+ All Categories
Home > Documents > The Outline of the Water Management and “The ......The Outline of the Water Management and “The...

The Outline of the Water Management and “The ......The Outline of the Water Management and “The...

Date post: 14-Mar-2020
Category:
Upload: others
View: 8 times
Download: 0 times
Share this document with a friend
19
The Outline of the Water Management and “The Subcommittee on Handling of ALPS Treated Water” Agency for Natural Resources and Energy, METI September, 2019
Transcript
  • The Outline of the Water Management and “The Subcommittee on Handling

    of ALPS Treated Water”

    Agency for Natural Resources and Energy, METISeptember, 2019

  • 1. Generation of contaminated water, purification process and tank storage

    Bird’s eye view of tank area

    ◇ Contaminated water in buildings is generated by continuous water injection to fuel debris in reactors To Prevent leakage of the contaminated water from the buildings:

    The level of groundwater outside is controlled to be higher than that of contaminated water inside the buildings.

    Groundwater keeps flowing into the buildings and mixes with contaminated water and the amount of contaminated water in the buildings keeps increasing.* Fuel debris retrieval is necessary to suppress the rate of arising contaminated water

    To Purify the contaminated water: “ALPS treated water” ALPS (Multi-nuclide retrieval equipment) and the other equipment have been used; and Most of the radionuclides except tritium were removed.

    At present, ALPS treated water (≠contaminated water) is being continuously stored on site.

    1

  • Status of ALPS treated water at the site(As of Sep. 18th , 2019)

    Volume of water stored in tanks About 1.16 million m

    Planned tank volume

    About 1.37 million m3(end of 2020)

    Amount of increase of ALPS treated water generated

    About 50,000-80,000m3/year

    Concentration of Tritium in ALPS treated water

    About 1 million Bq/L(About 0.02μg/L)

    Amount of Tritium in tanks

    About 1 quadrillion Bq(About 20g)

    ◇ The rate of arising contaminated water has been reduced by effects of measures such as pumping up of groundwater by sub-drain and construction of frozen-soil wall.

    540m3/day(2014, May) → 170m3/day (average FY2018)◇ The amount of the treated water※ stored exceeds 1.1 million ㎥ and is expected to keep

    increasing, with moderate rate of increase.

    2.Storage of ALPS treated water in tanks

    2Figure. Site map of Fukushima Daiichi

    Unit 1 2 3 4

    Okuma TownFutaba Town

    Waste storage area

    Incinerator

    Research and analysis center(to be constructed)

    ※The treated water means ALPS treated water and Sr treated water.

  • 2. Technical evaluation of disposal methods by the Tritiated Water Task Force

    “The Tritiated Water Task Force (2013-2016)”Technical feasibility (including monitoring to ensure safety), regulatory feasibility period and cost of five handling methods were examined; All cases were examined on the premise that there is no scientific impact on the human habitant. Verification project showed that the separation technology for tritium cannot yet put into use.

    “The Subcommittee on Handling ALPS Treated Water (2016-)”Handling of ALPS treated water has been continuously examined in a comprehensive manner, including from the perspective of countermeasure for reputational damage and of ensuring scientific safety.

    All the measures, throughout their implementation, are subject to the approval of Nuclear Regulatory Authority in accordance with the Reactor Regulation Act.

    3. Examination status of handling of ALPS treated water

    ① 地層注入の例 ② 海洋放出の例 ③ 水蒸気放出の例 ⑤ 地下埋設の例④ 水素放出の例Method of disposal z

    Image

    Technicalfeasibility

    - If proper stratum is not found, commencement of handling will be delayed.

    - There is no monitoring method established

    Examples)- Existing Nuclear facilities’

    liquid radioactive waste discharge to the sea

    Example) TMI-2- water volume: 8,700 m3- Tritium volume: 24 tri. Bq.

    Tritium conc.: 2.8mil. Bq/L- Total period: 2.8 years

    To handle the ALPS treated water, R&D for pre-treatment and scale expansion might be needed.

    examples)- Concrete pit disposal site- Shut-off disposal site

    Regulatory feasibility

    It is necessary to formulate new regulations and standards related to disposal concentration

    Feasible Feasible Feasible New standards might be needed.

    Table Results of assessment of Tritiated water task force

    (1) Example of geosphere injection

    (2) Example of discharge to the sea

    (3) Example of vapor release

    (5) Example of underground burial

    (4) Example of hydrogen release

    3

  • 4. ALPS subcommittee: Status of Review

    ◇ Toward the decision on handling of ALPS treated water, “The Subcommittee on Handling ALPS Treated Water” has started its examination from November 2016 In a comprehensive manner, including the perspective of countermeasures for reputational damage.

    ◇ For the purpose of listening the concerns on handling methods an itself from the public widely, public hearings were held in Fukushima and in Tokyo in August 2018. Issues raised at the public hearing has been examined at the subcommittee.

    ◇ Examination status at the subcommittee will be shared to the international society. Example (METI website) https://www.meti.go.jp/english/earthquake/nuclear/decommissioning/index.html#cwi

    < Issues raised at the public hearing >i) Treatment of radionuclides other than tritium (1 October, 2018) ii) Biological effects of tritium (30 November, 2018) iii) Continuation of storage (9 August and 27 September 2019) iv) Handling method (9 August and 27 September 2019) v) Environmental monitoring (30 November, 2018 and 28 December, 2018)vi) Countermeasures for reputational damage (28 December, 2018 and 27 September, 2019) vii) Consensus building ( 27 September, 2019)

    4

    https://www.meti.go.jp/english/earthquake/nuclear/decommissioning/index.html#cwi

  • 5

    Direct rays from tanks/skyshineDirect rays from sources other than tanks/skyshine

    Other (Groundwater bypass/sub-drains, etc.)

    9.76

    0.900.920.961.44 Am

    ount

    of w

    ater

    in ta

    nks

    Water treated in early years when crossflow filter permeate had trouble etc.

    Water treated in early years of the treatment

    5. Reviews at ALPS subcommittee (i. Treatment of radionuclides other than tritium)

    0

    50,000

    100,000

    150,000

    200,000

    250,000

    300,000

    350,000

    400,000

    ~1 1~5 5~10 10~100 100~

    177,100m3(18%)

    346,500m3(36%)

    207,800m3(22%) 161,700m3

    (17%)65,000m3

    (7%)

    ◇ Two regulatory Standards:1) Applicable to storage: to keep site boundary dose levels less than 1mSv/year Current operational goal of ALPS2) Applicable to release to the environment: to keep radionuclides concentrations of treated water less

    than the regulatory limit.

    ◇ There are various concentration of ALPS treated water in the tanks, because: Concentration of ALPS treated water depends on the attributes of water to be treated and operation

    management of ALPS such as frequency of absorbent exchange; and Especially in early years, before improvement of ALPS performance, concentrations of ALPS treated water is

    relatively higher.

    ◇ In case of releasing ALPS treated water to the environment, the water needs to satisfy standard 2). TEPCO announced to re-purify ALPS treated water, to meet standard 2) for radionuclides other than tritium.

    Subject to re-purification

    5

    Sum of the ratios of actual concentrations to regulatory standards for 62 nuclides* (estimated) * other than tritium

    Site Boundary dose levels

    *These drawings are quoted from “Treated water `portal site(TEPCO HP)”

    Graph1

    End of FY2013End of FY2013End of FY2013

    End of FY2014End of FY2014End of FY2014

    End of FY2015End of FY2015End of FY2015

    End of FY2016End of FY2016End of FY2016

    End of FY2017End of FY2017End of FY2017

    その他(地下水バイパス・サブドレン等)

    タンク以外に起因する直接線・スカイシャイン線

    タンクに起因する直接線・スカイシャイン線

    Site boundary dose levels (assessed value) (mSv/year)

    Site boundary dose levels (assessed values)

    0.03

    0.54

    9.19

    0.325

    0.5574622827

    0.55834994

    0.316

    0.44

    0.208

    0.316

    0.43

    0.17

    0.316

    0.53

    0.052

    グラフ

    平成 ヘイセイH26.3H27.3H28.3H29.3H30.3

    平成25年度 ヘイセイネンド平成26年度 ヘイセイネンド平成27年度 ヘイセイネンド平成28年度 ヘイセイネンド平成29年度 ヘイセイネンド

    西暦 セイレキ2014.32015.32016.32017.32018.3

    西暦 セイレキEnd of FY2013End of FY2014End of FY2015End of FY2016End of FY2017

    タンクに起因する直接線・スカイシャイン線 キインチョクセツセンセン9.190.560.210.170.052

    タンク以外に起因する直接線・スカイシャイン線 イガイキインチョクセツセンセン0.540.560.440.430.53

    その他(地下水バイパス・サブドレン等) タチカスイナド0.030.3250.3160.3160.316

    合計 ゴウケイ9.761.440.960.920.90

    グラフ

    その他(地下水バイパス・サブドレン等)

    タンク以外に起因する直接線・スカイシャイン線

    タンクに起因する直接線・スカイシャイン線

    敷地境界線量「評価値」(mSv/年)

    敷地境界線量「評価値」

  • ◇ Tritium is a relative of hydrogen that emits weak radiation. ◇ Tritium exists naturally and is found in water such as water vapour in the atmosphere, rain, sea

    water, and tap-water.

    5. Reviews at ALPS subcommittee (ii. Biological effects of tritium)

    3H concentration in river water and tap water in Fukushima pref. and 3H concentration in precipitation at Chiba pref.

    (1978-2017)

    Precipitation (Chiba)

    3 H C

    once

    ntra

    tion

    (BqL

    -1)

    Tap water (Fukushima)

    River water, and lake and marsh water (Fukushima)

    Comparison of impact of tritium and well-known radioactive nuclides on living organisms

    Tritium (Water)

    Carbon 14

    Sodium 24

    Phosphorus 32

    Potassium 40

    Cobalt 60

    Iodine 131

    Cesium 137

    10000 times

    1000 times

    100 times

    10 times

    Actual sizeEx

    istin

    g in

    N

    atur

    e

    Exist

    ing

    in

    Nat

    ure

    Non

    -des

    truc

    tive

    insp

    ectio

    n ra

    diat

    ion

    sour

    ce

    –Ca

    ncer

    tr

    eatm

    ent

    Fiss

    ion

    prod

    uct

    Fiss

    ion

    prod

    uct

    Non

    -des

    truc

    tive

    insp

    ectio

    n ra

    diat

    ion

    sour

    ce

    –Ca

    ncer

    tr

    eatm

    ent

    It has not been found that tritium concentrates in human beings and particular living organisms, as tritiated water has similar properties as water.

    Impact on health is very low, around 1/700 of that of Cesium 137.

    The total annual amount of tritium, which is generated at domestic nuclear power plants (NPPs) and released to the sea*, is around 1.7 times as much as that of tritium found in precipitation in Japan. (* 5 year average before 2011)

    NPPs in Japan have been discharging water containing tritium for more than 40 years in compliance with the standard limits based on the laws and regulations. Concentration of tritium in sea water near NPPs are significantly lower than that of drinking water standards in the world. It has not been found that tritium from NPPs have an impact on health.

    *Overseas NPPs also discharge water containing tritium whose concentration is under standard limits.

    Precipitation (Chiba)

    Tap water (Fukushima)

    River, lake and marsh water(Fukushima)

    6

  • 海洋への汚染水の影響に対する政府認識

    Purification of contaminated water/Suppression of contaminated water generation

    5. Reviews at ALPS subcommittee (iii. Continuation of storage)

    Removing fuel from the Spent Fuel Pool

    Fuel debris retrieval

    Disassembly of reactor facility, etc

    Rubble removal

    Ascertaining of the situation inside the PCV/ consideration of fuel debris retrieval etc

    Installation of fuel removal equipment

    Fuel debris retrieval

    Design and construction of equipment

    Fuel removal Storage/Transportation

    Storage/Transportation

    Dismantling and other tasks

    Current progress

    Units 1 and 2 Unit 3 Unit 4

    Units 1-3

    ◇ Fukushima Daiichi Decommissioning is a continuous risk reduction activity to protect the people and the environment from the risks associated with radioactive substances by: Removing spent fuel and fuel debris from the Reactor Building Reducing the risks associated with contaminated water and radioactive waste

    ◇ Safe and steady decommissioning is a prerequisite for reconstruction of Fukushima

    7

    【Fukushima reconstruction and Decommissioning work】 Decommissioning of TEPCO’s Fukushima Daiichi NPS is a continuous risk reduction activities to protect the people

    and the environment from the risks associated with radioactive substances by removing spent fuel and retrieving melted and solidified fuel debris from reactor buildings.

    There has been/will be no conflict between “Fukushima reconstruction” and “decommissioning and treatment of contaminated water”. “Decommissioning” is a prerequisite for “reconstruction”. “Reconstruction” efforts should not be undermined by rush “decommissioning”.

    Given the fact that all handling cases are examined on the premise that there is no scientific impact on the human habitant, handling of treated water in any way needs to be completed by the end of decommissioning.

    ➡ To proceed decommissioning and reconstruction, considering reputational impact is a key issue.➡ Timeline of the handling options will be reviewed at the committee.

    Consideration of scenario and technologies

    Storage of treated water in tanks

    Completion of disposal of treated water /

    Dismantle of tanks

    Contaminated Water

    Management

    3 Basic Principles(1) Isolating (2) Preventing leakage(3) Removing

  • 海洋への汚染水の影響に対する政府認識

    8Figure. Site map of Fukushima Daiichi

    【Facilities considered necessary for decommissioning work】(1) Tanks for storage ALPS treated water

    N

    (2-1) Temporary storage for Spent Fueland Fuel Debris

    – Temporary storage for dry cask:About 21,000m2

    • For spent fuel pool from Unit 1-6:About5,000m2

    • For common pool:Abut 16,000m2

    – Temporary storage for Fuel Debris:MAX About 60,000m2

    (2 – 2) Facilities to be considered in the futureー Facilities for analyzing various samples– Storage facility for fuel debris retrieval equipment– Mock-up facilities for fuel debris retrieval– Training facilities for fuel debris retrieval– R&D facilities related to fuel debris and radioactive waste– Waste recycle facilities– Temporary storage area for waste– Storage facilities for accident

    response equipment etc.About 60,000m2

    About 16,000m2About 5,000m2

    5. Reviews at ALPS subcommittee (iii. Continuation of storage) Tank area occupies much of the southern half of the site. Under current tank construction plan of 1.37 million

    m3 (by the end of 2020) , the time to reach the full capacity is forecasted to be around summer of 2022. Site area which is available for building new tanks is approaching the limit, considering the fact that northern

    half of the site is planned to be used for the solid radioactive waste storage. The whole premise should be effectively utilized, considering limitation of site use as well as the tanks and other

    facilities which will be needed for decommissioning.

  • Start the disposal

    [Wholesale/Retail]Decrease in

    distribution volume /Price decrease

    Suppression of production

    /decrease in willingness to

    produce

    Decrease in willingness for reconstruction

    [Agricultural, Forestry and Fishery Products]

    Import banStrengthen import measure/ boycott

    movement

    Concern for sluggish

    sales

    Concern for decrease in

    trade volume

    <production stage><distribution stage><consumption Stage>【Domestic】

    【Overseas】

    lack of information

    Producers’ concern for

    safety

    information propagation(Mass Media,

    SNS, etc)

    Concernn for agricultural. forestry and

    fishery products around the site

    [tourism industry]Cancellation

    Concern for environment

    around the site

    [citizen]Evacuation /

    Temporary refuge

    → constantly refrained

    → industry deterioration

    → Stop distributionoutlet pricing of brands

    → decrease in attractiveness

    → depopulation

    Decision on Handling method

    [Agricultural, Forestry and Fishery Products]conservative purchase

    5.Reviews at ALPS subcommittee (vi. countermeasures for reputational damage)

    ◇ Various concerns arising from the handling of ALPS treated water may induce reputational damage.◇ Appropriate countermeasures for reputational damage should be examined for each layer, by analyzing

    the occurrence mechanism.◇ It should be noted that influence of tsunami and Fukushima Daiichi accident damage on general

    perception is still remaining.

    9[tourism industry]

    Cancellation

  • <direction of stakeholder engagement (outline)> “decision of basic policy for handling” will be made by GOJ After receiving the report from subcommittee, GOJ will communicate with broad range of people 

    directly involved, such as local community people, and make a decision with transparency. After making the decision, GOJ will keep providing information and communicating interactively 

    for the better understanding, on a long‐term basis. In particular,

    To people directly involved (e.g. local community that might be suffered from reputational damage): hear opinions before the decision‐making and keep providing information

    To people that might have concern with insufficient information: keep providing information inside/outside Japan

    <Ref.> Fourth IAEA Peer Review Mission Final Report (January 2019)“The IAEA Review Team holds that a decision on the disposition path for the stored ALPS treated water containing tritium and other radionuclides,after further treatment as needed, must be taken urgently, engaging all stakeholders, to ensure the sustainability of the decommissioning activities andof the safe and effective implementation of other risk reduction measures.”

    “engaging all stakeholders, to ensure the sustainability of the decommissioning activities and of the safe and effective implementation of other risk reduction measures.”- IAEA Fourth Peer Review Mission Final Report (January, 2019)

    Subcommittee reviewed the direction of engagement with people directly involved (e.g. Local community that might be suffered from reputational damage), and people that might have concern with insufficient information 

    10

    5. Reviews at ALPS subcommittee (vii. Consensus building)

  • 海洋への汚染水の影響に対する政府認識

    Role of the subcommittee:1) to examine in a comprehensive manner, such as countermeasures for reputational damage, and 2) to compile report for the government

    GOJ will decide basic policy, after receiving report of subcommittee and having stakeholder discussion.

    6. Examination Process ahead

    The Subcommitteeon handling of

    ALPS treated waterGovernment

    Report

    Wide range of Stakeholders

    (community people etc.)

    Request for examination Hear opinions of stakeholdersDiscuss from experts’ point of view

    TEPCO

    Decide on engineering

    vi) Approve

    v) Apply

    Measures for handlingNuclear Regulation

    Authority

    1 2

    Decide on basic policy

    Share discussion under subcommittee

    11

  • [Ref. 1] Decommissioning of TEPCO Fukushima Daiichi NPS

    12

    Removing fuel from the Spent Fuel Pool

    Fuel debris retrieval

    Disassembly of reactor facility, etc

    Rubble removal

    Ascertaining of the situation inside the PCV/ consideration of fuel debris retrieval etc

    Consideration of scenario and technologies

    Installation of fuel removal equipment

    Fuel debris retrieval

    Design and construction of equipment

    Fuel removal Storage/Transportation

    Storage/Transportation

    Dismantling and other

    tasks

    Current progress

    Units 1 and 2 Unit 3 Unit 4

    Units 1-3

    Extended to 30-40 years

    ◇ Fukushima Daiichi Decommissioning is a continuous risk reduction activity to protect the people and the environment from the risks associated with radioactive substances by: Removing spent fuel and fuel debris from the Reactor Building Reducing the risks associated with contaminated water and radioactive waste

    ◇ Safe and steady decommissioning is a prerequisite for reconstruction of Fukushima

    Water

    Fuel Debris

    Spent fuel(Spent fuel pool)

    Fuel that remains after its usage for power generation. Continuous cooling is needed to suppress the heat

    Fuel that has melted and solidified by the accident. Continuous cooling is needed to suppress the heat

    Contaminated Water Management

    Radioactive Solid Waste Management

  • 0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    200

    [Ref. 2-1] Impact on the Surrounding Environment

    • The environmental impact on the site and surrounding area have been significantly reduced.

    Guidance value recommended in the WHO Guidelines for Drinking water quality (10Bq/L)

    (Bq/L)

    There has been no effect of the radioactive material (dusts etc.) to the outside in the

    course of decommissioning work.

    Whole map of Fukushima Daiichi Nuclear plant

    Sea

    AirR

    adia

    tion

    dose

    rat

    e (

    mSv

    /yea

    r)

    10,000 over

    13

    Near the south discharge channel

    N

    Evaluation of annual exposure dose at the site boundary due to radioactive materials (cesium) from the reactors buildings of Units 1-4

  • 5. Seawater radiation monitor near Fukushima Daiichi NPS Regulatory Limit Specified by Reactor Regulation・Cesium 137: 90Bq/L・Cesium 134: 60Bq/L

    ③ Near South Discharge Channel

    Bq/l ① North side of units 5 and 6 discharge channel

    ② Real time monitoring

    <TEPCO’s website>

    N

    Unit 1 -4

    Sea-SideImpermeable Wall

    Frozen-soil Wall

    Fukushima Daiichi NPS

    http://www.tepco.co.jp/en/nu/fukushima-np/f1/seawater/index-e.html

    14

    [Ref.2-2] Seawater radiation monitor near Fukushima Daiichi NPS

    http://www.tepco.co.jp/en/nu/fukushima-np/f1/seawater/index-e.html

  • 5. Seawater radiation monitor around Fukushima Daiichi NPS

    Seawater sampling points

    (Source : NRA website)https://radioactivity.nsr.go.jp/en/contents/8000/7742/24/engan.pdf

    FukushimaPrefecture

    FukushimaDaiichi

    NPS

    sampling points

    ~20Km from Fukushima Daiichi NPS

    30~100Km from Fukushima Daiichi NPS

    ① ②

    ③ ④①

    As the Government of Japan received IAEA’s assessment that reads “ongoing monitoring in the surrounding ocean area has detected no significant increase in radiation levels outside the port or in the open sea, and has shown that radiation levels inthese areas remain within the standards of the WHO’s guidelines for drinking water.”, and “the IAEA considers the public is safe”, there has been no leakage of contaminated groundwater at a level which has any impact on the public safety.

    IAEA assessment (December 2013)

    https://www.iaea.org/sites/default/files/recoveryoperations201213.pdf(Source : IAEA website)

    15

    [Ref. 2-3] Seawater radiation monitor near Fukushima Daiichi NPS

    https://radioactivity.nsr.go.jp/en/contents/8000/7742/24/engan.pdfhttps://www.iaea.org/sites/default/files/recoveryoperations201213.pdf

  • Decommissioning and Contaminated Water Managementat TEPCO's Fukushima Daiichi NPS

    Film, Fukushima Today 2018 - Efforts to Decommission and Reconstruction

    https://www.youtube.com/watch?v=TZV2HRKNvao Film, Fukushima Today

    - 8 years after the earthquake -https://www.youtube.com/watch?v=pKjsSAz5Kws

    [Ref. 3] Information Portal site (1) : Fukushima Daiichi NPS

    https://www.meti.go.jp/english/earthquake/nuclear/decommissioning/index.html

    Observation Data, Fukushima Daiichi NPShttps://www7.tepco.co.jp/responsibility/decommissioning/1f_newsroom/data/index-e.html

    Treated Water Portal Sitehttp://www.tepco.co.jp/en/decommission/progress/watertreatment/index-e.html

    16

    https://www.youtube.com/watch?v=TZV2HRKNvaohttps://www.youtube.com/watch?v=pKjsSAz5Kwshttps://www.meti.go.jp/english/earthquake/nuclear/decommissioning/index.htmlhttps://www7.tepco.co.jp/responsibility/decommissioning/1f_newsroom/data/index-e.htmlhttp://www.tepco.co.jp/en/decommission/progress/watertreatment/index-e.html

  • Fukushima Daiichi Status Updates

    [Ref.3] Information Portal site (2) : Fukushima Daiichi NPS

    https://www.iaea.org/newscenter/focus/fukushima/status-update

    IAEA Team Completes Fourth Review of Japan’s Plants to Decommission Fukushima Daiichi (November 13, 2018)https://www.iaea.org/newscenter/pressreleases/iaea-team-completes-fourth-review-of-japans-plans-to-decommission-fukushima-daiichi

    IAEA Issues Final Report on Fourth Review of Fukushima Decommissioning (January 31, 2019)https://www.iaea.org/newscenter/pressreleases/iaea-issues-final-report-on-fourth-review-of-fukushima-decommissioning

    IAEA Review mission reports (Press release )

    UNSCEAR 2016 REPORT Annex C - Biological effects of selected internal emitters-Tritium

    https://www.unscear.org/docs/publications/2016/UNSCEAR_2016_Report-CORR.pdf

    17

    https://www.iaea.org/newscenter/focus/fukushima/status-updatehttps://www.iaea.org/newscenter/pressreleases/iaea-team-completes-fourth-review-of-japans-plans-to-decommission-fukushima-daiichihttps://www.iaea.org/newscenter/pressreleases/iaea-issues-final-report-on-fourth-review-of-fukushima-decommissioninghttps://www.unscear.org/docs/publications/2016/UNSCEAR_2016_Report-CORR.pdf

  • (i) TEPCO: the current status of Fukushima Daiichi Decommissioning(ii) IAEA: “the Peer-review mission” held in Nov.ember 2018 (iii) METI: treated water issue and Fukushima reconstruction(iv) MAFF: Food safety management(v) OECD/NEA: “Symposium on Decommissioning/Reconstruction

    and Food Safety” held in March 2019. https://www.meti.go.jp/english/earthquake/nuclear/decommissioning/index.html#iaea

    Screening the film on “Fukushima Daiichidecommissioning”

    Providing Japanese “Sake” from Fukushima at opening ceremony of Japan’s booth.

    Participants: About 150 people

    Ref.4 Side event at IAEA General Conference (cont’d) [Ref. 4] Side event on Fukushima Daiichi Decommissioning & Food Safety

    at 63rd IAEA General Conference

    * Delegate Statement of Japan is available at https://www.iaea.org/sites/default/files/19/09/gc63-japan.pdf 18

    https://www.meti.go.jp/english/earthquake/nuclear/decommissioning/index.html#iaeahttps://www.iaea.org/sites/default/files/19/09/gc63-japan.pdf

    The Outline of the Water Management and “The Subcommittee on Handling of ALPS Treated Water”スライド番号 2スライド番号 3スライド番号 4スライド番号 5スライド番号 6スライド番号 7スライド番号 8スライド番号 9スライド番号 10スライド番号 11スライド番号 12スライド番号 13スライド番号 14スライド番号 15スライド番号 16[Ref. 3] Information Portal site (1) :  Fukushima Daiichi NPS[Ref.3] Information Portal site (2) :  Fukushima Daiichi NPS[Ref. 4] Side event on Fukushima Daiichi Decommissioning & Food Safety� at 63rd IAEA General Conference


Recommended