Date post: | 21-Mar-2017 |
Category: |
Documents |
Upload: | allana-robertson |
View: | 62 times |
Download: | 0 times |
Real Time, Low Costs Technologies for Determining Treated Oil & Gas Produced Water StabilityMaster of Science Research Project Allana Robertson
2
Road Map through Oil & Gas ProjectI. Introduction
A. Statement of ProblemB. Approach to Solve the ProblemC. Research ObjectivesD. Significance of Study
II. Description of WorkA. Research Design
i. Examples of Treatment SystemsB. Operation Strategy and Sampling Locations
Sampling Scheme C. Instrumentation: Experimental Filtration Unit
SetupD. Instrumentation: Chemical Analysis
InstrumentationE. Results & DiscussionF. Findings Related to Objective One:
Microbial Activity Post Continuous Treatment
G. Findings Related to Objective One: Reduction of Microbial Electron Donors and Acceptors
H. Findings Related to Objective One: Reduction of Microbial Electron Donors and Acceptors
I. Findings Related to Objective One: Problems/ Successes
i. Filtration Technology DemonstrationJ. Findings Related to Objective Two:
Equipment FailureK. Findings Related to Objective Two: Storage in
Open and Sealed Containmenti. Examples of Containment
L. Findings Related to Objective Two: Problems/ Successes
III. ConclusionsA. Main IssuesB. Lessons LearnedC. Future Outlook
05/02/2023
Introduction
05/02/20234
I. A. Statement of Problem• Oil & Gas production in arid locations is forcing many companies to
consider produced water reuse. Microbial activity has been overlooked when evaluating produced water quality for reuse. In addition, general standards do not exist for grading produced waters even after treatment.
• Because of this, the following has been documented: • Higher incidence of MIC related corrosion • Larger expenditures on equipment maintenance and replacement • More frequent equipment malfunctions
05/02/20235
I. B. Approach to Solve the Problem• Evaluate the use of membrane filtration to reduce microbial activity in
treated produced waters. Chemical components related to microbial growth will be monitored to determine activity potential in treated produced waters during storage. Results will be adapted to current field procedures during future A&M field trials.
05/02/20236
I. C. Research Objectives • Determine water stability during continuous treatment
• Microbial activity• Reduction of microbial electron donors and acceptors• Reduction of dissolved TIC & TOC• Total hardness reduction (QC)• Microbial nutrient levels post treatment
• Determine water stability during suspended treatment• Short term and Long term equipment failures• Storage in open and sealed containment
05/02/20237
I. D. Significance of Study • Concluding this study, the
following will be understood from the experimental work:
Broader understanding of microbial activity in produced waters.
Better understanding of the need to treat produced waters prior to reuse.
Open access to research data for use in developing treatment process SOP’s.
Enhanced environmental awareness
Description of Work
05/02/20239
II. A. Research Design
05/02/202310
II. A. i. Research DesignExamples of Treatment Systems
NF Treatment System
MF Treatment System
05/02/202311
II. B. Operation Strategy and Sampling Locations• Pre-treatment:
• Two stage pre-treatment process and stored in the MF feed tank
• Microfiltration (MF):• Pretreated water pumped into MF system running in concentrate mode• MF permeate transferred to the NF feed tank in 5 gallon increments
• Nanofiltration (NF): • MF permeate pumped into NF system running in concentrate • NF permeate was collected and stored in 5 gallon increments
Ideally tanks would be used to collect all process waters when running a system with larger flow rates and feed volumes greater than benchtop scale.
05/02/202312
II. B. Operation Strategy and Sampling Locations• Samples were taken from the
following locations:
1 Raw feed2 Pretreat3 MF feed4 MF permeate5 NF feed6 NF permeate
• Single samples were taken of the following: • Raw feed• Pretreat
• Replicate samples were taken of the following: • MF feed • MF permeate• NF feed • NF permeate
05/02/202313
II. B. Operation Strategy and Sampling Locations
Run Number of Replicates for MF Concentrate
Number of Replicates for MF Permeate
Number of Replicates for NF Concentrate
Number of Replicates for NF Permeate
Failure Trial 3 4 1 1
Trial 1 2 4 2 2
Trial 2 3 3 3 3
05/02/202314
II. C. Instrumentation: Experimental Filtration Unit Setup• See Handout
05/02/202315
II. D. Instrumentation: Chemical Analysis InstrumentationField Technologies• HACH HQ40d• HACH 2100P Turbidometer• Fischer Scientific Accumet AP74
DO meter• Bactiquant-WATER Meter Laboratory Benchtop• HACH Spectrophotometer DR
5000• GE InnoVox TOC Analyzer
Commercial Laboratory • Potassium • Alkalinity• Carbonate• Bicarbonate• Total phosphorus• Total dissolved iron • Sulfate• Magnesium• Calcium• Total hardness• Chloride
05/02/202316
II. D. Instrumentation: Chemical Analysis InstrumentationNew Microbial Field Technology• Bactiquant-WATER meter
• Total active biomass• Mobile, field ready • Yields results in 10-30 minutes
05/02/202317
II. E. Results & DiscussionTreatment of Produced Water
• Continuous Processing Trialsi. Trial 1ii. Trial 2
• Failure Testi. Minor and major equipment failuresii. Storage during failures
05/02/202318
II. F. Findings Related to Objective One: Microbial Activity Post Continuous Treatment
i. Trial 1 ii. Trial 2
a. Reduction of total biomass activity • Continuous processing yields best results for
reduction of microbial activity• Linear decline in microbial activity with each
processing step• MF treatment reduces raw water microbial
populations• NF treatment reduces microbial populations
from contamination during open air processing
MF_Raw_Feed
Pretreated MF_Permeate NF_Permeate0.1
1
10
100
1000
10000
100000
1000000
171.40
3.57 5.44 3.25
174,381.20
22,255.60
68.80
0.15
58,815.00
2,041.30303.70
0.83
Failure TestTrial 1Trial 2
Bact
iqua
nt V
alue
(m
l^-1
)
05/02/202319
II. G. Findings Related to Objective One: Reduction of Microbial Electron Donors and Acceptors
i. Trial 1 ii. Trial 2
b. Reduction of microbial nutrients• Metabolic cycling of electron donors• Total soluble iron exhibited the highest
reduction
MF_Raw
_Fee
d
Pretre
ated
MF_Per
meate
NF_Per
meate
0
10
20
30
40
50
60
70
80
90
100
18.91
0.01
10.02251.925.70
10.051.37 0.04
Trial 1 Total Soluble IronTrial 2 Total Soluble IronTrial 1 Ammonium, Ammonia, NitriteTrial 2 Ammonium, Ammonia, NitriteSp
ecie
s (m
g/l)
05/02/202320
II. H. Findings Related to Objective One: Reduction of Microbial Electron Donors and Acceptors
i. Trial 1 ii. Trial 2
b. Reduction of microbial nutrients• Metabolic cycling of electron acceptors. • Improved water quality as a result of
increased DO levels
MF_Raw_F
eed
Pretre
ated
MF_Per
meate
NF_Per
meate
0
50
100
150
200
250
300
0
1
2
3
4
5
6
7
0.730.73
0.7375 0.550.31
0.330.32 0.20
0.04
3.37
2.332.61
0.040.04 0.04 0.04
2.07
2.72
5.46255.72
0.79
2.97
5.37
Trial 1 ManganeseTrial 2 ManganeseTrial 1 NitrateTrial 2 NitrateTrial 1 Dissolved Oxygen Trial 2 Dissolved Oxygen Trial 1 SulfateTrial 2 Sulfate
Spec
ies
(mg/
l)
05/02/202321
II. I. Findings Related to Objective One: Problems/ Successesiii. Problems/Successes
• Problems• Lack of digital flow meter integration• Inconsistent replicate numbers
• Successes• Larger volume of permeate from new NF treatment system• Data collected during all 3 treatments was consistent
05/02/202322
III. I. i. Filtration Technology Demonstration
Raw Produced Water
MF Permeate Water
MF Permeate Water
NF Permeate Water
5 minutes after
collection
05/02/202323
II. J. Findings Related to Objective Two: Equipment Failure
i. Minor and Major Equipment Failures
• Minor equipment failure• 1 hour downtime• Total biomass activity
• Major equipment failure• 4 day downtime• Total biomass activity
Raw Feed Pretreated MF Permeate Minor Failure
Stored Water Major Failure
NF Permeate1
10
100
1000
171.40
3.575.44
11.83
3.25
Bact
iqua
nt V
alue
(m
l-1)
05/02/202324
II. K. Findings Related to Objective Two: Storage in Open and Sealed Containment
ii. Storage During Failure• Storage in simulated open air
containment• Elevated total biomass activity levels
• Storage in simulated sealed containment• Lower total biomass activity levels
0 40
5
10
15
20
25
2.77
4.68
20.6
Sealed Water SampleOpen Air Water Sample
Time (days)
Bact
iqua
nt V
alue
(m
l-1)
05/02/202325
II. K. i. Findings Related to Objective Two: Examples of Containment
Sealed ContainmentOpen Air Containment
05/02/202326
II. L. Findings Related to Objective Two: Problems/ Successes
iii. Problems/Successes• Problems
• Replicate sampling • NF system limited the volume of NF treated permeate • MF and NF systems are analog not digital• Data appears to be collected in a scattered pattern, not consistent • Select HACH field kit analysis appeared to be inconsistent with commercial laboratory
• Successes• Data supported steady state assumption• Data analysis re-directed chemical analysis efforts• Commercial laboratory results made testing more manageable per trial• Bactiquant analysis was consistent throughout the trial • Replicate averaging yielded consistent chemical ion data for data analysis.
Conclusions
29
05/02/202328
IV. A. Main Issues• Down Market
• Oil & Gas companies must cut production costs to survive.
• Maintenance costs for maturing and matured producing wells are rising
• Environmental Awareness• Water supplies in arid oil & gas producing locations • Reuse without treatment and treatment standards• Oil & Gas currently experiencing pre-regulation phase
05/02/202329
IV. B. Lessons Learned
• Treatment of raw produced water prior to use in drilling and completions is necessary to lower maintenance costs• Reduced MIC corrosion• Reduced reservoir plugging
• General treatment guidelines will be needed to guide companies during treatment assessment and design • Pretreatment-necessary• Treatment levels- recommended according to need• Quality control throughout treatment process- necessary
05/02/202330
IV. C. Future Outlook• 2017 market increase (hopefully)
• Everyone can go back to work!
• Publication of Produced Water Treatment Guidelines
• Increased produced water reuse• Reduced MIC• Reduced scaling
• Ease of tensions between municipal and Oil & Gas
05/02/202331
Midland, TX April, 2015Northeast, TX Area8 Years Ago
05/02/202332
Special Thanksto
Committee Members
Dr. Xingmao “Samuel” MaAssociate Professor Zachry Department of Civil EngineeringSpecialty: Environmental Engineering
Dr. Bill BatchelorR.P. Gregory ’32 Chair ProfessorZachry Department of Civil EngineeringSpecialty: Environmental Engineering
David BurnettHarold Vance Department of Petroleum EngineeringTEES Associate Research Scientist Director of Technology GPRI
05/02/202333
Special Thanksto
Technical Support
Petroleum Engineering Staff for helping with technical logistics
Jennifer Fichter for inviting me attend her microbial field trial and sharing data
GPRI Staff for helping run filtration equipment and transport raw produced water.
Mikah Bradford for networking and connecting me with Jennifer Fichter
Ecolyse microbiologists for help with metagenomic analysis of raw SWD water. Also without their help, the amazing results achieved from Jennifer’s field trial would not have been possible.
Thank you for supporting our research by providing SWD water at no cost for all treatment runs.
Questions?
05/02/202335
V. A. Findings Related to Objective One: Reduction of Dissolved Organic Carbon i. Trial 1 ii. Trial 2
c. Reduction of total dissolved organic carbon
• TOC levels increase during the failure test
• TOC levels decrease during both trial 1 and trial 2.
• Post MF treatment, produced water contains roughly 84-88% TOC
• Post NF treatment, produced water contains roughly 45-54% TOC
MF_Raw
_Fee
d
Pretre
ated
MF_Per
meate
NF_Per
meate
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
140.00%
36.69%
98.75%
126.26%100.00%
86.94%84.16%
54.19%
104.43%
88.75%
45.84%
Failure Test Total Organic CarbonTrial 1 Total Organic CarbonTrial 2 Total Organic Carbon
% T
otal
Org
anic
Car
bon
05/02/202336
V. B. Findings Related to Objective One: Reduction of Dissolved Inorganic Carbon i. Trial 1 ii. Trial 2
c. Reduction of total dissolved inorganic carbon
• TIC appears to decline as treatment progresses for all three trials.
• Post MF treatment, produced water contains roughly 91-94% TIC
• Post NF treatment, produced water contains roughly 66-67% TIC
MF_Raw
_Fee
d
Pretre
ated
MF_Per
meate
NF_Per
meate
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
100.00%
12.92%
68.41%
42.92%
102.37%91.97%
66.18%
92.67%
94.25%
67.56%
Failure Test Inorganic CarbonTrial 1 Inorganic CarbonTrial 2 Inorganic Carbon
% T
otal
Inor
gani
c C
arbo
n
05/02/202337
V. C. Findings Related to Objective One: Total Hardness Reduction i. Trial 1 ii. Trial 2
d. Reduction of total hardness• Calcium and magnesium appear to
decline linearly with respect to treatment stages.
• Produced waters exhibit reduced scaling potential post treatment with NF technology.
• Total hardness reduction acts as QC for treatment scheme
MF_Raw
_Fee
d
Pretre
ated
MF_Per
meate
NF_Per
meate
0
10000
20000
30000
40000
50000
60000
0
5000
10000
15000
20000
25000
30000
35000
29185.71
21648.92
29130.77
22278.24
2045.27 2057.76 2039.45 1503.36
4817.96 4134.39 4857.08 1570.99
Trial 1 Calcium-CaCO3Trial 2 Calcium-CaCO3Trial 1 Magnesium-CaCO3Trial 2 Magnesium-CaCO3Trial 1 Total Hardness-CaCO3Trial 2 Total Hardness-CaCO3
Har
dnes
s S
peci
es-C
aCO
3 (
mg/
l)
05/02/202338
V. D. Findings Related to Objective One: Microbial Nutrient Levels Post Filtration Treatment with MF and NF Systems
Nanofiltration Failure Test Trial 1 Trial 2 Carbon: 100.00% 100.00% 100.00%
Nitrogen: 21.27% 146.36% 23.35%
Sulfur: 1.36% 60.56% 3.31%
Phosphorus: 1.61% 20.76% 3.48%
Sulfate: 4.07% 181.30% 9.92%
Iron: 0.02% 3.63% 0.02%
Manganese: 0.09% 1.04% 0.11%
Oxygen: 3.29% 10.80% 3.13%
Microfiltration Failure Test Trial 1 Trial 2 Carbon: 100.00% 100.00% 100.00%
Nitrogen: NA 85.12% 16.25%
Sulfur: 17.12% 85.93% 4.40%
Phosphorus: 3.30% 14.54% 3.41%
Sulfate: 51.24% 257.28% 13.18%
Iron: 0.10% 12.83% 0.47%
Manganese: 0.45% 0.94% 0.11%
Oxygen: NA 6.99% 1.01%