Unlocking North Sea CO2 Storage for Europe
Hans Aksel Haugen, Tel-Tek. Edinburgh 12 September 2013
The role of shipping and FPSOs in offshore injection
Ship based CCS chain
CO2 source Liquefaction Intermediate
storage
Loading Pre
treatment / Unloading
Injection for EOR
Onshore Hub Pipeline
2
Ship based CO2 transportation alternatives
• Ships carrying liquiefied CO2
– Industrial experience exists • Barges • Ships carrying compressed CO2
– No existing practical experience
3
Transportation of food grade CO2
M/T Yara Gas III alongside the quay near Yara’s ammonia plant in Porsgrunn, Norway. Capacity: 1200 tons of liquiefied CO2 in 2 tanks of 600 tons capacity each Ship type: Converted container vessel
Photo: Larvik Shipping 4
Ship size and installations on land
• Optimal size of ship vary with transporting distance and CO2 volume – 10000 – 50000 tons of cargo?
• CO2 to be liquiefied (7 barg, -50˚C, <50 ppm H2O)
• Need of intermediate storage tanks, capacity about +50% of ship
• Need of loading facilities
5
Yara’s CO2 import terminal in Montoir-de-Bretagne, France
CO2 storage tanks 2 * 450 tons 50 meters * 5 m diameter 300 m pipeline to quay
Photo: Yara 6
CO2-transportation, ships vs. pipelines Pipelines
Ships
+ - + - Low Opex High Capex Low Capex
High Opex
Onshore needs: Compression
Relatively low flexibility
Large flexibility (volume and route)
Onshore need for intermediate storage and liquefaction plants
Can be built both onshore and offshore
Low potential for re-use
Re-use potential
Large sunk cost Lower sunk cost
Short delivery time (2 years ?)
7
Ship based CCS chain
CO2 source Liquefaction Intermediate
storage
Loading Pre
treatment / Unloading
Injection for EOR
Onshore Hub Pipeline
8
Combination of ships and pipelines: An example from the Skagerrak area
Emission SourcesHub locationStorage location Pipeline networkShip transport route
Norway
Sweden
Denmark
Skagerrak
Kattegat
0 55 km
Oslo
Kristiansand
Grenland
Tønsberg
Halden
Lysekil
Stenungsund
Gӧteborg
VӓrӧAalborg
© map: Mareano 9
Transport cost – ramp up • Unless building strict one-to-one pipelines, 100%
capacity utilization from day 1 is very unlikely • Alternative solutions:
– Replace pipelines concurrently with increasing CO2 volumes
– Parallell pipelines
– One oversized pipeline from day 1 • Challenges:
Reasonable knowledge of future CO2-volumes Who to pay for redundant capacity until full volume
– Ships
10
Cost estimations. Assumptions
• 14 Mtons CO2/y • 100% utilization of capacity • 8% average rate of return, project lifetime = 25
years (construction time 1 year, operation time 24 years)
• Transport – Ships: Liquefaction, intermediate storage,
preparation for storage – Pipelines: Compression
• Uncertainty: ± 30%
11
Transport costs – 6 Mtons/y and 14 Mtons/y
12
0
5
10
15
20
25
Case 1.1 Case 2.1 Case 3.1
Cos
t (€/
tonn
e C
O2)
6 Mtonne CO2
14 Mtonne CO2
Pipeline Ship Combination
Transport cost - sensitivities • Which parameters have the biggest influence on
transport cost? • Assumption: 5 Mtons CO2 to be transported 500 km
13
-2 -1 0 1 2 3
Capex
Opex
Years
Rate
Length
Amount
Change €/tonne CO2
Pipeline, 9.8 €/tonne CO2
-50%
+50%
-5 -4 -3 -2 -1 0 1 2 3 4 5
Capex
Opex
Years
Rate
Length
Amount
Change €/tonne CO2
Ship, 9 €/tonne CO2
-50% +50%
Transport cost, pipelines and ships
14
0
10
20
30
40
50
60
70
80
90
100
0 200 400 600 800 1000 1200 1400
€/to
nne
CO
2
Length [km]
Cost variation with length and capacity
Pipeline, 300 kt
Pipeline, 600 kt
Ship, 300 kt
Ship, 600 kt
Pipeline, 5000 kt
Ship, 5000 kt
Pipeline, 15000 kt
Ship, 15000 kt
Ship based CCS chain
CO2 source Liquefaction Intermediate
storage
Loading Pre
treatment / Unloading
Injection for EOR
Onshore Hub Pipeline
15
The far end of the chain: FPSOs
FPSO: Floating Production, Storage and Offloading
16
FPSOs: Possible benefits
• Ships may deliver directly to FPSO • Remove CO2 handling from platform • Reducing need for closing down
production (?) – Postponed oil production can
significantly reduce NPV of CO2-EOR
17
FPSOs: Challenges
• Incoming CO2 has very low temperature • Ice formation
• Intermediate storage need? • Unloading under hard weather conditions
18
Conclusions
• To transport CO2 by ship introduces flexibility into the CCS chain
• As a start-up method ships are advantageous as compared to pipelines
• Cost of ship transport does not vary much with volume and distance, but..
• Pipelines are more economical for larger volumes over shorter distances
• There is industrial experience with ship transport and handling of CO2
• FPSOs seem to be an interesting option for offshore unloading in combination with ships, however, not without challenges
19