and Rodolfo de Castro Vila, 2008, “An evaluation of the

Value Steam mapping tool” Business process management Journal, Vol 14, No 1, pp 39-52

• Inman, R.R, 1999, “Are you implementing a pull system by putting the cart before the horse?”,

Production and Inventory Management Journal, Vol. 40 No. 2, pp. 67-71.

• Jacobs F. Roberts and Chase B. Richard, 2008, Operations and Management: The core, The Mc

Graw-Hill/ Irwin series

• Kaplan, RS and Norton, PD. ,1992, “The balanced scoreboard-measures that drives

performance”, Harvard Business Review, January-February, pp.71-79

Page 67: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

67

• Karlsson C. and Aslstrom P. ,1996, “Assessing changes towards lean production”, , International

journal of Operations & Production Management, Vol. 16 No 2, pp. 24-41.

• Lawler III, E.E., 1996, From the Ground Up: Six Principles for Building the New Logic Corporation,

Jossey-Bass, San Francisco, CA.

• Lee- Mortimer A. ,2006, “A lean Route to manufacturing survival”, Assembly automation, Vol 26,

No 4 pp. 265-272

• Lee, H.L and Billington, C. ,1992, “Managing supply chain inventory: Pitfalls and opportunities”,

Sloan Management Review, Spring, pp.65-73

• Linderman, K., Schroeder, R.G., Zaheer, S., Liedtke, C., Choo, A.S., 2004, “Integrating quality

management practices with knowledge creation processes, Journal of Operations Management

No 22 vol.6, pp. 589–607.

• Marchwinski, C and Shook, J ,2003, Lean Lexion; A graphical Glossary for lean thinkers, lean

enterprise Institute, Cambridge, MA

• Maskell, B.H. ,1991, Performance Measurement for world class Manufacturing, Productivity

Press, Portland, OR

• McManus, K. ,1999, “Is quality dead?” IIE Solutions No 31 Vol.7, pp. 32–35.

• Minarro-Viseras E, Baines T, Sweeney M ,2005, “Key success factors when implementing

strategic manufacturing initiatives”, International Journal of Operations & production

Management, Vol 25 No 2, 2005 pp. 151-179

• Panniselvram G.P, Fergusson, L.A, Ash R.C and Siferd, S.P ,1999, “Operations management

research, and update for the 1990s” Journal of Operations Management, vol 18, pp. 95-112

• Peter Hines et al ,1998, “Value Stream Management”, the International journal of logistics

management, Vol 9, number 1, pp 25-42

• Pettersen J. ,2009, “Defining Lean production: Some conceptual and practical issues”, The TQM

Journal, Vol. 21 No2, pp. 127-142

• Puis Achanga, Esam Shehab, Rajkumar Roy and Geoff Nelder ,2006, “Critical success factors for

the lean implementation within SMEs”, Journal of Manufacturing Technology Management, Vol

17 No 4, pp. 460-471

• Rother, M and Shook, J. ,1998, Learning to see: Value stream Mapping to add value and

eliminate Muda, lean enterprise Institute, Cambridge, MA

Page 68: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

68

• Sanchez Angel Martinez and Perez Manuelle Perez, 2001, “lean indicators and manufacturing

strategies”, International Journal of Operations & production Management, Vol 21 No 11, pp.

1433-1451

• Scherrer-Rathje Maike, Boyle Todd A and Deflorin Patricia, 2009, “Lean, take two! Reflection

from the second attempt at lean implementation”, Business Horizon Vol 52, Pg 79-88

• Schroeder Roger G., Linderman Kevin, Liedtke Charles, Choo Adrian S., 2008, “Six Sigma:

Definition and underlying theory”, Journal of operations Management No. 26 pp. 536-554

• Shad, R. and Ward, P.T. ,2003, “Lean manufacturing: context, practice bundles, and performance

“ Journal of Operations Management, Vol 21 No. 2, pp. 129-49

• Shahram Taj, 2008, “Lean Manufacturing performance in China: assessment of 65

manufacturing plants”, Journal of manufacturing Technology Management, Vol 19 No.2 pp 217-

234

• Sheridan, J.H. ,2000, “Lean Sigma synergy”, Industry Week, Vol. 249 No. 17, pp. 81-2.

• Slack Nigel, Chambers Stuart, Johnston Robert and Betts Alan, 2006, Operations and process

Management, principles and practice for strategic impact, Pearson Education

• Smith, D., Blakeslee, J., Koonce, R., 2002. Strategic Six Sigma, Wiley, Hoboken, NJ.

• Tom Luyster and Tom Shuker, 2002, “Value Stream Management: Eight Steps to Planning,

Mapping, and Sustaining Lean Improvements”, review in TQM Magazine Vol 16 n 1, 2004 pp 68-

70

• Van der Merwe, A.P. ,2002, “Project management and business development; Integrating

strategy, structure, processes and project”, International Journal of Project Management, Vol

20, pp. 401-411

• Westbrook Roy, 1994, “Action Research: A new Paradigm for research in production and

operations management” International journal of Operations & Production Management, Vol 15

No. 2 pp 6-20

• Worley J.M and Doolen T.L (2006), “The role of communication and management support in a

lean manufacturing implementation”, Management Decision, Vol 44 No. 2, pp.228-245

Page 69: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

69

Appendix 1: Value Stream Maps (Full Products and Empties)

C/T:

1 shift

C/T:

2 shift for trucks

C/T: 18 sec

2 shifts

C/T: 86 sec

1 shift

C/T: 638 sec

Mixed pallets : 69%Full pallets: 31%Picking rate 229 cases / hrD/Time electric transpallets > 80%

1 shift 8hrs

C/T: 170 sec

1 shift

C/T:

1 shift

Warehouse ControlWMS

Value Stream Mapping – Full products

Production Distribution120 trips a day (960 pallets)

1 or 2 trips per lorry( 3 in peak)

ASN generated

Load docs

Weekly forecast W1-4

Full picks orders

Pick ticketsASN completed

Daily request

Load manifest

Daily: Limo: 500 PalletsBrewery: 400 pallets

8%92%

Loading Trailer

3

Driving

Limo: 4 Trailers + 1 truckBrewery: 3 Trailers + 1 truck

Receiving

2

unloading

3-5

Picking

18-20

Loading

3-5

Check out

2-6

2.76 days

I

Production warehouse

18 sec 56 sec 638 sec 170 sec

8.75 days 0.5 days 0.3 days

I I I I I I

Lead time: 12.36 days

Processing time: 1010 sec (17 mins)

23 mins34 mins 10 mins

55 sec58 sec 15 sec

D/T: 14%D/T: 14%

D/T: 14%

Takt time = (27,000 / 960=) 28 sec

Time available (from 7:00 to 14:30)= 27,000 sec

HR: 15 mins break system

Staging lanes

Page 70: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

70

II

Check In Double check In Unloading sorting

3-6 1 4 12-16

C/T: 30 sec C/T: 30 sec C/T: 38 sec C/T: 654 sec

Sorting time for 1 pallet65cl: approx 5 minsChop: approx 12 minsMixed: approx 20 mins

C/T: 37 sec

Warehouse ControlWMS

Value Stream Mapping – Empties

ProductionDistribution

120 trips a day (450 pallets)

Load in ASN Generated

ASN Completed

Weekly / daily empties request

Loading on trailers

2

Lead time: 2.77 days

Processing time:789 seconds

6 mins

30 sec 30 sec

10 mins 14 mins

38 sec 654 sec 37 sec

.75 day 2 days

Total: 450 pallets per day

Total time available: 7:00 to 19:00 (43,200 sec)

Takt time = (43,200 / 450=) 96 sec

I I I I

HR: Piece Rate system - weather conditions

Page 71: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

71

Appendix 2: Action research Journal

Date Place Purpose Participants Outcome Insights gained 29-Jan PBL

boardroom OE introduction meeting by mr. Gerald Glancey ( Technical Operations Manager Coca-Cola East and Central Africa Business Unit

All senior Managers

Commitment for OE implementation at PBL

Introduction to OE

Antis Treebobhun designated project manager

Basic training on OE history and methodology

Project plan, timing, deliverables

PBL to employ OE manager

30-Jan PBL training room

OE introduction to key staff-

Senior Manager + key staff

Basic introduction to OE, tools and methodology

Basic knowledge of OE program by Key staff

30-Jan PBL Pre-Diagnostic data pack

All senior managers

Templates of data to be filled for diagnostic phase remitted to all senior managers.

Data that will be needed for diagnostic phase

List of staff that would for part in OE teams

24-Apr PBL, 3rd floor meeting room

OE general presentation and how schedule of diagnostic phase

All OE team leaders / Members- into 4 different groups

Timing, load of work, deliverables of diagnostic and future OE phases

Basic understanding of what is the OE project.

4th May

PBL training room

OE kick off meeting, start of diagnostic phase.

All team leaders, team members, core team, senior management, CEO

Presentation of program, welcome speech, break in teams, agenda for next two weeks, deliverables, templates etc.

Overview of program and deliverables

PBL training room

8 waste training OE teams Training on the 8 types of waste, examples, tips for identification.

What is defined as waste, where to look for waste

My office 1st team meeting Team 8 Introduction and presentation of team members, agreement on deliverables, planning 2 days ahead

Start of group bonding, agreement on way forward, definition on scope of work, overview of processes in the scope of operations.

On site- LIMO factory

8 waste identification on the site

Team 8 Identified several type of waste in different areas of operation

Waste present in all operations, scope for improvement

5th May

My office Team working sessions

Team 8 Continue site visit for waste identification.

Several areas of waste detected

Brewery site / Commercial unit warehouse

Entering waste observed on data record sheet

Page 72: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

72

6th May

My office Compilation of Waste detection report

Team 8 Record of 69 different observation of waste on the 3 sites we visited during the last 2 days

There is much more waste that we thought there was.

Identification of certain areas where operations could be significantly improved.

Training room

Presentation of waste findings to OE core team

Team 8 / Core team

Presentation of list of waste priorities by score (mixture of impact and resource needed to eliminate) + series of photos to show these waste.

Feedback on work performed, to categories the list of waste into 4/5 broad categories to be tackled together

7th May

PBL training room

Feedback of all group on waste observation

All teams

PBL training room

Value added / non value added analysis, VSM and process mapping training

All teams Introduction to techniques for mapping processes and separate value added to non value added activities in our system

My office Planning and draft VSM layout for our operations (Logistics and reverse logistics)- split of tasks

Team 8 Have our plan of action validated by core team member before proceeding

Can do a single VSM for the entire operation, initially wanted to perform two separate.

Production and warehouse site

Time keeping exercise in order to get data for our VSM

Team 8 Data for the different processes

Lot of variability in process depending on several factors, challenge to work out averages. Not enough data captured due to lack of time, to have more data during the course of the project

My office Start the VSM with data obtained

Team 8 Draft VSM Not so easy to draw VSM, after time keeping exercise, several parts of the map had to be changed.

8th May

Production and warehouse site

Additional time keeping to compile data set.

Team 8 Data for the different processes

Finalize VSM

My office Finalize VSM and analysis with team

Team 8 Final VSM drawing, brainstorming and identification of key problem areas.

Identification of key areas we would focus on namely receiving, picking and sorting

My office In-depth study of processes that will be investigated

Team 8 Draw functional process maps for the key areas of study following value stream map done

Lot of dependent parameters to take into consideration when drawing process map for one process, must consider support functions

Page 73: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

73

My office Presentation of VSM and findings to core team

Team 8 / core team

Validation of key areas of research + agree on other parameters to consider (like glass breakages, damages products on trade etc)

What are the important parameters to consider in our process, effect these can have on other parts of our business

11th May

3rd floor meeting room

Briefing with core team on way forward

All team leaders Inter team communication, each team to meet supplier team(s) and client team(s)- our team to meet production and distribution

Final objective of the OE diagnostic phase

Template for final presentation- key findings and projects

New member in team for end of the week- Francine from Madagascar

Examples of other OE implementation for idea generation

Production site

Meet with ‘ Supplier’

Production team, part team 8

Talk about initiative of inventory reduction and improvement of T/Around time for trailers

Inventory reduction may not be applicable to them running longer batches to improve productivity and yields- T/around welcomed, less driving for them also (fork lift drivers)

Commercial unit

Meet with ‘ Client’ Distribution team, part team 8

Obtain client’s demand from us their suppliers

To Improve lorry turnaround, load preparation, damaged products, avoid errors in loads.

My office Team meeting- briefing, brainstorming on action points to present- plan ahead- review of past OE initiatives

Team 8 Start working on draft presentation- share tasks among members

Initiatives are very much interlinked

12 – 14 May

My office / Site

Finalise list of opportunities and quantify financial impact these can have on operations

Team 8 / OE core team

Presentation, 6 identified opportunities with potential saving of Rs 3.2 m

Clear definition of projects that will be held during first phase of OE implementation

Overview of projects in Warehouse & Transfer operating area

15th May

Sofitel hotel – conference room

Presentation by teams of key opportunities identified that will be dealt with during first phase of OE implementation

All teams / all PBL management / OE core team

Presentation of each team’s findings and opportunities selected to be focused on during OE first phase of implementation

Overview of all the teams identified opportunities and financial impact in terms of cast saving

Our team got special price for ‘Best use of tools’

19Th May

PBL”s Board room

Steering committee selected opportunities for

OE steering committee

List of 21 opportunities from the total list to be implemented in first wave starting 1st June

Priority given to opportunities according to their impact and resources needed.

Page 74: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

74

first wave implementation process

2009

(3 OE projects for the warehouse area)

26th May

PBL’s Warehouse

Introduction meeting with project teams

Project teams for the three identified OE projects for warehouse section

Brief on the different projects, explain to team members the general purpose of OE program

Buy in of team members, very motivated to make things happen. Confident that the projects can be implemented

27th

May PBL board room

OE Steering committee

OE steering committee

Finalized projects that would be implemented and teams

30th May

My office Informal meeting with my brother Jean Marc- Six Sigma green belt and some experience in lean implementation

Jean Marc Rivet + me

Validation of project and some new ideas about framing the project

Lean initiative must have clear customer oriented purpose, else drive towards a corporate global strategy.

Importance of human aspect in the implementation process

1st June

PBL training room

Six Sigma Green Belt training

Team leaders and team champions

Classification of selected projects into track 1 projects (Quick gains) and track 3 projects (DMAIC)

Methodology for problem solving, new tools for the define stage in DMAIC.

Introduction to DMAIC methodology Tool kit for the define stage

Taking a structured approach is the long route but will produce sustainable results

Overview of lean and Six Sigma tools Time table for project implementation.

Detailed training on ‘Define’ phase of DMAIC

2nd June

PBL training room

Six Sigma Green belt training.

Team leaders and team champions

Toolkit for the measure stage.

Methodology and tools to be used.

Detailed training on ‘Measure’ stage of DMAIC

Finalization of OE projects team.

Importance of data, what to measure

Quick wins project format

Quick changeover module and exercise

3rd June

Warehouse Meeting with teams for the two main OE projects

Teams Picking and Sorting

Basic overview of OE program and specific project.

Lot of insight for team members embarking on OE project just now.

Explanation of the different implementation stages (DMAIC)

Detail explanation of Define stage and requirement for next meeting

4th June

My office Meeting with Mark Sinnick (Master black belt) and Barlen to validate projects

Team leader / champion + MS / BA

Validation of warehouse projects, teams and Outcome indicators (Y)

Page 75: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

75

5th June

PBL’s boardroom

OE Steering Committee

OE steering committee / MS

Brief overview of DMAIC methodology, recap of all projects phase one, key responsibilities and deliverables

Clear project timelines and deliverables.

11th June

Warehouse Meeting with OE groups for picking and sorting projects

OE team Finalization of Define stage and agree on measures to be taken for next meeting.

Importance of define stage to go down to the root cause of the problem

Sorting project

18th June

Warehouse Meeting with OE groups for picking and sorting projects

OE team Validation by team of storyboard of projects. Discuss measures taken and agree on pilot test for projects. Communication plan set up for pre-sorting and finalise / validate communiqué for sales attendants

Start seeing a progress even at preliminary stage.

Teams motivated for projects- forecasting on the potential benefits.

My office Meeting with OE coordinator

OE coordinator + Me

Update of project progress and planning for future stage

30th June

Training room

Six Sigma green belt training analyze

Team leader / champion + MS / BA

Analyze stage of DMAIC- training on tools and methods to be used in the Analyze Stage

1st July

Training room

Six Sigma green belt training Improve stage

Team leader / champion + MS / BA

Improve stage Risk analysis, pilot testing

3rd July

Training room

Presentation to Master Black belt on Define and Measure stage for projects

OE team + MS / FH / BA

Define and Measure stage storyboard review

Black belt very happy with storyboards

7th - 10th July

My office Analyze stage with team

OE team Brainstorming - C&effect diagram - identification of root causes

Lot of ideas coming from supervisor / coordinator - to organize a session tomorrow with some sorters and Boodhun who was abs today

14th July

My office review Analyze stage with Sarind

Sarind and Me review presentation and modified where needed

14th July

warehouse yard

organized for repairs of crates conveyors

supervisors / garage mechanics

plan for repair and installation of conveyors in yard to help sorting

14th July

My office Review Analyze stage with team and start with improve

OE team Sorting start 'improve' stage create solution Matrix - lot of small solutions ranked by importance

15th July

My office Improve stage- risk analysis

OE team Sorting FMEA tool Tool over killed for the project. Useful to see the risks that we could be experiencing when implementing solutions but the tool itself is not very

Page 76: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

76

appropriate

16th July

My office Complete improve stage

OE team sorting Action plan the action plan of piloting and implementation will be done simultaneously. We have a pretty good idea how things will work out, in terms of principles and framework but trial and error will be necessary to implement these changes.

24th August

My office Review project- Y indicator, improvement solutions, review of what works and not

OE Sorting team Pre-sorting works more or less okay- see with distribution for reinforcement. Fast track working fine. Train employees for conveyor- sell the system

Decide on strategy to sell in the conveyor system with employees.

25th august

Warehouse yard

Sorting on conveyors

Sorters / supervisor

Talk to employees – see them in action. Explain to employees the ideas behind and principles in using conveyor

Conveyor system can work correctly, some minor modifications on conveyor necessary

28th August

My office Review of project Sarind / Myself Very different solutions than those initially thought of during diagnostic

Ideas have to mature, DMAIC process has been useful to get to the roots of the problems and identified the correct long term sustainable solutions to the problems.

Page 77: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

77

Appendix 3: Online Survey Questionnaire

Operational Excellence (OE) implementation at PBL

Page 1 of 1

Dear Colleague, In the context of my studies, I am conducting a survey on the implementation of the OE program at PBL. The objective of the survey is to determine the factors that contributed to the success or failure of the projects being implemented in the OE program. Your opinion and experience will be of great interest for this survey and ultimately for the improvement of the OE process at PBL. Thank you for taking a few minutes to answer the questions below. All answers and opinions in that survey will be kept strictly confidential. Thank you very much in advance, Hugues Rivet - Supply Chain Manager, Phoenix Beverages Limited

Section A. Leadership, Management support and Commitment

1. During the implementation of the OE project, there was good*

Strongly Agree Agree Neutral Disagree Strongly

Disagree Leadership Management Support and Commitment Availability of resources Access to information

2. Any other comments on leadership, Management Support and Commitment?

Section B. Communication

3. During the implementation of the OE project, there was good communication between*

Strongly

Agree Agree Neutral Disagree Strongly Disagree

OE coordinator and teams

Page 78: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

78

Management and teams OE teams and the workforce Communication among team members

4. The OE programme has increased the communication in the company Strongly Agree Agree Neutral Disagree Strongly Disagree

5. Any other comment on communication?

Section C. Group / Team problem solving

6. What do you think of the following statements?*

Strongly Agree Agree Neutral Disagree Strongly

Disagree I enjoyed working in my team There was enough members in my team There was a good team spirit in my team There was good leadership in my team

7. Any other comment on the work in teams?

Section D. Worker empowerment and involvement

8. How much do you agree with the folowing statements?*

Strongly Agree Agree Neutral Disagree Strongly

Disagree Employees in the process are aware of the OE project Employees were well involved about the OE projects Employees participated in Brainstorming sessions Employees were empowered to implement changes

Page 79: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

79

9. Do you have any other comment on employee involvement and empowerment?

Section E. Training. Tools and Time

10. What do you think of the following statements*

Strongly Agree Agree Neutral Disagree Strongly

Disagree The training given was very satisfactory The tools were appropriate for the OE projects The tools were correctly explained by the team leader / trainer We received good feedback and support from trainer and OE coordinator We had enough time to work on our projects The period of implementation of the projects was appropriate

11. Any other comment on training and tools used in the OE project implementation?

Section F. Key learnings, what went well and what went wrong

12. tell me more about....

Your key learnings in the OE project implementation: What do you think worked well in the OE project implementation: What do you think went wrong in the OE project implementation: How do you think the future implementation of OE projects could be improved:

Page 80: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

80

Appendix 4: Y indicators

Page 81: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

81

Page 82: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

82

Appendix 5: Answers to open ended questions

Section A: Leadership, Management support and Commitment 1 N.B: All answers in this questionnaire are related to the diagnostic phase only. 2 Top management leadership and support weren't visible and tangible. Management level staff who

weren't involved in OE showed no interest probably because there had been no formal presentation to them

3 Very good, done in interest of company but constraints regarding time and involvement 4 management support was total 5 Oe project has been implemented to show that savings can be done in various departments. However

for propoer support and better output, someone must have been made available to guide the team as Mark

6 management suppoirt and commitment must be well attended 7 TIME LIMIT TOO SHORT 8 There was very much involvement/push of management to implementation OE, employees had to be

involved and priority was given to access information 9 There was little access to information, we had issues to contact people from finance to get

information 10 This was the first time that I could see the Management around me and I felt very good

Section B: Communication

1 More regular meetings would have been beneficial 2 In many cases communication has stopped at a certain point, mainly high level. The latter should have

been brought even to the down level too as mainly all processes which we evaluated were their's. 3 More to do on communication 4 The big problem in the company is lack of communication and this problem has never been resolved. 5 Communication within a team was fine but no communication in between teams probably because of

limited time and huge amount of work. Need to rethink well choice of team members and subjects. 6 This was very good and had opportunity to know more about other team members 7 constant communication with OE coordinator has kept all OE team on track regarding their specific

field 8 OE has been a very good tool for communication among employees from different departments. 9 Through OE, we team members of OE witnessed the fact that much things can be done through

communication. 10 Some frustrations could be communicated to management 11 I could voice out things that were not going on smoothly in the company which I wanted to say much

before

Section C: Group / Team problem solving 1 In order for this to be a success, each and everyone in the team should work on the same level sharing

their ideas, feelings, etc... 2 Need to balance teams in terms of number of members, competences and from different backgrounds

- other department views might prove most useful 3 Particulaer attention should be given to profile of team member before forming a team

Page 83: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

83

4 Their was agood listening to each other in the team 5 brilliant experience 6 the purpose of OE is team oriented approach to solutions and better ways of doing things. However

groups working seperately took this challenge and critisise in the wrong way the other members. 7 Everybody in the team got the opportunity to share and discuss at ease 8 perhaps it will be more effective if all team members were in the same dept 9 Traits of team members should be clearly reviewed before team is setup.

10 Unfortunately everyone had to spare time from daily works to be able to involve in team and time to match all team members was difficult

11 I have most of the time worked in team, we should respect opinions of other team members

Section D: Worker empowerment and involvement 1 Owner of the process should be more involved so as to help in the improvement, but also in order to

make his task more easy and more efficient. 2 Worker involvement was very limited - formal awareness sessions prior to projects would be welcome

and certainly tools to be provided to them for execution of changes would be most beneficial for OE

3 No 4 a small explanation session / overview on OE would have triggered better involvement of employees 5 employee very keen in participating in brainstorming sessions 6 make group session for employee after OE project 7 Empowerment of employees to implement projects is a need in today's business, people feel a sense

of belonging to the company and are more cost-oriented when decisions are taken 8 There was lack of communication to other employees not in OE, and so they were not that incolved

and had fears in brainstorming session 9 Employees in general were not aware of this programme, we had to explain before we brainstorm,

employees had fear to tell their opinion at time in the braistorm

Section E: Training, Tools and Time 1 Training not yet performed 2 May be more on Time management 3 Define and measure phases too short 4 Training and tools can be used in our day to day activities - both at work and at home 5 need more training 6 tools very appropriate in implementing the project 7 need more time to perform well in the OE project 8 Some tools are very bulky for the OE project, time has beenn very limited, however the time limit

factor has indirectly push us to complete projects 9 Training was too much in one days- should have been done off site for three days instead of two

consecutive days 10 The training was quite hard for me, this should have also been translated in french

Key learnings

1 It is really valu added when we measure and target improvement based on reliable figures. 2 Fail safe device and Control

Page 84: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

84

3 Quick, organised way of looking at problems and taking corrective action 4 How to make the work more productive and effective with reduced costs. 5 New Tools 6 New methodology of work were shown. 7 DMAIC and benefits 8 DMAIC tools, time management 9 To challenge my ways of doing things

10 concious and focus on waste 11 8 waste survey improved my views towards processes 12 more used of statistical tools 13 savings for the company 14 usefull tools to identify & solve problems 15 The different tools/graphs used. 16 Usage of new tools to identify and eliminate waste 17 I developed a new mindset in doing and leading projects (Define your problem first/know the root

cause/ tackle the root cause) 18 learnt a lot 19 Problems should be solved through models given

Went well

1 The support of the champion and the willingness to improve. 2 Good spirit / team building 3 Team spirit and having clear and well defined measurable targets 4 Good team spirit. 5 Served as eye opener to Senior Mgt Team on a lot of wastage /non conformances that had long been

communicated but not addressed 6 New way of doing sorting (Type 1 & Type 2) Fast-Track project. 7 better comunications and able to deal with sensitive issues 8 The team spirit 9 all team members were involved in the project

10 Quick response from management, new tools bought 11 involvement of team members and sharing views with other team members concerning projects 12 well attended 13 Brainstorming sessions 14 The fact of implementing the project rapidly i. e just after the diagnosis phase 15 define and control 16 Everybody were involved any different level. 17 Motivation/Communication/Pleasure in doing it/It was a pride in doing it 18 management had time to hear us 19 We had time limits to complete projects

Went wrong

1 The time available to balance usual tasks and tasks specific to project areas.

Page 85: The Implementation of Operational Excellence Program at …gsblibrary.uct.ac.za/researchreports/2009/Rivet.pdf ·  · 2010-07-05Acknowledgement ... This paper will evaluate the implementation

Copyright UCT

85

2 Commitment of all team members 3 Low cost investments or investments or finace availability 4 Communication issues. 5 The implementation plan was disrupted by bad weather conditions and lack of sorters. 6 fight with time 7 Had to cope with routine workload & OE 8 lack of information to employees, not concious of big waste 9 lack of follow up and conselling during the project

10 too many details 11 Time period 12 We cannot expect the results now. I think we have to give some "adaptataion time" to be able to get

the real results. 13 measurement 14 There were like a competition between some teams 15 The OE coordinator lacked experience in OE model projects. 16 time restraints 17 I had difficulties to understand english

Suggestions for future

1 Giving more time for the improve step as some needed investment (even minor ) but the administrative and implementation takes time like ordering , and installation.

2 Time management and Finance ( investments)related to improvement 3 By giving more appropriate equipment and good information among the company. 4 Improve communication, choice of subjects and teams but mostly keep track over time +

accountability 5 Advanced training should be provided. 6 To have a better OE facilitator full time on site 7 Training sessions, time lapse for implementation of each phase of DMAIC 8 by providing an overview training to employees - awareness of OE 9 support, counselling& Guidance throughout the project

10 reorganise the teams 11 more time to implement OE 12 To concentrate on one dept at a time 13 New people should get involved 14 OE coordinator to coordinate/set on track/monitor/advise/guide on project

develepment/implementation 15 to be allocated only OE projects during its implementation 16 to have a simpler training version of the oe in french or creole