Date post: | 17-Jan-2016 |
Category: |
Documents |
Upload: | hortense-greene |
View: | 229 times |
Download: | 1 times |
THEORY OF CONSTRAINTS (TOC) AND CRITICAL CHAIN PROJECT MANAGEMENT (CCPM)LEO LAURAMAA IBM - HELSINKI, SEPTEMBER 20 2013
Presentation for PMI Chapter Finland
Leo Lauramaa - TOC & CCPM
2
Constraint
2013 09 20
Constraints are the physical limitations and policies that prevent the system from achieving more of its goal.
Bottleneck and constraint are often used interchangeably - pay attention to context
Time saved at the bottleneck can rapidly increase throughput. More efficient use of a non-capacity constrained resource does not
increase throughput– only gives illusion of efficiency. Traditional improvement provides less leverage since it encourages
improving the entire process, including non-constrained resources.
TOC provides high-leverage improvements – Almost 100% of the improvement comes from work done at the constraint.
Leo Lauramaa - TOC & CCPM
3
2013 09 20
“There really is no choice in the matter. Either YOU manage the constraints
or THEY manage you.
The constraints will determine the output of
the system whether they are acknowledged
and managed or not.”Source: Noreen, Smith, and Mackey, The Theory of Constraints and its Implications for Management Accounting (North River Press, 1995)
Leo Lauramaa - TOC & CCPM
4
Some remarks
2013 09 20
Most improvements to most links do NOT improve overall performance (the chain)
System wide, or "global" improvement are NOT equal to the sum of the local improvements The way to improve the organization is,
definitely not through inducing many local improvements
Thus a company should focus on best possible flow “allowed by” the "chain strength" – managing the constraint(s)!
Leo Lauramaa - TOC & CCPM
5
The constraint is
2013 09 20
The leverage point –
where the biggest effect
can be achieved from the least effort
Leo Lauramaa - TOC & CCPM
6
TOC, Theory Of Constraints
2013 09 20
provides a set of holistic processes and rules, all based on a systems approach,exploiting the inherent simplicity within
complex systems through focusing on the (few) “leverage
point(s)”as a way to synchronize and align the parts
to achieve ongoing improvement in the performance of the system as a whole
Leo Lauramaa - TOC & CCPM
7
Constraint Management
2013 09 20
System stability: Often times it makes sense to manage the bottleneck where it is rather than to try and break it1. Called Constraints Management2. Improvement becomes iterative process
a. Improve the bottleneckb. Ensure non-constraints have sufficient protective capacity
(PC)c. If they don’t then refocus improvement to add PC
Operating any part of the process above 85% of capacity will eventually create delays and interruptions – wait time increases exponentially as capacity utilization nears 100%
8
Leo Lauramaa - TOC & CCPM
TOC Knowledge in the Areas of
The four pillars of TOC Process of ongoing
improvement the five focusing steps the change question sequence buffer management
2013 09 20
Thinking Processes Manufacturing Distribution & Supply Chain
Retail
Sales & Marketing Finance & Measurements
Throughput accounting
Managing People Applying new technology Project management
Internal, Engineering, R&D, IT
Strategy Education Healthcare Public services Personal issues
Leo Lauramaa - TOC & CCPM
9
About TOC applications
2013 09 20
When TOC is used to manage production, manufacturers make the most of their capacity, finding anywhere from 15-50% more capacity than they thought they had – product flows faster, and orders are on time, every time.
When used in Distribution and Supply chains, TOC’s pull approach ensures near 100% availability while at the same time increasing inventory turns significantly.
The TOC-based selling process increases salespeople’s hit rate by systematically removing the obstacles to closing the sale.
TOC-marketing provides the capability to define an offering that satisfies a significant need of a market (unrefusable offer);
When used in Projects, TOC’s approach shortens the overall project timelines and projects are at least 95% on time, without compromising budget or scope.
And, when TOC is used to develop strategy, it puts all of the above together in an integrated way to lead the entire company to profitable growth and stability.
Leo Lauramaa - TOC & CCPM
10
The 25 Most Influential Business Management Books - The Goal (1984), by Eliyahu Goldratt
2013 09 20
Unusual among business management books for at least two reasons. Goldratt wasn't a titan of industry, a b-school professor,
or even a consultant, but rather a physicist. The Goal is a novel.
Centered on a production manager named Alex Rogo who has three months to turn around a deficient, unprofitable manufacturing plant, The Goal explains the "Theory of Constraints," which among other points incorporates the idiom,
"A chain is only as strong as its weakest link;"
and focuses on bottlenecks, the great hindrances to productivity.
Rogo uses the Socratic method to help fix his marriage, then applies it to his plant crew, coming up with steps to solve the plant's problems. The Goal has been in print since 1984, and a revised third edition was released on the book's 20th anniversary.
The Time Magazine, August 2011
Sold more than 3 million copies,
translated in 21 languages
Leo Lauramaa - TOC & CCPM
11
Eli Goldratt
2013 09 20
“We must have the honesty to see reality as it is, we must
have the courage to challenge assumptions, and above all, we must use the
gift of thinking. “
Leo Lauramaa - TOC & CCPM
12
The four pillars of TOC
2013 09 20
Leo Lauramaa - TOC & CCPM
13
Inherent simplicity: WHICH system is more complex?
2013 09 20
Leo Lauramaa - TOC & CCPM
14
Convergence - simplicity
2013 09 20
Everything within a system is connected by cause and effect relationships. Identification of the causes leads us to converge onto an apparent core problem/contradiction/conflict.
As long as you cannot clearly verbalize your intuition, the only thing you will communicate is your own confusion.
Leo Lauramaa - TOC & CCPM
Theory of Constraints
1970’s 1980’s 1990’s 2000’s
OPT
ProductionSupply Chains Distribution
ProjectsSales Marketing
Strategy & Tactics
The theory was developed by Dr. Eliyahu Goldratt, physicist (1947 – 2011)
Ever Flourishing
2013 09 20
15
Optimized Production Technique
Eli Goldratt was an educator, author, scientist, philosopher and business leader. But he was, first and foremost, a thinker who provokes others to think. Often characterized as unconventional, stimulating, and "a slayer of sacred cows," Dr. Goldratt exhorted his audience to examine and reassess their business practices with a fresh, new vision.
Leo Lauramaa - TOC & CCPM
16
1975 1985 1990 1995 2000 2005
Production, Throughput Accounting – OPT, The Goal, The Race, The Haystack Syndrome
The Thinking Processes – Jonah Program
Distribution, Marketing, Management Skills – It’s Not Luck
Project Management – Critical Chain
The TOC Holistic Approach
TOC & Technology– Necessary but not Sufficient
TOC & Business Strategy - Viable Vision
The Evolution of TOC – 30 years
2013 09 20
Leo Lauramaa - TOC & CCPM
17
The Five Focusing Steps of TOC
2013 09 20
1. IDENTIFY the system’s constraint.
2. Decide how to EXPLOIT the system’s constraint.
3. SUBORDINATE everything else to the above decisions.
4. ELEVATE the system’s constraint.
5. Warning!!!!! Do not let INERTIA become the system’s constraint. When a constraint is broken, return to Step 1.
A process of ongoing improvement that can be applied to any organization to continuously improve the achievement of
more “goal units”.
Leo Lauramaa - TOC & CCPM
18
The change question sequence
2013 09 20
Why change What to change To what to change How to cause the change How to measure and sustain the change
and achieve a process on ongoing improvement.
Leo Lauramaa - TOC & CCPM
19
TOC Buffer Management (BM)
2013 09 20
A control mechanism based on the amount of time (till the due date) or stock remaining used in the execution phase of TOC applications (operations, distribution and projects). Buffer management functions
Prioritize tasks/orders based on buffer penetration / consumption.
Signal when to expedite (red zone). Provide feedback to the planning process (changing
parameters etc.) Identify prime causes of delay to focus ongoing
improvement activity.
Leo Lauramaa - TOC & CCPM
20
Drum-Buffer-Rope (DBR)
2013 09 20
The TOC method for scheduling and managing operations when there is an internal resource constraint.
Drum
Internal constraint
Rope
Release Inventorybuffer
21
Leo Lauramaa - TOC & CCPM
Layers of resistance
The six layers of resistance, as expressed by the person(s) resisting change, are:
1. Disagree on the problem. 2. Disagree on the direction of
the solution. 3. Disagree that the solution
solves the problem. 4. Yes, but there are potential
negative consequences. 5. Yes, but there are obstacles
to implementing the solution.
6. Unverbalized fears.
More recently, nine layers of resistance have been identified:
0. “There is no problem.”1. Disagreement on the problem. 2. “The problem is out of my control.”3. Disagreement on the direction for the
solution. 4. Disagreement on the details of the
solution. 5. “Yes, but… the solution has negative
ramification(s).”6. “Yes, but… we can‘t implement the
solution.”7. Disagreement on the details of the
implementation. 8. You know the solution holds risk. 9. “I don‘t think so” – Social or
psychological barriers.
2013 09 20
“Resistance” is a force for managing change.
How? By systematically overcoming each
layer of resistance and obtaining buy-in.
TOC tool: The thinking processes
Leo Lauramaa - TOC & CCPM22 2013 09 20
“Show me how you measure me, I’ll show you how I’ll behave”
"If you measure me in an irrational way, don't complain about irrational behavior."
Eli Goldratt
Leo Lauramaa - TOC & CCPM
23
Cost World vs. Throughput World
2013 09 20
Cost World Thinking
”We want to minimize the cost of
capacity”.
Throughput Thinking
”We want to maximize the use of
capacity”.
Leo Lauramaa - TOC & CCPM
24
TOC metrics – Throughput accounting
2013 09 20
Metrics - Real improvement vs. the goal is measured by the change (Δ) in T, I, &OE: ΔT: Increasing Throughput - cash flow over and
above truly variable costs ΔI: Reducing Investment - cash tied up in the
business, including working capital items such as inventory and accounts receivable
ΔOE Reducing Operating Expenses - costs of running the business, not including raw materials
System level metricsNet Profit = ΣT – ΣOEROI = Net Profit / ICash Flow = ΔT- ΔOE / ΔIProductivity = T / OEInvestment Turns = T / I
Leo Lauramaa - TOC & CCPM
25
Green & Red curve
2013 09 20
Performance
Time
Leo Lauramaa - TOC & CCPM
26
Three mechanisms distorting management attention
2013 09 20
Fear of complexity Imposing Simplicity on Complexity
create and manage sub systems – local optima, conflicts between sub sections
Fear of Unknown Imposing Certainty on Uncertainty
manage by “accurate” indicators – micromanagement, reacting to “noise”
Fear of conflicts Imposing Harmony on Conflicts
strive for a compromise between extremes – struggling with unacceptable compromises, dealing with symptoms other than core conflict, loose-loose in stead of win-winBAD MULTI TASKING
LOOSING FOCUS
27
Logical Thinking Process for Strategy
Goal Tree
CurrentReality
Tree
EvaporatingCloud
FutureReality
Tree
PrerequisiteTree
Critical Chain Project
By Bill Dettmer
Leo Lauramaa - TOC & CCPM28
Focus (CRT) – One of the TOC ways to analyze reality
We are losing sales
Our reputation is deteriorating
It is impossible to have a good
forecast
We are losing profit
margins
We have cash limits
We have space
limitations
We cant hold the full product
portfolio
We have too many write
offs
We have shortages of some items
We are overstocked with some
items
Our suppliers are not reliable
Our suppliers do not react fast enough
The common practice- launch multiple improvement / correction initiatives. Spread your resources & management attention too thin and waste a lot of resources with limited results.
We give to many discount
s
We are losing sales
Our reputation is deteriorating
It is impossible to have a good
forecast
We are losing
profit/profit margins
We have cash limits
We have space
limitations
We cant hold the full product portfolio
We have too many write
offs
We have shortages of some items
We are overstocked with some
items
Our suppliers are not reliable
Our suppliers do not react fast
enough
We give to many
discounts
2013 09 20
Leo Lauramaa - TOC & CCPM
29
Some reported TOC results
2013 09 20All material © CMG &/or CMS, 2004
Lead Times
70%
Cycle Times
65%
InventoryLevels 49%
44%On-Time Delivery,Availability
63%73%
Revenue,Throughput
CombinedFinancial
The World of Theory of Constraints, Vicky Mabin & Steven Balderstone,
St. Lucie Press, 1999
Leo Lauramaa - TOC & CCPM
30
ABB – Multiple TOC based initiatives
2013 09 20
Average payback time 2,14 months!
Leo Lauramaa - TOC & CCPM
31
TOC RESULTS – CASE SANMINA TOC-LEAN-SIX SIGMA
2013 09 20
Leo Lauramaa - TOC & CCPM
32
About TOC LEAN and SIX SIGMA
2013 09 20
The best results to improve the system performance is achieved by: Using TOC / Constraint Management as a
focusing mechanismAnd then Using Lean and Six Sigma on focused way
Recommended reading:Velocity: Combining Lean, Six Sigma and the Theory of Constraints to Achieve Breakthrough Performance A Business Novel by Dee Jacob, Suzan Bergland, Jeff Cox, 2010
33
Leo Lauramaa - TOC & CCPM
Legacy from Eli Goldratt since 1997
Critical Chain Project Management (CCPM)
2013 09 20
The TOC solution for planning, scheduling, and managing
performance in a project environment.
Leo Lauramaa - TOC & CCPM
34
Typical complaints
2013 09 20
Our project lead times are too long. Project ROI and cash flow are frequently jeopardized. Due dates, budget, quality and/or scope are frequently
compromised. There is a constant battle to reduce safety time. We sometimes miss dependencies in the project plan. Deliverables are not always clear. Critical resources are losing a lot of time moving from one
task to another and having to report progress on all tasks.
Erroneous belief: In order to finish the project on time, we must finish each task on time.
35
Background phenomena
2013 09 20Leo Lauramaa - TOC & CCPM
Early start Start the project sooner, you’ll finish it sooner?
Parkinson’s law Work expands so as to fill the time available for its completion.
And … work continues because it must take the full scheduled time to be of high quality.
The “Students syndrome” When people will start to fully apply themselves to a task just at the last
possible moment before a deadline. This leads to wasting any buffers built into individual task duration estimates. What if and when Murphy will strike?
Bad Multitasking Occurs when resources stop work on a task to start another task even
though they could still work on the first task. The lead time increases significantly, even without considering
additional setup time.
Significant safety is inserted into the project plan and wasted.
Leo Lauramaa - TOC & CCPM
36
The vicious cycle
2013 09 20
Resources receive a poor evaluation for missed deadlines
Resources will inflate estimates more
The project still does not complete on time, within budget and scope
Promised lead times for future projects are even longer (causing lost work?)
Leo Lauramaa - TOC & CCPM
37
Responsibilities & task estimates
2013 09 20
Reliability of a person and negotiating position
How much safety buffer is needed, if you must be fully in charge of your task estimate?- what if the task itself is on planning stage a bit fuzzy?
Resources do not typically report early finishes.
Leo Lauramaa - TOC & CCPM
38
Critical Path vs. Critical Chain
2013 09 20
Critical Path Longest sequence of task dependencies in terms of
time. This is the traditional term and path that is NOT used in TOC.
Critical Chain Longest sequence of task and resource
dependencies in terms of time. In other words, it is the longest sequence of dependencies, with explicit consideration of resource availability.
Leo Lauramaa - TOC & CCPM
39
CCPM in breaf
2013 09 20
Objective of a project: On time, full content, within budget
In a single-project environment the critical chain project management solution includes the following:
1. Removal of existing behaviors that are harmful for the project
2. A plan, or project network, that includes all task and resource dependencies as well as time estimates with safety removed
3. A schedule showing the critical chain and the buffers4. Implementation of new behaviors critical to streamlining flow
such as the relay runner work ethic and frequent reporting of work remaining
5. Expediting and improvement activities based on buffer management
Leo Lauramaa - TOC & CCPM
40
CCPM principle
2013 09 20
Securing the project, not individual tasks
Leo Lauramaa - TOC & CCPM
41
Buffer management for projects
2013 09 20
Buffer Management is the process used to plan for and take any necessary corrective actions based on the impact of actual and predicted variability.
These actions include: Assessing status of the project and, if appropriate, taking
steps to recover schedule on the few tasks that are having impact,
Assessing status and taking steps to recover schedule on the few materials that are having impact,
Prioritization of available task work for a given resource to minimize queuing on the wrong tasks, and
Reducing developing peak loads that can lead to serious resource delays.
Leo Lauramaa - TOC & CCPM42
D We Feel Pressure to
Add significant safety time to each task time
estimate
D’(But) We also feel pressure to Add the absolute
minimum safety to task time estimates
C We must Contribute to
creating a competitive lead
time advantage and not create
opportunities for wasting time
B We must Make reliable
promisesA
Satisfy customer and shareholder
expectations (time, budget,
scope)
Assumption
Assumption
Assumption
Assumption
Assumption
Prerequisite / TacticsRequirement / Strategy
Objective
Dilemma regarding: Our project lead times are too long Background: Our customers have been complaining that our project lead times are too long.
Some customers have defected to our competitors as a result of our long lead times.
2013 09 20
Leo Lauramaa - TOC & CCPM43
D We Feel Pressure to Frequently multitask
D’(But) We also feel pressure to Limit the amount of multitasking
C We must Minimize time lost
on “set-ups” and
progress reporting
B We must Ensure that
progress is made on all tasks
A Satisfy customer and
shareholder expectations (time, budget,
scope)
Prerequisite / TacticsRequirement / Strategy
Objective
Dilemma regarding: Critical resources are losing a lot of time moving from one task to another and having to report progress on all the tasksBackground: Our resources have to spend a long time getting up to speed on a task that was set aside for a period of time. This time is non-productive time. A significant amount of set-up and set-down time is affecting resource productivity.
2013 09 20
Leo Lauramaa - TOC & CCPM44
D We Feel Pressure to
Start work as early as possible
D’(But) We also feel pressure to
Delay start of work as late as possible (especially on
subcontractors)
C We must Postpone spending
B We must Ensure that we have sufficient safety for each
taskA Satisfy customer and
shareholder expectations (time, budget,
scope)
Prerequisite / TacticsRequirement / Strategy
Objective
Dilemma regarding: Project ROI and cash flow are frequently jeopardized
Background: We must pay our subcontractors when they start working for us and for materials when we start using them. However, we do not receive payments until progress is made on the project. Therefore, our cash outflows exceed our cash inflows during initial stages of projects.
2013 09 20
Leo Lauramaa - TOC & CCPM45
D We Feel Pressure to
Take actions / use rules that will
optimize task and resource
performance (increase safety,
multitasking; start as early as possible)
D’(But) We also feel pressure to
Take actions / use rules to improve overall project
performance (reduce safety, multitasking;
start as late as possible)
C We must Finish projects in
minimum time and cost
B We must Complete the
project based on the original promises
A Satisfy customer and
shareholder expectations (time, budget,
scope)
Prerequisite / TacticsRequirement / Strategy
Objective
Systemic Core Conflict/Dilemma
2013 09 20
Leo Lauramaa - TOC & CCPM
46
Direction of the Solution
2013 09 20
Do not turn estimates into commitments. Minimize the wasting of safety. Enable early and late finishes to compensate
each other. Minimize bad multitasking.
47
Example
2013 09 20Leo Lauramaa - TOC & CCPM
Remove task safety
Resource contentionCritical chain Add project safety
Leo Lauramaa - TOC & CCPM
48
Example: Insert the feeding buffers
2013 09 20
The feeding buffer, which is half the safety removed from the non-critical chain tasks, is placed where a path feeds into the critical chain or end of the network
Leo Lauramaa - TOC & CCPM
49
Example: Insert the resource buffers
2013 09 20
Project lead time = 90(25% less than 120)PB is 1/3 of lead time
50
Critical Chain Project Management Before (Traditional)
Resolving Resource Contention (CC)
Aggressive Schedule & Inserting Buffers
A-14 C-16
E-20
B-10 C-16
D-20 C-16
E-20 LT = 72 days
A-7 B-5 FB-6 C-8
D-10 C-8E-10 PB-18 LT = 54 days
A-14 C-16
D-20 C-16E-20
B-10A-14 C-16E-20
B-10LT = 60 days
Note: ALWAYS check “given” information:
are times padded or has padding been removed?
Leo Lauramaa - TOC & CCPM
51
Five Focusing Steps - CCPM
2013 09 20
1 Identify the system’s constraint(s) Identify the critical chain (the longest sequence of task and resource dependencies)
2 Decide how to exploit the systems constraint(s) Ensure that the critical chain time is minimized, but protected strategically with safety
We use an early warning mechanism (resource buffer) to ensure that resources working on the critical chain are prepared to start on time or start earlier than the scheduled start date if gains were achieved in upstream tasks on the critical chain
The project buffer (which is HALF of the safety removed from critical chain tasks) is used to ensure timely or early completion of the project overall.
Introduce and use measures that reinforce road runner and relay race behaviors.
3 Subordinate everything to the above decision. Use feeding buffers (HALF of the safety removed) wherever non-critical paths/tasks
feed into a critical chain task [to protect the constraint from delays]. Schedule non-critical chain tasks to start as late as possible. Introduce and use measures to reinforce road runner and relay race behaviors
[eliminates problematic behaviors].
4. Elevate the System’s Constraint(s) Shorten project lead time by adding resources to break resource contention.
Leo Lauramaa - TOC & CCPM
52
Fever chart
2013 09 20
Progress along the Critical
Chain is typically
accompanied by a reduction in the amount of safety that is
required in the Project Buffer
– The overall
Project Buffer requirement is
indeed dynamic, not static,
during project execution.
% Critical Chain completed0 100
33%
66%
100%
% P
roje
ct B
uff
er
Consu
med
Leo Lauramaa - TOC & CCPM
53
Strategy & Tactics Tree - Projects
2013 09 20
http://www.goldrattresearchlabs.com/default.aspx?ven=goldrattmarketinghttp://www.youtube.com/watch?v=5QVLjQJdIBoCheck these links
All generic TOC application S&T Treesare available free of charge – see the link below
Leo Lauramaa - TOC & CCPM
54
CCPM results
2013 09 20
Leo Lauramaa - TOC & CCPM
55
CCPM results
2013 09 20
Leo Lauramaa - TOC & CCPM
56
Practical Ideas for Improving Project Execution
2013 09 20
Start projects as late as possible Cut the number of projects in the portfolio by
half (don’t start a new one until you finish one)
One person decides work priorities Don’t start a task unless you can finish it
completelyBy Mark Woeppel /Pinnacle Strategies
We are planning a TOC / CCPM training together with Pinnacle in Finland.
-Are you interested?
Leo Lauramaa - TOC & CCPM
57
CCPM software
2013 09 20
CCPM+: Advanced Projects Inc. - http://www.advanced-projects.com/ ProChain : ProChain Solutions Inc. - http://www.prochain.com/ cc-Pulse & cc-MPulse : Spherical Angle - http://sourceforge.net/projects/cc-
mpulse/ Exepron - http://exepron.com/ Lynx - www.a-dato.net PS8 : SciForma - http://www.sciforma.com/en-uk/ Adept Tracker AgileCC - http://www.adepttracker.com/agilecc/index.html Guided Innovations - http://www.guidedinnovation.com/simplecc/ Aurora - http://www.stottlerhenke.com/products/index.htm Being Management - http://www.toc-ccpm.net/eng/bm2.html FLOW MPM from Glow Management - http://www.glow-management.com/ Concerto: Realization - http://www.realization.com/ Schedlyzer Lite: , http://www.optisol.biz/lean-production.html Sciforma VPM Lite (free IOS app) – very simple…
58
Leo Lauramaa - TOC & CCPM
Other links
Books The Goal - Special Edition Eli Goldratt
(1 May 2013) Eli Goldratt, Jeff Cox 2004 Critical Chain, Eli Goldratt 1997 Simplifying Innovation, Mike Dalton
2010 Ebook Theory Of Constraints – Do It
Yourself Kit For Small and Medium Sized Companies, Rajeev Athavale, 2011
TOC roof organization TOCICO see www.tocico.org (also free
guest membership possibility)
Best free TOC source www.dbrmfg.co.nz/
Other TOC links http://www.toc.tv order
newsletter http://www.goldratt.com
Some TOC linkedin groups TOC4U – Theory of Constraints TLS – TOC Lean Six Sigma TOC4FINLAND Critical Chain Visual Project Management
2013 09 20
Leo Lauramaa - TOC & CCPM
CV Summary Leo Lauramaa
2013 09 20
59
Age 55, M. Sc. (Econ), ConsultantCompany: Kukonaskel Oy2008 Management ConsultantKaukomarkkinat Oy1981 - 20082005 – 2008 Director strategic development, management systems,
member of management team1998 – 2005 Deputy Director, development, international activities &
group level1989 – 1998 Controller/Business Controller, import, international
activities
Strengths Good business overview, holistic approach Wide experience of strategy and development work in different
businesses and levels Strategy driven development projects with different tools including
process modeling Helping in change management, e.g. in integration or
organizational change situations Positive purposeful approach, analytical, creative problem solving
Using constantly TOC thinking, tools and applications on consulting engagements
Languages finnish (native), english (good), swedish (moderate)
leo.lauramaa (at) kukonaskel.com +358 400 727 625
60
Leo Lauramaa - TOC & CCPM
Thank You for Your attention!
2013 09 20