+ All Categories
Home > Documents > The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for...

The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for...

Date post: 28-May-2020
Category:
Upload: others
View: 5 times
Download: 0 times
Share this document with a friend
72
The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL DOCUMENT (QER STAGE) ON A PROPOSED IBRD LOAN IN THE AMOUNT OF US$ 270 MILLION AND A PROPOSED CLEAN TECHNOLOGY FUND (CTF) LOAN IN THE AMOUNT OF US$ 30 MILLION TO THE POWERGRID CORPORATION OF INDIA LIMITED FOR TRANSMISSION FOR POWER EVACUATION FROM SOLAR PARKS PROJECT (P156974) DECEMBER 16, 2015 Vice President: Annette Dixon, SARVP Country Director: Onno Ruhl, Practice Manager: Senior Global Practice Director: Julia Bucknall, GEEDR Anita Marangoly George, GEEDR Task Team Leader: Mohua Mukherjee, GEEDR This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization.
Transcript
Page 1: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

The World Bank

FOR OFFICIAL USE ONLY

PROJECT APPRAISAL DOCUMENT (QER STAGE)

ON A

PROPOSED IBRD LOAN

IN THE AMOUNT OF US$ 270 MILLION

AND A

PROPOSED CLEAN TECHNOLOGY FUND (CTF) LOAN

IN THE AMOUNT OF US$ 30 MILLION

TO THE

POWERGRID CORPORATION OF INDIA LIMITED

FOR

TRANSMISSION FOR POWER EVACUATION FROM SOLAR PARKS PROJECT

(P156974)

DECEMBER 16, 2015

Vice President: Annette Dixon, SARVP

Country Director: Onno Ruhl,

Practice Manager:

Senior Global Practice Director:

Julia Bucknall, GEEDR

Anita Marangoly George, GEEDR

Task Team Leader: Mohua Mukherjee, GEEDR

This document has a restricted distribution and may be used by recipients only in the performance of

their official duties. Its contents may not otherwise be disclosed without World Bank authorization.

Page 2: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

i

ABBREVIATIONS AND ACRONYMS

ADB Asian Development Bank

AIS Activity Initiation Summary

AT&C Aggregate Technical and Commercial

BOO Build Own Operate

BOOT Build Own Operate Transfer

CEA Central Electricity Authority

CFA Central Financial Assistance

CPS Country Partnership Strategy

CTF Clean Technology Funds

DFID Department for International Development

DLI Disbursement Linked Indicator

Discoms Electricity distribution companies

ESSA Environmental and Social Systems Assessment

FITs Feed in Tariffs

FIL Financial Intermediary Loan

FM Financial Management

GEF Global Environment Facility

GHG Green House Gas

GoI Government of India

GRPV Grid connected rooftop solar PV

GW Gigawatts

GRSPP Grid-connected Rooftop and Small Power Plant

IBRD International Bank for Reconstruction & Development

IPF Investment Project Financing

IPP Independent Power Producer

IREDA Indian Renewable Energy Development Agency

JNNSM Jawaharlal Nehru National Solar Mission

Kwh Kilowatt-Hour

MNRE Ministry of New & Renewable Energy

MOP Ministry of Power

MW Megawatts

NDMC New Delhi Municipal Corporation

NAPCC National Action Plan on Climate Change

OM Operational Manual

O&M Operate and Maintain

PAP Program Action Plan

PDO Program Development Objective

PforR Program for Results

PIU Program Implementation Unit

PPA Power Purchase Agreement

PV Photovoltaics

SBI State Bank of India

SECI Solar Energy Corporation of India

SERC State Electricity Regulatory Commissions

Page 3: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

ii

SNA State Nodal Agencies

TA Technical Assistance

UNDP United Nations Development Programme

UNIDO United Nations Industrial Development Organization

WBG World Bank Group

Page 4: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

iii

INDIA

TRANSMISSION FOR POWER EVACUATION FROM SOLAR PARKS (P156974)

TABLE OF CONTENTS

Page

I. STRATEGIC CONTEXT .................................................................................................1

A. Country Context ............................................................................................................ 1

B. Sectoral and Institutional Context ................................................................................. 1

C. Higher Level Objectives to which the Project Contributes .......................................... 5

II. PROJECT DEVELOPMENT OBJECTIVES ................................................................6

A. PDO............................................................................................................................... 6

B. Project Beneficiaries ..................................................................................................... 6

C. PDO Level Results Indicators ....................................................................................... 6

III. PROJECT DESCRIPTION ..............................................................................................7

A. Project Components ...................................................................................................... 8

B. Project Financing .......................................................................................................... 8

C. Lessons Learned and Reflected in the Project Design .................................................. 9

IV. IMPLEMENTATION .......................................................................................................9

A. Institutional and Implementation Arrangements .......................................................... 9

B. Results Monitoring and Evaluation ............................................................................ 10

C. Sustainability............................................................................................................... 10

V. KEY RISKS AND MITIGATION MEASURES ..........................................................11

A. Overall Risk Rating Explanation ................................................................................ 11

VI. APPRAISAL SUMMARY ..............................................................................................12

A. Economic and Financial Analysis ............................................................................... 12

B. Technical ..................................................................................................................... 14

C. Financial Management ................................................................................................ 14

D. Procurement ................................................................................................................ 15

E. Environment & Social (including Safeguards) ........................................................... 15

F. World Bank Grievance Redress .................................................................................. 16

Annex 1: Results Framework and Monitoring .........................................................................18

Page 5: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

iv

Annex 2: Detailed Project Description .......................................................................................21

Annex 3: Implementation Arrangements ..................................................................................31

Annex 4: Implementation Support Plan ....................................................................................43

Annex 5: Economic Analysis .......................................................................................................46

Annex 6: Clean Technology Fund (CTF) Annex ......................................................................53

.

Page 6: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

v

PAD DATA SHEET

India

Transmission for Power Evacuation from Solar Parks (P156974)

PROJECT APPRAISAL DOCUMENT .

SOUTH ASIA

0000009260

Report No.: PAD1660 .

Basic Information

Project ID EA Category Team Leader(s)

P156974 B - Partial Assessment Mohua Mukherjee

Lending Instrument Fragile and/or Capacity Constraints [ ]

Investment Project Financing Financial Intermediaries [ ]

Series of Projects [ ]

Project Implementation Start Date Project Implementation End Date

01-Mar-2016 31-Dec-2020

Expected Effectiveness Date Expected Closing Date

31-Dec-2020

Joint IFC

No

Practice

Manager/Manager

Senior Global Practice

Director Country Director Regional Vice President

Julia Bucknall Anita Marangoly George Onno Ruhl Annette Dixon .

Borrower: Department of Economic Affairs

Responsible Agency: Power Grid Corporation of India Limited

Contact: B Mishra Title: Executive Director

Telephone No.: 0124-2571700 Email: [email protected] .

Project Financing Data(in USD Million)

[ X ] Loan [ ] IDA Grant [ ] Guarantee

[ ] Credit [ ] Grant [ ] Other

Total Project Cost: 600.00 Total Bank Financing: 270.00

CTF 30.00

Financing Gap: 0.00 .

Page 7: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

vi

Financing Source Amount

Borrower 300.00

International Bank for Reconstruction and

Development

270.00

Clean Technology Fund 30.00

Total 600.00 .

Expected Disbursements (in USD Million)

Fiscal

Year

2016 2017 2018 2019 2020 2021 0000 0000 0000 0000

Annual 30.00 90.00 180.00 180.00 120.00 0.00 0.00 0.00 0.00 0.00

Cumulati

ve

30.00 120.00 300.00 480.00 600.00 600.00 0.00 0.00 0.00 0.00

.

Institutional Data

Practice Area (Lead)

Energy & Extractives

Contributing Practice Areas

Cross Cutting Topics

[ X ] Climate Change

[ ] Fragile, Conflict & Violence

[ ] Gender

[ ] Jobs

[ X ] Public Private Partnership

Sectors / Climate Change

Sector (Maximum 5 and total % must equal 100)

Major Sector Sector % Adaptation

Co-benefits %

Mitigation

Co-benefits %

Energy and mining Other Renewable Energy 20 100

Energy and mining Transmission and

Distribution of

Electricity

80 100

Total 100

I certify that there is no Adaptation and Mitigation Climate Change Co-benefits information

applicable to this project. .

Themes

Theme (Maximum 5 and total % must equal 100)

Page 8: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

vii

Major theme Theme %

Financial and private sector development Infrastructure services for private sector

development

70

Public sector governance Other public sector governance 30

Total 100 .

Proposed Development Objective(s)

The project development objective is “to evacuate power from the selected solar generation parks to the

Inter-State Transmission System”. .

Components

Component Name Cost (USD Millions)

0.00 .

Systematic Operations Risk- Rating Tool (SORT)

Risk Category Rating

1. Political and Governance Low

2. Macroeconomic Low

3. Sector Strategies and Policies Moderate

4. Technical Design of Project or Program Low

5. Institutional Capacity for Implementation and Sustainability Low

6. Fiduciary Low

7. Environment and Social Moderate

8. Stakeholders Moderate

9. Other

OVERALL Moderate .

Compliance

Policy

Does the project depart from the CAS in content or in other significant

respects?

Yes [ ] No [ X ]

.

Does the project require any waivers of Bank policies? Yes [ ] No [ X ]

Have these been approved by Bank management? Yes [ ] No [ ]

Is approval for any policy waiver sought from the Board? Yes [ ] No [ X ]

Does the project meet the Regional criteria for readiness for implementation? Yes [ X ] No [ ] .

Safeguard Policies Triggered by the Project Yes No

Environmental Assessment OP/BP 4.01 Yes

Page 9: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

viii

Natural Habitats OP/BP 4.04 Yes

Forests OP/BP 4.36 Yes

Pest Management OP 4.09 No

Physical Cultural Resources OP/BP 4.11 Yes

Indigenous Peoples OP/BP 4.10 Yes

Involuntary Resettlement OP/BP 4.12 Yes

Safety of Dams OP/BP 4.37 No

Projects on International Waterways OP/BP 7.50 No

Projects in Disputed Areas OP/BP 7.60 No .

Legal Covenants

Name Recurrent Due Date Frequency

Description of Covenant

.

Conditions

Source Of Fund Name Type

Description of Condition

Team Composition

Bank Staff

Name Role Title Specialization Unit

Mohua Mukherjee Team Leader

(ADM

Responsible)

Senior Energy

Specialist GEEDR

Arun Kumar Kolsur Procurement

Specialist

Senior Procurement

Specialist GGODR

Savinay Grover Financial

Management

Specialist

Sr Financial

Management

Specialist

GGODR

Amit Jain Team Member Energy Specialist GEEDR

Bipulendu Narayan

Singh

Team Member Energy Economist GEEES

Joonkyung Seong Team Member CTF Specialist GEEDR

Page 10: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

ix

Gaurav D. Joshi Safeguards

Specialist

Senior

Environmental

Specialist

GENDR

Gevorg Sargsyan Team Member Program Manager GEEDR

Kumudni Choudhary Team Member Program Assistant SACIN

Mani Khurana Team Member Energy Specialist GEEDR

Pyush Dogra Team Member Senior

Environmental

Specialist

GENDR

Surbhi Goyal Team Member Energy Specialist co-TTL GEEDR

Suryanarayan Satish Safeguards

Specialist

Senior Social

Development

Specialist

social GSURR

Extended Team

Name Title Office Phone Location

Dinkar Sohony Consultant-Technical Hyderabad .

Locations

Country First

Administrative

Division

Location Planned Actual Comments

India Karnataka Tumkur X .

Consultants (Will be disclosed in the Monthly Operational Summary)

Consultants Required ? No consultants are required

.

Page 11: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

1

I. STRATEGIC CONTEXT

A. Country Context

1. India’s power system needs to grow rapidly to fuel its economic growth and provide

electricity to its growing population. During the last decade, India’s economy expanded at an

average annual rate of 7.6 percent, placing it among the top 10 of the world’s fastest growing

nations; projections are for such high rates of growth to continue. The demand for power is

expected to rise to support the growing manufacturing sector and meet the rising aspirations of its

people. With about 275GW of installed capacity (as of November 2015), the Indian power system

is among the largest in the world, but per-capita consumption of electricity is less than one-fourth

of the world average. An estimated 300 million people are not connected to the national electrical

grid, and those who are, face frequent disruptions. Power shortages in FY2015 were equivalent to

about 3.6% of total energy and 4.7% of peak capacity requirements. To meet the power demand,

industrial establishments and manufacturers have been relying on diesel-based back-up power

supplies, which are significantly more expensive than grid-based electricity. The cost of un-served

energy is high, placing an inordinate burden on households and industries. Lack of regular supply

of electricity is also leading to diversion of resources into coping costs that could otherwise be

used to support growth.

2. The Government of India (GoI) wants a growing share of the country’s electricity to

come from renewable energy. GoI has set an ambitious goal of providing uninterrupted power

for all homes, industrial and commercial establishments and adequate power for farms by 2022.

Currently, India relies largely on coal, both domestic and imported, for about 60 percent of its

electricity generation requirements. India is the world’s third largest emitter of carbon emissions

behind China and USA, although per capita emissions are far lower. According to a recent World

Health Organization report, 13 of the 20 most polluted cities in the world are in India. GoI

recognizes that it must supplement non-renewable sources with cleaner and abundant renewable

sources and has accordingly announced plans to quadruple India’s renewable energy capacity from

35.8 GW (as in November 2015) to 175 gigawatts by 2022 , which is expected to require more

than $150 billion in investments. To achieve these targets, GoI is using innovative public private

partnership models and has doubled the clean energy cess levied on coal.

B. Sectoral and Institutional Context

3. Solar PV has emerged as a promising long-term option to meet the growing energy

demand in India while addressing the adverse environmental impacts of conventional fuels. Since India lies in the high solar insolation region, it is endowed with huge solar energy potential

with most of the country having about 300 days of sunshine per year with annual mean daily global

solar radiation in the range of 3.5-6.5 kWh/m2/day. Solar power can help India meet its growing

electricity demand as well as foster energy security by reducing dependence on imported fossil

fuel such as coal and diesel. The confluence of declining cost trends in solar photovoltaic (PV)

power generation (mainly through dramatic declines in solar panel prices) and innovations in

energy storage technology that are putting downward pressure on battery prices, offer exciting

opportunities for India. In rural areas, solar PV can offer significant health benefits by displacing

Page 12: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

2

the use of kerosene for lighting. Energy efficient irrigation pumps running on solar panels can

provide reliable cost effective irrigation for agricultural consumers.

4. GoI has announced a bold target of installing 100GW of solar power out of the total

renewable target of 175GW by 2022 – for solar power this represents about a thirty fold

increase from 3.7 GW installed in 2015. The total installed grid-connected solar capacity base

of the country has reached 3.7 GW (or 3,700 MW) as of June 2015, from less than only 2 MW in

2009. The Government would like to significantly increase the pace of solar power deployment to

meet its ambitious targets. The Government foresees that 60GW of the targeted installations will

come from utility-scale ground mounted solar power plants.

5. The development of utility scale solar power on this scale in such a short time frame

presents significant challenges. In particular, the following barriers to development of utility

scale solar power have been identified in India:

Availability of land. The availability of large tracts of suitable land at short notice

continues to be a key barrier to the development of solar power in India. Private sector

developers (including foreign investors), in particular, continue to run into a myriad of

legal and social issues with land acquisition, which serves to reduce the interest of

investors in the solar power sector.

Permits and Clearances. Private developers have to reach out to multiple departments and

ministries to obtain permits and clearances for land, transmission evacuation,

environment, which can cause delays and increase costs.

Availability of transmission and other infrastructure. Given the specific transmission

requirements of solar power and risk of stranded assets, private sector investors continue

to see the availability of state of art transmission infrastructure to connect solar generation

to load centers across the country as a precondition to major investment decisions.

Capacity of sector institutions. The institutions tasked with overseeing the development

of the solar power such as SECI State Nodal Agencies (SNAs) for renewable energy, state

transmission utilities, regulators are either very new or lack familiarity with specific

requirements of the sector. They hence lack the capacity to deliver on their mandate in

solar energy.

Cost of solar power. While there have been dramatic reductions in the cost of solar power

in recent years, solar generation is still more expensive than thermal generation in

financial terms. This means that there continues to be need for public support for solar

power both in terms of regulatory support as well as the development of enabling

infrastructure, to enable large amounts of solar power to be taken up in the grid. Focus has

been on utility scale ground mounted solar, little emphasis has been on tracking

technologies, storage or other high efficiency measures.

Page 13: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

3

Variability of solar power. Cloudy conditions can cause the amount of generation from

solar plants to vary significantly, requiring grid operators to maintain alternative

generation capacities.

6. GoI is taking action on multiple fronts to address these challenges. The following are

the main initiatives undertaken by GoI to facilitate development of large amounts of solar power:

Cost of solar power. State Governments and the Central Government are using a number

of mechanisms to lower the cost of solar power for off takers, including (i) reverse auctions

for Viability Gap Funding; (ii) bundling of private sector generated solar power with

cheaper public sector coal power. This has facilitated the discovery of increasingly

competitive solar power prices in India1 together with a large investor turnout.

Development of solar parks. Large solar parks have been developed in Charanka (Gujarat)

and Bhadla (Rajasthan) with dedicated land and evacuation infrastructure for private sector

developers.

Regulation. Amendments currently being tabled in Parliament are seeking to increase

Renewable Purchase Obligation (RPO) targets from 3% to 8% by 2019, introduce

Renewable Generation Obligation (RGO) targets, and impose penalties on RPO and RGO

non-compliance. In addition, amendments have also been proposed for the National Tariff

Policy 2005, to socialize interstate transmission of renewable power, procurement of

bundled solar power by DISCOMs from conventional power generators on a cost plus

basis, and easy pass-through of RPO compliance cost.

Grid Integration of Renewable Energy. Grid integration issues are being addressed by the

India Smart Grid Task Force (ISGTF), an inter-ministerial task force and the India Smart

Grid Forum (ISGF), a public-private partnership initiative. The national transmission

utility, Power Grid Corporation India Limited (POWERGRID) is taking the lead in

implementing the Green Energy Corridor Project to facilitate evacuation of renewable

energy across the country.

7. The Ministry of New and Renewable Energy (MNRE) has launched a ‘solar park scheme’

to facilitate the development of utility scale solar power in India. This scheme will use public

private partnership arrangements to set up 20 solar parks with a cumulative installed capacity of

about 60 GW of solar power by 2020. This scheme internalizes the lessons of the Charanka and

Bhadla solar parks in India as well utility scale solar power developments in other parts of the

World2. Under the scheme, a joint venture (JV) company comprising of the SECI, state utilities

1 Contracted tariffs have fallen from INR 17/kWh (or about 28 cents/unit) in 2010 to about INR 4.7/kWh (or about 8.4 cents/unit)

in 2015, a decline of more than 70 percent in five years. 2 The proposed project will draw on international experience with development of utility scale solar parks as well as India’s

experience with, and important lessons learned from other solar parks. In year 2009, Clinton Foundation initiated work on large

scale solar parks in South Africa, Australia, USA and India. It signed a MoU with Gujarat and Rajasthan government in India to

set up solar parks. Solar parks in Australia and USA did not move forward because of the regulatory hurdles. Solar park in South

Africa by ESKOM is under development. Gujarat (Charanka) solar park has been commissioned and Rajasthan (Bhadla) solar park

is under construction. Experience from the earlier solar parks was incorporated in the project during the preparation phase.

Page 14: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

4

and in some cases the private sector is proposed to be set up in each state to provide specialized

services and to be the owner of the park and its shared infrastructure, in order to incentivize solar

power developers to invest in solar energy in the park (see Box 1 for more details on the scheme).

8. This proposed project is one in a series of three engagements requested by the GoI from

the World Bank for US$1 billion of funding in the solar power sector3 4. All three projects are

expected to support achievement of the government’s new solar targets, and to demonstrate

important economies of scale in utility scale solar generation, push down equipment and

transaction costs, and also increase efficiency while reducing unit costs of solar power. It is

expected that the Bank-supported projects will create market confidence and will catalyze further

support from other investor groups for the GoI to help with achievement of its ambitious target of

installing 100GW of solar power capacity by 2022.

9. In particular, the proposed operation will support MNRE’s announced “solar park scheme”

by setting up transmission infrastructure to evacuate power from selected solar parks in Karnataka,

M.P and possibly also Telangana. This project will be implemented by Powergrid. IBRD funding

is being made available to provide transmission interconnections to the Inter State Transmission

System (ISTS) at the border of the respective solar park. The ISTS provides direct access to the

3 During their July 2014 and January 2015 meetings, Prime Minister Narendra Modi and President Jim Kim had agreed that the

Bank would provide financing for Solar Parks in the country 4 In particular, GoI requests have been received for all other Bank engagements to (i) support the establishment of grid connected

rooftop PV; (ii) fund the construction of associated evacuation infrastructure from Bank-supported solar parks; and (iii) shared

infrastructure for solar parks.

Box 1 - Ministry of New and Renewable Energy’s Solar Park Scheme

The development of solar parks will streamline development of solar power generation projects

with government agencies undertaking land acquisition or arranging for lease of a large parcel of

land from private owners. The public sector (in this case the JV company) will be responsible for

obtaining necessary permits, as well as providing common infrastructure such as site preparation

and leveling, construction power, power evacuation and water infrastructure, access roads,

security, and related services necessary to set up such power generation projects or plants.

The JV company will allocate space inside the park amongst solar power developers. The

allotment price per meter square payable by developers for the plots inside the solar park will be

specified by the implementing agency of the solar park, which is the JV company. Developers

will be able to get into long term Power Purchase Agreements (PPAs) with buyers (mostly

discoms or aggregators) inside and outside the state or they may develop solar power for captive

consumption by selected industrial customers.

POWERGRID or the State Transmission Utility (STU) will set up a sub-station outside the solar

park to feed power from one or more pooling stations into the National Grid or State Grid,

respectively. In cases where electricity utilities in the state are not willing to buy entire power

generated from such solar parks , POWERGRID is expected to be given the responsibility of

setting up 400/220 kV or bigger sub-station right next to the solar park and ensuring its

connectivity to the Inter State Transmission System (ISTS). The development of interconnection

will be coordinated and prioritized to ensure the availability of the evacuation infrastructure to

private sector developers well in advance of their plant commissioning date.

Page 15: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

5

entire national power market, and will therefore allow solar developers from these parks to more

easily sign PPAs with customers and off-takers anywhere in the country5. The supporting project

for solar park shared infrastructure ( which is also currently under preparation) will use IBRD

funding to develop the enabling infrastructure for utility scale development of solar power,

including common infrastructure such as large areas of land, power pooling sub-stations as well

as intra-park transmission infrastructure, access roads, lighting, communications and common

security arrangements. This will facilitate investment in solar power development by private or

public sector developers, who may be able to shorten the time from contract award to

commissioning from 20 months to less than 10 months. Before the solar park model, all of these

supporting infrastructure investments had to be made by the power developers themselves,

including factoring in the waiting time to obtain necessary permits and clearances.

10. POWERGRID is the Central Transmission Utility (CTU) of the country and owns and

operates the National Grid, which is an integration of the five regional transmission grids in India.

Strong regional grid interconnections enlarge the balancing areas and help connect renewable

energy generation to the National Grid, enabling tapping into huge hydro power potential and

storage type hydro power plants (capacity of which will also need to be increased to support the

increased national renewable energy generation targets of GoI) that are suitable for providing grid

balancing services. Further, as per the provisions of the Electricity Act 2003, the state electricity

regulatory commission have already specified renewable purchase obligations (RPO) on the state

distribution utilities. Access to larger markets enables the transfer of power from renewable energy

resource rich state to renewable energy resource scarce states and hence enabling the power-deficit

states to comply with their respective RPO. Targets for RPO are going to be enhanced substantially

and monitored closely with the application of strict penalties in case of default once the proposed

amendments to the Act are approved. Though there is of course an inherent risk of financial

strength of these discoms to adhere to RPO targets. However, there is a separate government

scheme underway called UDAY, which is also supported by the World Bank through a series of

engagements under the 24*7 Power for All program, to strengthen the finances of distribution

companies. When this risk of discom financial weakness was analyzed as a risk to the viability of

the solar park business model, it was found that solar power procurement is such a tiny percentage

of the overall power procurement of discoms (even if it were to go up from 3% to 8%), that it does

not make a material difference and does not pose a great risk. If the penalties are high enough to

incentivize compliance, the discoms (even in solar-scarce states) will comply with their renewable

purchase obligations. Also, costs are continually coming down through aggressive bidding that is

occurring in each successive auction, and the large gap between solar energy cost and thermal

energy cost is disappearing fast, making the discom much less reluctant to purchase solar power

on a 25 year PPA arrangement. Therefore the risk of the ISTS lines not being used, due to lack of

demand by faraway discoms to access solar power from solar rich states, is judged to be very low.

C. Higher Level Objectives to which the Project Contributes

11. Alignment with GoI’s National priorities: The project is aligned with GoI’s National

Action Plan for Climate Change (NAPCC), which was issued in 2008 to enhance India’s ecological

sustainability & encourage sustainable energy sources. It is also consistent with the Jawaharlal

5 Until the Open Access system is made fully operational, this direct access to PowerGrid’s network confers an additional benefit

relative to exclusive dependence on the state transmission utility’s network and the latter’s possible reluctance to allow power to

be sold outside of the state, contractual obligations notwithstanding

Page 16: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

6

Nehru National Solar Mission (JNNSM) that was launched in 2010 as part of NAPCC to promote

the development of solar power in India. GoI has significantly scaled up the target of 20 GW of

solar power in JNNSM to 100 GW by 2022. GoI has reiterated these commitments as part of its

Intended Nationally Determined Contributions (INDCs) commitment to achieve about 40 percent

cumulative electric power installed capacity from non-fossil fuel based energy resources by 2030.

12. Alignment with World Bank’s India Country Partnership Strategy (CPS). The proposed

project is aligned with the India Country Partnership Strategy along its three pillars –integration,

transformation, and inclusion. Under integration, the project will accelerate private investment in

solar power in some of India’s solar-resource rich states such as Karnataka and Madhya Pradesh.

Under transformation, the project directly aims to reduce environmental pollution and GHG

emissions, add clean power generation capacity, and foster innovative solar development through

shared large-scale infrastructure. Under inclusion, the project offers the opportunity to increase

access to electricity by increasing the availability of electricity generation in the system. In

addition, the operation conforms to the emphasis of the CPS on GoI’s “Finance-Plus” approach

whereby the value-added by the Bank goes beyond financing and contributes to the transfer of

knowledge and international best practices, reform of processes and systems, and strengthening of

institutional capacity.

13. Furthermore, the proposed operation supports the World Bank Group’s corporate

commitment to increase renewable energy lending, and address climate change. The program is

also aligned with the WBG’s goal of reducing poverty and promoting shared prosperity.

II. PROJECT DEVELOPMENT OBJECTIVES

A. PDO

14. The proposed development objective is “to evacuate power from the selected solar power

generation parks to the Inter-state Transmission System.”

B. Project Beneficiaries

15. The direct beneficiaries of the project are (i) the people in the participating states and

elsewhere who will benefit from the electricity generated in the solar parks and (ii) discoms which

will be able to meet their RPOs with electricity generated from solar parks.

16. The indirect beneficiaries are people who will benefit from (i) avoided local environmental

damage costs (ii) additional growth and productivity due to improvements in power supply

situation.

C. PDO Level Results Indicators

17. The following indicators will be used to track progress in achieving the project

development objectives:

Transformation capacity installed as part of the project (MVA)

Transmission system availability of dedicated network for evacuation of solar

power from the generation point (%)

Page 17: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

7

Energy evacuated from the solar parks to the ISTS (GWh)

III. PROJECT DESCRIPTION

18. The Ministry of New and Renewable Energy (MNRE) aims to provide impetus to solar

energy generation by establishing flagship demonstration facilities to encourage project developers

and investors, prompting additional projects of similar nature (including scale), triggering

economies of scale for cost reductions, technical improvements and achieving large scale GHG

emissions reductions. As per the scheme, a solar park is a concentrated zone of development of

solar power generation projects and provides developers an area well characterized with proper

infrastructure and access to amenities and where the risk of the projects can be minimized. The

scheme intends to attract significant investments from project developers in the States to enable

them to meet RPO mandate and provide employment opportunities to local population to the extent

possible. It aims to reduce the number of approvals required by developers to set up solar

generation plants and hence attract private investments in such solar plants. The State will also

reduce its carbon footprint by avoiding emissions equivalent to the solar park’s generation. Further,

the State will also avoid procuring fossil fuels to run conventional power plants.

19. The power evacuation arrangement consists of two parts – (i) pooling stations and network

within the Park to collect power from each project and transmitting it to the transmission substation

at the park boundary; and, (ii) the transmission substation and the linked transmission line up to

the Central Transmission Utility’s (CTU)/State Transmission Utility’s (STU) existing network.

Part two of the evacuation arrangement depends on whether the host State is inclined to bridge its

power demand-supply gap that depends on number of factors such as grid stability, redundancy in

the system, etc. and/or whether it wants to export the surplus solar power to other power deficit

states and to the states that are unable to meet their mandated RPO.

20. During the identification phase, consultations about the Bank financing going to solar parks

were carried out with various stakeholders like MNRE, SECI and relevant state agencies. It was

requested that the World Bank should fund transmission infrastructure for power evacuation from

the selected solar parks. Given the specific transmission requirements of solar power and risk of

stranded assets, investors continue to see the availability of state of art transmission infrastructure

to connect solar generation to load centers across the country as a precondition to major investment

decisions.

21. The proposed project focuses on financing the part two with CTU (POWERGRID) as the

implementing agency, that is, the project finances the transmission substation and the transmission

lines at the periphery of the selected solar parks up to the CTU’s existing network. POWERGRID

will build, own and operate the inter-state transmission system (ISTS) as per the requirement of

power transfer across various states/regions of the Country. With access to the National Grid, the

project will give the solar power developers, who are setting up their solar generation plants within

these parks, access to potential power sellers and buyers beyond regions and hence accessing the

regional market and further integration of the regional grids.

22. The activities will involve setting up of substations at the periphery of the solar park,

building infrastructure using the latest technology (like SCADA, GIS, STATCOM, bay controller,

Page 18: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

8

OPGW, PLCC, etc.), real time monitoring of solar generation and hence integration of solar energy

with inter-state transmission system.

23. Since all the solar parks have not been finalized these investments under this project will

be taken up in a phased manner. The following solar parks that are in advanced stages, to be taken

up immediately:

A. Project Components

24. Component 1. Transmission evacuation infrastructure for 2000 MW Pavagada Solar

Park in Karnataka (US $180 million). This will entail: (i) establishment of 5x500MVA,

400/220kV pooling substation at Tumkur along with 1x125MVAR Bus Reactor; (ii) Tumkur

Pooling Station-Hiriyur 400kV D/C transmission line; (iii) Hiriyur-Mysore 400kV D/C line; (iv)

LILO of Gooty-Madhugiri 400kV D/C line at Tumkur pooling station; and, (v) +/-150MVAR

STATCOM at Tumkur.

25. Component 2: Transmission evacuation infrastructure for 750 MW Rewa Solar Park in

Madhya Pradesh (US $100 million). This will entail: (i) establishment of 3x500MVA, 400/220kV

pooling station at Rewa with 1x125MVAR Bus Reactor, and (ii) LILO of Vindyachal-Jabalpur

400kV D/C line at Rewa Pooling Station.

26. The tentative list of the schemes that may be financed under the project includes

Transmission system Neemuch and Agra (MP) solar parks, Mehboobnagar (Telangana) solar parks

and any other future transmission schemes for solar parks in the states of Karnataka, MP and

Telangana. These will be finalized upon obtaining approval from Central Electricity Authority

(CEA) and/or Standing Committee on Power System Planning. Additional transmission

subprojects/schemes will also be identified to meet the overall funding commitment.

B. Project Financing

27. The project will be financed through the Investment Project Financing instrument, which

will cover the investments required for shared infrastructure in identified states. GoI has chosen to

denominate the loan in USD. The total cost of the project is estimated at US$600m, of which

US$270 will be the World Bank IBRD financing and $30 million will be CTF financing. GoI has

opted for variable spread option for this loan. [WILL BE CONFIRMED AT

NEGOTIATIONS]. Powergrid will sign the project agreement with the Bank for the

implementation of the project while GoI will sign the loan agreement with the Bank.

28. The CTF funding, US$ 30 million, will be extended under softer concessional terms. The

CTF loan is offered with a service charge of 0.25% per annum on the disbursed and outstanding

loan balance and 40-year maturity, including a 10-year grace period, with Principal repayments at

2% for Years 11-20 and at 4% for Years 21-40. Principal and service charge payments accrue

semi-annually. A management fee equivalent to 0.45% of the total loan amount ($135,000) will

be charged, to be capitalized from the loan proceeds, following the effectiveness of the loan

29. Table 1 provides a breakdown of project costs and financing by component:

Page 19: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

9

Table 1: Project Costs and Financing (US$ million)

Project Components Project

cost

IBRD

Financing

CTF

Financing

GoI and State

Government Financing

Pavagada Solar Park 180 81 9 90

Madhya Pradesh Solar Park 100 45 5 50

Others 320 144 16 160

Total Project Costs 600 270 30 300

C. Lessons Learned and Reflected in the Project Design

30. The project builds on the lessons learned from the GoI’s experience with the

implementation of Charanka and Bhadla Solar Parks in the states of Gujarat and Rajasthan,

respectively. In particular, these experiences have highlighted the need to (i) keep the shared

infrastructure costs of solar parks low to attract developers to the park; (ii) have access to the ISTS

from the solar park to ensure linkage with the national market and (iii) closely co-ordinate the

development of transmission interconnections to the park to ensure that assets of developers are

not stranded. These lessons have been built into the design of the project by MNRE and World

Bank.

31. Another important lesson is how to successfully design and implement a project under the

framework of a Centrally Sponsored Scheme (CSS). The past experience of implementing similar

projects, which normally across multiple states, clearly underscored that project implementation

is often adversely affected because of inadequate attention to a range of issues in preparation. To

avoid implementation delays, the project has to adopt a sub-project readiness criteria specifying

the critical actions related to technical, environmental, and social aspects that need to be completed

prior to contract award.

IV. IMPLEMENTATION

A. Institutional and Implementation Arrangements

32. Over the past decade, POWERGRID has acquired and developed skills required for

successfully planning and implementing large scale capital investment programs, through its

mandate to develop the inter-state transmission network of India and also by acting as Consultant

to some states to assist them to plan, design and implement their transmission and distribution

networks. All the schemes envisaged under this operation are being designed, procured and

implemented by POWERGRID. Local and foreign contractors engaged through international

competitive bidding will carry out the supply, installation and erection works.

Page 20: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

10

33. The project implementation will be under the institutional oversight of the Ministry of

Power (which is the line ministry overseeing POWERGRID operations), the Ministry of New &

Renewable Energy (MNRE), the Ministry of Finance (MoF) and CEA.

B. Results Monitoring and Evaluation

34. PowerGrid, as the implementing agency, will provide the Bank with quarterly physical

progress reports, interim financial reports, audited financial statements (within six months of the

end of each financial year), and other such information as the Bank may reasonably require. Since

the nature of these contracts will be Supply and Installation (S&I), Monitoring and Evaluation

(M&E) is linked to project targets upon completion of milestones like delivery of material, erection

and commissioning.

35. PDO level results indicators are (i) Transformation capacity installed as part of the project

(MVA) (ii) Transmission system availability of dedicated network for evacuation of solar power

from the generation point (%)

36. The intermediate outcome indicators will be (i) transmission lines constructed (in circuit

km); (ii) number of grid sub-stations constructed

37. The project is not financing new household connections or last mile connectivity (11kV

and below), and is not directly contributing to expanding access in the participating states.

However, the project is likely to have a significant indirect contribution to expansion of access to

electricity, as a result of the increased availability of electricity in all project states, wherein the

investments supported under the project are expected to lead to increased hours of supply to

existing customers, and increased availability of electricity supply, which may enable utilities to

connect and serve new customers.

C. Sustainability

38. POWERGRID’s involvement is a reasonable assurance that project design and

implementation will be of high standards. In addition, environmental and social issues will be

handled with adequate expertise and attention, building on POWERGRID’s implementation track

record of earlier World Bank funded projects.

39. The Environmental and Social sustainability is facilitated through will adoption of a

framework approach for this project as all the investments have not been identified as yet. Power

Grid has recently (2014-15) developed ESPP Framework for six north eastern states in the context

of the preparation of the World Bank assisted North East Power System Improvement Project,

incorporating the provisions of India’s new ‘The Right to Fair Compensation and Transparency in

Land Acquisition, Rehabilitation and Resettlement Act, 2013’ as well as the provisions of Sixth

Schedule of the Indian constitution.

Page 21: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

11

V. KEY RISKS AND MITIGATION MEASURES

A. Overall Risk Rating Explanation

40. The key risks and issues associated with the proposed project are as follows:

41. Grid Parity for Solar: The GoI has announced the ambitious targets of installing 100GW

of solar power generation capacity in the country by 2022. The current installed capacity of solar

stands at 3.7GW. Unless this is backed up by strong political will and solar generation costs

achieving grid parity, achieving these targets are extremely ambitious. To factor this in, the GoI

has announced schemes and policies to boost the solar energy sector in the country, for instance,

the scheme on development of solar parks and ultra-mega solar power projects was launched in

December 2014. Similarly, almost 19 states and union territories have come up with the state

specific solar policies to enable conducive environment for growth of this sector. Solar energy has

shown a dramatic fall in tariffs in India, with the recent tender floated by the state of Madhya

Pradesh receiving the lowest tariff at INR 5.05 per unit without any subsidy.

42. Minimum Generation required to break-even the investments isn’t installed in the Solar

Park. During project preparation, the team will analyze the minimum percentage of occupancy by

solar developers that is required in the solar parks for “break even” of the solar parks in financial

and economic terms. The investments in transmission network for evacuation of solar park has

longer gestation period than setting up the solar projects. Hence, it is important to ensure that the

minimum solar generation that will make the investments under the project at least break even,

will be coming up in the solar parks. This is likely to happen if developing solar power plants

inside the Solar Parks is perceived to be more expensive than developing solar plants outside, the

space inside the Solar Parks may or may not be utilized fully. Even the delays in putting up the

solar generation projects within the park will also have an impact on the already built transmission

infrastructure. To mitigate this, the Bank will facilitate a close dialogue between the developers

and the implementing agencies to ensure that the costs associated with the Solar Parks don’t

escalate and concerns of developers are addressed. Lessons from the existing parks in India

(Charanka in Gujarat and Bhadla in Rajasthan) will also be incorporated suitably to address such

concerns. Further, POWERGRID also does its due diligence before investing into the project and

closely monitors the implementation schedule of generation assets to match up with its

transmission investments to the extent possible.

43. Non-availability of grid in a timely manner. There is a possible risk that the solar assets are

stranded due to non-availability of transmission evacuation grid in a timely manner. The possible

reasons for the same could be solar generation comes on-stream before the scheduled completion

date of transmission assets or may be due to right-of-way issues. To mitigate this risk, the Bank is

closely monitoring the plan for implementation of the evacuation infrastructure by POWERGRID

and match the timelines with solar generation commissioning to the extent possible. With regard

to right-of-way issues, the Ministry of Power has already formed a committee with selected states

to decide on provision of the compensation to be paid for such issues.

44. Grid instability. There is a possible risk of grid instability in frequency, current, and voltage

due to large-scale solar generation at a single point. To mitigate this, it will be necessary to carry

out a detailed system study to identify ways to ensure uninterrupted operation of grid. It may also

Page 22: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

12

be important to install specialized equipment between the solar power plants and the main

electrical grid. The Bank will work closely with relevant state and central agencies and utilities to

ensure that these concerns are addressed during project preparation and lessons from Charanka

Solar Park in Gujarat and Bhadla Solar Park in Rajasthan are incorporated in project design.

Further, POWERGRID and POSOCO in association with National Renewable Energy Lab

(NREL), USA are already collaborating to address this issue.

45. Overall: Given the long-term partnership of the Bank with POWERGRID, the latter has

become a strong entity that is capable to ensure that the investments are made well in time and are

not left stranded. Since POWERGRID owns, operates and maintains the National Grid, it in

association with POSOCO, takes all due measures required to ensure grid stability. Based on this,

the risk is assessed at "Moderate" during project implementation.

VI. APPRAISAL SUMMARY

A. Economic and Financial Analysis

46. A cost-benefit analysis consistent with recent Bank guidance on this topic6 was carried out

for the 2GW Pavagada Solar Park in Karnataka, which is the most advanced in terms of design of

the solar parks covered under the project7. The economic analysis covers the entire package of

solar park investments comprising of solar park investments, transmission investment, and solar

generation plants installed by developers rather than just the Bank financed portions of the solar

parks projects8. The economic analysis covers 28 years, including 3 years of construction and 25

years of operation. A discount rate of 12% was used for the calculation9. The analysis includes a

consideration of the relevant negative global and local environmental externalities.

47. The economic analysis indicates that in India utility scale solar power is increasingly

competitive with thermal generation using imported coal. The baseline economic return of

Pavagada Solar Park against the “without solar park scenario” is 7% (NPV –US$ 386 million),

which is below the 12% hurdle rate used for Bank projects (see Table 2). However, the solar park

has substantial local and global environmental benefits and consideration of these benefits

increases the ERR of the solar park significantly. The inclusion of avoided damage costs of local

pollution in the economic flows, increases the ERR to 10% (NPV -US$163 million). The

inclusion of avoided global environmental damage costs (using the Bank guidance on social value

of carbon), increases the ERR to 18% (NPV $ 545 million).

Table 2: Summary of Economic Analysis

6 These include the 2015 World Bank guidance on the economic analysis of renewable energy projects and the 2014 “Operational

Policy and Bank Procedure (OP/BP) 10.00, Investment Project Financing” 7 Once design elements are firmed up, the team will carry out the economic analysis of additional solar parks 8 This is consistent with the Bank’s 2015 guidance on economic analysis of renewable energy projects. 9 A review of discount rates used in Bank projects is currently underway. The economic analysis will revised once the new

guidance on discount rate is finalized.

Page 23: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

13

Economic rate of return Unit Values

ERR % 7%

ERR + local externalities % 10%

ERR + local externalities + GHG % 18%

Switching value, avoided GHG emission $ /ton $6

Composition of NPV

Cost of Solar Park

capital cost $USm 1265

O&M $USm 31

Benefits of avoided coal generation

Avoided coal costs $USm 824

Capacity credit $USm 86

NPV (before environmental benefits) $USm -386

local environmental benefits $USm 223

GHG emissions @$30/ton $USm 708

NPV (including environment) $USm 545

Lifetime GHG emissions undiscounted

Mtons

CO2

69

Marginal abatement cost MAC $/ton 5.6

48. Reduction in GHG emissions. The analysis indicates that the solar park will reduce

GHG emissions by 69 million tons over the life of project compared to the thermal counterfactual.

The marginal abatement cost of GHG emission for the Solar Park is $5.6/ton. The Solar Park will

help avoid local and environmental damage costs equal to $931 million compared with the thermal

counterfactual.

49. Sensitivity Analysis. The switching values for the important variables such as capital

costs, Capacity Utilization Factor, PV generation capital costs, coal prices, capacity credit and

discount rate are presented in Table 3.

Table 3: Switching Values

Input Unit Baseline Value Switching Value

Project Cost $ Million 1296 910

CUF % 19% 27%

PV Cost $M/MW 1.06 0.70

Annual Increase Coal

Prices % 0% 5%

Discount Rate % 12% 7%

Capacity Credit % 19% 103%

Grid Integration Costs % 0 -2.70%

Page 24: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

14

Project cost overrun

factor Ratio 1 0.7

B. Technical

50. POWERGRID, in its capacity as CTU, is designated as the Nodal Agency for grant of

Connectivity, Long-Term Access and Medium-Term Open Access to the inter-State transmission

system as per the Regulation 4 of the Central Electricity Regulatory Commission (Grant of

Connectivity, Long-term Access and Medium-term Open Access in Inter-State transmission and

related matters) Regulations, 2009. Under this, POWERGRID ensures that the generators,

irrespective of source of generation (whether conventional or renewable), files a long term open

access (LTA) application with it before it takes up the proposal for implementing any transmission

investments at inter-state level. Once LTA is finalized and submitted, POWERGRID along with

State Transmission Utility (if the State’s network is likely to be used) carries out the necessary

interconnection study as specified in Central Electricity (Technical Standards for Connectivity to

the Grid) Regulations, 2007. A detailed load flow study for the network is carried out and

accordingly establishing new links as well as strengthening of the existing networks is undertaken.

51. The investments include construction of transmission systems for evacuation of the power

from solar park. It includes packages on pooling stations, transmission lines etc. Powergrid had

carried out a detailed evacuation studies on the Rewa and Pavagada solar parks. Whenever any

new generating source is set up and is required to be connected to the existing ISTS network it is

essential that system studies are conducted by the CTU , in this case POWERGRID to assess the

impact of the new additions on the running grid. The intention is to establish augmentation/

additions needed to the existing network so that the generation can be absorbed without any

adverse effect.

52. The study covers the Load flow analysis, Reactive power flow patterns, and

Measures/Corrective actions to be implemented by the partners in the Grid. Study also assess the

health of the consolidated system in case of outage of any network element of the grid including

the generator itself, the Solar Park in present case. After such a study is carried out by

POWERGRID it is presented in the Standing Committee chaired by CEA with other constituent

members from the region for deliberations and clearance. Post studies POWERGRID has already

identified the network to be added to the present system for both REWA and Pavagada solar parks.

C. Financial Management

53. POWERGRID shall be responsible for the project’s financial management arrangements.

POWERGRID is already implementing Bank funded projects and is well aware of Bank’s

fiduciary requirements. POWERGRID shall provide the fiduciary assurance to IBRD on proper

and efficient use of Bank financing. POWERGRID will implement the Project as per the financial

management provisions of Loan Agreement and as further detailed in the Project Implementation

Plans. With financial management arrangements described below and given the POWERGRID’s

experience in implementation of Bank funded projects, the financial management risk for the

project remains Moderate.

Page 25: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

15

D. Procurement

54. Procurement for the project will be carried out in accordance with the World Bank’s

“Guidelines: Procurement of Goods, Works and Non-Consulting Services under IBRD Loans and

IDA Credits and Grants by World Bank Borrowers” (January 2011 revised July 2014)

[Procurement Guidelines]; “Guidelines: Selection and Employment of Consultants under IBRD

Loans and IDA Credits & Grants by World Bank Borrowers (January 2011 revised July 2014)”

[Consultant Guidelines]; and the provisions stipulated in the Legal Agreements. The project would

be subject to the Bank’s Anti-Corruption Guidelines, dated October 15, 2006, and revised January

2011.

55. Procurement Risk Assessment: Power Grid would be responsible for undertaking all

procurements and contract management activities under the project.

56. The Procurement Risk Assessment and Management System (PRAMS) is presently being

undertaken and will be finalized during appraisal, based on the assessment and the experience of

Power Grid in implementing Bank funded projects, the procurement risk rating is rated as “Low”.

Power Grid has staff with expertise in procurement and contract management in conducting

procurement in accordance with Bank policies and procedures, having successfully handled

procurement activities under Bank funded projects.

57. E-procurement System. Power Grid would be using e-procurement system for all

procurements under the Project. The e- procurement system assessment was carried out against

the Multilateral Development Banks (MDB) requirements, and has been accepted for use for

Procurements under Bank funded projects by the Bank.

58. Procurement Plan and Readiness. The draft procurement plan for the project

implementation is enclosed in Annex 3. Power Grid has already identified the investment and

tentative packaging of approx. USD 190 million for the sub projects in Rewa, Madhya Pradesh

and Tumkur, Karnataka. Another approx. USD 200 million are allocated for the sub projects in

Neemuch & agar, Madhya Pradesh and Gattu, Telengana. Power Grid would finalize the full

investments and the tentative packaging and procurement plan by appraisal for the full project cost

of USD 600 million.

E. Environment & Social (including Safeguards)

59. The environmental aspects that need to be handled through the environmental assessment

( OP 4.01) include the removal of vegetation, possible hindrance to movement of fauna alteration

to local or area’s drainage pattern, as well as health and safety of workers and residents near the

facilities, and handling of chemicals. The assessment would also need to examine issues related to

Natural Habitats (OP 4.04), Forests (OP4.36), and Physical Cultural Resources (OP4.11).

60. Relative flexibility available in locating facilities within an area allow judicious selection

of sites for most transmission infrastructure elements. The potential adverse environmental

impacts can be managed adequately with advance planning and early consideration of the issues

Page 26: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

16

like minimization of the forest land to be used for the project, proper management of drainage, and

avoidance of sites of cultural importance.

61. Powergrid has been recognized for successful management of environmental and social

aspects of its activities in line with Bank expectations over past decades. This is undertaken in line

with its Environmental and Social Policies and Procedures, which were approved for use under

the Use of Country System pilot program in 2009 and follow the hierarchy of choosing avoidance,

minimization, mitigation for adverse impacts and enhancement of positive impacts, wherever

possible.

62. Major social safeguard aspects relate to: land and tribal. Project require lands for: (i)

erection of pole to draw lines; and (ii) construction of sub-stations transformation of power. The

former does not entail permanent acquisition of lands, but, creates some temporary disturbances

demanding a Compensatory Plan (Compensatory Plan for Temporary Disturbance or CPTD).

Number of people/ families likely to be impacted/ involved in the CPTD is expected to be quite

high and hence demands a highly responsive and effective interface with the communities. The

latter, sub stations, however, does require land on a permanent basis. Additionally, in some of the

sites, the project may have to encounter tribal/ scheduled areas, covered under the Fifth Schedule

of the Indian Constitution which provides protection to the tribal people living in the scheduled

areas with a variety of guarantees. The governance and administrative arrangements are also

different in these areas. So, interventions to secure lands in these areas will have to be necessarily

associated with an interface with the tribals. Given this situation, project triggers OP 4.12

(Involuntary Resettlement) and OP 4.10 (Indigenous Peoples).

63. The project will adopt a framework approach as all the investments have not been identified

as yet. Power Grid has recently (2014-15) developed ESPP Framework for six north eastern states

in the context of the preparation of the World Bank assisted North East Power System

Improvement Project, incorporating the provisions of India’s new ‘The Right to Fair

Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013’

as well as the provisions of Sixth Schedule of the Indian constitution.

64. While environmental aspects of the ESPP hold good for the current project as well,

additional aspects need to be ingrained into social management framework. They include: (i)

managing due diligence in respect of Associated Activities; (ii) Ministry of Power’s recently issued

guidelines on financial compensations for Right of Way; and (iii) Indian constitution’s Fifth

Schedule provision related to tribal areas. It was agreed that an updated social management

framework comprising the following elements will be prepared by Powergrid by end November:

resettlement policy framework, tribal peoples planning framework, compensatory plan for

temporary disturbance (ROW) and a gender action plan.

65. As and when the project sites are firmed up, plans for consultations with stakeholders as

well as preparation of IEARs will be undertaken in line with the ESPP.

F. World Bank Grievance Redress

Page 27: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

17

66. Communities and individuals who believe that they are adversely affected by a World Bank

(WB) supported project may submit complaints to existing project-level grievance redress

mechanisms or the WB’s Grievance Redress Service (GRS). The GRS ensures that complaints

received are promptly reviewed in order to address project-related concerns. Project affected

communities and individuals may submit their complaint to the WB’s independent Inspection

Panel which determines whether harm occurred, or could occur, as a result of WB non-compliance

with its policies and procedures. Complaints may be submitted at any time after concerns have

been brought directly to the World Bank's attention, and Bank Management has been given an

opportunity to respond. For information on how to submit complaints to the World Bank’s

corporate Grievance Redress Service (GRS), please visit http://www.worldbank.org/GRS. For

information on how to submit complaints to the World Bank Inspection Panel, please visit

www.inspectionpanel.org.

Page 28: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

18

Annex 1: Results Framework and Monitoring

Country: India

Project Name: Transmission for Power Evacuation from Solar Parks (P156974)

Results Framework

Project Development Objectives

The proposed development objective is “to evacuate power from the selected solar power generation parks to the Inter –state

Transmission System.”

These results are at Project Level

Indicator Name Baseline Cumulative Target Values

YR1 YR2 YR3 YR4 YR5 End Target

Transformation

capacity installed as

part of the project

(MVA)

0 0 1000 2000 2500 2750 2750

Transmission system

availability of

dedicated network for

evacuation of solar

power from the

generation point (%)

0 0 99% 99% 99% 99% 99%

Electricity evacuated

from solar parks using

ISTS (GWh)

0 0 1400 2800 3500 3850 3850

Page 29: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

19

Indicator Name Baseline Cumulative Target Values

YR1 YR2 YR3 YR4 YR5 End Target

Transmission lines

constructed under the

project

(Kilometers - Sub-

Type: Breakdown) -

(Core)

0.00 0.00 100 200 250 270 270

Number of Grid

substations

constructed/upgraded

(Number)

0 0 1 2 3 4 4

Indicator Description

.

Project Development Objective Indicators

Indicator Name Description (indicator definition etc.) Frequency Data Source /

Methodology

Responsibility for Data

Collection

Transformation capacity

installed as part of the

project (MVA))

This indicator measures the

transformation capacity added to

evacuate the solar power from the solar

parks under the project.

Annual Progress Report Implementing Agency

Transmission system

availability of dedicated

network for evacuation of

solar power from the

generation point (%)

This indicator measures the

transmission system availability.

Annual Progress Report Implementing Agency

Page 30: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

20

Electricity evacuated

from solar parks using

ISTS (GWh)

This indicator measures the amount of

electricity evacuated from solar parks

using the Inter-state Transmission

System.

Annual Progress Report Implementing Agency

Intermediate Results Indicators

Indicator Name Description (indicator definition etc.) Frequency Data Source /

Methodology

Responsibility for Data

Collection

Transmission lines

constructed under the

project

This indicator measures the length of

the transmission lines constructed

under the project.

Annual Progress Report Implementing Agency

Number of Grid

substations constructed

This indicator measures the number of

220/132 kV, 132/33 kV substations

constructed under the project

Annual Progress Report Implementing Agency

Page 31: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

21

Annex 2: Detailed Project Description

INDIA: Transmission for Power Evacuation from Solar Parks (P156974)

1. This proposed project is one in a series of three engagements requested by the GoI from

the World Bank for US$1 billion of funding in the solar power sector10 11. All three projects are

expected to support achievement of the government’s new solar targets, and to demonstrate

important economies of scale in utility scale solar generation, push down equipment and

transaction costs, and also increase efficiency while reducing unit costs of solar power. It is

expected that the Bank-supported projects will create market confidence and will catalyze further

support from other investor groups for the GoI to help with achievement of its ambitious target of

installing 100GW of solar power capacity by 2022.

2. To help meet this target, Ministry of New and Renewable Energy (MNRE) has come up

with a ‘solar park scheme’ with an objective to provide impetus to solar energy generation by

establishing flagship demonstration facility to encourage project developers and investors,

prompting additional projects of similar nature (including scale), triggering economies of scale for

cost reductions, technical improvements and achieving large scale GHG emissions. As per the

scheme, a solar park is a concentrated zone of development of solar power generation projects and

provides developers an area well characterized with proper infrastructure and access to amenities

and where the risk of the projects can be minimized. The scheme intends to attract significant

investments from project developers in the States to enable them to meet RPO mandate and provide

employment opportunities to local population to the extent possible. It aims to reduce the number

of approvals required by developers to set up solar generation plants and hence attract private

investments in such solar plants. The State will also reduce its carbon footprint by avoiding

emissions equivalent to the solar park’s installed capacity and generation. Further, the State will

also avoid procuring fossil fuels to run conventional power plants.

3. The power evacuation arrangement consists of two parts – (i) pooling stations and network

within the Park to collect power from each project and transmitting it to the transmission substation

at the park boundary; and, (ii) the transmission substation and the linked transmission line up to

the Central Transmission Utility’s (CTU)/State Transmission Utility’s (STU) existing network.

Part two of the evacuation arrangement depends on whether the host State is inclined to bridge its

power demand-supply gap that depends on number of factors such as grid stability, redundancy in

the system, etc. and/or whether it wants to export the surplus solar power to other power deficit

states and to the states that are unable to meet their mandated RPO.

4. During the identification phase, consultations about the Bank financing going to solar parks

were carried out with various stakeholders like MNRE, SECI and relevant state agencies. It was

requested that the World Bank should fund transmission infrastructure for power evacuation from

the selected solar parks. Given the specific transmission requirements of solar power and risk of

stranded assets, investors continue to see the availability of state of art transmission infrastructure

10 During their July 2014 and January 2015 meetings, Prime Minister Narendra Modi and President Jim Kim had agreed that the

Bank would provide financing for Solar Parks in the country 11 In particular, GoI requests have been received for all other Bank engagements to (i) support the establishment of grid

connected rooftop PV; (ii) fund the construction of associated evacuation infrastructure from Bank-supported solar parks; and

(iii) shared infrastructure for solar parks.

Page 32: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

22

to connect solar generation to load centers across the country as a precondition to major investment

decisions.

5. The proposed project focuses on financing the part two with CTU (POWERGRID) as the

implementing agency, that is, the project finances the transmission substation and the transmission

lines at the periphery of the selected solar parks up to the CTU’s existing network. POWERGRID

will build, own and operate the inter-state transmission system (ISTS) as per the requirement of

power transfer across various states/regions of the Country. With access to the National Grid, the

project will give the solar power developers, who are setting up their solar generation plants within

these parks, access to potential power sellers and buyers beyond regions and hence accessing the

regional market and further integration of the regional grids.

6. Presence of ISTS at the solar park border therefore allows India’s solar-resource rich states

to transfer solar energy to solar-resource poor states, whose distribution utilities nevertheless face

renewable purchase obligations and must meet these by “importing” renewable energy from

elsewhere. This is a nascent or not yet developed market, which will be supported by the

implementation of the current project and a few more like it.

7. The activities will involve setting up of substations at the periphery of the solar park,

building infrastructure using the latest technology (like SCADA, GIS, STATCOM, bay controller,

OPGW, PLCC, etc.), real time monitoring of solar generation and hence integration of solar energy

with inter-state transmission system.

8. Since all the solar parks have not been finalized these investments under this project will

be taken up in a phased manner. The following solar parks that are in advanced stages, to be taken

up immediately:

9. Component 1. Transmission evacuation infrastructure for 2000 MW Pavagada Solar

Park in Karnataka (US $180 million). This will entail: (i) establishment of 5x500MVA,

400/220kV pooling substation at Tumkur along with 1x125MVAR Bus Reactor; (ii) Tumkur

Pooling Station-Hiriyur 400kV D/C transmission line; (iii) Hiriyur-Mysore 400kV D/C line; (iv)

LILO of Gooty-Madhugiri 400kV D/C line at Tumkur pooling station; and, (v) +/-150MVAR

STATCOM at Tumkur.

10. Component 2: Transmission evacuation infrastructure for 750 MW Rewa Solar Park in

Madhya Pradesh (US $100 million). This will entail: (i) establishment of 3x500MVA, 400/220kV

pooling station at Rewa with 1x125MVAR Bus Reactor, and (ii) LILO of Vindyachal-Jabalpur

400kV D/C line at Rewa Pooling Station.

11. The tentative list of the schemes that may be financed under the project includes

Transmission system Neemuch and Agra (MP) solar parks, Mehboobnagar (Telangana) solar parks

and any other future transmission schemes for solar parks in the states of Karnataka, MP and

Telangana. These will be finalized upon obtaining approval from Central Electricity Authority

(CEA) and/or Standing Committee on Power System Planning. Additional transmission

subprojects/schemes will also be identified to meet the overall funding commitment.

Page 33: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

23

12. POWERGRID is aware of the importance of real time monitoring of solar generation and

its impact on the grid. Hence, it has already proposed to establish a Renewable Energy

Management Center (REMC) at Karnataka State Load Despatch Centre (SLDC) and Southern

Region Load Despatch Centre (SRLDC). REMC at MP SLDC is under consideration. These will

be funded either through internal resources of POWERGRID or from sources other than the World

Bank. The Bank’s project focuses on financing the transmission network assets only but

establishment of these REMCs will be monitored during the project cycle.

13. POWERGRID, in its capacity as CTU, is designated as the Nodal Agency for grant of

Connectivity, Long-Term Access and Medium-Term Open Access to the inter-State transmission

system as per the Regulation 4 of the Central Electricity Regulatory Commission (Grant of

Connectivity, Long-term Access and Medium-term Open Access in Inter-State transmission and

related matters) Regulations, 2009. Under this, POWERGRID ensures that the generators,

irrespective of source of generation (whether conventional or renewable), files a long term open

access (LTA) application with it before it takes up the proposal for implementing any transmission

investments at inter-state level. Once LTA is finalized and submitted, POWERGRID along with

State Transmission Utility (if the State’s network is likely to be used) carries out the necessary

interconnection study as specified in Central Electricity (Technical Standards for Connectivity to

the Grid) Regulations, 2007. A detailed load flow study for the network is carried out and

accordingly establishing new links as well as strengthening of the existing networks is undertaken.

14. Commercial Aspects of the project: CERC has directed not to levy any transmission

charges on the solar developers if the evacuation lines are ISTS (refer Central Electricity

Regulatory Commission (Sharing of Inter State Transmission Charges and Losses) Regulations,

2010, amended in March 2015). Since all discoms are subject to Renewable Purchase Obligations

it is important to create a level playing field for discoms that are located far away from solar-

resource rich locations, as they will have to purchase their renewable energy from generators

located in solar-rich regions. The transmission charges are to be calculated as decided by CERC

regulations and to be borne by the beneficiary states hence socializing these transmission costs in

order to create a level playing field for all discoms. As India is following Point-of-Connection

(PoC) mechanism, all the Designated ISTS Consumers (DICs) will bear this transmission cost.

PoC is the methodology of computation and sha ring of ISTS Charges and Losses among DICs

which depends on location and sensitive to distance and direction of the node in the grid. Charges

would be computed for each node of DICs based on Hybrid Method as explained in the Regulations

(Refer Central Electricity Regulatory Commission (Sharing of Inter State Transmission Charges

and Losses) Regulations, 2010). Since the costs are being socialized, part of MNRE subsidy

earmarked for solar parks along with access to concessional financing will contribute towards

reduction in such transmission charges to minimize the burden on DICs and to ensure that the cost

per kWh for solar PV remains affordable even for states that are located far away, to avoid placing

a burden on those discoms and their customers.

15. Proposed developers and off-takers of the parks: In Pavagada solar park in Karnataka, it

has been proposed that NTPC, a central sector utility, will set up 600MW solar project to be set

up through bundling with unallocated thermal power under JNNSM, Phase II, Batch II scheme.

This 600MW is proposed to be purchased by the distribution companies of Karnataka. SECI,

another central sector organization, has proposed to install 500MW capacity of solar power

Page 34: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

24

projects whereas remaining capacity will be allocated to solar power developers including captive

power producers through bidding process. This is in keeping with the strategy in Karnataka to use

public sector companies as anchor tenants in the solar park so that they may quickly start operations

and also create a market for large scale EPC contractors to bid for such opportunities (to build the

generation capacity that will be owned by NTPC and SECI) and thereby demonstrate the

operations of the park. This public sector demonstration effect in Phase 1 will give confidence to

private commercial lenders that the park and its transmission infrastructure is indeed working

smoothly and will thereby mitigate risk perceptions of private developers who seek debt financing

for large scale generation projects. Both public and private developers are free to sell to customers

located in the state, or in any location in the country, using the inter-state evacuation infrastructure.

It is anticipated at this stage that about 1.5GW (that is almost 75% of the installed capacity of the

park) of the installed capacity will serve the State of Karnataka.

16. Access to National Grid ensures that any surplus power generated within the park and the

state can be easily dispatched to rest of the states. Furthermore, POWERGRID has rich experience

of successfully establishing 400kV network and given the grid intermittency issues linked to

renewable energy generation, it has been considered prudent to evacuate entire energy from the

park through ISTS network. With regard to absorption of solar power within the state, since the

actual generation of solar energy is much less than the installed capacity, the power from Pavagada

park to be absorbed within the state will be balanced by the existing hydropower plant in the state

(installed capacity of 3.6GW).

17. In MP, it has been proposed that the entire capacity will be set up through competitive

bidding. As off-takers of the power, the state government of MP is targeting to absorb 300MW,

the state of Chattisgarh to absorb 200 MW and the state Government of Uttar Pradesh to absorb

250 MW.

18. Technical Standards for Connection to the National Grid: India already has a well-

established ‘Indian Electricity Grid Code, 2010’ (IEGC) issued, monitored and amended from time

to time by Central Electricity Regulatory Authority (CERC). The IEGC lays down the rules,

guidelines and standards to be followed by various persons and participants in the system to plan,

develop, maintain and operate the power system, in the most secure, reliable, economic and

efficient manner, while facilitating healthy competition in the generation and supply of electricity.

The IEGC brings together a single set of technical and commercial rules, encompassing all the

Utilities connected to/or using the ISTS. IEGC clearly defines the Planning Code for ISTS, the

Connection Code that specifies minimum technical and design criteria to be complied by any user

seeking connection to the ISTS to maintain uniformity and quality across the system, the Operating

Code to maintain efficient, secure and reliable grid operation, and, the Scheduling and Despatch

Code. The Regional Power Committee (RPC) in the region monitors the instances of non-

compliance of the provisions of IEGC and deliberate on the ways in which such cases of non-

compliance are prevented in future by building consensus. Given that Indian Grid is one of the

most complex grids and the third in terms of size in the world, IEGC has been able to successfully

achieve the desired purpose in grid operations and its stability. But with target of adding renewable

energy generation at a very large scale, it is important to note that introduction of suitable technical

standards for grid connectivity, specifically for solar generation, are required to be developed

Page 35: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

25

further by Central Electricity Authority (CEA), the planning arm of Ministry of Power (MoP).

Project preparation will look into the developments on this aspect as well.

19. The States along with MNRE, which is the central ministry for the New and Renewable

Energy sector in India have drawn-up a long list of candidate solar parks. The proposed project

can fund any of the transmission evacuation project from solar parks in Madhya Pradesh,

Karnataka and Telangana. Following table shows the summary of planned long list of potential

solar parks.

S.No State Location & capacity

Type

Intra-State Inter-State

1 Gujarat Banaskantha (700 MW) - 700

2 Madhya Pradesh Rewa (750 MW)

Neemuch (435 MW) 1,500

Agar (315 MW)

3 Telangana Gattu, Mehboob Nagar (1000 MW) 1,000

4 Andhra Pradesh Anantpur (1500 MW) 1,000 1,500

Kurnool (1000 MW)

5 Karnataka Tumkur (2000 MW) 2,000

6 Uttar Pradesh Jalaun (370 MW) 230 370

Sonbhadra, Allahabad & Mirzapur (230 MW)

7 Meghalaya West & Esat Jayantia Hills (50 MW) 50

8 J&K Leh & Kargil (7500 MW) 7,500

9 Punjab

Patiala, Fatehgarh Sahib, Ludhiana & Gurdaspur

(1000 MW) 1,000

10 Rajasthan Bhadla (1700 MW) & Jaisalmer (2000 MW) 700 3,000

11 Tamil Nadu Ramanathapuram (500 W) 500

12 Odisha Location not stated (1000 MW) 1,000

Total 22,050 4,480 17,570

20. The section below provides details about the proposed solar park in Karnataka.

Solar Parks in Karnataka

21. There are around five Solar Parks proposed in the state of Karnataka and around 25 such

parks across the country in association with the Solar Energy Corporation of India (SECI);

Government of India. KREDL has taken the advance initiative in the Tumkur district to develop

the first Solar Park of the state of the cumulative capacity of 2000 MW. The power evacuation

facilities from Solar Park will be furnished by Power Grid Corporation of India Limited

(POWERGRID).

22. KREDL has selected the land in Pavagada Tehsil of Tumkur district of the state of

Karnataka. Presently around 14000 acres of the land has been identified for which the acquisition

Page 36: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

26

process has been started. The selected land required less amount of civil work and well addresses

the essential requirements of Solar Park. It has been noticed that the selected location satisfies

most of the essential requirements towards setting up a Solar Park in the vicinity. The project is

planned with multi-crystalline and CdTe based Thin Film Solar PV technologies (which are the

well mature and proven technology across the globe) along with central type inverter for minimum

project capacity of 50 MW. The present Detailed Project Report (DPR) contains all key aspects of

a Solar Park of the capacity of 2000 MW in the Tumkur District of the state of Karnataka, India.

Current Status

23. Project Implementing Agency: For the World Bank loan, a JV company between KREDL

and SECI will be the project implementing agency. It has been formed to oversee the development

of solar parks in the state during project preparation.

24. Land Status: A plot of approximately 11,000 acres of private land has been identified for

project site. To use this land, JV proposes to sign a land lease agreement with farmers, to avoid

delay in land acquisition. Farmers have the option to lease their land on lease for 25-35 years. So

far, more than 2000 farmers totaling 11,000 acres of land have already given their consent letter

for signing lease.

Planning for construction of shared infrastructure which includes construction of civil

infrastructure and transmission infrastructure has been started.

Long Term Application (LTA): JV has already applied for LTA application with

POWERGRID following CERC’s regulations on ‘Grant of Connectivity and Open

Access’.

Land Lease Agreements: Land records for 2000 farmers are being scrutinized for land lease

agreements under solar park. 21000 INR land lease rate per acres and 5 % escalation every

two years has been fixed after stakeholder consultation with the farmers. 800 records has

already confirmed, 400 are being clarified. It terms of timelines, land lease for all the plots

will be signed by Nov end and land will be transferred to JV by 1st January 2016.

Land Conversion: Gazette notification has already been issued by Government of

Karnataka (GoK) for conversion of land from agriculture to solar in Pavagada area.

Conversion letter has gone from energy to revenue department in GoK and process of land

conversion will be started very soon for the farmers.

25. Project finance: As mentioned above, the project aims to demonstrate minimizing public

funding requirement through a combination of scale, long-tenor financing and tariff structuring.

The proposed funding is as follows:

Solar Park (Shared infrastructure): MNRE will provide grant at the rate of up to INR 20

lakhs/MW or 30% of the project cost including grid connectivity cost whichever is lower,

which will be released as per the milestones as defined under its Solar Park Scheme. Of

the available MNRE grant, 50% (tentative) will go towards transmission evacuation to

POWERGRID.

Likely composition for shared infrastructure for Pavagada Solar Park total capital cost

requirement of $180 m

a. MNRE grant for solar park- $75 m

b. Partial upfront payment of 4 lakh per MW- $15 m

Page 37: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

27

c. World bank funding – $90 m

26. Power Offtake: To avail the ISTS, the host state has to evacuate at least 10% of the power

generated outside. GoK is planning to offtake 80-90% of the power generated from Pavagada Solar

Park. The remaining power will be transmitted outside the state using ISTS.

Tentative project allocation of solar park

a. 600 MW NTPC (already tendered, PPA with NTPC, owned and operated by

private developers)

b. 1000 MW NTPC (TBC, owned and operated by NTPC with INR 4 tariff)

c. 400-500 MW KREDL (TBC, owned and operated by private developers, PPA

with state discom)

d. SECI- 500 MW (TBC)

It is also decided that Pavagada capacity will not increase more than 2000 MW and other park of

200-500 MW will be developed separately

Site Assessment

27. The selected land (around 14000 acres at present stage) for Solar Park establishment is

located in five villages namely Valluru, Rayacharlu, Balasamudra, Kyathaganacharlu and

Thirumani of Pavagada Taluk of Tumkur district of the state of Karnataka. The site assessment

section addresses the connectivity and accessibility (road/ rail/ air) aspects of the region. Pavagada

comprises established road connectivity as the State Highway (KA SH 03) passes from the city

and connect it from Madugiri to Chikkahalli. It has been observed that the project location receives

monthly average daily solar irradiance of 4.81 kWh/m2(August) to 6.55 kWh/m2 (March). The

annual GHI is 2008 kWh/m2 (annual average daily 5.50 kWh/m2) which contains 826 kWh/m2

(annual average daily 2.26 kWh/m2) diffuse component (around 41%).

Infrastructure plan of solar park

28. This section elaborates the infrastructure development over the conceptual plan of the

Solar Park. There are five key dimensions of infrastructure addressed in the section viz. Site

preparation (leveling, cleaning, plantation for dust deposition and wall with gates etc.), Land

(survey, soil investigation and geotechnical aspects etc.), Roads & Network (major and minor

roads of different width), Power Evacuation & Transmission (metering system, construction power

arrangements and transmission substation etc.) and Water Supply Systems (Water Requirement

for Module Washing and Other Purposes, Water Requirement for 2000 MW Solar Park, Source

and storage of Water and Requirement of Water Treatment etc.).

29. The proposed 2000 MW Solar Power would be developed in eight blocks of 250 MW

capacity. For each 250 MW Solar Power capacity block, one pooling substation of 66/ 220 kV is

proposed in which 2 x 150 MVA step-up transformers are considered. 250 MW block is further

subdivided into 50 MW sub blocks. Thus, these 5 X 50 MW sub blocks shall be connected to

pooling substation through 66 kV underground cables. The voltage will again be stepped up to

220kV at the Solar Project Pooling Station and again stepped up to 400kV at the proposed 400kV

Grid Substation by POWERGRID at Solar power. Karnataka Solar Power Development

Corporation Limited (KSPDCL)(JV of SECI and KREDL) will establish 8 Nos. of 220/66kV

Page 38: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

28

pooling stations at Pavagada site to evacuate 2000MW solar power generated at the Park. The

400kV Grid substation at the Solar Project is proposed to be connected to POWERGRID’s 765KV

Station at Madhugiri.

Project cost estimates

30. The land is proposed to purchase on the annual lease basis of Rs 21000 per acres with 5%

escalation on base year lease every second year; however the current price of the private land in

the vicinity has also been presented from the ongoing practices in the vicinity. Detailed costing of

8 numbers of 220/66 kV substation, 200 kV transmission line and 400 /220 kV substation will be

prepared given with their elaborated bill of material. The cost of administrative building,

warehouses, training center etc. have been estimated from best market practices in solar power

projects. In addition the present cost (recently commissioned projects) of solar PV power projects

with multi-crystalline and thin film technologies in India has been given with detailing from in

house data.

31. Table XX below presents the key insights of the Solar Park of the capacity of 2000 MW

in Tumkur district of the state of Karnataka, India.

Table XX. Project at a glance

1. S.

No

2. Particulars 3. Description

4. Project site Pavagada

5. District Name Tumkur

6. Name of the

State

Karnataka

7. Geographical

coordinates

Latitude 14.1oN and

Longitude 77.27oE

8. Land availability

(acres)

More than 14000 acres

9. Land quality Barrein and non-agricultural land

10. Connectivity and

accessibility

Well establishes and adjacent to Sate highway-03 of Karnataka

11. Minimum plant

size capacity

50 MW

12. Minimum plot

size (acres)

250 acres

13. Nearest airport Bangluru

14. Nearest railway

station

Hindupur Railway station (52 KM), Anantapur Railway station (101

KM) and Bellary (137 KM) are the nearest Railway Stations

15. Solar PV

Technology

Multi-crystalline solar PV /Thin Film

16. Proposed

Voltage Level

66 kV from each Plant and then step upto 220kV

Page 39: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

29

17. Tentative Capital

Cost

Capital Cost

Components

Unit Cost (Phase

1)

Cost

(Phase 2)

Total Solar park Cost Rs Crores

Land cost12

21,000 Rs per acre per

year with 2% escalation

on base year (Escalation

in every 2nd year)

Rs Crores

29.73 30.1

Site Development Rs Crores 17.5 16.6

Road & Drainage

system

Rs Crores

21.6 5.10

Street light Rs Crores 3.39 0.69

Water Supply system Rs Crores 5.85 5.72

Poolingi substations Rs Crores 187.08 187.08

Transmission line cost Rs Crores 10.00 10.00

Admin Building Rs Crores 11 -

Total Hard Costs Rs Crores 286.15 255.29

Total Hard costs

(P1+P2)

Rs Crores 541.47

Soft cost Rs Crores 11.9 17.6

Total soft cost Rs Crores 29.5

Total project cost Rs Crores 571.0

32. Upfront payment from project developer will be utilized in solar park development

expenditure by solar park agency. Annual fee will cater to recurring expenses over the project life.

Timelines: Scheduled timelines for setting up of Solar Power Park is as under:

S. No. Milestone Timelines

1 Pavagada Solar park preparation March 2015

2 Land leasing process completion

and transfer of land to JV

1 Jan 2016

3 Construction of Pooling Substation,

Land Development and other

Common facilities as per DPR

Transmission line and Grid

Connectivity

Aug 2017

4 1000 MW commissioned Sep 2017

5 2000 MW commissioned Sep 2018

33. State Government’s obligation to purchase power: Karnataka State Government in which

the solar park is developed has agreed agree to buy atleast 1600 MW of the power produced in the

park through its Discom.

12 Land lease is considered in capital cost only till Phase-1 and Phase-2 CODs. After COD, Land cost is considered as an annual expense. For

first 6 months, No land lease is considered as financial closure is attained after 6 months of project award.

Page 40: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

30

34. Similar analysis and information will be collected for Rewa solar park in Madhya Pradesh.

Rewa solar park is also currently under development and appraisal is underway.

Page 41: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

31

Annex 3: Implementation Arrangements

Financial Management, Disbursements and Procurement

Financial Management

1. POWERGRID shall be responsible for the project’s financial management arrangements.

POWERGRID is already implementing Bank funded projects and is well aware of Bank’s

fiduciary requirements. POWERGRID shall provide the fiduciary assurance to IBRD on proper

and efficient use of Bank financing. POWERGRID will implement the Project as per the

financial management provisions of Loan Agreement and as further detailed in the Project

Implementation Plans.

2. Staffing. POWERGRID will provide for adequate financial management staffing. The

project’s financial arrangements would be handled by the finance staff working at the Corporate

Centre, Regional Headquarters and the project site office along with regular finance work. The

International Finance division and Resource Mobilization Cell at the Corporate Centre would

coordinate with the various units within POWERGRID for seeking disbursements and servicing

the existing debt with the Bank respectively. It would be responsible for meeting the information

requirement of the external agencies and providing interim financial reports in the agreed

formats to the Bank through the Corporate Planning Department. As on March 31, 2015, total

finance staff in POWERGRID is 386.

3. Budgeting. Preparation of proper plan and budget plays an important role in timely

implementation of a project. Planning and budgeting involves identifying specific tasks or

objectives of the project to be achieved in a given time frame. The planning and budgeting at

POWERGRID for the project will be as described herein further. For effective project

implementation, POWERGRID shall prepare activity wise:

i. An overall plan for the duration of the project;

ii. Annual plan and budget with quarterly break-ups; and

iii. Quarterly statements providing variance between planned and actual

expenditure.

4. Accounting Policies and Procedures. POWERGRID has been incorporated as a company

under the Companies Act, 1956, and hence the financial reporting (balance sheet and the profit

and loss account) is governed by the provisions of that Act. In accordance with the Companies

Act, POWERGRID follows accrual/ commercial system of accounting and adheres to the

national accounting standards, as issued by the Institute of Chartered Accountants of India and

notified by GoI. Project accounting shall be carried out in accordance with accounting policy of

POWERGRID using the existing accounting systems. The claims submitted to the Bank will be

on cash basis eliminating items like retention money and unpaid liabilities. The project

accounting will be carried out at the respective Regional headquarter and the accounting records

will also be maintained at the said location. Regional headquarter/ Corporate Centre will be

responsible for release of all payments under the project as per current practice followed in

POWERGRID. Bills will be duly approved as per the existing delegation and procedures and

will be forwarded to Regional headquarter/ Corporate Centre for subsequent checks and release

Page 42: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

32

of payment. POWERGRID shall maintain all records and documents (contracts, orders, invoices,

bills, receipts and other documents) evidencing expenditures under the Project and retain these

until at least the later of: (i) one year after the Bank has received the final/ last audited financial

statements required under the IBRD Loan; and (ii) two years after the closing date of the IBRD

Loan. During such retention period, POWERGRID shall enable the World Bank representatives

to examine those records.

5. Funds Flow. The loan will be taken by POWERGRID and the disbursements will also be

managed by POWERGRID. Based on quarterly IUFRs, withdrawal claims will be submitted to

the Bank by POWERGRID for disbursement. The funds flow and reporting arrangements under

the project will be as below:

6. Reporting. The FM Reporting under the project shall be as follows:

a. IUFR: POWERGRID would be required to submit to the Bank quarterly IUFRs within

45 days from the end of the quarter. The IUFR would be prepared by POWERGRID

on the basis of information generated from POWERGRID’s MIS systems and will be

reconciled to the books of accounts and shall contain information on project

implementation including the expenditure incurred during the last quarter, and forecast

for the next two quarters. The format of the IUFR is provided in the PIPs and will also

be appended to the Bank's Disbursement Letter.

b. Project Annual Financial Statements: The project annual financial statements will

include (a) IUFRs for the fourth quarter; and (b) any other statement agreed with the

Bank.

7. Inventory and Asset Management. POWERGRID’s own inventory management systems

and procedures will be used for the purposes of the project. The inventory procured shall be used

in the identified projects generally. POWERGRID, which will have the primary responsibility

for physical verification of inventory and assets under construction, the Internal and External

Auditors will also carry out physical verification on a sample basis.

IUFR, claims, reports

Invoices

Funds

Funds

World Bank

POWERGRID –

Segregated Bank

Account(s)

Vendors/ Contractors

Page 43: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

33

8. Internal Audit: The internal audit of the project shall be carried out by: (i) option 1:

Hiring services of The Institute of Public Auditors of India (IPAI), a body of specialist in public

finance with focus on Auditing, comprising of serving and former officers from the Indian Audit

& Accounts Services and also senior Accounts and Audit professional with diverse experience in

Financial Management functions. In case it does not work out, then (ii) option 2: Internal Audit

firm empanelled by POWERGRID based on offer for EoI on competitive basis shall be

appointed as Internal Auditors.

The scope of audit will be as per agreed ToR. Based on the audit, the auditor will provide

suggestions for improvement.

9. External Audit13. The external audit of the project will be carried out by a firm of

chartered accountants appointed as per procurement procedure acceptable to the Bank. The ToRs

for the external audit will be agreed with the Bank and provided in the PIP. The annual audit

report shall be submitted to the Bank within nine months of the closure of the financial year. The

annual audit report would be accompanied by (i) audited project financial statements which

would separately identify each component under the project, its progress and the funding sources

for each of the components, with management assertion; (ii) an audit report expressing an

opinion on (a) the project financial statements; and (b) the accuracy of the IUFRs submitted

under the project; and (iii) management letter from auditors highlighting significant issues to be

reported to the management.

10. Eligible expenditure. All expenditure relating to project which will be undertaken in line

with the loan agreement and disbursement letter are an eligible expenditure.

11. Ineligible expenditure. The following expenditure are treated as ineligible expenditure for

financing from the World Bank under this project:

i. Retention money/ security deposit retained (till the time it is not released);

ii. Expenditure incurred after the project closing date;

iii. Expenditure not in line with project description in legal agreement;

iv. Procurement not in line with agreed procurement procedures;

v. Land costs and expenditure on R&R;

vi. Expenses disallowed by auditors and not resolved adequately;

vii. Expenses found ineligible during Bank review;

12. Disclosure. Under the Access to Information Policy of the Bank, the annual project audit

report and the audited Project Financial Statements (PFS) will be disclosed in the Bank's website.

Disbursements

IBRD funds will be disbursed using reimbursement method, based on expenditure reported in the

quarterly IUFRs. The other methods of disbursement available under the project shall be:

13 As on date, there are no overdue audit reports from the implementing agency (POWERGRID).

Page 44: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

34

advance payment and direct payment. Supporting documents required for Bank disbursement

using these various methods are documented in the Disbursement Letter issued by the Bank.

Procurement

13. Procurement for the proposed project will be carried out in accordance with the World

Bank’s "Guidelines: Procurement of Goods, Works and Non-Consulting Services under IBRD

Loans and IDA Credits and Grants by World Bank Borrowers" dated January 2011 revised July

2014 (Procurement Guidelines); and "Guidelines: Selection and Employment of Consultants

under IBRD Loans and IDA Credits and Grants by World Bank Borrowers" dated January 2011

revised July 2014 (Consultant Guidelines) and the provisions stipulated in the Legal Agreement.

The project would be subject to the Bank’s Anti-Corruption Guidelines, dated October 15, 2006,

and revised January 2011.

14. E-procurement System. POWERGRID is going to use the e-procurement system for all

procurements to be carried out under the project. An assessment of the e-procurement system

being used by POWERGRID [supported by TCIL ltd] was carried out as per the Multilateral

Development Banks (MDB) requirements and the system is acceptable. For any ICB

procurements, POWERGRID has to ensure that foreign bidders are not required to travel to India

for getting the Digital Signature to participate in bidding, by providing assistance to them. The

assessment was carried out as part of the ongoing PSDP-V project.

15. The following major procurements are envisaged under the Project:

a. Procurement of Works: The works envisaged to be procured under the project are still to

be identified.

b. Procurement of Goods: “Procurement of Goods” includes intra-state transmission for

evacuating the power generated from the identified solar parks (funded under the Bank

funded solar parks project), which would be carried out based on using “Procurement of

Plant Design, Supply and Installation” basis. Further Goods would also be procured

under “Procurement of Plant Design, Supply and Plant Design, Supply and Installation”

contracts following ICB and NCB procedures of the Bank using the Bank’s Standard

Bidding Documents (SBD) as a base and as agreed with the Bank.

The Bank’s SBD for “Procurement of Goods, March 2013” and the Bank’s SBD for

“Procurement of Plant Design, Supply and Installation, April 2015 version. The

provisions of paragraphs 2.55 and 2.56 of the Procurement Guidelines, providing for

domestic preference in the evaluation of bids, shall apply to only goods manufactured in

the territory of the borrower.

Other goods including IT equipment and software will be procured following ICB, NCB,

shopping methods and having framework agreements. Framework Agreements using

DGS&D rate contracts can be used to procure goods up to NCB threshold subject to

incorporation of right to audit and fraud & Corruption clauses. The Standard Bidding

Page 45: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

35

documents of the Bank as agreed with Government of India task force (as amended from

time to time) for goods and works procurement under NCB will be used.

c. Selection of Consultants: The consultancies needed are still to be identified and the

selection / hiring of such consultancies shall follow the Bank Guidelines.

The full details of the procurements to be carried out under the project would be finalized during

appraisal and will be disclosed in the Procurement plan.

Procurement capacity and Risk Assessment of implementing agencies

16. Procurement Risk Assessment: POWERGRID would be responsible for undertaking all

procurements and contract management activities under the project.

The Procurement Risk Assessment and Management System (PRAMS) is presently being

undertaken and would be finalized during appraisal. POWERGRID has staff with expertise in

procurement and contract management in conducting procurement in accordance with Bank

policies and procedures, having successfully handled procurement activities under Bank funded

projects. Hence, the procurement risk rating is rated as “LOW”.

17. Record Keeping. All records pertaining to award of tenders, including bid notification,

register pertaining to sale and receipt of bids, bid opening minutes, Bid Evaluation Reports and

all correspondence pertaining to bid evaluation, communication sent to/ with the World Bank in

the process, bid securities, approval of invitation/evaluation of bids by POWERGRID would be

retained by POWERGRID.

18. Procurement Plan. For contracts to be financed by the Bank, the different procurement

methods or consultant selection methods, the need for prequalification, estimated costs, prior

review requirements, and time-frame are agreed between the Borrower and the Bank in the

procurement plan.

19. Procurement Plan and Readiness. The draft procurement plan for procurements to be

taken up under of project implementation is being finalized and is enclosed as Annex 3. The

Procurement plan would be prepared using the Bank system “STEP”. The procurement plan will

be updated using the system at least annually or as required to reflect the actual project

implementation needs and improvements in institutional capacity.

20. Disclosure of Procurement Information. The following documents shall be disclosed on

the POWERGRID website: (i) procurement plan and updates; (ii) invitation for bids for goods

and works for all ICB, NCB and shopping contracts; (iii) request for expression of interest for

selection/hiring of consulting services; (iv) contract awards of goods and works procured

following ICB/NCB procedures; (v) list of contracts/purchase orders placed following shopping

procedure on quarterly basis; (vi) list of contracts following DC on a quarterly basis; (ix)

monthly financial and physical progress report of all contracts; and (x) action taken report on the

complaints received on a quarterly basis.

Page 46: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

36

21. The following details shall be sent to the Bank for publishing in the UNDB and World

Bank external website: (a) invitation for bids for procurement of goods and works using ICB

procedures, (b) contract award details of all procurement of goods and works using ICB

procedure, and (c) list of contracts/purchase orders placed following DC procedures on a

quarterly basis.

22. Further POWERGRID/ State Utilities will also publish on their websites, any information

required under the provisions of “suo moto” disclosure as specified by the Right to Information

Act.

23. Review by Bank: All contracts not covered under prior review by the Bank will be subject

to post review during Implementation Support Missions and/or special post review missions

including missions by consultant hired by the Bank. For the avoidance of doubts, Bank may

conduct, at any time, Independent Procurement Review (IPRs) of all the contracts financed under

the loan.

24. Frequency of Procurement Supervision. Two missions in a year each at an interval of six

months are envisaged for procurement supervision of the proposed project.

25. Contract Management. A fully staffed PIU (POWERGRID) will be responsible for

overall project/ contract management. The team will be ably assisted by a multi-skilled project

management team, engaged to provide overall implementation support and monitor all works

and consultancy contracts.

.

Page 47: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

37

Draft Procurement Plan

I. General

1. Project Information

Country : India

Borrower : Government of India

Project Name : Transmission for Power Evacuation for Solar Parks

Loan Credit No. :

2. Bank’s Approval Date of the Procurement Plan :

3. Date of General Procurement Notice : Dec 2015

4. Period Covered by this procurement plan : 24 Months

II. Goods, Works and Non consulting Services

1. Thresholds for method of Procurement:

Method of Procurement Thresholds for Method (USD equivalent)

ICB (Goods) > 3 million

NCB ( Goods) > USD 100,000 and up to USD 3 million

Shopping (Goods) Up to USD 100,000

ICB (Supply & Installation) > 40 million

NCB (Supply & Installation) > 100,000 and up to USD 40 million

ICB (Non-Consulting Services) > 1 million

NCB (Non-Consulting Services) < 1 million

Direct Contracting No Threshold; meet paragraph 3.7 of

Guidelines

Prior Review Thresholds:

(a) For the purpose of clearance of the bidding documents, the value of each slice will be

considered:

If the estimated value of any slice of a package is more than US$ 25 million, the bidding

document for the entire package will be prior reviewed.

If the estimated value of each slice is less than US$ 25 million, but the combined value of

all the slices is more than US$ 25 million, the bidding documents will not be prior

reviewed. However, one sample bidding document will be agreed with the Bank for each

type of package and the bidding documents, including those under post review, will be

Page 48: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

38

prepared as per this agreed sample. The clauses which will need modifications will also be

agreed with the Bank.

(b) For the purpose of clearance of the recommendation for award, the following will considered:

If the estimated value of any of the slices in the package is US$ 25 million or more, the

entire package will be subject to prior review.

If the estimated value of each slice is less than US$ 25 million but the value of complete

package is US$ 25 million or more, the award recommendation and the evaluation report

for the complete package of all the slices will be subject to prior review. For this purpose,

POWERGRID will forward a set of complete bidding documents and the evaluation report

to the Bank for prior review.

The Prior Review Thresholds will be reviewed and updated during the implementation of

the project and modified, based on the risk assessment.

In the case of contracts subject to prior review, before granting / agreeing to (a) a material

extension of the stipulated time for performance of a contract; or (b) any substantial modification

or waiver of the scope of services or other significant changes to the terms and conditions of such

that the contract, including issuing; or (c) any change variation order or orders under such contract

amendment (except in cases of extreme urgency) which would in aggregate, singly or combined

with all variation orders or amendments previously issued, increase the original contract amount

of the contract by more than 15% (fifteen percent); or (d) the proposed termination of the original

price contract, the Borrower shall seek the Bank’s no objection to the proposed extension,

modification, or change order.

A copy of all amendments to the contract shall be furnished to the Bank for its record.

2. Prequalification

Not Applicable

3. Domestic Preference: The provisions of paragraphs 2.55 and 2.56 of the Procurement

Guidelines, providing for domestic preference in the evaluation of bids is applicable.

4. Reference to Project operational/Procurement Manual

Standard Bidding Documents agreed between Project and Bank will be used for all

Supply & Installation, consultancy, Works and goods procurements.

5. Any Other Special Procurement Arrangements:

National Competitive Bidding (NCB) method for procurement and goods and works as per the

above value thresholds will be conducted in accordance with paragraph 3.3 and 3.4 of the World

Bank Procurement Guidelines and the following provisions: a. Only the model bidding documents for NCB agreed with the GoI Task Force (and as

amended for time to time), shall be used for bidding;

b. Invitations to bid shall be advertised in at least one widely circulated national daily

newspaper (or on a widely used website or electronic portal with free national and

Page 49: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

39

international access along with an abridged version of the said advertisement published

in a widely circulated national daily inter-alia giving the website/electronic portal details

from which the details of the invitation to bid can be downloaded), at least 30 days prior

to the deadline for the submission of bids;

c. No special preferences will be accorded to any bidder either for price or for other terms

and conditions when competing with foreign bidders, state owned enterprises, small

scale enterprises or enterprises from any given state;

d. Extension of bid validity shall not be allowed with reference to Contracts subject to

Bank prior review without the prior concurrence of the Bank (i) for the first request for

extension if it is longer than four weeks; and (ii) for all subsequent requests for extension

irrespective of the period (such concurrence will be considered by Bank only in cases

of Force Majeure and circumstances beyond the control of the Purchaser/ Employer).

e. Re-bidding shall not be carried out with reference to Contracts subject to Bank prior

review without the prior concurrence of the Bank. The system of rejecting bids outside

a pre-determined margin or “bracket” of prices shall not be used in the project;

f. Rate contracts entered into by Directorate General of Supplies and Disposals will not be

acceptable as a substitute for NCB procedures unless incorporation of right to audit and

Fraud & Corruption clauses. DGS&D contracts will be acceptable however for any

procurement under the Shopping procedures.

g. Two or three envelope system will not be used (except when using e-Procurement

system assessed and agreed by the Bank);

h. No negotiations are conducted even with the lowest evaluated responsive bidders.

6. The bid evaluation will be carried out as per agreed timeline in the Procurement Activity

Schedule

Page 50: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

40

Summary of the Procurement Packages planned during the first 24 months after project

effectiveness (including those that are subject to retroactive financing and advance procurement):

Goods/ Works:

Sr

No

Description Estimated

to Cost

(INR

Million)

Est

cost

USD

million

Method of

Procurement

Post /

Prior

Expected

Date of Bid

Opening

Expected

Date of

Contract

Page 51: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

41

III. Selection of Consultants

1. Prior Review Threshold

Method of Procurement Threshold (USD

Equivalent) Prior Review Threshold

(a) Quality and Cost Based

Selection No threshold First 1consultancy contract and

subsequently all other contracts

above USD 2.0 million (b) Quality Based Selection No threshold

(c) Selection Made Under a

Fixed Budget No threshold

(d) Least Cost Selection No threshold

(e) Selection Based on

Consultant’s Qualifications < 300,000

(f) Single Source Selection of

firms As per Consultant

Guidelines Para 3.9 All contracts above USD

50,000

(g) Selection of Individual

Consultants No threshold All contracts above USD

500,000. In case of contract to

individuals, the qualifications,

experience, terms of reference

and terms of employment shall

be subject to prior review

Note: The Prior Review Thresholds will be reviewed during the implementation of the

project and modified.

In the case of contracts subject to prior review, before agreeing to: (a) an extension of the

stipulated time for performance of a contract; (b) any substantial modification of the scope

of services, substitutions of key experts, or other significant changes to the terms and

conditions of the contract; or (c) the proposed termination of the contract, the Borrower

shall seek the Bank’s no objection. A copy of all amendments to the contract shall be

furnished to the Bank for its record.

2. Short List comprising entirely of national consultants: Short list of consultants for services,

estimated to cost less than USD 800,000 equivalent per contract, may comprise entirely of

national consultants in accordance with the provisions of paragraph 2.7 of the Consultant

Guidelines.

3. The Request for Expression of Interest for consultancy services estimated to cost above

USD 300,000 equivalent per contract for firms shall be advertised in UNDB online and

World Bank external Website and in accordance with other provisions of Para 2.5 of the

Consultant Guidelines

Page 52: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

42

4. Any other Special Selection Arrangements: [including advance procurement and

retroactive financing, if applicable]

5. Consultancy Assignments with Selection Methods and Time Schedule:

No 1 2 3 4 5 6 7 8

Ref No Description Of

Assignment

Estimated

Cost

(Million

US$)

Selection

Method

Review

by Bank

(Prior

/Post)

Expected

Proposals

Submission

Date

Expected

Contract

Award

Date

Comments

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

Environmental and Social (including safeguards)

Page 53: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

43

Annex 4: Implementation Support Plan

Strategy and Approach for Implementation Support

I. The strategy for implementation support has been developed based on the nature of

activities involved in the project and their commensurate risk profile in accordance with

the SORT. The Implementation Support Plan (ISP), as described below, will be a live

document and will be reviewed regularly and revised, as and when required during the

implementation.

II. Technical Support.

III. Procurement.

IV. Financial management.

V. Environmental and Social Safeguards.

Implementation Support Plan

1. Most of the Bank team members will be based in the India country office, (Task Team

Leader is based out of DC office), technical, procurement, financial management, and safeguards

specialists, which would facilitate timely, efficient, and effective implementation support to the

client.

2. Project implementation and supervision will be conducted through:

Project launch, to be conducted soon after the project approval, to bring all project

functionaries together and ensure a clear understanding of the project scope,

design, process and responsibilities;

At least two regular supervision missions in a year during the project duration;

Intermediate technical missions by specialists, as needed;

Quarterly implementation progress reports (physical and financial progress)

prepared by the project PPIU;

A Mid Term Review (MTR) once the project is around half way in project

implementation/ loan tenure to review the progress and assess the need for any

mid-course correction and

An Implementation Completion and Results (ICR) report at the end of the project

to assess achievement towards PDO and lessons.

3. The main focus of implementation support is summarized below:

Time Focus Skills Needed Resource

Estimate

Partner

Role

First twelve

months

Investment Component

A: Fiduciary and

Safeguards, Preparation

and implementation of

contracts as per schedule

Technical

Specialist

Procurement

Specialist

Environment

Specialist

XX SW

XX SW

XX SW

XX SW

Page 54: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

44

Time Focus Skills Needed Resource

Estimate

Partner

Role

Institutional

Strengthening

Component B

Social

Development

Specialist

Financial

Management

Specialist

Institutional

Development

Specialist

Task Team Leader

XX SW

XX SW

XX SW

12-84

months

Implementation of

Investment Component A

Implementation of

Institutional

Strengthening

Component B

Technical

Specialist

Procurement

Specialist

Environment

Specialist

Social

Development

Specialist

Financial

Management

Specialist

Institutional

Development

Specialist

Task Team Leader

XX SW

XX SW

XX SW

XX SW

XX SW

XX SW

XX SW

4. The skills mix required is:

Skills Needed Number of Staff

Weeks

Number of Trips

(Annually)

Comments

Technical Specialist XX SWs first year and

then XX SWs annually

XX

Institutional Development

Specialist

XX SWs every year XX

Procurement Specialist XX SWs first year and

then XX SWs annually

XX Country Based

Page 55: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

45

Financial Management Specialist XX SWs first year and

then XX SWs annually

XX Country Based

Environment Specialist XX SWs every year XX Country Based

Social Specialist XX SWs every year XX Country Based

Communications Specialist XX SWs every year XX Country Based

Task Team Leader XX SWs every year XX

Page 56: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

46

Annex 5: Economic Analysis

1. This annex discusses the rationale for public financing of the project, the valued added

from the Bank support and presents the analysis of the project’s development impact in terms of

expected benefits and costs. Since the transmission and shared infrastructure investments (that are

funded by the World Bank through two related projects) cannot have an economic return

independent of the solar PV generation investments, the economic analysis covers the entire

package of solar park investments of the Pavagada Solar Park in the state of Karnataka14. This

economic analysis is consistent with the new Bank guidelines in Operational Policy and Bank

Procedure (OP/BP) 10.00, Investment Project Financing and Social Value of Carbon in Project

Appraisal.

Rationale for public sector provision/financing

2. The Government of India has announced a bold target of installing 100GW of solar power

capacity by 2022 – a thirty fold increase from 3.7GW in 2015. The push in solar energy underpins

GoI’s Power for All program to supply 24x7 electricity to residential, commercial and industrial

consumer by 2019 and is a key part of its efforts to reduce environmental pollution and greenhouse

gas emissions. There is a need to significantly scale up of both private and public investments to

meet GoI’s solar power targets. In particular, there is a strong justification for the use public

financing to on the following grounds:

Public financing can be used to provide services where the public sector has an advantage

such as land acquisition, obtaining necessary permits, providing common infrastructure

and interconnections from the solar park to the state and national grid. This helps remove

or reduce the private sector’s risk perception about solar power and increase the

availability of private investment and financing for solar power.

Public support and financing for solar parks infrastructure is also necessary reduce the

financial costs of solar power and to enable it to be competitive with thermal generation –

so that the full externalities of solar power through avoided environmental and health

damage costs can be captured.

Value added of the Bank’s support

3. GoI has requested Bank support for solar power at the highest levels15. India’s push in solar

power will increase the share of renewable energy in India’s electricity generation mix and aid

efforts to increase electricity access and meet the growing demand in the country. However, since

solar power is intermittent energy source, this transition will have to be managed carefully and

efficiently to be successful. The World Bank Group can play a valuable role in this transition by

14 The Pavagada Solar Park has been selected because it is the most advanced in design amongst the solar parks that

Bank has been asked to finance as part of MNRE 20GW Solar Park Scheme. 15 During their July 2014 and January 2015 meetings, Prime Minister Narendra Modi and President Jim Kim had

agreed that the Bank would provide financing for Solar Parks in the country

Page 57: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

47

(i) making long term concessional financing available for development of solar power;

(ii) sharing international knowledge and experience on how utility scale solar parks have

been implemented across the world; and

(iii) providing technical assistance and capacity building support to key stakeholders

.

Pavagada Solar Park in India’s Generation Mix

4. Assessment of the impact of a new generation source (in this case the solar park) is carried

out jointly by the State Transmission Utility (KSTCL), the Central Transmission Utility

(POWERGRID) and the Central Electricity Agency. These assessments help determine the

required investments in transmission evacuation arrangements, future generation planning as well

as any measures and investments that may be needed to manage the generation from the solar park.

5. For the Pavagada Solar Park, the implementing agency, Karnataka Solar Power

Corporation Development Limited has filed a Long Term Access Application with POWERGRID.

The LTA application indicates that up to 90% of the electricity from the park will be utilized inside

the state, with the remaining power evacuated to consumers outside the state. Based on the LTA

application, POWERGRID, STU and CEA have carried out assessments of the impact of the solar

park on the grid and generation mix. These studies will be made available to the Bank once they

have been presented at the meeting of the Standing Committee on Power System Planning in the

Southern Region in the third week of November 2015.In absence of these studies, this economic

analysis uses generation from imported coal (which is the marginal electricity generation source

for India) as the counter factual to the generation from the Pavagada solar park.

The Project and its Rationale

6. An estimated 300 million people are not connected to the national electrical grid in India

and those who are, face frequent disruptions. Power shortages in FY2015 were equivalent to about

3.6% of total energy and 4.7% of peak capacity requirements. To meet the power demand,

industrial establishments and manufacturers have been relying on diesel-based back-up power

supplies, which are significantly more expensive than grid-based electricity. Coal currently fuels

two thirds of India’s electricity generation. To avoid the global and local environmental damage

costs associated with thermal generation, the Government of India (GoI) wants to install 100GW

of solar power by 2022.The proposed project is a key part of GoI’s solar park scheme to install

20GW of utility scale solar power by 2020 and will help in meeting the rapidly growing electricity

demand in an environmentally sustainable way/.

Cost Benefit Analysis of the Pavagada Solar Park

7. The economic viability of the project was assessed through a cost-benefit analysis. Net

benefits for the Pavagada Solar Park was calculated by comparing total system costs and benefits

for the “with project” and “without project” scenario. A range of scenarios and sensitivities that

meaningfully reflect the uncertainties of key input variables are evaluated. The analysis includes

a consideration of the relevant environmental and social externalities. Monte Carlo simulation,

Page 58: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

48

which assumes input assumptions are defined as probability distributions rather than as single “best

estimates”, is used to analyze the possibility of more than one input assumption combines

unfavorably.

Project costs

Capital costs

8. The total project (financial) cost excluding price contingencies and interest during

construction is $1.9 billion (Table 1). This includes $87 million of shared infrastructure costs, $164

million of transmission costs and $1.7 billion of PV generation capital cost. The 2014 Central

Electricity Regulatory Commissions (CERCs) benchmark capital cost for Solar PV is used as the

basis for solar generation costs; a reduction of 10% per year is assumed through to 2017 when the

actual investments are projected to take place. Subtracting taxes and duties from the base cost, one

obtains an economic cost of $1.6 billion.

Table 1 – Total project cost

Base Cost ($ Million) Taxes and Duties ($

Million)

Economic Cost ($

Million)

Shared Infrastructure 87 22 65

Transmission 164 41 123

PV Generation 1668 278 1390

1918 340.75 1578

Operating and Maintenance costs

9. The operation and maintenance (O&M) costs are estimated as 1% of the capital costs,

which computes to $14 million per year.

Grid integration costs

10. Since the grid is not designed to manage intermittent sources of generation, solar power

can impose additional coping costs on the grid. These include but are not limited to (i) the

requirements of connecting generation far away sources to load centers through transmission lines;

(ii) additional operation and maintenance costs of thermal plants if they have to operate at lower

load factors that would otherwise be the case; (iii) the need for standby generation to provide power

when there is no sunshine. It is generally agreed that these cost are negligible or very low at lower

levels of penetration of variable renewable energy. This economic analysis zero value for grid

integration cost in the base case but then uses sensitivity analysis to calculate the impact of grid

integration costs on the

Project benefits

Page 59: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

49

Fuel costs of the thermal counterfactual using coal

11. Avoided fuel costs of thermal counterfactual (which is assumed to be coal in this economic

analysis) constitutes one of the main economic benefits associated with solar power generation.

These avoided costs are calculated based on the coal supply requirements of producing electricity

equivalent to those produced from the Pavagada solar park. A capacity utilization factor of 19% is

used the solar park based on the analysis that has been carried out in the Detailed Project Report

of the solar park. The coal is valued at import price of coal from Australia, which is higher than

the domestic price of coal in Australia.

Capacity credit of the solar park

12. A capacity credit equal to the forecast capacity factor of the solar park (19%) is used in the

base case of the economic analysis. Sensitivity analysis is then used to analyze the impact of the

capacity credit on the economic returns of the project.

Avoided global environmental damage cost

13. Avoided global externalities constitute another economic benefit of the Pavagada Solar

Park, given that solar power replaces coal generation. Emissions of coal based generation displaced

by the solar park estimated are using a emission factor of 830 tonnes/Gwh. Consistent with Bank

guidance on the social value of carbon, carbon emission reductions are valued in the base case at

US$30 in 2015 and increasing to US$80 in real terms by 2050. The low ($15 in 2015 increasing

to $50 in 2050) and the high paths ($50 in 2015 increasing to $150 in 2050) for the social value of

carbon suggested in the Bank guidance are used for sensitivity analysis.

Avoided local environmental damage costs

14. The emission factors and per unit damage costs for So2, Nox, and PM for coal generation

plants in India from Cropper et al. (2012)16 are used to compute the avoided local environmental

damage costs of having the Solar Park (Table 2).

Table 2 – Emission Factor and Damage Costs

Units Nox PM10 SO2

Emission Factor,

coal

g/kwh 2.09 0.227 1.44

Damage costs,

coal

USc/kwh 0.21 0.06 0.63

Non Quantified Benefits

16 Cropper, M., S. Gamkhar, K. Malik, A Limonov, and I Partridge, The Health Effects of Coal Electricity

Generation in India, Resources for the Future, June 2012

Page 60: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

50

15. The proposed Solar Park is also expected to have a number of additional benefits which

are either uncertain or difficult to quantify such as (i) energy security (ii) macroeconomic benefits

through the development solar manufacturing industries; (iii) employment generation; (iv)

learning and economy of scale benefits which can help facilitate further reductions in cost of PV.

These benefits have not been included in this economic analysis.

Economic analysis

Assumptions

16. In addition to the costs and benefits noted in the previous section, the economic analysis

rests on the following additional assumptions:

Discount rate for calculation of NPV: 12%, which is the rate used by past Bank financed

power sector projects in India and is consistent with Bank guidance on this topic17.

Project cost phasing: as follows:

2016 2017

Shared Infrastructure 40% 60%

Transmission 40% 60%

PV Generation 100%

First year of operation: 2018

Results

17. The economic analysis indicates that in India utility scale solar power is increasingly

competitive with thermal generation using imported coal. The baseline economic return of

Pavagada Solar Park against the “without solar park scenario” is 7% (NPV –US$ 386 million),

which is below the 12% hurdle rate used for Bank projects (see Table 3). However, the solar park

has substantial local and global environmental benefits and consideration of these benefits

increases the ERR of the solar park significantly. The inclusion of avoided damage costs of local

pollution in the economic flows, increases the ERR to 10% (NPV -US$163 million). The inclusion

of avoided global environmental damage costs (using the Bank guidance on social value of

carbon), increases the ERR to 18% (NPV $ 545 million).

Table 3 – Summary of Economic Analysis

Economic rate of return Unit Values

ERR % 7%

17 The World Bank is presently formulating new guidance note for the choice of discount rate. If the guidance is

available before project appraisal, the economic analysis will we revised accordingly.

Page 61: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

51

ERR + local externalities % 10%

ERR + local externalities + GHG % 18%

Switching value, avoided GHG emission $ /ton $6

Composition of NPV

Cost of Solar Park

capital cost $USm 1265

O&M $USm 31

Benefits of avoided coal generation

Avoided coal costs $USm 824

Capacity credit $USm 86

NPV (before environmental benefits) $USm -386

local environmental benefits $USm 223

GHG emissions @$30/ton $USm 708

NPV (including environment) $USm 545

Lifetime GHG emissions undiscounted

Mtons

CO2

69

Marginal abatement cost MAC $/ton 5.6

18. Reduction in GHG emissions. The analysis indicates that the solar park will reduce GHG

emissions by 69 million tons over the life of project compared to the thermal counterfactual. The

marginal abatement cost of GHG emission for the Solar Park is $5.6/ton. The Solar Park will help

avoid local and environmental damage costs equal to $931 million compared with the thermal

counterfactual.

19. Sensitivity Analysis. The sensitivity analysis in Table 4 calculates the switching values

for the important variables such as capital costs, Capacity Utilization Factor, PV generation capital

costs, coal prices, capacity credit and discount rate.

Table 4 – Switching Values

Input Unit Baseline Value Switching Value

Project Cost $ Million 1296 910

CUF % 19% 27%

PV Cost $M/MW 1.06 0.70

Annual Increase Coal

Prices % 0% 5%

Discount Rate % 12% 7%

Capacity Credit % 19% 103%

Grid Integration Costs % 0 -2.70%

Project cost overrun

factor Ratio 1 0.7

Page 62: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

52

20. Sensitivity analysis using the low case (increasing from $15 per ton in 2015 to $50 in 2050)

and high case (increasing from $50 per ton in 2015 to 150 in 2050) social values of carbon

recommended by Bank guidance impacts the returns of the project significantly. There is 8%

percent difference between the ERRs for low case and high case social value of carbon (Table 4).

This suggests that the climate change and local pollution impacts are an important deciding factor

in whether or not to go ahead with this project.

Table 4 – Sensitivity on Social Value of

Carbon

Social Value of

Carbon

EIRR NPV

Low Case 412 14%

Base Case 751 18%

High Case 1233 23%

Page 63: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

53

ANNEX 6: CLEAN TECHNOLOGY FUND (CTF) ANNEX

India: Shared Infrastructure for Solar Parks &

Transmission for Power Evacuation from Solar Parks18

Key Indicators CTF/World Bank-funded

Project

Scaled-up Phase: Solar Park

Scheme of the Ministry of New and

Renewable Energy (MNRE) by

202019

Installed solar PV

generation capacity in

supported solar parks

(MW)

3,500 MW 22,050 MW

Tons of GHG emissions

reduced or avoided

- Tons per year

[mtCO2eq/yr]

- Tons over lifetime

[mtCO2eq / 25 years]20

4.8

120.2

30.3

757.5

Financing leveraged

through CTF financing

(US$ million)

US$ 4,420 million

- US$ 420 million by IBRD

US$ 150 million for shared

infrastructure

US$ 270 million for

transmission

- US$ 500 million by the

Government of India (GoI)

and state governments

US$ 200 million for shared

infrastructure

US$ 300 million for

transmission

- US$ 3,500 million by private

and public sector for

generation capacity in the solar

parks

US$ 28.2 billion

- US$ 420 million by IBRD

- US$ 5.8 billion by GoI and

state governments

- US$ 22 billion by private and

public sector for generation

capacity in the solar parks

CTF leverage ratio 1 : 55.3 1 : 352.8

18 This CTF Annex presents two World Bank-funded projects: i) Shared Infrastructure for Solar Parks; and ii)

Transmission for Power Evacuation from Solar Parks. The results indicated in this Annex will be achieved by

implementing two projects together. 19 The Scaled-up Phase assumes that the proposed CTF-funded Project contributes to the achievement of the ‘solar

park scheme’ launched by the Ministry of New and Renewable Energy (MNRE) to facilitate the development of

utility scale solar power in India. The scheme will install utility scale grid-connected solar parks by 2020, with a

targeted, collective installed capacity of 20GW. 20 The lifetime of solar PV generation facilities was hereby assumed at 25 years.

Page 64: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

54

Cost effectiveness

- CTF cost effectiveness

[$CTF/tCO2eq avoided

over lifetime]

- Total project cost

effectiveness [$Total Project

/tCO2eq avoided over

lifetime]

0.67

37.42

0.11

37.36

Other co-benefits - Support in meeting the electricity demand and contribute to the

universal access agenda.

- Increased opportunities of local employment.

- Contribute to cost reduction in solar PV technologies.

- Environmental co-benefit: reduced local air pollution of 74.8 kt of

NOx, 51.5 kt of SOx and 8.1 kt of PM10 per annum after the Scaled-

up Phase.

- Gender co-benefit: interventions to be designed to address gender

issues in the proposed solar park sites.

I. Introduction

Background: country and sector context

1. India’s power system needs to grow rapidly to fuel the country’s economic growth and

provide electricity to its growing population. During the last decade, India’s economy expanded

at an average annual rate of 7.6 percent; projections are for high rates of growth to continue. The

demand for power is expected to rise to support the growing manufacturing sector and meet the

rising aspirations of its people. Yet power quality is still poor and falls far short of demand. Power

shortages in FY2015 were equivalent to about 3.6% of total energy and 4.7% of peak capacity

requirements. An estimated 300 million people are still not connected to the national electrical

grid, and those that are connected face frequent disruptions. Private investment in diesel generators

as a coping mechanism against frequent power cuts is widespread, and estimates of installed diesel

generation capacity are as high as 70 GW. Furthermore, local environmental pollution is a major

issue in India. According to the World Health Organization, 13 of the 20 most polluted cities in

the world are in India. Renewable energy is increasingly seen as an important contributor to

meeting this energy demand in an environmentally sustainable way and to India’s energy security.

2. The Government of India (GoI) announced its intention to increase its target for solar

installed capacity from 20 to 100GW by 202221. The total installed grid-connected solar capacity

base of the country has reached 3.7 GW as of June 2015, from less than only 2 MW in 2009. The

Government would like to significantly increase the pace of solar power deployment to meet its

ambitious targets. The Government foresees that 60GW of the targeted installations will come

from utility-scale ground mounted solar power plants.

21 Government of India, 2015 (http://pib.nic.in/newsite/PrintRelease.aspx?relid=122566)

Page 65: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

55

3. The development of utility scale solar power on this scale in such a short time frame

presents significant challenges, including availability of land, permits and clearances, availability

of transmission and other infrastructure, capacity of sector institutions, and cost and variability of

solar power. To address these barriers, the GoI is developing large scale solar parks – concentrated

zones of development of solar power generation projects – which provide private sector developers

with dedicated land, evacuation infrastructure and other proper infrastructure. Two large solar

parks have been so far developed in Charanka (Gujarat) and Bhadla (Rajasthan).

4. The Ministry of New and Renewable Energy (MNRE) has launched ‘solar park scheme’

to facilitate the development of utility scale solar power in India. This scheme will use public

private partnership arrangements to set up 20 solar parks with a cumulative installed capacity of

about 60 GW of solar power by 2020. Within this total target of 60GW of ground-mounted solar

capacity in solar parks, about 20GW is expected to come from investments by Public Sector

Undertakings (PSUs) and 40GW from private investors. MNRE is providing Central Financial

Assistance (CFA) of up to 30% of the project costs or INR 2 million per MW for the solar parks.

This scheme internalizes the lessons of the Charanka and Bhadla solar parks in India as well utility

scale solar power developments in other parts of the World22. The scheme intends to attract

significant investments from project developers in the States to enable them to meet Renewable

Purchase Obligation (RPO) mandate and provide employment opportunities to local population to

the extent possible. It aims to reduce the number of approvals required by developers to set up

solar generation plants and hence attract private investments in such solar plants. The State will

also reduce its carbon footprint by avoiding emissions equivalent to the solar park’s installed

capacity and generation. Further, the State will also avoid procuring fossil fuels to run conventional

power plants. Under the scheme, a joint venture (JV) company comprising of the Solar Energy

Corporation of India (SECI), state utilities and in some cases the private sector is proposed to be

set up in each state to provide specialized services and to be the owner of the park and its shared

infrastructure, in order to incentivize solar power developers to invest in solar energy in the park.

India’s CTF Investment Plan

5. The CTF Investment Plan for India was originally endorsed in November 2011, and

subsequently revised in August 2015, with a total indicative allocation of USD 775.0 million of

CTF resources. The revised Investment plan aims to support GoI’s ambitious target of 100 GW of

solar installed capacity by 2022. The Plan includes the following proposed activities (Table 1).

Table 1 – Revised CTF Investment Plan of India, Indicative Financing Plan (US$ million)

CTF Project/Program MDB CTF financing

(US$ m)

22 The proposed project will draw on international experience with development of utility scale solar parks as well as

India’s experience with, and important lessons learned from other solar parks. In year 2009, Clinton Foundation

initiated work on large scale solar parks in South Africa, Australia, USA and India. It signed a MoU with Gujarat and

Rajasthan government in India to set up solar parks. Solar parks in Australia and USA did not move forward because

of the regulatory hurdles. Solar park in South Africa by ESKOM is under development. Gujarat (Charanka) solar park

has been commissioned and Rajasthan (Bhadla) solar park is under construction. Experience from the earlier solar

parks will be incorporated in the project during the preparation phase.

Page 66: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

56

Himachal Pradesh Environmentally Sustainable Development

Policy Loan (HP DPL)

World Bank 100

Partial Risk Sharing Facility for Energy Efficiency (PRSF) World Bank 25

Solar Park: Rajasthan ADB 200

Solar Parks Infrastructure World Bank 50

ADB 50

Solar Parks Transmission World Bank 30

ADB 50

Solar Rooftop PV World Bank 125

ADB 125

Solar PV Generation by Solar Energy Corporation of India (SECI) World Bank 20

Total 775

Project Description

6. The objective of the proposed Project is: (i) to increase solar generation capacity through

the establishment of utility-scale solar parks in India; and (ii) to evacuate power from the selected

solar power generation parks to the Inter-state Transmission System. This will contribute to the

achievement of GoI’s target of installing 100GW solar power by 2022.

7. The World Bank has prepared two projects to support the development of solar parks in

India. Under Shared Infrastructure for Solar Parks project, the World Bank will support for setting

up solar parks in four states – Karnataka, Madhya Pradesh, Andhra Pradesh and Telangana,

keeping the option open for other states to join if they are able to meet the necessary conditions. It

will cover financing for shared infrastructure such as security, access roads, water supply and

drainage, telecommunications, and pooling stations (with 220/66/33 kV or as may be suitable

switchyard and respective transformers) inside the solar parks and transmission lines connecting

these internal pooling stations to 400/220 kV substation. The project will also provide technical

assistance for capacity building of state nodal agencies and JVs across the participating States (see

page 7 of the PAD for Shared Infrastructure for more details).

8. Under Transmission for Power Evacuation from Solar Parks project, the World Bank will

support Tumkur (Karnataka) solar park and Rewa (Madhya Pradesh) solar park that are in

advanced stages, along with other solar parks under the scheme in the states of Karnataka, Madhya

Pradesh and Telangana, which will be finalized upon obtaining approval from Central Electricity

Authority (CEA) and/or Standing Committee on Power System Planning. This project will finance

the establishment of 400/220 kV transmission substations at the park boundary and the linked

transmission lines up to the existing transmission network (see page 8 of the PAD for Transmission

for more details).

9. This proposed Project will mobilize US$ 1,000 million, including US$ 420 million from

IBRD, US$ 80 million from CTF and US$ 500 million from the GoI and state governments. The

solar parks supported by the Project are expected to mobilize additional US$ 3,500 million of

private and public sector financing for solar PV generation capacity. The CTF funding would

comprise US$ 78 million to be extended under softer concessional terms and US$ 2 million to be

extended in the form of a grant.

Page 67: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

57

10. Among the aforementioned US$ 1,000 million, US$ 400 million in total, a sum of US$ 150

million from IBRD, US$ 50 million from CTF and US$ 200 million from public sector will support

Shared Infrastructure for Solar Parks, while the rest US$ 600 million will finance Transmission

for Power Evacuation from Solar Parks.

II. Assessment of the Proposed Project with CTF Investment Criteria

Potential for GHG Emission Savings

11. Emission reduction potential of investment. The total emission reduction potential was

estimated at 120.2 million tonnes of CO2 equivalent over the lifetime of solar PV power generation

facilities within the supported solar parks, hereby assumed 25 years. These estimates were based

on the installation of 3,500 MW of solar PV power generation capacity with 18.9 percent capacity

factor, displacing an equivalent of 5,795 GWh per year of “thermal-based” power in the baseline

scenario. The baseline scenario assumes “thermal-based power generation” using imported coal.

The emission factors under the baseline scenario was estimated at 830 kg/MWh23, which is more

conservative than the grid emission factor for India24. Using this emission factor, the CO2 savings

were estimated at 4.8 million tonnes of CO2 equivalent per year. Savings have been calculated in

accordance with CTF and World Bank guidelines25.

12. Technology development status. The utility-scale solar PV generation is already

technically proven and commercially viable. Over the past ten years, solar power has grown rapidly

driven by government policy and rapidly declining costs, propelling the solar industry into the

mainstream of energy policy. From 2009, the Jawaharlal Nehru National Solar Mission and state

policies, especially in Gujarat, Karnataka, Rajasthan, and Tamil Nadu helped bring down the cost

of generation. With the most recent bid of Rs 5.05/kWh for a utility-scale solar PV project in

Madhya Pradesh, solar costs have fallen over 70% from 2010 levels. Since India lies in the high

solar insolation region, declining cost trends in solar PV, along with innovations in energy storage

technology, offer exciting opportunities for India to address its challenges in the energy sector.

13. The key technical issue for the Project is the availability of a sound internal and external

evacuation system for solar parks. Based on Long Term Access (LTA) application from Tumkur

(Karnataka) solar park and Rewa (Madhya Pradesh) solar park, Power Grid Corporation India

Limited (POWERGRID) has carried out detailed grid evacuation and grid impact studies and

established augmentation/additions needed to the existing network so that the generation can be

absorbed without any adverse effect. These studies cover load flow analysis, reactive power flow

patterns, and measures and corrective actions to be implemented by the partners in the Grid. The

studies also assess the health of the consolidated system in case of outage of any network element

of the grid including solar park generation. The findings of these studies are presented in the

Standing Committee chaired by CEA, for deliberations and clearance.

23 830 kg/MWh for coal generation from supercritical plants 24 980 kg/MWh, from CO2 Baseline Database for the Indian Power Sector, Central Electricity Authority 25 World Bank, Guidance Manual: Greenhouse Gas Accounting for Energy Investment Operations, 2015

Page 68: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

58

Cost-effectiveness

14. The cost effectiveness is 0.67 US$/tCO2eq for CTF funding and 37.42 US$/tCO2eq

considering total funding for the Project. In the Scaled-up Phase, the cost effectiveness will

improve to 0.11 US$/tCO2eq for CTF funding and 37.36 US$/tCO2eq when considering total

funding.

15. Marginal abatement cost. In October 2013, the CTF Trust Fund Committee suggested

providing information on the estimated marginal abatement cost (MAC) for projects for which the

marginal abatement cost is likely to exceed US$100 per ton of CO2eq. This decision draws from

the CTF criteria which specifies that CTF co-financing will not be available for investments in

which the marginal cost of reducing a ton of CO2eq exceeds US$200, which reflects the lower-

end estimate of the incentive needed to achieve the objectives of the BLUE Map Scenario as

indicated in the International Energy Agency’s Energy Technology Perspectives 2008 Report.

16. The MAC of the proposed Project based on the economic analysis of the 2GW Pavagada

Solar Park is 5.6 US$/tCO2eq. These calculations confirm that the MAC will not exceed the

aforementioned US$100 threshold value per ton of CO2eq. The Project will help avoid local and

environmental damage costs equal to US$ 931 million compared to the thermal counterfactual (see

page 13 of either PAD for more details).

17. The marginal abatement cost is computed as the project’s NPV divided by lifetime CO2eq

(LCO2) avoided emissions:

2LCO

NPVMAC ,

where NPV stands for Net Present Value and LCO2 stands for Lifetime CO2eq emissions.

Demonstration Potential at Scale

18. Scope of avoided GHG emissions through replication. India’s ambitious target calls for the

installation of 60 GW of utility-scale ground mounted solar power plants by 2022. MNRE’s solar

park scheme aims at the development of utility scale grid-connected solar parks through public

private partnership arrangement with a cumulative installed capacity of about 20 GW of solar

power by 2020. The proposed Project will directly contribute towards these targets, therefore

contributing to significant emission reduction. It is expected that CTF and IBRD support on the

selected solar parks will create market confidence and will catalyze further support from other

investor groups for the GoI to help with achievement of its targets. The expected emission

reduction from achieving the Scaled-up Phase is estimated at 30.3 million tonnes of CO2

equivalent per year, or 757.5 million tonnes over the 25-year lifetime of technologies.

19. Transformation potential. The proposed Project has high transformational potential as it

will contribute to the accelerated development of utility-scale solar PV generation and the rapid

increase in the share of renewable energy in the power sector of India. Developing solar parks will

provide the enabling infrastructure for utility scale development of solar power, including common

Page 69: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

59

infrastructure such as large areas of land, power pooling sub-stations as well intra-park

transmission infrastructure, access roads, common security arrangements. This will facilitate

investment in solar power development by private or public sector developers, who may be able

to shorten the time from contract award to commissioning from 20 months to less than 10 months.

MNRE’s solar park scheme also aims to reduce the number of approvals required by developers

to set up solar generation plants and hence attract private investments in such solar plants. In fact,

there has been strong response to solar parks in Rajasthan and Andhra Pradesh that have recently

invited bids from the private sector. This trend is expected to continue for the solar parks that are

being developed inside the park, which will help solar parks make transformational impacts on the

power sector.

Development Impact

20. Support to bridge the supply gap of energy and contribute to the universal access

agenda. Power shortages in FY2015 were equivalent to about 3.6% of total energy and 4.7% of

peak capacity requirements. An estimated 300 million people are still not connected to the national

electrical grid, and those that are connected face frequent disruptions. Meeting the growing energy

demand of a rapidly growing economy while reducing air pollutants and carbon emissions through

solar energy is a top priority for GoI, particularly given the high costs of unserved electricity

demand in the country and growing energy imports. The development of solar energy will have

significant benefits in terms of the reliability and security of electricity supply to consumers. The

Project is also likely to have a significant indirect contribution to expansion of access to electricity,

as a result of the increased availability of electricity in all project states, wherein the investments

supported under the project are expected to lead to increased hours of supply to existing customers,

and increased availability of electricity supply, which may enable utilities to connect and serve

new customers.

21. Increased opportunities of local employment. The development of large scale solar parks

will attract significant investments from project developers which will generate employment

opportunities to local population. Local contractors, engaged through international competitive

bidding, will carry out the supply, installation and erection works. Joint ventures created under the

scheme will develop the capacity required to operate and maintain the assets created through this

Project, which would provide long-term employment opportunities.

22. Environmental Co-benefits. Currently, India relies on coal as the fuel source for two

thirds of its electricity requirements and is the world’s third largest carbon emitter. Private

investment in diesel-based back-up power supplies is widespread. The energy sector also causes

local environmental problems. The Project has substantial local environmental benefits. At local

level, air pollutant emissions under the thermal counterfactual are estimated at 74.8 kt of NOx, 51.5

kt of SOx and 8.1 kt of PM10 per annum, which will be reduced by displacing imported coal in

power generation with increased supply of electricity from the solar parks developed under the

Scaled-up Phase. The local and global environmental benefits of the 2GW Pavagada Solar Park

are estimated at US$ 931 million (see page 13 of either PAD for more details).

23. Gender Co-benefit. The Project is expected to bring positive gender co-benefits by

incorporating gender impacts of this intervention. Most of the women’s status indicators (including

Page 70: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

60

those pertaining to health, literacy, work force participation,) show that gender equity and

empowerment remain serious issues in the proposed solar park sites. As part of the Social

Management Framework (SMF), a Gender Development Framework and a Gender Action Plan

will be designed which will help to analyze gender issues and to design interventions to address

women’s needs. Gender analysis will be part of the social impact assessment.

Implementation Potential

24. The Project is aligned with GoI’s National Action Plan for Climate Change (NAPCC),

which was issued in 2008 to enhance India’s ecological sustainability and encourage sustainable

energy sources. It is also consistent with the Jawaharlal Nehru National Solar Mission (JNNSM)

that was launched in 2010 as part of NAPCC to promote the development of solar power in India.

GoI has significantly scaled up the target of 20 GW of solar power in JNNSM to 100 GW by 2022.

GoI has reiterated these commitments as part of its Intended Nationally Determined Contributions

(INDCs) commitment to achieve about 40 percent cumulative electric power installed capacity

from non-fossil fuel based energy resources by 2030.

25. There is strong ownership of the Project at the highest levels of GoI, MNRE, the

participating states, discoms and the JVs responsible for implementing this Project. This

commitment has been demonstrated through their intensive engagement and involvement during

the project preparation. As mentioned in the preceding sections, GoI and state governments are

pushing through with a number of policy and regulatory reforms, implementation mechanisms and

incentives to ensure that there costs of solar power are kept low and there is sufficient demand for

the offtake of solar power generated under the project. There has been strong responses from the

private sector to the bids to the solar parks that have been recently developed in Rajasthan and

Andhra Pradesh, which proves that solar park modality will continue to work. It will help ensure

the financial sustainability of the park.

26. POWERGRID’s involvement is a reasonable assurance that project design and

implementation will be of high standards. It has become a strong entity that is capable to ensure

that the investments are made well in time and are not left stranded. Over the past decade,

POWERGRID has acquired and developed skills required for successfully planning and

implementing large scale capital investment programs, through their its mandate to develop the

inter-state transmission network of India and also by acting as Consultant to some states to assist

them to plan, design and implement their transmission and distribution networks. All the schemes

envisaged under this operation are being designed, procured and implemented by POWERGRID.

Since POWERGRID owns, operates and maintains the National Grid, it in association with

POSOCO, takes all due measures required to ensure grid stability. In addition, environmental and

social issues will be handled with adequate expertise and attention, building on POWERGRID’s

implementation track record of earlier World Bank funded projects.

27. Leverage: The total investment of the Project would be funded through the CTF (US$ 80

million), IBRD (US$ 420 million), Central and State governments (US$ 500 million) and public

and private sector participation to solar PV generation facilities in the solar parks (US$ 3,500

million). The CTF leverage ratio will be 1 to 55.3. The CTF leverage ratio will increase to 352.8

when considering the Scaled-up Phase by 2020. The leverage effect is expected very high, as this

Page 71: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

61

proposed Project will effectively mobilize large amounts of investment in generation capacity by

utilizing public sector financing for the development of the required infrastructure which is a

relatively small portion of total investment but will reduce the risk of investment in generation

capacity.

CTF Additionality

28. The use of CTF concessional financing under the Project is essential to develop solar parks

that will enable large-scale deployment of solar PV generation in a short time frame. Solar parks

can effectively address a number of challenges in accelerating the scale-up of solar PV generation

capacity, which was committed by the GoI, but it requires public sector investment in transmission

and other shared infrastructures within the parks. Given the specific transmission requirements of

solar power and the risk of stranded assets, private sector investors continue to see the availability

of state of the art transmission infrastructure to connect their solar generation project to load

centers across the country, as a precondition to major investment decisions. By using concessional

financing for the investment, the GoI will be able to establish the required infrastructure with a

reduced cost of capital, which will be translated into a lower cost to private sector developers who

will invest in generation capacity within the solar parks.

29. The economic rate of return of the solar park is calculated at 7%, which is lower than the

hurdle rate of 12% (see page 12 of either PAD). This estimate is based on the baseline scenario

before taking into account environmental externalities and can be affected by a range of risk

factors. The use of CTF concessional financing to enable the establishment of transmission system

and shared infrastructure in the solar parks is hence essential for fully capturing the local and global

environmental benefits associated with this Project, which will raise the economic rate of return to

18% and make this Project economically viable.

Implementation Readiness

30. Among the long listed solar parks in Table 2, the two solar parks, Tumkur (Karnataka) and

Rewa (Madhya Pradesh), are in the most advanced stage, followed by Neemuch and Agar (Madhya

Pradesh). Based on Long Term Access (LTA) applications from two JVs of the first two solar

parks, POWERGRID had already carried out a detailed evacuation studies. Since all the solar parks

have not been finalized, investments under this Project will be taken up in a phased manner. The

Government of India is keen to move this proposed Project forward to help achieve its ambitious

target on solar generation capacity.

Table 2 –Planned Long List of Potential Solar Parks under MNRE Scheme

No State Location & capacity

1 Gujarat Banaskantha (700 MW)

2 Madhya Pradesh Rewa (750 MW)

Neemuch (435 MW)

Agar (315 MW)

3 Telangana Gattu, Mehboob Nagar (1000 MW)

4 Andhra Pradesh Anantpur (1500 MW)

Kurnool (1000 MW)

Page 72: The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL … · 2019-08-21 · the world bank for official use only project appraisal document (qer stage) on a proposed ibrd loan in

62

5 Karnataka Tumkur (2000 MW)

6 Uttar Pradesh Jalaun (370 MW)

Sonbhadra, Allahabad & Mirzapur (230 MW)

7 Meghalaya West & Esat Jayantia Hills (50 MW)

8 Jammu and Kashmir Leh & Kargil (7500 MW)

9 Punjab Patiala, Fatehgarh Sahib, Ludhiana & Gurdaspur (1000 MW)

10 Rajasthan Bhadla (1700 MW)

Jaisalmer (2000 MW)

11 Tamil Nadu Ramanathapuram (500 W)

12 Odisha Location not stated (1000 MW)

Total 22,050 MW


Recommended