The World Bank
FOR OFFICIAL USE ONLY
PROJECT APPRAISAL DOCUMENT (QER STAGE)
ON A
PROPOSED IBRD LOAN
IN THE AMOUNT OF US$ 270 MILLION
AND A
PROPOSED CLEAN TECHNOLOGY FUND (CTF) LOAN
IN THE AMOUNT OF US$ 30 MILLION
TO THE
POWERGRID CORPORATION OF INDIA LIMITED
FOR
TRANSMISSION FOR POWER EVACUATION FROM SOLAR PARKS PROJECT
(P156974)
DECEMBER 16, 2015
Vice President: Annette Dixon, SARVP
Country Director: Onno Ruhl,
Practice Manager:
Senior Global Practice Director:
Julia Bucknall, GEEDR
Anita Marangoly George, GEEDR
Task Team Leader: Mohua Mukherjee, GEEDR
This document has a restricted distribution and may be used by recipients only in the performance of
their official duties. Its contents may not otherwise be disclosed without World Bank authorization.
i
ABBREVIATIONS AND ACRONYMS
ADB Asian Development Bank
AIS Activity Initiation Summary
AT&C Aggregate Technical and Commercial
BOO Build Own Operate
BOOT Build Own Operate Transfer
CEA Central Electricity Authority
CFA Central Financial Assistance
CPS Country Partnership Strategy
CTF Clean Technology Funds
DFID Department for International Development
DLI Disbursement Linked Indicator
Discoms Electricity distribution companies
ESSA Environmental and Social Systems Assessment
FITs Feed in Tariffs
FIL Financial Intermediary Loan
FM Financial Management
GEF Global Environment Facility
GHG Green House Gas
GoI Government of India
GRPV Grid connected rooftop solar PV
GW Gigawatts
GRSPP Grid-connected Rooftop and Small Power Plant
IBRD International Bank for Reconstruction & Development
IPF Investment Project Financing
IPP Independent Power Producer
IREDA Indian Renewable Energy Development Agency
JNNSM Jawaharlal Nehru National Solar Mission
Kwh Kilowatt-Hour
MNRE Ministry of New & Renewable Energy
MOP Ministry of Power
MW Megawatts
NDMC New Delhi Municipal Corporation
NAPCC National Action Plan on Climate Change
OM Operational Manual
O&M Operate and Maintain
PAP Program Action Plan
PDO Program Development Objective
PforR Program for Results
PIU Program Implementation Unit
PPA Power Purchase Agreement
PV Photovoltaics
SBI State Bank of India
SECI Solar Energy Corporation of India
SERC State Electricity Regulatory Commissions
ii
SNA State Nodal Agencies
TA Technical Assistance
UNDP United Nations Development Programme
UNIDO United Nations Industrial Development Organization
WBG World Bank Group
iii
INDIA
TRANSMISSION FOR POWER EVACUATION FROM SOLAR PARKS (P156974)
TABLE OF CONTENTS
Page
I. STRATEGIC CONTEXT .................................................................................................1
A. Country Context ............................................................................................................ 1
B. Sectoral and Institutional Context ................................................................................. 1
C. Higher Level Objectives to which the Project Contributes .......................................... 5
II. PROJECT DEVELOPMENT OBJECTIVES ................................................................6
A. PDO............................................................................................................................... 6
B. Project Beneficiaries ..................................................................................................... 6
C. PDO Level Results Indicators ....................................................................................... 6
III. PROJECT DESCRIPTION ..............................................................................................7
A. Project Components ...................................................................................................... 8
B. Project Financing .......................................................................................................... 8
C. Lessons Learned and Reflected in the Project Design .................................................. 9
IV. IMPLEMENTATION .......................................................................................................9
A. Institutional and Implementation Arrangements .......................................................... 9
B. Results Monitoring and Evaluation ............................................................................ 10
C. Sustainability............................................................................................................... 10
V. KEY RISKS AND MITIGATION MEASURES ..........................................................11
A. Overall Risk Rating Explanation ................................................................................ 11
VI. APPRAISAL SUMMARY ..............................................................................................12
A. Economic and Financial Analysis ............................................................................... 12
B. Technical ..................................................................................................................... 14
C. Financial Management ................................................................................................ 14
D. Procurement ................................................................................................................ 15
E. Environment & Social (including Safeguards) ........................................................... 15
F. World Bank Grievance Redress .................................................................................. 16
Annex 1: Results Framework and Monitoring .........................................................................18
iv
Annex 2: Detailed Project Description .......................................................................................21
Annex 3: Implementation Arrangements ..................................................................................31
Annex 4: Implementation Support Plan ....................................................................................43
Annex 5: Economic Analysis .......................................................................................................46
Annex 6: Clean Technology Fund (CTF) Annex ......................................................................53
.
v
PAD DATA SHEET
India
Transmission for Power Evacuation from Solar Parks (P156974)
PROJECT APPRAISAL DOCUMENT .
SOUTH ASIA
0000009260
Report No.: PAD1660 .
Basic Information
Project ID EA Category Team Leader(s)
P156974 B - Partial Assessment Mohua Mukherjee
Lending Instrument Fragile and/or Capacity Constraints [ ]
Investment Project Financing Financial Intermediaries [ ]
Series of Projects [ ]
Project Implementation Start Date Project Implementation End Date
01-Mar-2016 31-Dec-2020
Expected Effectiveness Date Expected Closing Date
31-Dec-2020
Joint IFC
No
Practice
Manager/Manager
Senior Global Practice
Director Country Director Regional Vice President
Julia Bucknall Anita Marangoly George Onno Ruhl Annette Dixon .
Borrower: Department of Economic Affairs
Responsible Agency: Power Grid Corporation of India Limited
Contact: B Mishra Title: Executive Director
Telephone No.: 0124-2571700 Email: [email protected] .
Project Financing Data(in USD Million)
[ X ] Loan [ ] IDA Grant [ ] Guarantee
[ ] Credit [ ] Grant [ ] Other
Total Project Cost: 600.00 Total Bank Financing: 270.00
CTF 30.00
Financing Gap: 0.00 .
vi
Financing Source Amount
Borrower 300.00
International Bank for Reconstruction and
Development
270.00
Clean Technology Fund 30.00
Total 600.00 .
Expected Disbursements (in USD Million)
Fiscal
Year
2016 2017 2018 2019 2020 2021 0000 0000 0000 0000
Annual 30.00 90.00 180.00 180.00 120.00 0.00 0.00 0.00 0.00 0.00
Cumulati
ve
30.00 120.00 300.00 480.00 600.00 600.00 0.00 0.00 0.00 0.00
.
Institutional Data
Practice Area (Lead)
Energy & Extractives
Contributing Practice Areas
Cross Cutting Topics
[ X ] Climate Change
[ ] Fragile, Conflict & Violence
[ ] Gender
[ ] Jobs
[ X ] Public Private Partnership
Sectors / Climate Change
Sector (Maximum 5 and total % must equal 100)
Major Sector Sector % Adaptation
Co-benefits %
Mitigation
Co-benefits %
Energy and mining Other Renewable Energy 20 100
Energy and mining Transmission and
Distribution of
Electricity
80 100
Total 100
I certify that there is no Adaptation and Mitigation Climate Change Co-benefits information
applicable to this project. .
Themes
Theme (Maximum 5 and total % must equal 100)
vii
Major theme Theme %
Financial and private sector development Infrastructure services for private sector
development
70
Public sector governance Other public sector governance 30
Total 100 .
Proposed Development Objective(s)
The project development objective is “to evacuate power from the selected solar generation parks to the
Inter-State Transmission System”. .
Components
Component Name Cost (USD Millions)
0.00 .
Systematic Operations Risk- Rating Tool (SORT)
Risk Category Rating
1. Political and Governance Low
2. Macroeconomic Low
3. Sector Strategies and Policies Moderate
4. Technical Design of Project or Program Low
5. Institutional Capacity for Implementation and Sustainability Low
6. Fiduciary Low
7. Environment and Social Moderate
8. Stakeholders Moderate
9. Other
OVERALL Moderate .
Compliance
Policy
Does the project depart from the CAS in content or in other significant
respects?
Yes [ ] No [ X ]
.
Does the project require any waivers of Bank policies? Yes [ ] No [ X ]
Have these been approved by Bank management? Yes [ ] No [ ]
Is approval for any policy waiver sought from the Board? Yes [ ] No [ X ]
Does the project meet the Regional criteria for readiness for implementation? Yes [ X ] No [ ] .
Safeguard Policies Triggered by the Project Yes No
Environmental Assessment OP/BP 4.01 Yes
viii
Natural Habitats OP/BP 4.04 Yes
Forests OP/BP 4.36 Yes
Pest Management OP 4.09 No
Physical Cultural Resources OP/BP 4.11 Yes
Indigenous Peoples OP/BP 4.10 Yes
Involuntary Resettlement OP/BP 4.12 Yes
Safety of Dams OP/BP 4.37 No
Projects on International Waterways OP/BP 7.50 No
Projects in Disputed Areas OP/BP 7.60 No .
Legal Covenants
Name Recurrent Due Date Frequency
Description of Covenant
.
Conditions
Source Of Fund Name Type
Description of Condition
Team Composition
Bank Staff
Name Role Title Specialization Unit
Mohua Mukherjee Team Leader
(ADM
Responsible)
Senior Energy
Specialist GEEDR
Arun Kumar Kolsur Procurement
Specialist
Senior Procurement
Specialist GGODR
Savinay Grover Financial
Management
Specialist
Sr Financial
Management
Specialist
GGODR
Amit Jain Team Member Energy Specialist GEEDR
Bipulendu Narayan
Singh
Team Member Energy Economist GEEES
Joonkyung Seong Team Member CTF Specialist GEEDR
ix
Gaurav D. Joshi Safeguards
Specialist
Senior
Environmental
Specialist
GENDR
Gevorg Sargsyan Team Member Program Manager GEEDR
Kumudni Choudhary Team Member Program Assistant SACIN
Mani Khurana Team Member Energy Specialist GEEDR
Pyush Dogra Team Member Senior
Environmental
Specialist
GENDR
Surbhi Goyal Team Member Energy Specialist co-TTL GEEDR
Suryanarayan Satish Safeguards
Specialist
Senior Social
Development
Specialist
social GSURR
Extended Team
Name Title Office Phone Location
Dinkar Sohony Consultant-Technical Hyderabad .
Locations
Country First
Administrative
Division
Location Planned Actual Comments
India Karnataka Tumkur X .
Consultants (Will be disclosed in the Monthly Operational Summary)
Consultants Required ? No consultants are required
.
1
I. STRATEGIC CONTEXT
A. Country Context
1. India’s power system needs to grow rapidly to fuel its economic growth and provide
electricity to its growing population. During the last decade, India’s economy expanded at an
average annual rate of 7.6 percent, placing it among the top 10 of the world’s fastest growing
nations; projections are for such high rates of growth to continue. The demand for power is
expected to rise to support the growing manufacturing sector and meet the rising aspirations of its
people. With about 275GW of installed capacity (as of November 2015), the Indian power system
is among the largest in the world, but per-capita consumption of electricity is less than one-fourth
of the world average. An estimated 300 million people are not connected to the national electrical
grid, and those who are, face frequent disruptions. Power shortages in FY2015 were equivalent to
about 3.6% of total energy and 4.7% of peak capacity requirements. To meet the power demand,
industrial establishments and manufacturers have been relying on diesel-based back-up power
supplies, which are significantly more expensive than grid-based electricity. The cost of un-served
energy is high, placing an inordinate burden on households and industries. Lack of regular supply
of electricity is also leading to diversion of resources into coping costs that could otherwise be
used to support growth.
2. The Government of India (GoI) wants a growing share of the country’s electricity to
come from renewable energy. GoI has set an ambitious goal of providing uninterrupted power
for all homes, industrial and commercial establishments and adequate power for farms by 2022.
Currently, India relies largely on coal, both domestic and imported, for about 60 percent of its
electricity generation requirements. India is the world’s third largest emitter of carbon emissions
behind China and USA, although per capita emissions are far lower. According to a recent World
Health Organization report, 13 of the 20 most polluted cities in the world are in India. GoI
recognizes that it must supplement non-renewable sources with cleaner and abundant renewable
sources and has accordingly announced plans to quadruple India’s renewable energy capacity from
35.8 GW (as in November 2015) to 175 gigawatts by 2022 , which is expected to require more
than $150 billion in investments. To achieve these targets, GoI is using innovative public private
partnership models and has doubled the clean energy cess levied on coal.
B. Sectoral and Institutional Context
3. Solar PV has emerged as a promising long-term option to meet the growing energy
demand in India while addressing the adverse environmental impacts of conventional fuels. Since India lies in the high solar insolation region, it is endowed with huge solar energy potential
with most of the country having about 300 days of sunshine per year with annual mean daily global
solar radiation in the range of 3.5-6.5 kWh/m2/day. Solar power can help India meet its growing
electricity demand as well as foster energy security by reducing dependence on imported fossil
fuel such as coal and diesel. The confluence of declining cost trends in solar photovoltaic (PV)
power generation (mainly through dramatic declines in solar panel prices) and innovations in
energy storage technology that are putting downward pressure on battery prices, offer exciting
opportunities for India. In rural areas, solar PV can offer significant health benefits by displacing
2
the use of kerosene for lighting. Energy efficient irrigation pumps running on solar panels can
provide reliable cost effective irrigation for agricultural consumers.
4. GoI has announced a bold target of installing 100GW of solar power out of the total
renewable target of 175GW by 2022 – for solar power this represents about a thirty fold
increase from 3.7 GW installed in 2015. The total installed grid-connected solar capacity base
of the country has reached 3.7 GW (or 3,700 MW) as of June 2015, from less than only 2 MW in
2009. The Government would like to significantly increase the pace of solar power deployment to
meet its ambitious targets. The Government foresees that 60GW of the targeted installations will
come from utility-scale ground mounted solar power plants.
5. The development of utility scale solar power on this scale in such a short time frame
presents significant challenges. In particular, the following barriers to development of utility
scale solar power have been identified in India:
Availability of land. The availability of large tracts of suitable land at short notice
continues to be a key barrier to the development of solar power in India. Private sector
developers (including foreign investors), in particular, continue to run into a myriad of
legal and social issues with land acquisition, which serves to reduce the interest of
investors in the solar power sector.
Permits and Clearances. Private developers have to reach out to multiple departments and
ministries to obtain permits and clearances for land, transmission evacuation,
environment, which can cause delays and increase costs.
Availability of transmission and other infrastructure. Given the specific transmission
requirements of solar power and risk of stranded assets, private sector investors continue
to see the availability of state of art transmission infrastructure to connect solar generation
to load centers across the country as a precondition to major investment decisions.
Capacity of sector institutions. The institutions tasked with overseeing the development
of the solar power such as SECI State Nodal Agencies (SNAs) for renewable energy, state
transmission utilities, regulators are either very new or lack familiarity with specific
requirements of the sector. They hence lack the capacity to deliver on their mandate in
solar energy.
Cost of solar power. While there have been dramatic reductions in the cost of solar power
in recent years, solar generation is still more expensive than thermal generation in
financial terms. This means that there continues to be need for public support for solar
power both in terms of regulatory support as well as the development of enabling
infrastructure, to enable large amounts of solar power to be taken up in the grid. Focus has
been on utility scale ground mounted solar, little emphasis has been on tracking
technologies, storage or other high efficiency measures.
3
Variability of solar power. Cloudy conditions can cause the amount of generation from
solar plants to vary significantly, requiring grid operators to maintain alternative
generation capacities.
6. GoI is taking action on multiple fronts to address these challenges. The following are
the main initiatives undertaken by GoI to facilitate development of large amounts of solar power:
Cost of solar power. State Governments and the Central Government are using a number
of mechanisms to lower the cost of solar power for off takers, including (i) reverse auctions
for Viability Gap Funding; (ii) bundling of private sector generated solar power with
cheaper public sector coal power. This has facilitated the discovery of increasingly
competitive solar power prices in India1 together with a large investor turnout.
Development of solar parks. Large solar parks have been developed in Charanka (Gujarat)
and Bhadla (Rajasthan) with dedicated land and evacuation infrastructure for private sector
developers.
Regulation. Amendments currently being tabled in Parliament are seeking to increase
Renewable Purchase Obligation (RPO) targets from 3% to 8% by 2019, introduce
Renewable Generation Obligation (RGO) targets, and impose penalties on RPO and RGO
non-compliance. In addition, amendments have also been proposed for the National Tariff
Policy 2005, to socialize interstate transmission of renewable power, procurement of
bundled solar power by DISCOMs from conventional power generators on a cost plus
basis, and easy pass-through of RPO compliance cost.
Grid Integration of Renewable Energy. Grid integration issues are being addressed by the
India Smart Grid Task Force (ISGTF), an inter-ministerial task force and the India Smart
Grid Forum (ISGF), a public-private partnership initiative. The national transmission
utility, Power Grid Corporation India Limited (POWERGRID) is taking the lead in
implementing the Green Energy Corridor Project to facilitate evacuation of renewable
energy across the country.
7. The Ministry of New and Renewable Energy (MNRE) has launched a ‘solar park scheme’
to facilitate the development of utility scale solar power in India. This scheme will use public
private partnership arrangements to set up 20 solar parks with a cumulative installed capacity of
about 60 GW of solar power by 2020. This scheme internalizes the lessons of the Charanka and
Bhadla solar parks in India as well utility scale solar power developments in other parts of the
World2. Under the scheme, a joint venture (JV) company comprising of the SECI, state utilities
1 Contracted tariffs have fallen from INR 17/kWh (or about 28 cents/unit) in 2010 to about INR 4.7/kWh (or about 8.4 cents/unit)
in 2015, a decline of more than 70 percent in five years. 2 The proposed project will draw on international experience with development of utility scale solar parks as well as India’s
experience with, and important lessons learned from other solar parks. In year 2009, Clinton Foundation initiated work on large
scale solar parks in South Africa, Australia, USA and India. It signed a MoU with Gujarat and Rajasthan government in India to
set up solar parks. Solar parks in Australia and USA did not move forward because of the regulatory hurdles. Solar park in South
Africa by ESKOM is under development. Gujarat (Charanka) solar park has been commissioned and Rajasthan (Bhadla) solar park
is under construction. Experience from the earlier solar parks was incorporated in the project during the preparation phase.
4
and in some cases the private sector is proposed to be set up in each state to provide specialized
services and to be the owner of the park and its shared infrastructure, in order to incentivize solar
power developers to invest in solar energy in the park (see Box 1 for more details on the scheme).
8. This proposed project is one in a series of three engagements requested by the GoI from
the World Bank for US$1 billion of funding in the solar power sector3 4. All three projects are
expected to support achievement of the government’s new solar targets, and to demonstrate
important economies of scale in utility scale solar generation, push down equipment and
transaction costs, and also increase efficiency while reducing unit costs of solar power. It is
expected that the Bank-supported projects will create market confidence and will catalyze further
support from other investor groups for the GoI to help with achievement of its ambitious target of
installing 100GW of solar power capacity by 2022.
9. In particular, the proposed operation will support MNRE’s announced “solar park scheme”
by setting up transmission infrastructure to evacuate power from selected solar parks in Karnataka,
M.P and possibly also Telangana. This project will be implemented by Powergrid. IBRD funding
is being made available to provide transmission interconnections to the Inter State Transmission
System (ISTS) at the border of the respective solar park. The ISTS provides direct access to the
3 During their July 2014 and January 2015 meetings, Prime Minister Narendra Modi and President Jim Kim had agreed that the
Bank would provide financing for Solar Parks in the country 4 In particular, GoI requests have been received for all other Bank engagements to (i) support the establishment of grid connected
rooftop PV; (ii) fund the construction of associated evacuation infrastructure from Bank-supported solar parks; and (iii) shared
infrastructure for solar parks.
Box 1 - Ministry of New and Renewable Energy’s Solar Park Scheme
The development of solar parks will streamline development of solar power generation projects
with government agencies undertaking land acquisition or arranging for lease of a large parcel of
land from private owners. The public sector (in this case the JV company) will be responsible for
obtaining necessary permits, as well as providing common infrastructure such as site preparation
and leveling, construction power, power evacuation and water infrastructure, access roads,
security, and related services necessary to set up such power generation projects or plants.
The JV company will allocate space inside the park amongst solar power developers. The
allotment price per meter square payable by developers for the plots inside the solar park will be
specified by the implementing agency of the solar park, which is the JV company. Developers
will be able to get into long term Power Purchase Agreements (PPAs) with buyers (mostly
discoms or aggregators) inside and outside the state or they may develop solar power for captive
consumption by selected industrial customers.
POWERGRID or the State Transmission Utility (STU) will set up a sub-station outside the solar
park to feed power from one or more pooling stations into the National Grid or State Grid,
respectively. In cases where electricity utilities in the state are not willing to buy entire power
generated from such solar parks , POWERGRID is expected to be given the responsibility of
setting up 400/220 kV or bigger sub-station right next to the solar park and ensuring its
connectivity to the Inter State Transmission System (ISTS). The development of interconnection
will be coordinated and prioritized to ensure the availability of the evacuation infrastructure to
private sector developers well in advance of their plant commissioning date.
5
entire national power market, and will therefore allow solar developers from these parks to more
easily sign PPAs with customers and off-takers anywhere in the country5. The supporting project
for solar park shared infrastructure ( which is also currently under preparation) will use IBRD
funding to develop the enabling infrastructure for utility scale development of solar power,
including common infrastructure such as large areas of land, power pooling sub-stations as well
as intra-park transmission infrastructure, access roads, lighting, communications and common
security arrangements. This will facilitate investment in solar power development by private or
public sector developers, who may be able to shorten the time from contract award to
commissioning from 20 months to less than 10 months. Before the solar park model, all of these
supporting infrastructure investments had to be made by the power developers themselves,
including factoring in the waiting time to obtain necessary permits and clearances.
10. POWERGRID is the Central Transmission Utility (CTU) of the country and owns and
operates the National Grid, which is an integration of the five regional transmission grids in India.
Strong regional grid interconnections enlarge the balancing areas and help connect renewable
energy generation to the National Grid, enabling tapping into huge hydro power potential and
storage type hydro power plants (capacity of which will also need to be increased to support the
increased national renewable energy generation targets of GoI) that are suitable for providing grid
balancing services. Further, as per the provisions of the Electricity Act 2003, the state electricity
regulatory commission have already specified renewable purchase obligations (RPO) on the state
distribution utilities. Access to larger markets enables the transfer of power from renewable energy
resource rich state to renewable energy resource scarce states and hence enabling the power-deficit
states to comply with their respective RPO. Targets for RPO are going to be enhanced substantially
and monitored closely with the application of strict penalties in case of default once the proposed
amendments to the Act are approved. Though there is of course an inherent risk of financial
strength of these discoms to adhere to RPO targets. However, there is a separate government
scheme underway called UDAY, which is also supported by the World Bank through a series of
engagements under the 24*7 Power for All program, to strengthen the finances of distribution
companies. When this risk of discom financial weakness was analyzed as a risk to the viability of
the solar park business model, it was found that solar power procurement is such a tiny percentage
of the overall power procurement of discoms (even if it were to go up from 3% to 8%), that it does
not make a material difference and does not pose a great risk. If the penalties are high enough to
incentivize compliance, the discoms (even in solar-scarce states) will comply with their renewable
purchase obligations. Also, costs are continually coming down through aggressive bidding that is
occurring in each successive auction, and the large gap between solar energy cost and thermal
energy cost is disappearing fast, making the discom much less reluctant to purchase solar power
on a 25 year PPA arrangement. Therefore the risk of the ISTS lines not being used, due to lack of
demand by faraway discoms to access solar power from solar rich states, is judged to be very low.
C. Higher Level Objectives to which the Project Contributes
11. Alignment with GoI’s National priorities: The project is aligned with GoI’s National
Action Plan for Climate Change (NAPCC), which was issued in 2008 to enhance India’s ecological
sustainability & encourage sustainable energy sources. It is also consistent with the Jawaharlal
5 Until the Open Access system is made fully operational, this direct access to PowerGrid’s network confers an additional benefit
relative to exclusive dependence on the state transmission utility’s network and the latter’s possible reluctance to allow power to
be sold outside of the state, contractual obligations notwithstanding
6
Nehru National Solar Mission (JNNSM) that was launched in 2010 as part of NAPCC to promote
the development of solar power in India. GoI has significantly scaled up the target of 20 GW of
solar power in JNNSM to 100 GW by 2022. GoI has reiterated these commitments as part of its
Intended Nationally Determined Contributions (INDCs) commitment to achieve about 40 percent
cumulative electric power installed capacity from non-fossil fuel based energy resources by 2030.
12. Alignment with World Bank’s India Country Partnership Strategy (CPS). The proposed
project is aligned with the India Country Partnership Strategy along its three pillars –integration,
transformation, and inclusion. Under integration, the project will accelerate private investment in
solar power in some of India’s solar-resource rich states such as Karnataka and Madhya Pradesh.
Under transformation, the project directly aims to reduce environmental pollution and GHG
emissions, add clean power generation capacity, and foster innovative solar development through
shared large-scale infrastructure. Under inclusion, the project offers the opportunity to increase
access to electricity by increasing the availability of electricity generation in the system. In
addition, the operation conforms to the emphasis of the CPS on GoI’s “Finance-Plus” approach
whereby the value-added by the Bank goes beyond financing and contributes to the transfer of
knowledge and international best practices, reform of processes and systems, and strengthening of
institutional capacity.
13. Furthermore, the proposed operation supports the World Bank Group’s corporate
commitment to increase renewable energy lending, and address climate change. The program is
also aligned with the WBG’s goal of reducing poverty and promoting shared prosperity.
II. PROJECT DEVELOPMENT OBJECTIVES
A. PDO
14. The proposed development objective is “to evacuate power from the selected solar power
generation parks to the Inter-state Transmission System.”
B. Project Beneficiaries
15. The direct beneficiaries of the project are (i) the people in the participating states and
elsewhere who will benefit from the electricity generated in the solar parks and (ii) discoms which
will be able to meet their RPOs with electricity generated from solar parks.
16. The indirect beneficiaries are people who will benefit from (i) avoided local environmental
damage costs (ii) additional growth and productivity due to improvements in power supply
situation.
C. PDO Level Results Indicators
17. The following indicators will be used to track progress in achieving the project
development objectives:
Transformation capacity installed as part of the project (MVA)
Transmission system availability of dedicated network for evacuation of solar
power from the generation point (%)
7
Energy evacuated from the solar parks to the ISTS (GWh)
III. PROJECT DESCRIPTION
18. The Ministry of New and Renewable Energy (MNRE) aims to provide impetus to solar
energy generation by establishing flagship demonstration facilities to encourage project developers
and investors, prompting additional projects of similar nature (including scale), triggering
economies of scale for cost reductions, technical improvements and achieving large scale GHG
emissions reductions. As per the scheme, a solar park is a concentrated zone of development of
solar power generation projects and provides developers an area well characterized with proper
infrastructure and access to amenities and where the risk of the projects can be minimized. The
scheme intends to attract significant investments from project developers in the States to enable
them to meet RPO mandate and provide employment opportunities to local population to the extent
possible. It aims to reduce the number of approvals required by developers to set up solar
generation plants and hence attract private investments in such solar plants. The State will also
reduce its carbon footprint by avoiding emissions equivalent to the solar park’s generation. Further,
the State will also avoid procuring fossil fuels to run conventional power plants.
19. The power evacuation arrangement consists of two parts – (i) pooling stations and network
within the Park to collect power from each project and transmitting it to the transmission substation
at the park boundary; and, (ii) the transmission substation and the linked transmission line up to
the Central Transmission Utility’s (CTU)/State Transmission Utility’s (STU) existing network.
Part two of the evacuation arrangement depends on whether the host State is inclined to bridge its
power demand-supply gap that depends on number of factors such as grid stability, redundancy in
the system, etc. and/or whether it wants to export the surplus solar power to other power deficit
states and to the states that are unable to meet their mandated RPO.
20. During the identification phase, consultations about the Bank financing going to solar parks
were carried out with various stakeholders like MNRE, SECI and relevant state agencies. It was
requested that the World Bank should fund transmission infrastructure for power evacuation from
the selected solar parks. Given the specific transmission requirements of solar power and risk of
stranded assets, investors continue to see the availability of state of art transmission infrastructure
to connect solar generation to load centers across the country as a precondition to major investment
decisions.
21. The proposed project focuses on financing the part two with CTU (POWERGRID) as the
implementing agency, that is, the project finances the transmission substation and the transmission
lines at the periphery of the selected solar parks up to the CTU’s existing network. POWERGRID
will build, own and operate the inter-state transmission system (ISTS) as per the requirement of
power transfer across various states/regions of the Country. With access to the National Grid, the
project will give the solar power developers, who are setting up their solar generation plants within
these parks, access to potential power sellers and buyers beyond regions and hence accessing the
regional market and further integration of the regional grids.
22. The activities will involve setting up of substations at the periphery of the solar park,
building infrastructure using the latest technology (like SCADA, GIS, STATCOM, bay controller,
8
OPGW, PLCC, etc.), real time monitoring of solar generation and hence integration of solar energy
with inter-state transmission system.
23. Since all the solar parks have not been finalized these investments under this project will
be taken up in a phased manner. The following solar parks that are in advanced stages, to be taken
up immediately:
A. Project Components
24. Component 1. Transmission evacuation infrastructure for 2000 MW Pavagada Solar
Park in Karnataka (US $180 million). This will entail: (i) establishment of 5x500MVA,
400/220kV pooling substation at Tumkur along with 1x125MVAR Bus Reactor; (ii) Tumkur
Pooling Station-Hiriyur 400kV D/C transmission line; (iii) Hiriyur-Mysore 400kV D/C line; (iv)
LILO of Gooty-Madhugiri 400kV D/C line at Tumkur pooling station; and, (v) +/-150MVAR
STATCOM at Tumkur.
25. Component 2: Transmission evacuation infrastructure for 750 MW Rewa Solar Park in
Madhya Pradesh (US $100 million). This will entail: (i) establishment of 3x500MVA, 400/220kV
pooling station at Rewa with 1x125MVAR Bus Reactor, and (ii) LILO of Vindyachal-Jabalpur
400kV D/C line at Rewa Pooling Station.
26. The tentative list of the schemes that may be financed under the project includes
Transmission system Neemuch and Agra (MP) solar parks, Mehboobnagar (Telangana) solar parks
and any other future transmission schemes for solar parks in the states of Karnataka, MP and
Telangana. These will be finalized upon obtaining approval from Central Electricity Authority
(CEA) and/or Standing Committee on Power System Planning. Additional transmission
subprojects/schemes will also be identified to meet the overall funding commitment.
B. Project Financing
27. The project will be financed through the Investment Project Financing instrument, which
will cover the investments required for shared infrastructure in identified states. GoI has chosen to
denominate the loan in USD. The total cost of the project is estimated at US$600m, of which
US$270 will be the World Bank IBRD financing and $30 million will be CTF financing. GoI has
opted for variable spread option for this loan. [WILL BE CONFIRMED AT
NEGOTIATIONS]. Powergrid will sign the project agreement with the Bank for the
implementation of the project while GoI will sign the loan agreement with the Bank.
28. The CTF funding, US$ 30 million, will be extended under softer concessional terms. The
CTF loan is offered with a service charge of 0.25% per annum on the disbursed and outstanding
loan balance and 40-year maturity, including a 10-year grace period, with Principal repayments at
2% for Years 11-20 and at 4% for Years 21-40. Principal and service charge payments accrue
semi-annually. A management fee equivalent to 0.45% of the total loan amount ($135,000) will
be charged, to be capitalized from the loan proceeds, following the effectiveness of the loan
29. Table 1 provides a breakdown of project costs and financing by component:
9
Table 1: Project Costs and Financing (US$ million)
Project Components Project
cost
IBRD
Financing
CTF
Financing
GoI and State
Government Financing
Pavagada Solar Park 180 81 9 90
Madhya Pradesh Solar Park 100 45 5 50
Others 320 144 16 160
Total Project Costs 600 270 30 300
C. Lessons Learned and Reflected in the Project Design
30. The project builds on the lessons learned from the GoI’s experience with the
implementation of Charanka and Bhadla Solar Parks in the states of Gujarat and Rajasthan,
respectively. In particular, these experiences have highlighted the need to (i) keep the shared
infrastructure costs of solar parks low to attract developers to the park; (ii) have access to the ISTS
from the solar park to ensure linkage with the national market and (iii) closely co-ordinate the
development of transmission interconnections to the park to ensure that assets of developers are
not stranded. These lessons have been built into the design of the project by MNRE and World
Bank.
31. Another important lesson is how to successfully design and implement a project under the
framework of a Centrally Sponsored Scheme (CSS). The past experience of implementing similar
projects, which normally across multiple states, clearly underscored that project implementation
is often adversely affected because of inadequate attention to a range of issues in preparation. To
avoid implementation delays, the project has to adopt a sub-project readiness criteria specifying
the critical actions related to technical, environmental, and social aspects that need to be completed
prior to contract award.
IV. IMPLEMENTATION
A. Institutional and Implementation Arrangements
32. Over the past decade, POWERGRID has acquired and developed skills required for
successfully planning and implementing large scale capital investment programs, through its
mandate to develop the inter-state transmission network of India and also by acting as Consultant
to some states to assist them to plan, design and implement their transmission and distribution
networks. All the schemes envisaged under this operation are being designed, procured and
implemented by POWERGRID. Local and foreign contractors engaged through international
competitive bidding will carry out the supply, installation and erection works.
10
33. The project implementation will be under the institutional oversight of the Ministry of
Power (which is the line ministry overseeing POWERGRID operations), the Ministry of New &
Renewable Energy (MNRE), the Ministry of Finance (MoF) and CEA.
B. Results Monitoring and Evaluation
34. PowerGrid, as the implementing agency, will provide the Bank with quarterly physical
progress reports, interim financial reports, audited financial statements (within six months of the
end of each financial year), and other such information as the Bank may reasonably require. Since
the nature of these contracts will be Supply and Installation (S&I), Monitoring and Evaluation
(M&E) is linked to project targets upon completion of milestones like delivery of material, erection
and commissioning.
35. PDO level results indicators are (i) Transformation capacity installed as part of the project
(MVA) (ii) Transmission system availability of dedicated network for evacuation of solar power
from the generation point (%)
36. The intermediate outcome indicators will be (i) transmission lines constructed (in circuit
km); (ii) number of grid sub-stations constructed
37. The project is not financing new household connections or last mile connectivity (11kV
and below), and is not directly contributing to expanding access in the participating states.
However, the project is likely to have a significant indirect contribution to expansion of access to
electricity, as a result of the increased availability of electricity in all project states, wherein the
investments supported under the project are expected to lead to increased hours of supply to
existing customers, and increased availability of electricity supply, which may enable utilities to
connect and serve new customers.
C. Sustainability
38. POWERGRID’s involvement is a reasonable assurance that project design and
implementation will be of high standards. In addition, environmental and social issues will be
handled with adequate expertise and attention, building on POWERGRID’s implementation track
record of earlier World Bank funded projects.
39. The Environmental and Social sustainability is facilitated through will adoption of a
framework approach for this project as all the investments have not been identified as yet. Power
Grid has recently (2014-15) developed ESPP Framework for six north eastern states in the context
of the preparation of the World Bank assisted North East Power System Improvement Project,
incorporating the provisions of India’s new ‘The Right to Fair Compensation and Transparency in
Land Acquisition, Rehabilitation and Resettlement Act, 2013’ as well as the provisions of Sixth
Schedule of the Indian constitution.
11
V. KEY RISKS AND MITIGATION MEASURES
A. Overall Risk Rating Explanation
40. The key risks and issues associated with the proposed project are as follows:
41. Grid Parity for Solar: The GoI has announced the ambitious targets of installing 100GW
of solar power generation capacity in the country by 2022. The current installed capacity of solar
stands at 3.7GW. Unless this is backed up by strong political will and solar generation costs
achieving grid parity, achieving these targets are extremely ambitious. To factor this in, the GoI
has announced schemes and policies to boost the solar energy sector in the country, for instance,
the scheme on development of solar parks and ultra-mega solar power projects was launched in
December 2014. Similarly, almost 19 states and union territories have come up with the state
specific solar policies to enable conducive environment for growth of this sector. Solar energy has
shown a dramatic fall in tariffs in India, with the recent tender floated by the state of Madhya
Pradesh receiving the lowest tariff at INR 5.05 per unit without any subsidy.
42. Minimum Generation required to break-even the investments isn’t installed in the Solar
Park. During project preparation, the team will analyze the minimum percentage of occupancy by
solar developers that is required in the solar parks for “break even” of the solar parks in financial
and economic terms. The investments in transmission network for evacuation of solar park has
longer gestation period than setting up the solar projects. Hence, it is important to ensure that the
minimum solar generation that will make the investments under the project at least break even,
will be coming up in the solar parks. This is likely to happen if developing solar power plants
inside the Solar Parks is perceived to be more expensive than developing solar plants outside, the
space inside the Solar Parks may or may not be utilized fully. Even the delays in putting up the
solar generation projects within the park will also have an impact on the already built transmission
infrastructure. To mitigate this, the Bank will facilitate a close dialogue between the developers
and the implementing agencies to ensure that the costs associated with the Solar Parks don’t
escalate and concerns of developers are addressed. Lessons from the existing parks in India
(Charanka in Gujarat and Bhadla in Rajasthan) will also be incorporated suitably to address such
concerns. Further, POWERGRID also does its due diligence before investing into the project and
closely monitors the implementation schedule of generation assets to match up with its
transmission investments to the extent possible.
43. Non-availability of grid in a timely manner. There is a possible risk that the solar assets are
stranded due to non-availability of transmission evacuation grid in a timely manner. The possible
reasons for the same could be solar generation comes on-stream before the scheduled completion
date of transmission assets or may be due to right-of-way issues. To mitigate this risk, the Bank is
closely monitoring the plan for implementation of the evacuation infrastructure by POWERGRID
and match the timelines with solar generation commissioning to the extent possible. With regard
to right-of-way issues, the Ministry of Power has already formed a committee with selected states
to decide on provision of the compensation to be paid for such issues.
44. Grid instability. There is a possible risk of grid instability in frequency, current, and voltage
due to large-scale solar generation at a single point. To mitigate this, it will be necessary to carry
out a detailed system study to identify ways to ensure uninterrupted operation of grid. It may also
12
be important to install specialized equipment between the solar power plants and the main
electrical grid. The Bank will work closely with relevant state and central agencies and utilities to
ensure that these concerns are addressed during project preparation and lessons from Charanka
Solar Park in Gujarat and Bhadla Solar Park in Rajasthan are incorporated in project design.
Further, POWERGRID and POSOCO in association with National Renewable Energy Lab
(NREL), USA are already collaborating to address this issue.
45. Overall: Given the long-term partnership of the Bank with POWERGRID, the latter has
become a strong entity that is capable to ensure that the investments are made well in time and are
not left stranded. Since POWERGRID owns, operates and maintains the National Grid, it in
association with POSOCO, takes all due measures required to ensure grid stability. Based on this,
the risk is assessed at "Moderate" during project implementation.
VI. APPRAISAL SUMMARY
A. Economic and Financial Analysis
46. A cost-benefit analysis consistent with recent Bank guidance on this topic6 was carried out
for the 2GW Pavagada Solar Park in Karnataka, which is the most advanced in terms of design of
the solar parks covered under the project7. The economic analysis covers the entire package of
solar park investments comprising of solar park investments, transmission investment, and solar
generation plants installed by developers rather than just the Bank financed portions of the solar
parks projects8. The economic analysis covers 28 years, including 3 years of construction and 25
years of operation. A discount rate of 12% was used for the calculation9. The analysis includes a
consideration of the relevant negative global and local environmental externalities.
47. The economic analysis indicates that in India utility scale solar power is increasingly
competitive with thermal generation using imported coal. The baseline economic return of
Pavagada Solar Park against the “without solar park scenario” is 7% (NPV –US$ 386 million),
which is below the 12% hurdle rate used for Bank projects (see Table 2). However, the solar park
has substantial local and global environmental benefits and consideration of these benefits
increases the ERR of the solar park significantly. The inclusion of avoided damage costs of local
pollution in the economic flows, increases the ERR to 10% (NPV -US$163 million). The
inclusion of avoided global environmental damage costs (using the Bank guidance on social value
of carbon), increases the ERR to 18% (NPV $ 545 million).
Table 2: Summary of Economic Analysis
6 These include the 2015 World Bank guidance on the economic analysis of renewable energy projects and the 2014 “Operational
Policy and Bank Procedure (OP/BP) 10.00, Investment Project Financing” 7 Once design elements are firmed up, the team will carry out the economic analysis of additional solar parks 8 This is consistent with the Bank’s 2015 guidance on economic analysis of renewable energy projects. 9 A review of discount rates used in Bank projects is currently underway. The economic analysis will revised once the new
guidance on discount rate is finalized.
13
Economic rate of return Unit Values
ERR % 7%
ERR + local externalities % 10%
ERR + local externalities + GHG % 18%
Switching value, avoided GHG emission $ /ton $6
Composition of NPV
Cost of Solar Park
capital cost $USm 1265
O&M $USm 31
Benefits of avoided coal generation
Avoided coal costs $USm 824
Capacity credit $USm 86
NPV (before environmental benefits) $USm -386
local environmental benefits $USm 223
GHG emissions @$30/ton $USm 708
NPV (including environment) $USm 545
Lifetime GHG emissions undiscounted
Mtons
CO2
69
Marginal abatement cost MAC $/ton 5.6
48. Reduction in GHG emissions. The analysis indicates that the solar park will reduce
GHG emissions by 69 million tons over the life of project compared to the thermal counterfactual.
The marginal abatement cost of GHG emission for the Solar Park is $5.6/ton. The Solar Park will
help avoid local and environmental damage costs equal to $931 million compared with the thermal
counterfactual.
49. Sensitivity Analysis. The switching values for the important variables such as capital
costs, Capacity Utilization Factor, PV generation capital costs, coal prices, capacity credit and
discount rate are presented in Table 3.
Table 3: Switching Values
Input Unit Baseline Value Switching Value
Project Cost $ Million 1296 910
CUF % 19% 27%
PV Cost $M/MW 1.06 0.70
Annual Increase Coal
Prices % 0% 5%
Discount Rate % 12% 7%
Capacity Credit % 19% 103%
Grid Integration Costs % 0 -2.70%
14
Project cost overrun
factor Ratio 1 0.7
B. Technical
50. POWERGRID, in its capacity as CTU, is designated as the Nodal Agency for grant of
Connectivity, Long-Term Access and Medium-Term Open Access to the inter-State transmission
system as per the Regulation 4 of the Central Electricity Regulatory Commission (Grant of
Connectivity, Long-term Access and Medium-term Open Access in Inter-State transmission and
related matters) Regulations, 2009. Under this, POWERGRID ensures that the generators,
irrespective of source of generation (whether conventional or renewable), files a long term open
access (LTA) application with it before it takes up the proposal for implementing any transmission
investments at inter-state level. Once LTA is finalized and submitted, POWERGRID along with
State Transmission Utility (if the State’s network is likely to be used) carries out the necessary
interconnection study as specified in Central Electricity (Technical Standards for Connectivity to
the Grid) Regulations, 2007. A detailed load flow study for the network is carried out and
accordingly establishing new links as well as strengthening of the existing networks is undertaken.
51. The investments include construction of transmission systems for evacuation of the power
from solar park. It includes packages on pooling stations, transmission lines etc. Powergrid had
carried out a detailed evacuation studies on the Rewa and Pavagada solar parks. Whenever any
new generating source is set up and is required to be connected to the existing ISTS network it is
essential that system studies are conducted by the CTU , in this case POWERGRID to assess the
impact of the new additions on the running grid. The intention is to establish augmentation/
additions needed to the existing network so that the generation can be absorbed without any
adverse effect.
52. The study covers the Load flow analysis, Reactive power flow patterns, and
Measures/Corrective actions to be implemented by the partners in the Grid. Study also assess the
health of the consolidated system in case of outage of any network element of the grid including
the generator itself, the Solar Park in present case. After such a study is carried out by
POWERGRID it is presented in the Standing Committee chaired by CEA with other constituent
members from the region for deliberations and clearance. Post studies POWERGRID has already
identified the network to be added to the present system for both REWA and Pavagada solar parks.
C. Financial Management
53. POWERGRID shall be responsible for the project’s financial management arrangements.
POWERGRID is already implementing Bank funded projects and is well aware of Bank’s
fiduciary requirements. POWERGRID shall provide the fiduciary assurance to IBRD on proper
and efficient use of Bank financing. POWERGRID will implement the Project as per the financial
management provisions of Loan Agreement and as further detailed in the Project Implementation
Plans. With financial management arrangements described below and given the POWERGRID’s
experience in implementation of Bank funded projects, the financial management risk for the
project remains Moderate.
15
D. Procurement
54. Procurement for the project will be carried out in accordance with the World Bank’s
“Guidelines: Procurement of Goods, Works and Non-Consulting Services under IBRD Loans and
IDA Credits and Grants by World Bank Borrowers” (January 2011 revised July 2014)
[Procurement Guidelines]; “Guidelines: Selection and Employment of Consultants under IBRD
Loans and IDA Credits & Grants by World Bank Borrowers (January 2011 revised July 2014)”
[Consultant Guidelines]; and the provisions stipulated in the Legal Agreements. The project would
be subject to the Bank’s Anti-Corruption Guidelines, dated October 15, 2006, and revised January
2011.
55. Procurement Risk Assessment: Power Grid would be responsible for undertaking all
procurements and contract management activities under the project.
56. The Procurement Risk Assessment and Management System (PRAMS) is presently being
undertaken and will be finalized during appraisal, based on the assessment and the experience of
Power Grid in implementing Bank funded projects, the procurement risk rating is rated as “Low”.
Power Grid has staff with expertise in procurement and contract management in conducting
procurement in accordance with Bank policies and procedures, having successfully handled
procurement activities under Bank funded projects.
57. E-procurement System. Power Grid would be using e-procurement system for all
procurements under the Project. The e- procurement system assessment was carried out against
the Multilateral Development Banks (MDB) requirements, and has been accepted for use for
Procurements under Bank funded projects by the Bank.
58. Procurement Plan and Readiness. The draft procurement plan for the project
implementation is enclosed in Annex 3. Power Grid has already identified the investment and
tentative packaging of approx. USD 190 million for the sub projects in Rewa, Madhya Pradesh
and Tumkur, Karnataka. Another approx. USD 200 million are allocated for the sub projects in
Neemuch & agar, Madhya Pradesh and Gattu, Telengana. Power Grid would finalize the full
investments and the tentative packaging and procurement plan by appraisal for the full project cost
of USD 600 million.
E. Environment & Social (including Safeguards)
59. The environmental aspects that need to be handled through the environmental assessment
( OP 4.01) include the removal of vegetation, possible hindrance to movement of fauna alteration
to local or area’s drainage pattern, as well as health and safety of workers and residents near the
facilities, and handling of chemicals. The assessment would also need to examine issues related to
Natural Habitats (OP 4.04), Forests (OP4.36), and Physical Cultural Resources (OP4.11).
60. Relative flexibility available in locating facilities within an area allow judicious selection
of sites for most transmission infrastructure elements. The potential adverse environmental
impacts can be managed adequately with advance planning and early consideration of the issues
16
like minimization of the forest land to be used for the project, proper management of drainage, and
avoidance of sites of cultural importance.
61. Powergrid has been recognized for successful management of environmental and social
aspects of its activities in line with Bank expectations over past decades. This is undertaken in line
with its Environmental and Social Policies and Procedures, which were approved for use under
the Use of Country System pilot program in 2009 and follow the hierarchy of choosing avoidance,
minimization, mitigation for adverse impacts and enhancement of positive impacts, wherever
possible.
62. Major social safeguard aspects relate to: land and tribal. Project require lands for: (i)
erection of pole to draw lines; and (ii) construction of sub-stations transformation of power. The
former does not entail permanent acquisition of lands, but, creates some temporary disturbances
demanding a Compensatory Plan (Compensatory Plan for Temporary Disturbance or CPTD).
Number of people/ families likely to be impacted/ involved in the CPTD is expected to be quite
high and hence demands a highly responsive and effective interface with the communities. The
latter, sub stations, however, does require land on a permanent basis. Additionally, in some of the
sites, the project may have to encounter tribal/ scheduled areas, covered under the Fifth Schedule
of the Indian Constitution which provides protection to the tribal people living in the scheduled
areas with a variety of guarantees. The governance and administrative arrangements are also
different in these areas. So, interventions to secure lands in these areas will have to be necessarily
associated with an interface with the tribals. Given this situation, project triggers OP 4.12
(Involuntary Resettlement) and OP 4.10 (Indigenous Peoples).
63. The project will adopt a framework approach as all the investments have not been identified
as yet. Power Grid has recently (2014-15) developed ESPP Framework for six north eastern states
in the context of the preparation of the World Bank assisted North East Power System
Improvement Project, incorporating the provisions of India’s new ‘The Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013’
as well as the provisions of Sixth Schedule of the Indian constitution.
64. While environmental aspects of the ESPP hold good for the current project as well,
additional aspects need to be ingrained into social management framework. They include: (i)
managing due diligence in respect of Associated Activities; (ii) Ministry of Power’s recently issued
guidelines on financial compensations for Right of Way; and (iii) Indian constitution’s Fifth
Schedule provision related to tribal areas. It was agreed that an updated social management
framework comprising the following elements will be prepared by Powergrid by end November:
resettlement policy framework, tribal peoples planning framework, compensatory plan for
temporary disturbance (ROW) and a gender action plan.
65. As and when the project sites are firmed up, plans for consultations with stakeholders as
well as preparation of IEARs will be undertaken in line with the ESPP.
F. World Bank Grievance Redress
17
66. Communities and individuals who believe that they are adversely affected by a World Bank
(WB) supported project may submit complaints to existing project-level grievance redress
mechanisms or the WB’s Grievance Redress Service (GRS). The GRS ensures that complaints
received are promptly reviewed in order to address project-related concerns. Project affected
communities and individuals may submit their complaint to the WB’s independent Inspection
Panel which determines whether harm occurred, or could occur, as a result of WB non-compliance
with its policies and procedures. Complaints may be submitted at any time after concerns have
been brought directly to the World Bank's attention, and Bank Management has been given an
opportunity to respond. For information on how to submit complaints to the World Bank’s
corporate Grievance Redress Service (GRS), please visit http://www.worldbank.org/GRS. For
information on how to submit complaints to the World Bank Inspection Panel, please visit
www.inspectionpanel.org.
18
Annex 1: Results Framework and Monitoring
Country: India
Project Name: Transmission for Power Evacuation from Solar Parks (P156974)
Results Framework
Project Development Objectives
The proposed development objective is “to evacuate power from the selected solar power generation parks to the Inter –state
Transmission System.”
These results are at Project Level
Indicator Name Baseline Cumulative Target Values
YR1 YR2 YR3 YR4 YR5 End Target
Transformation
capacity installed as
part of the project
(MVA)
0 0 1000 2000 2500 2750 2750
Transmission system
availability of
dedicated network for
evacuation of solar
power from the
generation point (%)
0 0 99% 99% 99% 99% 99%
Electricity evacuated
from solar parks using
ISTS (GWh)
0 0 1400 2800 3500 3850 3850
19
Indicator Name Baseline Cumulative Target Values
YR1 YR2 YR3 YR4 YR5 End Target
Transmission lines
constructed under the
project
(Kilometers - Sub-
Type: Breakdown) -
(Core)
0.00 0.00 100 200 250 270 270
Number of Grid
substations
constructed/upgraded
(Number)
0 0 1 2 3 4 4
Indicator Description
.
Project Development Objective Indicators
Indicator Name Description (indicator definition etc.) Frequency Data Source /
Methodology
Responsibility for Data
Collection
Transformation capacity
installed as part of the
project (MVA))
This indicator measures the
transformation capacity added to
evacuate the solar power from the solar
parks under the project.
Annual Progress Report Implementing Agency
Transmission system
availability of dedicated
network for evacuation of
solar power from the
generation point (%)
This indicator measures the
transmission system availability.
Annual Progress Report Implementing Agency
20
Electricity evacuated
from solar parks using
ISTS (GWh)
This indicator measures the amount of
electricity evacuated from solar parks
using the Inter-state Transmission
System.
Annual Progress Report Implementing Agency
Intermediate Results Indicators
Indicator Name Description (indicator definition etc.) Frequency Data Source /
Methodology
Responsibility for Data
Collection
Transmission lines
constructed under the
project
This indicator measures the length of
the transmission lines constructed
under the project.
Annual Progress Report Implementing Agency
Number of Grid
substations constructed
This indicator measures the number of
220/132 kV, 132/33 kV substations
constructed under the project
Annual Progress Report Implementing Agency
21
Annex 2: Detailed Project Description
INDIA: Transmission for Power Evacuation from Solar Parks (P156974)
1. This proposed project is one in a series of three engagements requested by the GoI from
the World Bank for US$1 billion of funding in the solar power sector10 11. All three projects are
expected to support achievement of the government’s new solar targets, and to demonstrate
important economies of scale in utility scale solar generation, push down equipment and
transaction costs, and also increase efficiency while reducing unit costs of solar power. It is
expected that the Bank-supported projects will create market confidence and will catalyze further
support from other investor groups for the GoI to help with achievement of its ambitious target of
installing 100GW of solar power capacity by 2022.
2. To help meet this target, Ministry of New and Renewable Energy (MNRE) has come up
with a ‘solar park scheme’ with an objective to provide impetus to solar energy generation by
establishing flagship demonstration facility to encourage project developers and investors,
prompting additional projects of similar nature (including scale), triggering economies of scale for
cost reductions, technical improvements and achieving large scale GHG emissions. As per the
scheme, a solar park is a concentrated zone of development of solar power generation projects and
provides developers an area well characterized with proper infrastructure and access to amenities
and where the risk of the projects can be minimized. The scheme intends to attract significant
investments from project developers in the States to enable them to meet RPO mandate and provide
employment opportunities to local population to the extent possible. It aims to reduce the number
of approvals required by developers to set up solar generation plants and hence attract private
investments in such solar plants. The State will also reduce its carbon footprint by avoiding
emissions equivalent to the solar park’s installed capacity and generation. Further, the State will
also avoid procuring fossil fuels to run conventional power plants.
3. The power evacuation arrangement consists of two parts – (i) pooling stations and network
within the Park to collect power from each project and transmitting it to the transmission substation
at the park boundary; and, (ii) the transmission substation and the linked transmission line up to
the Central Transmission Utility’s (CTU)/State Transmission Utility’s (STU) existing network.
Part two of the evacuation arrangement depends on whether the host State is inclined to bridge its
power demand-supply gap that depends on number of factors such as grid stability, redundancy in
the system, etc. and/or whether it wants to export the surplus solar power to other power deficit
states and to the states that are unable to meet their mandated RPO.
4. During the identification phase, consultations about the Bank financing going to solar parks
were carried out with various stakeholders like MNRE, SECI and relevant state agencies. It was
requested that the World Bank should fund transmission infrastructure for power evacuation from
the selected solar parks. Given the specific transmission requirements of solar power and risk of
stranded assets, investors continue to see the availability of state of art transmission infrastructure
10 During their July 2014 and January 2015 meetings, Prime Minister Narendra Modi and President Jim Kim had agreed that the
Bank would provide financing for Solar Parks in the country 11 In particular, GoI requests have been received for all other Bank engagements to (i) support the establishment of grid
connected rooftop PV; (ii) fund the construction of associated evacuation infrastructure from Bank-supported solar parks; and
(iii) shared infrastructure for solar parks.
22
to connect solar generation to load centers across the country as a precondition to major investment
decisions.
5. The proposed project focuses on financing the part two with CTU (POWERGRID) as the
implementing agency, that is, the project finances the transmission substation and the transmission
lines at the periphery of the selected solar parks up to the CTU’s existing network. POWERGRID
will build, own and operate the inter-state transmission system (ISTS) as per the requirement of
power transfer across various states/regions of the Country. With access to the National Grid, the
project will give the solar power developers, who are setting up their solar generation plants within
these parks, access to potential power sellers and buyers beyond regions and hence accessing the
regional market and further integration of the regional grids.
6. Presence of ISTS at the solar park border therefore allows India’s solar-resource rich states
to transfer solar energy to solar-resource poor states, whose distribution utilities nevertheless face
renewable purchase obligations and must meet these by “importing” renewable energy from
elsewhere. This is a nascent or not yet developed market, which will be supported by the
implementation of the current project and a few more like it.
7. The activities will involve setting up of substations at the periphery of the solar park,
building infrastructure using the latest technology (like SCADA, GIS, STATCOM, bay controller,
OPGW, PLCC, etc.), real time monitoring of solar generation and hence integration of solar energy
with inter-state transmission system.
8. Since all the solar parks have not been finalized these investments under this project will
be taken up in a phased manner. The following solar parks that are in advanced stages, to be taken
up immediately:
9. Component 1. Transmission evacuation infrastructure for 2000 MW Pavagada Solar
Park in Karnataka (US $180 million). This will entail: (i) establishment of 5x500MVA,
400/220kV pooling substation at Tumkur along with 1x125MVAR Bus Reactor; (ii) Tumkur
Pooling Station-Hiriyur 400kV D/C transmission line; (iii) Hiriyur-Mysore 400kV D/C line; (iv)
LILO of Gooty-Madhugiri 400kV D/C line at Tumkur pooling station; and, (v) +/-150MVAR
STATCOM at Tumkur.
10. Component 2: Transmission evacuation infrastructure for 750 MW Rewa Solar Park in
Madhya Pradesh (US $100 million). This will entail: (i) establishment of 3x500MVA, 400/220kV
pooling station at Rewa with 1x125MVAR Bus Reactor, and (ii) LILO of Vindyachal-Jabalpur
400kV D/C line at Rewa Pooling Station.
11. The tentative list of the schemes that may be financed under the project includes
Transmission system Neemuch and Agra (MP) solar parks, Mehboobnagar (Telangana) solar parks
and any other future transmission schemes for solar parks in the states of Karnataka, MP and
Telangana. These will be finalized upon obtaining approval from Central Electricity Authority
(CEA) and/or Standing Committee on Power System Planning. Additional transmission
subprojects/schemes will also be identified to meet the overall funding commitment.
23
12. POWERGRID is aware of the importance of real time monitoring of solar generation and
its impact on the grid. Hence, it has already proposed to establish a Renewable Energy
Management Center (REMC) at Karnataka State Load Despatch Centre (SLDC) and Southern
Region Load Despatch Centre (SRLDC). REMC at MP SLDC is under consideration. These will
be funded either through internal resources of POWERGRID or from sources other than the World
Bank. The Bank’s project focuses on financing the transmission network assets only but
establishment of these REMCs will be monitored during the project cycle.
13. POWERGRID, in its capacity as CTU, is designated as the Nodal Agency for grant of
Connectivity, Long-Term Access and Medium-Term Open Access to the inter-State transmission
system as per the Regulation 4 of the Central Electricity Regulatory Commission (Grant of
Connectivity, Long-term Access and Medium-term Open Access in Inter-State transmission and
related matters) Regulations, 2009. Under this, POWERGRID ensures that the generators,
irrespective of source of generation (whether conventional or renewable), files a long term open
access (LTA) application with it before it takes up the proposal for implementing any transmission
investments at inter-state level. Once LTA is finalized and submitted, POWERGRID along with
State Transmission Utility (if the State’s network is likely to be used) carries out the necessary
interconnection study as specified in Central Electricity (Technical Standards for Connectivity to
the Grid) Regulations, 2007. A detailed load flow study for the network is carried out and
accordingly establishing new links as well as strengthening of the existing networks is undertaken.
14. Commercial Aspects of the project: CERC has directed not to levy any transmission
charges on the solar developers if the evacuation lines are ISTS (refer Central Electricity
Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) Regulations,
2010, amended in March 2015). Since all discoms are subject to Renewable Purchase Obligations
it is important to create a level playing field for discoms that are located far away from solar-
resource rich locations, as they will have to purchase their renewable energy from generators
located in solar-rich regions. The transmission charges are to be calculated as decided by CERC
regulations and to be borne by the beneficiary states hence socializing these transmission costs in
order to create a level playing field for all discoms. As India is following Point-of-Connection
(PoC) mechanism, all the Designated ISTS Consumers (DICs) will bear this transmission cost.
PoC is the methodology of computation and sha ring of ISTS Charges and Losses among DICs
which depends on location and sensitive to distance and direction of the node in the grid. Charges
would be computed for each node of DICs based on Hybrid Method as explained in the Regulations
(Refer Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges
and Losses) Regulations, 2010). Since the costs are being socialized, part of MNRE subsidy
earmarked for solar parks along with access to concessional financing will contribute towards
reduction in such transmission charges to minimize the burden on DICs and to ensure that the cost
per kWh for solar PV remains affordable even for states that are located far away, to avoid placing
a burden on those discoms and their customers.
15. Proposed developers and off-takers of the parks: In Pavagada solar park in Karnataka, it
has been proposed that NTPC, a central sector utility, will set up 600MW solar project to be set
up through bundling with unallocated thermal power under JNNSM, Phase II, Batch II scheme.
This 600MW is proposed to be purchased by the distribution companies of Karnataka. SECI,
another central sector organization, has proposed to install 500MW capacity of solar power
24
projects whereas remaining capacity will be allocated to solar power developers including captive
power producers through bidding process. This is in keeping with the strategy in Karnataka to use
public sector companies as anchor tenants in the solar park so that they may quickly start operations
and also create a market for large scale EPC contractors to bid for such opportunities (to build the
generation capacity that will be owned by NTPC and SECI) and thereby demonstrate the
operations of the park. This public sector demonstration effect in Phase 1 will give confidence to
private commercial lenders that the park and its transmission infrastructure is indeed working
smoothly and will thereby mitigate risk perceptions of private developers who seek debt financing
for large scale generation projects. Both public and private developers are free to sell to customers
located in the state, or in any location in the country, using the inter-state evacuation infrastructure.
It is anticipated at this stage that about 1.5GW (that is almost 75% of the installed capacity of the
park) of the installed capacity will serve the State of Karnataka.
16. Access to National Grid ensures that any surplus power generated within the park and the
state can be easily dispatched to rest of the states. Furthermore, POWERGRID has rich experience
of successfully establishing 400kV network and given the grid intermittency issues linked to
renewable energy generation, it has been considered prudent to evacuate entire energy from the
park through ISTS network. With regard to absorption of solar power within the state, since the
actual generation of solar energy is much less than the installed capacity, the power from Pavagada
park to be absorbed within the state will be balanced by the existing hydropower plant in the state
(installed capacity of 3.6GW).
17. In MP, it has been proposed that the entire capacity will be set up through competitive
bidding. As off-takers of the power, the state government of MP is targeting to absorb 300MW,
the state of Chattisgarh to absorb 200 MW and the state Government of Uttar Pradesh to absorb
250 MW.
18. Technical Standards for Connection to the National Grid: India already has a well-
established ‘Indian Electricity Grid Code, 2010’ (IEGC) issued, monitored and amended from time
to time by Central Electricity Regulatory Authority (CERC). The IEGC lays down the rules,
guidelines and standards to be followed by various persons and participants in the system to plan,
develop, maintain and operate the power system, in the most secure, reliable, economic and
efficient manner, while facilitating healthy competition in the generation and supply of electricity.
The IEGC brings together a single set of technical and commercial rules, encompassing all the
Utilities connected to/or using the ISTS. IEGC clearly defines the Planning Code for ISTS, the
Connection Code that specifies minimum technical and design criteria to be complied by any user
seeking connection to the ISTS to maintain uniformity and quality across the system, the Operating
Code to maintain efficient, secure and reliable grid operation, and, the Scheduling and Despatch
Code. The Regional Power Committee (RPC) in the region monitors the instances of non-
compliance of the provisions of IEGC and deliberate on the ways in which such cases of non-
compliance are prevented in future by building consensus. Given that Indian Grid is one of the
most complex grids and the third in terms of size in the world, IEGC has been able to successfully
achieve the desired purpose in grid operations and its stability. But with target of adding renewable
energy generation at a very large scale, it is important to note that introduction of suitable technical
standards for grid connectivity, specifically for solar generation, are required to be developed
25
further by Central Electricity Authority (CEA), the planning arm of Ministry of Power (MoP).
Project preparation will look into the developments on this aspect as well.
19. The States along with MNRE, which is the central ministry for the New and Renewable
Energy sector in India have drawn-up a long list of candidate solar parks. The proposed project
can fund any of the transmission evacuation project from solar parks in Madhya Pradesh,
Karnataka and Telangana. Following table shows the summary of planned long list of potential
solar parks.
S.No State Location & capacity
Type
Intra-State Inter-State
1 Gujarat Banaskantha (700 MW) - 700
2 Madhya Pradesh Rewa (750 MW)
Neemuch (435 MW) 1,500
Agar (315 MW)
3 Telangana Gattu, Mehboob Nagar (1000 MW) 1,000
4 Andhra Pradesh Anantpur (1500 MW) 1,000 1,500
Kurnool (1000 MW)
5 Karnataka Tumkur (2000 MW) 2,000
6 Uttar Pradesh Jalaun (370 MW) 230 370
Sonbhadra, Allahabad & Mirzapur (230 MW)
7 Meghalaya West & Esat Jayantia Hills (50 MW) 50
8 J&K Leh & Kargil (7500 MW) 7,500
9 Punjab
Patiala, Fatehgarh Sahib, Ludhiana & Gurdaspur
(1000 MW) 1,000
10 Rajasthan Bhadla (1700 MW) & Jaisalmer (2000 MW) 700 3,000
11 Tamil Nadu Ramanathapuram (500 W) 500
12 Odisha Location not stated (1000 MW) 1,000
Total 22,050 4,480 17,570
20. The section below provides details about the proposed solar park in Karnataka.
Solar Parks in Karnataka
21. There are around five Solar Parks proposed in the state of Karnataka and around 25 such
parks across the country in association with the Solar Energy Corporation of India (SECI);
Government of India. KREDL has taken the advance initiative in the Tumkur district to develop
the first Solar Park of the state of the cumulative capacity of 2000 MW. The power evacuation
facilities from Solar Park will be furnished by Power Grid Corporation of India Limited
(POWERGRID).
22. KREDL has selected the land in Pavagada Tehsil of Tumkur district of the state of
Karnataka. Presently around 14000 acres of the land has been identified for which the acquisition
26
process has been started. The selected land required less amount of civil work and well addresses
the essential requirements of Solar Park. It has been noticed that the selected location satisfies
most of the essential requirements towards setting up a Solar Park in the vicinity. The project is
planned with multi-crystalline and CdTe based Thin Film Solar PV technologies (which are the
well mature and proven technology across the globe) along with central type inverter for minimum
project capacity of 50 MW. The present Detailed Project Report (DPR) contains all key aspects of
a Solar Park of the capacity of 2000 MW in the Tumkur District of the state of Karnataka, India.
Current Status
23. Project Implementing Agency: For the World Bank loan, a JV company between KREDL
and SECI will be the project implementing agency. It has been formed to oversee the development
of solar parks in the state during project preparation.
24. Land Status: A plot of approximately 11,000 acres of private land has been identified for
project site. To use this land, JV proposes to sign a land lease agreement with farmers, to avoid
delay in land acquisition. Farmers have the option to lease their land on lease for 25-35 years. So
far, more than 2000 farmers totaling 11,000 acres of land have already given their consent letter
for signing lease.
Planning for construction of shared infrastructure which includes construction of civil
infrastructure and transmission infrastructure has been started.
Long Term Application (LTA): JV has already applied for LTA application with
POWERGRID following CERC’s regulations on ‘Grant of Connectivity and Open
Access’.
Land Lease Agreements: Land records for 2000 farmers are being scrutinized for land lease
agreements under solar park. 21000 INR land lease rate per acres and 5 % escalation every
two years has been fixed after stakeholder consultation with the farmers. 800 records has
already confirmed, 400 are being clarified. It terms of timelines, land lease for all the plots
will be signed by Nov end and land will be transferred to JV by 1st January 2016.
Land Conversion: Gazette notification has already been issued by Government of
Karnataka (GoK) for conversion of land from agriculture to solar in Pavagada area.
Conversion letter has gone from energy to revenue department in GoK and process of land
conversion will be started very soon for the farmers.
25. Project finance: As mentioned above, the project aims to demonstrate minimizing public
funding requirement through a combination of scale, long-tenor financing and tariff structuring.
The proposed funding is as follows:
Solar Park (Shared infrastructure): MNRE will provide grant at the rate of up to INR 20
lakhs/MW or 30% of the project cost including grid connectivity cost whichever is lower,
which will be released as per the milestones as defined under its Solar Park Scheme. Of
the available MNRE grant, 50% (tentative) will go towards transmission evacuation to
POWERGRID.
Likely composition for shared infrastructure for Pavagada Solar Park total capital cost
requirement of $180 m
a. MNRE grant for solar park- $75 m
b. Partial upfront payment of 4 lakh per MW- $15 m
27
c. World bank funding – $90 m
26. Power Offtake: To avail the ISTS, the host state has to evacuate at least 10% of the power
generated outside. GoK is planning to offtake 80-90% of the power generated from Pavagada Solar
Park. The remaining power will be transmitted outside the state using ISTS.
Tentative project allocation of solar park
a. 600 MW NTPC (already tendered, PPA with NTPC, owned and operated by
private developers)
b. 1000 MW NTPC (TBC, owned and operated by NTPC with INR 4 tariff)
c. 400-500 MW KREDL (TBC, owned and operated by private developers, PPA
with state discom)
d. SECI- 500 MW (TBC)
It is also decided that Pavagada capacity will not increase more than 2000 MW and other park of
200-500 MW will be developed separately
Site Assessment
27. The selected land (around 14000 acres at present stage) for Solar Park establishment is
located in five villages namely Valluru, Rayacharlu, Balasamudra, Kyathaganacharlu and
Thirumani of Pavagada Taluk of Tumkur district of the state of Karnataka. The site assessment
section addresses the connectivity and accessibility (road/ rail/ air) aspects of the region. Pavagada
comprises established road connectivity as the State Highway (KA SH 03) passes from the city
and connect it from Madugiri to Chikkahalli. It has been observed that the project location receives
monthly average daily solar irradiance of 4.81 kWh/m2(August) to 6.55 kWh/m2 (March). The
annual GHI is 2008 kWh/m2 (annual average daily 5.50 kWh/m2) which contains 826 kWh/m2
(annual average daily 2.26 kWh/m2) diffuse component (around 41%).
Infrastructure plan of solar park
28. This section elaborates the infrastructure development over the conceptual plan of the
Solar Park. There are five key dimensions of infrastructure addressed in the section viz. Site
preparation (leveling, cleaning, plantation for dust deposition and wall with gates etc.), Land
(survey, soil investigation and geotechnical aspects etc.), Roads & Network (major and minor
roads of different width), Power Evacuation & Transmission (metering system, construction power
arrangements and transmission substation etc.) and Water Supply Systems (Water Requirement
for Module Washing and Other Purposes, Water Requirement for 2000 MW Solar Park, Source
and storage of Water and Requirement of Water Treatment etc.).
29. The proposed 2000 MW Solar Power would be developed in eight blocks of 250 MW
capacity. For each 250 MW Solar Power capacity block, one pooling substation of 66/ 220 kV is
proposed in which 2 x 150 MVA step-up transformers are considered. 250 MW block is further
subdivided into 50 MW sub blocks. Thus, these 5 X 50 MW sub blocks shall be connected to
pooling substation through 66 kV underground cables. The voltage will again be stepped up to
220kV at the Solar Project Pooling Station and again stepped up to 400kV at the proposed 400kV
Grid Substation by POWERGRID at Solar power. Karnataka Solar Power Development
Corporation Limited (KSPDCL)(JV of SECI and KREDL) will establish 8 Nos. of 220/66kV
28
pooling stations at Pavagada site to evacuate 2000MW solar power generated at the Park. The
400kV Grid substation at the Solar Project is proposed to be connected to POWERGRID’s 765KV
Station at Madhugiri.
Project cost estimates
30. The land is proposed to purchase on the annual lease basis of Rs 21000 per acres with 5%
escalation on base year lease every second year; however the current price of the private land in
the vicinity has also been presented from the ongoing practices in the vicinity. Detailed costing of
8 numbers of 220/66 kV substation, 200 kV transmission line and 400 /220 kV substation will be
prepared given with their elaborated bill of material. The cost of administrative building,
warehouses, training center etc. have been estimated from best market practices in solar power
projects. In addition the present cost (recently commissioned projects) of solar PV power projects
with multi-crystalline and thin film technologies in India has been given with detailing from in
house data.
31. Table XX below presents the key insights of the Solar Park of the capacity of 2000 MW
in Tumkur district of the state of Karnataka, India.
Table XX. Project at a glance
1. S.
No
2. Particulars 3. Description
4. Project site Pavagada
5. District Name Tumkur
6. Name of the
State
Karnataka
7. Geographical
coordinates
Latitude 14.1oN and
Longitude 77.27oE
8. Land availability
(acres)
More than 14000 acres
9. Land quality Barrein and non-agricultural land
10. Connectivity and
accessibility
Well establishes and adjacent to Sate highway-03 of Karnataka
11. Minimum plant
size capacity
50 MW
12. Minimum plot
size (acres)
250 acres
13. Nearest airport Bangluru
14. Nearest railway
station
Hindupur Railway station (52 KM), Anantapur Railway station (101
KM) and Bellary (137 KM) are the nearest Railway Stations
15. Solar PV
Technology
Multi-crystalline solar PV /Thin Film
16. Proposed
Voltage Level
66 kV from each Plant and then step upto 220kV
29
17. Tentative Capital
Cost
Capital Cost
Components
Unit Cost (Phase
1)
Cost
(Phase 2)
Total Solar park Cost Rs Crores
Land cost12
21,000 Rs per acre per
year with 2% escalation
on base year (Escalation
in every 2nd year)
Rs Crores
29.73 30.1
Site Development Rs Crores 17.5 16.6
Road & Drainage
system
Rs Crores
21.6 5.10
Street light Rs Crores 3.39 0.69
Water Supply system Rs Crores 5.85 5.72
Poolingi substations Rs Crores 187.08 187.08
Transmission line cost Rs Crores 10.00 10.00
Admin Building Rs Crores 11 -
Total Hard Costs Rs Crores 286.15 255.29
Total Hard costs
(P1+P2)
Rs Crores 541.47
Soft cost Rs Crores 11.9 17.6
Total soft cost Rs Crores 29.5
Total project cost Rs Crores 571.0
32. Upfront payment from project developer will be utilized in solar park development
expenditure by solar park agency. Annual fee will cater to recurring expenses over the project life.
Timelines: Scheduled timelines for setting up of Solar Power Park is as under:
S. No. Milestone Timelines
1 Pavagada Solar park preparation March 2015
2 Land leasing process completion
and transfer of land to JV
1 Jan 2016
3 Construction of Pooling Substation,
Land Development and other
Common facilities as per DPR
Transmission line and Grid
Connectivity
Aug 2017
4 1000 MW commissioned Sep 2017
5 2000 MW commissioned Sep 2018
33. State Government’s obligation to purchase power: Karnataka State Government in which
the solar park is developed has agreed agree to buy atleast 1600 MW of the power produced in the
park through its Discom.
12 Land lease is considered in capital cost only till Phase-1 and Phase-2 CODs. After COD, Land cost is considered as an annual expense. For
first 6 months, No land lease is considered as financial closure is attained after 6 months of project award.
30
34. Similar analysis and information will be collected for Rewa solar park in Madhya Pradesh.
Rewa solar park is also currently under development and appraisal is underway.
31
Annex 3: Implementation Arrangements
Financial Management, Disbursements and Procurement
Financial Management
1. POWERGRID shall be responsible for the project’s financial management arrangements.
POWERGRID is already implementing Bank funded projects and is well aware of Bank’s
fiduciary requirements. POWERGRID shall provide the fiduciary assurance to IBRD on proper
and efficient use of Bank financing. POWERGRID will implement the Project as per the
financial management provisions of Loan Agreement and as further detailed in the Project
Implementation Plans.
2. Staffing. POWERGRID will provide for adequate financial management staffing. The
project’s financial arrangements would be handled by the finance staff working at the Corporate
Centre, Regional Headquarters and the project site office along with regular finance work. The
International Finance division and Resource Mobilization Cell at the Corporate Centre would
coordinate with the various units within POWERGRID for seeking disbursements and servicing
the existing debt with the Bank respectively. It would be responsible for meeting the information
requirement of the external agencies and providing interim financial reports in the agreed
formats to the Bank through the Corporate Planning Department. As on March 31, 2015, total
finance staff in POWERGRID is 386.
3. Budgeting. Preparation of proper plan and budget plays an important role in timely
implementation of a project. Planning and budgeting involves identifying specific tasks or
objectives of the project to be achieved in a given time frame. The planning and budgeting at
POWERGRID for the project will be as described herein further. For effective project
implementation, POWERGRID shall prepare activity wise:
i. An overall plan for the duration of the project;
ii. Annual plan and budget with quarterly break-ups; and
iii. Quarterly statements providing variance between planned and actual
expenditure.
4. Accounting Policies and Procedures. POWERGRID has been incorporated as a company
under the Companies Act, 1956, and hence the financial reporting (balance sheet and the profit
and loss account) is governed by the provisions of that Act. In accordance with the Companies
Act, POWERGRID follows accrual/ commercial system of accounting and adheres to the
national accounting standards, as issued by the Institute of Chartered Accountants of India and
notified by GoI. Project accounting shall be carried out in accordance with accounting policy of
POWERGRID using the existing accounting systems. The claims submitted to the Bank will be
on cash basis eliminating items like retention money and unpaid liabilities. The project
accounting will be carried out at the respective Regional headquarter and the accounting records
will also be maintained at the said location. Regional headquarter/ Corporate Centre will be
responsible for release of all payments under the project as per current practice followed in
POWERGRID. Bills will be duly approved as per the existing delegation and procedures and
will be forwarded to Regional headquarter/ Corporate Centre for subsequent checks and release
32
of payment. POWERGRID shall maintain all records and documents (contracts, orders, invoices,
bills, receipts and other documents) evidencing expenditures under the Project and retain these
until at least the later of: (i) one year after the Bank has received the final/ last audited financial
statements required under the IBRD Loan; and (ii) two years after the closing date of the IBRD
Loan. During such retention period, POWERGRID shall enable the World Bank representatives
to examine those records.
5. Funds Flow. The loan will be taken by POWERGRID and the disbursements will also be
managed by POWERGRID. Based on quarterly IUFRs, withdrawal claims will be submitted to
the Bank by POWERGRID for disbursement. The funds flow and reporting arrangements under
the project will be as below:
6. Reporting. The FM Reporting under the project shall be as follows:
a. IUFR: POWERGRID would be required to submit to the Bank quarterly IUFRs within
45 days from the end of the quarter. The IUFR would be prepared by POWERGRID
on the basis of information generated from POWERGRID’s MIS systems and will be
reconciled to the books of accounts and shall contain information on project
implementation including the expenditure incurred during the last quarter, and forecast
for the next two quarters. The format of the IUFR is provided in the PIPs and will also
be appended to the Bank's Disbursement Letter.
b. Project Annual Financial Statements: The project annual financial statements will
include (a) IUFRs for the fourth quarter; and (b) any other statement agreed with the
Bank.
7. Inventory and Asset Management. POWERGRID’s own inventory management systems
and procedures will be used for the purposes of the project. The inventory procured shall be used
in the identified projects generally. POWERGRID, which will have the primary responsibility
for physical verification of inventory and assets under construction, the Internal and External
Auditors will also carry out physical verification on a sample basis.
IUFR, claims, reports
Invoices
Funds
Funds
World Bank
POWERGRID –
Segregated Bank
Account(s)
Vendors/ Contractors
33
8. Internal Audit: The internal audit of the project shall be carried out by: (i) option 1:
Hiring services of The Institute of Public Auditors of India (IPAI), a body of specialist in public
finance with focus on Auditing, comprising of serving and former officers from the Indian Audit
& Accounts Services and also senior Accounts and Audit professional with diverse experience in
Financial Management functions. In case it does not work out, then (ii) option 2: Internal Audit
firm empanelled by POWERGRID based on offer for EoI on competitive basis shall be
appointed as Internal Auditors.
The scope of audit will be as per agreed ToR. Based on the audit, the auditor will provide
suggestions for improvement.
9. External Audit13. The external audit of the project will be carried out by a firm of
chartered accountants appointed as per procurement procedure acceptable to the Bank. The ToRs
for the external audit will be agreed with the Bank and provided in the PIP. The annual audit
report shall be submitted to the Bank within nine months of the closure of the financial year. The
annual audit report would be accompanied by (i) audited project financial statements which
would separately identify each component under the project, its progress and the funding sources
for each of the components, with management assertion; (ii) an audit report expressing an
opinion on (a) the project financial statements; and (b) the accuracy of the IUFRs submitted
under the project; and (iii) management letter from auditors highlighting significant issues to be
reported to the management.
10. Eligible expenditure. All expenditure relating to project which will be undertaken in line
with the loan agreement and disbursement letter are an eligible expenditure.
11. Ineligible expenditure. The following expenditure are treated as ineligible expenditure for
financing from the World Bank under this project:
i. Retention money/ security deposit retained (till the time it is not released);
ii. Expenditure incurred after the project closing date;
iii. Expenditure not in line with project description in legal agreement;
iv. Procurement not in line with agreed procurement procedures;
v. Land costs and expenditure on R&R;
vi. Expenses disallowed by auditors and not resolved adequately;
vii. Expenses found ineligible during Bank review;
12. Disclosure. Under the Access to Information Policy of the Bank, the annual project audit
report and the audited Project Financial Statements (PFS) will be disclosed in the Bank's website.
Disbursements
IBRD funds will be disbursed using reimbursement method, based on expenditure reported in the
quarterly IUFRs. The other methods of disbursement available under the project shall be:
13 As on date, there are no overdue audit reports from the implementing agency (POWERGRID).
34
advance payment and direct payment. Supporting documents required for Bank disbursement
using these various methods are documented in the Disbursement Letter issued by the Bank.
Procurement
13. Procurement for the proposed project will be carried out in accordance with the World
Bank’s "Guidelines: Procurement of Goods, Works and Non-Consulting Services under IBRD
Loans and IDA Credits and Grants by World Bank Borrowers" dated January 2011 revised July
2014 (Procurement Guidelines); and "Guidelines: Selection and Employment of Consultants
under IBRD Loans and IDA Credits and Grants by World Bank Borrowers" dated January 2011
revised July 2014 (Consultant Guidelines) and the provisions stipulated in the Legal Agreement.
The project would be subject to the Bank’s Anti-Corruption Guidelines, dated October 15, 2006,
and revised January 2011.
14. E-procurement System. POWERGRID is going to use the e-procurement system for all
procurements to be carried out under the project. An assessment of the e-procurement system
being used by POWERGRID [supported by TCIL ltd] was carried out as per the Multilateral
Development Banks (MDB) requirements and the system is acceptable. For any ICB
procurements, POWERGRID has to ensure that foreign bidders are not required to travel to India
for getting the Digital Signature to participate in bidding, by providing assistance to them. The
assessment was carried out as part of the ongoing PSDP-V project.
15. The following major procurements are envisaged under the Project:
a. Procurement of Works: The works envisaged to be procured under the project are still to
be identified.
b. Procurement of Goods: “Procurement of Goods” includes intra-state transmission for
evacuating the power generated from the identified solar parks (funded under the Bank
funded solar parks project), which would be carried out based on using “Procurement of
Plant Design, Supply and Installation” basis. Further Goods would also be procured
under “Procurement of Plant Design, Supply and Plant Design, Supply and Installation”
contracts following ICB and NCB procedures of the Bank using the Bank’s Standard
Bidding Documents (SBD) as a base and as agreed with the Bank.
The Bank’s SBD for “Procurement of Goods, March 2013” and the Bank’s SBD for
“Procurement of Plant Design, Supply and Installation, April 2015 version. The
provisions of paragraphs 2.55 and 2.56 of the Procurement Guidelines, providing for
domestic preference in the evaluation of bids, shall apply to only goods manufactured in
the territory of the borrower.
Other goods including IT equipment and software will be procured following ICB, NCB,
shopping methods and having framework agreements. Framework Agreements using
DGS&D rate contracts can be used to procure goods up to NCB threshold subject to
incorporation of right to audit and fraud & Corruption clauses. The Standard Bidding
35
documents of the Bank as agreed with Government of India task force (as amended from
time to time) for goods and works procurement under NCB will be used.
c. Selection of Consultants: The consultancies needed are still to be identified and the
selection / hiring of such consultancies shall follow the Bank Guidelines.
The full details of the procurements to be carried out under the project would be finalized during
appraisal and will be disclosed in the Procurement plan.
Procurement capacity and Risk Assessment of implementing agencies
16. Procurement Risk Assessment: POWERGRID would be responsible for undertaking all
procurements and contract management activities under the project.
The Procurement Risk Assessment and Management System (PRAMS) is presently being
undertaken and would be finalized during appraisal. POWERGRID has staff with expertise in
procurement and contract management in conducting procurement in accordance with Bank
policies and procedures, having successfully handled procurement activities under Bank funded
projects. Hence, the procurement risk rating is rated as “LOW”.
17. Record Keeping. All records pertaining to award of tenders, including bid notification,
register pertaining to sale and receipt of bids, bid opening minutes, Bid Evaluation Reports and
all correspondence pertaining to bid evaluation, communication sent to/ with the World Bank in
the process, bid securities, approval of invitation/evaluation of bids by POWERGRID would be
retained by POWERGRID.
18. Procurement Plan. For contracts to be financed by the Bank, the different procurement
methods or consultant selection methods, the need for prequalification, estimated costs, prior
review requirements, and time-frame are agreed between the Borrower and the Bank in the
procurement plan.
19. Procurement Plan and Readiness. The draft procurement plan for procurements to be
taken up under of project implementation is being finalized and is enclosed as Annex 3. The
Procurement plan would be prepared using the Bank system “STEP”. The procurement plan will
be updated using the system at least annually or as required to reflect the actual project
implementation needs and improvements in institutional capacity.
20. Disclosure of Procurement Information. The following documents shall be disclosed on
the POWERGRID website: (i) procurement plan and updates; (ii) invitation for bids for goods
and works for all ICB, NCB and shopping contracts; (iii) request for expression of interest for
selection/hiring of consulting services; (iv) contract awards of goods and works procured
following ICB/NCB procedures; (v) list of contracts/purchase orders placed following shopping
procedure on quarterly basis; (vi) list of contracts following DC on a quarterly basis; (ix)
monthly financial and physical progress report of all contracts; and (x) action taken report on the
complaints received on a quarterly basis.
36
21. The following details shall be sent to the Bank for publishing in the UNDB and World
Bank external website: (a) invitation for bids for procurement of goods and works using ICB
procedures, (b) contract award details of all procurement of goods and works using ICB
procedure, and (c) list of contracts/purchase orders placed following DC procedures on a
quarterly basis.
22. Further POWERGRID/ State Utilities will also publish on their websites, any information
required under the provisions of “suo moto” disclosure as specified by the Right to Information
Act.
23. Review by Bank: All contracts not covered under prior review by the Bank will be subject
to post review during Implementation Support Missions and/or special post review missions
including missions by consultant hired by the Bank. For the avoidance of doubts, Bank may
conduct, at any time, Independent Procurement Review (IPRs) of all the contracts financed under
the loan.
24. Frequency of Procurement Supervision. Two missions in a year each at an interval of six
months are envisaged for procurement supervision of the proposed project.
25. Contract Management. A fully staffed PIU (POWERGRID) will be responsible for
overall project/ contract management. The team will be ably assisted by a multi-skilled project
management team, engaged to provide overall implementation support and monitor all works
and consultancy contracts.
.
37
Draft Procurement Plan
I. General
1. Project Information
Country : India
Borrower : Government of India
Project Name : Transmission for Power Evacuation for Solar Parks
Loan Credit No. :
2. Bank’s Approval Date of the Procurement Plan :
3. Date of General Procurement Notice : Dec 2015
4. Period Covered by this procurement plan : 24 Months
II. Goods, Works and Non consulting Services
1. Thresholds for method of Procurement:
Method of Procurement Thresholds for Method (USD equivalent)
ICB (Goods) > 3 million
NCB ( Goods) > USD 100,000 and up to USD 3 million
Shopping (Goods) Up to USD 100,000
ICB (Supply & Installation) > 40 million
NCB (Supply & Installation) > 100,000 and up to USD 40 million
ICB (Non-Consulting Services) > 1 million
NCB (Non-Consulting Services) < 1 million
Direct Contracting No Threshold; meet paragraph 3.7 of
Guidelines
Prior Review Thresholds:
(a) For the purpose of clearance of the bidding documents, the value of each slice will be
considered:
If the estimated value of any slice of a package is more than US$ 25 million, the bidding
document for the entire package will be prior reviewed.
If the estimated value of each slice is less than US$ 25 million, but the combined value of
all the slices is more than US$ 25 million, the bidding documents will not be prior
reviewed. However, one sample bidding document will be agreed with the Bank for each
type of package and the bidding documents, including those under post review, will be
38
prepared as per this agreed sample. The clauses which will need modifications will also be
agreed with the Bank.
(b) For the purpose of clearance of the recommendation for award, the following will considered:
If the estimated value of any of the slices in the package is US$ 25 million or more, the
entire package will be subject to prior review.
If the estimated value of each slice is less than US$ 25 million but the value of complete
package is US$ 25 million or more, the award recommendation and the evaluation report
for the complete package of all the slices will be subject to prior review. For this purpose,
POWERGRID will forward a set of complete bidding documents and the evaluation report
to the Bank for prior review.
The Prior Review Thresholds will be reviewed and updated during the implementation of
the project and modified, based on the risk assessment.
In the case of contracts subject to prior review, before granting / agreeing to (a) a material
extension of the stipulated time for performance of a contract; or (b) any substantial modification
or waiver of the scope of services or other significant changes to the terms and conditions of such
that the contract, including issuing; or (c) any change variation order or orders under such contract
amendment (except in cases of extreme urgency) which would in aggregate, singly or combined
with all variation orders or amendments previously issued, increase the original contract amount
of the contract by more than 15% (fifteen percent); or (d) the proposed termination of the original
price contract, the Borrower shall seek the Bank’s no objection to the proposed extension,
modification, or change order.
A copy of all amendments to the contract shall be furnished to the Bank for its record.
2. Prequalification
Not Applicable
3. Domestic Preference: The provisions of paragraphs 2.55 and 2.56 of the Procurement
Guidelines, providing for domestic preference in the evaluation of bids is applicable.
4. Reference to Project operational/Procurement Manual
Standard Bidding Documents agreed between Project and Bank will be used for all
Supply & Installation, consultancy, Works and goods procurements.
5. Any Other Special Procurement Arrangements:
National Competitive Bidding (NCB) method for procurement and goods and works as per the
above value thresholds will be conducted in accordance with paragraph 3.3 and 3.4 of the World
Bank Procurement Guidelines and the following provisions: a. Only the model bidding documents for NCB agreed with the GoI Task Force (and as
amended for time to time), shall be used for bidding;
b. Invitations to bid shall be advertised in at least one widely circulated national daily
newspaper (or on a widely used website or electronic portal with free national and
39
international access along with an abridged version of the said advertisement published
in a widely circulated national daily inter-alia giving the website/electronic portal details
from which the details of the invitation to bid can be downloaded), at least 30 days prior
to the deadline for the submission of bids;
c. No special preferences will be accorded to any bidder either for price or for other terms
and conditions when competing with foreign bidders, state owned enterprises, small
scale enterprises or enterprises from any given state;
d. Extension of bid validity shall not be allowed with reference to Contracts subject to
Bank prior review without the prior concurrence of the Bank (i) for the first request for
extension if it is longer than four weeks; and (ii) for all subsequent requests for extension
irrespective of the period (such concurrence will be considered by Bank only in cases
of Force Majeure and circumstances beyond the control of the Purchaser/ Employer).
e. Re-bidding shall not be carried out with reference to Contracts subject to Bank prior
review without the prior concurrence of the Bank. The system of rejecting bids outside
a pre-determined margin or “bracket” of prices shall not be used in the project;
f. Rate contracts entered into by Directorate General of Supplies and Disposals will not be
acceptable as a substitute for NCB procedures unless incorporation of right to audit and
Fraud & Corruption clauses. DGS&D contracts will be acceptable however for any
procurement under the Shopping procedures.
g. Two or three envelope system will not be used (except when using e-Procurement
system assessed and agreed by the Bank);
h. No negotiations are conducted even with the lowest evaluated responsive bidders.
6. The bid evaluation will be carried out as per agreed timeline in the Procurement Activity
Schedule
40
Summary of the Procurement Packages planned during the first 24 months after project
effectiveness (including those that are subject to retroactive financing and advance procurement):
Goods/ Works:
Sr
No
Description Estimated
to Cost
(INR
Million)
Est
cost
USD
million
Method of
Procurement
Post /
Prior
Expected
Date of Bid
Opening
Expected
Date of
Contract
41
III. Selection of Consultants
1. Prior Review Threshold
Method of Procurement Threshold (USD
Equivalent) Prior Review Threshold
(a) Quality and Cost Based
Selection No threshold First 1consultancy contract and
subsequently all other contracts
above USD 2.0 million (b) Quality Based Selection No threshold
(c) Selection Made Under a
Fixed Budget No threshold
(d) Least Cost Selection No threshold
(e) Selection Based on
Consultant’s Qualifications < 300,000
(f) Single Source Selection of
firms As per Consultant
Guidelines Para 3.9 All contracts above USD
50,000
(g) Selection of Individual
Consultants No threshold All contracts above USD
500,000. In case of contract to
individuals, the qualifications,
experience, terms of reference
and terms of employment shall
be subject to prior review
Note: The Prior Review Thresholds will be reviewed during the implementation of the
project and modified.
In the case of contracts subject to prior review, before agreeing to: (a) an extension of the
stipulated time for performance of a contract; (b) any substantial modification of the scope
of services, substitutions of key experts, or other significant changes to the terms and
conditions of the contract; or (c) the proposed termination of the contract, the Borrower
shall seek the Bank’s no objection. A copy of all amendments to the contract shall be
furnished to the Bank for its record.
2. Short List comprising entirely of national consultants: Short list of consultants for services,
estimated to cost less than USD 800,000 equivalent per contract, may comprise entirely of
national consultants in accordance with the provisions of paragraph 2.7 of the Consultant
Guidelines.
3. The Request for Expression of Interest for consultancy services estimated to cost above
USD 300,000 equivalent per contract for firms shall be advertised in UNDB online and
World Bank external Website and in accordance with other provisions of Para 2.5 of the
Consultant Guidelines
42
4. Any other Special Selection Arrangements: [including advance procurement and
retroactive financing, if applicable]
5. Consultancy Assignments with Selection Methods and Time Schedule:
No 1 2 3 4 5 6 7 8
Ref No Description Of
Assignment
Estimated
Cost
(Million
US$)
Selection
Method
Review
by Bank
(Prior
/Post)
Expected
Proposals
Submission
Date
Expected
Contract
Award
Date
Comments
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Environmental and Social (including safeguards)
43
Annex 4: Implementation Support Plan
Strategy and Approach for Implementation Support
I. The strategy for implementation support has been developed based on the nature of
activities involved in the project and their commensurate risk profile in accordance with
the SORT. The Implementation Support Plan (ISP), as described below, will be a live
document and will be reviewed regularly and revised, as and when required during the
implementation.
II. Technical Support.
III. Procurement.
IV. Financial management.
V. Environmental and Social Safeguards.
Implementation Support Plan
1. Most of the Bank team members will be based in the India country office, (Task Team
Leader is based out of DC office), technical, procurement, financial management, and safeguards
specialists, which would facilitate timely, efficient, and effective implementation support to the
client.
2. Project implementation and supervision will be conducted through:
Project launch, to be conducted soon after the project approval, to bring all project
functionaries together and ensure a clear understanding of the project scope,
design, process and responsibilities;
At least two regular supervision missions in a year during the project duration;
Intermediate technical missions by specialists, as needed;
Quarterly implementation progress reports (physical and financial progress)
prepared by the project PPIU;
A Mid Term Review (MTR) once the project is around half way in project
implementation/ loan tenure to review the progress and assess the need for any
mid-course correction and
An Implementation Completion and Results (ICR) report at the end of the project
to assess achievement towards PDO and lessons.
3. The main focus of implementation support is summarized below:
Time Focus Skills Needed Resource
Estimate
Partner
Role
First twelve
months
Investment Component
A: Fiduciary and
Safeguards, Preparation
and implementation of
contracts as per schedule
Technical
Specialist
Procurement
Specialist
Environment
Specialist
XX SW
XX SW
XX SW
XX SW
44
Time Focus Skills Needed Resource
Estimate
Partner
Role
Institutional
Strengthening
Component B
Social
Development
Specialist
Financial
Management
Specialist
Institutional
Development
Specialist
Task Team Leader
XX SW
XX SW
XX SW
12-84
months
Implementation of
Investment Component A
Implementation of
Institutional
Strengthening
Component B
Technical
Specialist
Procurement
Specialist
Environment
Specialist
Social
Development
Specialist
Financial
Management
Specialist
Institutional
Development
Specialist
Task Team Leader
XX SW
XX SW
XX SW
XX SW
XX SW
XX SW
XX SW
4. The skills mix required is:
Skills Needed Number of Staff
Weeks
Number of Trips
(Annually)
Comments
Technical Specialist XX SWs first year and
then XX SWs annually
XX
Institutional Development
Specialist
XX SWs every year XX
Procurement Specialist XX SWs first year and
then XX SWs annually
XX Country Based
45
Financial Management Specialist XX SWs first year and
then XX SWs annually
XX Country Based
Environment Specialist XX SWs every year XX Country Based
Social Specialist XX SWs every year XX Country Based
Communications Specialist XX SWs every year XX Country Based
Task Team Leader XX SWs every year XX
46
Annex 5: Economic Analysis
1. This annex discusses the rationale for public financing of the project, the valued added
from the Bank support and presents the analysis of the project’s development impact in terms of
expected benefits and costs. Since the transmission and shared infrastructure investments (that are
funded by the World Bank through two related projects) cannot have an economic return
independent of the solar PV generation investments, the economic analysis covers the entire
package of solar park investments of the Pavagada Solar Park in the state of Karnataka14. This
economic analysis is consistent with the new Bank guidelines in Operational Policy and Bank
Procedure (OP/BP) 10.00, Investment Project Financing and Social Value of Carbon in Project
Appraisal.
Rationale for public sector provision/financing
2. The Government of India has announced a bold target of installing 100GW of solar power
capacity by 2022 – a thirty fold increase from 3.7GW in 2015. The push in solar energy underpins
GoI’s Power for All program to supply 24x7 electricity to residential, commercial and industrial
consumer by 2019 and is a key part of its efforts to reduce environmental pollution and greenhouse
gas emissions. There is a need to significantly scale up of both private and public investments to
meet GoI’s solar power targets. In particular, there is a strong justification for the use public
financing to on the following grounds:
Public financing can be used to provide services where the public sector has an advantage
such as land acquisition, obtaining necessary permits, providing common infrastructure
and interconnections from the solar park to the state and national grid. This helps remove
or reduce the private sector’s risk perception about solar power and increase the
availability of private investment and financing for solar power.
Public support and financing for solar parks infrastructure is also necessary reduce the
financial costs of solar power and to enable it to be competitive with thermal generation –
so that the full externalities of solar power through avoided environmental and health
damage costs can be captured.
Value added of the Bank’s support
3. GoI has requested Bank support for solar power at the highest levels15. India’s push in solar
power will increase the share of renewable energy in India’s electricity generation mix and aid
efforts to increase electricity access and meet the growing demand in the country. However, since
solar power is intermittent energy source, this transition will have to be managed carefully and
efficiently to be successful. The World Bank Group can play a valuable role in this transition by
14 The Pavagada Solar Park has been selected because it is the most advanced in design amongst the solar parks that
Bank has been asked to finance as part of MNRE 20GW Solar Park Scheme. 15 During their July 2014 and January 2015 meetings, Prime Minister Narendra Modi and President Jim Kim had
agreed that the Bank would provide financing for Solar Parks in the country
47
(i) making long term concessional financing available for development of solar power;
(ii) sharing international knowledge and experience on how utility scale solar parks have
been implemented across the world; and
(iii) providing technical assistance and capacity building support to key stakeholders
.
Pavagada Solar Park in India’s Generation Mix
4. Assessment of the impact of a new generation source (in this case the solar park) is carried
out jointly by the State Transmission Utility (KSTCL), the Central Transmission Utility
(POWERGRID) and the Central Electricity Agency. These assessments help determine the
required investments in transmission evacuation arrangements, future generation planning as well
as any measures and investments that may be needed to manage the generation from the solar park.
5. For the Pavagada Solar Park, the implementing agency, Karnataka Solar Power
Corporation Development Limited has filed a Long Term Access Application with POWERGRID.
The LTA application indicates that up to 90% of the electricity from the park will be utilized inside
the state, with the remaining power evacuated to consumers outside the state. Based on the LTA
application, POWERGRID, STU and CEA have carried out assessments of the impact of the solar
park on the grid and generation mix. These studies will be made available to the Bank once they
have been presented at the meeting of the Standing Committee on Power System Planning in the
Southern Region in the third week of November 2015.In absence of these studies, this economic
analysis uses generation from imported coal (which is the marginal electricity generation source
for India) as the counter factual to the generation from the Pavagada solar park.
The Project and its Rationale
6. An estimated 300 million people are not connected to the national electrical grid in India
and those who are, face frequent disruptions. Power shortages in FY2015 were equivalent to about
3.6% of total energy and 4.7% of peak capacity requirements. To meet the power demand,
industrial establishments and manufacturers have been relying on diesel-based back-up power
supplies, which are significantly more expensive than grid-based electricity. Coal currently fuels
two thirds of India’s electricity generation. To avoid the global and local environmental damage
costs associated with thermal generation, the Government of India (GoI) wants to install 100GW
of solar power by 2022.The proposed project is a key part of GoI’s solar park scheme to install
20GW of utility scale solar power by 2020 and will help in meeting the rapidly growing electricity
demand in an environmentally sustainable way/.
Cost Benefit Analysis of the Pavagada Solar Park
7. The economic viability of the project was assessed through a cost-benefit analysis. Net
benefits for the Pavagada Solar Park was calculated by comparing total system costs and benefits
for the “with project” and “without project” scenario. A range of scenarios and sensitivities that
meaningfully reflect the uncertainties of key input variables are evaluated. The analysis includes
a consideration of the relevant environmental and social externalities. Monte Carlo simulation,
48
which assumes input assumptions are defined as probability distributions rather than as single “best
estimates”, is used to analyze the possibility of more than one input assumption combines
unfavorably.
Project costs
Capital costs
8. The total project (financial) cost excluding price contingencies and interest during
construction is $1.9 billion (Table 1). This includes $87 million of shared infrastructure costs, $164
million of transmission costs and $1.7 billion of PV generation capital cost. The 2014 Central
Electricity Regulatory Commissions (CERCs) benchmark capital cost for Solar PV is used as the
basis for solar generation costs; a reduction of 10% per year is assumed through to 2017 when the
actual investments are projected to take place. Subtracting taxes and duties from the base cost, one
obtains an economic cost of $1.6 billion.
Table 1 – Total project cost
Base Cost ($ Million) Taxes and Duties ($
Million)
Economic Cost ($
Million)
Shared Infrastructure 87 22 65
Transmission 164 41 123
PV Generation 1668 278 1390
1918 340.75 1578
Operating and Maintenance costs
9. The operation and maintenance (O&M) costs are estimated as 1% of the capital costs,
which computes to $14 million per year.
Grid integration costs
10. Since the grid is not designed to manage intermittent sources of generation, solar power
can impose additional coping costs on the grid. These include but are not limited to (i) the
requirements of connecting generation far away sources to load centers through transmission lines;
(ii) additional operation and maintenance costs of thermal plants if they have to operate at lower
load factors that would otherwise be the case; (iii) the need for standby generation to provide power
when there is no sunshine. It is generally agreed that these cost are negligible or very low at lower
levels of penetration of variable renewable energy. This economic analysis zero value for grid
integration cost in the base case but then uses sensitivity analysis to calculate the impact of grid
integration costs on the
Project benefits
49
Fuel costs of the thermal counterfactual using coal
11. Avoided fuel costs of thermal counterfactual (which is assumed to be coal in this economic
analysis) constitutes one of the main economic benefits associated with solar power generation.
These avoided costs are calculated based on the coal supply requirements of producing electricity
equivalent to those produced from the Pavagada solar park. A capacity utilization factor of 19% is
used the solar park based on the analysis that has been carried out in the Detailed Project Report
of the solar park. The coal is valued at import price of coal from Australia, which is higher than
the domestic price of coal in Australia.
Capacity credit of the solar park
12. A capacity credit equal to the forecast capacity factor of the solar park (19%) is used in the
base case of the economic analysis. Sensitivity analysis is then used to analyze the impact of the
capacity credit on the economic returns of the project.
Avoided global environmental damage cost
13. Avoided global externalities constitute another economic benefit of the Pavagada Solar
Park, given that solar power replaces coal generation. Emissions of coal based generation displaced
by the solar park estimated are using a emission factor of 830 tonnes/Gwh. Consistent with Bank
guidance on the social value of carbon, carbon emission reductions are valued in the base case at
US$30 in 2015 and increasing to US$80 in real terms by 2050. The low ($15 in 2015 increasing
to $50 in 2050) and the high paths ($50 in 2015 increasing to $150 in 2050) for the social value of
carbon suggested in the Bank guidance are used for sensitivity analysis.
Avoided local environmental damage costs
14. The emission factors and per unit damage costs for So2, Nox, and PM for coal generation
plants in India from Cropper et al. (2012)16 are used to compute the avoided local environmental
damage costs of having the Solar Park (Table 2).
Table 2 – Emission Factor and Damage Costs
Units Nox PM10 SO2
Emission Factor,
coal
g/kwh 2.09 0.227 1.44
Damage costs,
coal
USc/kwh 0.21 0.06 0.63
Non Quantified Benefits
16 Cropper, M., S. Gamkhar, K. Malik, A Limonov, and I Partridge, The Health Effects of Coal Electricity
Generation in India, Resources for the Future, June 2012
50
15. The proposed Solar Park is also expected to have a number of additional benefits which
are either uncertain or difficult to quantify such as (i) energy security (ii) macroeconomic benefits
through the development solar manufacturing industries; (iii) employment generation; (iv)
learning and economy of scale benefits which can help facilitate further reductions in cost of PV.
These benefits have not been included in this economic analysis.
Economic analysis
Assumptions
16. In addition to the costs and benefits noted in the previous section, the economic analysis
rests on the following additional assumptions:
Discount rate for calculation of NPV: 12%, which is the rate used by past Bank financed
power sector projects in India and is consistent with Bank guidance on this topic17.
Project cost phasing: as follows:
2016 2017
Shared Infrastructure 40% 60%
Transmission 40% 60%
PV Generation 100%
First year of operation: 2018
Results
17. The economic analysis indicates that in India utility scale solar power is increasingly
competitive with thermal generation using imported coal. The baseline economic return of
Pavagada Solar Park against the “without solar park scenario” is 7% (NPV –US$ 386 million),
which is below the 12% hurdle rate used for Bank projects (see Table 3). However, the solar park
has substantial local and global environmental benefits and consideration of these benefits
increases the ERR of the solar park significantly. The inclusion of avoided damage costs of local
pollution in the economic flows, increases the ERR to 10% (NPV -US$163 million). The inclusion
of avoided global environmental damage costs (using the Bank guidance on social value of
carbon), increases the ERR to 18% (NPV $ 545 million).
Table 3 – Summary of Economic Analysis
Economic rate of return Unit Values
ERR % 7%
17 The World Bank is presently formulating new guidance note for the choice of discount rate. If the guidance is
available before project appraisal, the economic analysis will we revised accordingly.
51
ERR + local externalities % 10%
ERR + local externalities + GHG % 18%
Switching value, avoided GHG emission $ /ton $6
Composition of NPV
Cost of Solar Park
capital cost $USm 1265
O&M $USm 31
Benefits of avoided coal generation
Avoided coal costs $USm 824
Capacity credit $USm 86
NPV (before environmental benefits) $USm -386
local environmental benefits $USm 223
GHG emissions @$30/ton $USm 708
NPV (including environment) $USm 545
Lifetime GHG emissions undiscounted
Mtons
CO2
69
Marginal abatement cost MAC $/ton 5.6
18. Reduction in GHG emissions. The analysis indicates that the solar park will reduce GHG
emissions by 69 million tons over the life of project compared to the thermal counterfactual. The
marginal abatement cost of GHG emission for the Solar Park is $5.6/ton. The Solar Park will help
avoid local and environmental damage costs equal to $931 million compared with the thermal
counterfactual.
19. Sensitivity Analysis. The sensitivity analysis in Table 4 calculates the switching values
for the important variables such as capital costs, Capacity Utilization Factor, PV generation capital
costs, coal prices, capacity credit and discount rate.
Table 4 – Switching Values
Input Unit Baseline Value Switching Value
Project Cost $ Million 1296 910
CUF % 19% 27%
PV Cost $M/MW 1.06 0.70
Annual Increase Coal
Prices % 0% 5%
Discount Rate % 12% 7%
Capacity Credit % 19% 103%
Grid Integration Costs % 0 -2.70%
Project cost overrun
factor Ratio 1 0.7
52
20. Sensitivity analysis using the low case (increasing from $15 per ton in 2015 to $50 in 2050)
and high case (increasing from $50 per ton in 2015 to 150 in 2050) social values of carbon
recommended by Bank guidance impacts the returns of the project significantly. There is 8%
percent difference between the ERRs for low case and high case social value of carbon (Table 4).
This suggests that the climate change and local pollution impacts are an important deciding factor
in whether or not to go ahead with this project.
Table 4 – Sensitivity on Social Value of
Carbon
Social Value of
Carbon
EIRR NPV
Low Case 412 14%
Base Case 751 18%
High Case 1233 23%
53
ANNEX 6: CLEAN TECHNOLOGY FUND (CTF) ANNEX
India: Shared Infrastructure for Solar Parks &
Transmission for Power Evacuation from Solar Parks18
Key Indicators CTF/World Bank-funded
Project
Scaled-up Phase: Solar Park
Scheme of the Ministry of New and
Renewable Energy (MNRE) by
202019
Installed solar PV
generation capacity in
supported solar parks
(MW)
3,500 MW 22,050 MW
Tons of GHG emissions
reduced or avoided
- Tons per year
[mtCO2eq/yr]
- Tons over lifetime
[mtCO2eq / 25 years]20
4.8
120.2
30.3
757.5
Financing leveraged
through CTF financing
(US$ million)
US$ 4,420 million
- US$ 420 million by IBRD
US$ 150 million for shared
infrastructure
US$ 270 million for
transmission
- US$ 500 million by the
Government of India (GoI)
and state governments
US$ 200 million for shared
infrastructure
US$ 300 million for
transmission
- US$ 3,500 million by private
and public sector for
generation capacity in the solar
parks
US$ 28.2 billion
- US$ 420 million by IBRD
- US$ 5.8 billion by GoI and
state governments
- US$ 22 billion by private and
public sector for generation
capacity in the solar parks
CTF leverage ratio 1 : 55.3 1 : 352.8
18 This CTF Annex presents two World Bank-funded projects: i) Shared Infrastructure for Solar Parks; and ii)
Transmission for Power Evacuation from Solar Parks. The results indicated in this Annex will be achieved by
implementing two projects together. 19 The Scaled-up Phase assumes that the proposed CTF-funded Project contributes to the achievement of the ‘solar
park scheme’ launched by the Ministry of New and Renewable Energy (MNRE) to facilitate the development of
utility scale solar power in India. The scheme will install utility scale grid-connected solar parks by 2020, with a
targeted, collective installed capacity of 20GW. 20 The lifetime of solar PV generation facilities was hereby assumed at 25 years.
54
Cost effectiveness
- CTF cost effectiveness
[$CTF/tCO2eq avoided
over lifetime]
- Total project cost
effectiveness [$Total Project
/tCO2eq avoided over
lifetime]
0.67
37.42
0.11
37.36
Other co-benefits - Support in meeting the electricity demand and contribute to the
universal access agenda.
- Increased opportunities of local employment.
- Contribute to cost reduction in solar PV technologies.
- Environmental co-benefit: reduced local air pollution of 74.8 kt of
NOx, 51.5 kt of SOx and 8.1 kt of PM10 per annum after the Scaled-
up Phase.
- Gender co-benefit: interventions to be designed to address gender
issues in the proposed solar park sites.
I. Introduction
Background: country and sector context
1. India’s power system needs to grow rapidly to fuel the country’s economic growth and
provide electricity to its growing population. During the last decade, India’s economy expanded
at an average annual rate of 7.6 percent; projections are for high rates of growth to continue. The
demand for power is expected to rise to support the growing manufacturing sector and meet the
rising aspirations of its people. Yet power quality is still poor and falls far short of demand. Power
shortages in FY2015 were equivalent to about 3.6% of total energy and 4.7% of peak capacity
requirements. An estimated 300 million people are still not connected to the national electrical
grid, and those that are connected face frequent disruptions. Private investment in diesel generators
as a coping mechanism against frequent power cuts is widespread, and estimates of installed diesel
generation capacity are as high as 70 GW. Furthermore, local environmental pollution is a major
issue in India. According to the World Health Organization, 13 of the 20 most polluted cities in
the world are in India. Renewable energy is increasingly seen as an important contributor to
meeting this energy demand in an environmentally sustainable way and to India’s energy security.
2. The Government of India (GoI) announced its intention to increase its target for solar
installed capacity from 20 to 100GW by 202221. The total installed grid-connected solar capacity
base of the country has reached 3.7 GW as of June 2015, from less than only 2 MW in 2009. The
Government would like to significantly increase the pace of solar power deployment to meet its
ambitious targets. The Government foresees that 60GW of the targeted installations will come
from utility-scale ground mounted solar power plants.
21 Government of India, 2015 (http://pib.nic.in/newsite/PrintRelease.aspx?relid=122566)
55
3. The development of utility scale solar power on this scale in such a short time frame
presents significant challenges, including availability of land, permits and clearances, availability
of transmission and other infrastructure, capacity of sector institutions, and cost and variability of
solar power. To address these barriers, the GoI is developing large scale solar parks – concentrated
zones of development of solar power generation projects – which provide private sector developers
with dedicated land, evacuation infrastructure and other proper infrastructure. Two large solar
parks have been so far developed in Charanka (Gujarat) and Bhadla (Rajasthan).
4. The Ministry of New and Renewable Energy (MNRE) has launched ‘solar park scheme’
to facilitate the development of utility scale solar power in India. This scheme will use public
private partnership arrangements to set up 20 solar parks with a cumulative installed capacity of
about 60 GW of solar power by 2020. Within this total target of 60GW of ground-mounted solar
capacity in solar parks, about 20GW is expected to come from investments by Public Sector
Undertakings (PSUs) and 40GW from private investors. MNRE is providing Central Financial
Assistance (CFA) of up to 30% of the project costs or INR 2 million per MW for the solar parks.
This scheme internalizes the lessons of the Charanka and Bhadla solar parks in India as well utility
scale solar power developments in other parts of the World22. The scheme intends to attract
significant investments from project developers in the States to enable them to meet Renewable
Purchase Obligation (RPO) mandate and provide employment opportunities to local population to
the extent possible. It aims to reduce the number of approvals required by developers to set up
solar generation plants and hence attract private investments in such solar plants. The State will
also reduce its carbon footprint by avoiding emissions equivalent to the solar park’s installed
capacity and generation. Further, the State will also avoid procuring fossil fuels to run conventional
power plants. Under the scheme, a joint venture (JV) company comprising of the Solar Energy
Corporation of India (SECI), state utilities and in some cases the private sector is proposed to be
set up in each state to provide specialized services and to be the owner of the park and its shared
infrastructure, in order to incentivize solar power developers to invest in solar energy in the park.
India’s CTF Investment Plan
5. The CTF Investment Plan for India was originally endorsed in November 2011, and
subsequently revised in August 2015, with a total indicative allocation of USD 775.0 million of
CTF resources. The revised Investment plan aims to support GoI’s ambitious target of 100 GW of
solar installed capacity by 2022. The Plan includes the following proposed activities (Table 1).
Table 1 – Revised CTF Investment Plan of India, Indicative Financing Plan (US$ million)
CTF Project/Program MDB CTF financing
(US$ m)
22 The proposed project will draw on international experience with development of utility scale solar parks as well as
India’s experience with, and important lessons learned from other solar parks. In year 2009, Clinton Foundation
initiated work on large scale solar parks in South Africa, Australia, USA and India. It signed a MoU with Gujarat and
Rajasthan government in India to set up solar parks. Solar parks in Australia and USA did not move forward because
of the regulatory hurdles. Solar park in South Africa by ESKOM is under development. Gujarat (Charanka) solar park
has been commissioned and Rajasthan (Bhadla) solar park is under construction. Experience from the earlier solar
parks will be incorporated in the project during the preparation phase.
56
Himachal Pradesh Environmentally Sustainable Development
Policy Loan (HP DPL)
World Bank 100
Partial Risk Sharing Facility for Energy Efficiency (PRSF) World Bank 25
Solar Park: Rajasthan ADB 200
Solar Parks Infrastructure World Bank 50
ADB 50
Solar Parks Transmission World Bank 30
ADB 50
Solar Rooftop PV World Bank 125
ADB 125
Solar PV Generation by Solar Energy Corporation of India (SECI) World Bank 20
Total 775
Project Description
6. The objective of the proposed Project is: (i) to increase solar generation capacity through
the establishment of utility-scale solar parks in India; and (ii) to evacuate power from the selected
solar power generation parks to the Inter-state Transmission System. This will contribute to the
achievement of GoI’s target of installing 100GW solar power by 2022.
7. The World Bank has prepared two projects to support the development of solar parks in
India. Under Shared Infrastructure for Solar Parks project, the World Bank will support for setting
up solar parks in four states – Karnataka, Madhya Pradesh, Andhra Pradesh and Telangana,
keeping the option open for other states to join if they are able to meet the necessary conditions. It
will cover financing for shared infrastructure such as security, access roads, water supply and
drainage, telecommunications, and pooling stations (with 220/66/33 kV or as may be suitable
switchyard and respective transformers) inside the solar parks and transmission lines connecting
these internal pooling stations to 400/220 kV substation. The project will also provide technical
assistance for capacity building of state nodal agencies and JVs across the participating States (see
page 7 of the PAD for Shared Infrastructure for more details).
8. Under Transmission for Power Evacuation from Solar Parks project, the World Bank will
support Tumkur (Karnataka) solar park and Rewa (Madhya Pradesh) solar park that are in
advanced stages, along with other solar parks under the scheme in the states of Karnataka, Madhya
Pradesh and Telangana, which will be finalized upon obtaining approval from Central Electricity
Authority (CEA) and/or Standing Committee on Power System Planning. This project will finance
the establishment of 400/220 kV transmission substations at the park boundary and the linked
transmission lines up to the existing transmission network (see page 8 of the PAD for Transmission
for more details).
9. This proposed Project will mobilize US$ 1,000 million, including US$ 420 million from
IBRD, US$ 80 million from CTF and US$ 500 million from the GoI and state governments. The
solar parks supported by the Project are expected to mobilize additional US$ 3,500 million of
private and public sector financing for solar PV generation capacity. The CTF funding would
comprise US$ 78 million to be extended under softer concessional terms and US$ 2 million to be
extended in the form of a grant.
57
10. Among the aforementioned US$ 1,000 million, US$ 400 million in total, a sum of US$ 150
million from IBRD, US$ 50 million from CTF and US$ 200 million from public sector will support
Shared Infrastructure for Solar Parks, while the rest US$ 600 million will finance Transmission
for Power Evacuation from Solar Parks.
II. Assessment of the Proposed Project with CTF Investment Criteria
Potential for GHG Emission Savings
11. Emission reduction potential of investment. The total emission reduction potential was
estimated at 120.2 million tonnes of CO2 equivalent over the lifetime of solar PV power generation
facilities within the supported solar parks, hereby assumed 25 years. These estimates were based
on the installation of 3,500 MW of solar PV power generation capacity with 18.9 percent capacity
factor, displacing an equivalent of 5,795 GWh per year of “thermal-based” power in the baseline
scenario. The baseline scenario assumes “thermal-based power generation” using imported coal.
The emission factors under the baseline scenario was estimated at 830 kg/MWh23, which is more
conservative than the grid emission factor for India24. Using this emission factor, the CO2 savings
were estimated at 4.8 million tonnes of CO2 equivalent per year. Savings have been calculated in
accordance with CTF and World Bank guidelines25.
12. Technology development status. The utility-scale solar PV generation is already
technically proven and commercially viable. Over the past ten years, solar power has grown rapidly
driven by government policy and rapidly declining costs, propelling the solar industry into the
mainstream of energy policy. From 2009, the Jawaharlal Nehru National Solar Mission and state
policies, especially in Gujarat, Karnataka, Rajasthan, and Tamil Nadu helped bring down the cost
of generation. With the most recent bid of Rs 5.05/kWh for a utility-scale solar PV project in
Madhya Pradesh, solar costs have fallen over 70% from 2010 levels. Since India lies in the high
solar insolation region, declining cost trends in solar PV, along with innovations in energy storage
technology, offer exciting opportunities for India to address its challenges in the energy sector.
13. The key technical issue for the Project is the availability of a sound internal and external
evacuation system for solar parks. Based on Long Term Access (LTA) application from Tumkur
(Karnataka) solar park and Rewa (Madhya Pradesh) solar park, Power Grid Corporation India
Limited (POWERGRID) has carried out detailed grid evacuation and grid impact studies and
established augmentation/additions needed to the existing network so that the generation can be
absorbed without any adverse effect. These studies cover load flow analysis, reactive power flow
patterns, and measures and corrective actions to be implemented by the partners in the Grid. The
studies also assess the health of the consolidated system in case of outage of any network element
of the grid including solar park generation. The findings of these studies are presented in the
Standing Committee chaired by CEA, for deliberations and clearance.
23 830 kg/MWh for coal generation from supercritical plants 24 980 kg/MWh, from CO2 Baseline Database for the Indian Power Sector, Central Electricity Authority 25 World Bank, Guidance Manual: Greenhouse Gas Accounting for Energy Investment Operations, 2015
58
Cost-effectiveness
14. The cost effectiveness is 0.67 US$/tCO2eq for CTF funding and 37.42 US$/tCO2eq
considering total funding for the Project. In the Scaled-up Phase, the cost effectiveness will
improve to 0.11 US$/tCO2eq for CTF funding and 37.36 US$/tCO2eq when considering total
funding.
15. Marginal abatement cost. In October 2013, the CTF Trust Fund Committee suggested
providing information on the estimated marginal abatement cost (MAC) for projects for which the
marginal abatement cost is likely to exceed US$100 per ton of CO2eq. This decision draws from
the CTF criteria which specifies that CTF co-financing will not be available for investments in
which the marginal cost of reducing a ton of CO2eq exceeds US$200, which reflects the lower-
end estimate of the incentive needed to achieve the objectives of the BLUE Map Scenario as
indicated in the International Energy Agency’s Energy Technology Perspectives 2008 Report.
16. The MAC of the proposed Project based on the economic analysis of the 2GW Pavagada
Solar Park is 5.6 US$/tCO2eq. These calculations confirm that the MAC will not exceed the
aforementioned US$100 threshold value per ton of CO2eq. The Project will help avoid local and
environmental damage costs equal to US$ 931 million compared to the thermal counterfactual (see
page 13 of either PAD for more details).
17. The marginal abatement cost is computed as the project’s NPV divided by lifetime CO2eq
(LCO2) avoided emissions:
2LCO
NPVMAC ,
where NPV stands for Net Present Value and LCO2 stands for Lifetime CO2eq emissions.
Demonstration Potential at Scale
18. Scope of avoided GHG emissions through replication. India’s ambitious target calls for the
installation of 60 GW of utility-scale ground mounted solar power plants by 2022. MNRE’s solar
park scheme aims at the development of utility scale grid-connected solar parks through public
private partnership arrangement with a cumulative installed capacity of about 20 GW of solar
power by 2020. The proposed Project will directly contribute towards these targets, therefore
contributing to significant emission reduction. It is expected that CTF and IBRD support on the
selected solar parks will create market confidence and will catalyze further support from other
investor groups for the GoI to help with achievement of its targets. The expected emission
reduction from achieving the Scaled-up Phase is estimated at 30.3 million tonnes of CO2
equivalent per year, or 757.5 million tonnes over the 25-year lifetime of technologies.
19. Transformation potential. The proposed Project has high transformational potential as it
will contribute to the accelerated development of utility-scale solar PV generation and the rapid
increase in the share of renewable energy in the power sector of India. Developing solar parks will
provide the enabling infrastructure for utility scale development of solar power, including common
59
infrastructure such as large areas of land, power pooling sub-stations as well intra-park
transmission infrastructure, access roads, common security arrangements. This will facilitate
investment in solar power development by private or public sector developers, who may be able
to shorten the time from contract award to commissioning from 20 months to less than 10 months.
MNRE’s solar park scheme also aims to reduce the number of approvals required by developers
to set up solar generation plants and hence attract private investments in such solar plants. In fact,
there has been strong response to solar parks in Rajasthan and Andhra Pradesh that have recently
invited bids from the private sector. This trend is expected to continue for the solar parks that are
being developed inside the park, which will help solar parks make transformational impacts on the
power sector.
Development Impact
20. Support to bridge the supply gap of energy and contribute to the universal access
agenda. Power shortages in FY2015 were equivalent to about 3.6% of total energy and 4.7% of
peak capacity requirements. An estimated 300 million people are still not connected to the national
electrical grid, and those that are connected face frequent disruptions. Meeting the growing energy
demand of a rapidly growing economy while reducing air pollutants and carbon emissions through
solar energy is a top priority for GoI, particularly given the high costs of unserved electricity
demand in the country and growing energy imports. The development of solar energy will have
significant benefits in terms of the reliability and security of electricity supply to consumers. The
Project is also likely to have a significant indirect contribution to expansion of access to electricity,
as a result of the increased availability of electricity in all project states, wherein the investments
supported under the project are expected to lead to increased hours of supply to existing customers,
and increased availability of electricity supply, which may enable utilities to connect and serve
new customers.
21. Increased opportunities of local employment. The development of large scale solar parks
will attract significant investments from project developers which will generate employment
opportunities to local population. Local contractors, engaged through international competitive
bidding, will carry out the supply, installation and erection works. Joint ventures created under the
scheme will develop the capacity required to operate and maintain the assets created through this
Project, which would provide long-term employment opportunities.
22. Environmental Co-benefits. Currently, India relies on coal as the fuel source for two
thirds of its electricity requirements and is the world’s third largest carbon emitter. Private
investment in diesel-based back-up power supplies is widespread. The energy sector also causes
local environmental problems. The Project has substantial local environmental benefits. At local
level, air pollutant emissions under the thermal counterfactual are estimated at 74.8 kt of NOx, 51.5
kt of SOx and 8.1 kt of PM10 per annum, which will be reduced by displacing imported coal in
power generation with increased supply of electricity from the solar parks developed under the
Scaled-up Phase. The local and global environmental benefits of the 2GW Pavagada Solar Park
are estimated at US$ 931 million (see page 13 of either PAD for more details).
23. Gender Co-benefit. The Project is expected to bring positive gender co-benefits by
incorporating gender impacts of this intervention. Most of the women’s status indicators (including
60
those pertaining to health, literacy, work force participation,) show that gender equity and
empowerment remain serious issues in the proposed solar park sites. As part of the Social
Management Framework (SMF), a Gender Development Framework and a Gender Action Plan
will be designed which will help to analyze gender issues and to design interventions to address
women’s needs. Gender analysis will be part of the social impact assessment.
Implementation Potential
24. The Project is aligned with GoI’s National Action Plan for Climate Change (NAPCC),
which was issued in 2008 to enhance India’s ecological sustainability and encourage sustainable
energy sources. It is also consistent with the Jawaharlal Nehru National Solar Mission (JNNSM)
that was launched in 2010 as part of NAPCC to promote the development of solar power in India.
GoI has significantly scaled up the target of 20 GW of solar power in JNNSM to 100 GW by 2022.
GoI has reiterated these commitments as part of its Intended Nationally Determined Contributions
(INDCs) commitment to achieve about 40 percent cumulative electric power installed capacity
from non-fossil fuel based energy resources by 2030.
25. There is strong ownership of the Project at the highest levels of GoI, MNRE, the
participating states, discoms and the JVs responsible for implementing this Project. This
commitment has been demonstrated through their intensive engagement and involvement during
the project preparation. As mentioned in the preceding sections, GoI and state governments are
pushing through with a number of policy and regulatory reforms, implementation mechanisms and
incentives to ensure that there costs of solar power are kept low and there is sufficient demand for
the offtake of solar power generated under the project. There has been strong responses from the
private sector to the bids to the solar parks that have been recently developed in Rajasthan and
Andhra Pradesh, which proves that solar park modality will continue to work. It will help ensure
the financial sustainability of the park.
26. POWERGRID’s involvement is a reasonable assurance that project design and
implementation will be of high standards. It has become a strong entity that is capable to ensure
that the investments are made well in time and are not left stranded. Over the past decade,
POWERGRID has acquired and developed skills required for successfully planning and
implementing large scale capital investment programs, through their its mandate to develop the
inter-state transmission network of India and also by acting as Consultant to some states to assist
them to plan, design and implement their transmission and distribution networks. All the schemes
envisaged under this operation are being designed, procured and implemented by POWERGRID.
Since POWERGRID owns, operates and maintains the National Grid, it in association with
POSOCO, takes all due measures required to ensure grid stability. In addition, environmental and
social issues will be handled with adequate expertise and attention, building on POWERGRID’s
implementation track record of earlier World Bank funded projects.
27. Leverage: The total investment of the Project would be funded through the CTF (US$ 80
million), IBRD (US$ 420 million), Central and State governments (US$ 500 million) and public
and private sector participation to solar PV generation facilities in the solar parks (US$ 3,500
million). The CTF leverage ratio will be 1 to 55.3. The CTF leverage ratio will increase to 352.8
when considering the Scaled-up Phase by 2020. The leverage effect is expected very high, as this
61
proposed Project will effectively mobilize large amounts of investment in generation capacity by
utilizing public sector financing for the development of the required infrastructure which is a
relatively small portion of total investment but will reduce the risk of investment in generation
capacity.
CTF Additionality
28. The use of CTF concessional financing under the Project is essential to develop solar parks
that will enable large-scale deployment of solar PV generation in a short time frame. Solar parks
can effectively address a number of challenges in accelerating the scale-up of solar PV generation
capacity, which was committed by the GoI, but it requires public sector investment in transmission
and other shared infrastructures within the parks. Given the specific transmission requirements of
solar power and the risk of stranded assets, private sector investors continue to see the availability
of state of the art transmission infrastructure to connect their solar generation project to load
centers across the country, as a precondition to major investment decisions. By using concessional
financing for the investment, the GoI will be able to establish the required infrastructure with a
reduced cost of capital, which will be translated into a lower cost to private sector developers who
will invest in generation capacity within the solar parks.
29. The economic rate of return of the solar park is calculated at 7%, which is lower than the
hurdle rate of 12% (see page 12 of either PAD). This estimate is based on the baseline scenario
before taking into account environmental externalities and can be affected by a range of risk
factors. The use of CTF concessional financing to enable the establishment of transmission system
and shared infrastructure in the solar parks is hence essential for fully capturing the local and global
environmental benefits associated with this Project, which will raise the economic rate of return to
18% and make this Project economically viable.
Implementation Readiness
30. Among the long listed solar parks in Table 2, the two solar parks, Tumkur (Karnataka) and
Rewa (Madhya Pradesh), are in the most advanced stage, followed by Neemuch and Agar (Madhya
Pradesh). Based on Long Term Access (LTA) applications from two JVs of the first two solar
parks, POWERGRID had already carried out a detailed evacuation studies. Since all the solar parks
have not been finalized, investments under this Project will be taken up in a phased manner. The
Government of India is keen to move this proposed Project forward to help achieve its ambitious
target on solar generation capacity.
Table 2 –Planned Long List of Potential Solar Parks under MNRE Scheme
No State Location & capacity
1 Gujarat Banaskantha (700 MW)
2 Madhya Pradesh Rewa (750 MW)
Neemuch (435 MW)
Agar (315 MW)
3 Telangana Gattu, Mehboob Nagar (1000 MW)
4 Andhra Pradesh Anantpur (1500 MW)
Kurnool (1000 MW)
62
5 Karnataka Tumkur (2000 MW)
6 Uttar Pradesh Jalaun (370 MW)
Sonbhadra, Allahabad & Mirzapur (230 MW)
7 Meghalaya West & Esat Jayantia Hills (50 MW)
8 Jammu and Kashmir Leh & Kargil (7500 MW)
9 Punjab Patiala, Fatehgarh Sahib, Ludhiana & Gurdaspur (1000 MW)
10 Rajasthan Bhadla (1700 MW)
Jaisalmer (2000 MW)
11 Tamil Nadu Ramanathapuram (500 W)
12 Odisha Location not stated (1000 MW)
Total 22,050 MW