+ All Categories
Home > Documents > The Quality and Thoroughness of Construction Documents CMIC Presentation to the North American...

The Quality and Thoroughness of Construction Documents CMIC Presentation to the North American...

Date post: 12-Jan-2016
Category:
Upload: cody-hawkins
View: 216 times
Download: 0 times
Share this document with a friend
10
The Quality and Thoroughness of Construction Documents CMIC Presentation to the North American Construction Federation Conference Sun River Resort- Bend, Oregon United States August 12-14, 2010 B E T T E R P R E P A R E D P R O J E C T S
Transcript
Page 1: The Quality and Thoroughness of Construction Documents CMIC Presentation to the North American Construction Federation Conference Sun River Resort- Bend,

The Quality and Thoroughness of Construction Documents

CMIC Presentation to the North American Construction Federation

Conference

Sun River Resort- Bend, OregonUnited States

August 12-14, 2010

BETTER

PREPARED

PROJECTS

Page 2: The Quality and Thoroughness of Construction Documents CMIC Presentation to the North American Construction Federation Conference Sun River Resort- Bend,

CONTENTS

2

1. Problems Affecting Projects

2. Proposals for Solutions

Better Prepared Projects

Page 3: The Quality and Thoroughness of Construction Documents CMIC Presentation to the North American Construction Federation Conference Sun River Resort- Bend,

3

1. Problems Affecting Projects

The Mexican Law of Public Works and Related Services establishes the following:

“To perform any public work, it is required that the studies and designs, construction specifications, quality-related regulations, and the construction schedule be fully completed”.

Better Prepared Projects

Page 4: The Quality and Thoroughness of Construction Documents CMIC Presentation to the North American Construction Federation Conference Sun River Resort- Bend,

4

1. Problems Affecting Projects

However:

In reality, on many occassions public works bids are tendered without completed Construction Documents that can guarantee the correct execution of the project.

Better Prepared Projects

Page 5: The Quality and Thoroughness of Construction Documents CMIC Presentation to the North American Construction Federation Conference Sun River Resort- Bend,

5

1. Problems Affecting Projects

This situation causes a series of adverse results that affect the time and cost required to complete these projects. Among them:

● Authorization of additional resources to obtain the elements necessary for the completion of the project.

● Changes and modifications in the building process of the projects, with resulting imbalances in the contracts and cost increases.

● Differences and / or controversies bewteeen the parties , that may cause nonconformity and litigation.

● Release of funds falls behind regulatory allotment schedule.

● Start projects in the third quarter of the year.

● Cancellation of resources by the Secretariat of Public Finance and Credit.

Better Prepared Projects

Page 6: The Quality and Thoroughness of Construction Documents CMIC Presentation to the North American Construction Federation Conference Sun River Resort- Bend,

6

1. Problems Affecting Projects

Deficiency:

Currently no mechanism exists to assure that reserves for Construction Documents are set aside to guarantee the correct implementation of public projects.

Better Prepared Projects

Page 7: The Quality and Thoroughness of Construction Documents CMIC Presentation to the North American Construction Federation Conference Sun River Resort- Bend,

7

2. Proposals for Solutions

Given the present situtation CMIC is promoting two proposals for the generation of reserves for Consruction Documents through:

● The 32 State governments (proposal 1)

● The Federal Government (proposal 2)

Better Prepared Projects

Page 8: The Quality and Thoroughness of Construction Documents CMIC Presentation to the North American Construction Federation Conference Sun River Resort- Bend,

8

2. Proposals for Solutions

Proposal I: “National Reserve of Complete Construction Documents for Infrastructure Projects ” with State

Governments

Proposal I: “National Reserve of Complete Construction Documents for Infrastructure Projects ” with State

Governments

State governments

Decentralized Organisms or with state participation

Economic Proposal

The 0.5% is specified in a unit price analyisis

Adjudication of contracts

Construction execution

Progress

Payment

Application

Retention of 0.5%

/direct cost

Public trusts in different regions of the country (center, south, northeast, northwest)

Financing and operation with reserve for infrastructure

Licitaciones de obra pública

Retención de 2 al millar para capacitación

Bids for public works

Include an obligation of retaining 0.5%

1 2 3 4 5 6

7 8 9 10 11

Better Prepared Projects

Page 9: The Quality and Thoroughness of Construction Documents CMIC Presentation to the North American Construction Federation Conference Sun River Resort- Bend,

9

2. Proposals for Solutions

Proposal II: “National Reserve of Complete Construction Documents for Infrastructure Projects” with the Federal

Government

Proposal II: “National Reserve of Complete Construction Documents for Infrastructure Projects” with the Federal

Government

Legislative Branch

Secretariat of Finance and Public Credit

To exercise 5 to 7%

Execution of public works

Assigned budget for investment in federal government entities and institutions.

1 2 3 4

Better Prepared Projects

Page 10: The Quality and Thoroughness of Construction Documents CMIC Presentation to the North American Construction Federation Conference Sun River Resort- Bend,

The Quality and Thoroughness of Construction Documents

CMIC Presentation to the North American Construction Federation

Conference

Sun River Resort- Bend, OregonUnited States

August 12-14, 2010

BETTER

PREPARED

PROJECTS


Recommended