+ All Categories
Home > Documents > The World Bank€¦ · PERUMKA Railway State Enterprise PERSERO State Owned Limited Liability...

The World Bank€¦ · PERUMKA Railway State Enterprise PERSERO State Owned Limited Liability...

Date post: 31-Jan-2021
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
49
Document of The World Bank FOR OFFICIAL USE ONLY Report No: 31719 IMPLEMENTATION COMPLETION REPORT (SCL-41060) ON A LOAN IN THE AMOUNT OF US$105.0 MILLION TO THE INDONESIA FOR A RAILWAY EFFICIENCY PROJECT June 29, 2005 Transport Sector Unit East Asia and Pacific Region This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized
Transcript
  • Document of The World Bank

    FOR OFFICIAL USE ONLY

    Report No: 31719

    IMPLEMENTATION COMPLETION REPORT(SCL-41060)

    ON A

    LOAN

    IN THE AMOUNT OF US$105.0 MILLION

    TO THE

    INDONESIA

    FOR A

    RAILWAY EFFICIENCY PROJECT

    June 29, 2005

    Transport Sector UnitEast Asia and Pacific Region

    This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization.

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

  • CURRENCY EQUIVALENTS

    (Exchange Rate Effective As of December 31, 2004)

    Currency Unit = Indonesian Rupiah (Rp) Rp 1 million = US$ 107.65

    US$ 1.00 = Rp 9,290

    FISCAL YEARJanuary 1 to December 31

    ABBREVIATIONS AND ACRONYMS

    Bank The World BankBoD Board of DirectorsBPKP Financial and Development Supervisory BoardCAS Country Assistance StrategyCWR Continuous Welded RailDaop Director of OperationsDGLC Directorate General of Land CommunicationsEIRR Economic Internal Rate of ReturnENPV Economic Net Present ValueGOI Government of IndonesiaIACC Inter Agency Coordination CommitteeICB International Competitive BiddingICR Implementation Completion ReportIMO Infrastructure Maintenance and OperationJABOTABEK Greater Jakarta Metropolitan RegionKA Type of rail clip fastenerMoC Ministry of CommunicationsMoF Ministry of FinanceMoSE Ministry of State EnterprisesN.A. Not ApplicableOED Operations Evaluation DepartmentPAP Project Affected PeoplePerjan Departmental AgencyPERUMKA Railway State EnterprisePERSERO State Owned Limited Liability Company (PT)PIU Project Implementation UnitPLN Indonesia's State-Run Electricity CompanyPMU Project Management UnitPSO Public Service ObligationPSP Private Sector ParticipationPT KA Railway PerseroREP Railway Efficiency ProjectREPELITA Indonesia National Five Year Development Plan

  • RTAP Railway Technical Assistance ProjectRTF Restructuring Task ForceSAR Staff Appraisal ReportTA Technical AssistanceTAC Track Access ChargesUIC Union Internationale de Chemins de fer

    Vice President: Jemal-ud-din Kassum, EAPVPCountry Director Andrew Steer, EACIFSector Manager Jitendra N. Bajpai, EASTR

    Task Team Leader/Task Manager: Edward Dotson, EASTR

  • INDONESIARailway Efficiency Project

    CONTENTS

    Page No.1. Project Data 12. Principal Performance Ratings 13. Assessment of Development Objective and Design, and of Quality at Entry 14. Achievement of Objective and Outputs 55. Major Factors Affecting Implementation and Outcome 96. Sustainability 137. Bank and Borrower Performance 148. Lessons Learned 179. Partner Comments 1810. Additional Information 30Annex 1. Key Performance Indicators/Log Frame Matrix 31Annex 2. Project Costs and Financing 32Annex 3. Economic Costs and Benefits 34Annex 4. Bank Inputs 39Annex 5. Ratings for Achievement of Objectives/Outputs of Components 41Annex 6. Ratings of Bank and Borrower Performance 42Annex 7. List of Supporting Documents 43

    Maps(s) IBRD 27873 and IBRD 27874

  • Project ID: P004026 Project Name: Railway Efficiency ProjectTeam Leader: Edward Dotson TL Unit: EASTRICR Type: Core ICR Report Date: June 29, 2005

    1. Project DataName: Railway Efficiency Project L/C/TF Number: SCL-41060

    Country/Department: INDONESIA Region: East Asia and Pacific Region

    Sector/subsector: Railways (100%)Theme: Other financial and private sector development (P)

    KEY DATES Original Revised/ActualPCD: 08/02/1994 Effective: 06/13/1997 06/13/1997

    Appraisal: 06/28/1996 MTR: 04/01/2000 06/30/2001Approval: 11/21/1996 Closing: 09/30/2002 12/30/2004

    Borrower/Implementing Agency: GOI/PTKAI/PERUMKAOther Partners:

    STAFF Current At AppraisalVice President: Jemal-ud-din Kassum Javad Khalilzadeh-Shirazi (Acting)Country Director: Andrew D. Steer Marianne HaugSector Manager: Jitendra N. Bajpai Anupam KhannaTeam Leader at ICR: Edward Dotson Joris Van der VenICR Primary Author: Baher El-Hifnawi

    2. Principal Performance Ratings

    (HS=Highly Satisfactory, S=Satisfactory, U=Unsatisfactory, HL=Highly Likely, L=Likely, UN=Unlikely, HUN=Highly Unlikely, HU=Highly Unsatisfactory, H=High, SU=Substantial, M=Modest, N=Negligible)

    Outcome: U

    Sustainability: UN

    Institutional Development Impact: SU

    Bank Performance: S

    Borrower Performance: U

    QAG (if available) ICRQuality at Entry: S

    Project at Risk at Any Time: Yes

    3. Assessment of Development Objective and Design, and of Quality at Entry

    3.1 Original Objective:

    The general development objective of the project was to improve the economic efficiency and service quality of the Borrower’s railway sub-sector. The more specific objectives were: (a) to carry out sub-sector policy reform by restructuring the Railway State Enterprise (Perumka), reforming the

  • relationship between it and the Government of Indonesia (GOI), and creating the foundations for expanded private participation; (b) to rationalize sub-sector capital investments; (c) to improve sub-sector management and operations; and (d) to increase the physical capacity of the Jakarta-Bandung corridor.

    Assessment of Objectives

    The development objectives reflected GOI’s increased focus on the railway sector and its strong desire to increase sub-sector efficiency. GOI’s commitment to the reforms started in the early nineties and resulted in the conversion of the railways from a dependent agency (Perjan) to a more autonomous and commercially oriented public corporation (Perumka) in 1991 and the enactment of a new law on railways in 1992. During Repelita VI (1994/95 – 1998/99), GOI established a set of policies and action plans that included strengthening the railway management capacities and systems, modernizing the railway operating regulations and encouraging private sector participation (PSP). It established a high level Inter Agency Coordination Committee (IACC) and a Restructuring Task Force (RTF) to see the reforms through.

    This project built on the Railway Technical Assistance Project-RTAP (1987-1993) and two Private Sector Development Loans (1989-90; 1990-91) and its objectives were supported by the 1995-7 CAS which called for supporting infrastructure investments to eliminate bottlenecks, improving the regulatory framework for private sector participation, increasing operational efficiency and strengthening infrastructure sector management. Moreover, prior to the completion of the RTAP, GOI had specifically requested for continued Bank support of the plans to develop Indonesia’s interurban railways.

    The development and specific objectives were clear. In assessing the links between the specific and development objectives, it is clear that the accomplishment of the first three specific objectives would improve efficiency and service quality. While the linkages might not appear as obvious in the case of the fourth specific objective, increasing the physical capacity on the most heavily trafficked rail route in Indonesia would raise the service quality by offering more frequent service. The Jakarta Bandung corridor upgrading was considered a “no regrets” investment in as much as parts of the corridor had already reached capacity with the remaining sections quickly approaching full capacity, and the fact that rail services on the corridor would remain competitive with aviation and road services even after the opening of the proposed toll road.

    3.2 Revised Objective:

    N.A.

    3.3 Original Components:

    The project had five main components as outlined below (Refer to SAR for specifics):

    1. Policy reform; Cost: US $4.3 million—This consisted of (a) establishing a mechanism to compensate Perumka for its public service obligations (PSO); (b) establishing a mechanism to compensate Perumka for infrastructure maintenance and operation (IMO); (c) establishing a system of track access charges (TAC); (d) transforming Perumka into a limited liability company (Persero) structured along line of business principles, which included the separation of Jabotabek from Java Interurban Rail system, a tariff rationalization and exit plan, corporate planning, and asset revaluation; and (e) developing a framework and strategy for expanded PSP.

    - 2 -

  • 2. The Jakarta Bandung Corridor Improvements; Cost: US $121.3 million—This consisted of (a) a modern centralized traffic control signal system on sections of the line; (b) double tracking 27.7 kms of the line; (c) remodeling of station trackage for a number of stations; (d) replacing 24 kms of the existing partly worn out rail which would be relaid on lower tonnage, lower speed lines elsewhere; and (e) technical assistance (TA) for project management and training of Perumka staff.

    3. Track upgrading and maintenance system; Cost: US $37.5 million—This consisted of (a) renewal of 100 km of main track; (b) partial restoration of 160 equivalent km of track; and (c) establishment of a modern track maintenance system on Java; and (d) training and supporting studies. A criticial component of the maintenance system was to establish a rail reclamation yard for the preparation of continuous welded (CWR) new and relay rail.

    4. Diesel electric locomotive unit exchange maintenance system on Java Cost; US $15.0 million—This consisted of establishing an “on-time preventative maintenance system with unit exchange” for diesel electric locomotives to provide ready-for-use components before similar components are removed from the locomotive for overhaul. This process would shorten locomotive maintenance downtime and increase its availability for service. The component included a locomotive workshop and two running maintenance depots and was to provide initial quantities of critical spare parts, components, consulting services and training.

    5. Strengthening Perumka’s management; Cost: US $4.0 million—This component aimed at developing the institutional capability of the railway in operations and planning focusing on four areas: (a) bridge maintenance management system; (b) improved signal and train operating regulations and related training programs; (c) network simulation models used in capital investment planning; and (d) capacity building to assess long term demand for railway services.

    Assessment of Design

    The project’s objectives and components were clearly linked and reflected the government’s priorities for the rail sector. The design was built largely on the lessons learned from two railway projects implemented in Indonesia and a study of railway lending by the Operations Evaluation Department (OED) of the Bank. Two of these lessons were that railway reforms cannot be carried out piecemeal and should not only include institutional and operational improvements and tariff revisions but should also include priority investments in track and rolling stock. Given the reform objectives of the project, its wide scope and large number of subcomponents, the project was complex. This complexity was addressed in the designation of the high level IACC, (which was already established by Ministerial Decree to manage the sub-sectoral reforms) to coordinate and guide implementation. The IACC would supervise a Restructuring Task Force (RTF) to implement the reform component of the project and a Project Management Unit (PMU) to handle the other project components. Despite its complexity, the project was within the implementation capacity of the RTF and PMU who were also to be supported with adequate TA. The PMU was led by a competent manager who had excelled in the RTAP and had been involved from the outset in this project’s preparation.

    Not withstanding the sound design of the project, there appeared to be some overlap among a few of the project’s subcomponents. For example one of the subcomponents of the Jakarta Bandung corridor improvement was to “replace and modernize operating rules governing train operations to benefit fully from the introduction of the new signaling system”. A subcomponent under institutional development “development and introduction of improved signal operating regulations” seemed to address to some

    - 3 -

  • extent the same issue.

    3.4 Revised Components:

    1. Policy Reform: no change

    2. Improvements to the Jakarta – Bandung CorridorIn December 1998 and owing to GOI’s desire to reduce its borrowing as a result of the Asian financial crisis, the Bank and GOI agreed to substitute the electronic signaling system that was to be installed on the Jakarta-Bandung corridor with a mechanical system resulting in the cancellation of US $20 million. Instead, an electronic signaling system was subsequently implemented with Dutch financing.

    3. Track Upgrading and Maintenance System In September 2002, the rail reclamation yard subcomponent was cancelled due to slow progress (see Section 5.1.4).

    4. Locomotive Exchange System: no change

    5. Strengthen Perumka's ManagementFinancing for subcomponent (b) was provided by other sources and dropped in 1999. Subcomponent (d) was cancelled in June 2002 due to long delays in procurement (See Sections 5.2.5 and 5.3.1).

    3.5 Quality at Entry:

    The quality at entry is rated satisfactory. The timing of the project was right building on the momentum of the Railway Technical Assistance Project (RTAP) and the Private Sector Development Loans (as mentioned in Section 3.1). The project was in line with GOI’s priorities and the Bank’s CAS. Its development and specific objectives were well conceived and the components were well designed and took into account past lessons. The Bank’s requirements for identifying and assessing potential environmental and social impacts were discussed with both Perumka and its consultants and a resettlement plan was prepared by PTKA and later revised based on the Bank’s comments. The project enjoyed the explicit support and commitment of senior officials in the involved ministries and agencies. The risks of such a reform were identified by the Bank team, and it was hoped that with GOI’s strong commitment and the additional visibility and transparency that the Bank brings would diminish the chances of failure. Senior government officials displayed their commitment to the reforms by repeatedly emphasizing that the project was a reform project with an investment component and not the other way around. The risk of consuming the spare parts required for a sustainable locomotive exchange maintenance system was mitigated by the fact that Perumka had identified, and decided to adopt, such a maintenance system on its own initiative.

    Nevertheless, the extent of the resistance to the reforms was not anticipated and its impacts had not been “socialized” among the key stakeholders (see Section 5.2.1). With the benefit of hindsight it would have been more realistic to have a longer tenure on the loan for the reform component. Even if the financial crisis and the political changes in Indonesia had not taken place, key reforms of this nature that will always face resistance require institutional and behavioral changes and are likely to extend beyond the tenure of one or two administrations in the supervising ministries requiring a longer time to implement.

    - 4 -

  • 4. Achievement of Objective and Outputs

    4.1 Outcome/achievement of objective:

    The main objectives of improving economic efficiency and service quality of railway sub-sector were not satisfactorily met, although the physical improvements in the Jakarta-Bandung corridor, the moderate success of the locomotive exchange maintenance system and some capacity building have contributed to a small degree toward achieving these objectives as described below.

    (a) Sub-sector policy reform: UnsatisfactoryThe key components of the reform were not undertaken (see Section 4.2.1). Consequently, the objectives of the reform were not met.

    (b) Rationalization of sub-sector capital investments: Unsatisfactory.This objective was to be accomplished primarily by refining and operationalizing network simulation models to be used to evaluate capacity expansion proposals for different corridors in the country. The models are not being used (see Section 4.2.5). A PTKA staff member has recently completed graduate studies abroad on their use and PTKA expects to start using them in the future.

    (c) Improvement of sub-sector management and operations: Unsatisfactory.A major objective was improving maintenance operations by investing in a rail reclamation yard to prepare continuous welded (CWR) new and relay rail and establish a locomotive exchange maintenance system. While the locomotive maintenance system was moderately successful, the rail reclamation yard was never established. Some institutional capacity was built in developing and employing bridge maintenance management systems. Attempts to estimate long term demand and sub-sector needs and to improve the investment and operation planning were not successful (see Section 4.2.5).

    (d) Increasing the physical capacity of the Jakarta-Bandung Corridor: Moderately Unsatisfactory.Although the physical improvements to this corridor increased capacity as envisioned, the economic rate of return was negative due to a drop in demand following the Asian crisis (see Sections 4.3.1). As such the objective cannot be rated satisfactory despite the accomplishments. Trains running during peak periods doubled (see Annex 1, number 5) between 1995 and 2003 and the rate of accidents declined as expected due to the reduction in the number of crossing points after double-tracking (actual rates are not available). Even though passenger journey times were not reduced as planned but in fact they increased due to corrective works on the tracks to remedy the damage created by land slides between Sukatani and Ciganea, the delays would have been even longer had it not been for the improvements.

    4.2 Outputs by components:

    1. Policy Reform—Rating: UnsatisfactoryOn the positive side, Permuka was converted to a Persero albeit after an 18 month delay, several studies were prepared on the necessary restructuring, the Jabotabek suburban railway was separated from the Java interurban rail system, and a Joint Decree of Bappenas, MoF and MoC and its implementing regulations were issued to establish the legal basis for the implementation of the PSO, IMO, and TAC. Nevertheless, the newly established Persero was not reorganized along “line of business” principles and the PSO, IMO, and TAC were never agreed to and implemented. The company’s assets were not revalued, tariff rationalization plans were not carried out and a framework for PSP was never adopted.

    - 5 -

  • 2. Jakarta-Bandung Corridor Improvements-- Rating: SatisfactoryThe key subcomponents (except for the electronic signaling system that was cancelled-see Section 3.4.2) were completed. Despite significant procurement delays, smaller than planned windows of work time available to contractors, a seven-month loan disbursement suspension, and the several land slips and slides that occurred between Sukatani and Ciganea, 28 kms of double tracking were laid, 24 kms of the existing partly worn out rail were replaced by new rail with the old rail relaid on lower-tonnage lower-speed lines, 14 stations were remodeled, 8 bridges and 6 box culverts were constructed and the supporting TA provided. The windows of time available to contractors to work on the double tracking of the main corridor were shorter than planned due to the collapse of a 100 year old tunnel on the alternative route though Bogor. Deforestation in 2000 above the portal at the Jakarta end resulted in a massive landslide that blocked the tunnel entrance. Corrective works were aborted when heavy rains resulted in the collapse of the tunnel and rendered the alternative track that had been upgraded under the project unfit to carry the container traffic to Bandung. This tunnel has not been reopened.

    Land Acquisition and Resettlement: The implementation of land acquisition for double tracking construction started in 1997 and was initially completed in 1999. Due to the required corrective works, some additional land acquisition took place in 2001-2. There were 398 households affected by the project: 58 land owners and 340 households who occupied Perumka/PTKA’s land. Implementation was satisfactory (see Section 7.6).

    3. Modern Track Maintenance System—Rating: Unsatisfactory.While this component provided a 100 km of new UIC 54 rail including concrete sleepers and fastenings for the main track, it failed to provide a track maintenance system in Java due to the lengthy delays in procuring the rail reclamation yard which was ultimately cancelled. As the maintenance system was not established, some supporting components such as the partial restoration of 160 equivalent km of track were not implemented.

    4. Locomotive Exchange Maintenance System—Rating: Moderately SatisfactoryThis component was implemented with few delays and was rated highly satisfactory at the time of loan closing (loan closing for this component was September 2003--see Section 5.4). The envisioned maintenance system was successfully developed. It created pools of critical components to be supplied to the workshop and depots to replace worn out and damaged components. Facilities were established in Bandung and Yogyakarta and were operational by mid 2002. However, in April 2005, PTKA informed the ICR mission that some of the machines had broken down and that the repair process was delayed due to inadequate training of staff. The high voltage connection that was required for Yogyakarta had not been made and work had to be planned in stages to utilize the limited power supply available. A small percentage of spare parts (3%) was consumed due to budgetary constraints which was in turn partly a result of PTKA’s not receiving fair compensation for the PSO and IMO. (The success of the maintenance system required that the spare parts not be used for consumption but only to replace a damaged part until it was repaired.) Despite these shortcomings, the maintenance system had resulted in some efficiency. A particularly good case is the reduction in the washing time of a locomotive gear box from 3 days to 3 hours (see Section 9.1.3.e). Nevertheless, due to the limitations mentioned above, the component was rated moderately satisfactory.

    5. Strengthen Perumka's Management—Rating: Moderately UnsatisfactoryOf the three remaining subcomponents (subcomponent (b) was dropped—see Section 3.4e) that were to be implemented, component (d), the development of the railway’s capability for assessing the long term demand for railway services was cancelled due to long delays in procurement; component (a), the bridge maintenance program was developed and is being utilized; and component (c), an updated version of the

    - 6 -

  • network simulation planning model was procured and the necessary training provided. The ICR mission was informed, however, that the network simulation model was no longer being used. PTKA attributed this to the large data requirements and the high cost of securing the data but was hopeful on using the model in the near future (see Section 4.1.b)

    4.3 Net Present Value/Economic rate of return:

    The Economic Net Present Value (ENPV) and Economic Internal Rate of Return (EIRR) were estimated in the SAR for three of the project’s components: the Jakarta-Bandung Corridor, the track maintenance system and the locomotive exchange maintenance system. The table below shows the original as well as the re-estimated, ENPVs for the three components.

    Economic Net Present Value in SAR and ICR

    Project ComponentENPV

    (1996 RP billion)[SAR Estimate]

    ENPV (1996 RP billion)[ICR Estimate]

    Jakarta – Bandung Corridor 81 (77)Track Maintenance System 228 ZeroLocomotive Exchange Maintenance System

    39 21

    1. The Jakarta Bandung Corridor

    In the original estimation, this component had an ENPV of 81 billion Rupiah in 1996 prices and an EIRR of 15%. When re-estimated for the ICR, the economic returns were negative with an ENPV of minus 77 billion Rupiah (in 1996 prices). The main economic benefit of this corridor upgradation is the time and vehicle operating cost savings. There are also additional benefits due to the reduction in accident rates and pollution. All benefits are a direct function of the number of car users who switch to rail as a result of the project. In the original estimation, rail passenger traffic was projected to grow at 8% per annum and the full capacity of the railway corridor was projected to be reached by 2003. Consequently from 2004 on any incremental traffic could only be accommodated by road. However, and largely influenced by the 1997 Asian crisis, the maximum capacity has not been reached yet and is projected to be reached by 2008 and PTKA has revised annual passenger growth projections down from 8% to about 5%. As a result, the projected number of executive and business class passengers in 2020 dropped from 11.1 million to 7.2 million. The 8% growth rate projected by the Bank was plausible given that the annual growth rate between 1987 and 1995 was 9.4%. Another contributing factor to the drop in the economic benefits is the sharp decline in container traffic from 435 thousand tons in year 2002 to about 171 thousand tons in 2003 (largely due to a 130% tariff increase). At present, there is plenty of capacity for container movements on the rail corridor and achieving the benefits of the projected increase in container traffic through 2020 would not have required the upgradation. See Annex 3 for details.

    2. The Track Maintenance System

    The focus in the estimation of the economic benefits was the establishment of the maintenance system, an objective that did not materialize (see Section 4.2.3). Under these component, the project also

    - 7 -

  • supplied rail parts. The Bank’s assessment was that these parts would be the minimum necessary and would be carried out with or without the project. Consequently, there is no difference between the “without the project” case, typically known as the base case and the project case and the ENPV is zero for both components. Potential savings from procurement under ICB or an increase in cost incurred in preparing, tendering, and evaluating bids could have resulted in marginal positive or negative impacts.

    3. The Locomotive Unit Exchange Maintenance System

    The objective of the new system was to increase maintenance efficiency and to reduce the down time of locomotives consequently increasing their availability and productivity. The SAR estimated that a) on time maintenance rather than maintenance at time of component failure, b) the use of readily available exchange components and c) the reduction in the frequency of locomotive maintenance would result in savings equivalent to adding 10, 14 and 4 locomotives respectively. These benefits were assumed to be generated gradually over a 6 year period after which they would remain constant. The ENPV and EIRR for the maintenance system were estimated in the SAR at 39 billion 1996 Rupiahs and 26.3% respectively.

    The ENPV and the EIRR estimated for the ICR were 21 billion 1996 Rupiah and 18.5% respectively. The difference is due to an increase in cost of about 11.9 billion 1996 Rupiah (see Section 5.4) and a reduction in benefits. The savings generated from on time maintenance and the reduction in scheduled maintenance were smaller than those projected in the SAR. The gross benefits expressed as additional locomotives dropped from 28 in the SAR to 24 in the ICR. See Annex 3 for details.

    4.4 Financial rate of return:

    1. Financial Performance of PTKA

    Most of the key reforms that would have positively impacted the financial performance of PTKA were not undertaken. Consequently, any changes in the company’s financial performance cannot be attributed to the project. Also, the financial indicators listed in Annex 1 should be interpreted with caution. The low return on net assets of 0.15% compared to a target of about 5% would have been even lower if assets were revalued as necessary. The debt coverage ratios appear reasonable but are not predicated on the proper bases as the values on financial statements do not reflect actual costs incurred.

    2. The Jakarta Bandung Corridor

    The financial returns for this component as estimated in the SAR are marginally negative at a discount rate of 12% (FNPV of minus 10 billion 1996 Rupiah) and an FIRR of 11.7%. However, these variables serve as descriptive statistics and not decision criteria as it was clear that the project's investments in the corridor were not going to be financed by the private sector. From financial and fiscal perspectives, the important question is with respect to the financial sustainability of the investments in the corridor (availability of resources for maintenance and operation) but this is necessarily linked to the overall financial performance and reforms of PTKA (see Section 4.4.1). This issue is further discussed in Section 6.1 on sustainability.

    To obtain a general sense of how the financial returns have changed after implementation, a re-estimation using price and passenger growth projections provided by PTKA was carried out. It shows a sharp decline in the financial returns to the investment. The sharp drop is due to two main reasons: lower traffic volumes and tariffs. The present value of the incremental revenues as projected in the SAR

    - 8 -

  • was 375 billion 2001 Rupiahs compared to 190 billion 2001 Rupiahs as re-estimated in the ICR. The downward revision of the projected demand and the slow growth over the past few years is discussed in Section 4.3.1 above. With respect to projected tariff rates, real prices were held constant throughout the analysis period in the estimation in the SAR. However, real tariffs declined under PTKA’s projections. Adjustment of the nominal tariffs projected by PTKA through 2021 for business and executive classes lags well behind an assumed average annual inflation rate of 6%. By 2021, the projected tariff for the executive service will be less than 60% of its real value in 2002. Further contributing to the negative financial returns, although to a smaller degree, is the fact that container traffic dropped significantly in 2003 and has not recovered (see Section 4.3.1).

    It is important to keep in mind that the financial analysis conducted for this project does not address the commercial viability of the entire corridor, but rather the financial return on a particular investment to upgrade the corridor.

    4.5 Institutional development impact:

    Despite the project’s failure to meet its development objectives, its institutional development impact is substantial. Knowledge and skills were acquired throughout the design and implementation phases of the different project components. The TA helped build capacity in the use of bridge maintenance programs and network simulation models for planning (even if these models are not being used at present). More importantly, the failed reforms have increased the awareness of PTKA’s board and staff, the IACC and senior government officials of the main issues involved in restructuring, as well as the different alternatives and approaches. These are critical prerequisites for any successful reform and cannot be accomplished in a short time. Whether the Bank is involved in other railway projects in Indonesia that support the ongoing reform efforts to their fruition or PTKA carries out the reforms without the Bank’s assistance, the project has “planted the seed” for the reforms. The long delays in the procurement starting from preparing terms of reference, to establishing a decision process have spurred the PMU and PIUs to streamline and simplify procurement processes. One recommendation made by a PTKA director during the ICR mission was for MoC and the Bank to agree on a standard form of contract during preparation to shorten the lengthy procurement process and avoid unnecessary delays.

    5. Major Factors Affecting Implementation and Outcome

    5.1 Factors outside the control of government or implementing agency:

    Four factors outside of the Government’s control contributed to the project’s shortcomings.

    1. The Asian financial crisis

    The crisis affected the project in several interrelated ways:

    (a) The crisis shifted the attention of senior and key government officials to social safety nets and poverty alleviation policies. As Perumka/PTKA was functioning and did not seem in need of immediate attention, the reforms became less of a priority and the strong commitment that was enjoyed at the outset of the project weakened.

    (b) The fiscal impacts of the crisis faced by GOI were massive. Debt service, fuel subsidies and restructuring of PLN placed huge burdens on the budget. The railways would continue to operate even if the PSO and IMO payments were not made in full while other payments were much harder to defer.

    - 9 -

  • Consequently, MoF did not acknowledge, or make, the estimated payments.

    (c) The sharp depreciation of the Rupiah created uncertainty, at least in the short run, with respect to the political acceptability as well as the financial viability of a tariff rationalization plan, particularly not knowing the impact of large tariff increases on ridership.

    2. Change in political environment and succession of leaders

    During the project, there were 4 presidential changes and many changes in the senior leadership and board of Perumka/PTKA, MoC, the IACC and RTF. During one 6 month period in 2001, there was effectively no IACC to guide implementation. (Some of the changes were within the control of the government as discussed in Section 5.2 below.) At the very least these changes disrupted continuity as sometimes the majority of the new appointees were not fully aware of the project and had to be briefed in depth. In one case, the resignation of the entire board of PTKA was in response to a train accident that had resulted in the loss of lives. Consequently, the resolution of safety issues took precedence by the new board over anything else.

    3. Land slides/slips in the Jakarta Bandung Corridor

    The extension of the project’s closing date was due primarily to geological conditions that caused numerous landslides and landslips in the Jakarta Bandung Corridor, specifically in the area between Sukatani and Ciganea (Km 100 to Km 104). A major landslide in the mid 1970s revealed the area’s vulnerability. This section of the corridor requires continuous monitoring and maintenance as there are significant geological differences within this relatively small area. It was essential to fix these problems so that the rail line could continue to operate. Consequently the closing date was extended twice for this purpose for a total of 15 months to allow for the completion of the corrective works.

    4. Failure of the first round of tendering for the railway reclamation subcomponent

    Upon the Bank’s recommendation, bidding for the railway reclamation subcomponent, the core of the track maintenance management program, was split into three packages: the railway reclamation facility, rail welding machines, and supervision and training. This was proposed to increase participation and competition for the different packages. However, no bids were submitted for the first package and those received for the other two were non-responsive. The three packages ultimately had to be combined into a single responsibility contract. While the package could still have been executed had it not been for the lengthy procurement delays (see Sections 5.2.5 and 5.3.1), the time lost in the first round of tendering contributed to the cancellation of this subcomponent.

    5.2 Factors generally subject to government control:

    1. Resistance to reforms

    Resistance to the reforms within some ministries and agencies contributed to a large extent to the suspension of loan disbursements and later downgrading of project implementation and achievement of development objectives to unsatisfactory status (see Section 7.7).

    (a) MoF was supportive from the beginning but never delegated high level officials to attend meetings which delayed decisions and made the resolution of differences more difficult. While MoF agreed in principle to the reforms and the budgetary mechanisms proposed by PTKA

    - 10 -

  • (PSO/IMO/TAC), MoF did not make available the appropriate amount of funds as estimated by PTKA according to the Joint Decree and its implementing regulations but paid only a “balancing” amount that was a small fraction of what had been estimated. The resistance was in large part due to scarce public funds (discussed in Section 5.1.b) and possibly due to the fact that PTKA’s financial statements showed profits, although these were primarily a result of low depreciation values. Had these values been revised upwards as per the project’s plans, it would have been clear that PTKA did not have the resources to replace its rolling stock, let alone finance expansion and upgrading.

    (b) At times MoC showed less than full commitment. Law 13 of 1992 on the railways required 12 Ministerial Decrees for its complete implementation, many of which were necessary for the satisfactory progress of the project. Nine years later, as of June 2001, only five had been issued with an additional one pending.

    (c) The envisioned reforms were to leave DGLC/MOC primarily with regulatory responsibilities with PTKA carrying out maintenance and upgradation works and paying compensation for the use of the tracks. As this represented a change from the existing paradigm where DGLC also carried out upgradation works, there was some resistance to the reforms within DGLC.

    (d) The resistance within PTKA was stronger than anticipated. Perumka was organized along regional/geographical lines where Directors of Operations (Daops) were responsible for all business and technical aspects of running the railway within their respective regions. As the reorganization of PTKA along line-of-business principles would reduce the responsibilities of many of the Daops, they resisted the reforms.

    2. Intermodal Imbalance

    The financial viability of the rail sector and its ability to compete on an equal footing with the road sector required that road users pay a charge for using the roads along the same principles of PTKA’s paying a track access charge for using rail. Indeed, GOI’s 1996 “Statement of Goals and Policies” for the sub-sector envisaged track access charges being introduced in concert with road user charges. The lack of implementation of road user charges made the financial viability of PTKA more difficult. To compensate, tariffs needed to be raised, but charging the tariff rates necessary for commercial viability would have shifted ridership to the subsidized road sector.

    3. Change in the shareholder responsibility of PTKA

    At preparation, MoC was the policymaker, regulator, shareholder representative for Perumka and owner of the infrastructure. The establishment of the Ministry of State Enterprises (MoSE) in 1998 meant that Perumka would fall under its purview and not that of MoC. Frequent changes of shareholding responsibility for PTKA delayed the reform process. It was not clear which responsibilities would remain with MoC and which would move to MoSE. This issue was ultimately resolved by a Presidential Decree to keep Perumka under MoC. However, shortly after its conversion in July 1999, PTKA was shifted from MoC to MoSE in December of the same year then back to MoC in July 2000 and once again back to MoSE in November 2001. MoSE’s main focus was to deal with state enterprises that were imposing large burdens on the budget and so PTKA was not a priority. Even with full commitment, these changes greatly inhibited the reform process as the new supervising ministry had to be briefed each time on the project’s reforms before sanctioning them.

    - 11 -

  • 4. Flaws in the decision making processes affected project progress and resulted in lengthy delays

    (a) The instruction by DGLC to use KA clip rail fasteners instead of the specified Pandrol clips without consulting the Bank, despite the fact that KA clips had not been tested in accordance with accepted international standards and did not provide any cost savings. The Bank indicated that it would entertain the idea of testing the KA clips on side tracks but the contractor proceeded to order large numbers of the clip and installed some of them on the main line. These were later replaced by Pandrol clips.

    (b) Delays in approving concrete sleepers on curves to replace steel sleepers that had manufacturing problems and that had not been inspected at point of of manufacture and later rejected on delivery for quality reasons.

    (c) The decision to build an Austrian-financed bridge on the Jakarta-Bandung Corridor without an overall analysis of the benefits of such bridge.

    (d) In a conscious effort to reduce its borrowing, GOI decided to cancel the electronic signaling component, which was subsequently financed by the Netherlands without consulting the Bank. This complicated implementation and resulted in the Bank’s shifting construction priorities on the Jakarta Bandung corridor to coordinate signal commissioning with station remodeling. Coordination was in general satisfactory but there were safety concerns during implementation.

    5. Complex GOI procurement rules

    These generally slowed implementation (also see Section 5.3.1 below). Civil works were delayed due to excessive micromanagement, with decisions taken by the project group needing to be confirmed by PTKA and then ratified by DGLC. There was a procurement committee for the project that included different institutions which sometimes had different opinions. Ambiguities in the interpretation of different government regulations (Kepres 6/99, Kepres 16/94 and MoC implementing regulation KM 48/95) also contributed to confusion and delays.

    5.3 Factors generally subject to implementing agency control:

    1. Delays in implementation(Delays resulting from the complexity of the procurement rules are discussed above in Section 5.2.5)Considerable, often unwarranted, delays in preparing terms of reference and evaluating bids played a large role in the cancellation of the key subcomponent of the track maintenance management component (the rail reclamation yard-see Section 5.1.4) and the institutional development subcomponent on long term demand estimation. In at least one instance, the validity of the proposals expired before they could be evaluated. Other examples include contract signature that was delayed for two months despite completion of evaluation (the UIC 54 rail, turn-outs and steel sleepers) and a delay of about one month in the start of the evaluation of submitted bids for supervision of the Jakarta-Bandung corridor.

    2. Implementation problems due to inadequate monitoring For example, a Bank mission found a construction site for double tracking works at Sukatani to be in poor condition for lack of temporary drainage and no clearly set out survey pegs raising safety concerns. The equipment at the site was also insufficient to carry out the contract within the specified time.

    5.4 Costs and financing:

    - 12 -

  • Several subcomponents were canceled and the loan agreement was amended 4 times and the closing date was extended for a total of 27 months to December 30, 2004. The first amendment, effective August 1998, cancelled US $20 million and changed the loan reallocations among the different categories while increasing the share financed by the Bank for some categories. The second amendment extended the closing date by one year to September 30, 2003 and cancelled an additional amount of US $27.325 million as of September 24, 2002 while also changing some loan reallocations. The third and fourth amendments extended the closing dates by 12 and 3 months respectively to allow for completion of the corrective works on the double tracking between Ciganea and Sukatani on the Jakarta-Bandung Corridor component only. Land slips and slides that had occurred in that section necessitated the corrective works (see Section 5.1.3). The amendments also included some reallocation in the loan categories to allow for the financing of the corrective works in that section. Other than the civil works for the Ciganea Sukatani section and associated TA, the closing date for all other project components was September 30, 2003.

    The cost of the project at appraisal was estimated at US $207.3 million of which the Bank, the Government of Australia and GOI/Perumka were to finance US $107.4 million (US $105 million from the REP loan, and US $2.4 million from Loans 3385 IND and 3913 IND), US $56 million and US $43.9 million respectively. (See Annex 2 for details.) There are however descrepencies in the sources of finance as presented in the SAR. While Table 4.2 shows the contribution of GOI/Perumka and the Government of Australia at US $43.9 million and US $56.0 million respectively; Table 4.3 shows them at US $37.8 million and US $62.2 million respectively. The total actual project cost is estimated at US $130.9 million financed as follows: US $57.6 million by the Bank, US $55.2 million by the Government of Australia, US $13.0 million by the Government of the Netherlands and US $5.2 million by GOI/Perumka.

    Expenditures on the policy reform and institutional development components as a percentage of the estimates at appraisal were the lowest at 4% and 21.5% respectively due to the lack of progress on the reform and the cancellation of subcomponents (see the first table of Annex 2). IBRD financing of the Jakarta Bandung civil works was US $15.5 million compared to an allocated amount of US $22.8 million in the December 99 Amendment, resulting in about US $8 million in savings. The small percentage of actual expenditures on the track maintenance component was mainly due to the cancellation of the rail reclamation yard and related works; while the overexpenditure on the locomotive exchange unit maintenance system was due to the procurment of additional components that were required.

    6. Sustainability

    6.1 Rationale for sustainability rating:

    As the single rating given to the whole project (unlikely) does not cover specific project components, their sustainability is discussed below:

    (a) The sustainability of the physical improvements (stations remodeling and double tracking) on the Jakarta Bandung Corridor is rated as likely. Even though the project’s investment has proved not to be financially or economically viable (see Sections 4.3 and 4.4), this corridor remains the most heavily trafficked one in Indonesia and is the most commercially viable line that PTKA operates. It should also be noted that the analysis covered the project’s investments in the corridor not its overall commercial viability. The viability of the corridor is enhanced by the fact that plans to build a toll road were delayed

    - 13 -

  • as a result of the Asian financial crisis (one lane only was completed in April 2005 ahead of the Asia-Africa meeting that took place in Bandung). At present, trip time by rail is usually around 2.5-3.0 hours compared to about 4-5 hours by car on the untolled road. Nevertheless, the budgetary mechanisms that would have assured the allocation of sufficient funds for the maintenance of the tracks have never been agreed to by MoF, and PTKA continues to receive a small fraction of what has been estimated following the Joint Decree on the budgetary mechanisms and its implementing regulations. Consequently, the likely maintenance of the route will depend on the availability of funds and competing priorities.

    (b) The sustainability of the locomotive exchange maintenance system is rated as likely. While the system has to some extent faltered since its successful completion, only 3% of the parts have been consumed despite budgetary constraints; and machines that have broken down are being repaired. This, together with the fact that Perumka had planned to develop this maintenance system on its own initiative, would indicate that the system ranks high on the company's priority list.

    (c) The institutional subcomponent on network simulation modeling proved to be unsustainable. (see Section 4.2.5).

    (d) Other project components were largely unsuccessful.

    6.2 Transition arrangement to regular operations:

    PMU and PIU members are PTKA staff and so the transition from the project to regular operations has taken place with no disruption. Members of the RTF within PTKA continue to work on the restructuring despite the closing of the loan. There is a system in place for collecting the performance indicators on the available capacity and utilization during peak hour on the Jakarta Bandung Corridor and on locomotive availability (see Annex 1).

    7. Bank and Borrower Performance

    Bank7.1 Lending:

    The bank’s performance for this stage was satisfactory. The assessment of objectives and design in Sections 3.1 and 3.3 respectively and Section 3.5 on the "quality at entry" explain that the project was well conceived and designed, and how the implementation arrangements were set up to deal with the complexity of this project. The project was prepared with the active participation of the Borrower and complied with all relevant safeguard policies. Key risks were identified; and the preparation team members, complemented by consultants, covered the different areas of expertise required for the project (see Annex 4).

    The economic analysis of the physical improvements proved their viability. There was however some arbitrariness in the appraisal of the Jakarta Bandung corridor improvements. Because a section on the corridor was common to more than one route in Java, the total cost of the corridor improvements was reduced by a fraction and only the benefits specific to the corridor were included. A better approach would have been to account for the benefits to all passenger networks and freight trains (even those outside the corridor) and the total costs of improvement. Given that increasing safety on the Jakarta Bandung corridor was one of the objectives of the corridor component, the performance indicators could

    - 14 -

  • have included one or two indicators on accidents. Finally, the slight descrepancy in the sources of the project's financing as presented in the SAR (see Section 5.4) could have been easily avoided.

    7.2 Supervision:

    The Bank’s performance during supervision was satisfactory. The project had three task managers but continuity was maintained by the second task manager who remained as a Bank consultant and was heavily involved through loan closing. The Bank’s Transport Sector Coordinator, based in Jakarta, supervised the reform aspects of the project and played a major role in its design and preparation. He was very familiar with Indonesian economic and political circumstances and had also worked on the earlier RTAP. The Project’s second task manager, who supervised physical improvements, was also based in Indonesia and a key member of the project team from the beginning. Consequently, both were very accessible, provided key inputs and tight follow up. In addition, both were well respected by PTKA who updates the Bank on the performance of the physical improvements despite loan closing and informally seeks their advice on other matters. Missions included a balanced mix of the necessary expertise (see Annex 4). During Fiscal Year 2004, twelve site visits were carried out by the Bank. These were not formal missions but this approach was appropriate given that as of September 2003 only one component was to be held open to complete the corrective works resulting from the landslides.

    The Bank team provided constructive advice to the problems that plagued the project and organized thematic supervision missions to deal with safeguard and fiduciary issues. Despite tight follow up and supervision, there were a few instances where the Bank was not kept abreast of all project-related develpments but nevertheless showed considerable flexibility. One example was in rearranging implementation priorities on the Jakarta Bandung corridor to coordinate with the implementation of the Dutch financed signaling system. Another one was granting an approval on an exceptional basis to allow for the use of the untested KA railway clips on some secondary rail lines even though the Bank was never consulted on their procurement. The Bank also showed understanding in extending the loan closing date 15 months to carry out the corrective works on the Jakarta Bandung corridor that had resulted from the land slides and slips.

    The Bank was firm on the key issues and correctly suspended loan disbursements less than 18 months after effectiveness due to failure to abide by important loan covenants regarding the reform. This demonstrated the Bank’s seriousness about supporting the reform process and trying to secure the utmost support from GOI. The Bank displayed flexibility again in lifting the suspension despite the fact that not all the covenants that had resulted in the suspension had been met. Nonetheless, the key covenant regarding the conversion of Perumka to a Persero status had taken place following a Presidential Decree.

    There were a few shortcomings with respect to the supervision of the locomotive exchange maintenance system. While the system was installed and rated highly satisfactory, training had not been fully completed and the installation of the high voltage connection to the Yogyakarta workshop had not been made (see Section 4.2.4). The weakness in the Bank's supervision in this regard is reflected in not pursuing the matter to closure and secondly in the highly satisfactory rating despite these pending issues.

    The Bank could have also given some consideration to restructuring the reform component in light of the major changes in the political, financial and economic landscape in Indonesia. Realizing the change in the government’s priorities and the reluctance of the private sector to be involved at that time, particularly in long term investments, could have warranted a formal reduction in the scope of, or a longer implementation schedule for, the reforms.

    - 15 -

  • 7.3 Overall Bank performance:

    The Bank’s overall performance was satisfactory.

    Borrower7.4 Preparation:

    The Borrower’s performance during preparation was satisfactory. GOI’s commitment to the reforms at the beginning was strong and evident in the attendance of project meetings by 3 high level (Echelon 1) staff (two Secretaries General from MoC and DGLC and one Deputy Chairman from Bappenas) to reinforce their commitment. The Borrower worked closely with the Bank and preparation consultants to define the project. Several of the studies required for the project had already been completed by MoC/DGLC prior to the start of the project. GOI’s commitment to move fast on the reforms was demonstrated in its request that the management consultancy assistance for the development and implementation of the reforms be initiated with financing from the ongoing RTAP. The PMU and PIUs were staffed with adequate numbers of full time staff at loan effectiveness. The preparation of a Resettlement Action Plan according to Bank’s policy took place in a timely manner. With the benefit of hindsight, PTKA believed that better geological surveys of the Sukatani-Ciganea section of the Jakarta-Bandung corridor could have helped in identifying vulnerable areas and carrying out the necessary corrective works earlier.

    7.5 Government implementation performance:

    The Government’s performance during implementation was unsatisfactory. Physical improvements were delayed due to complex procurement and sometimes flawed decision making processes and deadlines for key actions on reforms were rarely met (see Section 5.2). These resulted in the suspension of the loan for 7 months (see Section 7.2) and for unsatisfactory project ratings on implementation and achievement of development objectives for most of its life.

    7.6 Implementing Agency:

    The implementing agency’s performance during preparation was satisfactory. The IACC adequately guided implementation with the RTF and the PMU reporting to it. The RTF was in charge of the reform component and the PMU of all the other components, and each generally carried out its responsibilities satisfactorily. The resistance and delays that resulted were largely due to the government and not the RTF and PMU. The RTF, for example, continued to prepare PSO/IMO/TAC proposals, as mandated, despite their not been accepted by MoF. With a few exceptions, the PMU’s performance on financial management was satisfactory. Progress reports were furnished to the Bank in a timely manner, progressively improved in identifying issues and proposing solutions, although alerting the Bank to potential delays was not always satisfactory. Of the few issues that were brought to the PMU’s attention were the discrepancy between expenditures reported to DGLC and the Bank, and the need to better correlate payments with supporting documents for easier management and audit. The PMU was also not always proactive in providing updates on performance indicators.

    Despite significant delays, the quality of completed work on the Jakarta Bandung corridor was good. This not withstanding, there were a few incidents where the performance of the PMU could have improved (see Section 5.3).

    - 16 -

  • The implementation of land acquisition and resettlement on this project is considered satisfactory. No significant problems arose during implementation. Both land owners and those who occupied Perumka’s land got fair compensation. When PAPs were interviewed people, they expressed their satisfaction with the compensation rate and timeliness of receiving compensation.

    7.7 Overall Borrower performance:

    Despite a satisfactory performance in preparation, the Borrower’s overall performance was unsatisfactory. Development objectives were not achieved. The sectoral reforms fell very short, and the important track maintenance management system is not in operation. Project implementation and financial performance were often rated unsatisfactory. Lack of progress on the reforms led to the suspension of the loan for a seven month period between December 1998 and July 1999. Eighteen months after lifting the suspension, implementation was downgraded to unsatisfactory where it remained for the rest of the project (with the exception of one conditionally satisfactory rating).

    8. Lessons Learned

    1. Cultivate commitment in upcoming managerial cadresAside from resistance to reforms from some quarters which should be expected, the problem of commitment to reform was exacerbated by changes in the senior management who was advocating the reforms. The Borrowers need to build strong commitment at all managerial levels to enhance the reform’s sustainability over time.

    2. Identify opposition from the outset and gauge resistance to proposed reformsThe project had many strong supporters and enjoyed solid commitment that carried over from the Railway Technical Assistance Project. However, some resistance arose from the outset from DGLC and even the Daops in Perumka/PTKA, and the commitment of MoF was not as strongly demonstrated as that of Bappenas and the railways. More efforts are necessary during preparation to identify the opposition, assess their potential influence on the project, institute mitigation measures and carry out a “socialization” of the reforms.

    3. The Bank’s presence keeps momentum for reforms alive Despite the failure of the reforms, the studies undertaken have increased the awareness of PTKA’s board and staff, the IACC and senior government officials of the main issues involved in restructuring, as well as the different alternatives and approaches, and critical prerequisites for any successful reform. The Bank’s engagement and support of the reform process helped keep it alive (PTKA is still looking into restructuring options and experimenting with pilot projects). However, without the Bank’s support, the reforms, even though they may ultimately succeed, they will be harder to achieve and most likely take more time.

    4. Policy reform takes timeReform processes are inherently complex to implement, require high degree of stakeholder consultation, analysis of impacts on the various affected groups and consensus building. They often require institutional as well as behavioral changes. For this reason, the Bank may want to consider (or realistically expect) longer tenures for loans dealing with challenging policy reform issues.

    5. Simplified and harmonized procurement procedures are necessary

    - 17 -

  • Procurement was delayed for many reasons as discussed in Sections 5.2 and 5.3. While harmonization of DGLC’s and the Bank’s requirements as suggested in Section 4.5 early on would save time, the Bank needs to set realistic schedules. Given that this was the PMU’s first experience with ICB, delays were probable. It would be useful for the Bank to assess procurement capacity and risks of delays.

    9. Partner Comments

    (a) Borrower/implementing agency:

    9.1 Project Implementation

    9.1.1 Organization and Staffing

    Overall responsibility for coordinating and guiding the implementation of REP vested in the IACC (Inter Agency Coordinating Committee) established by a Minister of Communication’s Decree. This committee consists of a Steering Committee (chaired by the Secretary General of MOC, with members from representatives of related Government Officials), and an Inter Agency Working Group (chaired by the Secretary of Land Transport Directorate General, with members from the Deputies of the above mentioned officials).

    For the Non Physical component’s implementation, a Restructuring Task Force (RTF) was established, chaired by the BoD of Perumka/PT. KA, with Perumka/PT.KA staffs as the members.

    The physical component execution is the responsibility of the Project Management Unit (PMU), which consists of three Project Implementation Units (PIUs), namely :

    a. PIU for Jakarta – Bandung Corridor improvements and track maintenance systems, including related training.

    b. PIU for Locomotive Unit Exchange Maintenance System, including related trainingc. PIU for the Institutional Development

    9.1.2 The Non Physical Components Implementations

    a. Transforming Perumka into PT.Kereta Api (Persero)

    Based on the “Goals and Policies”, in the covenant stated that Perumka will be transformed into PT Kereta Api (Persero) on January 1, 1998. In deciding the transformation, there were some argues in the company, causing the delay in the process, so that the transformation happened in June 1, 1999, resulting an Unsatisfactory rating from the Bank, and an administrative sanction was implemented (suspension of disbursements: from December 1998 up to June 1999). The Organization structure will be arranged on regional and line of business. The PT KA Board of Directors decided that Java organized on line of business principle (Divisions), and Sumatera on regional basis. In Java 7 divisions shall be established (Jabotabek Railway, Rolling Stock, Training, Property, Passenger, Freight, and IMO Debates on the choice between establishing an IMO Division or an IMC Division, solved by the help of an International Consultant (Canarail). IMO = Infrastructure Maintenance and Operation, IMC = Infrastructure Maintenance and Construction Divisions), and a Train Restaurant sister company. Sumatera is divided into 3 Regional Divisions (North, West and South Sumatera

    - 18 -

  • Regional Divisions). Java organization structure is being implemented gradually with the 4 first Divisions already established. The 3 latter Divisions is currently under intensive preparation and planned to be declared in mid September 2005 and in full operation by January 2006.

    b. Separation of Jabotabek

    One of the policy reform plan (as stated in the SAR) is the financial and managerial separation of the Jabotabek and Java Inter-city systems. From the agreement reached it was stated that the GOI implement the financial separation of the Jabotabek and Java Inter-urban rail systems by February 28, 1997. The separation of the Jabotabek and Java interurban rail systems is actually implemented in 1999, except for basic infrastructures which is still jointly used with Java Interurban transport. Ideally the Jabotabek Railway should operate on its own infrastructure, with some joint/integrated stations.

    c. Tariff Rationalization and Exit Plan

    As stated in the Goals & Policies, the Management entity will in general be empowered to set the tariffs and rates for railway services at levels that will enable it to cover the associated financial costs of provisions, including track charges – if and when levied – and to earn a reasonable return on assets employed. To reach this condition, the BoD of PT.KA hired an Australian Consultant to study on the tariff calculation and setting, including the exit plan for loosing services. PT KA BoD has prepared the basic concept for tariff specifically for the economy class passenger and now in the process of approval from MOC and the Parliament.

    d. Assets Revaluation

    The Bank criticized the financial report of PT KA (not picturing the real numbers) due to the fact that PT KA assets are calculated on much lower price basis. This down pricing was happened when Perumka transformed into PT KA, to avoid high taxation. At present a simulation is being undertaken to foresee the impact if the re-evaluation is done.

    e. Implementation of PSO, IMO, TAC

    The Reform covers administrative and financial relationship to reposition both the Government (as Regulator and Owner) and the company (as Operator). For the financial relationship, a Joint Decree of three Ministers (and an implementation decree of three Director Generals) were published to regulate, calculate and implement the PSO (Public Service Obligations), IMO (Infrastructure Maintenance and Operation Cost), and TAC (Traffic Access Charges) budget arrangement. The implementation, however, is not coincide with the agreed process, and not meet the principle stated in the Goals and Policies.The World Bank commented that the PSO, IMO, TAC budget mechanisms are still not being implemented in accordance with the adopted procedures and that the Parliament has recently expressed concern of this matter (Aide Memoire of June 23, 2003). Since the implementation from year 2000 until 2004, in accordance to audit results from BPKP, there still exists a cumulative difference of 1.3 trillion Rupiah. The principle stated in the Goals & Policies determine that the TAC will be implemented in line with the implementation of the RUC (Road User Charges). The RUC is not implemented

    - 19 -

  • yet, but the TAC is already implemented.

    f. Regulations for Implementing Law 13/92

    To support the Railway law No. 13/92 some regulations have been issued, i.e.:a. Government Regulations (GR) No. 69/98, concerning Infrastructure and Rolling Stock, issued

    on August 20, 1998b. GR No. 81/98 concerning Railway Traffic and Transport, issued on November 30, 1998

    g. Business Chance Identification

    Perumka physical utilization of assets is good but the financial return on assets is poor. From the analysis made it is concluded that Perumka has relatively high in terms of physical measures of asset utilization, but mainly due to depressed passenger fares, the revenue earnings of its physical assets are inadequate and significantly lower than the railways in Thailand, Austria and Belgium.

    h. Regulation Formulation for Private Sector Participation (PSP)The RTF (PSP Working Group) has prepared a draft for the Ministerial Decree on the Regulation for the PSP and has been submitted to MOC. The Working Group has prepared also a computer based data and site plan on land use for join project with Private Sectors, whether BOT, BOO or other form of join business to invite PSP for utilising space of lands belongs to Perumka/PT.KA. While in the field of the core business itself few companies have expressed their interest but did not follow up due to commercial considerations.

    i. Implementation of Infrastructure Investment Plan

    Beside the double track construction in the Jakarta – Bandung corridor, GOI is also constructing double track at some locations, i.e. :- Cikampek – Cirebon line, funded by JBIC loan- Kroya – Yogyakarta line, funded by JBIC loan- Manggarai – Cikarang line (a double double track) funded by JBIC loan- Yogyakarta – Solo funded through own budget (APBN)- The next double track construction is in Cirebon – Kroya line which would be funded by

    China.

    9.1.3 The Physical Components Implementations

    a. Double Tracking Construction

    The construction of double tracking was done in the sections of Cikampek-Purwakarta 19 km, Ciganea-Sukatani 7 km, and Plered-Cisomang 6 km.Due to the slowness burreaucracy of the tender process, the completion of the double tracking civil works planned to be finished on April 2003 exceeded the original loan closing date (September 2002), and the loan was extended (one year, up to September 30, 2003). The construction works of the double tracking was slow progressing, and the completions were delayed i.e.: Cikampek – Purwakarta end of July 2003, Ciganea – Sukatani end of August 2003, Plered – Cisomang end of July 2003, comparing with the plan that all the double

    - 20 -

  • tracking work should be finished in June 2003.

    The double tracking on the Ciganea-Sukatani section is delayed due to the soil stabilization problem in the area. A significant landslide occurred in km 110, so that the completion was delayed and consequently the Loan was extended again for another one year, especially for completing the section and landslide countermeasure works. All works related with the landslide countermeasures was completed in December 2004 and the line has been in full operation since February 2005.

    b. Modernization of the Signalling System

    The signalling modernization was cancelled from the loan which resulted in reducing the loan from USD 105 million to USD 85 million. The system then modernized, supported by Dutch loan. The modernization of signalling system (electric) was cancelled from the Bank Loan, the existing system (electro mechanical) retained. GOI accepted Dutch Loan for the signalling modernization. and is currently operating.

    c. Stations Remodelling

    The remodelling of stations were implemented in 14 stations, i.e.: Cikampek, Cibungur, Sadang, Purwakarta, Ciganea, Sukatani, Plered, Cisomang, Cikadongdong, Rendeh, Maswati, Sasaksaat, Cilame and Padalarang.

    d. Modernization of Track Maintenance System

    At the implementation stage the tender process for the establishment of the Rail Reclamation Yard was very slow. The first tender failed, due to : (i) . reluctance of the management involved (traumatic fail experience in a similar project in 1980s, (ii) monetary crisis in the country.The 3 packages tendered (procurement of track materials and machineries, construction of Rail Reclamation Yard, training for operating personnels) then simplified into one single turn key package, helped by a Belgium consultant, and re-tendered. To the program, the work will be completed in mid 2004, far exceeding the loan closing date, resulting in an agreement to cancel the Rail Reclamation Yard, except the purchase of 100 km track new rails, including the sleepers and fastenings.

    The implemented activities are:· Procurement of new rails, PC sleepers with and without guard rails (for straight and curve

    sections)· Technical assistance for Bid Document preparation to convert the 3 bid documents into

    one single package and for bid evaluation (for the Rail Reclamation yard),

    As the consequence of the cancellation of the Rail Reclamation Yard construction, the modernization of the track maintenance system is not functioned, but the partial restoration (track rehabilitation program) to change R42 rails on wooden/steel sleepers to R54 rails on concrete sleepers is implemented as follows :

    · In FY 2004 - 17.15 km have been installed between Cimekar – Cicalengka and Ciawi – Rajapolah.

    · In this FY 2005 - 28.460 km will be installed between Bandung - Lebakjero and 11.105

    - 21 -

  • km between Purwakarta - Padalarang· In FY 2006 , 29.095 km between Lebakjero – Tasikmalaya and 14.190 km between

    Purwakarta – Padalarang has been programmed

    The replaced R42 rails shall be selected for use in lower tonnage lines.

    Training of Maintenance PersonnelThe training of maintenance personnel is directly related to the establishment of the Rail Reclamation Yard (RRY). Because the RRY was cancelled, consequently the training was also cancelled.

    Consultants ServicesThe consultant service related to this package was only for the design of the RRY and the change of tender documents, from three packages into one single package (Belgium Consultant).

    e. Modernization of Locomotive Maintenance System

    Activities implemented to achieve the modernization plan were:· Procurement of machinery such as Long Lead Machinery, Medium Lead Machinery and

    Short Lead Machinery· Construction and Installation civil works for Underfloor wheel lathe construction· Procurement of Unit Exchange Components and Spareparts· Consulting Services and Training T.A. for the Implementation of Locomotive Maintenance

    · A multi media modules for training

    The implementation has begun from June 2002 and up to date 70 % of the parts have been used up consisting of 97 % used for production of Unit Exchange Components and 3 % consumed for spare parts., due to the shortage of available maintenance spare parts This is caused by the fact that the utilization of components used are much faster than the production due to shortage of available spareparts.

    As an ilustration, the yearly requirement of spareparts for 149 GE locomotives is estimated at 91 billion rupiah while the available budget in 2005 is only 79 billion rupiah where 35 billion is allocated for the Unit Exchange Program to maintain buffer stock of components.

    The shortage of electricity supply for the Yogyakarta workshop has been resolved by optimizing the available capacity and arranging working time so that not all machines work at the same time. Some machines had broken down and repairs already undertaken by local resources. Up to date, 3 machines are still under process of repair and scheduled to be completed by end of July 2005. The utilization of machines needed some time for adaptation and change of mindset of the operators but is gradually being accepted. Another illustration is the use of the gear case washer machine to clean TM gear box which now takes only 3 hours for 1 locomotive set compared to previously 3 days for 1 locomotive set.

    With the numerous items (~ 6.000 items ) being circulated a computerized Management Information System is currently being developed to replace the current system.

    - 22 -

  • f. Institutional Developments

    To implement the development concept for Institutional Strengthening, some consultants’ services and procurement of equipment were implemented:- Network Simulation Model (NSM) for line capacity planning- Development of a Bridge Maintenance Management System (BMMS)

    The Long term study for the Jakarta-Bandung corridor development was cancelled on two reasons: the implementation will exceed the existing available allocated time, and the result will not be implemented in a quite long period. The NSM and the BMMS were already implemented and could support the reformed management to work in more sophisticated and accurate way, especially in operating the railway and maintaining its facilities.

    While the NSM software is running and in good condition, the main constraint now is the effort to collect and input all actual data (conditions). Since the implementation of the software, some changes have occurred to the original team due to dynamics of internal staff rotation where one of the key personnel have undertaken a masters program abroad and shall graduate on September 2005. PT KA BoD has planned for him to undertake this task.

    g. Alternative Route

    The works for improvement of the alternative route was already implemented and completed, but heavy landslides occurred on the hill above the Lampegan tunnel between Cianjur and Sukabumi, causing the collapse of the tunnel, and the route was impossible to be operated. Repair works for the tunnel is planned in this FY 2005.

    - 23 -

  • 9.2 Project Cost and Disbursement

    9.2.1 Project Cost Data

    Executing AgencyProject NamaLoan NumberLoan Effective DateLoan Closing Date

    Loan Amount :·

    OriginalOn GOI’s AccountOn Perumka/PT.KA Account

    ·

    Revised 1 (December 2, 1999)·

    Revised 2 (September 27, 2002)

    Loan Category (after revision – January 30, 2003)(1) Civil Works (Jkt - Bdg Corridor)(2) Civil Works (Loco Unit Exchange)(3) Jkt-Bad Corridor Signal(4) Equipment and Materials

    (a) for part B and C of the project(b) for part D of the Project

    (5) Consultant Services(a) for part A, D , E1 and E2 of the project(b) for part B and C of the Project

    Unallocated

    Ministry of CommunicationRailway Efficiency Project (REP)IBRD No. 4106 – IND13 June 199730 September 2003 for Category (2), (4)(b) and (5)(a)30 December 2004 for Category (1) and (5)(b)

    US $ 105,000,000US $ 85,200,000US $ 19,800,000( SLA ) Out of the US $ 105 millions, US $ 19,8 million is lended through by GOI/MOF to Perumka/PT.KA, named as Subsidiary Loan Agreement (SLA), where Perumka/PT.KA acts as the Executing Agency. This sum is not changed until the closing of the Loan.US $ 85,000,000US $ 57,625,000

    US $ 15,200,000US $ 200,000US $ 0

    US $ 17,360,000US $ 18,670,000 ( SLA )

    US $ 850,000 ( SLA ) US $ 4,300,000 US$ 1,095,000

    - 24 -

  • 9.2.2 Project Disbursement

    PART Currency ACTUAL CONTRACT

    VALUE

    IBRD FINANCING

    TOTAL DISBURSEMENT

    GOI LOAN (Excl.VAT)GOILOAN%

    Part A USDIDR

    00

    78,232958,792,208

    71,120871,629,2800

    071,120864,705,35999.54

    Part B USDIDR

    046,408,774,309

    9,655,629163,103,302,

    921

    8,777,845148,275,729,928

    46,364,456,6758,676,089

    148,159,823,49399.55Part C USD

    IDR00

    5,212,58567,115,125,0

    00

    4,738,71461,013,750,0000

    04,269,2273,208,502,29099.98

    Part D USDEURIDR

    9,485

    518,297,600

    19,933,612288,714

    10,100,278,183

    18,121,466262,467

    9,182,071,0758,622

    515,357,72118,119,127262,467

    9,131,694,37899.96Part E USD

    IDR00

    773,5181,932,602,33

    4

    703,1981,756,911,2130

    0669,9781,638,088,85694.83

    TOTAL USDEURIDR

    9,485

    46,927,071,909

    35,653,576288,714

    243,210,100,646

    32,412,342262,467

    221,100,091,4968,622

    46,879,814,39632,274,148

    262,467220,796,309,37699.70

    1 US$ = Rp. 9.0001 Eur = Rp. 9.000

    - 25 -

  • FINANCIAL POSITION BASED ON LOAN RECIPIENT

    -

    10,000,000

    20,000,000

    30,000,000

    40,000,000

    50,000,000

    60,000,000

    US

    $

    BUDGET 37,875,000 19,800,000 57,675,000

    CONTRACTED (fixed exchange rate) 37,518,537 19,722,949 57,241,486

    Disbursed (based on fixed exchange) 37,361,764 19,707,863 57,069,628

    Replenished (actual exchange rate) 37,842,784 19,781,731 57,624,515

    BALANCE 32,216 18,269 50,485

    GOI -MOC SLA - PT KA TOTAL

    t

    - 26 -

  • FINANCIAL POSITION BASED ON PROJECT PART

    -

    10,000,000

    20,000,000

    30,000,000

    40,000,000

    50,000,000

    60,000,000

    70,000,000

    US

    $

    CONTRACTED loan protion - fixed rate 167,968 25,252,926 11,518,020 19,404,163 898,411 57,241,486

    DISBURSED (fixed exchange rate 9.000) 167,287 25,138,291 11,515,833 19,396,227 851,988 57,069,628

    REPLENISHED - actual exchange rate 169,801 25,087,262 12,037,600 19,466,304 863,548 57,624,515

    Part A (Policy Reform)

    Part B (Jak - Bd corridor)

    Part C (Track maint syst)

    Part D (Loco maint syst)

    Part E (Institutional

    Dev.)TOTAL

    - 27 -

  • FINANCIAL POSITIONBASED ON DISBURSEMENT CATEGORY

    -

    2,000,000

    4,000,000

    6,000,000

    8,000,000

    10,000,000

    12,000,000

    14,000,000

    16,000,000

    18,000,000

    20,000,000U

    S$

    Budget 15,200,000 200,000 17,360,000 18,670,000 850,000 4,300,000

    contracted -fixed rate - 9.000 15,315,378 201,733 17,361,686 18,672,358 848,858 4,841,473

    disbursed - fixed rate - 9.000 15,313,512 201,733 17,319,286 18,672,358 833,772 4,728,966

    Replenished - actual rate 15,248,502 218,784 17,856,828 18,734,905 828,042 4,737,454

    (1) Civil works for Jak. BD Corridor

    (2) Civil works for loc. Unit Exch.-SLA

    (4)(a) Equip.and material for part B & C

    (4)(b) Equip. and Material for part D -

    SLA

    (5)(a) Cons. services for parts A ,D and E(1) -

    SLA

    (5)(b) Cons. services for part B, C, E(2) &

    E(4)

    - 28 -

  • 9.3 Lessons Learned

    9.3.1 Responsibility as Bank Borrower

    The loan is soft and for a long period, but the implementation is very tight, due to Bank policy implementing its process approach. Plenty covenants must be obeyed and fulfilled by GOI and PT KA, and in some cases not fully under control of the policy maker, such as the PSO, IMO, TAC budget arrangement, so that up to the closing of the loan, the agreed mechanism (rules) is not fully implemented. In some cases, the borrower feel as if haunted by the lender.

    On the other side, due to the deep involvement (penetration) of the Bank, some difference of opinions (friction) between the Bank and the Borrower were happened. To mention as an example: the KA-Clips case. GOI and PT.KA declared that the KA-Clips rail fastening is technically legalized to be installed on the PT.KA tracks. The Bank, however, will not legalize (and will not bare the cost of) the installation if the clips is not Internationally certified, but will support the installation in sidings only.

    9.3.2 Internal Borrower’s Problem

    a. Functional ProblemAlthough the executing organization for implementing the REP is good, but in some extent, parts of the organization were not functioning well as regulated in the MOC (establishment) Decree. This was happened due to the fact that not all related officials master fully the stipulations and covenants stated in the Goals & Policies, SAR, Loan Agreement and Project Agreement which were agreed by GOI and the World Bank, and become the basis for executing the project.

    b. Physical ComponentLaw 13/92 stipulated that the infrastructure is owned by the Government. Based on this principle, the infrastructure development and construction must be processed through the owner (proposed by the Project Manager, discussed in PT KA Board of Directors, proposed to DGLC, discussed to MOC and to Bappenas). This is time consuming. Based on the experience, DGLC implemented some shortcut steps and succeeded in making the process faster than before.

    c. Non Physical ComponentThe consistency in the Government decision is low. As an example : the PSO, IMO, TAC budget arrangement was agreed by three Ministers and three Director Generals, but the implementation is not following the agreed rules fully, due to the change in the related Government officials. The TAC as stated in the Goals & Policies will be applied in line with the Road User Charges. The RUC is not applied yet, but the TAC is applied.

    9.4 Sustainability of Railway Development

    The sustainability will depend on:· legal basis of the government policy to develop the railway. The existing document is the Goals &

    Policies, which has weakness in the format as a legal document and need to be renewed and published as a stronger document

    · strong commitment on the related officials in the Government and the company. The commitments to implement the Government Policy must be possessed by all related officials, materialized by strong support in the implementations

    - 29 -

  • · consistency in the implementation· availability of funds needed

    These factors should be developed for the sustainability of the railway transport sub-sector development

    9.5 Conclusions

    a. The REP Benefit for the Railway Transport Sub-sector Development

    As a Policy Reform Project, REP is successful in introducing the change in the railway management. To be mentioned among others are :- the mind set change, where most of related officials are now aware that the railway company

    must be handled as a service business, and that the business must be done not as usual.- repositioning of both the Government (as owner and regulator) and the railway company as

    operator, with clear relationships, administratively and financially.- although still not fully well applied, the PSO, IMO, TAC budget arrangement is now familiar

    and become a model for public sector services.

    b. The Follow Up

    The REP is actually not fully completed yet, both in the Non Physical Component and in the Physical Component. Up to the closing of the related funding from the Loan, the Non Physical (Policy Reform) is just reaching the decision and preparation for implementing the planned Organization Structure, which planned to be in full operational on year 2006.

    Based on past experience, the consistency of implementation needs to be guided and monitored by the policy makers, and escorted by experience professionals.

    On the Physical part, some cancelled packages need to be thought the possibility of execution to complete the development plan.

    (b) Cofinanciers:

    (c) Other partners (NGOs/private sector):

    10. Additional Information

    - 30 -

  • Annex 1. Key Performance Indicators/Log Frame Matrix

    Actual N o Objectives Indicator Unit

    Base Year 1995

    [SAR]

    Year 2002

    target [SAR]

    2003 2004 2005

    1 Policy Reform a. Action Plan Implementation % completed on schedule n.a.

    2

    Capital Investment Rationalization

    a. Annual revision of infrastructure investment plan

    submitted on t ime n.a.

    b. Financial evaluation of Perumka investment projects grater than

    Rp billion n.a.

    3 a. Loco availability at Bandung and Semarang % available 80 85 81.3 91 91

    Operational Performance b. Loco availability at other

    Java depots % available 82.3 85 83


Recommended