+ All Categories
Home > Documents > THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be...

THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be...

Date post: 03-Jun-2020
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
51
Transcript
Page 1: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included
Page 2: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included
Page 3: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER 201X

EXPLANATORY MEMORANDUM

19 July 2019

Pursuant to Regulation 5(2)(c) Infrastructure Planning (Applications:

Prescribed Forms and Procedure) Regulations 2009

DOCUMENT 3.2A2B

Eversheds Sutherland (International) LLP

Page 4: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2A2B

Eversheds Sutherland (International) LLP

19 July 2019

This page is left intentionally blank

Page 5: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

EXPLANATORY MEMORANDUM

Contents

Section Page

1. Introduction 5

2. The Purpose of the Order 5

3. Location of the development to be authorised 8

4. Plans 8

5. The Assessment Parameters 10

6. The Draft Order

- Preliminary

- Principal Powers

- Streets

- Supplemental Powers

- Powers of Acquisition

- Miscellaneous and General

- Schedules

11

13

15

17

2625

26

31

35

Page 6: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2A2B

Eversheds Sutherland (International) LLP

19 July 2019

4

This page is left intentionally blank

Page 7: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

5

1. Introduction

1.1 This memorandum accompanies an application for a development consent order

(“the Application”) submitted on behalf of Four Ashes Limited (“the Applicant”). The

Application seeks approval of the Draft West Midlands Rail Freight Interchange

Order 201X (“the DCO”).

1.2 As required by Regulation 5(2)(c) Infrastructure Planning (Applications: Prescribed

Forms and Procedure) Regulations 2009, as amended, (“the Regulations”), this

memorandum explains the purpose and the effect of provisions in the draft Order. It

has been prepared taking into account the guidance set out in the Advice Note 13:

Preparing the Draft Order and Explanatory Memorandum (April 2012February 2019)

and the DCO has been prepared taking into account the guidance set out in Advice

Note 15: Drafting a Development Consent Order (October 2014July 2018).

1.3 The Applicant is Four Ashes Limited, a special purpose vehicle set up to promote

and develop the development applied for. The company is a joint venture between:

1.3.1 Kilbride Holdings – a company specializing in rail infrastructure to serve

business and industry;

1.3.2 the Grosvenor Group – a privately owned international property group;

and

1.3.3 Piers Monckton – the primary land owner.

1.4 This Explanatory Memorandum relates to the draft DCO submitted to the Examining

Authority for Deadline 5 on 519 July 2019 (Document 3.1C1D). Each version of the

draft DCO submitted to the Examining Authority has been accompanied by a DCO

changes tracker which identifies the changes from the preceding version and

explains the reasons for those changes (Document series 3.4).

2. The Purpose of the Order

NSIP Criteria

2.1 Section 14 of the Planning Act 2008 (as amended) (“the 2008 Act”) sets out the type

of projects that are classified as nationally significant infrastructure projects (“NSIP”).

Section 14(1)(l) of the 2008 Act identifies “the construction or alteration of a rail

freight interchange”.

2.2 Section 26 of the 2008 Act sets out the conditions which must be satisfied for the

construction of a rail freight interchange to be classified as an NSIP. Section 26(1)

advises that a rail freight interchange will only be treated as an NSIP when each of

the conditions set out in subsections (3) to (7) are expected to be met.

Page 8: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

6

2.3 The authorised development accords with these conditions as the proposed

development includes the construction of a new rail freight interchange that will:

2.3.1 be situated in England and be at least 60 hectares in area (section 26(3)(a)

and (b));

2.3.2 be capable of handling consignments of goods from more than one

consignor and to more than one consignee and at least four goods trains

per day (section 26(4)(a) and (b));

2.3.3 be part of the railway network in England (section 26(5));

2.3.4 include warehouses to which goods can be delivered from the railway

network in England either directly or by means of another form of transport

(section 26(6)); and

2.3.5 not be part of a military establishment (section 26(7)).

2.4 The proposed development therefore falls within the definition of a rail freight

interchange NSIP as set out in the 2008 Act.

2.5 Consideration has been given as to whether any of the highway works might

constitute an NSIP in their own right. Whether they do depends on whether the

works meet the criteria and thresholds relating to ‘highway’ NSIPs set out in section

22 of the 2008 Act.

2.6 The only highway works which are capable of being a ‘highway’ NSIPs are new

highways, or works being carried out on highways, for which the Secretary of State

or a strategic highways company will be, or is, the highway authority.

2.7 There are no new lengths of highway included in the proposals for which the

Secretary of State or a strategic highways company would be the highway authority.

For the avoidance of doubt the highway authority for the A5/A449 link road to be

constructed will be Staffordshire County Council.

2.8 The works to the existing highways are relatively minor and considered to be an

improvement and are not considered in themselves to have a significant effect on

the environment and do not therefore meet the criteria for an NSIP. Were they to

be considered “alterations” then they each fall well below the lowest threshold for

alterations being 9.24ha. None of the highway works are therefore considered to be

an NSIP in their own right.

Page 9: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

7

Scope of the proposed development

2.9 The DCO sought will permit, in summary, the following works:-

i) An intermodal freight terminal with direct connections to the West

Coast Main Line capable of accommodating up to 10 trains per day

and trains of up to 775m long, including container storage, associated

Heavy Goods Vehicle parking, rail control building and staff facilities;

ii) Up to 743,200 sq m of rail served warehousing and ancillary service

buildings;

iii) New road infrastructure and works to the existing road infrastructure;

iv) Demolition of and alterations to existing structures and earthworks to

create development plots and landscape zones;

v) Reconfiguring and burying of electricity pylons and cables; and

vi) Strategic landscaping and open space, including alterations to

public rights of way and the creation of new ecological enhancement

areas and publicly accessible open areas.

2.10 The proposed development is more fully described in Schedule 1 of the draft DCO

(Document 3.1C) and in the other Application documentation. The individual works

are described in Section 6 (see paragraphs 6.108116 – 6.112120).

2.11 The draft DCO also authorises associated development (see paragraph 2.12 below).

Provision for ancillary matters is made in the body of the draft DCO (see paragraph

2.13 below).

Associated Development

2.12 The draft DCO specifically authorises development which is not part of the NSIP

itself but is associated with it, as provided for by section 115(2) of the 2008 Act.

These comprise Works No.s 6, 7, 8, 9a, 9b, 10a, 10b, 11 and 12. These aspects of

the authorised development are considered to be associated development as they

each are “typical of development brought forward” with the NSIP or “help address

its impacts”. They are “not an aim in itself” but are “subordinate to the principal

development1.

1 See paragraph 5(ii) Guidance on associated development applications for major infrastructure

projects April 2013.

Page 10: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

8

Ancillary Matters

2.13 The draft DCO also deals with some ancillary matters – that is, provisions not

dealing with development.

2.14 For example, it seeks powers for the purposes of carrying out the authorised

development to acquire rights and land pursuant to section 120 of the Act and

powers, under section 120 (3) and (4) and Part 1 of Schedule 5, paragraph 2, to

authorise the creation, extinguishment and interference with interests in, or rights

over, land (including the stopping up of a public right of way and creation of public

rights of way).

2.15 The compulsory purchase powers sought are explained within the Statement of

Reasons (Document 4.11A).

3. Location of the development to be authorised

3.1 The land affected by the proposed development is referred to in the draft DCO as

the Order limits. These are shown on the Order Limits and Parish Boundaries Plan

(Document 2.4). The Order limits comprise approximately 297 hectares of land lying

to the west of Junction 12 of the M6 approximately 10km to the north of

Wolverhampton and west of Cannock.

3.2 The Order limits are located within South Staffordshire District. Whilst the majority

of the land is within the parish of Penkridge, parts are also within the parishes of

Brewood and Coven, and Hatherton. The boundaries of the parishes are shown on

the Order Limits and Parish Boundaries Plan.

3.3 The strategic rail freight interchange (“SRFI”) would broadly be bounded by the A5

trunk road to the north (from Junction 12 to the Gailey Roundabout); Calf Heath

reservoir, the M6, Stable Lane and Woodlands Lane to the east; Station Drive,

Vicarage Road and Straight Mile to the south; and the A449 trunk road (Stafford

Road), from the Gailey Roundabout to Station Drive to the west. The south-eastern

area of the site is also bisected by Vicarage Road.

4. Plans

4.1 The plans submitted with the Application include:

i) An Order Limits and Parish Boundaries Plan enabling the

identification of the land affected and; the existing development in

the immediate locality; and the parish boundaries (Document 2.4);

ii) Land Plans (pursuant to Regulation 5(2)(i) - Documents 2.1A to and

2.1L) showing the land affected by the development and the land

subject to compulsory purchase and temporary possession powers.

Page 11: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

9

iii) Works Plans (pursuant to Regulation 5(2)(j) - Documents

2.2A to 2.2I) identifying the areas for the different works which cross

refer to Schedule 1 in the Draft DCO and, where appropriate, show

the limits of deviation.

iv) Access and Rights of Way Plans (pursuant to Regulation

5(2)(k) - Documents 2.3A to 2.3G) which identify new and altered

means of access, stopping up of streets and roads, stopped up

and new public footpaths, bridleways, cycle tracks and diversions.

v) Parameters Plans (pursuant to Regulation 5(2)(o) - Documents 2.5A-D,

2.6A-D and 2.7A-D) which identify the parameters with which the Works

must comply. The parameters plans are the plans upon which the

environmental assessment reflected in the Environmental Statement

has been based. The approach taken by the parameters plans is

described in more detail in Section 5 below.

vi) Highway General Arrangement Plans, Rail Plans and Bridge

Plans (pursuant to Regulation 5(2)(o) – Document series 2.9, 2.14,

2.15 to 2.18) which describe various aspects of the road and rail

infrastructure. Although there are rail and highway elements included

in the proposed development it was established at an early stage of

pre-application discussions with the Planning inspectorate that

Regulation 6 of the Regulations 2 was not engaged since those

elements were not NSIPs in their own right. Nonetheless the

information supplied does contain the information required to comply

with Regulation 6.

vii) Other Plans – these comprise the remainder of the plans submitted

with the Application. Some are cross referred to within the description

of the Works in Schedule 1 of the Draft DCO and/or the requirements

in Schedule 2 of the Draft DCO. Some are supplied for illustrative

purposes only. These plans include:

a) Highway Classification Plans (Document series 2.13) which

identify the new classification of the A5/A449 link road following the

construction of the authorised development;

b) Future Highways Maintenance Plans (Document series 2.10)

which identify the extent of works on the trunk road network and

2 Infrastructure Planning (Applications: Prescribed Forms and procedure) Regulations 2009 (as

amended).

Page 12: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

10

the county highway network and future responsibility for

maintenance;

c) Traffic Regulation Order Plans (Document series 2.11) and

Speed Limit Plans (Document series 2.12) which deal with

consequential changes to the regulation of highways as a result

of the works;

d) An Illustrative Masterplan (Document series 2.8), is also provided

to assist in demonstrating a form of development which would

comply with the parameters which have been assessed (as

shown on the Parameter Plans). It is not the basis for the

environmental assessment reflected in the Environmental

Statement and it identifies simply one way in which a

development may come forward in conformity with the

Parameters Plans.

5. The Assessment Parameters

5.1 The Parameters Plans (Documents 2.5 to 2.7) are the plans which identify the

parameters of the authorised development and are the basis of the environmental

assessment that has been carried out.

5.2 The Parameters Plans identify the parameters which apply to different areas of the

Order limits. These include the maximum overall floorspace to be constructed, the

building height range and the green infrastructure to be provided. These provide the

“Rochdale Envelope” for the purposes of the environmental assessment of the

development on the site. This is in line with Advice Note 9 “Using the Rochdale

Envelope”.

5.3 The control of the development is secured by reference to:

5.3.1 Articles 4 (Parameters of authorised development) and 4544

(Governance of requirements and protective provisions relating to

highway works);

5.3.2 the description of the works in Schedule 1;

5.3.3 the requirements in Schedule 2; and

5.3.4 the parameters on the Parameters Plans and the limits of deviation shown

on the Works Plan, Bridge Plans and Rail Section Plans.

5.4 Details over and above those shown on the Parameters Plans, including, for

example, the precise location and height of buildings within the development zones;

the detailed design of the rail infrastructure; detailed landscaping scheme and

Page 13: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

11

ecological mitigation details, are to be approved following the grant of the DCO and

following the submission of details to the local planning authority pursuant to the

requirements contained in Schedule 2 of the DCO.

5.5 In the case of highway works comprised in Works No. 4 and 7 , and any parts of

works numberWorks No. 5 that involve the public highway, the detailed working

drawings of the works involved will be governed by Parts 2 and 3 of Schedule 13.

Those designs are required to be in accordance with the Highway General

Arrangement Plans (Document Series 2.9).

5.6 The approved details cannot however stray outside the description of the authorised

development or beyond the parameters shown on the Parameters Plans as is made

clear by Articles 4 and 4544. The approval of details subsequent to the making of

the Order, and the ability to change details approved, as provided for in Article

4544(2), is in accordance with paragraph 19.4 of Advice Notice 15: Drafting

Development Consent Orders3.

6. The Draft Order

6.1 This section of the memorandum explains the provisions of the draft Order as

submitted to the Planning Inspectorate with the Application. There are substantial

departures from the model provisions in view of their lack of direct relevance to the

development proposed, the revocation of Section 38(3) of the Act 2008 and repeal

of the Infrastructure Planning (Model Provisions) (England and Wales) Order 2009.

The starting point therefore was Articles used in other approved Development

Consent Orders. In particular regard has been had to The Daventry International

Rail Freight Interchange Alteration Order4; The East Midlands Gateway Rail Freight

Interchange and Highway Order5; The A14 Cambridge to Huntingdon Improvement

Scheme Development Consent Order6 and The York Potash Harbour Facilities

Order7.

6.2 The text below deals in turn with each Article and Schedule of the draft DCO. To

assist the Examining Authority, and to provide context for the dDCO, the relevant

provisions of the 2008 Act are described below. In addition, further explanation is

included for each article to confirm the relevant powers under the 2008 Act.

6.3 The 2008 Act allows a Development Consent Order to contain various powers

provided that those powers are related to or ancillary to the proposed development.

Section 120 of the 2008 Act sets out what a DCO may contain:

3 The Planning Inspectorate, Version 1 (October 2014). 4 S.I. 2014 No. 1796. 5 S.I. 2016 No. 17. 6 S.I. 2016 No. 547. 7 S.I. 2016 No. 772.

Page 14: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

12

6.3.1 Section 120(1) permits the inclusion of “requirements in connection with

the development for which consent is granted”. Section 120(2) states that

requirements “may in particular include”:

(a) requirements which are akin to conditions which could have

been imposed on the grant of a permission or consent which

would have been required for the development, were it not

required to be authorised by the DCO (i.e. were it not an

NSIP development); or

(b) requirements to obtain the approval of the Secretary of State

or any other person, if they do not fall within (a) above.

6.3.2 There is therefore no limit to the general scope of requirements set out in

section 120(1). Section 120(2) does not limit the scope of requirements

but simply gives examples. The ability to impose requirements in law is

therefore unconstrained other than that the requirement must be

connected to the development.

6.3.3 The NPSNN provides guidance as to the imposition of requirements and

states that they should only be imposed if they are necessary, relevant to

planning, relevant to the development to be consented, enforceable,

precise and reasonable in all other respects (Paragraph 4.9).

6.3.4 Section 120(3) of the 2008 Act permits the inclusion in the DCO of a

provision “relating to, or to matters ancillary to, the development for which

the consent is granted.” This is a wide power, only limited by the fact that

a provision must be related to the authorised development for it to be

included. The Applicant therefore considers that all powers sought under

the DCO fall within section 120(3), but it has also, where applicable, set

out in this Explanatory Memorandum where a matter might also be

covered by one or more of the other sub-sections in s120 of the 2008 Act.

6.3.5 Section 120(4) sets out (together with Part 1 of Schedule 5 to the 2008

Act) some specific matters which may be included in a DCO. It is

important to note that this subsection does not limit the matters which may

be included in a DCO pursuant to s.120(3) – notably, the section states:

“the provision that may be made under subsection (3) includes in

particular provision for or relating to any of the matters listed in Part 1 of

Schedule 5” (Applicant’s underlining). The Applicant considers, therefore,

that a provision is not precluded simply because it is not specifically listed

in Part 1 of Schedule 5 (indeed, section 120(4) also allows a provision

which is related to those matters listed in Part 1 of Schedule 5 to the 2008

Act), provided that the provision is related to the authorised development.

Page 15: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

13

6.3.6 Section 120(5) sets out further specific powers which a DCO may include,

and importantly, only some of these powers are limited to circumstances

where certain tests must be met:

(a) a DCO may apply, modify or exclude a statutory provision

which relates to any matter for which provision may be made

in the order;

(b) a DCO may make amendments, repeals or revocations of

statutory provision of local application as appear to the

Secretary of State to be necessary or expedient in

consequence of a provision of or in connection with that

DCO;

(c) a DCO might include any provision that appears to the

Secretary of State to be necessary or expedient for giving

full effect to any other provision of the DCO; and

(d) a DCO may include incidental, consequential,

supplementary, transitional or transitionary provisions and

savings.

PART 1

PRELIMINARY

Article 1 (Citation and commencement)

6.4 This Article provides for citation and commencement of the Order.

Article 2 (Interpretation)

6.5 This Article provides for the interpretation of the Order principally including the

definition of terms.

6.6 Definitions to note are:

i) “authorised development” has been amended from the term in

the model provisions to include any works carried out pursuant

to the requirements.

ii) the terms “relevant highway authority” and “relevant street

authority” have both been included as defined terms, as,

whilst some Articles apply only to public highways (e.g. Article

12 public rights of way – creation and stopping up) and

therefore refer to the “highway authority”, the term “street

Page 16: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

14

authority” is also needed as some Articles apply to private

streets, such as those to be provided on the main site (e.g.

Article 9 power to alter layout, etc., of streets).

iii) The definition of “undertaker” has been amended, as

permitted by section 156(2) of the 2008 Act, to expressly refer

to Four Ashes Limited and includes (in respect of the main site

only) those persons who have the benefit of the Order in

accordance with Section 156 of the Planning Act 2008. Article

7 restricts the benefit of the order in certain respects to Four

Ashes Limited only.

iv) Definitions of the “main site” and “highway works” have been

added to facilitate the drafting of the separate provisions

relating to those elements of the development.

6.7 Article 2 (2) expands the definition of rights over land and clarifies that it includes

rights to do, or to place and maintain, anything in, on or under land or in the airspace

above its surface.

6.8 Article 2 (3) makes it clear that measurements are approximate to take account of

marginal differences arising out of construction of the works. This allows only small

tolerances since the works are still subject to the constraints imposed by Articles 4

and 45. This provision is normal and was included in The Keuper Gas Underground

Storage Facility Order 20178 and the M20 Junction 10a Development Consent

Order 20179.

6.9 Article 2 (4) ties in references to work numbers to the works in Schedule 1 and

references to requirements to the requirements listed in Part 1 and Part 2 of

Schedule 2.

6.10 Article 2 (5) provides that areas referred to in the Book of Reference (Document

4.33A) are approximate – for the same reason as Article 2 (3) is required.

6.11 Articles 2 (3) - (5) are identical to those included in the East Midlands Gateway Rail

Freight Interchange and Highway Order10.

6.12 Article 2 (6) clarifies that where the word approximate is used prior to a quantum it

does not provide latitude for going beyond the parameters and carrying out works

that have not been assessed. This provision is a sensible precaution to ensure that

8 S.I. 2017 No. 433. 9 S. I. 2017 No. 1202. 10 S. I. 2016 No. 17.

Page 17: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

15

the Rochdale Envelope is not breached and was included in the York Potash

Harbour Facilities Order 201611.

PART 2

PRINCIPAL POWERS

Article 3 (Development consent granted by the Order)

6.13 This Article provides development consent for the authorised development to be

carried out within the Order limits subject to the provisions of the Order and to the

requirements.

Article 4 (Parameters of authorised development)

6.14 This Article is included to allow flexibility for the works to be carried out within the

parameters identified on the Parameters Plans. The parameters identified on the

Parameters Plans have been used for the purposes of environmental assessment

of the authorised development.

6.15 As explained above, this approach is in line with the Rochdale Envelope approach

and the guidance set out in Planning Inspectorate’s Advice Notes 9 and 15.

6.16 The Article also provides for limits of deviation as shown on the Works Plans

(Document 2.2A-I), Bridge Plans (Document 2.17 and 2.18A-D) and Rail Section

Plans (Document 2.16A-E).

6.17 As in recent orders the The Article allows for exceptions to the application of the

limits where the local planning authority are satisfied that it would not result in any

significant adverse effects on the environment12. This approach was the subject of

specific consideration during the examination of the DCO for the A14 Cambridge to

Huntingdon Improvement Scheme and the specific drafting of this provision was

discussed and altered, as a result of which, the Examining Authority made a specific

finding that the proposed Article was acceptable13. The principle is the same here,

except:

6.17.1 the local planning authority is the proposed adjudicator rather than the

Secretary of State, which it is felt is more appropriate, given the

involvement of the local planning authority in dealingconsistent with

approval of details for the remainder of the development. The Applicant

11 S. I. 2017 No. 772. 12 For example Article 7 The A14 Cambridge to Huntingdon Improvement Scheme Development Consent

Order 2016. 13 See paragraphs 8.2.15 – 8.2.21 of the Examining Authority’s Report

Page 18: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

16

has also provided its view on the justification for the local planning

authority dealing with the approval in response to ISH1:1.11 (see

Document 9.1, REP1-002) and ISH4:1.5 (see Document 14.2, REP4-

010).; and

6.17.2 the wording refers to the exception to the application of the limits being

permitted only where there the local planning authority is satisfied that it

wouldn’t result in “significant adverse effects on the environment” as

opposed to other DCOs which refer to “materially new or materially worse

environmental effects.” The intention is that the test applied is the same

test as that set out for “subsequent applications” in Schedule 2 of the

Infrastructure Planning (Environmental Impact Assessment) Regulations

201714.

6.186.17 The proviso to the Article referred to above is felt to be preferable to the

approach containedthe equivalent article in the East Midlands Gateway Rail Freight

Interchange and Highway Order15 whereby 20 metres flexibility was allowed either

side of the boundary between two numbered works, irrespective of the

environmental impact of that change. .

Article 5 (Authorisation of Use)

6.196.18 This Article authorises the operation of the SRFI development and ensures

that the concept of ancillary uses applies to the warehousing built pursuant to the

DCO as it would had the warehousing been built pursuant to a planning permission.

The Article includes confirmation that the development of the SRFI and warehousing

may be used for the purposes for which they are designed. This follows the

approach taken in Thames Tideway Tunnel Article 416. The article gives express

authorisation for the use of Works 1 – 3 pursuant to section 157 of the 2008 Act.

Article 6 (Maintenance of authorised development)

6.206.19 This Article is based upon Article 3 of the model provisions and provides for

the maintenance of the authorised development by the undertaker. The definition of

maintenance is identical to that contained in the recently approved East Midlands

Gateway Rail Freight Interchange and Highway Order 201617 except that a caveat,

in respect of works which would result in a significant environmental effect which

had not been assessed, has been deleted from the definition and is instead in Article

6(2). This follows the advice in Advice Note 15: Drafting Development Consent

Orders to the effect that operative provisions should not be contained in definitions

14 S.I. 2017 No. 572 (as amended) 15 S. I. 2016 No. 17 16 The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S. I. 2014 No. 2394) 17 S.I. 2016 No. 17

Page 19: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

17

(paragraph 6.1). The power is permitted by section 120(3) of the 2008 Act because

maintenance of the authorised development is clearly “related” to the consent.

Article 7 (Benefit of the Order)

6.216.20 The Order will benefit the “undertaker”, as defined, which in the case of the

main site, will include all parties who qualify under Section 156 of the 2008 Act.

However, some powers will benefit only Four Ashes Limited, as follows:

(a) Part 5 (Powers of Acquisition) will be for the sole benefit of Four

Ashes Limited to ensure that the Articles relating to the exercise of

compulsory acquisition powers cannot be transferred unless the

Secretary of State consents; and

(b) only Four Ashes Limited have the power to carry out the highway

works and deliver them in accordance with the protective

provisions in Parts 2 and 3 of Schedule13 unless the Secretary of State

consents to a transfer of those powers or the relevant highway authority

takes over responsibility for carrying out the highway works in default of

the undertaker pursuant to the provisions of Schedule 13.

6.226.21 In respect of (b) above, it is felt that the power to carry out the highway works

should be restricted to the named undertaker rather than be available to all the

owners of the land interests within the Order limits to ensure an orderly and

comprehensive approach to the carrying out of the works.

6.236.22 Sub-paragraph 4 has been included to ensure that any works which may be

carried out by other parties under the protective provisions are authorised18. Such a

provision is included in other Orders such as The M4 Motorway (Junctions 3 to 12)

(Smart Motorway) Development Consent Order 201619.

PART 3

STREETS

Article 8 (Street works)

18 For example, the protective provisions for the Canals and Rivers Trust (Part 7 of Schedule 13) include

the ability of the Trust to carry out works instead of the undertaker. 19 S. I. 2016 No. 863 (Article 7(2)).

Page 20: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

18

6.246.23 This Article is broadly based on Article 8 of the general model provisions. It

makes provision for the undertaker to carry out the works described in Article 8 (a)

– (j) for the purposes of the authorised development affecting the streets specified

in Schedule 3. Ordinarily the undertaker would require a street works licence

pursuant to the New Roads and Street Works Act 1991 to carry out such works,

however, the inclusion of this Article in the Order will provide a statutory right to

undertake street works within the specified streets without the need for the

undertaker to obtain a separate licence from the street authority. The authority given

by Article 8(1) is a statutory right for the purposes of sections 48(3) and 51(1) of the

New Roads and Street Works Act 1991 and is permitted by section 120(5)(a) of the

2008 Act.

6.256.24 This Article is similar to Article 10 of the East Midlands Gateway Rail Freight

Interchange and Highway Order 20 with the exception that the East Midlands

Gateway Order refers to highways rather than streets and relates only to highway

works affecting the public highway. The Article included in this draft DCO is broader

and includes private streets, given the number of private accesses affected. The

provision relates to the authorised development and is therefore permitted by

section 120(3) of the 2008 Act. The Applicant also considers the powers are

permitted by section 120(4) and specifically paragraph 15 of Part 1 of Schedule 5 to

the 2008 Act (i.e. the carrying out of civil engineering or other works).

6.266.25 Sub-paragraphs (3) and (4) have been added in response to a request from

Staffordshire County Council.

Article 9 (Power to alter layout, etc., of streets)

6.276.26 This Article is not contained in the model provisions but is based upon an

Article that has precedent in other approved Development Consent Orders, for

example the Heysham to M6 Link Road Order21, North Doncaster Chord Order22

and The Keuper Underground Gas Storage Facility Order23. It is similar to Article

9(1) of the East Midlands Gateway Rail Freight Interchange and Highway Order24.

The Article is authorised pursuant to section 120(3) of the 2008 Act since any

necessary works are related to the authorised development, as well as section

120(4) and specifically paragraph 15 of Part 1 of Schedule 5 to the 2008 Act (i.e.

the carrying out of civil engineering or other works). The provision is also authorised

by section 120(c), given that it is necessary and expedient to give full effect to the

20 S.I. 2016 No. 17. 21 The Lancashire County Council (Torrisholme to the M6 Link (A683 Completion of Heysham to M6 Link Road))

Order 2013 S.I. 2013 No. 675. 22 The Network Rail (North Doncaster Chord) Order 2012 S.I. No. 2635. 23 S.I. 2017 No. 433. 24 S.I. 2016 No. 17.

Page 21: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

19

development consent granted by the Order (Article 3) in order to authorise the

development detailed in Schedule 1.

6.286.27 This Article is confined to the roads which will be maintained as private roads.

Any alteration to those roads, although private, will still require the consent of the

local highway authority who will be concerned to ensure that the arrangement of

streets within the main site is acceptable. A deemed consent provision has been

included to ensure there is a timely route to a decision. This deemed consent

approach was incorporated in The National Grid (Hinkley Point C Connection

Project) Order25.

Article 10 (Permanent stopping up of streets)

6.296.28 This Article makes provision for the stopping up of streets permanently where

a substitute is to be provided. Schedule 4 of the Order has been completed to

identify the street that is to be permanently stopped up subject to this Article (known

as Gravelly Way) and alternative streets to be provided. This is also shown on the

Access and Rights of Way Plans (Document 2.3A and 2.3C).

6.306.29 This Article also makes provision for all rights of way (both public and private)

in the stopped up street to be extinguished and provision is made for the payment

of compensation. The Article is similar to the Article contained in the East Midlands

Gateway Rail Freight Interchange and Highway Order26 save that the East Midlands

Gateway Order also deals with the stopping up of streets for which no substitute is

to be provided, which is not applicable in this case. The power is authorised by

section 120(3) by virtue of the stopping up being related to the authorised

development, as well as section 120(4) and paragraph 17 of Part 1 of Schedule 5

to the 2008 Act.

Article 11 (Temporary stopping up of streets)

6.316.30 This Article deals with the temporary stopping up of streets for the purpose

of carrying out the authorised development. It is included in the Order as it may be

necessary for the undertaker to stop up streets temporarily. As with article 10, in

addition to section 120(3) (i.e. by virtue of any temporary stopping up being related

to the authorised development), the inclusion in the DCO of the power to stop up

these streets is specifically authorised by section 120(4) and paragraph 17 of Part

1 of Schedule 5 to the 2008 Act.

6.326.31 The drafting of this Article generally reflects that provided for by the model

provisions, however, paragraphs 3 and 4(a) of the model provisions have not

been included as it is considered that it is not necessary to specify any streets to

be temporarily stopped up at this stage and it is drafted so that the prior

25 S. I. 2016 No. 49 (for example, Articles 12, 13 and 14). 26 S. I. 2016 No. 17.

Page 22: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

20

consent of the street authority is required before any streets are stopped up

temporarily.

6.336.32 The Article is, in substance, the same as Article 14 of the M20 Junction 10a

Development Consent Order 201727, the only difference being that the earlier order

also included a restriction of use, which it is not necessary to include in this case.

Article 12 (Public rights of way – creation and stopping up)

6.346.33 This Article has been included in the Order to allow for the creation and

stopping up of rights of way affecting land within the Order limits. It is necessary for

a public right of way to be stopped up in order for the authorised development to be

carried out.

6.356.34 Section 136 of the 2008 Act provides that the Order may include the stopping

up of a public right of way provided that an alternative right of way will be provided,

or an alternative is not required.

6.366.35 As part of the authorised development, at the time of writing, there is one

existing public right of way proposed to be stopped up with no substitute

provided. This is footpath Penkridge 29, to the extent shown with a dashed red

line on the Access and Rights of Way Plans (Document 2.3A). There is no

proposed substitute because the footpath does not connect with other footpaths

and is therefore effectively a cul-de-sac terminating in the area which is to

comprise the Croft Lane Community Park to be provided as part of the

authorised development. There is proposed to be the provision of permissive

footpaths throughout the community parks, which, combined with the footpaths

adjacent toa new public footpath linking the onsite road infrastructure and the

canal towpath, will provide extensive accessibility to and throughout the site.

This is further explained in the Applicant’s response to ExQ2.13.7 (Document

15.1) submitted at Deadline 5.

6.376.36 Schedule 5 of the Order identifies the public right of way that is affected by

this Article. Part 1 specifies the extent of the permanent stopping up of footpath

Penkridge 29.

6.386.37 At the time of writing, the Applicant is aware that Staffordshire County Council

made an order on 25 April 2019 to amend the definitive map to add a byway open

to all traffic pursuant to an application from 1998. The order is the subject of ongoing

consultation and, as discussed during the Examination of the DCO and following a

representation received by the County Council that the byway should be a bridleway,

the Applicant has inserted a new provision (amended Article 12(3)) so) to refer to a

public right of way rather than a byway open to all traffic. The provision ensures that

27 S. I. 2017 No. 1202.

Page 23: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

21

if that order is confirmed at any time the byway open to all trafficpublic right of way

shall be stopped up without the need for any further order. The route of the byway

open to all trafficpublic right of way is shown on sheet 7 of the access and rights of

way plans (Document 2.3G) between points A and B. The route of the byway open

to all trafficpublic right of way effectively follows the extent of the currently adopted

public highway known as Gravelly Way until that road turns into a private road

shortly after the railway bridge. The bywayroute then continues until it meets the

bridge over the Canal. There is no proposed substitute because Gravelly Way is

proposed to be stopped up and replaced with the A5/A449 link road which itself will

include a public footway and cycleway. The Applicant proposes a range of

improvements to the private access arrangements to the existing business park

which involves vehicular access from the link road and pedestrian and cycle routes

over the Canal bridge linking to the Canal towpath and the link road.

6.396.38 This Article also provides for the creation of the wholly new public right of

way (i.e. not provided as a result of the stopping up of an existing right of way)

comprised in the authorised development. Part 2 of Schedule 5 specifies the new

public right of way that is to be created. The Schedule fixes terminus points for

the new right of way to be created. The creation of public rights of way is permitted

by section 120(3) of the 2008 Act. The purpose for which the provisions relating

to the creation of the pubicpublic right of way are included in the DCO is to

facilitate the development authorised by the DCO, and therefore its creation is

clearly related to the authorised development.

6.406.39 Some of the paths across the site are to be permissive. This is to allow

flexibility in respect of their alignment during the course of the development and the

finalising of details for the Community Parks. The provision of the permissive paths

is secured by requirement 22 contained in Part 1 of Schedule 2 to the DCO.

Article 13 (Accesses)

6.416.40 The new means of accesses to the main site are identified in Schedule 1

and are part of the highway works covered by Schedule 13. However, to allow

some flexibility, this Article is included to allow for modification of the accesses, or

other means of access to be provided. This is subject to prior agreement with

the relevant highway authority or, in the case of private streets, the street authority.

6.426.41 Paragraph 4 refers to some private means of access which are being closed for

which no substitute is to be provided. These are listed in Part 1 of Schedule 6. The

reasons why no substitute is being provided are set out below.

Private Means of Access Reason why it is no longer required

Field access to the west of the A449

shown with a green dot at point 1 on

This access is being removed in order to

accommodate the relocated A5 laybys.

Page 24: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

22

Private Means of Access Reason why it is no longer required

the Access and Rights of Way Plans

(Document 2.3A and 2.3F)

Access to this land is currently available

from the south via Marsh Farm, which is

not affected by the development.

Field access to the east of the A449

shown with a green dot at point 2 on

the Access and Rights of Way Plans

(Document 2.3A and 2.3F)

This access is an access to land which

will be developed as part of the

authorised development and it will

therefore no longer be required as a field

access.

Field access to the south of the A5

shown with a green dot at point 3 on

the Access and Rights of Way Plans

(Document 2.3A and 2.3B)

This access is an access to land which

will be developed as part of the

authorised development and it will

therefore no longer be required as a field

access.

Access to Clovelly south of the A5

shown with a green dot at point 4 on

the Access and Rights of Way Plans

(Document 2.3A and 2.3B)

This access is an access to land which

will be developed as part of the

authorised development and access

thereto will therefore no longer be

required.

Access to Fir Tree Cottage to the east

of the A449 shown with a green dot at

point 5 on the Access and Rights of

Way Plans (Document 2.3E)

This access is an access to land which

will be developed as part of the

authorised development and access

thereto will therefore no longer be

required.

Field access to the east of the A449

shown with a green dot at point 6 on

the Access and Rights of Way Plans

(Document 2.3E)

This access is an access to land which

will be developed as part of the

authorised development and it will

therefore no longer be required as a field

access.

Access to Croft Farm shown coloured

purple between points FF and GG on

the Access and Rights of Way Plans

(Document 2.3A)

This access is an access to land which

will be developed as part of the

authorised development and access

thereto will therefore no longer be

required.

Access to Calf Heath Quarry shown

coloured purple between points HH

This access is an access to land which

will be developed as part of the

authorised development and access

Page 25: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

23

Private Means of Access Reason why it is no longer required

and II on the Access and Rights of

Way Plans (Document 2.3B)

thereto will therefore no longer be

required.

6.436.42 Paragraph 5 provides for alterations to private means of access to be

carried out (as detailed in Schedule 6) to enable the carrying out and use of the

highway works.

6.446.43 The purpose for which the provisions relating to the creation of private

accesses are included in the DCO is to facilitate the development consented by the

DCO, hence their creation is “related to the authorised development”. The

provisions are therefore permitted by section 120(3) of the 2008 Act.

6.456.44 Article 13 is the same as Article 14 of The East Midlands Gateway Rail Freight

Interchange and Highway Order28 save that –

6.45.16.44.1 a deemed approval provision has been included at Article 13(3); and

6.45.26.44.2 the stage by which the access must be closed, or by which any

replacement, or new, access is to be provided is identified, as provided

for in Articles (4), (5) and (6).

Article 14 (Maintenance of highway works)

6.466.45 This Article is included to provide for the maintenance of the new A5/A449

Link Road and altered public highways following the completion of the relevant

works. It cross refers to the process of certification of commencement of

maintenance by the highway authority upon the issue of the relevant certificates

under the provisions of Parts 2 and 3 of Schedule 13. The Article is based on Article

15 of The East Midlands Gateway Rail Freight Interchange and Highway Order29

but, it is more specific as to the point of which maintenance of the highway works is

the responsibility of the relevant highway authority. In addition the Article also cross

refers to the dedication provisions contained in Parts 2 and 3 of Schedule 13.

6.476.46 This provision is permitted by section 120(3) of the 2008 Act because

maintenance of the highway works is clearly “related” to the consent. The

specification of the highway authorised is authorised by section 120(4) and

paragraph 23 of Part 1 to Schedule 5 of the 2008 Act.

28 S.I. 2016 No. 17. 29 S.I. 2016 No. 17.

Page 26: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

24

Article 15 (Classification of A5/A449 link road)

6.486.47 This Article is based on Articles found in other Development Consent Orders30

and is included to make provision for the classification of the new A5/A449 link road.

The provision to classify the link road is specifically permitted by section 120(3) of

the 2008 Act since the classification of the link road (being part of the authorised

development) is clearly a matter ancillary to the proposed development.

Article 16 (Speed limits)

6.496.48 This Article is based upon Articles in other Development Consent Orders, for

example, the M1 Junction 10a Order31, the Houghton Regis Order32 and the East

Midlands Gateway Rail Freight Interchange and Highway Order 33 . It makes

provision for the lengths of road identified in Schedule 8 to be subject to new speed

limits as set out in that Schedule upon completion of the authorised development,

as if such restrictions were imposed by an order under the Road Traffic Regulation

Act 1984. The article also enables temporary speed limits during construction by

agreement with the relevant traffic authority. The inclusion of the article is permitted

by section 120(3) of the 2008 Act, since the regulation of speed limits on the various

highways is related to the provision of the highway works as part of the authorised

development. The requirement of the various speed limits is also necessarily

related to the classification of the various highways, and is therefore permitted by

section 120(3) of the 2008 Act as a matter ancillary to the proposed development

and by section 120(4) and paragraphs 19 and 20 of Part 1 of Schedule 5 of the 2008

Act.

6.506.49 Paragraph 8 of this Article makes it clear that the new speed limits set by

the Order may be varied in the future by the relevant traffic authority, as they could

have been had they been imposed by an order under the Road Traffic Regulation

Act 1984.

Article 17 (Traffic Regulation)

6.50 This Article provides for the amendments to existing traffic regulation orders

requested by Highways England and consequent on Article 18 (Clearways, No

Waiting and Limited Waiting) and Article 19 (Motor Vehicle Restrictions), as set out

30 e.g. the Heysham to M6 Link Road Order 2013 S.I. 2013 No. 675. 31 The M1 Junction 10a (Grade Separation) Order 2013 S.I. 2013 No. 2808. 32 The Central Bedfordshire Council (Woodside Link Houghton Regis) Development Consent Order 2014

S.I. 2014 No. 2637. 33 S.I. 2016 No. 17.

Page 27: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

25

in Part 1 of Schedule 9. The justification for the amendments sought, provided by

Highways England (in their Deadline 5 submission (REP5-046) is as follows:

“The wide verges of the SRN on the A449 and A5 leave open the option of uncontrolled and

indiscriminate parking by HGVs and other vehicles. This leads to significant safety concerns created by uncontrolled parking – reductions in sighting distances on the main carriageways by indiscriminately parked vehicles, damage to SRN assets by vehicles accessing and egressing the verge, and potential for the depositing of mud and detritus on the live carriageway.

Should the DCO be made and the SRFI delivered this will increase the number of vehicles, particularly HGVs, in the area. The Site-wide HGV Management Plan (document AS-040) is based on the premise that HGV routing and parking falls under its scope. The Plan is intended (among other things) to “provide a strategy for the management of road based HGVs to and from the Site together with the methods and measures by which these will be achieved”. A prohibition on verge parking in the locality of the site is entirely consistent with the Plan’s desired outcomes that seeks to prevent off-site parking. Without such prohibition(s) these outcomes could be undermined. On this basis, and the known pressures on formal roadside facilities, it is probable that indiscriminate verge parking will occur without a suitable prohibition. We would therefore expect to see the existing orders amended to address this and we support the principle of the applicant’s amendments to Schedule 9 of the dDCO in this regard.”

6.51 Copies of the existing orders to be amended are contained in Document 7.8. The

provision is permitted by section 120(4) and paragraph 20 of Part 1 to Schedule 5

of the 2008 Act which deals with the specification of the classes of traffic authorised

to use a highway – in that this is a provision relating to that paragraph (matters

“related to” or “ancillary to” being specifically permitted by section 120(4)).

6.52 The Article also allows for future traffic regulation (with consent of the relevant traffic

authority) which may be necessary for the construction, operation or maintenance

of the authorised development. These powers are similar to those contained in the

Thames Tideway Order34.

Article 18 (Clearways, No Waiting and Limited Waiting)

6.53 Article 18 provides for Clearways, No Waiting and Limited Waiting areas along

lengths of road identified in Parts 2, 3 and 4 of Schedule 9. The Article is based on

The East Midlands Gateway Rail Freight Interchange and Highway Order35 . Similar

to the inclusion of the article authorising traffic regulation, this article is related to the

authorised development and is permitted by section 120(3) of the 2008 Act.

Article 19 (Motor Vehicle Restrictions)

34 The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S. I. 2014 No. 2384, Article

18). 35 S. I. 2016 No. 17.

Page 28: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

26

6.54 Article 19 includes restrictions on use of parts of the highway consequential upon

the highway works as identified in Parts 5 and 6 of Schedule 9. This governs the

various prohibited movements and the proposed one way street along part of

Crateford Lane. The power is clearly required in order to facilitate the authorised

development and implement the prohibited movements. Its inclusion in the DCO is

therefore permitted by section 120(3) of the 2008 Act.

Article 20 (Agreements with Highway Authorities)

6.55 This Article is included to allow the undertaker to enter into agreements with the

relevant highway authority relating to the construction of a new highway, carrying

out of works in the highway, stopping up, alteration or diversion of highways,

maintenance of the structure of any bridge carrying a highway over or under a

railway and landscaping.

6.56 All of the highway works will be carried out in accordance with the powers within the

DCO and the relevant provisions of Schedule 13, however, this Article is included

in the Order as a precautionary measure in relation to any agreements that might

be required with the Highway Authority thus avoiding the need to find an alternative

statutory authority, which may not be fit for purpose. For example, section 278 of

the Highways Act 1980 can authorise works to the public highway, however they

have to be undertaken on behalf of the highway authority and be of public benefit,

which would not necessarily be the case.

6.57 The Article is in the same form as Article 21 of The East Midlands Gateway Rail

Freight Interchange and Highway Order36 with the addition of Article 21(d). The

Applicant considers that the inclusion of this Article is permitted by section 120(3) of

the 2008 Act because it would permit agreements related to the authorised

development or matters ancillary to the authorised development.

PART 4

SUPPLEMENTAL POWERS

Article 21 (Discharge of water)

36 S. I. 2016 No. 17.

Page 29: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

27

6.58 This Article largely reflects the drafting of Article 14 in the general model provisions

and is required to allow for the drainage of the land within the Order limits in

connection with the carrying out and maintenance of the development. Under the

provisions of this Article consent is required from the person who owns the relevant

watercourse, public sewer or drain but such consent may not be unreasonably

withheld. Its inclusion is permitted by section 120(3) as well as section 120(4) and

specifically paragraph 26 of Part 1 to Schedule 5 of the 2008 Act.

6.59 The drafting has been updated from the model provisions to refer to the

Environmental Permitting (England and Wales) Regulations 2016 which supersede

the relevant provisions of the Water Resources Act 1991.

Article 22 (Authority to survey and investigate the land)

6.60 This Article is included to enable the undertaker to enter land within the Order limits

to survey or investigate the land. This drafting broadly reflects that in Article 16 of

the model provisions save for an amendment to paragraph 2, so that notice need

not be served on the undertaker in the event that they are the owner of the land.

The provision is permitted by sections 120(3) and 120(4) of the 2008 Act, and

specifically paragraph 12 of Part 1 to Schedule 5.

PART 5

POWERS OF ACQUISITION

Article 23 (Guarantees in respect of payment of compensation)

6.61 The Applicant has included this Article as security in respect of payment of

compensation for the protection of any interests which are to be compulsorily

acquired. The Article will ensure that no compulsory acquisition can be pursued until

appropriate security for the liabilities of the undertaker to pay compensation in

respect of that acquisition has been provided to the local planning authority, being

South Staffordshire Council. The article is related to the powers for the acquisition

of land and is therefore related to paragraph 1 of Part 1 of Schedule 5 to the 2008

Act. Its inclusion is therefore authorised by section 120(4) of the 2008 Act.

6.62 The requirement to provide a form of security, for potential compensation as a result

of exercising compulsory acquisition powers, is a generally accepted principle which

has been included in various recently approved Orders37. It is considered that 15

years is an appropriate period for the relevant form of security to be in place, since

37 The East Midlands Gateway Rail Freight Interchange and Highway Order 2016 (S.I. 2016 No. 17,

Article 24), The York Potash Harbour Facilities Order 2016 (S.I. 2016 No. 772, Article 23) and The Triton Knoll Electrical System Order 2016 (S.I. 2016 No. 880, Article 37 (4)).

Page 30: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

28

this extends 10 years beyond the final date from which any compulsory acquisition

may be exercised under the DCO.

6.63 The scope of the Article is identical to that contained in The East Midlands Gateway

Rail Freight Interchange and Highway Order38, however, the specific drafting is

informed by the more recent York Potash and Triton Knoll approved Orders. Article

23(3) includes a provision requiring the local planning authority to be furnished with

relevant information when exercising its judgment on the adequacy of the proposed

security, which is identical to the York Potash Order. Article 23(5) is based on the

Triton Knoll Order.

Article 24 (Compulsory acquisition of land)

6.64 This Article will authorise the compulsory acquisition of land identified on the Land

Plans and described in the Book of Reference and is permitted by section 120(4)

and paragraph 1 of Part 1 of Schedule 5 to the 2008 Act, and by section 123 of the

2008 Act...

6.65 This Article also provides for the extinguishment of rights, trusts and incidents to

which the land was previously subject as permitted by paragraph 2 of Part 1 of

Schedule 5 to the 2008 Act..

6.66 Further detail on the rationale for this Article is contained in the Statement of

Reasons (Document 4.11A).

Article 25 (Compulsory acquisition of rights)

6.67 This Article is included to allow the compulsory acquisition of existing rights and

the power to create and acquire compulsorily new rights over the land shown on

the Land Plans and described in the Book of Reference. The land in which new

rights may be created is listed in Schedule 11 by reference to the land plans. The

article is permitted by section 120(4) and paragraphs 139 and 2 of Part 1 to

Schedule 5 of the 2008 Act.

6.68 The Article is based on recently approved provisions in various Development

Consent Orders40. This approach ensures that compulsory purchase is limited only

to the rights that are required.

38 S.I. 2016 No. 17. 39 Paragraph 1 refers to “land” but section 159 of the 2008 Act confirms that in this context, “land” includes

a right in, on, over or under land. 40 e.g. The York Potash Harbour Facilities Order 2016 (S.I. 2016 No. 772), The Triton Knoll Electrical

System Order 2016 (S.I. No 2016 No. 880) and The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014 No. 2384).

Page 31: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

29

6.69 The approach requires a modification to compulsory purchase and

compensation provisions and these are dealt with in Schedule 12 which is

permitted by section 120(5)(a) of the 2008 Act.

Article 26 (Acquisition of part of certain properties)

6.70 This Article follows model provision 26 and covers an alternative procedure where

the undertaker acquires only part of certain types of property, subject to the right

of the owner to require the whole of the property to be acquired, in the even that

part cannot be taken without material detriment to the remainder. The Article

replaces section 8(1) of the Compulsory Purchase Act 1965 and provides a

process and timetable for the dealing of claims of material detriment. The Article

is based on other DCOs such as the Triton Knoll Electrical System Order 201641

and is permitted by section 120(4) and paragraph 1 of Part 1 to Schedule 5, and

by section 123 of the 2008 Act.

Article 27 (Private Rights)

6.71 This Article is largely based on Article 22 of the model provisions, with some

amendments (most notably it applies to private rights generally rather than just

private rights of way). It provides that all private rights over land which is subject to

compulsory acquisition (in respect of the freehold) are extinguished and in respect

of compulsory acquisition of rights, are extinguished to the extent that those rights

are inconsistent with the rights required for the authorised development. This power

is permitted by section 120(4) and paragraph 2 of Part 1 to Schedule 5 of the 2008

Act. The power is also supplementary to articles 24 and 25 and the Applicant

considers that its inclusion is therefore necessary to give full effect to the Order; it

is therefore permitted by section 120(5)(c) of the 2008 Act.

Article 28 (Power to override easements and other rights)

6.72 Article 28 ensures that where the works permitted by the Order interfere with existing

easements or other rights, those rights shall not present an impediment to delivery.

Its purpose is to provide certainty that the carrying out of the authorised

development will not be prevented as a result of any unknown third party rights. It

also ensures that the land is affected to the minimum extent necessary to enable

the delivery of the development.

6.73 The Article provides for compensation to be payable to the beneficiary of any right

that is extinguished, abrogated or discharged. This power is permitted by sections

120(3), 120(4) and paragraphs 2 and 3 of Part 1 to Schedule 5 of the 2008 Act. As

with Article 27, the Applicant considers that the power is supplementary to articles

41 S.I. 2016 No.880

Page 32: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

30

24 and 25 and its inclusion is therefore necessary to give full effect to the Order; it

is therefore permitted by section 120(5)(c) of the 2008 Act.

Article 29 (Compulsory acquisition of land – incorporation of the mineral code)

6.74 By incorporating the ‘mineral code’ this Article exempts the existing minerals under

land being automatically acquired pursuant to the exercise of compulsory

acquisition. It also addresses the situation where an owner wishes to work existing

minerals and provides the undertaker with the ability to compensate the owner for

any inability to do so as a result of the development. The inclusion of the power is

permitted by 120(4) and paragraphs 2 and 3 of Part 1 to Schedule 5 of the 2008 Act.

6.75 As discussed during the Examination of the DCO, the Applicant has amended this

Article so that it is clear which parcels will not be affected by the mineral code.

6.756.76 It is intended that the mineral code will not apply to the parcels ofany land

owned by The Inglewood Investment Companywhich is to proposed to be

compulsorily acquired, or to land where the minerals are specifically noted as being

subject to compulsory acquisition (i.e. land shown tinted pink, hatched pink or tinted

orange on the land plans). This is because the mines/minerals will be acquired

pursuant to those compulsory acquisition powers or through voluntary agreement,

where agreements are concluded and honoured.

Article 30 (Time limit for exercise of authority to acquire land and rights

compulsorily)

6.766.77 This Article imposes a time limit of five years from the date the Order

comes into force for the exercise of compulsory acquisition powers. The time

limit for exercising the compulsory acquisition powers under Part 1 of the

Compulsory Purchase Act is disapplied by section 125(3)(a) of the 2008 Act.

This article imposes a time limit which is linked to the time period in which the

authorised development must commence (see Requirement 1), in accordance

with section 154(3) of the 2008 Act.

Article 31 (Application of Part 1 of the Compulsory Purchase Act 1965)

6.776.78 This Article modifies the provisions of Part 1 of the Compulsory Purchase Act

1965 as applied to the DCO by section 125 of the Planning Act 2008 and deals with

amendments required as a result of the Housing and Planning Act 2016. The

modification of those provisions is permitted by section 120(5)(a) of the 2008 Act.

Article 32 (Application of the Compulsory Purchase (Vesting Declarations) Act 1981)

6.786.79 This Article follows Article 23 of the model provisions to apply for the

application of the vesting declaration procedure to the compulsory acquisition

under the Order. Some of those provisions are changed to clarify that the

Page 33: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

31

“undertaker” will be a “public authority” under the Compulsory Purchase (Vesting

Declarations) Act 1981. It also departs from the model provisions to reflect the

recently enacted amendments to the Compulsory Purchase (Vesting Declarations)

Act 1981 made by the Housing and Planning Act 2016. The application of the

Act is permitted by section 120(5)(a) of the 2008 Act.

Article 33 (Statutory Undertakers and operators of the electronic communications

code network)

6.796.80 This Article allows the undertaker (subject to the protective provisions) to

extinguish rights of statutory undertakers and operators of the electronic

communications code network and to replace, renew, reposition, alter and/or

supplement apparatus belonging the statutory undertakers and operators of the

electronic communications code network within the Order Limits. The inclusion of

the Article is authorised by section 127(2) and (3) of the 2008 Act. The Applicant

considers that any statutory undertakers’ land affected can be replaced (or

relocated/diverted) without serious detriment to the carrying on of the undertaking,

and there are suitable protective provisions proposed in this regard.

Article 34 (Rights under or over streets)

6.806.81 Article 34 gives the Applicant the power to occupy land above or below streets

within the Order limits without having to acquire that land. Compensation is payable

for any loss or damage to structures along the relevant street. The power is required

in order to enable the carrying out of the authorised development and it therefore

permitted by section 120(3) of the 2008 Act.

Article 35 (Temporary use of land for carrying out the authorised development)

6.816.82 This Article allows the Applicant to occupy the land specified in Schedule 10

temporarily while the works are carried out, and also any of the land identified for

the permanent acquisition that has not yet been acquired.

6.826.83 The Article also makes provision for the time limit for return of the land,

restoration and payment of compensation.

6.836.84 Paragraph (10) incorporates section 13 of the Compulsory Purchase Act 1965

and applies it to the temporary use of the land specified in Schedule 10 and

identified on the Land Plans. Section 13, which allows enforcement of possession,

is automatically applied to the powers in Articles 23 – 38 by virtue of Section 125 of

the 2008 Act. The power is required in relation to the temporary use of land to

ensure that the undertaker will be able to enforce the taking of temporary possession

of the land to carry out the relevant works in the event that the owner or occupier

refuses to allow possession.

Page 34: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

32

Article 36 (Temporary use of land for maintaining authorised development)

6.846.85 This Article allows the undertaker to take temporary possession of land within

the Order limits to maintain the authorised development during the 5 year

maintenance period (being the five years from when that part of the development is

first brought into use). The article follows article 29 of the model provisions and its

inclusion in the Order is authorised by virtue of sections 120(3), 120(4) and

paragraph 1 of Part 1 to Schedule 5, and section 125 of the 2008 Act.

Article 37 (Apparatus and rights of statutory undertakers in stopped up streets)

6.856.86 The Article follows Article 32 of the model provisions and protects statutory

undertakers’ rights where their apparatus is under, in, along or across a street which

has been stopped up under the Order.

6.866.87 The Article provides that a statutory undertaker must remove/relocate the

apparatus at the reasonable request of the undertaker (the undertaker bearing the

cost of that relocation). The provision is linked to article 10 and its inclusion is

therefore authorised by sections 120(3) as well as 120(4) and paragraph 14 of Part

1 to Schedule 5 of the 2008 Act, which allows provision for the removal, disposal or

re-siting of apparatus.

Article 38 (No Double Recovery)

6.876.88 This Article is included to cover the well-established principle that a claimant

in a compulsory purchase matter is to be compensated for no more and no less

than the actual loss, and that compensation is not payable for the same loss or

damage under both the DCO and other compensation regimes. The Article is based

on such Articles included in other DCOs such as The Triton Knoll Electrical System

Order42. It is a supplementary provision and its inclusion is authorised by section

120(5)(d) of the 2008 Act as well as sections 120(3) and 120(4) and paragraph 36

of Part 1 to Schedule 5 of the2008 Act.

PART 6

MISCELLANEOUS AND GENERAL

Article 39 (Operation and Use of Railways)

6.886.89 This Article is based on the Article contained within Schedule 2 of the model

provisions (for Railways). It is included because part of the authorised development

comprises the provision of a railway. This Article has been amended from the Article

in the model provisions for Railways to allow only for the carriage of goods as the

42 S.I. 2016 No. 880.

Page 35: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

33

authorised development will not be used for the transport of passengers. The

provision is included pursuant to sections 115 and 120(3) of the 2008 Act.

Article 40 (Operational land for the purposes of the 1990 Act)

6.896.90 This Article declares that land within the Order Limits utilised for the highway

works shall be treated as operational land of a statutory undertaker for the

purposes of the Town and Country Planning Act 1990. The provision is included

pursuant to sections 115 and 120(3) of the 2008 Act.

Article 41 (Charges)

6.906.91 This Article is based on an Article at Schedule 2 of the model provisions (for

Railways). It is included to allow the undertaker to impose charges for the carrying

of goods on the railway, or for other services or facilities connected to its operation.

The Article has been amended from the Article contained in the model provisions,

as the proposed railway is to be used for the carriage of goods only. The provision

is authorised by section 120(4) and paragraph 18 of Part 1 to Schedule 5 of the

2008 Act.

[ Article 42 - Placeholder]

Article 43 (Felling or lopping of trees and removal of hedgerows)

6.916.92 This Article is based upon an Article in the model provisions. It is included

to enable the undertaker to fell or lop any tree hedgerow or shrub near the

authorised development, or cut back its roots, where it believes that it is

necessary to prevent the tree hedgerow or shrub from interfering with the

authorised development, but subject to some exceptions.

6.926.93 The Article makes provision for compensation to be payable for any loss or

damage arising.

Article 4443 (Protective Provisions)

6.936.94 The Article gives effect to the protective provisions which are contained in

Schedule 13, referred to further below.

Article 4544 (Governance of requirements and protective provisions relating to

highway works)

6.946.95 The Article addresses the tension between a desire to maintain flexibility on

details to be approved pursuant to requirements (and, in the case of the highway

works, protective provisions) and the need to ensure that any details approved do

not take the development outside the scope of the authorised development or

beyond the scope of what has been environmentally assessed.

Page 36: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

34

6.956.96 Paragraph (1), for the avoidance of doubt, makes it clear that all initial

approvals under the requirements and Part 2 and 3 of Schedule 13 are governed

by Article 4 and prevents details being approved which lead to a form of

development outside the scope of that which has been assessed. Paragraph (2)

then follows the advice in paragraph 19.4 of Advice Note Fifteen: Drafting

Development Consent Orders and makes it clear that approvals may subsequently

be amended but any changes to approved details must not stray outside the

parameters of what has been assessed. As with Article 4 (see paragraph 6.17.2

above), the dDCO applies the same test as that set out for “subsequent applications”

in Schedule 2 of the Infrastructure Planning (Environmental Impact Assessment)

Regulations 2017.

6.966.97 The approaches taken to the governance of approval of details and

subsequent amendments vary considerably in approved orders.

6.976.98 This Article is consistent with the approaches taken in Article 42 of The East

Midlands Gateway Rail Freight Interchange and Highway Order43, requirement 34

of The White Moss Landfill Order44 and requirement 35 of The Norfolk County

Council (Norwich Northern Distributor Road (A1067 to A47(T))) Order45.

6.986.99 It is felt preferable that an overarching provision such as that contained in this

Article 4544 should be within an Article rather than in the requirements. This is

logically the case since the paragraph covers Schedule 13 in addition to the

requirements in Schedule 2.

6.996.100 It is very important that the flexibility that is allowed for is retained. If no

provision is made for details to be approved subsequently and varied (within the

constraints referred to) then this development will be substantially disadvantaged in

comparison to other large scale distribution sites and its ability to compete with other

sites for footloose occupiers would be adversely affected.

6.1006.101 The opportunity is taken in this Article to make it absolutely clear that the

requirements are, unless otherwise stated, to be enforced by the local planning

authority.

Article 4645 (Disapplication, application and modification of legislative

provisions)

6.1016.102 This Article seeks, as permitted by section 120(5) of the 2008 Act, to

incorporate and modify legislative provisions which are necessary for carrying out

the authorised development.

43 S.I. 2016 No. 17. 44 S.I. 2015 No.1317. 45 S.I. 2015 No.1347.

Page 37: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

35

6.1026.103 Article 4645(1) disapplies the need for some additional consents to make use

of the ‘one stop shop’ and avoid the need to obtain a separate consent governing

the same development.

6.1036.104 Article 4645(2) provides that the provisions in the Neighbourhood Planning

Act 2017 relating to temporary possession do not apply to the temporary possession

of land under Articles 35 and 36 of the DCO. The rationale for this is that these

provisions have not yet come into force. It is therefore considered appropriate to

apply the temporary possession regime which has been included in numerous

DCOs and Orders made under the Transport and Works Act 1992 to date. It is noted

that this approach has also been taken in respect of the draft DCOs submitted in

respect of the applications for Tilbury 2, Milbrook Power (Gas Fired Power Station)

and the A19/A184 Testos Junction Improvement.

6.1046.105 Article 4645(3) provides that development carried out pursuant to a planning

permission following implementation of the DCO would not be in breach of the DCO,

ensuring no risk of criminal liability pursuant to section 161 of the 2008 Act. The

paragraph encompasses any development authorised by a general development

order as well as an express planning permission. This follows Article 5 (2) of The

East Midlands Gateway Rail Freight Interchange and Highway Order46.

6.1056.106 Article 4645(4) disapplies Regulation 4 of the Town and Country Planning

(Control of Advertisements) (England) Regulations 2007 and allows for

advertisements to be approved by the local planning authority under the relevant

requirement in Schedule 2, rather than the need for any separate consent.

6.1066.107 Article 4645(5) disapplies the community infrastructure levy (CIL) provisions

to ensure there are no unforeseen liabilities on the undertaker arising from any CIL

yet to be introduced. It is common for CIL to be disapplied in DCO47.

6.1076.108 Article 4645(6) disapplies the statutory defence for nuisance provided by

section 158 of the 2008 Act, as permitted by section 158(3) of the 2008 Act. The

Applicant has agreed to remove the statutory defence to nuisance following

discussions with South Staffordshire District Council and has therefore removed that

provision from the DCO (having previously been included at Article 42). Article

4645(6) is included to confirm the disapplication of the defence contained in section

158 of the 2008 Act.

6.1086.109 Article 4645(7) refers to Schedule 14 and a miscellany of controls and

applies/modifies and/or amends them as appropriate to ensure that they facilitate or

46 S.I. 2016 No. 17. 47 See for example, Thames Tideway Tunnel, Article 14 and National Grid Hinkley Point C Connection.

Page 38: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

36

do not constrain the development. This is based on the approach taken in the

Thames Tideway Tunnel Order48.

6.1096.110 Article 4645(8) ensures that anything permitted as a result of the provisions

of this Article 4645(1) to (7) does not prevent the operation of the 2017 EIA

Regulations, as suggested in Advice Note 15: Drafting Development Consent

Orders.

Article 4746 (Certification of plans and documents)

6.1106.111 This Article reflects the drafting of the model provisions and specifies (with

reference to Schedule 15) the plans and documents that must be submitted, as soon

as practicable following the making of the order, to the decision maker to be certified

as a true copy. The documents listed in Schedule 15 are those referred to in the

draft Order.

Article 4847 (Service of Notices)

6.1116.112 This Article is a departure from the model provisions. It is included to ensure

certainty regarding the procedure for service of any notice required by the Order, for

example, under Article 22 (authority to survey and investigate the land). The Article

is included pursuant to section 120(3) of the 2008 Act.

Article 4948 (Arbitration)

6.1126.113 This Article reflects that contained in the model provisions and is included in

case of any dispute regarding the provisions of this Order unless an alternative

dispute resolution is specifically referred to. The provision is included pursuant

to sections 120(3) and 120(4) and paragraph 37 of Part 1 to Schedule 5 of the 2008

Act.

6.1136.114 The Article was amended in a previous version of the DCO (Document 3.1A)

to reflect the various bodies to which specific matters are to be referred. It has been

amended in the latest version of the DCO (Document 3.1D) so that it does not apply

to decisions taken by the Secretary of State under the Order.

SCHEDULES

Schedule 1 (Authorised Development)

6.1146.115 This Schedule describes the authorised development for which Development

Consent is sought, including associated development. The NSIP and Associated

Development are identified separately.

48 The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014 No. 2384).

Page 39: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

37

6.1156.116 The Works are summarised below.

NSIP

Works No 1

This is the new rail infrastructure works from the existing West Coast Main Line

Loop to connect to the new rail terminal to be provided in Works No 2. This includes

the alteration of some of the existing rail track and the provision of additional rail

infrastructure.

Works No 2

This is the construction of the new rail freight terminal and rail tracks to connect with

Works No 1. It includes the provision of freight storage areas, rail sidings, refuelling

and maintenance areas, earthworks and other administrative buildings etc.

Works No 3

This is the construction of the rail served warehousing along with ancillary

development such as buildings, service yards, storage areas and infrastructure to

serve.

Works No 4

The A5/A449 Link Road through the site which is to become an adopted road and

the removal of the existing masonry bridge over the West Coast Main Line Loop.

Works No 5

The provision of internal estate (private) roads, footpaths and cycle tracks and site

accesses.

Associated development

Works No 6

This comprises structural landscaping surrounding the built development and

includes two community parks being one in the northern part of the site (Croft Lane

Community Park) and one in the southern part (Calf Heath Community Park). It also

provides for the remediation works required on part of the Order Limits (the SI Land

(as defined in Article 2)).

Works No 7

These works are the highway works around the periphery of the site the totality of

which is shown on the highway general arrangement plans (Document 2.9) and

associated landscaping and related works.

Works No 8

Page 40: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

38

These works relate to the Gravelly Way Farm buildings and authorise the

conversion and use of the buildings, and new build, for the purposes of estate

management offices, amenity and welfare facilities with ancillary parking and

landscaping. Details of the conversion and new build will need to be submitted to

and approved by the local planning authority pursuant to requirement 3 (3).

Works 9a

These works provide for the removal and undergrounding of the 132kv tower

situated to the north of the A5 and includes temporary access and accommodation

for the demolition of the existing tower and the construction of the new tower.

Works 9b

These works provide for the removal and undergrounding of the 132kv tower

situated to the north of Straight Mile and includes temporary access and

accommodation for the demolition of the existing tower and the construction of the

new tower.

Works 10a

These works are the alternative access arrangements for the SI Facility (as defined

in Article 2) as well as the provision of access to Works No. 3 (Zone A3) and Works

No. 8.

Works 10b

These works comprise the revised access arrangements to Four Ashes industrial

area. The current access off Gravelly Way will be demolished and replaced by a

new access round connecting to the new A5/A449 Link Road. The works also

include a new cycle path and footpath link to connect to the canal towpath.

Works 11

This provides for the retention of the residence known as Straight Mile Farm which

will remain within the Order Limits. This Works provides a curtilage providing a

garden area for the residential property.

Works 12

These works provide for an improved access to Avenue Cottages from the A5

including the provision of a turning area.

Page 41: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

39

6.1166.117 Schedule 1 also includes “Further Works” being diverse items the precise

locations of which it is not possible to identify at this stage49. These “Further Works”

are not location specific because they relate to items, the precise location of which

is not ascertainable at this stage, such as the location of sub-stations, which is

subject to more detailed engineering, or are items whose location may change, such

as temporary concrete batching plants.

6.1176.118 These works have been divided into four separate sections of further works.

These apply additional, further, works to:

6.117.16.118.1 firstly, Works Nos. 1 to 3 being the rail infrastructure, rail terminal and warehouses;

6.117.26.118.2 secondly, Works Nos. 1 to 6 and Works No. 8, being the above and principal on site infrastructure,

6.117.36.118.3 thirdly, Works No.s 4, 5, 7, 10a, 10b and 12 being the highway works; and

6.117.46.118.4 fourth and finally, the Works which would include the public right of way (byway open to all traffic, and/or bridleway), if the order amending the definitive map is confirmed (see paragraph 6.3837 above).

6.1186.119 All the “Further Works” are subject to the proviso contained in Schedule 1 that

they do not give rise to any new or materially worse significant environmental effects

not assessed in the environmental statement.

6.1196.120 The above approach is consistent with the other approved Rail Freight DCO

and is necessary to provide flexibility for the development in advance of knowing

the occupiers’ requirements and the ultimate layout. The details of these works will

be the subject of approval under the provisions of the requirements in Schedule 2.

Schedule 2 (Requirements)

6.1206.121 As permitted by section 120(1) and (2) of the 2008 Act, the DCO also includes,

requirements to govern the authorised development. The requirements are set out

in Schedule 2 of the draft DCO. These have had regard to the drafting of conditions

in planning permissions granted for similar schemes and also the requirements

contained in The Daventry International Rail Freight Interchange Alteration Order50

49 This approach is consistent with other approved DCO e.g. The Lancashire County Council (Torrisholme

to the M6 Link (A683 Completion of Heysham to M6 Link Road)) Order 2013 S.I. 2013 675), The Daventry International Rail Freight Interchange Order S.I. 2014 1796 and The East Midlands Gateway Rail Freight Interchange and Highway Order 2016 S.I. 17.

50 S.I. 2014 No. 1796.

Page 42: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

40

and The East Midlands Gateway Rail Freight Interchange and Highway Order51.

They are, however, bespoke for the particular development proposed. The

objective of these requirements is self-explanatory.

6.1216.122 The requirements are set out below, along with an explanation, where helpful::

Time limit (for commencing the authorised development) (Requirement 1)

Phases of development (Requirement 2)

This requirement sets out the details which must be included in the phasing

scheme.

Detailed Design Approval (Requirement 3)

This requirement ensures that no development may take place on a phase

until the details for that phase have been approved. The requirement sets

out the various details which must be approved, if they are contained within

that phase. The details must be in accordance with the principles contained

in the Design & Access Statement (Document 7.5).

Demolition and Construction Environmental Management Plan

(Requirement 4)

This requirement prevents any phase of development commencing

(excluding archaeology or ground investigations) until a demolition and

construction environmental management plan (“DCEMP”) has been

approved for that phase. The requirement sets out the detail to be included

in each DCEMP, which must comply with the Outline Demolition and

Construction and Environmental Management Plan, and requires that each

phase of development be carried out in accordance with its approved

DCEMP.

Rail (Requirement 5 and Part 2)

Originally the rail provisions were included in the draft section 106

Agreement which was under discussion with the local authorities at the time

of the first DCO Hearing (ISH1). At ISH1 the question arose as to whether

or not the rail requirements were more appropriately to be included in the

DCO, given the central nature of those requirements to the NSIP

development. Following ISH1 it was agreed with the local authorities that the

rail requirements should be contained within the DCO. Accordingly, the

appropriate provisions are now included in the draft DCO.

In summary, the Requirement:

51 S.I. 2016 No. 17.

Page 43: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

41

• commits the Applicant to apply for, and progress, applications for the

consents and approvals required for the construction of the terminal;

• ensures the delivery of the terminal by preventing the occupation of more

than 186,000 sqm of warehousing prior to the terminal being completed;

• requires the completion of the rail terminal within six years of the

occupation of more than 47,000 sqm;

• enables the Applicant to seek a review of the above requirements in the

event of a delay due to matters outside the Applicant’s control;

• provides that the terminal once completed must be kept available for use;

and

• requires the Applicant to appoint a rail freight co-ordinator to report on

progress in connection with the rail terminal

Part 2 includes an expanded process for determining whether or not a

deferral in the delivery of the rail terminal is justified. Further detail of this is

referred to in the Applicant’s Post Hearing Submissions (ISH6) (Document

16.3).

Construction Hours (Requirement 6)

This requirement places restriction on the hours during which construction

may take place.

Air Quality – Operational Emissions (Requirement 7 )

This requirement controls the occupation of any warehouse or the rail

terminal until details of any combustion plant where the single or combined

NOx emission is greater than 5mg/second have been approved and any

mitigation measures outlined where necessary.

Archaeology (Requirement 8)

This requirement provides for archaeological investigation for recording

purposes in respect of each phase.

Cultural Heritage – Demolition of Heritage Assets (Requirement 9)

This requirement governs the demolition of Woodside Harm House and its

associated structures and provides for a scheme of historic building

recording.

Cultural Heritage – Demolition of Canal Crossings (Requirement 10)

The requirement controls the timeframe for the demolition of the canal

crossings.

Ecological Mitigation and Management Plan (Requirement 11)

Page 44: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

42

This requirement ensures that no phase of the development which

incorporates ecological mitigation or management may commence until a

written ecological mitigation and management plan has been approved and

requires that any development must be carried out in accordance with that

approved plan.

Ground Conditions – Contamination Risk (Requirements 12 and 13)

These requirements ensure that no phase of the development (excluding

highway works on existing highways which are governed by the protective

provisions) may commence until a contamination report for that phase has

been approved and any necessary further investigation carried out. The

requirements provide that the development must be carried out in

accordance with the details submitted and approved.

Earthworks (Requirement 14)

This requirement ensures that no phase of the development (excluding

highway works on existing highways which are governed by the protective

provisions) may commence until the details set out in that requirement are

approved. The requirement provides that the development must be carried

out in accordance with the approved details.

Landscape – Written Landscaping Scheme (Requirement 15)

This requirement ensures that no phase of the development which

incorporates landscaping mitigation may commence until a written

landscaping mitigation scheme has been approved and requires that any

development must be carried out in accordance with that approved scheme.

Landscape – Implementation and Maintenance of Landscaping Works

(Requirement 16)

This requirement ensures that the landscaping must be implemented and

maintained in accordance with the scheme approved in requirement 15.

Landscape – Phasing of Landscaping and Ecology Works (Requirement

17)

This requirement ensures that certain landscaping works are completed by

a certain stage of the development.

Height of Containers (Requirement 18)

This requirement restricts the height of any stack of containers to 12 metres.

Lighting Details (Requirement 19)

This requirement prohibits any phase of development which contains

artificial lighting from commencing until a lighting scheme has been

Page 45: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

43

approved. The requirement provides that the lighting scheme must be

implemented as approved and further ensures that any lighting in the vicinity

of the bat hop-overs must be in accordance with the principles set out in the

framework ecological mitigation and management plan.

Noise – Construction Stage (Requirement 20)

The requirement sets out the maximum noise levels during construction

hours and provides a procedure for dealing with complaints.

Noise – Operational Stage (Requirement 21)

The requirement ensures that certain measures must be adhered to during

operation and provides a procedure for dealing with complaints.

Permissive Paths (Requirement 22)

This requirement ensures that no phase containing permissive paths may

be commenced until a scheme for their provision has been approved and

provides that the scheme must be implemented and maintained during the

operation of the development.

Transport – Demolition and Construction (Requirement 23)

This requirement governs traffic management for the construction of the

authorised development including the installation, maintenance and removal

of temporary signage.

Transport – Phasing of Highway Works (Requirement 24)

Requirement 24 controls the timing for the completion of the various highway

works.

Water and Flood Risk – Flood Risk Assessment (Requirement 25)

This requirement ensures that the development is carried out in accordance

with the flood risk assessment submitted with the Application.

Water and Flood Risk – Surface Water Drainage Scheme (Requirement

26)

The requirement prohibits any phase of development commencing

(excluding archaeology works) until a surface water drainage scheme has

been approved and requires that the scheme is implemented and

maintained.

Water and Flood Risk – Foul Water Drainage (Requirement 27)

This requirement ensures that a foul water drainage scheme is approved

prior to the commencement of development of a warehouse or the rail

terminal and secures the implementation of that scheme.

Page 46: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

44

Building Sustainability (Requirement 28)

The requirement imposes compliance with BREEAM 2011 “Very Good” in

respect of the construction of each warehouse.

Waste Management During the Operational Phase (Requirement 29)

This requirement prevents the bringing into use of any warehouse,

community park or the rail terminal until a waste management scheme for

that relevant part during the operational phase is approved and requires the

implementation and maintenance of that scheme for the duration of the

operation of that part.

Schedule 3 (Streets subject to Street Works)

6.1226.123 This Schedule lists the streets which are to be subject to the street works

pursuant to Article 8.

Schedule 4 (Streets to be permanently stopped up)

Part 1 - Streets to be permanently stopped up for which a substitute is to be

provided

6.1236.124 This Part of Schedule 4 lists the street which is to be stopped up pursuant

to Article 10 and details the substitution for that street with reference to the

Access and Rights of Way Plans.

Part 2 – Streets to be permanently stopped up and to become private streets

6.1246.125 This Part of Schedule 4 lists the street which is to be stopped up pursuant

to Article 10 and details the part of that street which is to become a private street

with reference to the Access and Rights of Way Plans.

Schedule 5 (Public Rights of Way to be Stopped Up)

Part 1 - Public Rights of Way to be Stopped Up for which no substitute is to be

provided.

6.1256.126 This Part details the public right of way which is to be stopped up pursuant

to Article 12 with reference to the Access and Rights of Way Plans.

Part 2 – New Public Right of Way to be Created.

Page 47: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

45

6.1266.127 This Part lists the new public right of way which is to be created pursuant

to Article 12 with reference to the Access and Rights of Way Plans and states

when the right of way will be delivered as part of the authorised development.

Schedule 6 (Private Means of Access)

Part 1 – Private Means of Access to be Closed for which no Substitute is to be

Provided

6.1276.128 This Part details the private means of accesses which are to be stopped up

pursuant to Article 13 and not replaced, with reference to the Access and Rights of

Way Plans.

Part 2 – Private Means of Access to be Closed and for which a substitute is to be

provided

6.1286.129 This part details the private means of access which are to be stopped up

and replaced pursuant to Article 13 with reference to the Access and Rights of

Way Plans.

Part 3 – New private means of Access Created

6.1296.130 This Part sets out the new private means of access which are to be provided

as part of the authorised development.

Schedule 7 (Classification of Roads) – New Roads

6.1306.131 This Part sets out the classification of the new A5/A449 Link Road.

Schedule 8 (Speed Limits)

6.1316.132 This Schedule sets out the new speed limits which will apply following the

completion of the works.

Schedule 9 (Traffic Regulation)

Part 1 - Amendments to Existing Orders

6.1326.133 This Part deals with any necessary amendments to existing Traffic

Regulations Orders.

Part 2 – Clearways

Page 48: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

46

6.1336.134 This Part describes the lengths of road to be subject to a new order for

clearways.

Part 3 – No waiting at any time

6.1346.135 This Part describes the lengths of road to be subject to a new order prohibiting

waiting at any time.

Part 4 – Limited Waiting

6.1356.136 This Part deals with a limited waiting order created on the new laybys created

on the A449.

Part 5 – Prohibited Movements

6.1366.137 This Part describes the newly prohibited movements consequent upon the

highway works.

Part 6 – One Way Streets

6.1376.138 This Part deals with the imposition of a one way street order on Crateford

Lane, adjacent to the A449.

Schedule 10 (Land for temporary possession)

6.1386.139 This Schedule sets out the land of which temporary position may be taken as

referred to in Article 35.

Schedule 11 (Land in which new rights may be created)

6.1396.140 This Schedule lists the parcels of land over which only new rights may be

created.

Schedule 12 (Modification of compulsory purchase enactments)

6.1406.141 This Schedule modifies provisions for compensation following the creation of

new rights.

Schedule 13 (Protective provisions)

6.1416.142 Schedule 13 includes provisions to protect the interests of various bodies

whose assets may be affected by the proposed development. These will comprise:

Page 49: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

47

Part 1: Network Rail

The protective provisions included in the draft DCO are based on

Network Rail’s standard provisions with some minor amendments,

mainly being the provision to allow acquisition of the bridge carrying the

existing Gravelly Way which is to be removed as part of the

development (paragraph 4(4)). The ownership of the bridge is unclear

and the Applicant must therefore secure the rights to remove the bridge

by compulsory acquisition. As explained in the Statement of Reasons

(Document 4.1), and confirmed in the protective provisions (paragraph

4(1)) the Applicant is not seeking compulsory acquisition of land owned

by Network Rail.

The protective provisions have been discussed with Network Rail but

they have not yet indicated agreement to them.

Part 2: Highways England

The provisions of Part 2 (and 3 – see below) of Schedule 13 contain

protective provisions to protect the interests of the highway authorities,

being Highways England and Staffordshire County Council. These

provisions govern the carrying out of the highway works and obviate the

need for any further agreements, such as agreements pursuant to s.38

and s.278 of the Highways Act 1980 which would be the usual manner

of governing highway works.

These Part 2 provisions have been extensively discussed with

Highways England and are agreed subject to :

the issue of deemed consent. which the Applicant addressed

in a note in Appendix 3 of the Applicant’s Responses to Other

Parties Deadline 2 Submissions (REP-007); and

agreement on .the amount of the Bond Sum and Cash Surety.

Information was supplied to HE on 24th May 2019 and a

response is awaited.

Part 3: Staffordshire County Council as Highway Authority

The provisions have been the subject of ongoing discussion with the

County Council andwhich has now concluded. They are agreed in full.

Page 50: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

48

Part 4: Western Power Distribution Limited

The provisions included in the draft DCO are agreed with Western

Power Distribution Limited as the electricity undertaker for the site.

These will cover the undergrounding of the electricity cables and also

the protection of other WPD apparatus in the site (for example, at the

Four Ashes industrial area). The provisions are agreed with WPD as

confirmed in their Relevant Representation (AS-008).

Part 5: Users of the Four Ashes Access Roundabout

These provisions are included for the benefit of those users of the

existing private access to the Four Ashes industrial area, or those with

apparatus in that land with rights of access for maintenance thereof.

They have the subject of lengthy discussions with those parties. At the

time of writing, the Applicant awaits responses from some of the parties,

but believes the provisions contained in the dDCO submitted for

Deadline 5 (Document 3.1C) represent the final version which will be

the subject of agreement with all parties.

Part 6: SI Group

These provisions are agreed with SI Group and relate to the agreement

reached between SI Group and the undertaker with regard to land within

the Order limits owned by SI Group which is the subject of ongoing

groundwater remediation.

Part 7: Canal and River Trust

The provisions have been discussed with the Canals and Rivers Trust

(“CRT”), and are agreed with the exception of the inclusion of an

indemnity for CRT in relation to loss of future income from tenants,

which for reasons set out in the DCO Tracker submitted at Deadline 3

(Document 3.4A), the Applicant does not feel appropriate.

Part 8: Cadent Gas Limited

These provisions are agreed with Cadent Gas as the gas undertaker for

the site as confirmed in their Relevant Representation (AS-007)..).

Part 9: General provisions for the protection of operators of the Electronic

Communications Code Network

Page 51: THE WEST MIDLANDS RAIL FREIGHT INTERCHANGE ORDER … · 2019-07-22 · rail requirements should be contained within the DCO. Accordingly, the appropriate provisions are now included

The West Midlands Rail Freight Interchange Order 201X

Explanatory Memorandum

Document 3.2B

Eversheds Sutherland (International) LLP

19 July 2019

49

These provisions are based on provisions for such operators, used in

other Orders. They are the subject of current discussions with mast

operators in respect of the relocation of the existing masts on the site.

Part 10: General provisions for the protection of Water and Sewerage

Undertakers

These provisions are based on provisions for such operators, used in

other Orders. They will operate to protect the interests of water and

sewerage undertakers with apparatus within the Order limits. It is

thought sensible to include these provisions given the size of the site

and the existence of utilities apparatus. Attempts have been made to

engage withA response is awaited from South Staffordshire Water but

no response has been received on the provisions at the time of writing.

Schedule 14 (Miscellaneous Controls)

6.1426.143 This Schedule sets out various legislative provisions which are modified or

excluded from application to the DCO.

Schedule 15 (Certification of Plans and Documents)

6.1436.144 This Schedule lists the various plans and documents that are to be certified

by the Secretary of State for the purposes of the DCO. The documents listed are

those referred to in the draft Order.

Eversheds Sutherland (International) LLP

19 July 2019


Recommended