PJOE Page 1 of 22 Experience PJOE yard 17 th May, 2016 From the start of the yard in May 2006 following projects have been realized: Client Project Description incl weight and year CNOOC Le Dong 15-1 and 22-1, South China Sea, China Launch jackets, 5,630/5,520T, 107/95m wd, piles and conductors, 4,880T 2007 CNOOC Wenchang 8-3A and 19- 1B, South China Sea, China Lift jackets, 2,930/3,160T, 113/126m wd, 2007 CNOOC JZ 9-3 WHPE, Bohai Bay, China Riser platform, suction foundation, 195T, 18m wd, 2007 APL Northeast Gateway, GoM, USA Suction anchors and PLEM structures, 1,524T, 2007 APL Maari, New Zealand Suction anchors, 580T, 2007 APL Vincent, Australia Midline Buoy Elements, 220T, 2007
Transcript
Page 1: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 1 of 22

Experience PJOE yard 17th May, 2016 From the start of the yard in May 2006 following projects have been realized: Client

Project Description incl weight and year

CNOOC Le Dong 15-1

and 22-1, South China Sea, China

Launch jackets, 5,630/5,520T, 107/95m wd, piles and conductors, 4,880T 2007

CNOOC Wenchang

8-3A and 19-1B, South China Sea, China

Lift jackets, 2,930/3,160T, 113/126m wd, 2007

CNOOC JZ 9-3

WHPE, Bohai Bay, China

Riser platform, suction foundation, 195T, 18m wd, 2007

APL Northeast

Gateway, GoM, USA

Suction anchors and PLEM structures, 1,524T, 2007

APL Maari, New

Zealand Suction anchors, 580T, 2007

APL Vincent,

Australia Midline Buoy Elements, 220T, 2007

Page 2: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 2 of 22

Client

Project Description incl weight and year

ROC Oil Zhao Dong

phase 2, Bohai Bay, China

EPIC for UDP wellhead and terminal foundation incl. pile guide bridge, 1,000T, IDP for OPA flare, ODB and OPB foundation incl. pile guide bridge, 3,500T including installation scope, 2007 and 2008.

APL Reliance D6

Krishna-Godavari, India

Suction anchors and Midline Buoy Elements (MLBE), 1,895T, 2007

CNOOC Bozhong,

Bonan, Jinzhou , Jinxian, Jinzhou, LvDa and Suizhong fields, Bohai Bay, China

Fabrication of jackets, piles and conductors for 20 platforms, 63,000 Ton total, 2008 and 2009

Bluewater Talimsan

Bunga Kekwa ETMS, Malaysia

External Turret Mooring System, 1,100T, 2008

Frigstad Frigstad Oslo

SSDR bracings

Fabrication of 4 pontoon bracings for Yantai Raffles yard, 800T, 2008

Hydralift/ AmClyde

Nor Offshore M60 Offshore Crane

Offshore crane, model M60, 640T plus 980T counter weight, 2008

Page 3: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 3 of 22

Client

Project Description incl weight and year

Awilco WilPioneer

SSDR sponsoon tanks

Fabrication of sponsoon blocks for Yantai Raffles yard, 1,200T

Aker Solutions/ Modec

Cidade de Santos FPSO, Brazil

Fabrication of the SRU module, 210T, 2009

APL Neptune

DWPP, suction anchors and subsea PLEM, USA

2 PLEM structures and 16 suction anchors, 1,160T, 2009, 186T, 2009

APL Chinook and

Cascade, suction anchors and MLBE’s, GOM USA

Fabrication of 12 mid line buoy elements and 11 suction anchors, 1,460T, 2009 740T, 2009

CNOOC Bozhong

field, Bohai Bay, China

Yoke Mooring System, refurbishment, 300T, 2008

Saipem Overhead

cranes assembly for CastorONE

Assembly and completion of cargo hold overhead cranes from Navalimpianti, 2009

Page 4: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 4 of 22

Client

Project Description incl weight and year

GustoMSC Aramco ARB-

3 jack-up, 550 T crane, Saudi Arabia

Fabrication of tub, column and boom, 500T total with 690 material, 2009

Bluewater CALM buoys

07 and 08 CALM buoys, combined 500T, 2008

Aker Solutions/ Modec

Cidade de Santos FPSO, Brazil

Fabrication of the MEG module, 630T, 2009

Hydralift/ AmClyde

Swiber M60 Offshore Crane

Offshore crane, model M60, 640T, 2009

Page 5: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 5 of 22

Client

Project Description incl weight and year

Hydralift/ AmClyde

Global PC-37 Offshore Mast Cranes Global 1200

Offshore crane, model PC-37, 1,400T, 2009

Hydralift/ AmClyde

GSP Bigfoot 1, KP-87 King Post crane

Offshore crane, model KP-87, 400T, 2009

CNOOC JZ25-1S LQ,

Bohai Bay, China

55 persons LQ incl helideck., 480T, 2009

Swiber LDB Swiber

Chai vessel Part engineering, fabrication of tub, counter weight, stinger, boom rest and installation of M60 AmClyde crane and engine room, 1,500T, 2009

Aker Solutions

Tupi SRU modules, Brazil

Exotic piping for Tupi modules, 150 kg, 2009.

Page 6: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 6 of 22

Client

Project Description incl weight and year

CNOOC Bozhong BZ

34-1N WHPC deck, Bohai Bay, China

Final commissioning and completion work, 2,500T, 2009

Saipem Completion

work on Pipe joint Hatches CastorONE

Assembly and completion of pipe joint cargo holds hatches from Navalimpianti, 2009

Hyundai Moon

Heat exchangers assembly for power plant Bahrain

Providing of facilities and assistance for heat exchanger assembly, 20, 300T each, 2009

CNOOC Jin Zhou

FPSO, Bohai Bay, China

Refurbishment of yoke turret system including swivel, 2010

Hydralift AmClyde

M52 crane for Bumi Armada

Offshore crane model M52 suitable for Caspian Sea transport, 410T, 2010

Conoco Phillips

Penglai helicopter base, China

Aluminum helicopter maintenance platform, 3T, 2010

Page 7: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 7 of 22

Client

Project Description incl weight and year

CITIC Pacific Mining

Cape Preston Iron Ore project, Desalination Plant, Australia

Part design, bulk procurement and fabrication of a desalination plant, total weight 23,000T. Scope included: 2 x Reverse Osmosis modules, 2 x 2,645T, 2 x Pump modules, 787T and 1,013T, Pre-treatment modules 2,780T and 2,890T, pipe racks and supports, total 600T, E-Houses, 780T, 50T and 54T, control room, 185T, equipment skids, up to 1,270T total, In-take caisson 4,340T, marine harbour caissons and dolphins 2,100T, Brine Tank out fall structure 560T, 7,600T pre-cast elements, 2009/2010

CNOOC Spooling

Reels Fabrication of 2 cable reels, 35T each, 2009

Hydralift/ AmClyde

Global PC-37 Offshore Mast Cranes Global 1201

Offshore crane, model PC-37, 1,200T capacity, 1,400T, 2010

Page 8: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 8 of 22

Client

Project Description incl weight and year

Hydralift AmClyde

PC-37 crane for Saipem FDS II

Offshore crane model PC-37 1,000T capacity for Saipem, 720T, 2010

COSL (ex Awilco)

WilPromoter lower hull semi-submersible construction

Construction and outfitting of hull, 8,500T total, Includes 8,000T steel, 410T piping, 47,000 m cables, 185 pcs of equipment, 2010

Bluewater STX FSO

project, ETMS

Fabrication of External Turret Mooring System, 750T, 2011

Hyundai Moon

Sabiya HRSG power plant, Kuwait,

Assembly and part fabrication of 92 heat exchanger modules including load-out, ~ 400T/each, 2010.

COSCO Nantong

ATP Cheviot Octobuoy floater, UK North Sea,

Fabrication and installation at shipyard of the Conductor Support structure, 2,900T, 2011

Page 9: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 9 of 22

Client

Project Description incl weight and year

CNOOC WeiZhou 11-

1 platform extension, South China Sea, China

Fabrication of jacket frame, piles, conductors and deck, 1,200T, wd 20 m, 2011

Sofec Oil Search,

Papua New Guinea LNG

Fabrication of 380T CALM buoy and PLEM for export, 2011.

EMAS Offshore

Oil Search, Kumul terminal, Papua New Guinea

Fabrication of installation aids, 87 T plus load-out and seafastening of CALM buoy system, 2011

Sofec CCCL Edac

Energy, Nagarjuna, India

Fabrication of 387T CALM buoy and PLEM for export, 2011.

Sofec IHI for

Chevron, Erawan FSO turret, Thailand

Fabrication of External Turret Mooring System, 677T, 2011

Page 10: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 10 of 22

Client

Project Description incl weight and year

Hyundai Moon

Power plant, Saudi Arabia

Assembly and part fabrication of 62 heat exchanger modules including load-out, ~ 300T/each, 2011

NOED Bohai Bay

offshore windmill test project, P R of China

Fabrication of 2 monopod foundations, 2011

GustoMSC Seajacks

Zaratan jack-up plfm, 800 ton crane

Fabrication of Leg Crane, 866T, 2011

GustoMSC A2SEA Sea

Installer jack-up plfm, 800 ton crane

Fabrication of Leg Crane, 866T, 2012

CNOOC Panyu 4-1 &

5-2, South China Sea, China

EPC fabrication of two 100 men living quarters, 1,175T each, 2012

Page 11: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 11 of 22

Client

Project Description incl weight and year

Karara Mining Ltd

Karara Iron Ore Mine, EPCM Worley Parsons, West Australia

Fabrication of chute platework for inland assembly including installation of liners, 1,315T, 2012

CNOOC Hai Yang Shi

You 161 Jack-Up, P R of China

Platform modifications and leg repair of jack-up, 2012.

COSCO Nantong

ATP, Cheviot filed, Octobuoy topsides

Rolling of tubulars for deck structure, 1,255T, 2012

Sofec Tesoro

Hawaii, USA Fabrication of CALM buoy, 210T, 2012.

Sofec CNOOC,

LuFeng field, P R of China

Fabrication of spider buoy, 290T, 2012.

Page 12: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 12 of 22

Client

Project Description incl weight and year

Heerema ExxonMobil

Arkutun-Dagi field, Sakhalin, Russia

Fabrication of spools, protection sections and miscellaneous structures, 400T total, 2012

BP BP, Jacobs

Engineering EPCM, Bulwer Refinery, Brisbane, Australia

Fabrication of Hydroisom & HF Alkylation modules, 550T, 2012

Sandvik Rio Tinto,

Hope Down, two Stackers and one reclaimer, Australia

Fabrication, final assembly and disassembly of two stackers, 590T/each and one reclaimer 1,530T, 2012

CNOOC SZ 36-1

WHPM, WHPC & WHPN, Bohai Bay, China

Fabrication of 3 jackets, piles and conductors, WHPM 6 pile 4,240T, WHPC 4 pile 1,670T, WHPN 4 pile 3,220T, 2012

Sandvik Rio Tinto,

Cape Lambert port B, Ship Loader 11, Australia

Fabrication, final assembly and disassembly of ship-loader, 1,060T, 2013

Page 13: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 13 of 22

Client

Project Description incl weight and year

Sofec Petrobra’s,

Tanker Pacific, UOTE FSO turret, Brazil

Fabrication of turret, ~ 1,200T, 2013

BMA (BHP Billiton & Mitsubishi Alliance)

Hay Point Expansion Stage 3, Australia

Procurement, fabrication and assembly of 7 Surge Bins and Transfer Tower modules, 6,600T and fabrication of 212T chutes platework, 2012 & 2013

CNOOC Panyu 34-1,

South China Sea, China

Fabrication of 220m long jacket and piles, 23,000T jacket, 10,500T piles, 2013

BMA (BHP Billiton & Mitsubishi Alliance)

Hay Point Expansion Stage 3, Australia

Procurement, fabrication and assembly of 262 Conveyor Gallery Modules, ~ 9,500T and fabrication of 176T welded frames for conveyor galleries drives, 2012 & 2013.

Page 14: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 14 of 22

Client

Project Description incl weight and year

SBM Offshore

FPSO Cidade de Ilhabela, Petrobra’s, Brazil

Fabrication and assembly of 24 Chain Connectors, 670T, 2013

Sofec OGX, OSX 3

FPSO, Brazil Fabrication of 515T 12 plus 1 mooring piles, 2013

CNOOC Huang Yan

WHPA, East China Sea, CanXue Oilfield, China

EPC for 4 leg jacket (3,100T) and piles (2,200T), waterdepth 108m, 2013

Sandvik, Brazil

Samarco, Brazil

Fabrication of shiploader, 1,325T, 2013

Schneider Electric

Sandvik Sacomar shiploader and reclaimer, Angola

Fabrication and part supply for 2 E-Houses, 35T, 2013

NOV APL Goliat FPSO

Project Fabrication of Goliat FPSO parts, 6.7T, 2013

Page 15: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 15 of 22

Client

Project Description incl weight and year

Sofec Hoegh LNG

Lampung, Indonesia

Fabrication of Soft Yoke Mooring System, 2,137T, MSS 2013 and platform, 2014

CNOOC EnPing 24-2

development, China

Fabrication of jacket (8,900T) and piles (6,600T), water depth 100m, 2014

CNOOC Bao Yun Ting

Process Platform, East China Sea, HuangYan Gas Development, China

EPC for 4 leg jacket (3,160T) and piles (2,610T), water depth 77m, 2014

CNOOC Tuan Jie Ting

TJT WHP, East China Sea, Pingbei HuangYan gas field, China

Fabrication of 4 leg jacket (2,600T) and piles (2,600T), water depth 80m, 2014

Page 16: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 16 of 22

Client

Project Description incl weight and year

Sandvik South Africa

Sacomar, Angola

Fabrication of shiploader, 1,000T, and reclaimer, 400T, 2014

Sofec Petronas,

FLNG1 turret, South China Sea, Malaysia

Fabrication of ETMS, 550T, 2014

NOV APL CNOOC

Enping STP internal turret, China

Fabrication of STP submerged internal turret, 235T, 2014

CNOOC Shao Xing

SHX 36-5 WHP, East China Sea, Pingbei HuangYan gas field, China

Fabrication of 4 leg jacket (2,690T) and piles (2,560T), waterdepth 82m, 2014

Page 17: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 17 of 22

Client

Project Description incl weight and year

NOV APL Anadarko,

CFD-11, Bohai Bay, China

Yoke Mooring and Torque Tower fabrication, 260T, 2014

NOV AmClyde

NOV Brazil, flexible production plant, yard quay side crane, Brazil

Fabrication of crane, pedestal and boom for 380 Ton onshore yard crane, model LSB-22, 400T, delivery 2014

SBM Offshore

Petrobras Cidade de FPSOs Cidade de Maricá and Cidade de Saquarema.

Fabrication and outfitting of hawser and loading hose reels, 2 x 2, 353T, 2014

CIMC Raffles

Coastal Marine Sdn Bhd (Thaumas Marine) for Pemex Gas Compressor Jack-up, (hull H1296)

Fabrication of helideck, 200T, 2014

Page 18: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 18 of 22

Client

Project Description incl weight and year

Hyundai Yantai

Az-Zour North IWPP Project, Kuwait

Fabrication of heat exchanger casings, 880T, 2014

NOV Kristian- sand

Frigstad SSDV Alpha and Beta for worldwide service

Fabrication of two times 1,250T capacity dual hoisting drilling tower, 1,400T, 2014 and 2015

Fluor for Exxon-Mobil Neftegaz

Odoptu stage II, Sakhalin Island, Russia

Fabrication of pile caps and well cellars, 929T, 2014

CNOOC Ping Hu

SDPP, East China Sea, Pingbei HuangYan gas field, China

EPC 4 leg jacket (3,062T) and piles (2,317T), waterdepth 80m, 2015

CIMC Raffles

Central Offshore Monaco, Jack-up drill rigs, (hulls 273&1284), CIMC Jack-up drill rig, (hull 1293)

Fabrication of 10, 5 and 28 deck box blocks, 400T, 220T and 1,800T, 2015

Page 19: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 19 of 22

Client

Project Description incl weight and year

CIMC Raffles

Coastal Marine Sdn Bhd for Pemex, Gas Compressor Jack-up (hull H1296)

Fabrication of 4 legs and assembly in Longkou yard, total length 108 m each, ~ 650T, 2015

NOV APL for Bumi Armada and EnQuest

Kraken FPSO, UK sector North Sea

Fabrication of 12 piled anchors for STP turret. 1030T, 2015

NOV APL for Statoil

Mariner FPSO, UK sector North Sea

Fabrication of 12 piled anchors for SLT turret. 580T, 2015

Sofec for JGC

NSRP Refinery, Gulf of Tongking, Vietnam

Fabrication of CALM buoy, anchor piles and PLEM plus piles, total weight 358T, 2015

Fluor for Exxon-Mobil Neftegaz

Odoptu stage II, Sakhalin Island, Russia

Fabrication of pile caps, 20 plus 296T and 36 well cellars, 225T, delivery 2015

Page 20: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 20 of 22

Client

Project Description incl weight and year

CNOOC Kong Queting

WHPA, East China Sea, HuangYan gas field, China

Fabrication of 4 leg launch jacket (4,920T) and 8 piles (4,070T), water depth ~80m, 2015

CNOOC Huang Yan 2-

2 WHP-A, East China Sea, Pingbei HuangYan gas field, China

Fabrication at COOEC ZhuHai yard of deck structure for wellhead platform, 1,417T, 2015

EVT for Chevron

Wheatstone LNG storage tanks modules and pipe-racks, Australia

Fabrication of manifold modules and pipe-racks including cryogenic insulation, 1,800T, plus 2 pump columns, 50 m long, SS, 79T each, s015

YamGaz (Technip/ JGC/ Chiyoda jv) for Yamal LNG (Total E&P/ Novatek/ CNPC)

Yamal LNG development, Yamal peninsula, Siberia, Russia

Delivery of train 1, PAR001, 1,500T, 2015

Page 21: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 21 of 22

Client

Project Description incl weight and year

Huadian Heavy Industries Co., Ltd for China Power Investment Co.

Jiangsu Binhai North H1#1000MW OWF, Shandong, P.R. of China

Supply and fabrication of 6 mono-piles, 65-79m long, max 6.8m diam, total 4,000T. Delivery 2015

NOV AmClyde

ZPMC Yantai Salvage Derrick Barge

Fabrication of M78 crane boom, 700T. Delivery 2015

YamGaz (Technip/ JGC/ Chiyoda jv) for Yamal LNG (Total E&P/ Novatek/ CNPC)

Yamal LNG development, Yamal peninsula, Siberia, Russia

Delivery of train 1, PAR004, 2,600T, 2016

CNOOC

EnPing 18-1 development, China

Fabrication of jacket (8,200T) and piles (6,450T), Water depth 95m. Delivery 2016

Page 22: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 22 of 22

NOV AmClyde

Solstad SCV for Saipem

Fabrication of MSB-264RT DWE 900T pedestal, mast and boom, 646T in total with 345T EN-10025 S690QL1 material. Scope includes outfitting of complete crane. Delivery 2016

Fluor for Exxon-Mobil Neftegaz

Odoptu stage II, Sakhalin Island, Russia

Repeat order for fabrication of 70 pile cap plates, 197T, delivery 2016.

Page 23: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 1 of 2

Ongoing projects PJOE yard 17h May, 2016 The following projects are presently ongoing in the PJOE yard: Client

Project Description incl weight and year

CNOOC BoZhong 25

yoke mooring platform

Refurbishment of topsides, delivery expected in 2017. SOW to be advised

NOV AmClyde

ZPMC Yantai Salvage Derrick Barge

Fabrication of M78 crane deck, 2,030T in total with 865T EN-10025 S690QL1 material. Scope includes outfitting of deck. Delivery 2016

NOV AmClyde

Petrofac DLV 5000 installation vessel

Fabrication of M78 crane deck A-frame and boom, 3,240T in total with 1,426T EN 10025 S690QL1 material. Scope includes full outfitting. Delivery postponed, crane ready April 2016

YamGaz (Technip/ JGC/ Chiyoda jv) for Yamal LNG (Total E&P/ Novatek/ CNPC)

Yamal LNG development, Yamal peninsula, Siberia, Russia

Fabrication of package 3, 95,000T 33 pipe-rack modules for train 3 trains, maximum weight 5,700T, delivery up to 2017

Page 24: · PDF fileFrom the start of the yard in May 2006 following projects have been realized: ... cargo hold overhead cranes ... Guinea LNG Fabrication of 380T

PJOE

Page 2 of 2

Client

Project Description incl weight and year

Fjords Proces-sing /Petronas

FLNG2 LNG FPSO, Malaysia

Part procurement and fabrication of MRU module, ~ 1,000T, 2016

Fluor for Exxon-Mobil Neftegaz

Odoptu stage II, Sakhalin Island, Russia

Repeat order for fabrication of pile cap plates, 14T, delivery 2016.

Mitsubishi Heavy Industries

Caribbean Gas Chemical, Trinidad, TMD module project

Part procurement and fabrication of 58 modules including process, pipe-racks and utility modules, 12,500T, 2017

Black & Veatch

Golar Hilli for Perenco FLNG vessel, completion of 4 HRSG modules

Part procurement, completion and pre-commissioning of 4 HRSG modules, 370T/each, 2016