+ All Categories
Home > Documents > The OPTICON I3

The OPTICON I3

Date post: 30-Jan-2016
Category:
Upload: deron
View: 25 times
Download: 0 times
Share this document with a friend
Description:
The OPTICON I3. 19.2 Million Euro EC grant over 5 years 47 partners, many involving several labs/telescopes under single agency umbrella Networking via ~ 15 working groups. Transnational access to 18 night-time and 4 solar telescopes 6 Joint Research Activities in Technology. - PowerPoint PPT Presentation
50
OPTICON Board Meeting Porto 2008 The OPTICON I3 •19.2 Million Euro EC grant over 5 years •47 partners, many involving several labs/telescopes under single agency umbrella •Networking via ~ 15 working groups. •Transnational access to 18 night- time and 4 solar telescopes •6 Joint Research Activities in Technology
Transcript
Page 1: The OPTICON I3

OPTICON Board Meeting

Porto 2008

The OPTICON I3

•19.2 Million Euro EC grant over 5 years

•47 partners, many involving several labs/telescopes under single agency umbrella

•Networking via ~ 15 working groups.

•Transnational access to 18 night-time and 4 solar telescopes

•6 Joint Research Activities in Technology

Page 2: The OPTICON I3

OPTICON Board Meeting

Porto 2008

ManagementOPTICON Board (18 partners) sets overall strategy and

priorities at annual meeting.

Executive committee (~9 agencies) make detailed financial decisions to implement that strategy ~ 6 monthly.

Cambridge (Gerry + Suzanne) is co-ordinator and finance office.

Project Office (John + Saskia at UKATC) supports board, runs some networks, attends board, manages budgets etc

Access Office (Jesus + Anselmo, at IAC) runs telescope grants,

JRA’s and some networks have internal management

Page 3: The OPTICON I3

OPTICON Board Meeting

Porto 2008

A Bit of HistoryOutline 5yr budgets were set at the beginning of the project (2004).

Regular monitoring of these budgets and progress achieved duringthe course of the activities by JKD/GG reporting to Executive and Board

.

Page 4: The OPTICON I3

OPTICON Board Meeting

Porto 2008

A Bit of HistoryOutline 5yr budgets were set at the beginning of the project (2004).

Regular monitoring of these budgets and progress achieved duringthe course of the activities by JKD/GG reporting to Executive and Board

JRA-3 (HTRA detectors) restructured, new PI, different budget distribution

JRA-2 had budget increase after Venice Exec meeting to cope with new demands

N3.4 (AVO) had programme extended, and its budget increased as circumstances changed, then its was spun off.

N4 (Space Ground Synergy) terminated and budget redeployed at Heidelberg Board meeting when it was clear that it had done as much as possible

Access Programme was oversubscribed, braked hard and then expanded.

Page 5: The OPTICON I3

OPTICON Board Meeting

Porto 2008

A Bit of HistoryOutline 5yr budgets were set at the beginning of the project (2004).

Regular monitoring of these budgets and progress achieved duringthe course of the activities by JKD/GG reporting to Executive and Board

JRA-3 (HTRA detectors) restructured, new PI, different budget distribution

JRA-2 had budget increase after Venice Exec meeting to cope with new demands

N3.4 (AVO) had programme extended, and its budget increased as circumstances changed, then its was spun off.

N4 (Space Ground Synergy) terminated and budget redeployed at Heidelberg Board meeting when it was clear that it had done as much as possible

Access Programme was oversubscribed, braked hard and then expanded.

Project is dynamic and responsive

Page 6: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Financial Controls

Ideally, we want to keep all activities within budget AND keep the distribution between agencies much as expected AND keep the cash flow under control despite long lags in the system. This does not sound simple.

Page 7: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Financial Controls

Ideally, we want to keep all activities within budget AND keep the distribution between agencies much as expected AND keep the cash flow under control despite long lags in the system. This does not sound simple. In fact it is even harder than it sounds!

Page 8: The OPTICON I3

OPTICON Board Meeting

Porto 2008

The Matrix

Agencies report to the EU this way

Page 9: The OPTICON I3

OPTICON Board Meeting

Porto 2008

The Matrix

Agencies report to the EU this way

but activities are managed this way

Page 10: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Financial controlDespite this complexity, by maintaining a detailed overview of every Form C submitted and by deconstructing its contents using the associated JoR form, fairly tight controls have been maintained. Activities going off track have been warned, and corrective action taken.

Page 11: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Financial controlDespite this complexity, by maintaining a detailed overview of every Form C submitted and by deconstructing its contents using the associated JoR form, fairly tight controls have been maintained. Activities going off track have been warned, and corrective action taken.

So, in almost every case, we have indeed stayed within the planned budgets and no major upsets are expected at the end. (Unless there are any ‘Unknown- Unknowns’)

Page 12: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Status Report2007 Annual report accepted by EC.2007/8 Payment received from EC.

•Reporting issues with INSU budget resolved and plan agreed.•Technical issues with TNO over JRA-5 being resolved but TNO payment frozen by EC due to audit issues unconnected with OPTICON.•Proposals made to INAF over reporting anomalies but no resolution yet

2007/8 payments made to all but 2 contractors (INAF & TNO).Access programme fully allocated, final runs happening now.No known problems with JRA or Networks

Page 13: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Finance report. November08FP6 Budget (EU contribution) 19,200,000

Total spend (declared via form C’s) by 31/12/07 = 16,229,696

So, remaining to spend on 1/1/2008 = 2,970,304

Page 14: The OPTICON I3

OPTICON Board Meeting

Porto 2008

2007/08 Payments

Cash just received from EU= 1,901,546(Recall that this payment is a refund of outstanding costs to 31/12/07 +

an 80% advance for 2008 plans, but reduced by the EC retention of 15%. of presently unaudited costs)

Page 15: The OPTICON I3

OPTICON Board Meeting

Porto 2008

2007/08 Payments

Cash just received from EU= 1,901,546(Recall that this payment is a refund of outstanding costs to 31/12/07 +

an 80% advance for 2008 plans, but reduced by the EC retention of 15%. of presently unaudited costs)

Paid out by November 2008 = 1,172,266

Cash in hand at Cambridge now = 786,980

OPTICON budget retained in Brx= 643,083

-----------

Available to distribute at end 2008 1,430,063

Page 16: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Projection to End of FP6Cash at UCAM and EC retention = 1,430,000

Liabilities

2008 User Fees 1,070,000

Remaining JRA spend (last 20% of 2008) 240,000

Remaining N/w spend (last 20% of 2008) 157,000

Audits (estimate) 10,000

Travel grants for access (estimate) 0

----------------

1,477,000

Page 17: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Outcome Projected overspend under these assumptions: 47K, or

0.2% of budget.

This is completely in the noise as regards outturns for most JRA, for the larger network costs, the TNO and INAF issues and for 2008 audit and EU financial control adjustments, so we need to have options for both potential over and underspends at the end.

Page 18: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Final Balancing

Adjustment options (if required)

Do not refund 100% at over allocating telescopes.

Slightly under-refund major partners.

Reduce -ve adjustments at INSU and NOVA (and any others)

Re-evaluate all Form C to check for under/over-reporting

Page 19: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Plan for existing cash balance. Although 2008 access costs are already known with some

precision, last minute changes, audit fees etc make precise payments now impossible. Proposal is to:

Page 20: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Plan for existing cash balance. Although 2008 access costs are already known with some

precision, last minute changes, audit fees etc make precise payments now impossible. Proposal is to:

Make any urgently needed payments needed before end 2008 for cash flow limited contractors..

Page 21: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Plan for existing cash balance. Although 2008 access costs are already known with some

precision, last minute changes, audit fees etc make precise payments now impossible. Proposal is to:

Make any urgently needed payments needed before end 2008 for cash flow limited contractors..

Retain balance at UCAM until early 2009 then pay it out to smaller, and in particular FP6 only, contractors on receipt of audited form C’s to close out the FP6 activity at these contractors in a timely way.

Page 22: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Plan for existing cash balance. Although 2008 access costs are already known with some

precision, last minute changes, audit fees etc make precise payments now impossible. Proposal is to:

Make any urgently needed payments needed before end 2008 for cash flow limited contractors..

Retain balance at UCAM until early 2009 then pay it out to smaller, and in particular FP6 only, contractors on receipt of audited form C’s to close out the FP6 activity at these contractors in a timely way.

Refund remaining partners once FP6 final report accepted and EC release retained cash.

Page 23: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Page 24: The OPTICON I3

OPTICON Board Meeting

Porto 2008

FIN

Page 25: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Access in FP6 and FP7

John Davies

OPTICON Project Scientist.

UK Astronomy Technology Centre (UKATC)

Royal Observatory, Edinburgh

Page 26: The OPTICON I3

OPTICON Board Meeting

Porto 2008

FP6 Summary

Units contracted = 1148. Delivered = 1204

4m 295 284.5

2m 625 668.5

solar 228 251.0

Contract Delivered

Page 27: The OPTICON I3

OPTICON Board Meeting

Porto 2008

FP6 Summary

Units contracted = 1148. Delivered = 1204

Planned spend 4,660,465. Actual spend 4,655,205 (99.887%)

4m 295 284.5

2m 625 668.5

solar 228 251.0

Contract Delivered

Page 28: The OPTICON I3

OPTICON Board Meeting

Porto 2008

The FP7 Access Programme

Page 29: The OPTICON I3

OPTICON Board Meeting

Porto 2008

FP7 Budget• 15ME requested for OPTICON

• Arbitrary cut by EC to 10ME

• Allocation to Access/TDF as follows

User fee budget 2000K, TDF,Office,etc 430K

This is enough for a only a few units at each telescope each year. ~105 nights/days per

year

Page 30: The OPTICON I3

OPTICON Board Meeting

Porto 2008

FP7 Starting Assumptions1. Board decision not to exclude any telescopes now

Page 31: The OPTICON I3

OPTICON Board Meeting

Porto 2008

FP7 Starting Assumptions1. Board decision not to exclude any telescopes now

2. Assume four year contract

Page 32: The OPTICON I3

OPTICON Board Meeting

Porto 2008

FP7 Starting Assumptions1. Board decision not to exclude any telescopes now

2. Assume four year contract

3. Anticipate continuing and improved access budget later in FP7

Page 33: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Conclusions from Schipol TDF

1. We will not accept less than 100% refunds for nights allocated by OPTICON.

2. We will not break the UF/Travel grant link, but will transfer some money (~50K) to the Enhancement network for extra travel support to telescopes..

Page 34: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Conclusions from Schipol TDF

1. We will not accept less than 100% refunds for nights allocated by OPTICON.

2. We will not break the UF/Travel grant link, but will transfer some money (~50K) to the Enhancement network for extra travel support to telescopes..

3 We propose to predefine a split of funds ~14% solar ~86% night-time and allocate them separately

Page 35: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Conclusions from Schipol TDF

1. We will not accept less than 100% refunds for nights allocated by OPTICON.

2. We will not break the UF/Travel grant link, but will transfer some money (~50K) to the Enhancement network for extra travel support to telescopes..

3 We propose to predefine a split of funds ~14% solar ~86% night-time and allocate them separately

Strategic Issue?

Page 36: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Night-time Options Considered

1. As now for 2009. Adopt new plan from 10A based on OPTICON TAC and allowing the money to follow the scientific priorities.

Page 37: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Night-time Options Considered

1. As now for 2009. Adopt new plan from 10A based on OPTICON TAC and allowing the money to follow the scientific priorities.

2. Stop the access programme until after ETSRC review

Page 38: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Night-time Options Considered

1. As now for 2009. Adopt new plan from 10A based on OPTICON TAC and allowing the money to follow the scientific priorities.

2. Stop the access programme until after ETSRC review

3. Allocate as now until ETSRC review then move to new, as yet undefined, scheme on subset of telescopes.

Page 39: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Night-time Options Considered

1. As now for 2009. Adopt new plan from 10A based on OPTICON TAC and allowing the money to follow the scientific priorities.

2. Stop the access programme until after ETSRC review

3. Allocate as now until ETSRC review then move to new, as yet undefined, scheme on subset of telescopes.

4. Spend all the money in 09 +10 on ‘as now’ basis, ask for more money later for ETSRC implementation

Page 40: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Night-time Options Considered

1. As now for 2009. Adopt new plan from 10A based on OPTICON TAC and allowing the money to follow the scientific priorities.

2. Stop the access programme until after ETSRC review

3. Allocate as now until ETSRC review then move to new, as yet undefined, scheme on subset of telescopes.

4. Spend all the money in 09 +10 on ‘as now’ basis, ask for more money later for ETSRC implementation

5. Support travel only until ETSRC implementation

Page 41: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Outcome.

Solar telescopes to be scheduled by EAST who will provide TAG process and travel support

Page 42: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Outcome.

Solar telescopes to be scheduled by EAST who will provide TAG process and travel support

As now (ie own TAC) for night telescopes in 09A+B.

Page 43: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Outcome.

Solar telescopes to be scheduled by EAST who will provide TAG process and travel support

As now (ie own TAC) for night telescopes in 09A+B.

09A+09B total allocations capped at 6nights/3m and 14 nights/2m to restrict cash flow to a no more than a flat spending profile

Page 44: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Outcome. Solar telescopes to be scheduled by EAST who will provide TAG process

and travel support

As now (ie own TAC) for night telescopes in 09A+B.

09A+09B total allocations capped at 6nights/3m and 14 nights/2m to restrict cash flow to a no more than a flat spending profile.

Implement new plan from 10A based on an OPTICON TAC and allow the user fee money to follow the scientific priorities.

New Access office at ING

Details to be worked out in the Spring

Page 45: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Pro: Clearly an advance on FP6.

Prototype for new scheme?

More control over TAC process

Network can evolve based on demand and

availability of nights and cash

Page 46: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Pro: Clearly an advance on FP6.

Prototype for new scheme?

More control over TAC process

Network can evolve based on demand and

availability of nights and cash

Con: Requires effort and cash for new processes

(Eg: TAC, new s/w)

No assured income for each telescope.

May not fit with ETSRC outcomes

Page 47: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Future of TDF.

Will review future structure, chairperson, meeting format, ToR etc at its next meeting. (2009 JENAM)

Will hold open session at JENAM on future plans to exchange info between TDF and engage with community.

Propose to organise one-off meeting of smaller telescope directors (esp from CEE countries) to see if more can be done and if programme meets their needs.

Page 48: The OPTICON I3

OPTICON Board Meeting

Porto 2008

The FP7 Access Programme

Page 49: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Page 50: The OPTICON I3

OPTICON Board Meeting

Porto 2008

Option 1 Details

1. Ask telescopes to place optional number of nights in the pool.

2. Make call indicating max possible nights available at each telescope

3. After deadline send proposals to TAC and telescopes for assessment

4. TAC meeting, produce ranked list, using OPTICON rules

5. Provisionally buy nights from telescopes, releasing clearly unused nights back to national TACs

6. Modify allocations as required in light of scheduling issues


Recommended