+ All Categories
Home > Documents > The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The...

The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The...

Date post: 18-Aug-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
23
The SECARB Anthropogenic Test: The SECARB Anthropogenic Test: The First U.S. Integrated CO The First U.S. Integrated CO 2 Capture, Capture, The First U.S. Integrated CO The First U.S. Integrated CO 2 Capture, Capture, Transportation and Storage Test Transportation and Storage Test George Koperna, Jr., Vello Kuuskraa, George Koperna, Jr., Vello Kuuskraa, and and David Riestenberg, David Riestenberg, Advanced Resources International Advanced Resources International Richard Rhudy Richard Rhudy and and Robert Trautz Robert Trautz, Electrical Power Research Institute , Electrical Power Research Institute Dr. Jerry Hill Dr. Jerry Hill, Southern States Energy Board , Southern States Energy Board Dr. Richard Esposito Dr. Richard Esposito, Southern Company , Southern Company
Transcript
Page 1: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

The SECARB Anthropogenic Test: The SECARB Anthropogenic Test: The First U.S. Integrated COThe First U.S. Integrated CO22 Capture,Capture,The First U.S. Integrated COThe First U.S. Integrated CO22 Capture, Capture, 

Transportation and Storage TestTransportation and Storage Test

George Koperna, Jr., Vello Kuuskraa, George Koperna, Jr., Vello Kuuskraa, andand David Riestenberg,  David Riestenberg,  Advanced Resources InternationalAdvanced Resources InternationalRichard Rhudy Richard Rhudy andand Robert TrautzRobert Trautz, Electrical Power Research Institute, Electrical Power Research Institute

Dr. Jerry HillDr. Jerry Hill, Southern States Energy Board, Southern States Energy BoardDr. Richard EspositoDr. Richard Esposito, Southern Company, Southern Company

Page 2: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

AcknowledgementAcknowledgement

This presentation is based upon work supported by the Department of Energy National

gg

Energy Technology Laboratory under DE-FC26-05NT42590 and was prepared as an accountof work sponsored by an agency of the United States Government. Neither the United StatesGovernment nor any agency thereof, nor any of their employees, makes any warranty,express or implied, or assumes any legal liability or responsibility for the accuracy,

f f fcompleteness, or usefulness of any information, apparatus, product, or process disclosed, orrepresents that its use would not infringe privately owned rights. Reference herein to anyspecific commercial product, process, or service by trade name, trademark, manufacturer, orotherwise does not necessarily constitute or imply its endorsement, recommendation, orf i b h U i d S G h f Th i d i i ffavoring by the United States Government or any agency thereof. The views and opinions ofauthors expressed herein do not necessarily state or reflect those of the United StatesGovernment or any agency thereof.

2

Page 3: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

Presentation OutlinePresentation Outline• Anthropogenic Test Introduction

• Project Discussion1. Assuring Safe Injection

2. Permitting

3. Research 

4. CO2 Capture, Transportation and Storage Integration

• Next StepsNext Steps

3

Page 4: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

SECARB’s Phase III Anthropogenic TestSECARB’s Phase III Anthropogenic TestSECARB s Phase III Anthropogenic TestSECARB s Phase III Anthropogenic TestWashington

CountyTh CO t it t Al b P ’

Project Schedule and MilestonesProject Schedule and MilestonesThe CO2 capture unit at Alabama Power’s(Southern Co.) Plant Barry becameoperational in 3Q 2011.

A newly built 12 mile CO pipeline from

Citronelle Dome

CO2 Injection Site

ama

sippi

CO2 Pipeline

A newly built 12 mile CO2 pipeline fromPlant Barry to the Citronelle Domecompleted in 4Q 2011.

A characterization well was drilled in 1Q

Alab

a

Miss

iss

Mobile County

2 p A characterization well was drilled in 1Q2011 to confirmed geology.

Injection wells were drilled in 4Q 2011.

Plant Barry

100 to 300 thousand metric tons of CO2 willbe injected into a saline formation over 2 to3 years beginning in 1Q 2012.

4

Mobile3 years of post-injection monitoring.

Page 5: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

Anthropogenic Test Goals and ObjectivesAnthropogenic Test Goals and Objectivesp g jp g j1. Support a fully integrated, commercial prototype CCS

j t ( t t t d t )project (capture, transport and storage)2. Test CO2 flow, trapping and storage mechanisms of a

regionally extensive Gulf Coast saline formationregionally extensive Gulf Coast saline formation.3. Test the adaptation of commercially available oil field

tools and techniques for monitoring CO2 storage2

4. Document the permitting process for all aspects of aCCS project

5. Understand the coordination required to successfullyintegrate all components of a CCS project

5

Page 6: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

1.1. Assuring Safety:Assuring Safety:Start with a Good Storage SiteStart with a Good Storage Site

• Proven four‐way closure at Citronelle D

Start with a Good Storage SiteStart with a Good Storage Site

Dome.• Injection site located within Citronelle oilfield where existing well logs are availableavailable

• Deep injection interval (Paluxy Fm at 9,400 feet)

• Numerous confining units g• Base of USDWs ~1,400 feet• Existing wells cemented through primary confining unit

• No evidence of faulting or fracturing, based on oilfield experience, new geologic mapping and reinterpretation of 

l

6

existing 2D seismic lines.

Page 7: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

1.1. Assuring Safety: Characterize The Geology, Assuring Safety: Characterize The Geology, Th Ch t i A i !Th Ch t i A i !

• Analysis of over 80 existing oilfield well logs for porosityBaseline (pre-drilling) reservoir characterization:

Then Characterize Again!Then Characterize Again!

• Analysis of over 80 existing oilfield well logs for porosity, thickness and depositional style.

• Sand mapping to determine “open” or “closed” sand units.

• Paluxy porosity ~19% and perm ~100 millidarcies

We collected new geologic data with the drilling of the project’s characterization well, the D9-8 #2:

Wh l (98 f t i t i t l ) l 45 id ll•Whole core (98 feet in two intervals) plus 45 sidewall cores.

•Full set of logs (quad combo, MRI, elemental capture

7

spectroscopy, waveform sonic, CBL, etc.).

Page 8: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

1. Assuring Safety 1. Assuring Safety –– PaluxyPaluxy Looks Like a Good Looks Like a Good Injection TargetInjection Target

9350

Porosity Range: 6-18%Permeability Range: 1 – 50 md

Porosity Average: 13 %

9400

Porosity Average: 13 %Permeability Average: 8 md

Porosity Range: 6-23%Permeability Range: 1 3 800 md9400 Permeability Range: 1 – 3,800 md

Porosity Average: 18%Permeability Average: 440 md

9450 Porosity Range: 8-22%Permeability Range: 1 – 1,900 md

Porosity Average: 18%

9500

o os ty e age 8%Permeability Average: 500 md

Medium to coarse grained sandstones of

9550

the upper Paluxy appear to represent excellent CO2 injection targets

8

Page 9: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

1. Assuring Safety 1. Assuring Safety –– Reservoir Simulation to Reservoir Simulation to Guide Injection DesignGuide Injection Design

Building the Geologic ModelCO2 Injector (Well D9-7#2)

Guide Injection DesignGuide Injection Design

Based on detailed characterizationof the Paluxy sand/shale interval,we selected 10 of the sand units for

(Well D9 7#2)

• 170 net feet of “clean” sand

CO2 injection:

• Average porosity of 19%

• Average permeability of 100md

• Normal pressure and temperature p pgradients

9

Page 10: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

1. Assuring Safety 1. Assuring Safety –– Reservoir Simulation to Reservoir Simulation to Guide Injection DesignGuide Injection Design

CO2 Plume Extent 10 yrs after End of Injection

• Inject at maximum injection rate during for three years (500

Guide Injection DesignGuide Injection Design

y j during for three years (500 tonnes per day).

• Plume area in topmost sand is 9460

p0.35mi2 (225 acres)

• Most of the CO2 enters the P l d d t

CO2 Saturation (v/v) 9520

upper Paluxy sands due to higher permeability and injection gradient9540

9570

9710

9740

9800

9900 These results are used to design injection (well design,

l ti

10

98009970

completion program, monitoring program)

Page 11: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

1. Assuring Safety 1. Assuring Safety –– Use Tried and True Use Tried and True Monitoring ToolsMonitoring Tools

D-4-13 and/or D-4-14In-zone monitoringAbove-zone monitoring

Monitoring ToolsMonitoring Tools

Fluid sampling

Primary Injector (D-9-7#2)Injection surveysPressure

Characterization Well (D-9-8#2)Neutron loggingPressureFluid samplingS i iPressure

SeismicGroundwater

SeismicDistributed Temperature

VSP and Crosswell Seismic

Backup Injector(D-9-9#2)Neutron loggingSeismic

D-9-11Neutron Logging

GroundwaterModel Plume Extent

11

Page 12: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

1.1. Assuring Safety Assuring Safety –– Transportation Transportation (Human Health and Safety)(Human Health and Safety)(Human Health and Safety)(Human Health and Safety)

• Approx. 12 mi to the Injection Site• Right-of-Way• Right-of-Way

– Utility corridor for80%; 9 land owners

• Pipe specifications

CitronelleSE Unit

Pipe specifications– 4-in pipe diameter– X70 carbon steel– DOT 29 CFR 195

PlantBarry

PipelineRoute

Citronelle Unit Detail

DOT 29 CFR 195liquid pipeline; buried 3 feet withsurface vegetationmaintenance

Barry

maintenance– 19 directional drills – Purity is 99.7% dry

CO2 at 115ºF 1 500 psig

12

CO2 at 115 F, 1,500 psig

Page 13: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

1.1. Assuring Safety Assuring Safety –– Transportation Transportation (Gopher Tortoise Health)(Gopher Tortoise Health)(Gopher Tortoise Health)(Gopher Tortoise Health)

• Threatened species (Gopher Tortoise) and their burrowscommon on ROW

• Over 100 burrows located along the 12 mile ROW• Directional drilling under large colonies• Wire backed fencing (i.e. “tortoise fencing”) between pipeline and burrows on ROW edgepipeline and burrows on ROW edge• Re-location of all turtles would have cost $ 2MM!

13

Page 14: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

2 Permitting2 Permitting (This Stuff Takes a While)(This Stuff Takes a While)2.  Permitting 2.  Permitting (This Stuff Takes a While)(This Stuff Takes a While)

• Alabama Department of Environmental Management (ADEM) Air Permit• Capture unit operationp p

• Army Corps of Engineers permit – Wetlands Impacts• Covers wetland impacts due to pipeline and injection site construction• Pipeline crosses 15 acres of wetlands• Pipeline crosses 15 acres of wetlands• Horizontal drilling under wetlands is preferred over “open-cutting” and

mitigation• Wetland impacts during well pad construction operations (fill) mitigated

after well drilling completed

• U.S. Fish and Wildlife permit – Threatened and Endangered Species• Potential impacts to threatened species (gopher tortoises)Potential impacts to threatened species (gopher tortoises)• Over 30 gopher tortoise burrows encountered along pipeline easement• Directional drilling under tortoise burrows/colonies is preferred over

temporary relocation

14

Page 15: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

2.  Permitting2.  Permittinggg• SHPO (State Cultural/Archaeological Assets)

• ADEM Underground Injection Control (UIC) Permit – Protect UndergroundSources of Drinking Water (USDWs)

• A Class V Experimental Well permit was sought for the following reasons– Short duration of injection (3 years)– Modest volumes of CO2 (less than 2% of Plant Barry’s annual CO2

output)output)– Characterization and modeling of “stacked” CO2 storage – CO2 Injection Under “Real World” Conditions – Demonstration of innovative monitoring tools and methods

15

Page 16: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

2 Permitting2 Permitting2.  Permitting2.  PermittingAfter comments by EPA, most Class VI (CO2 sequestration well) standards

were appliedpp– Injection Area of Review (AOR) determined by annual modeling– Periodic AOR updates based on monitoring and modeling results– Extensive deep, shallow and surface CO2 monitoring

Monthly reporting of injection pressures annular pressures and– Monthly reporting of injection pressures, annular pressures and injection stream composition

– Injection stream monitoring– Periodically updated Corrective Action Plan – Open-ended permit duration (based on USDW non-endangerment

demonstration)– Pressurized annulus throughout injection– Emergency and remedial response planEmergency and remedial response plan– Post-injection site care plan

Class V Experimental injection permit was awarded in November 2011, 11 months after initial draft application

16

Page 17: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

3. CO3. CO22 Storage ResearchStorage ResearchWe have been opportunistic about adding“experimental” aspects to the test

22 ggMBM Flat Pack

experimental aspects to the test.

•Modular Borehole Monitoring (Carbon Capture Project) - Sensor platform for acquiring multiple measurements using one deployment completion

•Comparison of Groundwater Sampling Methodologies - Deploy different methods (e.g., u- MBM Geophone Clampg p y ( gtube, gas-lift, pumping and wireline sampling) to evaluate impact on groundwater quality results

•Reservoir Dynamics and Formation Saturation -

MBM Geophone Clamp

Reservoir Dynamics and Formation Saturationin-zone tracer tests and fluid sampling to assess changes in inter-well formation saturation, sweep efficiency changes in the geochemistry of formation fluidsfluids

17

Page 18: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

3.  Research 3.  Research ––COCO Capture and CompressionCapture and CompressionCOCO22 Capture and CompressionCapture and Compression

• Scope: Demonstrate 25 MW equivalent post-combustion capture of CO2 from Plant Barry flue gas using MHI’s advanced amine (KS-1 solvent) process

• Objectives:

– Demonstrate integrated CO2 capture under realistic coal-fired plant operating conditions

– Economics: Establish realistic values for the energy penalty and implementation costs

– Test reliability of solvent-based capturey p

• Status:

– Engineering and procurement completed in July 2010

Fi t hi t t Pl t B i S t b 2010– First shipment to Plant Barry in September 2010

– Capture unit reached full operational capacity in June 2011

• Capture rates of up to 650 metric tonnes per day

• Over 40,000 metric tonnes captured to date

18

Page 19: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

3.  Research 3.  Research ––COCO Capture and CompressionCapture and CompressionCOCO22 Capture and CompressionCapture and Compression

19

See Mike Ivey’s presentation at 3:30 on See Mike Ivey’s presentation at 3:30 on Thursday for more detailsThursday for more details

Page 20: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

4. Integration 4. Integration –– Communication is Key!Communication is Key!Storage

C tDOE

SO. STATES ENERGY BOARDTransportCapture

Permitting Plant Integration& Construction

SiteHost

Mitsubishi Heavy

Advanced ResourcesInternational

yIndustries

Design TechnologyProvider

AdvancedAmines

NEPA Preparation

MMAActivities

FieldOperations

ReservoirModeling

Publiceducation/outreach

UICPermitting

GeologicModeling

DenburyResources

DenburyResources

Site Prep/DrillingContractors

FieldOperations

SiteHost

Resources

PipelinePermitting &Construction

FieldOperations

PipelineDesign

EconomicEvaluation

KnowledgeTransfer

3rd PartyEvaluation

20

Page 21: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

4. Integrated Test Plan4. Integrated Test Plan4.  Integrated Test Plan4.  Integrated Test Plan• Numerous parametric tests on capture unit

• Variations in flue gas processing volume (variations to occur over a matter of hours, ranging from 40% to 100% capacity

• Operational constraints on transport and storage• Dynamic transportation operations due to variations in capture unit PVT

outputoutput • Active management of pipeline and pump operations to maintain liquid

phase•Effects of periodic capture unit downtime on transportation and storage operations

•Minimize CO2 residency in transport and injection juncturestransport and injection junctures•Opportunity for safety inspections•Collection of pressure transient

21

data in the project injection and observation wells

Page 22: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

4. Integration4. Integration –– Risk AssessmentRisk Assessment4.  Integration 4.  Integration  Risk AssessmentRisk Assessment• We are participating with DNV in incorporating our test site procedures into a “risk

registry” g y• We are documenting our risk mitigation procedures for all aspect of test including

site construction, integrated transport and injection operations and closure.• Completed a registry of potential risks, consequence severity, likelihood ofCompleted a registry of potential risks, consequence severity, likelihood of

occurrence and safeguards for mitigation

See Jerry Hill’s presentation at 11:30 (#151144) on Thursday for more details

22

Page 23: The SECARB Anthropogenic Test: The First U.S. Integrated ... · The SECARB Anthropogenic Test: The First U.S. Integrated CO 2 Capture, Transportation and Storage Test George Koperna,

Next StepsNext StepsNext StepsNext Steps• Complete baseline monitoring in February 2012

• Permission to inject anticipated in March 2012

• CO2 injection operations begin in March 2012, continue for 1 to 2 years

3+ years of post injection monitoring then close site

A th i T t 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017Fiscal Year

• 3+ years of post-injection monitoring, then close site

Anthropogenic Test 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017Public Outreach & EducationSite PermittingSite Characterization and ModelingWell Drilling and Completiong pTransportation and Injection OperationsOperational Monitoring and ModelingSite ClosurePost Injection Monitoring and ModelingProject AssessmentProject Assessment

23


Recommended