1 U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY The webinar will start momentarily….
Transcript
Page 1: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

1U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

The webinar will

start momentarily….

Page 2: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

2U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Opportunities for ESPCs in Data CentersRachel Shepherd (FEMP), Dale Sartor (LBL), Tom Hattery (ORNL),

Meghann Ison (Schneider Electric), R.J. Dyrdek (Army)

May 21, 2020

Page 3: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

3U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Webinar Logistics

• This webinar is being recorded. The Q&A portion

will not be made publically available.

• Your phone will be muted throughout the

webinar.

• Enter any questions in the Question Box

throughout the webinar.

• Instructions to take the quiz will be provided at

the end of webinar.

• Slides will be sent out afterwards to those who

attend the entire webinar

Page 4: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

4U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Webinar Overview

Agenda

I. Introduction to Opportunities for ESPCs in Data Centers

II. Case Study – ESCO Perspective

III. Case Study – Federal Agency Perspective

III. Resources and Q&A

Learning Objectives• Understand why data center efficiency improvements are well-suited for inclusion in ESPCs

• Know practical steps to be take to determine the value of including your data center in an

ESPC project

• Have lessons learned from agencies that have successfully incorporated data centers into

their ESPC projects

• Have relevant resources to assist the federal project executive and agencies in conducting

additional preliminary work to further assess the potential of ESPC in their data center

Page 5: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

5U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Webinar Team

Rachel ShepherdData Center Program Lead

Federal Energy Management [email protected]

Dale Sartor, P.E.

Mechanical Staff Scientist / Engineer

Lawrence Berkeley National Lab

[email protected]

510-486-5988

Tom Hattery

Federal Project Executive

Oak Ridge National Lab

[email protected]

202-256-5986

Meghann Ison, P.E., LEED AP

Senior Project Development Engineer

Schneider Electric

[email protected]

206-940-9159

R.J. Dyrdek

Energy Program Manager

U.S. Army, Fort Knox

[email protected]

502-624-2604

Page 6: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

6U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Dale Sartor & Tom Hattery

Introduction to Opportunities for ESPCs in Data

Centers

Page 7: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

7U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Why the Need for Data Center Energy Efficiency?

Data Centers are energy intensive facilities

Data Centers are 10 to 100+ times more energy intensive than an office,

and represent approximately 2% of all U.S. electricity consumption.

No slowdown in sight

There is surging demand for data storage. Some server racks are now

designed for more than 30 kW each. Energy cost, once in the noise, is

now often the highest operating cost.

Page 8: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

8U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

US Data Center Energy Usage (2007 & 2016 Reports)

• 20-40% energy savings & high ROI typical

• Aggressive efficiency strategies can yield 50+% savings

• Efficiency can extend life and capacity of infrastructures and

improve resiliency

2007 US Data Center Energy Usage Report 2016 US Data Center Energy Usage Report

Page 9: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

9U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Federal Information Technology Acquisition Reform Act (FITARA) (2014)

Agency annual reports (inventories, strategies, timeline, savings)

OMB sets targets and collects agency performance

Data Center Optimization Initiative (DCOI)

OMB requires federal agencies to consolidate, optimize, and modernize IT / data centers (OMB Memo M-19-19)

Performance metrics include Virtualization, Advanced Energy Metering, Server Utilization, and Availability

Aligning energy-related strategies/activities with DCOI requirements is a win-win for agencies

See the Center of Expertise’s DCOI factsheet

Modernizing Government Technology (MGT) Act (Dec 2017)

Establishes Technology Modernization Fund (TMF)

Policy Drivers for Federal Data Center Optimization

“Agencies are also encouraged

to use performance contracting

including Energy Savings

Performance Contracts and

Utility Energy Service Contracts

to finance energy improvements

when cost-effective.”

– OMB Memo M-19-19

Page 10: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

10U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Data Center Energy Efficiency Opportunities

IT Load/

Computing

Operations

Cooling

Equipment

Power Conversion & Distribution

AlternativePower

Generation

• High-voltage distribution

• High-efficiency UPS

• Efficient redundancy strategies

• Use of DC power

• IT innovation

• Virtualization

• High-efficiency

power supplies

• Load management

• Better air management

• Move to liquid cooling

• Optimized chilled-water plants

• Use of free cooling

• Heat recovery

• On-site generation

Including fuel cells and

renewable sources

• CHP applications

(waste heat for cooling)

Page 11: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

11U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Energy savings performance contract (ESPC) is ano-upfront-capital-cost contracting method. Thecontractor incurs the cost of implementing energyconservation measures (ECM) and is paid fromthe energy, water, wastewater and operationssavings resulting from these ECMs. An ESPC is apartnership between an agency and an energyservice company (ESCO).

Definition of ESPC

Page 12: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

12U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

ESPCs Are a Budget-Neutral Solution to Infrastructure Backlog

Energy and

Related

Operations &

Maintenance

Reallocate the Government’s Utility Bill

Stop paying for waste and pollution Start paying for efficiency

Energy and

O&M Savings

as a Result

of the ESPC

Energy and

Related

Operations &

Maintenance

Energy and

Related

Operations &

Maintenance

Savings

Excess Savings

Payments to the

ESCO

Ag

en

cy’

s C

ash

Flo

w (

$)

Before ESPC Performance Period After ESPC

Page 13: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

13U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Two types of savings may be used to pay the ESCO

Savings Must Exceed Payments

Energy cost savings

Example: Less energy use due to more efficient

HVAC equipment

Energy-related cost savings

Example: Reduced operation and

maintenance expenses

Critical for IT/data center modernization and consolidation

Page 14: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

14U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

•Engaged and Happy employees

•Higher productivity

•Reimbursable customers leverage more lab up-time

•Reduced labor repair requirements

•Expanded technical skill sets of government employees

•More efficient systems

•Reduced Trouble Calls

•Time to focus on proper Preventative Maintenance

More Reliable Systems

Better Technology

Better Work Environments

Less Equipment Downtime

Ancillary Benefits of ESPC

Page 15: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

15U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

~$11 million project

21 year contract term

roughly half the total investment for the IT ECM

ESPC Project with IT

ECM Mbtu savings

Ice storage & chiller upgrade 1,800

HVAC controls 2,540

Lighting 4,603

IT 18,757 (over 90% savings)

Page 16: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

16U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

FEMP ESPC Team - Helping Agencies Succeed with ESPC

FEMP Headquarters

• Program and policy support

FEMP Federal Project Executive (FPE)

• Your first point of contact

• Coordinates FEMP ESPC assistance for agencies

FEMP Project Facilitators (PFs)

• Hands-on technical project support

DOE Golden Field Office

• DOE-FEMP ESPC IDIQ contract administration

• Procurement guidance

National Lab SME

• Technologies

• Pricing (ECM benchmarking, finance rates)

• Utility tariffs and escalation

• General ESPC expertise

Legal counsel

• ESPC guidance to agency GC

Page 17: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

17U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

• IT/data center ESPC projects can stand alone or be part of a

comprehensive project including other building systems

• High cost of consolidation and modernization strategies can

be too high to be financed by energy savings alone:

– O&M savings and/or appropriations may be needed to make a project

viable

– Technology Modernization Fund (TMF) and IT Working Capital Funds

(WCF) are opportunities for leverage

• Considerations for data center ESPC project scope:

– Data center size, energy use, energy intensity, etc.

– Data center configuration.

– Plans for growth or consolidation.

Financing IT/Data Center Projects with ESPCs

Page 18: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

18U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

• Organizational Inertia, conflicting goals, and risk aversion

– ESPCs traditionally used by Building and Public Works departments (facilities),

while IT managers are the key decision maker.

– Split Incentives - Energy cost savings typically accrue outside the IT department.

– High levels of coordination and communication needed on critical facilities.

– Data centers also have customers and other stakeholders that want control.

– Integrity of IT - Criticality raises concerns with risk adverse staff that any change

or work in the data center could compromise operations.

• Lack of Manpower/Expertise

– Organizations may not be familiar with ESPC model and benefits.

– Some ESCOs lack a credible IT team.

• Unique implementation challenges

– Data centers are constantly changing, multiple refresh cycles (3-5 years) during

typical contract term.

– Unique contract mechanism requires ongoing contract management effort

Why are there so few IT/Data Center ESPCs

Page 19: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

19U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

FEMP and ESPCs can help solve and overcome barriers!

Team building and communication - Project Facilitators can

help improve organizational communication.

IT Performance should be enhanced and security/resiliency

increased (non-energy benefits can “sell” the project).

Augment manpower and expertise - Bring in outside experts

where needed (on IT and facilities side).

solution must be developed by data center experts and

decisions made by the agency IT departments.

Provide alternative source of funding for high cost of

consolidation and optimization strategies.

How can ESPCs help overcome barriers?

Page 20: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

20U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Most importantly: Get IT

and Facilities people

talking and working

together as a team!!!

Data Center ESPC Best Practices

Page 21: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

21U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Introduction Takeaways

1. There are a lot of energy and cost-savings opportunities in

data centers both in the facilities and with the IT.

2. ESPCs are a procurement mechanism to finance IT and

data center projects with no upfront cost.

3. Solution must be developed by data center experts with full

“buy in” from the agency’s IT departments.

4. Budget impacted by savings (utility, building maintenance,

IT) requires cooperation

5. Term length, refresh need special consideration for IT ECMs

6. Your requirements hard to meet without these tools

Page 22: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

22U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Meghann Ison

Case Study – ESCO Perspective

Page 23: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

ESPCs for Data CentersSchneider Electric

Presented by: Meghann Ison

Confidential Property of Schneider Electric

Page 24: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

Page 24Confidential Property of Schneider Electric |

Scope Opportunities1) Server Load / Computing Operations• Virtualization

• Network storage optimization

• Overhead structured cable and network

• Power management software

• Equipment efficiency and consolidation

2) Cooling Equipment• Air management

• Move to liquid cooling

• Optimized chilled-water plants

• Use of free cooling

• Heat recovery

4) Power Security & Distribution• High voltage distribution

• High efficiency UPS systems

• Efficient redundancy strategies

3) Energy Management• Data center power metering

• Data center environmental metering

(temperature, pressure, humidity, etc.)

• Trending PUE (Power Usage Efficiency)

5) On-site Generation

• Fuel cells, micro-turbines,

renewable sources, etc.

• CHP applications

Page 25: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

Page 25Confidential Property of Schneider Electric |

Case Studies - U.S. Naval Base

The ESPC Addresses the Navy’s Mission Critical Goals - reliability,

sustainability, resiliency, and efficiency for this mission critical data center.

The TO was awarded Feb 2016 with a value of $114 M • Construction is 100% complete and we’re in the 2nd year of long-term services

• Guaranteed savings are $4.4 million/year

Results• Upgrade of all cooling, heating, primary & emergency power, and controls

• Conversion from mixed/open floor cooling & dehumidification to controlled POD

environment – hot/cold aisle configuration w/ integrated cooling

• PUE (Power Usage Effectiveness) reduced from 2.5 to 1.2

• Consumption of server floor area reduced from 60% to 20%

• N+1 cooling redundancy

• N+1 heating redundancy

• N+1 emergency power redundancy

• 2N primary power redundancy

• 40 hour/week on site energy manager

• Control Panel relaying specific equipment failures

• 1 hour response time for any equipment failures

• Project meets the (“five nines”) 99.999% availability requirement for mission critical

facilities

Data Center ESPC Overview

Page 26: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

Page 26Confidential Property of Schneider Electric |

ESPC Project’s Performance Guarantees

Efficiency - HVAC equipment installed under the ESPC will be maintained to operate within 4% of the installed

efficiency

Resiliency and Availability - HVAC equipment serving the facility will have N+1 redundancy throughout the

performance period. Equipment serving the data center will be maintained in a state of operational

readiness. Timeframes for loss of N+1 redundancy will be reported. Loss of N+1 redundancy beyond 14

days in a performance period will result in a financial penalty of $50,000.

Replacement - the equipment serving the facility will be replaced within the performance period resulting in

significant remaining equipment life at the end of the performance period.

M&V - Equipment performance, including efficiencies, power, temperatures, delivered tonnage of cooling, and

run times will be monitored and reported

Staffing and Response - an onsite FTE will be provided during normal working hours and a one hour response

will be provided at all other times.

This ESPC meets the Navy’s needs today and positions them well for the future. It builds the platform for consolidation and enables

the Navy to meet their reliability and sustainability requirements and provides the platform of scalability for future needs.

Page 27: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

Page 27Confidential Property of Schneider Electric |

Case Studies - U.S. Air Force Base

The IGA addressed AF Mission Critical Goals – consolidation, virtualization,

reliability, sustainability, resiliency, and efficiency for this mission critical data center.

The IGA performed 2015 with a value of $24M

• 12 year contract proposed

• Guaranteed savings $2 million/year

Results• Consolidate and Upgrade Data Center infrastructure and HW/SW in both primary data

center and back-up data center

• Modernize IT equipment and platforms by increasing the virtual to physical servers from

1.3:1 to 6:1.

• Create a virtualized computing HW and centralized storage / backup HW

• Reduce servers, storage, and networking equipment

• Consolidate existing oversized Uninterruptible Power Supplies (UPSs)

• Reduce energy usage by 27%.

• Convert from mixed/open floor cooling & dehumidification to controlled POD environment

– hot/cold aisle configuration w/ integrated cooling

• Implement a comprehensive Operations and Maintenance (O&M) approach that will

ensure the long-term sustainability of their facilities – renewal of licenses, applications, and

IT Refresh of equipment infrastructure as well as IT HW / SW.

Data Center Investment Grade Audit Overview

Page 28: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

Page 28Confidential Property of Schneider Electric |

Lessons Learned

1. Connecting with Stakeholders – tenants and IT Management

• Increased reliability, i.e. replacing old substations

• Increased capacity, i.e.- increased electrical load capacity, available floor space

2. Getting ahead of break/fix – look into IT expenses, end use devices and applications

3. Buy-in for reallocating funds to accommodate a proactive approach – IT Refresh

• O&M of Computing Equipment

• O&M of Infrastructure Equipment (HVAC)

• O&M of Power Distribution Equipment

Additional resources are available

• White Papers – Data Center Optimization Cybersecurity DC Life Cycle Mgmt

• Q&A – [email protected]

Page 29: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction
Page 30: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

30U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

R.J. Dyrdek

Case Study – Agency Perspective

Page 31: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

UNCLASSIFIED//FOUO

UNCLASSIFIED//FOUO

Fort Knox Energy Program is Complete Team Effort

Page 32: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

FORT KNOX ENERGY INITIATIVES

UNCLASSIFIED

32 of 38R.J. Dyrdek / KNOX-DPW/(502) 624-2604 (DSN 464) /[email protected]

REACTION TO THE 2009 ICE STORM:

Sitewide Upgrades Continuing Today

Page 33: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

“OFF THE GRID”

ENERGY SECURITY

Daily Baseline Power Generation: 14 MW

Additional Local Utility Power Reduction Due To Cogeneration: 2 MW

Peak Power Generation To Reduce Demand Charge: 16 MW

Peak Demand Last 12 Months: 38.2 MW

Central Water Plant Waste Water

Treatment Plant

Natural Gas

Compression

Energy Security Project 2.1 Megawatt Solar

Array

Page 34: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

Maude Complex: Home of Human Resources Command

3-Star

Command

Suite

Page 35: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

18K sq ft facility Hosts ~200 applications Hosts 2700+ servers (~70%

virtual) 60% Capacity (300+ Racks In

Use; Capacity For 500+Racks)

Exceeds federal energyefficiency mandates and Data Center Optimization Initiativerequirements

~30% power capacity(2,725 kW available)

~35% cooling capacity(1140 tons available)

Data Center – Attributes are ALWAYS changing

Page 36: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

BEFORE 2/3 of Air Handler Units Converted to Plug Fans w/

Electrically Commutated (EC) Variable Speed Motors(below)

1/3 of Air Handler Units Converted to VariableFrequency Drives With Original Fans

Belt-Driven Squirrel CageFans w/ Constant Speed Motors

Air Management Enabler – Variable Speed Fans

AFTER

ESPC vehicle allows “bundling” of projects for cost effectiveness and access to financing:• Sitewide LEDs help pay for data center-specific measures

Page 37: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

74.8

Data Center, Rm. 1 Data Center, Rm. 2

Ro

wD

irec

tio

n

Ho

t A

isle

/Co

ld A

isle

On

ly

Row Direction

Cold Aisle w/ Chimneys

#9

T

43.6

H

60%

59.4

#11 T

67.1

H

60%

45.3

H

73.0

T

#10

0% 53.2

H

72.3

T

#12

0%

53.7

H

76.1

T

#15

60%

72.5

#13 T

52.4

H

60%

77.5

#14 T

49.3

H

0%

76.1

#24 T

39.6

H

79%

DC -Rm. 4 Support, Rm. 1 Support, Rm. 2

Support, Rm. 3

#28

73.4

T46.0

H

60%

#1

76.8

T42.3

H

60%

#4

74.8

T43.6

H

60%

#3

74.3

T40.7

H

60%

#2

77.4

T42.4

H

100%

#16

76.5

T39.6

H

60%

#19

74.5

T39.6

H

60%

#18

75.4

T40.1

H

100%

#17

75.9

T39.7

H

60%

#25

40.2

H

0%

#27

39.6

H

60%

39.8

H

74.1

T

#26

60%

72.9

73.9

T

T

Data Center, Rm. 3

#874.8

T42.3

H60%

#574.8

T41.4

H60%

#675.0

T41.4

H79%

#777.4

T42.4

H100%

#2375.7

T40.6

H60%

#2074.7

T40.7

H60%

#2174.5

T38.5

H60%

#2275.0

T38.9

H60%

Fan Retrofit Map & Performance Observations

Fan Speed, %- At 60% fan speed, 81% reduction in power for fans- At 79% fan speed, 75% reduction in power for fans- At 100% fan speed, 35% reduction in power for fans

H = Humidity, %RH

T = Return Temp, °F

Computer Room AirHandlers (CRAH)

Compared to original drive/fan

configurationComputer Room AirHandlers (CRAH)

Page 38: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

1.00

1.50

2.00

2.50

3.00

3.50

4.00

Ap

r-10

Jul-

10

Oct

-10

Jan

-11

Ap

r-1

1

Jul-

11

Oct

-11

Jan

-12

Ap

r-1

2

Jul-

12

Oct

-12

Jan

-13

Ap

r-1

3

Jul-

13

Oct

-13

Jan

-14

Ap

r-1

4

Jul-

14

Oct

-14

Jan

-15

Ap

r-1

5

Jul-

15

Oct

-15

Jan

-16

Ap

r-1

6

Jul-

16

Oct

-16

Jan

-17

Ap

r-1

7

Jul-

17

Oct

-17

Jan

-18

Ap

r-1

8

Jul-

18

Oct

-18

Jan

-19

Ap

r-19

Jul-

19

Oct

-19

Jan

-20

PU

E

Data Center Power Usage Effectiveness (PUE) Start-Up to Present

Better Air Management Impacts on Data Center Efficiency

Combined Heat and Power (CHP) Facility Online

w/Absorption Chiller for DCCRAH Fan Upgrade

Project Started

Page 39: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

8835

9454

11140

7311

8725

7494

5950

45523549

29603041 2803

4659

3032

4576

2842

7537

6806

3002

4771

2854

3185

5205

3477

4017

3749

3763

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

22000

12

/31

/20

17

1/7

/20

18

1/1

4/2

01

8

1/2

1/2

01

8

1/2

8/2

01

8

2/4

/20

18

2/1

1/2

01

8

2/1

8/2

01

8

2/2

5/2

01

8

3/4

/20

18

3/1

1/2

01

8

3/1

8/2

01

8

3/2

5/2

01

8

4/1

/20

18

4/8

/20

18

4/1

5/2

01

8

4/2

2/2

01

8

4/2

9/2

01

8

5/6

/20

18

5/1

3/2

01

8

5/2

0/2

01

8

5/2

7/2

01

8

6/3

/20

18

6/1

0/2

01

8

6/1

7/2

01

8

6/2

4/2

01

8

7/1

/20

18

7/8

/20

18

7/1

5/2

01

8

7/2

2/2

01

8

7/2

9/2

01

8

8/5

/20

18

8/1

2/2

01

8

8/1

9/2

01

8

8/2

6/2

01

8

9/2

/20

18

9/9

/20

18

9/1

6/2

01

8

9/2

3/2

01

8

9/3

0/2

01

8

10

/7/2

01

8

10

/14

/20

18

10

/21

/20

18

10

/28

/20

18

11

/4/2

01

8

11

/11

/20

18

11

/18

/20

18

11

/25

/20

18

12

/2/2

01

8

12

/9/2

01

8

12

/16

/20

18

Met

ere

d E

ne

rgy

Usa

ge, k

Wh

/day

Week

Data Center Energy Usage

IT Usage

Cooling Usage

Savings due toLED installation

Savings due toFan Upgrades

NOTE: Peaks in Cooling Usage line are primarily due to use of in-house cooling equipment vs. CHP cooling.

Page 40: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

What efficiency is left for Fort Knox’s Data Center?

Page 41: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

Energy Efficiency Upgrades Sitewide

› • $26.4MM in upgrades across 452 buildings as part of ESPC project

› • $2.3MM in annual energy and related savings

› ○ Reduced total energy consumption by 8%

› ○ Reduced grid electricity usage by 25.9MM kWh/yr (20% reduction)

ECM 4.2- Data Center HVAC

› Substantially Complete

› • 32 out of 32 CRACs completely renovated

› • All units networked together with firmware updates

› • Temp increases and commissioning on hold until direction to proceed

› ○ Critical to get a notice to proceed with commissioning to ensure

that project is completed on schedule

› After agreement on higher temperature set points than planned, commissioning was

successful

Ft. Knox Now Has a High-Performing Data Center

(At Zero Upfront Cost)

Page 42: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

42U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Rachel Shepherd

Resources and Q&A

Page 43: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

43U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

FEMP’s Data Center Program

FEMP’s Data Center program assists federal agencies and

other organizations with optimizing the design and operation

of data centers. design and operation of energy and water

systems in data centers to enhance agency’s mission.

Assistance

• Project and technical

assistance from the

Center of Expertise

including identifying

and evaluating ECMs,

M&V plan review, and

project design review.

• Support agencies in

meeting OMB’s Data

Center Optimization

Initiative

requirements

Tools

• Data Center Profiler

(DC Pro) Tools,

including PUE

Estimator

• Air Management

Tools

• Energy Assessment

Worksheets

Key Resources

• The Energy

Assessment Process

Manual

• Data Center Master

List of Energy

Efficiency Actions

• Small Data Centers,

Big Energy Savings:

An Introduction for

Owners and

Operators

Training

• Better Buildings

webinar series

• Nine on-demand

FEMP data center

trainings

• Center of Expertise

Webinars

• Data Center Energy

Practitioner Trainings

Page 44: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

44U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

LBL’s Center of Expertise (CoE)

Visit us at datacenters.lbl.gov

Explore the

diverse activities

that CoE is

engaged in.

Use CoE’s Energy

Efficiency Toolkit

Filter CoE’s many

resources by type

and topic.

Choose from upcoming live

webinars, pre-recorded trainings,

and in-person Data Center

Energy Practitioner (DCEP)

trainings.

Search

resources

by topics

of interest.

Follow us on Twitter

@DataCenterCoE

Page 45: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

45U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Getting IT and Facilities Managers

Talking and Working Together as a Team!Tuesday, May 26 from 1:00 – 2:00 pm EST

• Part of the Cloud & Infrastructure Community of Practice hosted by

GSA.

• IT Deputy for Operations and a Chief Sustainability Officer share

their experience working together to make continual improvements

of energy and water performance

• Report on the process and progress that yields tangible results

• Presentation on tools and resources for teams and project

champions for planning and implementing energy efficiency

measures

Email [email protected] if interested in attending

Webinar for Feds – Next Tues. at 1:00 pm EST

Page 46: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

46U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Visit the Better Buildings website for more information

and register for virtual sessions here.

Better Buildings Summit

Date Time (EST) Virtual Session

Monday, June 8 1:00 – 2:30 pm Data Centers Sector Meet-Up

Monday, June 8 3:00 – 4:30 pm DOE Fireside Chat with the National Labs:

Trends and Emerging Technologies

Tuesday, June 9 3:00 – 4:30 pm What’s New in Energy Efficiency Finance?

Wednesday, June 10 3:00 – 4:30 pm Stump the Chumps: How to Optimize Critical

Facilities

Page 47: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

47U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Federal Project Executive

Northeast

RegionWestern Region

Southeast Region

Federal Project Executives

(FPEs)

Scott Wolf

Western Region

360-866-9163

[email protected]

Doug Culbreth

Southeast Region

919-870-0051

[email protected]

Tom Hattery

Northeast Region

202-256-5986

[email protected]

Page 48: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

48U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

FEMP ESPC Team - Helping Agencies Succeed with ESPC

FEMP Headquarters

• Program and policy support

FEMP Federal Project Executive (FPE)

• Your first point of contact

• Coordinates FEMP ESPC assistance for agencies

FEMP Project Facilitators (PFs)

• Hands-on technical project support

DOE Golden Field Office

•DOE-FEMP ESPC IDIQ contract administration

•Procurement guidance

National Lab SME

•Technologies

•Pricing (ECM benchmarking, finance rates)

•Utility tariffs and escalation

•General ESPC expertise

Legal counsel

•ESPC guidance to agency GC

Visit FEMP’s ESPC for Federal Agencies website

Contact FPEs for help with ESPCs or any questions

Page 49: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

49U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

Rachel Shepherd

Data Center Program Lead

Federal Energy Management Program

[email protected]

202-586-9209

Dale Sartor, P.E.

Mechanical Staff Scientist / Engineer

Lawrence Berkeley National Lab

[email protected]

510-486-5988

Tom Hattery

Federal Project Executive

Oak Ridge National Lab

[email protected]

202-256-5986

Meghann Ison, P.E., LEED AP

Senior Project Development Engineer

Schneider Electric

[email protected]

206-940-9159

R.J. Dyrdek

Energy Program Manager

U.S. Army, Fort Knox

[email protected]

502-624-2604

Page 50: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

50U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

IACET Credit for Webinar

The National Institute of Building Sciences’ (NIBS) Whole Building Design Guide (WBDG) hosts the FEMP training program’s learning management system (LMS).

The WBDG LMS:

• Allows for taking multiple trainings from multiple organizations through one platform.

• Houses the assessments and evaluations for all accredited courses.

• Allows you to:

– Track all of your trainings in one place.

– Download your training certificates of completion.

• Eases the CEU-achievement process.

Visit the WBDG at www.wbdg.org to view courses and create an account

Page 51: The webinar will start momentarily….datacenters.lbl.gov/sites/default/files/Data Center ESPC Webinar-PPT_0.pdfThe TO was awarded Feb 2016 with a value of $114 M • Construction

51U.S. DEPARTMENT OF ENERGY OFFICE OF ENERGY EFFICIENCY & RENEWABLE ENERGY

IACET Credit for Webinar

To receive IACET-Certified CEUs, attendees must:

• Attend the training in full (no exceptions).

– If you are sharing a web connection during the training, you must send an e-mail to Elena Meehan ([email protected]) and indicate who was on the connection and who showed as connected (will reflect in the WebEx roster).

• Complete an assessment demonstrating knowledge of course learning objectives and an evaluation within six weeks of the training. A minimum of 80% correct answers are required for the assessment.

To access the webinar assessment and evaluation, visit:

https://www.wbdg.org/continuing-education/femp-courses/femplw05212020

If you have a WBDG account and enrolled previously, simply log in and click the Continuing Education tab on the user account page. Click Proceed to Course next to the course title.

Opportunities for ESPCs in Data Centers