Baku, Azerbaijan, 20 October 2016 Central Asia Regional Consultation Meeting Jamil Malikov Deputy Chairman Opportunities and challenges for the development of the renewable energy in Azerbaijan The State Agency on Alternative and Renewable Energy Sources of the Republic of Azerbaijan
Transcript
Page 1: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

Baku, Azerbaijan, 20 October 2016

Central Asia Regional Consultation Meeting

Jamil MalikovDeputy Chairman

Opportunities and challenges for the development of the renewable energy in Azerbaijan

The State Agency on Alternative and Renewable Energy Sources of the Republic of Azerbaijan

Page 2: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

Current status of RE development in Azerbaijan

The State Program on Use of Alternative and Renewable Energy Sources in Azerbaijan Republic (2004);

Establishment of a regulatory State Agency on Alternative and Renewable Energy Sources;

Order of President of the Republic of Azerbaijan "On the development of the State Strategy on use of alternative and renewable energy sources in the Republic of Azerbaijan for 2012-2020”;

Order of President of the Republic of Azerbaijan “On the approval of “The main directions of the strategic roadmap for key sectors of the economy and national economy” and about subsequent issues;

Decree of President of the Republic of Azerbaijan on approval of “AZERBAIJAN 2020: LOOK INTO THE FUTURE” DEVELOPMENT CONCEPT.

Strategic support of developing RE:

Page 3: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

Current status of RE development in Azerbaijan

Existing legislation on RE:

On the use of energy resources (1996);

About Electric Energy (1998);

About Energy (1998) ;

About Electric and heat power plants (1999) ;

“On the use alternative and renewable energy sources” (draft);

About energy efficiency (draft).

Page 4: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

Current status of RE development in Azerbaijan

The State Program on Use of Alternative and Renewable Energy Sources in Azerbaijan Republic:

To determine potential of alternative and renewable energy in the electricity power generation;

To increase the efficiency of utilization of energy resources through attracting exploitation of renewable energy;

To provide additional job places by creating new energy production facilities;

To increase energy capacity and achieve energy security at expense of renewables by considering total capacity of traditional energy sources in Azerbaijan Republic.

Page 5: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

Current status of RE development in Azerbaijan

Realization of state policy by AREA:

State support to the sector;

Improvement of legislation;

Development of private sector;

Financial support and subsidy policy;

Adoption of modern technologies;

Research & development, information exchange;

Education, training and promotion of the green energy.

Page 6: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

Current status of RE development in Azerbaijan

Strategical directions of developing RE in Azerbaijan:

The production of electricity and thermal energy to determine

the main directions till 2020 by ARES;

Establishment of legal and regulatory framework in the sphere

of ARES;

Implementation of promotional events on the use of ARES;

Provision using ARES in all sectors of economy based on

domestic and international scientific and technical potential.

Page 7: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

Current status of RE development in Azerbaijan

Order of President of the Republic of Azerbaijan dated 16.03.2016 “On the approval of “The main directions of the strategic roadmap for key sectors of the economy and national economy” and about subsequent issues

Estimation:

“If no structural changes in the consumption over the next 5-10 years, new investment will be necessary to build production capacity of 1000 MW to ensure satisfactory supply”

-50 % of new investment are designed to be natural gas installations and 50 % ARES.

Safe, diversified and environmentally sustainable supply

Page 8: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

Current status of RE development in Azerbaijan

“AZERBAIJAN 2020: LOOK INTO THE FUTURE” DEVELOPMENT CONCEPT: Expanding the use of alternative and renewable energy sources;

Stimulating implementation of activities;

The development of the institutional atmosphere;

Strengthening of scientific and technical potential;

Continue training specialists;

Carrying out works to enlighten energy consumers;

Flexible regulation of energy tariffs;

Active participation of the private sector in this process will be

encouraged.

Page 9: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

Development map for RES - 2020

Page 10: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

Renewable energy technical potential in Azerbaijan

Small rivers Geothermal

Biomass and Waste Solar

Wind

%59

32

3.5

3.02.5

Total 25350 100

Page 11: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

3446.8 2681.0 1828.8 1631.7 1480.0 1828.5 2106.2 2605.6 2982.04157.8

5817.5

14900.1 16936.020619.9 21354.4

22882.5 22704.4 22424.722906.6

23550.623701.4

22598.9

0.0

5000.0

10000.0

15000.0

20000.0

25000.0

30000.0

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

Share of RE sources in energy supply, mln kW hour

Renewable sources Non-renewable sources

18346.9

19617.0

22448.7 22986.1

24362.5 24688.4 24530.925512.2

26532.6

27859.228416.4

Page 12: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

18.8 13.78.1 7.1 6.1 7.4 8.6 10.2 11.2 14.9

20.5

81.2 86.391.9 92.9 93.9 92.6 91.4 89.8 88.8 85.1

79.5

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

Share of RE in energy supply, %

Renewable sources Non-renewable sources

Page 13: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

0.0

1000.0

2000.0

3000.0

4000.0

5000.0

6000.0

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

Hydro Wind Solar Bio&Waste Bio&Waste

3446.8

2681.0

1828.81631.7

1480.01828.5

2106.2

2605.6

2982.0

4157.8

5817.5

Dynamics and forecast of renewable energy production, mln. kW hour

Page 14: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

0.0

500.0

1000.0

1500.0

2000.0

2500.0

3000.0

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

Hydro Wind Solar Bio&Waste

1023.5 1034.3 1061.0 1148.5 1178.4 1208.8 1232.0

1383.6

1563.6

2027.0

2676.0

Dynamics and forecast of renewable energy installation, MW

Page 15: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

Investments in RE (2005-2015)

467.5 mln.AZN (47.3%)

250.5 mln.AZN (25.4%)

164.3 mln.AZN (16.6%)

105.1 mln.AZN (10.7%)

Biomass & waste

Hydro (0.01<25 MW)

Wind energy

Photovoltaics & heatpumps

State investments – 83 %Non-state investments – 17%

987,4 mln. AZN

Page 16: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

Challenges in RE development in Azerbaijan

Technical challenges: problems with technology transfer;

Financial challenges: lack of financial resources; high level of interest rate;

Other challenges: lack of international organizations support in awareness sphere.

Page 17: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

Opportunities for increasing the development of RE

Hybrid PP

Gobustan Experimental Polygon and Training Center – 5.5 MW

Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan Solar Power Plant – 20 MW

Wind PP

Yeni Yashma Wind Farm - 50 MW Absheron Wind Farm (with PV component) – 80 MW Sitalchay Wind Farm – 3.6 MW Hokmaly Wind Farm – 8.0 MW

Biomass PP Biomass cogeneration on Oghuz, Aghjabedi and Samukh (feasibility study) – 16 MW

Page 18: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

RE support for agriculture

RE support for the solution of infrastructure issues Samukh Agro-Energy Residential Complex

“Wind Island – 1” Offshore Wind Farm

Waste-to-Energy Plant

Waste to energy

Opportunities for increasing the development of RE

Page 19: The State Agency on Alternative and Renewable Energy Sources … · 2016. 11. 16. · Solar PP Pirallahy Solar Power Plant – 2.8 MW Surakhany Solar Power Plant – 2.8 MW Nakhchivan

Thank you for your attention!