The US 5 Year Muon Acceleration R&D
Program
To Boldly Go…MICE Collaboration Meeting
HarbinJanuary, 2009
Overview
Much of this comes out of the DOE Review of Accelerator Science, December 2008
Page 3MICE CM – Harbin January 2009 A. Bross
The 5 Year PlanThe Proposal Has now been submitted to DOE
• A joint US: NFMCC-MCTF Plan– A measured program based on the solid muon accelerator
R&D achievements of the last decade – Sufficiently ambitious to make substantial progress before
the next round of long-term decisions by the particle physics community (Note: Coming soon – March 2009 DOE Retreat)
– Includes accelerator, physics & detector studies (only accelerator part in this talk – we also have plans & estimates for physics & detector studies)
• Meets our existing commitments (NF-RDR, MICE) and in addition will deliver:– MC performance requirements based on physics – A first end-to-end MC simulation– Critical component development & proof-of-principle
experiments– A first MC cost estimate
Page 4MICE CM – Harbin January 2009 A. Bross
Elements of the MC R&D Plan
BNLFNAL
LBNLFNAL
LBNLFNAL
LBNLFNAL
LBNLFNAL
FNAL BNL(Targetry)
LBNL
Page 5MICE CM – Harbin January 2009 A. Bross
Elements of the Plan - 2
• Design and Simulations – MC DFS
• Physics and Detector Study (Demarteau and Eichten)
• Accelerator Design & Simulation Study (Ankenbrandt & Fernow)
• Cost Estimation Study (Zisman)
– NF RDR (Bross) (under IDS-NF auspices)• Overall system design and staging scenarios • Siting issues• Participation in cost estimation activity
Page 6MICE CM – Harbin January 2009 A. Bross
Elements of the Plan - 3
• Component Development and Experiments – Carry out hardware development and
perform experimental tests to “inform” MC DFS and NF RDR
• Complete MICE!• Facilitate down-selection of MC cooling channel
options
– Includes ongoing work• RF testing, magnet development, absorbers, target
– Understand performance limits, engineering issues, costs
– Defines subsequent experimental program (extends beyond 5-yr plan)
Page 7MICE CM – Harbin January 2009 A. Bross
ResourcesAsking for a Significant Ramp-Up in Effort!
EFFORT REQUIREMENTS
0
10
20
30
40
50
60
70
80
90
YEAR
EF
FO
RT
(F
TE
)
MICE
NF-IDS
MC-DFS
FUNDING PROFILE
0
5000
10000
15000
20000
25000
30000
YEAR
FU
ND
S
(K$)
M&S
SWF
TOTAL
NOW 1 2 3 4 5 Yr
NOTE: Roll-over in years 4-5 provides an opportunity to initiate post-DFS activities, should the community wish us to proceed to the next step
NOW 1 2 3 4 5 Yr
Page 8MICE CM – Harbin January 2009 A. Bross
Why Muon Acceleration R&D?Muon Complex Evolution At Fermilab
• Starting with a high-intensity proton source: Project X• We see a natural evolution of
“muon” program for Fermilab
• Project X Low-Energy NF (pointing to Homestake) High-Energy NF 1.5 TeV MC 4 TeV MC
Page 9MICE CM – Harbin January 2009 A. Bross
Muon Acceleration and Future HEP FacilitiesNeutrino Factory & Muon Collider
MC: One Concept 4 TeV Center-of-Mass
• Rapid-Cycling Synchrotron Acceleration
• Neutrino Factory– IDS Baseline (FS1, FS2(a)(b), ISS)
25 GeV storage ring 4 GeV Option under study
ISS2006ISS2006
Common Front-End, SMALL FOOTPRINT
Page 10MICE CM – Harbin January 2009 A. Bross
Progress Potential
6D Cooling
Page 12MICE CM – Harbin January 2009 A. Bross
ACTIVITIES: YEARS 1 - 2
• MC-ZDR Physics & Detector– Establish physics reach vs E & L– Define performance goals (E, L, … )– Set up background & detector simulations– Define detector requirements & plan detector R&D to inform ZDR
• MC-ZDR Design & Simulations– Study alternatives for the accelerator subsystems using
defensible parameters– Cross-check promising subsystems with 2 simulation codes
• NF-RDR Studies– Determine relevant underground conditions at FNAL– Detector magnetization design & procurement for test– Interim NF-RDR report in 2010
• Components & Experiments– MICE: Complete Steps III – V (1 RF section + 2 absorbers)– RF in magnetic field studies: Determine viable options &
performance– HCC: 4-coil models (2009) & conceptual design + short demo HCC
magnet (2010)– Other magnets (ring, fast-ramping): Study options, define parameters
Page 13MICE CM – Harbin January 2009 A. Bross
ACTIVITIES: YEAR 3
• MC-ZDR Physics & Detector– Detector R&D, simulation & physics studies– Establish likely MC detector performance
• MC-ZDR Design & Simulations– Specify baseline accelerator design & study optimization (minimize
work on alternatives)– Simulate representative matching sections– Carry out representative tolerance studies– Freeze accelerator design
• NF-RDR Studies– Underground engineering: begin cost, schedule, risk analysis– Build detector test magnet
• Components & Experiments– MICE: Complete Last step – VI (2 RF sections + 3 absorbers)– Study 6D cooling experiment options– HCC-Section: Engineering design & procurement (magnet+RF)– Guggenheim-Section: RF Cavity and magnet conceptual
design– Other magnets (ring, fast-ramping): Define technology tests to inform
ZDR
Page 14MICE CM – Harbin January 2009 A. Bross
ACTIVITIES: YEAR 4 & 5
• MC-ZDR Physics & Detector– Continue detector R&D– Compare simulated physics reach with other machines (e.g.
CLIC) • MC-ZDR Design & Simulations (& cost)
– Complete design of all matching sections– End-to-end simulation of accelerator complex– Detailed tolerance studies– Cost estimate
• NF-RDR Studies– Complete RDR report
• Components & Experiments– MICE: Simple 6D cooling experiment (LiH wedge ?)– 6D Cooling experiment design studies to inform decision about what
to propose– HCC Section: Magnet test & RF integration & test– Guggenheim-Section: Engineering design & procurement
(magnet+RF) … build & test in year 5-6– Other magnets (ring, fast-ramping): Technology tests to inform ZDR
& post-ZDR R&D needs
Page 15MICE CM – Harbin January 2009 A. Bross
NICE (Next Ionization Cooling Experiment)6D Cooling Experiment
• There is no 6D Cooling Experiment in the 5 Year plan. A 6D cooling experiment would be a follow-on to the 5 Year plan AFTER technology down-select– A MICE extension using LiH wedge is in the plan.
Natural extension of our current LiH procurement effort
• 6D Cooling in the 5 Year Plan – “The bulk of the muon cooling is done in the 6D cooling channels” Proposed effort is component R&D to define specifications & conceptual design– Guggenheim– HCC– FOFO Snake– 50T HTS Channel (Very-High B + LH2)– PIC-REMEX– Low- Bucked-Coil Lattice– Li Lens Channel
FINAL COOLING
Page 16MICE CM – Harbin January 2009 A. Bross
Conclusions
• An overview of our proposal was presented at the DOE review of Accelerator Science in December, 2008
• The full proposal has now been submitted to DOE– (No feedback yet)– Will undoubtedly be discussed at the DOE Program retreat in
March (for out-years, beyond FY09)– No 6D Cooling experiment is in this proposal
• A FULL review of the proposal will occur at some future date– SOON we hope!