The Republic of Uganda
National Information Technology Project Management Methodology (NITPMM)
August, 2013
Version 0.6
i. National IT Project Management Methodology Version 0.6 Page 2
Document Version Control
Version Date Author Change Description
V 0.1 – 0.4 Jun 2013 Taskforce First Draft
V 0.5 July Taskforce Incorporated comments from consultative
and validation workshop
V 0.6 August Taskforce Included Quality Assurance and Control
function in the governance structure
i. National IT Project Management Methodology Version 0.6 Page 3
Table of Contents
LIST OF ACRONYMS 5
LIST OF TABLES 6
LIST OF FIGURES 7
FOREWORD 8
ACKNOWLEDGEMENT 10
1. INTRODUCTION 12
Readership of the Methodology 12
Rationale of the IT Project Management Methodology 13
Objectives 13
Benefits of the Methodology: 14
Differentiating IT Project from Operational Activities 15
Project Classification 16
2. IT PROJECT MANAGEMENT FIT IN MDAS STRUCTURES 18
IT Project Management Concepts in MDAs 18
IT Project Governance 19
Project Organization and Reporting Structures 20
Project Key Stakeholders, Roles and Responsibilities 22
Project Personnel Competencies and Knowledge Areas Required 23
3. IT PROJECT MANAGEMENT METHODOLOGY 24
IT Project Management Methodology 24
i. National IT Project Management Methodology Version 0.6 Page 4
Project Management Methodology User Interface 25
Programme and Project Management 25
Information System Acquisition 26
Project Lifecycle 28
Project Initiation Process group 29
Project Planning Process Group 31
Project Execution Process Group 32
Monitoring and Controlling Process Group 33
Project Closure Process Group 33
Project Management Tools and Techniques at each Stage 34
Operations and Maintenance (Transition to Support) 35
Project Documentation Management 36
Stage Gates Checklist 39
4. PROJECT INFORMATION SECURITY COMPLIANCE 42
5. PROJECT MANAGEMENT SUPPORT GUIDES 43
6. PROJECT MANAGEMENT SUPPORT TEMPLATES 46
7. PROJECT MANAGEMENT MATURITY MODEL 50
8. CODE OF ETHICS AND PROFESSIONAL CONDUCT 51
9. GENERAL PROJECT SUCCESS FACTORS 54
10. GLOSSARY 56
11. REFERENCES 58
i. National IT Project Management Methodology Version 0.6 Page 5
List of Acronyms Acronyms Description
ISO International Standard organization
IT Information Technology
MDA Ministries, Departments and Agencies
NITA-U National Information Technology Authority in Uganda
PIP Project Implementation Plan
PIT Project Implementation Team
PIR Post Implementation Review
PM Project Manager
PMO Programme Management Office
SC Steering Committee
TMT Top Management Team
TOR Terms of Reference
WBS Work Breakdown Structure
i. National IT Project Management Methodology Version 0.6 Page 6
List of Tables Table Description
1 Differentiating IT Projects from IT Operations
2 Description of Project Life Cycle Process Group
3 Sample Project Management Tools and Techniques used at each Project Stage
4 Initiation Stage Activities and Required Documentation
5 Planning Stage Activities and Required Documentation
6 Execution and Control Stage Activities and Required Documentation
7 Closure Stage Activities and Required Documentation
8 Stage Gate 1: From Initiation to Planning Stage
9 Stage Gate 2: From Planning to Execution Stage
10 Stage Gate 3: Execution to Closure Stage
11 Stage Gate 4: Closure Stage Support Stage
12 List and Description of Project Support Guide
13 List and Description of Project Templates
14 Description of Project Management Model
i. National IT Project Management Methodology Version 0.6 Page 7
List of Figures Figure Description
1 Overview of IT Project Management Concepts in MDAs Environment
2 IT Project Governance Structure for Projects in a single MDA
3 IT Project Governance Structure for Projects involving Multiple MDA
4 IT Project Management Methodology
5 Project Management Maturity Model
i. National IT Project Management Methodology Version 0.6 Page 8
Foreword The Government of Uganda has invested a lot in a number of IT related projects, however many of these
projects have not been delivered as expected. Many fail at inception stage, others are not delivered on time
and those which get delivered don’t meet expected objectives. Furthermore, the successful delivery of IT
projects in Government is critical in supporting strategic Government plans and service delivery to citizens.
In order to mitigate these challenges and meet the mandate to provide advice on IT Project Management
services to Government, National Information Technology Authority in Uganda (NITA-U) has developed this
National IT Project Management Methodology to provide guidance on how to manage IT projects from the
start to completion.
This methodology provides a structured approach to manage IT projects and programmes within
Government. It provides essential components of planning and management of IT projects and highlights
good practices that should be applied throughout the IT project lifecycle.
While these guidelines are relevant to all IT projects and or programmes regardless of their size and
complexity, they will require a high level of judgment from the users. The guidelines provide a starting point
to establish the project context, gain formal agreement to proceed and for considering the project
management methodology that is relevant to IT projects. It is built on the collective knowledge and
experience of IT project management professionals working within Government; and is intended to provide
guidance they could have provided on a consultancy basis. Project management support guides and
templates are also developed to further provide detailed guidance to users and ensure standardization. The
methodology also reflects on lessons learned from major Government IT projects implemented in the past.
These key learnings included the management of small and large projects and or programs and a move
towards adopting Project / Program Management practices within MDAs.
A taskforce, which included experienced project management professionals and practitioners in
government and private sectors, provided input during the development of this methodology. Join me to
thank the team for coming up with this first version.
i. National IT Project Management Methodology Version 0.6 Page 9
NITA-U will periodically establish a Review Group that will review this National IT Project Management
Methodology (NITPMM) to reflect changes in IT project maturity levels at MDAs, policies and procedures, as
well as rules and regulations from the Government of Uganda.
The review process will involve all stakeholders through a participative process. Hence, the NITPMM is a
living document that can accommodate changes in conditions.
I am pleased to introduce the National IT Project Management Methodology Version 1, 2013 which is one of
the most vital tools for MDAs who wish to successfully deliver their IT projects and or programmes. Please
take time to look through this methodology, use it as your quick reference guide and as a supplement to the
training you will receive.
Many thanks,
James Saaka
Executive Director, National Information Technology Uganda
i. National IT Project Management Methodology Version 0.6 Page 10
Acknowledgement The following people provided professional expertise and time during the development of this methodology. If it was not for their dedication this version could not have been available at this time. They deserve to be acknowledged for their contributions.
No. Name Designation Institution Role & Responsibility Towards Methodology Development
1 James Saaka Executive Director NITA-U Project Sponsor 2 Dr. Fredrick E. Kitoogo Director Planning,
Research & Development
NITA-U Project Owner
3 Abdul Nsubuga, PMP. Programme Manager NITA-U Project Manager / Content Developer
4 Peter Kahiigi, CISM, CISSP Director Information Security
NITA-U Project Quality Assurance
5 Gerald Kisongoch, PMP, RMP. Programme Officer NITA-U Content Developer
6 Rachel Nyatworo Programme Officer NITA-U Content Developer
The following project management professionals were assembled and formed a taskforce which peer reviewed the methodology to the current quality. We thank them for their expertise and time. No. Name Designation Institution 1 Samuel Baguma, PMP. Ass. Commissioner , MIS MOFPED 2 Ambrose Ruyooka, PMP. Ag Commissioner MOICT 3 Allan Kiwumulo Ag Manager MIS UNRA 4 Opio Nockline Manager IT Infrastructure URA 5 Petra Najjuka, PMP. Project Management Consultant LAP Marketing Consultants 6 Musa Musazi, PMP. Project Manager Warid Telecom During e-Government survey a number of MDAs indicated that they had a project management methodology they were following in delivering their IT projects. With that information, a targeted consultative workshop was organized for the following institutions; and their experts provided input to the process. We acknowledge their contributions and expertise they shared during the development of this methodology. No. Name Designation Institution
1 Monica Nyakaisiki Manager IT PPDA
2 Collin Babirukamu Head of IT / CIO NSSF
3 Patrick Ndahura Auditor OAG
i. National IT Project Management Methodology Version 0.6 Page 11
4 Eric Kagoda Principal Officer, Data and Information Analysis
UNBS
5 Charlotte Tinaruhanga IT Officer State House
6 Jackie Namyalo System Admin NPA
7 David Kikabi ICT Manager Judicature
8 Herbert Wamboko Head, IT Electoral Commission
9 Martin Ssekajja Manager IT KCCA
10 Julian Rweju Business Analyst NITA-U
11 Philip Walera Manager, Architecture, Standards and Certification
NITA-U
Finally, validation workshop was organized and many senior IT personnel from MDAs participated and provided input. We acknowledge all their contributions and time towards the finalization of this version.
i. National IT Project Management Methodology Version 0.6 Page 12
1. Introduction National Information Technology Authority - Uganda (NITA-U) was established by the Act of Parliament
(National Information Technology Authority, Uganda Act of 2009) and was operationalized in 2010. The
authority is charged with an overall mandate to coordinate, promote and monitor the development of
Information Technology (IT) in the context of social and economic development of Uganda. Among the
main functions of the authority is to provide advice on IT Project Management services to Government.
In order to operationalize this function, NITA-U set up a Programme Management Office (PMO)
department with the following objectives among others:
a. To develop a Project Management Methodology and Guidelines that would be used for IT Projects
in Government Ministries, Departments and Agencies (MDAs)
b. To set up governance models that would support the methodology
c. To provide IT Project Management support to MDAs
It is with this background that this IT Project Management Methodology has been developed. Project
management support user guides and templates are also available to provide detailed guidelines to IT
project stakeholders involved in IT project work in government.
Readership of the Methodology
1.1.1. This methodology provides guidance on concepts, processes, tools, governance and good
practices in IT project management that are important for, and have impact on, the
performance of IT projects in government.
1.1.2. The target readership for this methodology will include among others the following key
stakeholders:
a. Accounting Officers in Ministries, Departments and Agencies (MDAs)
b. Top Management Teams (TMT) at MDAs and project sponsors, in order to provide them with
a better understanding of the principles and practice of IT Project Management and to help
i. National IT Project Management Methodology Version 0.6 Page 13
them give appropriate support and guidance to their project managers, project management
teams and project teams;
c. Programme Managers, Project Managers, Project Management Teams and Project
Implementation Teams, so that they have a common basis upon which to carry out IT project
work successfully.
d. Key stakeholders such as IT Development Partners, Suppliers, Contractors or Consultants
for use as a reference framework when involved in IT projects work within government
Rationale of the IT Project Management Methodology
1.1.3. IT project management in government have traditionally relied upon the individual strengths
of project managers (in many cases contract managers) to plan and execute a variety of
simultaneous IT projects. Project management expertise currently varies by team, with each
relying upon its own unique project management approaches and tools. While this has served
government relatively well in the past, we have reached a critical point where the number of IT
projects in government, coupled with the necessity to share resources across multiple projects,
has created the need for a more formal and structured approach to managing IT projects and
ensure that they are delivered on time, within budget and desired quality.
1.1.4. Out of the total National Budget, 25% of the funds are allocated to projects and programmes;
and some are IT related projects. However, there is no defined methodology to guide in the
implementation of such investments.
Based on the above background, this methodology is developed to provide guidance on
processes, procedure, best practices and standards in planning and managing IT projects to
achieve the intended national benefits.
Objectives
The methodology should assist all stakeholders who are involved in IT projects and or programmes in
government to successfully and repeatedly manage their IT projects end-to-end within a structured
and systematic approach.
i. National IT Project Management Methodology Version 0.6 Page 14
The objectives of this methodology include the following among others:
a. Improve IT projects delivery success rate
b. Establish a secure structured Process - Provide a common, structured approach for initiating,
planning, executing, controlling and closing projects
c. Promote Consistency - Produce project management documents that are consistent across all IT
projects, thereby simplifying their management
d. Improve Resource Management – Outline the resources required for an IT project thereby
enabling MDA to better manage resources
e. Streamline and simplify IT project quality management and control practices
f. Make sure all IT projects follow regulatory, legislative and government compliance processes
g. Ensure proper planning with focus on key aspects like quality, risk management and change
management.
It is important to note that this methodology will work within the existing national legal, regulatory and
policy framework.
Benefits of the Methodology:
1.1.5. Using this methodology will bring several benefits and in turn offer a consistent, systematic
and repeatable approach that will:
i. Improve IT projects delivery success rates; and facilitate MDAs to realize
expected benefits; and minimize dependency to specific staff
ii. Align IT projects and programmes to ensure delivery within the expected
timelines, approved budgets and required quality
iii. Enhance interaction within stakeholders and help in aligning of stakeholders
roles and responsibilities
iv. Enable stakeholders use the same language while managing project work, thus
providing project and or programme managers and decision-makers with better
information for reporting, planning and decision marking
i. National IT Project Management Methodology Version 0.6 Page 15
v. Provide project and or programme managers, project management teams,
decision makers with better information for reporting and planning
vi. Enhance economy and value for money in utilization of public resources in
critical IT projects
vii. Enhance accountability and transparency in IT project delivery, and
viii. Promote learning and continuous improvement in project documentation,
which will act as lessons for future projects
1.1.6. This methodology can be used for all types of initiatives and can be easily scaled according to
the size or complexity of the initiative. Before employing the IT Project Management
Methodology, however, users must assess whether the initiative under consideration is an IT
project or simply an operational activity.
Differentiating IT Project from Operational Activities
1.1.7. Most IT work in MDAs is defined as either a project or an operation. However, determining
this can be a challenge given that many routine, operational IT activities share characteristics
with projects but are not technically IT projects.
1.1.8. The first question a user of this methodology needs to ask and answer is, “Does this work or
initiative qualify as an IT project?” At the heart of the question is whether the initiative is
unique and temporary. In general, unique initiatives are not repeated and thus not routine or
operational in nature. If the initiative is not unique, then it is not an IT Project and the IT Project
Management Methodology does not govern the initiative–even though applying project
management technique may improve the respective process or deliverable. The project
initiation support guide provides details.
1.1.9. The table below compares four example activities that can be used to differentiate IT projects
from routine operational activities.
i. National IT Project Management Methodology Version 0.6 Page 16
Table 1: Differentiating IT Projects from Operations Activities
IT Project Routine Operational Activity
Installing a new application or a full version upgrade Installing maintenance patches or releases
Installing a new IT infrastructure construction project Installing or maintaining of an IT infrastructure
Design and deploy a phase of the National Backbone
Infrastructure
Replacing a network equipment at the end of
product life
Activities are performed by temporary teams Activities are performed by a stable team
Project Classification
1.1.10. Project classification is an important aspect when initiating a project. Project classification
will determine whether the initiative will result into a small, medium or large project; and
appropriate documentation and activities of the project can be determined early to ensure
successful completion of a project with sufficient efforts.
1.1.11. Because of its importance, classification should occur while developing a business case or
during a feasibility study. The following are some of the attributes that can be used to classify a
project as small, medium or large:
a. Complexity of the project
b. Duration of a project
c. Budget at Completion
d. Project risk profile
e. Strategic importance
f. Political importance
g. Dependencies and Interrelated projects (Inter-ministerial)
h. Level of change management required
i. Reporting requirements
j. Programme (collection of related projects)
i. National IT Project Management Methodology Version 0.6 Page 17
1.1.12. A Project Initiation Support Guide provides a detailed classification model and an intelligent
tool, which project initiators should use during the classification efforts.
i. National IT Project Management Methodology Version 0.6 Page 18
2. IT Project Management Fit in MDAs Structures
IT Project Management Concepts in MDAs
2.1.1. Before developing this methodology, a survey was conducted in MDAs and selected private
companies. A detailed review of IT project management methodologies from other countries
was also undertaken. Throughout the development, the care was taken in mind the scope of
the methodology and existing legal, regulatory and policy framework of Uganda.
2.1.2. Project management requires significant coordination and, as such, requires each process
used to be appropriately aligned and connected with other processes within the governance
structures of the MDA.
2.1.3. Figure 1 below shows how IT project management concepts relate with existing MDA
governance structures. The strategy adopted by the MDAs will be the basis for identifying IT
project opportunities. The opportunities will be evaluated and documented into a concept note
and should be approved by the Top Management Team of the respective MDA.
2.1.4. Selected opportunities should further be developed into a business case or a feasibility study
performed, and could result in one or more IT projects that should provide deliverables in order
to realize the intended benefits. The benefits should be an input to realizing and further
developing the MDAs’ strategy.
i. National IT Project Management Methodology Version 0.6 Page 19
Figure 1- Overview of IT Project Management Concepts in MDAs Environment
Source: ISO 21500: 2012(E)
IT Project Governance
2.1.5. In conformance with section 8 of the Public Finance and Accountability Act 2003, the
Accounting Officer shall control and be personally accountable for the success of all IT projects
in his/her domain. He / she will ensure that adequate controls are exercised over the incurring
of commitments; that effective systems of internal controls and internal audits are in place in
respect of all transactions and resources assigned to the project.
2.1.6. The successful management of IT Projects is dependent on significant coordination through
clear defined leadership, accountability and organisational structures which ensure all
processes and procedures are appropriately aligned and interconnected.
i. National IT Project Management Methodology Version 0.6 Page 20
2.1.7. IT Projects governance should spell out clear leadership, organizational and reporting
structures; and processes that ensure that projects sustain and meet the intende objectives.
2.1.8. Roles and responsibilities must be clearly defined to avoid administrative issues. Project
governance is one of the critical success factors of project success, so it should be emphasized.
Separation of project governance and organizational/functional governance structures should
be considered for the success of the project.
2.1.9. The Project Governance and Reporting Structure Support Guide provides guidance on how
projects should be directed and controlled and includes subjects such as the following in
relation to IT projects:
a) Defining the management structure;
b) Stakeholder responsibilities and accountabilities;
c) Reporting hierarchy and escalation of issues or risks; and
d) Limits of authority for decision-making;
Project Organization and Reporting Structures
2.1.10. All IT Projects should have a defined project organization structure to ensure that all needed
commitments, reporting, roles and responsibilities are well defined to avoid administrative
challenges within a MDA. The organization structure below will be put in place for an IT Project
run in a single MDA.
i. National IT Project Management Methodology Version 0.6 Page 21
Figure 2: IT Project Governance Structure for a Project in a Single MDA
2.1.11. The organization structure below should be put in place for an IT Project cross cutting
multiple MDA. A lot of care should be taken when identifying key MDAs for cross cutting IT
projects; and chiefdoms should be avoided in such projects.
i. National IT Project Management Methodology Version 0.6 Page 22
Figure 3: IT Project Governance Structure for a Project Involving Multiple MDA
Project Key Stakeholders, Roles and Responsibilities
2.1.12. A successful project and or programme dependents on proper and full identification of
stakeholders (internal and external; direct and indirect) coupled with an effective stakeholders’
management and communication strategy. Stakeholders’ roles and responsibilities, influence /
power and interest should be clearly defined and managed. Stakeholder interfaces should be
managed within the project through the project life cycle.
2.1.13. It should be clearly understood that the project organization is a temporary structure that
includes project roles, responsibilities and levels of authority and boundaries that need to be
defined and communicated to all stakeholders of the project. The project organization may be
i. National IT Project Management Methodology Version 0.6 Page 23
dependent on multi-sectoral mandates, interdepartmental or any other legal methodology
existing in government.
2.1.14. The IT Project Governance and Reporting Support Guide provide details for the two
structures.
Project Personnel Competencies and Knowledge Areas Required
2.1.15. IT Project management personnel should develop competencies in project management
principles, processes and proficiency in usage of tools in order to achieve project objectives and
goals. Each project team requires competent individuals who are capable of applying their
knowledge and experience to provide the project deliverables. Any identified gaps between the
available and required competence levels represented on the project team could introduce risk
and should be addressed.
2.1.16. The following knowledge areas should be developed for project personnel in order to
manage IT projects successfully among others:
a. System Development life cycle and models
b. Project Integration Management
c. Project Scope Management
d. Project Time Management
e. Project Cost Management
f. Project Quality Management
g. Project Human Resources Management
h. Project Communications Management
i. Project Risk and Issue Management
j. Project Procurement Management
k. Project Information Security Management
l. Project Stakeholders Management
i. National IT Project Management Methodology Version 0.6 Page 24
2.1.17. Each of these knowledge areas has a Support Guide, which is providing detailed processes,
tools and techniques, good practices and examples. Please refer to these support guides for
detailed guidance. Furthermore, templates in the project management toolkit have been made
available to provide more information on these knowledge areas and expedite the
development of required project documentation.
2.1.18. However, understanding and applying the knowledge, skills, tools and techniques and good
practice are not sufficient alone for effective project management in general. Effective IT
project management requires that the project team understands and use knowledge and skills
from the following areas of expertise among others:
a. Communication skills
b. Application area knowledge, standards, and regulations
c. Understanding project Environment; including international and political environments
d. Interpersonal skills
e. Management and leadership Skills
f. Conflict / crisis management skills
g. Negotiation skills
2.1.19. Competency levels may be raised through professional development processes such as training, conferences, coaching and mentoring inside or outside an organization.
3. IT Project Management Methodology
IT Project Management Methodology
3.1.1. This methodology applies across the whole project lifecycle and should ideally be used for
any type of IT project, which may include among others: IT infrastructure and Information
System Development projects. Specifically, however, there are a number of key decisions to
make at the Project initiation stage, which will influence how the project will be managed
across all the subsequent stages of the lifecycle.
i. National IT Project Management Methodology Version 0.6 Page 25
3.1.2. The project methodology in figure 3 illustrates the project life cycle, activities performed at
each stage, high level deliverables (inputs or outputs) expected depending on the project type,
controls and stage gates.
The output of one stage will be the input of the subsequent stage. Stage gates will be critically
evaluated before a project progresses from one stage into another; and sign off should always
be sought.
Project Management Methodology User Interface
3.1.3. All IT projects should follow a logical sequence of stages as illustrated in figure 4, with an
initiation as a start and closure as an end of the process; before transiting the project final
deliverables into operations and maintenance stage.
3.1.4. In order to manage IT projects efficiently during the entire project life cycle, a set of activities
should be performed at each stage with deliverables continuously monitored and controlled.
The number and type of activities that a project team completes during each stage will be
determined by the way a project will be defined and classified. Large projects will call for more
rigor than small project.
3.1.5. The methodology is structured into: Programme and project management, System
Development and project life cycle with expected activities at each stage, deliverables and
controls.
3.1.6. Stage gates or decision points are included to indicate where critical GO/ NO Go decisions are
expected. By the end of the last project stage, the project should have provided all expected
deliverables. Timely decisions are expected at each stage gate to minimize project delays.
Programme and Project Management
In circumstance where multiple projects are derived from a business case or a feasibility
study, the aspect of programme management will be emphasized in order to manage related
i. National IT Project Management Methodology Version 0.6 Page 26
projects in a centrally and coordinated manner to achieve more benefits one could not get if
projects are managed discretely. The Programme Management Support Guide provides
details.
Information System Acquisition
3.1.7. For projects whose scope involves acquisition of a computerized information system, the
project planning team should agree on an appropriate System Development Life Cycle (SDLC)
model, identify and document all activities / tasks to be undertaken during project execution in
the project management plan (or inception report). A systems development support guide
provides further guidance, especially during project planning, execution and control.
3.1.8. Regardless of a selected SDLC model, during the project execution of the project
management plan, a Systems Analyst should collect business user requirements and analyse
them before a decision is made whether to develop the information system in-house or
procure off-the-shelve.
i. National IT Project Management Methodology Version 0.6 Page 27
Figure 4: IT Project Management Methodology User Interface
Stage Gates
Project Initiation / Setup Project Planning Project Execution Project Closure Operations &
MaintenancProgramme Management
Project Management
System Acquisition
Activities
Deliverables / Out puts
Controls
Initiating Planning
Executing & Controlling
Requirements Solicitation
Analysis & Design Developing Testing
Training, Deployment &
Stability
Close OutTransion to Operations &
Maintenance
- Identify business needs- Develop Concept Note - Develop TOR (Scope, time, cost, quality) & establish project type (small or big)- Develop business case based on project type & TOR- Develop a project charter based on project type selected and business case; and appoint a Project Manager
- Project type selected- Approved Concept Note & TOR- Business case- Approved Project Charter- Appointment of PM- Commitment of Resources
- No approved business case no project (big projects only)- No approved project charter no project - No approved project charter no engaging resources to start project planning- No project Sponsor no project
- Baselined Project Management Plan
- Project planning activities must be base on approved scope of work- All estimates must be realistic and achieveable - Key stakeholders should be consulted during project planning activities- Project Implementation Plan should be baselined before project execution starts- Project Management Plan should be approved and resources committed before project execution.
- PM identify & define planning team- Develop detailed Project Management Plan
- Work Breakdown Structure- Project Schedule / Time Mgt Plan- Project Procurement Mgt Plan ( refer to PPDA)- Project Scope Mgt plan- Project Cost Mgt Plan- Project Quality Mgt Plan- Project Risk Mgt Plan- Project Communication Mgt Plan- Project Human Resources Mgt Plan- Stakeholders Mgt Plan- Project Governance Structure- Project Information Security Compliance Plan- Configuration Mgt Plan- Project Closure Plan- Project Transittion to Support plan- Change Mgt Plan
- Direct and manage baselined Project Management Plan and project charter- Complete analysis and technical designs- Conduct design reviews- Procure / acquire technology and infrastructure- Develop solution- Develop Test plan- Perfom quality assurance- Execute unit, system and user acceptance testing- Document testing results- Conduct user training- Monitor & control project actual work completed against planned & correcting variances- Verifications and validations
- Approved requirements- Procurement schedules updates- Project progress updates- Project deliverables (e.g. Technical designs, user acceptance testing plans and results, solution modules, user training materials, operations & maintenance plans), etc- Stakeholders approvals
- Scheduled work/activities timelinesmust be respected- Regular meetings must be organized and well documented- Any project scope change must follow a scope change management process -
- Implement Closure Plan- Transition to servive delivery - Document migration to operation plan- Create lessons learned- Achieve documents- Formalizing project acceptance and bringing to an ordery end- Develop As Built Document (ABD)
- Migration and conversion plan- Lessons learned- Operations guide- Project closure document- Stakeholders approval
- Product scope verificaion before closure- Project management verification before closure
- Execute Operation & maintenance plan- Post Implementation Review (PIR)(by Internal Auditor 3 month after project closure)- Business case benefit tracking and measurement- Benefit reporting- Evaluateing sustainability
- Operational system- Product or service
- Change management aasurance
Monitoring and Control
4321
i. National IT Project Management Methodology Version 0.6 Page 28
Project Lifecycle
3.1.9. IT projects will go through five (5) process groups as defined by Project
Management Institute (PMI) namely: Initiation, planning, execution, monitoring &
control and closure. The monitoring and control process will be performed
throughout the project life cycle without a specific start or end. High level
activities performed at each stage, deliverables expected and controls at each
stage are illustrated in the methodology user interface in figure 3 above.
3.1.10. Table 2 below provides a quick description of the project life cycle process group
defined in the methodology user interface in figure 3.
Table 2: Description of Project Life Cycle Process Groups
Stage No. Process Group Description
1 Initiation Involves the processes required to go through to initiate, justify and
authorize a project or programme
2 Planning Involves the processes a project planning team should undertake to
define and develop a detailed project management plan. Enough
time should be allowed to define a detailed WBS and PIP. This is a
very important effort, which determines the successful delivery of a
project
3 Execution Involves processes to execute the plans defined in the project
management plan
4 Monitoring and
Controlling
This involves tracking, reviewing, monitoring and measuring progress
to identify variances (baseline- schedule, cost, quality) so that
corrective actions can be taken accordingly in order to meet
performance objectives defined in the project management plan. It
involves integrating change control, coordinating changes across the
project; Schedule control : controlling changes to the project
schedule; Cost control: controlling changes to the project budget;
i. National IT Project Management Methodology Version 0.6 Page 29
Quality control: monitoring specific project results to determine if
they comply with set quality standards and identifying ways to
eliminate causes of unsatisfactory performance; Status performance
reporting: progress measurement and forecasting; Risk monitoring
and control: keeping truck of identified risks and how to
reduce/eliminate risks among others
5 Closure Involves bringing a project to an orderly end and to gain formal
acceptance of the project; before transferring outcome into
operations.
Contract close out: completion and settlement of the contract,
including resolution of any open snags/tasks/items; perform
administrative closure: documentation (As Built Doc - ABD, evaluating
the Project; compiling lessons learned in the project closure
document for use in future similar efforts. A project manager should
spearhead the development of a closure report; and must be signed
off as per the project governance in place
Project Initiation Process group
3.1.11. The first stage, which is very critical, is the initiation. At this stage, it is where
initiatives are developed and also determine the level of details that will be
required for the rest of the project life cycle. For example, it is from this stage
where an initiative is categorized as a project or not, and whether a project is
small, medium or large.
3.1.12. IT Projects will be born and initiated by MDAs based on their mandate (s),
strategies, government directive (s), or any other initiative which can result into
improving social and economic development through IT. Opportunities or
initiatives will be evaluated through a set of activities that provide formal
i. National IT Project Management Methodology Version 0.6 Page 30
authorization to start a project. The organization should identify a project sponsor
to be responsible for project goals and benefits.
3.1.13. The goals and benefits of the initiative may result in a justification for the
investment in the project in a form of a business case or feasibility studies, and
that may contribute to a prioritization of all opportunities. The purpose of the
justification is to obtain organizational commitment and approval for investment in
the selected projects.
3.1.14. It should be noted that most approaches are unique to the circumstances when
it comes to managing IT projects. An IT project’s complexity, size and risk profile
will determine both the requirements for documentation and the activities to be
conducted by the project team.
3.1.15. The stage concludes when the sponsor signs off (Go / NO GO Stage gate 1) the
Project Charter, signalling that the project manager may begin the detailed
planning work required in the next stage. It will be in the interest of the sponsor to
ensure that the initiation stage is expedited to progress into the project planning
stage.
3.1.16. A project charter will be the main deliverable of project initiation stage. The
project charter template provides details.
3.1.17. Detailed guidance on classification, expected documents, roles and
responsibilities and best practices are contained in the project initiation support
guide.
i. National IT Project Management Methodology Version 0.6 Page 31
Project Planning Process Group
3.1.18. On receiving a Project Charter, a Project Manager should quickly set up a
skeleton team of Subject Matter Experts (SME) study the project charter and
develop a detailed Work Breakdown Structure (WBS) to clearly define a
comprehensive project scope, and thereafter draft a Project Management Plan.
3.1.19. A kick-off meeting with Project Implementation Team identified in the draft
Project Management Plan should be organized to discuss the draft plan and get a
buy-in from people going to participate in the execution of the project.
Subsequent planning meetings should be organized by the Project Manager until a
final Project Management Plan is developed
3.1.20. A detailed Project Management Plan should be sufficient to establish baselines
against which project implementation should be managed and project
performance measured and controlled. This can only be achieved if the planning
team is properly resourced, motivated, making use of templates and lessons learnt
from previous projects. The project manager should identify key resources to
develop the different plans as listed in the methodology user interface illustrated
in figure 3 above.
3.1.21. The planning stage should not take more than 2 weeks for small project and not
more than a month for large/ complex projects. The planning phase is concluded
with a Steering Committee or project sponsor approval (Go / NO GO stage gate 2)
of the Project Management Plan for large or small projects respectively, signalling
that the project execution could begin.
3.1.22. It is critical that all staff in the MDA involved in IT projects clearly understand
their roles in the implementation of any IT project for optimal results. Sensitization
i. National IT Project Management Methodology Version 0.6 Page 32
workshops on the implementation of IT projects will therefore be held for all
officers after project planning as a first activity in the implementation process.
3.1.23. The project planning support guide provides details.
Project Execution Process Group
3.1.24. The execution processes are used to perform the project management activities
and to support the provision of the project’s deliverables in accordance with the
project management plans. The actual work gets done; project team completes
the tasks outlined in the Project Implementation Plan (PIP) and develops project
deliverables.
3.1.25. The project manager takes lead of the project execution stage and has to ensure
that all activities are executed as planned with minimum surprises.
3.1.26. Duration of the project implementation should be determined from the PIP
baseline. The methodology user interface illustrates other tasks that are
performed during project execution.
3.1.27. The execution stage should be concluded when the entire project scope is
delivered to the satisfaction of the end users, project team, project manager,
sponsor, project owner and the Steering Committee. Approvals should be sought
(Go / NO GO stage gate 3)
3.1.28. The Project Execution Support Guide provides details.
i. National IT Project Management Methodology Version 0.6 Page 33
Monitoring and Controlling Process Group
3.1.29. The success of IT project implementation depends significantly on how the
planned activities and output are effectively supervised, monitored and evaluated.
The monitoring and controlling processes should be implemented to monitor,
measure and control project performance against the baseline project
management plan. Consequently, preventive and corrective actions may be taken
and change requests made, when necessary, in order to achieve project objectives.
3.1.30. The project monitoring and control support guide provides details.
Project Closure Process Group
3.1.31. Projects are temporary in nature and a project team must complete the planned
activities in order to complete the project life cycle. Conducting the activities of
this stage is vital to continuous improvement efforts and successful transition of
the project deliverables.
3.1.32. After achieving acceptance of the project deliverables, the project
implementation team should develop a project closure report, document lessons
learned and archives project documentation for future use.
3.1.33. The project manager should transfer the project deliverable(s) to operations and
support staff, who will assume responsibilities to maintain the project deliverables
as an operational activity. Finally, the project team should be disbanded.
3.1.34. However, a project can be closed at any stage of the project life cycle because of
one reason or another. Whatever the circumstances, a project should undergo a
closure process.
i. National IT Project Management Methodology Version 0.6 Page 34
3.1.35. The project closure support guide provides details.
Project Management Tools and Techniques at each Stage
3.1.36. There are several tools and techniques which can be used to perform or achieve
different deliverables at each stage of the project life cycle. In a table 3 below you
can find a sample of these tools and techniques. The project manager will be free
to use any other available automated support tools and techniques to achieve a
given deliverable.
Table 3: Sample Project Management Tools and Techniques used at each project stage
Tools / Techniques Initiation Planning Execution Monitoring
and Control
Closure
Work Breakdown
Structure (WBS)
√ √ √ √
Critical Path Analysis √ √ √
Project Information
Management Systems
√ √ √ √ √
Spread Sheet Software
such as Excel, etc
√ √ √ √
Project Management
Software tools such as
MS Project
√ √ √
Project drawing tools
such as Ms Visio
√
Meetings √ √ √ √ √
Expert Judgement √ √ √ √ √
i. National IT Project Management Methodology Version 0.6 Page 35
Interview √ √ √ √ √
Focus Groups √ √ √ √ √
Facilitated Workshops √ √ √ √ √
Delphi Technique √ √ √ √ √
Operations and Maintenance (Transition to Support)
3.1.37. All projects have to be concluded and transfer the project outcomes into
operations and maintenance phase; and start realizing the benefits which could
have been specified in the business case.
3.1.38. The process of transiting from a project stage into operations, maintenance and
support must be well planned and executed throughout the project life cycle. A
support focal point should be identified and participate at all governance
structures (e.g. Steering Committee and PIT) to ensure that operations and
maintenance requirements are taken care of throughout the project. This will also
result in knowledge transfer and smooth handover. The Project Manager will be
accountable for ensuring that this is done.
3.1.39. The Project Owner takes responsibility of the outcome on closing the project.
Project implementation team should not get involved in the operations and
maintenance phase unless if the resources were strategically involved in the
project phase to ensure knowledge transfer and capacity building.
3.1.40. The operations and maintenance support guide provides details.
i. National IT Project Management Methodology Version 0.6 Page 36
Project Documentation Management
3.1.41. Documentation throughout the project life cycle should be developed to
appropriate level and signed off. The table 4 provides guidance on minimum
documentation and activity effort required to complete this task based on project
classification.
3.1.42. Initiation Stage Activities and Required Documentation
Table 4: Initiation Phase Activities and Required Documentation
Activity Out put Small
Project
Medium
or Large
Project
Develop Concept Note Concept Note short form √
Concept Note long form √
Develop Business Case &
TOR
Business Case & TOR short form √
Business Case & TOR long form √
Preliminary Risk Assessment √ √
Appoint Project Sponsor √ √
Set up Steering Committee √
Develop Project Charter Project Charter short form √
Project Charter long form √
3.1.43. Planning Stage Activities and Required Documentation
Table 5: Planning Stage Activities and Required Documentation
Activity Out put Small
Project
Medium
or Large
Project
Project Scope Definition Scope Statement Sign Off √ √
i. National IT Project Management Methodology Version 0.6 Page 37
Project Manager Initial
work plan
Identify and define Planning
Team
√ √
Conduct planning kick off
meeting
√ √
Plan Schedule and
Resources
Work Breakdown Structure √ √
Project Implementation Plan
(PIP)
√ √
Resources Plan √
Procurement Plan √ √
Budget Plan √ √
Develop Supplemental
Plans
Risk Management Plan √ √
Communication plan √ √
Project Change and Configuration
Management Plan
√
Project Quality Management
Plan
√ √
Project Plans Approval Approval by Project Sponsor √ √
Approval by Steering Committee √
3.1.44. Execution and Control Stage Activities and Required Documentation
Table 6: Execution and Control Stage Activities and Required Documentation
Activity Out put Small
Project
Medium
or Large
Project
Conduct Execution Kick-off
Meeting
Quality Assurance
Meeting minutes √ √
i. National IT Project Management Methodology Version 0.6 Page 38
Project Implementation
Team (PIT) Mobilization
Set up a team of highly
motivated PIT
√ √
Execute Project Tasks Activity deliverables √ √
Manage Project
Procurement
Initiate required procurements √ √
Procurement Log √ √
Perform Project
Communication
Status Report, updates to
Sponsor
√ √
Status Report, updates to
Steering Committee
√
Track/Manage issues, Risks Issue and Risk logs √ √
Conduct Project Change
Management
Change Control Request √ √
Change Request Review √ √
Approve Change Request √ √
Change Request Log √ √
Scope Verification Scope Verification Reports √ √
Quality Assurance Quality Assurance Reports √ √
Project Deliverable
acceptance
Project Team √ √
Project Owner √ √
Project Sponsor √ √
i. National IT Project Management Methodology Version 0.6 Page 39
3.1.45. Closeout Stage Activities and Required Documentation
Table 7: Closeout Stage Activities and Required Documentation
Activity Out put Small
Project
Medium
or Large
Project
Conduct Closure Activities √ √
Create Closeout
Documentation
Lessons Learned √ √
Project Closure Report √ √
Transition Support to
Operation Staff
√ √
Perform Procurements
Audit
Procurement Audit Report √ √
Release Project
Implementation Team
Issue Project Completion
Certificates to PIT
√ √
Stage Gates Checklist
3.1.46. There are four (4) stage gates, which should be used as decision points to
progress a project from one stage into another. A Go or NO Go decision should be
given and a sign off from the Steering Committee and Project Sponsor should
always be sought.
3.1.47. The check list below provides guidance to ensure compliance before progressing
from a stage to the next one. A checklist for each stage gate is defined below and a
Project Manager will be accountable for ensuring that all documentation is
compiled, verified and filed in the project file.
i. National IT Project Management Methodology Version 0.6 Page 40
Table 8: Stage Gate 1: From Initiation to Planning Stage
No Deliverables Required Available on File
1 Approved Concept Note
2 Approved Terms of Reference with crystal clear Scope
3 Approved Business Case
4 Approved Request for Proposal (RFP) (if applicable)
5 Governance Structure in place (Steering Committee Setup)
and Appointments with TOR issued
6 Project Sponsor Assigned and Appointment issued
7 Project Funds Committed
8 Project Human Resources Committed (including support
focal point)
9 Project Manager assigned and appointment issued
10 High Level Stakeholders List and Analysis
11 Approved Project Charter
12 Project Charter forwarded to Project Manager for Action
Table 9: Stage Gate 2: From Planning Stage to Execution Stage
No Deliverables Required Available on File
1 Detailed Work Breakdown Structure
2 Detailed Project Implementation Plan
3 Detailed Phased Budget Work Plan
4 Human Resources Requirements
5 Procurement Plan (if applicable)
6 Risk log
7 Communication Plan
8 Planning Meeting Minutes
i. National IT Project Management Methodology Version 0.6 Page 41
9 Transit to Support Plan
10 Quality Requirements (Indicators)
11 Change Management Plan
12 Information Security Compliance Plan
13 Stakeholders Analysis Log and Engagement Plan
14 PIT signed recommendations to Steering Committee
15 Decision how to acquire Information System (in-house or
procure consultants) (if scope involve Information System
acquisition)
16 Integrated Project Management Plan (Implementation
Manual)
Table 10: Stage Gate 3: From Execution to Closure Stage
No Deliverables Required Available on File
1 Deliverables as defined in final TOR or Contract
2 Specification (Functional & Non-functional)Delivered
3 Documentation of Lessons Learnt
4 Updated PIP
5 Test results
6 Quality Requirements results
7 Progress Status Reports
8 Review Meeting Reports
9 Design Checklist
10 PIT signed recommendations to Steering Committee
i. National IT Project Management Methodology Version 0.6 Page 42
Table 11: Stage Gate 4: From Closure to Support Stage
No Deliverables Required Available on File
1 User Acceptance / Validation Results and Sign Off
2 As Build Document (if applicable)
3 Operational Readiness Checklist
4 Change management plan
5 Closure Report
6 End User Agreement to Operate
7 Steering Committee Sign Off
8 Deployment and Stabilisation Checklist
9 Deployment Plan
10 Project Support Manuals
11 PIT signed recommendations to Steering Committee
4. Project Information Security Compliance
Information Security Compliance Plan must be followed throughout the IT project life cycle
to reduce information security risks to acceptable levels. It should be noted that
Information Security transcends both electronic and non-electronic information (data
endowed with meaning) with the ultimate objective of supporting the attainment of
business objectives.
Security risk assessments should be conducted during the project initiation phase,
mitigation measures included in planning stage and controls implemented in the execution
stage of a project to ensure that any risks likely to affect the successful completion of the
project are responded to appropriately.
i. National IT Project Management Methodology Version 0.6 Page 43
Any changes must also undergo security risk assessment to ensure that appropriate controls
are implemented.
Information Security Compliance Support Guide provides details.
5. Project Management Support Guides Project Management Support Guides should be used by project managers, project
management teams and other stakeholders throughout the project life cycle as references
and getting guidance on how to manage different IT projects aspects. The guides contain
methods, tools, techniques, good practices and critical success factor.
Table 8 provides high level description of IT Project Management Support Guides. Users of
this methodology should refer to individual guides for more detailed guidelines while
managing IT projects.
Table 12: List and description of Project Support Guides
No. Guide Purpose
1. Project Initiation Guide Provides the processes to go through when initiating a project,
initiative classification, expected documentation that should be
developed based on a given classification, guiding principles to be
followed in order to successfully go through this stage; and tools
and techniques to be used during project initiation.
2. Project Planning Guide Provided guidelines and processes required for planning a project
after a charter sign off
3. Project Executing Guide Provided guidelines and processes required for executing a project
after planning phase.
4. Project Monitoring and
Control Guide
Provide processes for monitoring and controlling a project to ensure
intended product/service and project objectives are realized.
i. National IT Project Management Methodology Version 0.6 Page 44
5. Project Governance
Structure and Reporting
Guide
Provides project implementation governing structure and reporting.
Roles and responsibilities are defined and provides guiding
principles to ensuring governance is established.
6. Project Stakeholders
Management Guide
Provides strategies for managing project stakeholders in order to
deliver on their expectations.
7. Steering Committee
Support Guide
Focuses on selections of Steering Committee; and define their roles
and responsibilities.
8. Project Manager
Selections &
Responsibilities Guide
Provides guidelines on how an IT Project Manager should be
selected and his/her responsibilities defined.
9. Project Change
Management Guide
Provides processes and actions required for an organization to
understand, prepare for, implement and take full advantage of
significant change as a result of a project from initiation until
closure and during support.
10. Risk Management Guide Provides guidance on how to manage risks through the project life
cycle.
11. Communication Guide Is a guide that describes how you are going to communicate the
right messages, to the right people, at the right time. It sets out the
communications goals, stakeholders and strategies, as well as the
communications activities and timeframes
12. Quality Management
Guide
This guide will define coordinated activities to direct and control
quality of a project. It will provide a set of quality standards,
procedures and responsibilities
13. Project Closure Guide Provides guidance on the process of closing a project and transit it
to support
14 Project Scope
Management Guide
Provides guidance on the processes and tools used in project scope
management
15 Project Scheduling & To build a project schedule that consists of a work breakdown
i. National IT Project Management Methodology Version 0.6 Page 45
Resourcing Guide structure, deliverables, milestone and corresponding resources (HR
& cost)
16 Project Estimating Guide This guide is designed to provide Project Managers with an
understanding of how to create and present a project cost and time
estimate appropriate to the stage of the project. The content is
designed to be applicable to projects of all types, and includes
guidance to help to create an estimate in accordance with key
characteristics of project size, risk and criticality.
The Activity Sheet “Develop Project Cost Estimate” provides a high
level overview of the process described in this guide.
17 Feasibility Study Guide This guideline is to be used in preparing a feasibility study for major
projects. A feasibility study creates a holistic justification for the
project and serves as a living document against which project
deliverables are measured during procurement and even after
implementation of the project
18 Project Information
Security Compliance
Guide
Provide guidance on how to ensure information security compliance
19 Programme Management
Guide
Provide guidance on how to manage multiple projects within a
Programme.
20 Project Baselining Guide This guide is intended to provide the Project Manager with
guidance creating a project baseline (how to baseline a project
schedule and budget with the project scope) and when to re-
baseline.
This document provides high level guidance on when and how to
baseline a project schedule and budget with the project scope. It is
assumed that the reader has knowledge of budgeting and
scheduling techniques.
i. National IT Project Management Methodology Version 0.6 Page 46
21 Project Reporting Guide This guide is intended to provide the Project Manager with
guidance on how to monitor and report against project
performance and what action to take for projects off-track.
22 Testing and confirmation
Guide
This guide is intended to introduce the Project Manager to the
standard activities, deliverables and techniques incorporated in the
framework to enhance the effectiveness of testing and
confirmation. The content is drawn from a broader industry-base of
testing best-practices
23 Transition to Support
Guide
This guide provides the processes involved from project stage to
operations and maintenance.
6. Project Management Support Templates Project documentation is one of the most challenging and unpopular exercise by most IT
project management personnel, yet a very critical task throughout a project life cycle.
Furthermore, it is time consuming. In order to mitigate such challenges, templates have
been developed to expedite the process of project documentation and standardize IT
project reporting.
The table 13 provides high level description of IT Project Management templates, which
users should use to expedite project documentation process. Template can be accessed
from the IT Project Management Tool Kit.
i. National IT Project Management Methodology Version 0.6 Page 47
Table 13: List and description of Project Templates
STAGE TEMPLATES
DESCRIPTION PERSON
RESPONSIBLE
Initiation
Initiator
Concept Note Describes an initiative for considerations
Project Proposal A Project Proposal is written to convince a sponsor that a
project needs to be initiated to solve a particular problem or
opportunity in the business. It describes in depth, the basis
upon which the project needs to be commenced, so that the
sponsor fully understands why it’s critical to the business and
what is involved. It also needs to outline the implications of
not approving the project, so that the sponsor is forced to
make a clear decision – to approve the project, or not.
Initiator
Terms of Reference This can also be referred to as the Product description. This is
used to gain agreement from the user on the projects scope
and requirements to define quality expectations,
specifications & define acceptance criteria for the project
Initiator
Business case (
products/ services)/
Feasibility Study
The business case / feasibility study details the justification
for undertaking, and for continuing, a project. The
justification for an organisational activity (project) which
typically contains costs, benefits, risks and timescales and
against which continuing viability is tested
The Business case presents an optimum mix of information
used to judge whether a project is and remains desirable,
viable and achievable and therefore worth investing in.
Business
Analyst and
Initiator
Project Charter A Project Charter is a document which outlines the purpose
of the project, the way the project will be structured and how
it will be successfully implemented. It describes the project:
Project
Sponsor
i. National IT Project Management Methodology Version 0.6 Page 48
Vision, objectives, scope and deliverables (i.e. what we
have to achieve)
Stakeholders, roles and responsibilities (i.e. who will take
part in it)
Resource, financial and quality plans (i.e. how it will be
undertaken).
The Project Charter may also be referred to as a “Terms of
Reference (TOR)” or “Project Definition Report (PDR)”.
It is developed pre-project and is used to initiate a project,
hence the birth of a project.
Appointment letters
(SC & PM)
Appointment letters templates TMT
Planning
Project
Management Plan
Defines how the project will be undertaken by looking at all
aspects of the project plans: scope, schedule, cost, risk,
procurement, human resources, communication, and quality
management
Project
Manager
Project
Implementation
Plan
Defines procedures for the management of schedule, cost,
quality, risk, issues, communication, change control,
configuration management, health, environment, safety,
roles, responsibilities, organization and other subjects as
needed. It is a component of a Project Management Plan.
Project
Manager
Stakeholder Matrix
and Analysis
Defines stakeholders analysis, their roles and responsibilities Project
Manager
Risk Management
Plan Matrix
Defines risks and qualitative analysis Project
Manager
Communication
Plan
A Communications Plan is a document that describes how you
are going to communicate the right messages, to the right
Project
Manager
i. National IT Project Management Methodology Version 0.6 Page 49
people, at the right time. It sets out the communications
goals, stakeholders and strategies, as well as the
communications activities and timeframes
Progress Status
/Progress Reports
The Project Status Report is a document that is used by
Project Managers for formal regular reporting on the status of
a project to the Steering Committee, Project Sponsor, Senior
Manager or other Key Stakeholders, depending on the size of
the project.
Project
Manager
Project closure
Report
A Project Closure Report is a document which formalizes the
closure of the project. It provides confirmation that the
criteria for customer acceptance have been met and requests
sign-off from the Project Sponsor to close the project.
Project
Manager
Quality
Management Plan
A register containing summary details of all planned and
completed quality activities. The quality register is used by
the PM and the Project assurance as part of reviewing project
progress
Project
Manager
Lessons Learned Document lessons learned Project
Manager
Post
Implementation
Review form
Three (3) month after the close of a project, each MDA must
complete two post implementation reviews: one with the user
and the other with project team. The reviews must then be
reported at the next project managers meeting.
The completed and signed reviews must be maintained in the
project file and also copied to Steering and Policy Committees
of the project.
Internal Auditor
i. National IT Project Management Methodology Version 0.6 Page 50
7. Project Management Maturity Model In order to evaluate adoption of project management methodology by MDAs, the Project
Management Maturity Model (PMMM) illustrated in figure 5 will be used.
Figure 5: Project Management Maturity Model
Source: KLR Consulting Inc
Because government is desirous to have successful delivery of IT projects, it is important that
MDAs strive to be at level three or greater of the maturity model. The table 15 below provides
a description of the maturity model.
Table 15: Description of Project Management Model
Level Level Name Key Characteristics
1 Adhoc Each IT project handled differently
Highly dependent on project Manager
IT Project outcomes unpredictable
Little organization support for project management
Lessons learned are not gathered and passed on to other projects
2 Foundation Managed support for project management
Optimizing (5)
Integrated (4)
Managed (3)
Foundation (2)
Adhoc (1)
Consistent, basic approach to project planning and execution
Project- centred Organization
No formal Consistent process
Project portfolio management is Institutionalized and integrated into organization's business planning process
Consistent, comprehensive approach
Preferred levels for all Government IT Projects
i. National IT Project Management Methodology Version 0.6 Page 51
Repeatable processes are applied to basic project management steps
IT Project outcomes are more predictable
Use of common tools and techniques for key project management
processes
3 Managed Senior management support for project management
Organization can efficiently plan, execute, integrate, control single IT
projects
Repository or previous projects experiences is maintained and utilized
Team members and project managers trained in project management
Consistent use of tools and techniques for project management
processes
4 Integrated Active senior management support for integration of business
planning and IT project execution
Organization can efficiently plan, execute, integrate and control
multiple IT projects
Database of previous project data is maintained and utilized
5 Optimizing Project management environment improvement is actively
encouraged
Flexible, project-centred organization structure
Career programme for project managers
Project management training is a key component in staff
development
8. Code of Ethics and Professional Conduct The Code of Ethics and professional conduct shall apply to all persons involved in IT project
work in government, especially the Project Steering Committee (SC) and Project
Implementation Teams (PIT). All stakeholders involved in IT project work should commit to
doing what is right and honourable at all times, make wise decisions, particularly when
i. National IT Project Management Methodology Version 0.6 Page 52
faced with difficult situations where they may be asked to compromise their integrity or
values.
All key project stakeholders should sign the professional code of conduct and submit signed
copies to the project sponsor through the project manager. A template is available in the
tool kit.
The following values, defined by global project management community, should be
upheld: responsibility, respect, fairness and honesty.
8.1.1. Responsibility
Responsibility is stakeholders’ duty to take ownership for the decisions they make
or fail to make, the actions they take or fail to take, and the consequences that
result. Stakeholders should ensure:
a. All decisions and actions taken are based on the best interests of government,
public safety, information security and the environment.
b. They fulfil the commitments that they undertake – they do what they say they
will do.
c. When they make errors or omissions, they take ownership and make
corrections promptly.
d. When they discover errors of commission or omission caused by others, they
communicate them to the appropriate authorities as soon they are discovered.
They accept accountability for any issues resulting from their errors or
omissions and any resulting consequences.
e. They protect proprietary or confidential information that has been entrusted to
them.
f. Uphold the policies, rules, regulations and laws that govern their work and
profession. They should not engage in any illegal behaviour, including but not
limited to: theft, fraud, corruption, embezzlement, or bribery
i. National IT Project Management Methodology Version 0.6 Page 53
8.1.2. Respect
Stakeholders should show a high regard for themselves, others, and the
resources entrusted to them. Resources entrusted to them may include people,
money, reputations, the safety of others, and natural or environmental
resources. Stakeholders should ensure that:
a. They avoid engaging in behaviour they might consider disrespectful
b. They conduct themselves in a professional manner, even when it is not
reciprocated
c. They do not act in an abusive manner towards others
d. They do not exercise the power of their expertise or position to influence the
decisions or actions of others in order to benefit personally at their expense
e. They respect the property rights of others
8.1.3. Fairness
Fairness refers to the stakeholders’ duty to make decisions and act impartially
and objectively. Their conduct must be free from competing self-interest,
prejudice, and favouritism. Stakeholders should ensure that:
a. They demonstrate transparency in their decision-making process.
b. They provide equal access to information to those who are authorized to
have that information.
c. They proactively and fully disclose any real or potential conflicts of interest to
the appropriate authorities
8.1.4. Honesty
Stakeholders should understand the truth and act in a truthful manner both in
their communications and in their general conduct throughout the project life
cycle. Stakeholders should ensure that they:
a. Are truthful in their communications and in conduct
i. National IT Project Management Methodology Version 0.6 Page 54
b. Provide accurate information in a timely manner; including having the
courage to share bad news even when it may be poorly received
c. Make commitments and promises, implied or explicit, in good faith
d. Strive to create an environment in which others feel safe to tell the truth
e. Do not engage in or condone behaviour that is designed to deceive others,
including but not limited to, making misleading or false statements, stating
half-truths, providing information out of context or withholding information
that, if known, would render their statements as misleading or incomplete.
9. General Project Success Factors Whatever has been described in this methodology, if upheld, contribute to the successful
delivery of IT projects in Government. For bases of emphasis, below is quick reference to
some of these factors.
a. Understanding the project scope by all stakeholders
b. Top management support buy-in and availability
c. Constant availability of approved project funding
d. Setting up a dedicated (temporary) Project governance structure different from MDA’s
functional structure
e. Availability of skilled human resources to run IT projects
f. Implementation of a change management strategy
g. Project documentation at each project stage should be adhered to
h. Project big picture should be understood; Understanding the overall purpose and goal of
the project allows you to make decisions and resolve issues that arise
i. Project details should be closely managed; stay on top of the details
j. Decisions should be carefully and made promptly
k. Emphasis should be placed on project communication
l. Risk assessment and analysis should be carried out at every stage of the project
i. National IT Project Management Methodology Version 0.6 Page 55
m. Stakeholders expectations that are in line with the project’s objectives should be
properly managed; spend quality time with stakeholders to ensure their expectations
are met and managed
n. Approvals and Sign-Offs on changes, plans or deliverables should be respected. Make
sure appropriate parties are okay with a project moving forward
o. Meetings should be held regularly. It is tempting to get together only when there are
big problems, but when status meetings, project reviews, and other meetings are held
regularly, it minimizes the risk of unpreparedness in case any problem arises.
p. Post-implementation review should always be done
i. National IT Project Management Methodology Version 0.6 Page 56
10. Glossary For purpose of having a common understanding of terminologies used in this methodology, the
supporting guides and templates, the following definitions shall apply.
Activity: Identified component of work within a schedule that is required to be undertaken to complete
a project
Application area: Category of projects that generally have a common focus related to a product,
customer or sector
Baseline: Reference basis for comparison against which project performance is monitored and
controlled
Change request: Documentation that defines a proposed alteration to the project baseline scope
Concept note:
Configuration management: Application of procedures to control, correlate and maintain
documentation, specifications and physical attributes
Control: Comparison of actual performance with planned performance, analysing variances and taking
appropriate corrective and preventive action as needed
Corrective action: Direction and activity for modifying the performance of work to bring performance in
line with the plan
Critical path: Sequence of activities that determine the earliest possible completion date for the project
or phase
IT Projects: These are projects which will result into a product or service related to computing and
information Technology
Lag: Attribute applied to a logical relationship to delay the start or end of an activity
Lead: Attribute applied to a logical relationship to advance the start or end of an activity
Methodology: It is a collection of processes, methods and tools for accomplishing an objective.
Methodologies provide a checklist of key deliverables and activities to avoid missing key tasks. It can
also be defined as a set of guidelines or principles that can be tailored and applied to a specific situation.
In a project environment, these guidelines might be a list of things to do. A methodology could also be a
specific approach, templates, forms, and even checklists used over the project life cycle.
Project Charter: This is a major deliverable or output of the initiation stage. It specifies high level
project objectives, scope, timelines, cost, risks, stakeholders and used to appoint a Project Manager.
i. National IT Project Management Methodology Version 0.6 Page 57
Approved project charter signifies that the project is officially authorized and it provides authority to
project manager to apply organization resources to project activities. Approved project charter gives
way for a project to proceed to the planning stage.
Project Implementation Plan (PIP): This is a detailed list of all activities as defined in the work
breakdown structure with defined estimated durations, dependencies and assigned resource to execute
each activity. It can also be called a roadmap.
Project Management Methodology: provides a roadmap for managing projects. Project methodologies
provide guidance to project teams to collaborate in tackling projects.
Preventive action: Direction and activity for modifying the work, in order to avoid or reduce potential
deviations in performance from the plan
Project life cycle: Defined set of phases from the start to the end of the project
Project: Is a temporary endeavour undertaken to create a unique service or product
Project Management: Is the application of knowledge, skills, tools and techniques to Project
activities to meet project requirements. Also defined as: as the planning, organizing, directing
and controlling of assigned project resources in order to accomplish a given objective within the
constraints of time, cost and quality.
Risk register: Record of identified risks, including results of analysis and planned responses
Stakeholder: Person, group or organization that has interests in, or can affect, be affected by,
or perceive itself to be affected by, any aspect of the project
Tender: Document in the form of an offer or statement of bid to supply a product, service or
result, usually in response to an invitation or request
Work Breakdown Structure (WBS): This the decomposing of a huge project activity or task into
small manageable work packages, which can easily be managed, timelines and costs estimated.
Work Breakdown Structure Dictionary: Document that describes each component in the work
breakdown structure
i. National IT Project Management Methodology Version 0.6 Page 58
11. References List of standards this methodology is based on:
1) ISO 21500:2012 ( E )
2) Project Management Institute Body of Knowledge (PMI PMBOK) ver 4
3) PRINCE2
4) Selected project management frameworks and methodologies from different countries
and organizations