The Seven Legal & Business Issues Unique to Design-Build
By:
Mark C. FriedlanderPartner
Schiff Hardin LLPConstruction Law Group
Definition of Design-Build
• Design Professional and Contractor are “on the same team.”
• Fallacy: NOT a single contract for both design and construction
• Design-Build may involve multiple “back-to-back” contracts comprising a complete project
2
Seven Legal Issues Unique to Design-Build• Relationship of the parties• Standard of care of design work• Availability of performance warranties• Entitlement to change orders• Unique licensing problems• Unique insurance/bonding problems• Unique problems with competitive bidding
laws3
Seven Legal Issues Unique to Design-Build• Relationship of the parties• Standard of care of design work• Availability of performance warranties• Entitlement to change orders• Unique licensing problems• Unique insurance/bonding problems• Unique problems with competitive bidding
laws4
Types of Design-Build Relationships
• Integrated Company• Contractor Prime, Engineer Sub• Engineer Prime, Contractor Sub• Engineer Prime, Multiple Trade Subs• Design-Builder Prime, Engineer and
Contractor each Subs• Joint Business Venture by Engineer and
Contractor
5
Issues for Design-Build Teaming AgreementsI. Structure of the Team.
A. Structure of the Business Relationship1. One party prime, and the other as subcontractor2. Joint business venture:
a. Legal structure of venture: joint venture (partnership), corporation, limited liability company
b. Organization and control of the joint business venturec. Capitalization and financial issues
3. Lines of Communication
6
Issues for Teaming Agreements (Cont’d)
II. Sharing of Risks and RewardsA. Compensation
1. Amount2. Timing of payment3. Conditions
B. Project Profits and Losses1. Allocation of savings if project exceeds goals2. Allocation of losses if project fails to meet goals
C. Other Risks and Rewards1. Identify and describe each2. Allocate consequences between the parties
7
Issues for Teaming Agreements (Cont’d)
III. Design Phase Services (that may be different from traditional projects)
A. Services Provided by the Contractor1. Costing, estimating2. Value engineering3. Assistance in analyzing owner-provided information4. Constructability analysis5. Preliminary scheduling6. Checking design to anticipate problems7. Acquisition of long-lead items8. Procuring subcontractor participation and quotes9. Negotiation with subcontractors/vendors
8
Issues for Teaming Agreements (Cont’d)
B. Services Provided by the Engineer1. System-by-system design, with “looping” feedback from
trade contractors2. Informal communications rather than “defensive detailing”3. Greater (lesser) number of alternative designs4. MEP design only schematic, completed by trade
contractors5. Acceptance of greater-than-usual price constraints6. Out-of-sequence provision of design details7. Heavier reliance on performance specifications
9
Issues for Teaming Agreements (Cont’d)
IV. Construction Phase Services (that may be different from traditional projects)
A. By the Contractor1. Anticipation and avoiding or minimizing the consequences of
design problems2. Fast-tracking the construction
B. By the Engineer1. Informal provision of supplemental design information2. Cooperative approval of substitutions3. Cooperative trouble-shooting and problem-solving
10
Issues for Teaming Agreements (Cont’d)
V. Protective Business ProvisionsA. Confidentiality of InformationB. Exclusive Relationships or Agreements Not To
CompeteC. Future Marketing/Sales Efforts
1. Responsibility of each party2. Provisions regarding mutual commitment,
exclusivity
11
Issues for Teaming Agreements (Cont’d)
VI. Risk TransferenceA. Insurance Provisions
1. Coverage to be procured by each party, including limits, terms, etc.
2. Allocation of cost of insurance
B. Surety Bonds (if any)1. Description of bonds to be procured, by whom, terms,
etc.2. Provisions for allocating cost of bonds
12
Issues for Teaming Agreements (Cont’d)
C. Indemnity Provisions1. Engineer to indemnify contractor for claims
arising out of breaches of Engineer’s duties2. Contractor to indemnify Engineer for claims
arising out of breaches of Contractor’s duties3. Provisions for cooperative defense or splitting
costs of claims common to both parties4. Provisions for indemnification by others
13
Issues for Teaming Agreements (Cont’d)
VII. Dispute ResolutionA. Commencement of the Dispute Resolution Process
1. For claims initiated by or involving third parties, dispute process not to begin until third party aspects of claim are resolved
2. Provision tolling statute of limitations for claims involving third parties
B. Sequence of Dispute Resolution Actions1. Step negotiations between senior management2. Non-binding mediation3. Binding arbitration (or court litigation)
14
Seven Legal Issues Unique to Design-Build• Relationship of the parties• Standard of care of design work• Availability of performance warranties• Entitlement to change orders• Unique licensing problems• Unique insurance/bonding problems• Unique problems with competitive bidding
laws
15
Problem of the Flow-Down Warranty• Design-Builder typically warrants results to
Owner• But A/E’s are only held to a “standard of
care”• Design Professionals’ warranties are not
insurable• Design-Builder has narrow “window of
liability” that can’t be passed downstream
16
Seven Legal Issues Unique to Design-Build• Relationship of the parties• Standard of care of design work• Availability of performance warranties• Entitlement to change orders• Unique licensing problems• Unique insurance/bonding problems• Unique problems with competitive bidding
laws
17
Central Illinois Tire Processing Facility: Financeable Only Via Design-Build• Burning tires yield “carbon black” plus energy• Construction to be financed by sale of municipal bonds• Bond underwriter required engineer or contractor to
guarantee performance– Contract would quantify $ value of shortfall in kilowatt hours– Performance shortfall would be assessed as liquidated damages
• Neither Engineer nor Contractor could warrant performance because problem might be within the other’s scope
• Design-Build team could warrant performance because design, procurement and construction all within scope
18
New Jersey Wastewater Treatment Facility: Exception to Full Scope• Turnkey contract using patented process to clean
wastewater and produce fertilizer• Facility failed: liquids solidified and “gummed up”
mechanical machinery• Municipality sued design-builder since design, process,
procurement and construction all within its scope• But the cause of problem was that the average size of
particulate matter in wastewater significantly exceeded contractual feedstock parameters
• Owner was contractually responsible for feedstock
19
Seven Legal Issues Unique to Design-Build• Relationship of the parties• Standard of care of design work• Availability of performance warranties• Entitlement to change orders• Unique licensing problems• Unique insurance/bonding problems• Unique problems with competitive bidding
laws
20
Three Kinds of Change Orders
StandardConstruction
Design-Build
Scope Changes:- By Owner- By Municipality
√√
√Possibly
Surprises:- Force Majeure Events- Concealed Conditions
√√
√Possibly
Design Errors or Omissions √ No
21
Seven Legal Issues Unique to Design-Build• Relationship of the parties• Standard of care of design work• Availability of performance warranties• Entitlement to change orders• Unique licensing problems• Unique insurance/bonding problems• Unique problems with competitive bidding
laws
22
Licensing Issues• Licensing is a state function; rules are
different in each state• Design-Builder typically must have a design
professional license and a contractor’s license
• Laws and regulations often permit Design-Builder to subcontract to (or employ) licensed individuals/companies
23
Seven Legal Issues Unique to Design-Build• Relationship of the parties• Standard of care of design work• Availability of performance warranties• Entitlement to change orders• Unique licensing problems• Unique insurance/bonding problems• Unique problems with competitive bidding
laws
24
Insurance/Bonding Problems Largely Resolved
• Design-Builder wants to insure professional liability risks– Can rely on Engineer’s E&O policy plus indemnity– Contractors can now purchase their own E&O
insurance• Performance bonds have evolved to include
professional obligations in design-builder’s scope if design professional is properly insured
25
Seven Legal Issues Unique to Design-Build• Relationship of the parties• Standard of care of design work• Availability of performance warranties• Entitlement to change orders• Unique licensing problems• Unique insurance/bonding problems• Unique problems with competitive bidding
laws
26
Issues With Competitive Bidding
• Design-Build generally is not compatible with competitive bidding– Often the trades and vendors can be competitively bid– Exception: competitive proposals, but “apples & oranges”
• Problems with competitive proposals– Engineer’s contribution to proposal is disproportionate– Rarely any (or sufficient) stipend for unsuccessful proposals– Sparkman problem: too many proposing teams– Solution: shortlist based on qualifications
27
For More Information Contact:Mark C. Friedlander
Schiff Hardin LLP233 South Wacker Drive
Suite 6600Chicago, Illinois 60606
(312) 258-5546/Fax: (312) [email protected]
http://www.schiffhardin.com/design-build/
28