Faculty of Engineering Science and Technology Department of Civil and Transport Engineering
Date: 11 june 2012
MASTER THESIS (TBA4910, master thesis)
Spring 2012
Mignote Beyene
English title: Effect of Speed Reductions for Train Punctuality
Norwegian title Hastighetsnedsettelser Og Punktlighet
NORWEGIAN UNIVERSITY OF SCIENCE AND TECHNOLOGY DEPARTMENT OF CIVIL AND TRANSPORT ENGINEERING
Report Title: Effect of speed reductions for train punctuality
Date: 11 -06- 2012
Number of pages (incl. appendices):
Master Thesis √ Project Work
Name: MIGNOTE ABATE BEYENE
Professor in charge/supervisor: NILS OLSSON
Other external professional contacts/supervisors:
Abstract: The rail way sector has been losing market, required increased subsidies and failed to generate anticipated rate of return. Therefore there has been a strong interest to measure the performance of railway operators in terms of punctuality. It is evident that In Norway punctuality shows considerable variation; most of the line being in non-optimal condition, speed is frequently reduced. Such speed reductions are often highlighted as major causes of delays. This master thesis studied the actual delays occurring on the parts of the line between Oslo and Trondheim which have speed restrictions. In doing actual time, travel times and speed restriction magnitudes data have been collected along the line. Combining both qualitative and quantitative approach to research the master thesis have mapped and analyzed speed restriction zones along the line. Using restriction mapping, statistical tools and curve fittings, the analysis revealed that as long as there is sufficient data, uniformity and regular fluctuation of the time magnitudes data there is an increasing effect caused and trend displayed on the actual time taken in the presence of the speed restrictions. Furthermore the research has looked in to the magnitude based relationship between the lost time due to restrictions and associated deviations in travel time. These resulted in a strong correlation between deviation of travel time and magnitude of lost time due to restrictions.
Keywords:
1. Speed restriction
2. Railway
3. Lost time due to restriction
4. Devaition in travel time
_________________________________________
ii
iii
Preface This report is a result of a Master thesis TBA4910 in Project Management at the Norwegian
University of Science and Technology (NTNU) in Department Of Civil and Transport
Engineering in the spring of 2012. The report analyzes the effect of speed restrictions on
travel time there by its ultimate effect on delays and punctuality.
I would like to thank my supervisor Professor Nils Olsson for his invaluable guidance in
choice of the thesis thematic area and in further project work without his input this project
would not have come to reality. I would also like to extend my gratitude to Per Magnus
Hegglund from Jernbaneverket for his data supplements and assistance throughout the
project work process. Last but not least I would like to thank my wife, Mahlet, for her love,
support and patience during the past two or so years it has taken me to graduate. I would
like to thank Tizita and my parents for their unending love and support.
iv
v
Table of contents Preface ....................................................................................................................................... iii
Table of contents ........................................................................................................................ v
List of Tables ..............................................................................................................................vii
List of Figures .............................................................................................................................vii
Chapter one ................................................................................................................................ 1
Introduction ................................................................................................................................ 1
BACKGROUND ........................................................................................................................ 1
Overview ................................................................................................................................ 2
Data collection .................................................................................................................... 3
Research questions ............................................................................................................ 3
Method of attack ................................................................................................................ 4
Limitations .............................................................................................................................. 4
Outline of the report .............................................................................................................. 5
Chapter 2 .................................................................................................................................... 7
Literature study .......................................................................................................................... 7
The Norwegian railway network ............................................................................................ 7
Punctuality .............................................................................................................................. 8
Punctuality and Delays ......................................................................................................... 10
Variables affecting punctuality ........................................................................................ 10
Scheduling and running time calculation ............................................................................. 12
Traffic diagrams ................................................................................................................ 13
Recovery time as a component of total running time ..................................................... 16
Speed restrictions ................................................................................................................. 18
Permissible speed ............................................................................................................. 19
Temporary speed restrictions .......................................................................................... 21
Other types of speed restrictions ..................................................................................... 22
vi
Speed Restriction and the associated time calculations ...................................................... 23
Chapter 3 .................................................................................................................................. 29
Data Analysis ............................................................................................................................ 29
Data collected and restriction magnitudes .......................................................................... 30
The Train selection and the associated data ........................................................................ 32
The time calculations ........................................................................................................... 35
The effect of speed restriction on actual travel time .......................................................... 37
DOMBAS – FOKSTUA ........................................................................................................ 38
HJERKINN – KONGSVOL .................................................................................................... 39
LUNDAMO – LER ............................................................................................................... 40
MELHUS – NYPAN ............................................................................................................. 41
DRIVSTUA – OPPDAL ........................................................................................................ 43
FAGERHAUG – ULSBERG .................................................................................................. 44
GARLI – STØREN ............................................................................................................... 46
SELSBAKK – TRONDHEIM S ............................................................................................... 47
HJERNIK – DRIVSTUA ........................................................................................................ 48
OPPDAL – FAGERHAUG .................................................................................................... 50
LER – SØBERG ................................................................................................................... 51
NYPAN – HEIMDAL ........................................................................................................... 52
The correlation between restriction magnitude and deviation ........................................... 53
Conclusion ................................................................................................................................ 63
To what level of detail should such studies be done? ......................................................... 63
Relationship between speed reductions and delays ........................................................... 64
Trend based relationship ................................................................................................. 64
Magnitude based relationship ......................................................................................... 65
Appendix................................................................................................................................... 67
Bibliography .............................................................................................................................. 73
vii
List of Table Table 1 snapshot of the time restriction zones for week 1 2011 on Dovrebanen and
Rørosbanen .............................................................................................................................. 30
Table 2 summary of time loss due to speed restriction on the north line for week 1 2011 ... 31
Table 3 sample time record for train number 5733 between Alnabur and Bøn stations ....... 32
List of Figures Figure 1 the Norwegian railway network taken from (Sætermo, Olsson, & Veiseth, 2006) ...... 7
Figure 2 Punctuality measured as the percentage of punctuality to the final destination
(Olsson et.al 2010). .................................................................................................................... 8
Figure 3 componential tasks of scheduling and their relationship adapted from PESP model
(Liebchen & Möhring, 2007) .................................................................................................... 13
Figure 4 Horizontal traffic diagram (taken from Pachl 2002) .................................................. 14
Figure 5 Vertical traffic diagram (taken from Pachl 2002) ....................................................... 14
Figure 6 sectional view of vertical traffic diagram taken from the Norwegian Railway
infrastructure administrator Jernbaneverket website............................................................. 15
Figure 7 Components of total running time ............................................................................. 16
Figure 8 speed curve adapted from Pachl 2002 ...................................................................... 17
Figure 9 typical speed indicator taken from (Railway Group Standard, 2000) ........................ 20
Figure 10 deferential speed indicator taken from (Railway Group Standard, 2000) .............. 20
Figure 11 Permissible speed signing incase of diverging or crossover junctions (Railway
Group Standard, 2000) ............................................................................................................. 21
Figure 12 speed indicator in case of speed restrictions taken from (Railway Group Standard,
2000) ......................................................................................................................................... 22
Figure 13 deferential Speed indicator in case of speed restrictions taken from (Railway Group
Standard, 2000) ........................................................................................................................ 22
Figure 14 Illustration of Speed restriction zone and the associated velocities and
accelerations ............................................................................................................................ 23
Figure 15 Dombas - Fokstua travel time data and lost time due to speed restriction diagram
.................................................................................................................................................. 38
viii
Figure 16 Hjerkinn - Kongsvol travel time data and lost time due to speed restriction
diagram ..................................................................................................................................... 39
Figure 17 zoomed in view of speed restriction zone Hjerkinn - Kongsvol ............................... 39
Figure 18 Lundamo - Ler travel time data and lost time due to speed restriction diagram ... 40
Figure 19 Melhus - Nypan time data and lost time due to speed restriction diagram............ 41
Figure 20 snapshot of the restriction zone Melhus - Nypan .................................................... 42
Figure 21 Drivstua- Oppdal time data and lost time due to speed restriction diagram .......... 43
Figure 22 snapshot of the speed restriction zone Drivstua- Oppdal ....................................... 43
Figure 23 Fragerhuag - Ulsberg time data and lost time due to speed restriction diagram ... 45
Figure 24 exploded views of the speed restriction zones Fragerhuag - Ulsberg ..................... 45
Figure 25 Garli – Støren time data and lost time due to speed restriction diagram .............. 46
Figure 26 exploded view of the speed restriction zone Garli – Støren .................................... 47
Figure 27 Selsbakk – Trondheim S time data and lost time due to speed restriction diagram48
Figure 28 Hjernik – Drivstua data and lost time due to speed restriction diagram ................. 49
Figure 29 Exploded view of the speed restriction zone Hjernik – Drivstua ............................. 49
Figure 30 Oppdal – Fagerhaug time data and lost time due to speed restriction diagram..... 50
Figure 31 Exploded view of the speed restriction zone ........................................................... 50
Figure 32 Ler – Søberg time data and lost time due to speed restriction diagram ................. 51
Figure 33 Detailed view of the speed restriction zone Ler – Søberg ....................................... 52
Figure 34 Nypan – Heimdal time data and lost time due to speed restriction diagram ......... 52
Figure 35 Detailed view of the speed restriction zone Nypan – Heimdal ............................... 53
Figure 36 plot of the deviation magnitude against respective time lost due to deviation ..... 56
Figure 37 percentage of deviation against lost time ............................................................... 57
Figure 38 scatter diagram of percentage of deviation against lost time percentage .............. 58
Figure 39 scatter diagram of percentage of deviation against lost time percentage on first
week basis ................................................................................................................................ 60
Figure 40 scatter diagram of average deviation percentage against lost time percentage .... 61
ix
x
Chapter one
Introduction BACKGROUND The transportation industry is one of the prominent role playing sectors in setting the
central hub of nation’s economy and supporting economic development by aiding the
production and distribution of goods and services (WEF, 2010). From the wide range of
means of transportation the railway segment contributes a lot in the field and is one of the
major role players in the industry (NHO, 2007). During the past few decades and with
today’s ever changing business milieu the railway sector had gone through dramatic
reorganizations and governance structural reforms (Carney and Mew, 2003; Vatn, 2008).
The Governance reforms had led to the adoption of new technologies, and had also
redefined relationships and acted as a catalyst for innovation in the way how infrastructure
is handled, operated and maintained (Sascha Albersa, 2005 ).
The rail way sector had took the attention of policy makers owing to the fact that it has
been losing market, required increased subsidies and failed to generate anticipated rate of
return (Nash, 2000). As a result there has been a strong interest to measure the
performance of railway operators in terms of punctuality. Punctuality is a critical issue in
railways as the provision of reliable arrival time most often out ways the provision of faster
journey with less certain arrival times (Harris, 1992).
It is evident that In Norway punctuality shows considerable variation and the official target
for several railway lines and train is yet to be met (Olsson et.al 2010). With this context in
mind efforts had been employed to provide a holistic explanation regarding factors
influencing punctuality (Olsson & Haugland, 2004).
As a component of punctuality analysis comes, the need for finding out the influences of
speed reductions. Railways lines have defined maximum speed, which varies along the line.
When the line is in non-optimal condition, speed is frequently reduced. Such speed
reductions are often highlighted as major causes of delays. The lost time as a result of a
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
2
speed reduction is calculated, but the calculation is based on optimal conditions. As a result,
it is often claimed that the effect of speed reductions is higher than official calculations
show. Thus it is necessary for the railway organizations to develop the way they organize
and carry out their punctuality improvement activities.
The master thesis will study the actual delays occurring on the parts of the line which have
speed reductions. This information can be summarized in a table or database. The
information will be used in the planning and prioritization of maintenance activities. Data
on both speed reductions and delays are available. The thesis will include a literature study
of punctuality and previous studies.
The actual effect of speed reductions can be analyzed based on punctuality data. One
reason we are interested in this analysis is to be able to show the socio economic effect of
delays along the line. We can then point to certain parts of the line that need special
attention. The resources can be allocated based on this information.
Overview
As this project is conducted in order to look in to the overall effect of speed restriction on
punctuality, due focus has been set in analysing the railway line from Oslo to Trondheim.
Punctuality data generated from the Norwegian railway infrastructure administrator
Jernbaneverket is used for the analysis and further implications. The analysis also takes in to
account the utilization of other company or experience based analysis methods. The scope
of the data collected was limited to the extent of available data generated by
Jernbaneverket. The generated data were punctuality data including the train number, date
of travel, arrival and departure time for individual trains on individual stations.
The data were a mix of both freight trains and normal passenger trains. The intention
behind taking in to account various train types is to widen the manifestation of the effect of
speed restriction and to trace in detail, its associated effect on various incidents of
happenings. Besides it is necessary to analyse statistical data which describes these
conditions from observed occurrences. Both ways (from and to) punctuality data will be
used to look in to the magnified effect of the restrictions uphill and downhill. The data
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
3
collected from punctuality and speed restrictions will be used to further investigate the
relationship between the restrictions and their effect on delays.
Data collection
The data collection includes both primary and secondary data. The data collection horizon is
set wide so that it will give the sound base for the demonstration of the effects and
relationship between speed restrictions.
Primary data: The primary data will be the punctuality data generated by the Norwegian
Railway infrastructure administrator Jernbaneverket. The generated data is a recorded time
measure for individual trains in the year 2011 -2012 on individual travels. Besides the
associated weekly magnitudes of speed restrictions are inferred from the time plan of
speed restriction by the infrastructure handler.
Secondary data: in virtue of secondary data literature survey on theoretical backgrounds on
punctuality, delays and speed restrictions from books, journals, websites and other data
collection of written reports of company cases and country specific experiences is
conducted. The main data sources included:
Research journal articles - industry related journals such as Journal of Air Transport
Management, Journal of Transportation Planning and Technology and Review of
Network Economics,
Search engines and scientific databases: BIBSYS NTNU electronic library database,
Google scholar, Science direct, First Search, Transport and NTIS.
Websites of companies and governmental institutions – websites of the Ministry of
Transport offices of Norway, website of and publications from Jernbaneverket.
Research questions
The main objective of this study focuses on analysing the effect of speed restriction on
delays. In doing so the study tries to address the following research questions:
What is the relation between speed reductions and delays?
On what level of detail should such studies be done, such as for each train number,
week day, direction, train product, time of the year, etc.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
4
The first research question of the relationship between speed restriction and delays will be
addressed by reviewing literatures. Thereby efforts employed to explain the relationship
between speed reductions and delays will be reviewed. In addition the associated terms
and analysis methods used in this study will be highlighted in the light of literature review.
The second research question will discuss about determining the level of detail the study
should be set towards to, on the way of figuring out the effects. In doing so the appropriate
level of detail in the analysis in the likes of each train number, week day, direction, train
product, time of the year, etc. will be determined. In addressing the third research question
the study will analyze the available punctuality data and use plots and tables to look in to
the effect of the speed restriction and its contribution to specific delays given the
magnitude of the reduction.
Method of attack
The method of attack includes both primary and secondary data collection, literature study,
data analysis, interpretation and conclusion. As pointed above after data collection;
literature studies will aid as a tool in explaining the state of the art in the field under
concern. With that, the analysis will utilize various tools to illustrate the associated effects
between delays and restrictions. Thereby conclusions will be made based on the output of
the interpretations of the analysis. Basically this study holds a strong premises and
assumption related to the relationship between delays and speed restriction. Experience
and some studies have indicated that there is a hazy correlation between speed restriction
magnitude and delays. But it was difficult to illustrate this for a small set of data and low
magnitude of speed restrictions. Therefore this study works on the premise of finding the
fuzzy boundary above which a pattern of correlation comes in to manifestation. In doing so
physical inspection of trends on graphs and correlation analysis will be made on the
deviation magnitudes and the lost time due to restriction. Here analysis will be based on
day by day analysis , weekly analysis , peak point analysis and average analysis for
respective speed restrictions.
Limitations
This thesis thematic area is limited to looking in to the relationships and effect of speed
restriction and delays. Furthermore due to lack of weekly speed restriction and associated
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
5
data the analysis is done on the line segment of Oslo to Trondheim concentrating on the
section of the line Dombas to Trondheim. In addition given the amount of time of six
months for the literature reviews, data collection and analysis; the thesis only studies one
freight train coming from Oslo to Trondheim. As there are few available researches and
publications specifically conducted on this subject matter efforts had been employed to
include relevant issues on the shelf.
Outline of the report
The report is presented in such a way that the first chapter discusses the core issues and
thematical areas of the thesis. The second chapter reviews and presents literatures coined
with the subject matter; which would go in presenting what have been done so far when it
comes to effect of speed restrictions on delays and restriction . As well the literature review
will discuss key terms and analysis techniques utilized in planning and computing of speed
restrictions. The third chapter will present the collected data for analysis and the actual
analysis conducted. The analysis is utilizes two method of attacks. The first approach
investigates the effect of the speed restriction on delays there by punctuality. The second
approach looks in to the relationship between the magnitude of the lost time and the value
of the associated deviation in the actual travel times. Finally the last sections will summarize
the main findings of the thesis and present the list of main materials and literatures used in
the progress of the thesis, in the appendix and bibliography sections.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
6
The No
The Nor
country
track, 6
feature
distance
diagram
Figure 1
orwegian
rwegian rai
y from nort
60Km high s
of the netw
e, regional
mmatical dis
the Norwegi
n railway n
lway netwo
h to south.
speed track
work is its r
l and freig
splay of the
an railway ne
C
Liter
network
ork consists
. This line c
k, 696 tunn
relatively lo
ght trains
Norwegian
etwork taken
Chapter
rature s
s of a railwa
consists of
nels and 276
w share of
are single
n railway ne
n from (Sæter
2
study
ay track tha
2,622 km e
60 bridges
double trac
e tracks. T
etwork with
rmo, Olsson, &
t extends 4
electrified lin
(jernbaneve
cks. The ma
The figure
the major
& Veiseth, 20
4087 km acr
ne, 242 km
erket). The
ajor tracks f
below sh
destination
06)
ross the
double
special
for long
hows a
ns.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
8
Punctuality
In the transportation sector service planning goes further beyond determining optimal
travel cost and duration. It extends further in to meeting customer requirements and
expectations. Studies have shown that these days in the transport sector punctuality takes
of critical significance (Hariss, 1992, Bates, 2001). In rail way service in addition to
smoothening operations punctuality is contributing a lot towards insuring delivery of quality
service. Train stations currently, being crowded with busy multi-platform sets, it is
becoming critical to have a clear understanding of the punctuality of individual travels
coming in and going out (Carvile, 2003). Punctuality is a critical issue in railways as the
provision of reliable arrival time most often out ways the provision of faster journey with
less certain arrival times (Harris, 1992).
It have been noticed that in Norway the railway system doesn’t only show variation but also
there is a declining trend 1 When it comes to punctuality from the year 2005 to 2010 (see
figure 2 below ). With this context in mind efforts had been employed to provide a holistic
explanation regarding factors influencing punctuality (Olsson & Haugland, 2004).
Figure 2 Punctuality measured as the percentage of punctuality to the final destination (Olsson et.al 2010).
1 Punctuality measured as the percentage of punctuality to the final destination, month by month from January 2005 to April 2010 for the country as a whole (TIOS Trafikkinformasjon og oppfølgingssystem). Figure 2 is taken from Driftsstabilitet på Jernbaneverkets nett - årsaksanalyser 2005 – 2010 Punktlighets- og regularitetsutviklingen, gransking av årsaker by: Nils Olsson, Andreas Økland, Mads Veiseth og Øivind Stokland
30
40
50
60
70
80
90
100
110
120Langdistanse Mellomdistanse Lokaltog Oslo Godstog CN Flytog
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
9
Hansen (2001) defines punctuality as a percentage of trains arriving or departing a given
location or station across the railway network no later than a specified time in minutes.
With similar connotation Rudnicki (1997) also presents punctuality as a state of a measured
value that explains a given known vehicle arrives or departs a specific point in a previously
set time. In extension Olsson & Haugland (2004) defines Train punctuality as the associated
deviation, majorly negative from the defined timetable. For instance in most European
railway companies the threshold for delay is equal to or less than 5 minutes; on the other
hand trains arriving less than 3 minutes late in Netherlands are considered to be punctual.
The limit might also narrows down to 10-15 seconds in case of Japanese train operators.
This means that punctuality is often taken as, an event of meeting a set of predefined and
anticipated deviations from target value in a schedule. Ultimately failure to meet
punctuality or set target will end up in delays in the total train journey. With this context in
mind about punctuality, we will further try to look in to how it is measured and what factors
affect punctuality or contribute to delays.
Punctuality is a critical issue in railways as the provision of reliable arrival time most often
out ways the provision of faster journey with less certain arrival times (Hariss, 1992). Harris
(1992) points out three major reasons why punctuality is being taken worse than it actually
is as:
Passengers tend to have selective memory of concentrating more on poor
performances on top of good once
More often passengers take late trains than punctual once
Train operators tend to avoid early running, as it might balance out late arrivals
Generally for train operators it’s of great significance to have a detailed understanding of
punctuality as it helps a lot in optimizing their economical resource deployment in line with
meeting the requirement and expectation of their customers. Furthermore it enables them
to monitor their timetables and travel patterns giving a window of opportunity to analyze
and depict more efficient way of running their operations.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
10
Punctuality and Delays
The two terms are most often mentioned as similar terms but have different meaning
although delay could be other version of punctuality. Given a train is not punctual, and had a
negative deviation from predefined target time then we call it delayed. Delays are measured
in time units whereas punctuality is expressed through percentage of numbers.
Primarily there are two types of delays but different authors use different terminologies and
scope of definitions in presenting them. Gylee (1994) uses the term primary and secondary
delays to signify delays with their size to impact. The primary once being, the most impacting
and the secondary once being shadowed by the influence of the primary once. In
conjunction Olsson & Haugland (2004) present the Norwegian version of delay classification
as primary and secondary delays. Whereby primary delays are caused by direct influence on
the train itself and secondary delays are most often caused by the impact of other delayed
trains on the first one. Correspondingly different authors use other terms to explain the
above delay types. For instance Gibson et al. (2002) uses exogenous and reactionary. Carey
(1999) uses Exogenous versus knock on delays to express similar phenomenon but with
further emphasis on the terms.
Variables affecting punctuality
From above discussions it is evident that having detailed understanding of punctuality has
great significance. Hence the next level of understanding will be defining various factors that
influence punctuality. There are various factors affecting punctuality. Hariss (1992) has
listed five variables that affect punctuality of trains and tried to investigate in to their
correlations to punctuality with case studies. The major factors listed were:
Length of train in carriage: length of a train is assumed to have influence in virtue of
time taken to go across up and down hills and accelerate to regain speed in case of
speed restrictions.
Previous number of station stops: this is more related to the lateness caused by
loading and unloading as the train stops more frequently.
Previous distance covered: here it is assumed that with increased distance traveled
the probability of encountering defective tracks and wreckage is high.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
11
Age of the motive power unit: this is a factors more related to aging parameter
decreasing reliability of the train engine and power units
Track occupation: this is more related to secondary type of delays whereby delay or
failure of one train propagates in to other train delays on the congested and busier
tracks.
While making the regression analysis for these factors to look in to their correlation with
punctuality, Harris (1992) found out that only distance covered and train length were
statistically significant in determining punctuality.
Correspondingly Olsson & Haugland (2004) had made related investigation on factors
affecting punctuality which was a point of inspiration for this thesis research questions. In
their research they have used the Norwegian railway network near Oslo and the Nordland to
analyze the effect and correlation of certain variables to punctuality. The variables used
included:
Number of passengers and occupancy ratio: it was found out that number of
passengers with higher rate of occupancy and punctuality has a negative correlation.
With increased number of passengers, it was noticed that the trains tend to be not
punctual.
Infrastructure Capacity utilization : it was noticed that with increased capacity
comes increased punctuality
Cancelation and regularity: this showed that cancelation and punctuality have a
positive correlation, cancellation and delay being apparent at the same time.
Speed restriction: the correlation was found to be weak and sometimes negative
opposite to what is expected. This might be counter balanced by the 4% allowance
the Norwegian timetable takes in to account. This is the main thematic area of this
thesis; hence we will focus more in this area on the chapters to come.
Railway construction work: as expected during constructions period trains passing
by will tend to be less punctual due to jams and stop over’s.
Departure and arrival punctuality. Here the relationship and correlation between
departure delays and delays associated with arrival was investigated and it marked
strong correlation.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
12
Operational train priority rules
From the above mentioned and discussed factors which affect punctuality we will go in
depth to investigate the effect of speed restrictions on punctuality. This is because speed
reductions are often highlighted as major causes of delays. The lost time as a result of a
speed reduction is calculated, but the calculation is based on optimal conditions. As a result,
it is often claimed that the effect of speed reductions is higher than official calculations
show. Most often in Norwegian railway network time tabling, the 4% allowances counter
balance this phenomenon and it was difficult to purely notice the effects of the restrictions.
Besides train time table schedulers have a rule of thumb of adding 1 minute allowance per
every 100km the train travels. This might have also led to diminishing the contribution and
effect of speed restrictions on total travel time, hence punctuality.
There are various methods of measuring punctuality. For instance Rietveld et al. (2001)
mentioned the following lists of measurement methods:
1. the probability that a train arrives x minutes late
2. the probability of an early departure
3. the mean difference between the expected arrival and the scheduled arrival time
4. the mean delay of an arrival given that one arrives late
5. the mean delay of an arrival given that one arrives more than x minutes late
6. the standard deviation of arrival times
Olsson & Haugland (2004) also has cited other methods of measurements including the
travel time variability and Norwegian way of measuring punctuality at the destination
station.
Scheduling and running time calculation
Since scheduling is done in a greater picture for a long span of time and lots of trains’ passing
by numerous stations; at points the task becomes overwhelmingly difficult to compose.
Although scheduling encompasses by far a great deal of tasks the major specific components
are determinable. According to Pachl (2002) the main target of scheduling is to determine
the travel date, the route along the network, respective arrival and departure times and
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
13
maximum speeds for a given train running along the line. Most of these components are
determinable and could be monitor by data tracking along the path.
Going in to details scheduling in railway would infer additional tasks of network planning,
line planning, timetable generation, vehicle scheduling, crew scheduling, and crew rostering.
Although there is no distinct boundary between these interrelated tasks network planning
and line planning are more of strategic planning whereas vehicle scheduling and crew
scheduling have operational tendency (Liebchen & Möhring, 2007). In between these two
tasks lies, the timetable generation, this serves as a bridge between service and operation.
This is demonstrated diagrammatically in figure 3 below.
Figure 3 componential tasks of scheduling and their relationship adapted from PESP model (Liebchen & Möhring, 2007) In the coming sections due focus will be given towards scheduling related with timetabling.
Traffic diagrams Traffic diagrams or graphical route diagrams are schematical representations and overview
of pre-scheduled train traffic at varied intersections. The traffic diagrams have multi-function
in laying the basis for planning of railway traffic and serving as an essential document for
Network planning
Line planning
Crew Scheduling
Time tabling
Vehicle Scheduling
TBA49, Master t
monitor
describe
in hour
graphs
4).
Figure 4 In accor
organiza
Figure 5 In both
content
Master Theshesis Mignot
ring of ong
es distance
rs along the
representin
Horizontal t
rdance with
ations eithe
Vertical traf
cases the
t of the ind
sis te Beyene, S
going opera
on the line
e line. The
ng train mo
raffic diagra
h the orient
er use the h
ffic diagram (
content of
dividual axi
Spring 2012
ations. The
e, stations a
diagrams a
ovements, w
m (taken from
tation or wo
horizontal o
(taken from P
f the schem
is. In addit
14
diagrams
and sidings’
also include
with a train
m Pachl 2002
orking trad
r the vertica
Pachl 2002)
matics is th
ion these d
usually con
and a horiz
e train path
details em
2)
ition of a tr
al traffic dia
he same th
diagrams a
nsisted of a
zontal axis
hs, which a
mblazoned o
rain operato
agrams (see
he only diff
lso include
a vertical a
that describ
are a time-
on them (se
or different
e figure 5).
ference lies
e schematic
axis that
bes time
distance
ee figure
t railway
s on the
cs which
TBA49, Master t
describe
for resp
Figure 6 administ
The fig
Railway
Graphic
axis des
the time
The tim
with var
line tex
Besides
stripes
through
Master Theshesis Mignot
e the traffic
pective direc
sectional viewtrator Jernba
ure above
y infrastruc
cal train rou
scribes the
e frame; for
me-distance
ried line tex
xtures one
the arrow
and line
hout the line
sis te Beyene, S
c inside stat
ctions.
w of vertical aneverket web
displays a
ture admin
utes as of 1
station nam
r this sectio
graphs rep
xtures and t
can tell the
w directions
bending im
e of travel.
Spring 2012
tions and in
traffic diagrbsite
snapshot
nistrator Je
11 Decembe
me and dist
onal view on
presenting t
train numbe
e frequency
on the lin
mplicitly de
The full traf
15
nterlocking
am taken fro
of a vertic
ernbaneverk
er 2011. As
tances cove
nly time gap
train route
ers represe
y of travel
e indicate
efine track
ffic diagram
given there
om the Norwe
cal traffic d
ket website
can be see
ered where
p between 0
are also dis
nting train
and the ba
the directio
occupancy
ms are prese
e are differe
egian Railway
diagram fro
e. This is s
en on the d
as the hori
06:00 until
splayed all
specific info
asic functio
on of trave
y status o
ented in the
ent tracks a
y infrastructu
om the No
sectional pa
diagram the
zontal axis
12:00 is dis
over the sc
ormation. F
onality of th
el and the d
on a given
e Appendix
available
ure
orwegian
art of a
e vertical
displays
played.
chematic
From the
he train.
different
station
section.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
16
Recovery time as a component of total running time Running time of a train is a predefined scheduled time set that defines the total duration of
a travel between departure and destination stations. Running time is composed of
componential time sets including pure running time between scheduled stops, the dwell
time at scheduled stops, recovery time and scheduled waiting times. This is illustrated in
figure 7 below.
Figure 7 Components of total running time The pure running time is a mathematically calculated or operationally recorded shortest
time that a train takes to cover the distance between departure and destination station.
Here it should be noted that the running time is computed without adding time lost due to
small delays and malfunctions. It is purely the time taken while the train is under operation
and running. The computation of pure running time involves the construction of the speed
curve and integration of the curve to determine the running time. Figure 8 illustrates a
typical speed curve constructed to visualize and further integrate on the course of
computing the running time between two given stops.
Pure running time Dwell Time
Waiting time
Recovery time
Total running time
Total Dwell time
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
17
Figure 8 speed curve adapted from Pachl 2002 The associated elemental movements of the train between these two stop points are
composed of acceleration, running at constant speed, run out and braking. There are
associate calculations of force, inertia, acceleration and so forth to determine the
componential curves in the speed curve. As it is beyond the scope of this study we are not
going to deal with them in detail. In general literatures indicate that the construction of the
speed curve is a difficult task to develop analytically (Pachl 2002). Therefore one needs to go
for a step by step approximation from a series of straight lines.
The dwell time includes the time that is usually elapsed while alighting and boarding
passengers on scheduled start and stop stations. Dwell time usually takes in to account
those additional minutes consumed in the case of technical checks and schedule margins
(Heinz 2003).
To compensate for small delays there will be additional times added on the total running
time which is termed as Recovery time. Depending on the train operators geographical
location or country of origin there different magnitudes of recovery time additions.
Depending on the reason behind the need for the additions and condition specific situations
Acceleration Constant Speed Run-out Braking
V
S
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
18
there are two types of recovery times. Pachl (2002) uses regular and special recovery time
terminologies to explain the situations.
Regular recovery time is the time supplement usually added to running time as a percentage
of the pure running time. As discussed above this magnitude might vary based on
geographical location and country specific situations. In most European railways the
magnitude of the regular recovery time lies in between 3% to 7%. The North American
railways take an allowance of 6 - 8% (Pachl 2002). Some schedulers often spread the regular
recovery time throughout the total line of travel whereas; others supplement it at the end of
the last scheduled stop or large intermediate stations.
Special recovery time is another type of recovery time supplement whereby the allowance is
targeted at compensating lost time due to construction on the line, maintenance and
restrictions related to track malfunctions. Unlike regular recovery time which takes
percentage allowances, special recovery time is added as a fixed supplement to the running
time.
The fourth component is the scheduled waiting time. This time addition is made so as to
align travel time of passengers on change over stations and to make up for scheduled
passing or overtaking. Most often the scheduled waiting time is by default included under
dwell time as a supplement.
Speed restrictions
Speed restrictions or speed reduction is one of the variables that affect punctuality of trains.
In the presence of speed restrictions both freight and passenger trains need to make
technical adjustments so as to make it through the speed restriction zones. The railway
groups’ standard GK/RT0038 (Railway Group Standard, 2000) defines speed restriction as “a
set out principles governing the signing and advice of permissible speeds, temporary speed
restrictions and emergency speed restrictions on running lines to ensure that train drivers
have sufficient information to control their trains safely”. Speed restrictions influence the
travel time of the trains in virtue of time taken so as to adjust to the limit placed by the
restrictions. At times when the train approaches the speed restriction zone the operators
need to decelerate to attain the placed speed restriction and have to keep the speed
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
19
constant throughout the zone. In addition while exiting from the speed restriction zone the
operator again needs to accelerate to regain the optimal permissible speed set. Enticed with
this there will be train category and operator experience dependent associated time losses.
Most often the time taken to pass a speed restriction zone is merely a pure physics
calculation, which we will see later in the upcoming sections. But there are scenarios of
varied intensity which are taken in to account when it comes to the retardation and
acceleration of the trains. Despite all this there still prevails a conditional time loss which
may vary depending on the context of speed gains across uphill versus downhill, freight train
versus passenger train, short train versus long train etc.
In the railway business there are various types of speed restrictions which might include
permissible speed, temporary speed restriction, emergency speed restrictions and weekly
operating notice.
Permissible speed
Permissible speed restriction is on schedule basis computed and infrastructure controller
approved maximum speed limits over a section of line, for each planned direction of travel
and specific to each type of vehicle allowed to use the line. This often takes in to account the
physics based calculations so as to come up with the attainable maximum speed enabling
train operators to have full operational flexibility and safety clearance to guide their train
across the line. The permissible speed is further used to calculate and compose specific
deceleration distances. GK/RT0038 defines the deceleration distance as “The minimum
distance at which a warning indicator (for a permissible speed) or a warning board (for
temporary and emergency speed restrictions) shall be positioned approaching the start of
the change in speed to which it applies in order to ensure that all trains have sufficient
warning to be able to conform to the reduction in speed”.
Permissible speed should be backed by continuous route signing that provides a speed
indicator at each point where the permissible speed limit varies and the need for warnings
arises. Speed limits are usually presented with signings displaying the information with clear
and unambiguous clarity to the train drivers. Such signings design is based on the country
TBA49, Master t
specific
kilomet
(AWS) c
Figure 9
In case
restricti
use a m
Figure 10
There a
junction
differen
crossov
reduced
below).
Master Theshesis Mignot
traffic safe
ers per hou
could be pu
typical speed
of Differen
ion having t
modified ver
0 deferential
are also diff
ns on the ro
nt permissib
er. In this c
d permissib
sis te Beyene, S
ety standar
ur, yard per
t in practice
d indicator ta
ntial Speed
two values,
sion of the
speed indica
ferent desig
oute of the
ble speeds
case route s
ble speed a
Spring 2012
rds; as well
r hour etc. A
e. The figure
aken from (R
Restriction
each of wh
above diag
ator taken fro
gns of the s
e train. Wit
commenc
specific indi
nd directio
20
l as measur
As a supple
e below sho
Railway Group
n whereby t
hich is appli
ram as disp
om (Railway G
signing boa
h this set o
ement for
icators shou
on of diverg
rement sys
ement to th
ows a typica
p Standard, 2
there is the
icable to dif
played in the
Group Stand
ards in case
of design on
both route
uld be place
gence point
tems such
his automat
al speed ind
2000)
e need for
fferent type
e figure bel
dard, 2000)
of a diverg
ne can have
es at a div
ed indicatin
ted by arro
as miles p
tic warning
dicator in ra
displaying
es of trains
ow.
ging and cro
e displays s
verging jun
ng the comm
ows (see th
er hour,
systems
ailways.
A speed
one can
oss over
signaling
ction or
mencing
he figure
TBA49, Master t
Figure 12000)
Tempo Tempor
of six m
than the
work on
types o
should
affect p
restricti
maximu
operatin
Tempor
unambi
location
accelera
speed r
Master Theshesis Mignot
1 permissible
orary spee
rary speed r
months span
e permissib
n tracks, m
f restriction
be done ca
punctuality
ions should
um allowab
ng conditio
rary speed
guous infor
n of the spe
ation distan
estriction d
sis te Beyene, S
e speed signin
d restricti
restriction i
n, placed so
ble speed. T
maintenance
ns have gre
refully. Wh
with prop
d be impo
ble speed, w
ns (H. samu
restrictions
rmation dis
eed restrict
nces. Other
display boar
Spring 2012
ng in case of
ions
is a time bo
o as restric
Temporary
e work on t
eat contribu
ile such res
pagated de
sed lasting
with due co
uel, 1961).
s planning a
splay board
ion zone a
rwise accide
d is shown
21
diverging or
ounded spee
t the train
speed restr
the line, w
ution for oc
strictions ar
elays happ
g minimum
ourse taken
and design
s. This prov
head of tim
ents and de
in the figur
crossover ju
ed limit; us
speed to s
rictions are
weather con
ccurrence o
re place car
pening acro
m time spa
n in to acc
also needs
vides the tr
me to keep
elays are in
e below.
nctions (Rail
ually lasting
tick to a fix
placed in c
nditions and
of delays; th
e should be
oss the lin
n possible
ount the n
to be back
rain driver t
up with th
evitable. A
lway Group S
g up to a m
xed magnit
case of cons
d so forth.
he speed re
e taken so a
e. Here m
and allow
eed for saf
ked by a so
the magnit
he decelerat
A typical tem
Standard,
maximum
ude less
struction
As such
eduction
as to not
minimum
wing the
fety and
und and
ude and
tion and
mporary
TBA49, Master t
Figure 12 The spe
should
case of
higher o
Figure 132000)
Other t Depend
standar
once inc
Weekly
tempor
Master Theshesis Mignot
2 speed indic
eed indicato
designate t
a deferenti
one as depic
3 deferential
types of sp
ding on the
rds and type
clude week
temporary
ary speed r
sis te Beyene, S
cator in case o
or should i
the termina
ial speed th
cted in the
Speed indica
peed restri
internal op
es of restric
ly tempora
y notice is so
restrictions.
Spring 2012
of speed restr
nclude the
tion spot o
he magnitud
figure below
ator in case of
ictions
perating con
ctions other
ry notice an
omehow a
The main p
22
rictions taken
sign posts
of the temp
de of the low
w.
f speed restri
nditions an
r than the o
nd emergen
combinatio
purpose of t
n from (Railw
of start of
orary speed
wer speed s
ictions taken
d traffic sta
once discus
ncy speed re
on of both p
these types
way Group St
f the speed
d restriction
should be d
from (Railw
andards one
ssed above.
estrictions.
permissible
s of weekly
tandard, 2000
restriction
n with lette
displayed ab
ay Group Sta
e can find d
The major
speed chan
official repo
0)
n as well
er “T”. In
bove the
andard,
different
ly noted
nges and
orts is to
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
23
provide advice to the train driver about temporary speed restrictions and alteration in
permissible speed. The emergency restrictions are similar to the weekly notice but differ in
the context of their applicability. These types of restrictions are temporary restrictions;
which are more restrictive than they appear on the weekly notice and include those
restrictions note displayed on weekly notice. But still these restrictions could be traced from
updates and amendments to weekly notices. They appear to be more bounding even when
they are not shown.
Speed Restriction and the associated time calculations
Basically running time calculations will take more than simple physics computations to come
up with the determined travel time for a train across the line. The figure below
demonstrates a sample train movement between two stops having a speed restriction zone
in between them.
Figure 14 Illustration of Speed restriction zone and the associated velocities and accelerations The train first starts from station “A” and accelerates to attain the permissible speed Vp.
Starting from point “B” the train travels with constant speed Vp until it reaches the speed
Vp
D
B F C
E
H
G
A
Speed Restriction
Zone
Vpr
Distance S
V
aAB
VBC aCD aEF
aGF
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
24
restriction zone. At point “C” the deceleration distance starts and the train starts to slow
down to reach the speed restriction zone permissible speed Vpr. the Norwegian time table
developers take a deceleration rate of -0.7m/s2 in their computations. The speed restriction
zone starts at point “D” and the train travels at constant velocity of Vpr throughout the
restriction zone and again starts to accelerate at point “E” to regain its permissible speed Vp
at point “F”. The Norwegian time table developers take an acceleration rate of 0.5m/s2 in
their computations. From point “F” onwards it travels at constant speed of Vp until it reaches
point “G” and starts to slow down until it reaches the destination stop at Station “H”.
In case of constant speed zones the train can travel at the permissible speed and the
associated time calculation will be as simple as dividing the distance traveled by velocity. See
equation 1
T= ……………………………………………………………….. (Equation1)
Average Velocity = ………………………………………………………………………………… (Equation 2)
In the case of speed restrictions where by the condition of deferential speeds comes in to
play one need to take in to account the change in velocities and the associated acceleration
and decelerations. The following formulas become more significant:
S = ………………………………………………………………………………………… (Equation 3)
√ …………………………………………………………………………… (Equation 4)
We can now use figure 14 to calculate the total time taken between two stop stations “A”
and “H” thereby we can develop a common understanding of how timetables in case of
speed restriction are developed. First we need to segment the total time taken in to
componential times in line with prevailing motion mechanisms. We can develop the time
segments as
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
25
T Total = TAB +TBC + TCD + TDE + TEF + TFG + TGH ……………………………………………… (Equation 5)
The time taken between points “A” and “B” could be computed by using both equation 3
and equation 4. First we need to calculate the distance covered by the train using equation 3
from rest condition Vo= 0 m/s at point “A” until it reaches the permissible speed Vp at point
“B” assuming a constant acceleration rate of 0.5 m/s2 .
→ SAB = = m ………………………………………………………………………… (Equation 6)
Now substituting equation 6 in to equation 4 we can easily compute TAB as
→ TAB √ = √2 sec …………………………………………………………. (Equation 7)
The time taken between points “B” and “C” could be computed by using equation 1
assuming the train travels at constant speed Vp and the distance between reaching the
permissible speed and point of deceleration C SBC is known.
→ TBC = ∗ ………………………………………………………………………………………………… (Equation 8)
The time taken to reduce the permissible speed Vp at point “C” to the reduced speed Vpr at
point D is easily computed in similar way as we did for TAB except this time the initial velocity
is Vp and the deceleration rate is -0.7m/s2.
→ SCD = ∗ . ……………………………………………………………………………………. (Equation 9)
Substituting equation 9 in to equation 4 we can calculate TCD as
→ TCD = ∗ . / ∗ . / ……………………………………………………………. (Equation 10)
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
26
Given we have a constant speed along the speed restriction zone between “D” and “E” and
with knowledge about the length of the speed restriction zone we can easily compute the
time taken TDE along the restriction zone as we did for TBC.
→ TDE = ∗ ……………………………………………………………………………………………… (Equation 11)
For points between “E” and “F” the time taken can be calculated the same way as the time
calculation between points “A” and “B” except this time we have an initial speed of Vp.
→ SEF = ∗ . / .................................................................................... (Equation 12)
Substituting Equation 12 in to Equation 4 we can calculate TEF as
→ TEF = ∗ . / ∗ . / ……………………………….…………………… (Equation 13)
The time taken between “F” and “G” TFG could be calculated considering a constant speed
and knowledge of the distance between attaining the permissible speed again and the start
of the braking zone as:
→ TFG = ∗ ……………………………………………………………………………………………….. (Equation 14)
And finally one could compute the time taken to bring the train from the permissible speed
at point “G” to stop at station “H” , given a deceleration rate of 0.7 m/s as :
→ SGH = ∗ . / ..................................................................................... (Equation 15)
Substituting equation 12 in to equation 4 we can calculate TGH as
→ TGH = ∗ 0.7 m/s2 ∗ 0.7 m/s2 ……………………………….………………………… (Equation 16)
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
27
Therefore we can calculate the total time taken across the speed restriction zone and the
total time along the diagram demonstrated by figure 15 substituting the computed results
from equations 7, 8 10, 11, 13, 14 and 16 in to equation 5. In the above computations
involving the quadratic equations to calculate time, the negative outcomes should be
ignored as it doesn’t make sense to have a negative time value.
In case of other railway administrator setting different magnitudes of acceleration and
deceleration rates one can easily change the values utilized in the computation above but
the basic governing structure of computation remains the same.
One need to bear in mind as mentioned in the speed curve construction the above
computations only serve as the basis for the linear approximations on the development of
the speed curve. Otherwise every linear trajectory motions displayed are only ideally
attainable and depend on the experience of the driver, the type of train, the topographic
condition, the age of the engine and so forth.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
28
Chapter 3
Data Analysis
This chapter will present the method of attack and the analysis of this thesis. The chapter is
structured in such a way that first it discusses the typical calculations related with speed
restrictions. In continuation it discusses the data collected and the associated speed
restrictions across the railway line between Trondheim and Oslo. The major analysis part
will constitute investigating the effect of speed restriction on delays and punctuality. The
analysis will focus on representative train samples on the route including both freight and
passenger trains. The analysis will try to fill the research gap on the concept of speed
restrictions.
The basic premises behind the analysis is lost time as a result of a speed reduction. The lost
time due to the restriction is calculated using the appropriate physics formulas, but the
calculation is based on optimal conditions. As a result, it is often claimed that the effect of
speed reductions is higher than official calculations show. In this virtue literature studies
have shown that the effect of these restrictions seemed to get less significance as they are
canceled out due to allowances and long distance of travel. Therefore this analysis attempts
to widen the sample size and concentrate on speed restrictions to look in to its associated
ultimate effect. Majorly the analysis part will look in to freight train sample and follows the
train along the line to compute the deviation in running time with as well without the
presence of speed restrictions. Further efforts will be employed to compare the deviations
and come up with a reasonable explanation for the noted situations.
In doing so Train number 5733 is selected for further investigation as this train runs between
Trondheim and Oslo. Furthermore the delays related to this train and its economical
implication has been issue of hot debate in the Norwegian parliament. The analysis will use
this train to illustrate the effect of restriction in the respective speed restriction zone and
further investigates the associated relative effect of speed restriction magnitudes on the lost
times.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
30
Data collected and restriction magnitudes
As discussed in the literature review section experience of the driver, the type of train, the
topographic condition, the age of the engine and so forth influence the time taken to cover
the distance between stations on the line. Therefore railway time table developers usually
go for adding special recovery time to compensate for time loses due to these factors
mentioned.
But the extent to which theses recovery additions magnitude should be set without
undermining the effect of the speed restrictions remains debatable. In this thesis in line with
the Generated time Data by the Norwegian Railway infrastructure administrator
Jernbaneverket, we also have acquired data about magnitude of the speed restrictions on
weekly basis throughout the railway line from Oslo to Trondheim starting from beginning of
2011 until March 2012. These times are computed in the same way we illustrated in the
previous sections; therefore it simplifies the need for computing los times due to
restrictions.
Table 1 snapshot of the time restriction zones for week 1 2011 on Dovrebanen and Rørosbanen
Table 1 above displays a snapshot of the weekly time restriction zone on the north line from
Oslo to Trondheim for week 1 of 2011. The report is given in table format columns showing
the name of stations, the starting and end point of the restriction zone, the amount of time
lost in the zone, the restriction speed magnitude, the reason for restriction and the status.
Planlagte Ikke planlagte HastighetBane # Tidstap Avtale # Tidstap Nedsatt Årsak Tiltak Oppheves kostnad
Fra km Til km (sek) (min) (min) (sek) (min) til dato
0 0 .0 0 00:00 3 64.00 01:04 (Km/t)Fokstua st 361.380 361.580 1 31.10 00:31 60 Feil på spv bytte spv deler? jan 2011Hjerkinn st 381.910 382.100 1 26.60 00:27 60 Feil på spv kapping/bytte av deler jan 2011Lundamo st 514.830 515.020 1 6.30 00:06 40 avvikende spv signalteknisk 2011 0,1 mill
0 0.00 00:00 2 12.83 00:13Hamar - Løten 141.990 142.730 1 6.73 00:07 80 plo signal utflytting av innfelt 2011Opphus - Koppang 238.200 238.300 1 6.10 00:06 60 setning innflytting av spor 2011
2 136.60 02:17 7 163.10 02:43
STÅENDE SAKTEKJØRINGER I REGION NORDI hht T-sirkulære 1/2011 (T.heim) og 1/2011 (Hamar), samt ruteordrer
Dovrebanen
Rørosbanen
Nordlandsbanen
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
31
In addition to this the weekly speed restriction forms collected for the year 2011-2012 also
includes the summary of weekly time losses due to the speed restrictions (see Table 2
below). The summary is developed based on values from table shown above. This summary
also display the adjacent stations restriction zone lays in between, the planned and not
planned magnitude of time lost or delays occurred due to the induction of the speed
restriction.
Table 2 summary of time loss due to speed restriction on the north line for week 1 2011
Such similar data for the whole year of 2011 and three months of 2012 have been collected
detailing 72 weeks’ time loss data due to speed restrictions along the railway line between
Oslo and Trondheim.
In addition to the weekly time loss data due to individual restriction points, the time data
record for individual trains in the whole line between Oslo and Trondheim has also been
collected. These data includes Standard Arrival (STA_TID), Actual Arrival time (ATA_TID),
Standard Departure time (STD_TID) and Actual departure time(ATD_TID) records for
individual trains passing individual stations. This way it will be possible to monitor and follow
individual trains along the line and look in to the magnitude of change in time where speed
restrictions are placed. In line with the time magnitudes the station names and train
Strekning Planlagt Ikke planlagt Akseptert tidstap Totalt Kongsv - Elverum 00:00 00:15 01:30 00:15Hamar - Koppang 00:00 00:13 00:30 00:13Koppang - Røros 00:00 00:00 01:30 00:00Røros - Støren 00:00 00:00 01:00 00:00Dombås -Støren 00:00 00:58 01:30 00:58Støren - Trheim 00:00 00:06 00:30 00:06Trondheim - Hell 00:22 00:47 00:30 01:09Hell - Storlien 00:41 00:00 01:00 00:41Hell - Steinkjer 00:00 00:27 01:00 00:27Steinkjer - Grong 00:00 00:00 01:00 00:00Grong - Mosjøen 00:00 00:00 01:30 00:00Mosj - Mo i Rana 01:54 01:07 01:00 03:01Mo i Rana - Rognan 00:00 00:11 01:30 00:11Rognan - Bodø 00:00 00:11 01:00 00:11Ofotbanen 00:00 00:00 01:00 00:00Hele regionen 02:57 04:15 16:00 07:12
Tidstap for uke 1
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
32
numbers were displayed enabling the time calculation between stations a possibility. The
Table 3 displays the snapshot format of the sample data collected between consecutive
stations between Oslo and Trondheim. This data set is generated by the north line
administrative section of Jernbaneverket which tracks real-time data and stores in a
database, thus making generation of such data set possible up on request by interested
parties.
Table 3 sample time record for train number 5733 between Alnabur and Bøn stations
The Train selection and the associated data
From number of trains travelling between Trondheim and Oslo Train number 5733 is
selected as a focus of investigation for this thesis. Train number 5733 is a freight train
passing through the northern railway line it starts from Alnabur station in Oslo and stops at
Trondheim Station. This train was selected as a point of focus of the analysis for three
reasons:
UTG_DT TOG_NR STASJON_STA_TID ATA_TID STD_TID ATD_TID1/3/2011 5733 ALB 03/01/2011 20:31:00 03/01/2011 20:31:00 03/01/2011 20:31:00 03/01/2011 20:31:001/3/2011 5733 GRO 03/01/2011 20:36:09 03/01/2011 20:36:00 03/01/2011 20:37:251/3/2011 5733 HGA 03/01/2011 20:37:25 03/01/2011 20:38:00 03/01/2011 20:38:211/3/2011 5733 HØB 03/01/2011 20:38:21 03/01/2011 20:39:00 03/01/2011 20:40:021/3/2011 5733 LØR 03/01/2011 20:40:02 03/01/2011 20:40:00 03/01/2011 20:41:111/3/2011 5733 HAB 03/01/2011 20:41:11 03/01/2011 20:42:00 03/01/2011 20:42:381/3/2011 5733 FJE 03/01/2011 20:42:38 03/01/2011 20:43:00 03/01/2011 20:44:071/3/2011 5733 STN 03/01/2011 20:44:07 03/01/2011 20:44:00 03/01/2011 20:45:001/3/2011 5733 SDA 03/01/2011 20:45:34 03/01/2011 20:47:00 03/01/2011 20:46:281/3/2011 5733 LLS 03/01/2011 20:47:44 03/01/2011 20:49:001/3/2011 5733 LSD 03/01/2011 20:59:42 03/01/2011 21:00:00 03/01/2011 21:00:511/3/2011 5733 FRO 03/01/2011 21:02:06 03/01/2011 21:02:00 03/01/2011 21:02:471/3/2011 5733 LBG 03/01/2011 21:03:53 03/01/2011 21:04:00 03/01/2011 21:04:431/3/2011 5733 KLØ 03/01/2011 21:06:32 03/01/2011 21:07:00 03/01/2011 21:07:321/3/2011 5733 ASE 03/01/2011 21:10:13 03/01/2011 21:10:00 03/01/2011 21:12:481/3/2011 5733 LAL 03/01/2011 21:14:08 03/01/2011 21:12:00 03/01/2011 21:15:031/3/2011 5733 JEH 03/01/2011 21:17:01 03/01/2011 21:15:00 03/01/2011 21:17:581/3/2011 5733 HSR 03/01/2011 21:20:31 03/01/2011 21:19:00 03/01/2011 21:21:171/3/2011 5733 SAD 03/01/2011 21:23:00 03/01/2011 21:22:00 03/01/2011 21:23:351/3/2011 5733 DAL 03/01/2011 21:25:38 03/01/2011 21:25:00 03/01/2011 21:26:151/3/2011 5733 BØN 03/01/2011 21:30:00 03/01/2011 21:29:00 03/01/2011 21:35:12
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
33
First this train is a freight train; this enables to widen the parametrical range of investigation
of the study. Usually freight trains offer the window of opportunity to consider the effect of
speed restrictions in association with the load size on the train while the train passes
through the speed restriction zone. This issue takes in to account the extended effect of the
restrictions while the trains go along different topographies and landscape levelling. The
effect of the restrictions will vary when the train goes uphill and downhill as the ease of
respective accelerations and decelerations vary to great extent. It is usually considered
passenger trains; given the load size they carry, would take less time to accelerate than
freight trains which would carry some load way higher.
Secondly this freight train offers to great extent the opportunity to work on pure running
times and their additions, omitting dwell times and their allowances. Freight trains usually
have fewer stop stations or nothing at all except the loading and unloading stations or
crossovers. This means while analysing the time data one will be working most of the time
on pure running times avoiding the need to deal with dwell times and respective allowances
which would had been frequent on passenger trains. Passenger train stops almost on every
station for alighting and boarding passengers. This will bring in to play the need for
computing dwell times and allowances making the analysis of the whole line a complex
issue. In such situations it would be difficult to purely work with the effect of restrictions on
running times as allowances added to compensate dwell times might have extended effect
interfering in to allowances for restriction. Thus freight train is preferred and selected as
focal point to benefit from the advantages it offers and the level of analysis needed is eased
putting speed restrictions a singled out candidate of investigation.
Finally the freight train 5733 has been known for low punctuality issues. The low punctuality
trend associated with this train is known for its direct economic impact. As this train runs
majorly along the Trondheim- Oslo line the transported materials have higher economic
impact as they will be shipped further with ships to other destinations. Hence delay or time
lost by this train would have a chained economical effect to the economy as well to the
following shipment and the associated other means of transportation. Few years back this
train has even raised a subject of hot debate in the Norwegian parliament owing to the
chained economic impact associated with it. Hence working with this train and the effect of
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
34
speed restriction would give a clear and in depth understanding of the whole picture of
restrictions at its best.
Train number 5733 has been tracked all the way from ALNABRU station in Oslo to
Trondheim S in Trondheim. The major stations in between the start and stop stations in
sequential pattern included
ALNABUR – GRORUD – HAUGENSTUA – LØRENSKOG – HANABORG – FJELIHAMAR –
STRØMMEN – SAGDALEN – LILLESTRØM – LILLESTRØM N - FROGNER – LINDEBERG - KLØFTA
– ASPER – LANGELAND – JESSHEIM – HAUERSETER – SAND – DAL – BØN – EIDSVOLL –
MINNESUND – MOLYKJA – MORSKOGEN – STRANDLYKJA – ESPA – TANGEN – STEINSRUD –
SØRLI – STANGE – OTTESTAD – HAMAR – JESSNES – BRUMUNDDAL – RUDSHØGDA – MOELV
– BERGSVIKA – BRØTTUM – BERGSENG – LILLEHAMMER – HOVE – FABERG – ØYER –
TRETTEN – LOSNA – FAVANG – RINGEBU – HUNDORB – FRON – VINSTRA – KVAM – SJOA –
OTTA – SEL – BRENNHAUG – DOVRE – DOMBAS – FOKSTUA – HJERKINN – KONGSVOLL
DRIVSTUA – OPPDAL – ULSBERG – BERKAK – GARLI – SOKNEDAL – STØREN – HOVIN –
LUNDAMO – LER – SØBERG – MELHUS – NYPAN – HEIMDAL – SELSBAKK – TRONDHEIM S.
The total distance covered along one travel between ALNABUR and Trondheim S being
545.54 Km.
While tracking the train along the way time data of Standard Arrival (STA_TID), Actual Arrival
time (ATA_TID), Standard Departure time (STD_TID) and Actual departure time (ATD_TID)
has been taken in to consideration along a time range of 72 weeks. The actual and the
standard prefixes designate the real time off happening and ought to be planned schedules
respectively. In line with this the speed restriction zones and the respective magnitudes
were mapped throughout the line for the whole 72 weeks.
The mapping is done in such a way that the respective speed restriction zones have been
identified and the respective restrictions were place in between the adjacent stations to the
restriction zone. This will enable us in comparing and analyzing the magnitude and intensity
of the restrictions effect on the travel time between these adjacent stations. Thereby we can
infer implications and deduce conclusions in line with the computation of the standard time
and the actual travel time. With respect to speed restriction data, the obtained data set only
covers the line between Dombas and Trondheim S ranging 209.83 kilometers. This is
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
35
because of the fact that the generated data set were from the north line administrative
section of Jernbaneverket. The time table planners of the northern administrative section
are only responsible for administering the line from Trondheim to DOMBAS as far as the
route is concerned. Thus le the computation and analysis will be conducted for the line
mentioned above.
The time calculations
With the obtained time data for train number 5733 standard and actual times have been
computed for consecutive stations depicting the actual and standard travel times between
the stations. The formulas used included:
_ – STD_TID
_ – _ : _ _ _ _ The standard time is the planned time that the train takes to cover the distance between to
stations taking in to account optimal conditions, permissible speed and respective
allowances. Standard time usually remains constant throughout the years unless there is
generic change on the path followed or track set up. Whereas the Actual time is the noted
and computed travel time the train actually takes to cover the distance between two
adjacent stations from real time data records. Actual time between stations will vary from
day to day depending on different factors including the weather condition, the freight load,
the driver experience and so forth.
With this set up in mind on Microsoft Excel sheet the standard and actual travel times has
been computed between adjacent stations. In line with this the speed restriction zones were
mapped with their respective magnitudes along the line. This resulted in an excel sheet with
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
36
respective columns of departure date, the associated times, standard time, actual time and
speed restriction magnitudes (if there happens to be one).
While doing so 13 speed restriction zones were identified for the line between Dombas and
Trondheim S for the 72 weeks range. Each one of this restriction zones have their own
adjacent stations identified. The identified 13 restriction zones for Train 5733 along the line
during the span mentioned above included:
DOMBAS – FOKSTUA , HJERKINN – KONGSVOL , LUNDAMO – LER , MELHUS – NYPAN ,
DRIVSTUA – OPPDAL , FAGERHAUG – ULSBERG , GARLI – STØREN , SELSBAKK – TRONDHEIM ,
HJERKINN – DRIVSTUA , OPPDAL – FAGERHAUG , FOKSTUA – HJERKINN, LER – SØBERG and
NYPAN – HEIMDAL.
Having this in place the concentration of the thesis is now directed towards analyzing the
actual and standard time of the identified 13 restriction zones in line with the restriction
magnitude. In doing so, two approaches are utilized to aid the understanding and
implications of the computed data set for the given zones.
The first approach is to draw the three time sets; which are the actual time taken, the
standard time and the restriction magnitude, along a diagrammatic chart for individual time
restriction zones for the 72 weeks’ time range. This will enable us to have a close look in to
the effect of the speed restriction on punctuality or delays affecting the travel time. This
could be inferred from the pattern displayed on the chart by the actual time taken in the
presence and absence of the speed restrictions. What usually expected is the actual travel
time should go up than normal trends whenever there is an introduction of speed
restriction. Here note that the actual travel times will vary along the 72 weeks not only
because of speed restrictions but also due to other factors mentioned at the beginning of
this section. In addition the speed restrictions are distributed randomly along the 72 weeks.
Every day of the 72 weeks will not have a speed restriction in place. Some weeks or days will
entertain the restriction where as others will be set to the permissible speed. Besides the
restriction magnitudes will vary from time to time depending on the reason behind the need
for the speed restriction. Some restrictions associated with reconstruction of the track might
last few weeks whereas maintenance activities or temporary accidents might last only few
hours.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
37
The second approach is to plot the magnitude of the speed restrictions together with the
caused delay or any change in time on the actual travel time compared to the standard time.
To do so one can look in to first the deviation between the standard time and the actual
time. Thus plotting the magnitude of time lost due to the speed restriction along the x- axis
and placing the respective deviation on the y – axis one can investigate in to the effect of the
speed restriction magnitude on the deviation. The premise is that with increased time lost
due to speed restriction magnitude there will be increased travel time. Thus a strong
correlation trend between speed restriction magnitude and delays or lost time is expected.
This approach will ultimately enable us to detect if there is a correlation between the speed
restriction and the associated lost time.
Therefore the two approaches will enable us to understand and investigate in to first, the
effect of speed restriction on actual travel time and secondly if it does have effect, then to
what extent restriction magnitude affects travel time and to what level they correlate to
each other.
The effect of speed restriction on actual travel time
To understand the effect of the speed restriction on actual travel time we will take the first
approach. This approach is designated by plotting the three time sets; which are the actual
time taken, the standard time and the restriction magnitude, along a diagrammatic chart for
individual time restriction zones for the 72 weeks range. This is conducted in order to see if
there is any effect caused or trend displayed in the presence and absence of the restrictions.
With this context in mind a diagrammatical chart has been plotted for individual restriction
zones each having the time magnitude on the y-axis and the respective dates of the 72
weeks along the x- axis. The magnitudes on the y-axis will represent the three magnitudes
of standard time, actual time and the speed restriction magnitude with a notation of
individual series. In the coming sections we will go through the individual speed restriction
zone plotted diagrams and investigate in to and discuss the associated trends and patterns
displayed. From the inferred implications the first approach will deduce a concrete
conclusion on the effect of the speed restrictions on actual travel time on the basis of the
patterns displayed.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
38
DOMBAS – FOKSTUA
The distance between these two stations runs for a length of 18.61 km. while mapping the
speed restriction zone it was found out that there are three speed restriction zones between
DOMBAS and FOKSTUA. These restrictions have a speed magnitude of 0:00:30, 0:00:31 and
0:00:52 seconds. The restrictions run for 19th and 20th weeks of 2011, first week of 2011 and
week 35 of 2011 respectively. The actual time, standard time and the mapped speed
restriction magnitude are plotted; for the time range of 72 weeks starting from first week of
2011, on Microsoft excel as shown in figure 16 below.
Figure 15 Dombas - Fokstua travel time data and lost time due to speed restriction diagram
From figure 16 we can see that the actual travel time varies along the line in random pattern
fluctuating from higher to lower values regardless of the presence of the speed restriction.
At some points it even goes below the standard time. This could be a result of unbalanced
special recovery supplements and not custom tailed allowance magnitudes laid over the line
resulting in misinterpretation of the standard time. Thus at some point the train might pass
by ahead of the scheduled time, but most often it gets delayed more than the 4% allowance
added. When it comes to the effect of the speed restriction on travel time there is some sort
of paternal uniformity on the second restriction zone and the highest travel time deviations
of the whole time range have been noted on the third restriction zone. Thus even though it
0:00:00
0:07:12
0:14:24
0:21:36
0:28:48
0:36:00
restriction actual standard
TBA49, Master t
is diffic
there is
HJERKI
The line
minutes
kilomet
there a
respect
Figure 16
Figure 17
0:00:00
0:02:53
0:05:46
0:08:38
0:11:31
0:14:24
0:17:17
Master Theshesis Mignot
ult to conc
some sort
INN – KON
e between
s for train
er with a st
re two spee
ive magnitu
6 Hjerkinn -
7 zoomed in v
0
3
6
8
1
4
7 A
sis te Beyene, S
clude the re
of effect of
NGSVOL
Hjerkinn an
number 57
tandard tim
ed restrictio
udes being 0
- Kongsvol tr
view of speed
Actual Time ta
Spring 2012
estrictions
f the restrict
nd Kongsvo
733. The li
me of 8 min
on zones o
0:00:27 and
avel time dat
d restriction z
aken
39
have purely
tions on the
l extends 1
ne betwee
utes for tra
n the first w
d 0:04:09 m
ta and lost tim
zone Hjerkin
Standard Tim
y deducible
e actual trav
1.49 kilome
n Hjerkinn
ain number
week of 20
minutes.
me due to spe
n - Kongsvol
me R
e impact w
vel time.
eter with a
and Kongs
5733. Betw
011 and we
eed restriction
Restriction Ma
we can for s
standard ti
svol extend
ween these
ek 32 of 20
n diagram
agnitude
sure see
ime of 8
ds 11.49
stations
011. The
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
40
looking in to figure 17 we can see that the varaibility in the actual travel time is patternal
with the exception of some pick points. In most of the data ranges the actual travel time lies
below the standard time. Looking in to the first zoomed in picture of the speed restriction
zone of figure 18 , although the effect of the speed restriction is low the actual travel time is
kept above the standard time for the first restriction zone. If we zoom in further to the
second restriction zone we can see that the actual travel time goes way above the standard
time. In the restriction zone the devaition of the actual travel time from the standard time is
two fold larger than the lost time due to the imposed restriction. This might imply the larger
the magnitude of the restriction the bigger will be the devaition , but we will investigate the
correlation in the second approach.
LUNDAMO – LER
The track between Lundamo and Ler extends about 5.71 kilometer and ussualy takes a
standard time of 4 minutes for train number 5733. For the range of time considered the
speed restriction zone extends through out the whole 72 weeks with a magnitude of
0:00:06.
Figure 18 Lundamo - Ler travel time data and lost time due to speed restriction diagram
0:00:00
0:01:26
0:02:53
0:04:19
0:05:46
0:07:12
0:08:38
Actual Time Taken Standard Time Restriction Magnitude
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
41
Looking in to figure 19 above the actual time is distributed and varied in a uniform pattern
with centering well above the standard time. But throughout the whole data range the
actual travel time is way above the standard time close to tenfold of the lost time due to the
speed restriction. The speed restrictions effect is manifested all over the diagram lifting the
actual time way above the standard time throughout the diagram. In case of speed
restrictions running more than six months it would have been better to incorporate the
imposed restriction in to permanent speed limit so that the restriction would be adjusted in
to the standard time computation.
MELHUS – NYPAN
The rail way line between Melhus and Nypan runs for 5.2 kilometer taking a standard time
of 4 minutes. The speed restriction mapping shows there is one speed restriction zone
between these two stations within the time range of the 14th week up to the 20th week of
2011. The magnitude of the speed restriction is 0:00:20.
Figure 19 Melhus - Nypan time data and lost time due to speed restriction diagram
0:00:00
0:01:26
0:02:53
0:04:19
0:05:46
0:07:12
0:08:38
0:10:05
0:11:31
Restriction Magnitude Actual Time Taken Standard Time
TBA49, Master t
From fig
except
restricti
actual t
lost tim
and the
getting
The ma
late ea
restricti
imposit
dramati
Sometim
through
restricti
actual t
Master Theshesis Mignot
Figure 2
gure 20 we
for the re
ion zone on
travel time
e due to sp
en declines
accustome
in cause of
rly breakin
ion zone. S
ion of the
ically declin
mes there
h change o
ions clearly
ime from th
sis te Beyene, S
0 snapshot of
can see tha
striction zo
n figure 21
above the s
peed restrict
to oscillate
d and famil
f time loss i
g while ap
o it is no s
restriction.
nes and sta
could be a
f drivers. T
y illustrate t
he standard
Spring 2012
f the restricti
at the actua
one and fe
1 it is easily
standard ti
tion lifts the
e at a lower
iarized to th
n the restri
pproaching
surprise to
But once t
abilizes to o
a sudden in
Therefore t
the effect o
d time of tra
42
ion zone Melh
al time is w
ew exceptio
y observed
me. In the
e deviation
red level. T
he restrictio
iction zones
the zone
see the gra
the drivers
oscillate at
ncrease in
he analysis
of the rest
avel.
hus - Nypan
well distribut
ons. Lookin
that the s
diagram it
in an increa
This might b
on zone.
s for freight
and late a
aph to shoo
get used to
some leve
the diagra
s of the tim
riction on d
ted close to
ng in to th
peed restri
is noted th
asing patte
be a result
t trains is t
cceleration
ot up on th
o with the
l as seen o
am which c
me data an
delay or th
o the standa
e snapshot
iction lifted
at the effec
rn to reach
of the train
he time los
while leav
he first day
route the lo
on figure 21
could be ex
d lost time
e deviation
ard time
t of the
d up the
ct of the
the pick
n drivers
st due to
ving the
ys of the
ost time
1 above.
xplained
e due to
n on the
TBA49, Master t
DRIVST
The rai
standar
mappin
four we
second
magnitu
Figure 21
Figure 22
0:00:00
0:02:53
0:05:46
0:08:38
0:11:31
0:14:24
0:17:17
0:20:10
0:23:02
Master Theshesis Mignot
TUA – OPP
lway line
rd time of 1
g shows th
eeks betwee
one runs
ude of 0:00
1 Drivstua- O
2 snapshot of
0
3
6
8
1
4
7
0
2
R
sis te Beyene, S
PDAL
between D
15 minutes
hat there a
en the 15th
in the tim
:25.
Oppdal time d
f the speed re
Restriction Ma
Spring 2012
Drivstua an
for train nu
re two spe
week and 1
me range b
data and lost
estriction zon
agnitude
43
d Oppdal
umber 5733
ed restricti
18th week o
between we
time due to s
ne Drivstua- O
Actual Tim
runs for 2
3 to cover t
ion zones.
of 2011 with
eek 19th a
speed restrict
Oppdal
me Taken
2.16 kilom
the gap. Th
One runnin
h a magnitu
nd 22 wee
tion diagram
Standar
meters and
he speed re
ng for the d
ude of 0:01
ek of 2011
m
rd Time
takes a
striction
duration
1:19. The
1 with a
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
44
Figure 22 shows the time data and lost time due to speed restriction diagram for the line
between Drivstua and Oppdal. From the figure we can see that the actual time lies below
the standard time for most of the data ranges displayed and also it is varied uniformly
around the standard time. While zooming in to the speed restriction zone as displayed on
figure 23 one can see that the Actual travel time curve is lifted further above the standard
time. The actual travel time shows a trend of inclining, declining and again inclining and
declining.
This is typically associated with a cyclical change in the intensity of the reason behind the
speed restriction. For instance, if the weather is behind the imposition of the restriction then
cyclical variation in weather could bring the witnessed trend of change in the lost time. This
also could be explained through shifting of drivers, the drivers’ first hitting the pick and then
again lowering the lost time as time goes by supplemented by experience. Therefore from
this diagram we can see the actual travel time has been well affected by the imposition of
the speed restriction as the diagram entertains huge bump ups in the restriction zone unlike
the rest of the data range.
FAGERHAUG – ULSBERG
The line between Fagerhaug and Ulsberg that runs for 13.82 kilometers takes a standard
time of 10 minutes for train number 5733 to cross by. This is one of the most congested of
the zones mapped over the range of the 72 weeks. There are four speed restriction zones in
the data range at between 15th and 18th week, on the 20th week , between 24th and 25th
week and the last one running between week 38 and 39 0f 2011. These zones have a
restriction magnitude of 0:00:51, 0:00:45, 0:00:31 and 0:00:28 seconds respectively.
TBA49, Master t
Figure 23
Figure 24
As show
standar
time gra
speed r
lost due
deviatio
graph a
progres
0:00:00
0:02:53
0:05:46
0:08:38
0:11:31
0:14:24
0:17:17
Master Theshesis Mignot
3 Fragerhuag
4 exploded vi
wn in figur
rd time. But
aph tends t
estriction h
e to respec
on magnitud
at the begin
ssive severit
0
3
6
8
1
4
7
R
sis te Beyene, S
g - Ulsberg ti
iews of the sp
e 24 on no
t in the reg
o go up lea
having signif
ctive speed
de by the sa
nning to rea
ty of the re
Restriction Ma
Spring 2012
me data and
peed restrictio
ormal days,
gions where
ding the de
ficant effec
d restriction
ame or mor
ach a pick
estriction’s
agnitude
45
lost time due
on zones Frag
, most ofte
e the speed
eviation to g
t on the de
ns magnitu
re sums. Th
at the midd
background
Actual Ti
e to speed res
gerhuag - Uls
en the actu
d restriction
go higher. T
lays. Furthe
ude also ha
e progressiv
dle might a
d reason as
me Taken
striction diag
sberg
ual travel ti
n is impose
his affirms t
ermore the
as its share
ve tendency
also be exp
s time goes
Standar
ram
ime lies be
ed the actu
the premise
change in t
e of enhanc
y of the act
plained thro
s by. For ins
rd Time
elow the
al travel
es of the
the time
cing the
tual time
ough the
stance if
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
46
the restriction is imposed due to construction work, in the beginning the construction work
is not that intensively done and as time goes by the work reaches its major stage creating
difficult ease of pass for the drivers. Then when the work comes to a closure little congestion
will be imposed on the line and the train can pass through easily with less time lose due to
the restriction. Thereby the actual time curve follows the same progressive trend from the
beginning to the middle and declines back towards the end.
GARLI – STØREN
The distance between these two stations extends for a length of 9.29 kilometers having
another station called Soknedal between the two. Train number 5733 takes a standard time
of 19 minutes to pass through the two stations. The speed restriction is imposed on the 15th
week of 2011 with a magnitude of 15 minutes. The actual speed restriction zone starts on
the way from Garli and Soknedal and ends on the way to Soknedal to Støren. That is why the
analysis is being conducted on the margin between Garli and Støren.
Figure 25 Garli – Støren time data and lost time due to speed restriction diagram
0:00:00
0:07:12
0:14:24
0:21:36
0:28:48
0:36:00
Restriction Magnitude Actual Time Taken Standard Time
TBA49, Master t
Figure 2
except t
standar
the actu
But it i
imposit
approac
were so
ease of
reason
still exis
the rest
SELSBA
The line
to Tron
train nu
speed r
from th
zones h
Master Theshesis Mignot
Fi
26 shows th
the speed r
rd time curv
ual time cur
is interesti
ion. This co
ch that, the
ome activiti
f attaining t
could be th
sts even afte
trictions hav
AKK – TRO
e from Selsb
dheim exte
umber 5733
restriction r
e 38th week
ave a time
sis te Beyene, S
igure 26 explo
hat the actu
restriction r
ve. In the e
rve goes up
ng to see
ould be exp
e planners c
ies or sever
the permis
he placebo
er they had
ve significan
ONDHEIM S
bakk to Tro
ending a len
3 to pass by
ranges on b
k to 11th we
loss magnit
Spring 2012
oded view of
ual travel tim
egion. And
exploded vie
with the im
the curve
plained thro
could have
re condition
sible speed
effect on th
d been revo
nt effect on
S
ondheim S i
ngth of 6.43
y until it co
between 20
eek of 2012
tude of 0:01
47
the speed res
me is evenl
often the a
ew of the s
mposition of
even goin
ough two re
revoked the
ns continui
d a difficult
he drivers;
ked. Still fig
n the delays
s the last se
3. This segm
omes to sto
0th and 21
, which is th
1:51 and 0:0
striction zone
y distribute
actual time
peed restric
f the restric
ng up after
easoning’s.
e restriction
ng, hinderin
t task for t
keeping on
gure 26 affir
and lost tim
egment of t
ment takes 8
op at Trond
week of 20
he end of th
01:08.
e Garli – Stør
ed along the
taken lies a
ction zone
ction.
r the end
The first is
n but still o
ng passing
he train dr
to think th
rms our wo
mes.
the line on
8 minutes o
heim S. thi
011 and the
he data ran
ren
e whole dat
a little bit be
shown on f
of the res
s a straight
n the groun
by and ma
rivers. The
he speed re
rking prem
the way fr
of standard
s segment
e one that
ge. Each re
ta range
elow the
figure 27
trictions
forward
nd there
king the
e second
striction
ises that
om Oslo
time for
has two
extends
striction
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
48
Figure 27 Selsbakk – Trondheim S time data and lost time due to speed restriction diagram As seen on figure 28 the actual time curve, fluctuates randomly hitting higher points and all
of a sudden arbitrarily moving down. Most of the actual travel time’s magnitudes are above
the standard time. The fluctuation could be due to the intense traffic condition near
Trondheim S which could vary on daily or even hourly basis. Therefore from the diagram one
can concluded there is no concrete reason to claim the speed restrictions have affected the
travel time.
HJERNIK – DRIVSTUA
This section of the line extends for 25.36 kilometers having a station called Kongsvoll in
between. Train 5733 takes a standard time of 19 minutes to cross between the two stations.
The speed restriction mapping shows that there is one restriction zone on the 20th week of
2011on this segment of the line with a magnitude of 0:00:50. This restriction zone was
stretched between Hjernik and Drivstua leaving out kongsvoll in between, because of the
fact that the restriction zone lays the whole way across Kongsvoll station. The restriction
zone starts on the way between Hjernik to kongsvoll and ends on the way kongsvoll to
Drivstua.
0:00:00
0:02:53
0:05:46
0:08:38
0:11:31
0:14:24
0:17:17
0:20:10
0:23:02
0:25:55
0:28:48
Restriction Magnitude Actual Time Taken Standard Time
TBA49, Master t
Figure 28
Figure 29
As figur
variatio
Referrin
0:00:00
0:07:12
0:14:24
0:21:36
0:28:48
0:36:00
Master Theshesis Mignot
8 Hjernik – D
9 Exploded v
re 29 show
n but abru
ng to both f
0
2
4
6
8
0
R
sis te Beyene, S
Drivstua data
view of the sp
ws the actu
uptly there
figure 29 an
Restriction ma
Spring 2012
a and lost tim
eed restrictio
ual travel ti
e are some
nd figure 30
agnitude
49
me due to spee
on zone Hjern
ime curve
e bumps n
0 although
Actual Ti
ed restriction
nik – Drivstu
at points s
noticed ma
there is a s
ime Taken
diagram
ua
stabilizes an
king the v
small inclina
Standa
nd have a
variability ir
ation in tra
ard Time
uniform
rregular.
vel time
TBA49, Master t
curve, it
as comp
OPPDA
This seg
for train
betwee
Figure 30
Figure 31
0:00:0
0:02:5
0:05:4
0:08:3
0:11:3
0:14:24
0:17:1
0:20:1
Master Theshesis Mignot
t is difficult
pared to oth
AL – FAGER
gment of th
n number 5
n 33rd and 3
0 Oppdal – F
1 Exploded v
0
3
6
8
1
4
7
0
R
sis te Beyene, S
to conclud
her noticea
RHAUG
e line exten
5733 to cro
34th week o
Fagerhaug tim
view of the sp
Restriction M
Spring 2012
e the speed
ble upward
nds for 12.0
oss the sect
of 2011 with
me data and l
eed restrictio
agnitude
50
d restriction
d fluctuation
07 kilometer
ion. There
h a magnitu
lost time due
on zone
Actual T
n have signif
ns across th
rs and it tak
is one rest
de of 0:04:4
to speed rest
ime Taken
ficant effec
he data rang
kes 8 minut
riction zone
44.
triction diagr
Standa
t on the tra
ge.
es of standa
e in the dat
ram
ard Time
avel time
ard time
ta range
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
51
Looking in to figure 31 one can easily see that the actual travel time is regularly distributed
and centered below the standard time except few bumps and larger deviation in the speed
restriction zone of the data range. Zooming in to the restriction zone in figure 32it is seen
that the Zooming in to the restriction zone in figure 32 it is seen that the imposed restriction
first seemed to cause no effect at all but starts to kick of lifting the actual time curve upper
as time goes on. But after the imposed restriction was over the actual time curve goes a little
bit higher for a while and comes back to the regular variation stream. This only is explained
through the mismatch of the planned restriction schedule and what actually happened on
the ground. This means that the speed restriction was imposed on the ground later than
what was written on the weekly planned speed restriction schedule and also the restriction
was revoked later than what was set to be the due date . Still figure 31 as well as figure
illustrates the fact that the speed restrictions had a significant effect on the given span.
LER – SØBERG
This segment of the line extends for 8.28 kilometers and takes a standard time of six minutes
for train 5733. This section contains one speed restriction zone on the 10th and 11th week of
2012 with an associated time loss of 0:00:40.
Figure 32 Ler – Søberg time data and lost time due to speed restriction diagram
0:00:00
0:01:26
0:02:53
0:04:19
0:05:46
0:07:12
0:08:38
Restriction Magnitude Actual Time Taken Standard Time
TBA49, Master t
Figure 33 As can b
standar
through
curve. H
travel t
implicat
NYPAN
The dis
standar
one spe
magnitu
Figure 34
0:00:000:00:430:01:260:02:100:02:530:03:360:04:190:05:020:05:460:06:290:07:12
Master Theshesis Mignot
3 Detailed vie
be seen on
rd time. If
hout the tim
Hence this
time. Since
tion of the e
N – HEIMDA
tance betw
rd time of 4
eed restrict
ude of 0:00
4 Nypan – He
03603692692
sis te Beyene, S
ew of the spe
Figure 33 th
we look f
me range th
also confirm
e the collec
effect could
AL
ween these
4 minute fo
tion zone i
:33.
eimdal time d
Restriction M
Spring 2012
ed restriction
he travel tim
urther in t
he curve ten
ms our pre
cted data
d not be not
two statio
r train 5733
n the data
data and lost
Magnitude
52
n zone Ler – S
me is unifor
to the spee
nds to go up
emises on t
range is th
ticed.
ns runs for
3 to pass th
a range in
time due to s
Actual T
Søberg
rmly varied
ed restricti
p centering
he effect o
he end of
r a length o
hrough. This
the 10th an
speed restrict
Time Taken
centering a
ion zone u
g well above
of speed res
the limit f
of 4.3 kilom
s segment o
nd 11th we
tion diagram
Standa
a little bit be
unlike the
e the standa
strictions o
further con
meters and
of the line c
ek of 2012
ard Time
elow the
patterns
ard time
on actual
nditional
takes a
contains
2 with a
TBA49, Master t
Figure 35
Figure 3
time lin
though
conclus
ends at
imposit
support
In gene
sufficien
actual t
turn a s
there is
presenc
The co
From t
significa
from th
to rest
correlat
deviatio
the cor
Master Theshesis Mignot
5 Detailed vie
34 shows th
e in a non u
the travel
ion that wa
t this point
ion. Hence
ting argume
eral we can
nt data, uni
ime curve i
strong findin
s an increa
ce of the sp
orrelation
he first ap
ant effect o
he planned
rictions ha
tion betwee
on one need
relation bet
sis te Beyene, S
ew of the spe
hat the actu
uniform pat
l curve goe
as caused by
t we are in
e we can’t
ent for our p
n state tha
iformity and
is lifted up
ng that sup
sing effect
eed restrict
n between
pproach it
n the actua
standard ti
ave affecte
en the mag
d to go for t
tween the
Spring 2012
ed restriction
ual time tak
ttern. But lo
es high in
y the introd
no positio
use the
premises.
t most of
d regular fl
above the s
pplements o
caused an
tions.
n restricti
was seen
al travel tim
me. But it i
ed the dev
gnitude of t
the second
lost time d
53
n zone Nypan
ken curve f
ooking furth
an increas
duction of th
on to say if
data analy
the analysi
uctuation o
standard lin
our approac
d trend dis
ion magni
that the
me there by
is not clear
viation itse
the lost tim
approach.
due to the s
n – Heimdal
fluctuates a
her in to th
sing fashion
he restrictio
f it was aff
sis betwee
is done sho
of the time
ne curve wi
ches premis
splayed on
itude and
introductio
affecting th
how the m
elf. Therefo
me due to r
In the seco
speed restr
above and b
e speed res
n, it is diff
on. As the c
fected or n
en Nypan a
ows that, a
magnitude
th a signific
ses. Therefo
the actual
d deviation
on of spee
he deviation
magnitude o
ore to inve
restriction
nd approac
riction and
below the s
striction zon
ficult to de
ollected da
not affected
and Heimd
as long as
s on the cu
cant margin
ore we can
time take
n
ed restrictio
n of the tra
of the lost t
estigate in
and the as
ch tries to lo
the deviatio
standard
ne; even
educe a
ta range
d by the
dal as a
there is
rves the
n. This in
say that
n in the
on have
avel time
ime due
to the
sociated
ook in to
on, with
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
54
the premises of the deviation of the going up in line with an increase in the magnitude of
the computed lost time in the introduction of the speed restriction.
This premise is built up on the contextual understanding of the train drivers assuming higher
restriction magnitudes causing larger delays. To look in to this scenario this section tries to
compute the deviation of each recorded actual time from the planned standard time and
plots it on a graph against respective lost time magnitudes. Looking at the plots on the graph
we will check if there happens to be an increasing, decreasing or random trained in the plot
itself. This could be done in two ways; first plotting the actual deviation magnitude against
the lost time magnitudes and the second one by plotting the percentage of deviation against
the lost time. To do so one need first to compute the deviations and the percentage of
deviations. This is computed using the formulas below.
–
Percentage of deviation serves as a key factor to express deviations in terms of their basic
cause. Some small lost times could cause larger deviations compared to their own
magnitude; may be three times the computed lost time and at same time larger computed
lost times due to restriction may cause as half as their magnitude. But for someone who is
concentrating barely on caused deviations he/she would infer the larger the lost time the
larger would be the deviation. Therefore not to fall in this trap of delusion there needs to be
a consideration to take in to account the percentile of the deviation itself.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
55
Plotting the computed deviation magnitude against the lost time will only shows how
specific magnitude of restrictions have brought lost time and how the trend is displayed if
there is one. Whereas plotting the percentage of the deviation against lost time will provide
in depth understanding of the criticality as well as the intensity of the speed restriction
magnitude itself; thereby also providing an opportunity to investigate in to trends if there
happens to be one.
Even though the above notion seems true, there should be a consistency in data type and
external factors that will affect the delay of the train in addition to the restrictions. As the
set up and the affecting factors on travel time do vary along the line from station to station it
calls for the need of normalization. The normalization could be done in two ways either with
utilizing factors on the computation or introducing constant denominator that could give a
common basis for the computations.
To do so the second way, which is introduction of a consistent denominator is preferred for
this condition. Therefore we will compute the both the percentage of the lost time and the
deviation percentage. This will enable us to look in to how lost time due to restriction and
deviation will vary in line with the standard time. This will be done in such a way that the
percentage of the deviation will be computed and rated against respective standard times.
Similarly the lost time due to restriction will be rated in percentiles with respect to their
standard times. Here the standard time will serve us a basis of consistency for the
computation as well it will enable a common ground and base factor to reduce
inconsistencies due to variation in stations. Plotting the percentage of lost time due to
restriction against the percentile of deviations will give us a primary basis for conclusion
when it comes to investigating the relationship between magnitude of lost time due to
restriction and the associated deviation in travel time.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
56
Figure 36 plot of the deviation magnitude against respective time lost due to deviation with correlation factor of 0.092 Figure 36 displays the first way of plotting the deviation magnitude against lost time due to
imposition of the restriction. The trend shows that starting from a time loss of 0:00:06 until
0:00: 43 there is an increasing trend in lost time and then a decreasing and increasing
patterns fluctuate randomly until it reaches 0:01:19. After wards the graph shows an
increasingly upward curve. This implies with magnitudes larger than 0:01:19 the graph has
an increasing trend. Therefore we can state that for this data range collected; for speed
restrictions which have a computed time loss of greater than 0:01:19, the larger the
magnitude of the speed restriction the higher will be the associated deviation. Fitting the
time magnitude points on the scatter diagram with Microsoft excel an increasing linear curve
displayed as Linear (deviation) on the legend is obtained. This illustrates as the time lost
increases there is an associated increase in the actual travel time taken. Hence somewhat
for this data range, time loss due to restriction has positive impact on the associated
deviation in the travel time. In addition while doing the correlation analysis for this data set
it yielded a week correlation factor of 0.092.
00:00:0000:02:5300:05:4600:08:3800:11:3100:14:2400:17:1700:20:1000:23:02
0:00:00 0:00:43 0:01:26 0:02:10 0:02:53 0:03:36 0:04:19 0:05:02
Devaition
devaition Linear (devaition)
dev
Lost time
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
57
Figure 37 percentage of deviation against lost time Figure 37 illustrates a plot of the percentage of deviation drawn against the lost time due to
speed restriction. From the pattern displayed we can see that smaller lost times due to
restriction tend to have larger effect on travel time, causing by far larger deviations in
contrast to their magnitudes. Here further fitting points on the scatter diagram using
Microsoft excel we can obtain a down ward pointed decreasing linear curve designated as
linear (Series) on the legend. Hence even though small time losses due to restrictions have
small magnitude compared to their intensity they have, by far higher percentage of effect.
From the diagram we can see that the higher the lost time due to speed restrictions the
lower the percentage of the deviations get. Hence smaller speed restrictions, it tend to have
higher relative effect on the actual lost time compared to their magnitudes.
-20
-10
0
10
20
30
40
0:00:00 0:00:43 0:01:26 0:02:10 0:02:53 0:03:36 0:04:19 0:05:02
Series1 Linear (Series1)dev/lost t
Lost time
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
58
Figure 38 scatter diagram of percentage of deviation against lost time percentage with a correlation factor of 0.135 Figure 38 displays a scatter chart of travel time deviation percentage on the Y- axis plotted
against lost time due to restriction percentage on the X-axis. From the plots and the
percentages of respective magnitudes with respect to standard time percentage is the best
way to look in to the correlation between these two factors. Using the standard time as a
common of computation will ensure the consistency of the data as well serves a purpose of
normalization of the whole data set. Fitting the scatter diagram points in to a curve using
the curve fitting option on Microsoft excel the curve noted as Linear (Series 1) is obtained.
Although; the slope of the curve is so small, it depicts an increasing trend in the percentage
of deviation in line with increasing the lost time due to restrictions. Here in accordance to
the primary background premises of the thesis, what has been expected was a perfect linear
upward pointed curve especially for lost time magnitudes more than 4% of the standard
time. While conducting a correlation analysis for the whole data range including the whole
restriction period, it was found out that the percentage of lost time due to speed restriction
and the adjacent deviation percentage has a correlation factor of 0.135. Extending and
limiting the correlation analysis to peak values only somewhat similar correlation factor of
0.185 was obtained. The small angle of inclination or lower slope of the fitting curve implies
there appears to be low correlation between the percentage of deviation and the associated
lost time due to restriction. This weakness in the correlation, for the whole data set might be
due to in consistency in the setting and nature of the data considered, as the analysis has
-50%
0%
50%
100%
150%
200%
Series1 Linear (Series1)dev%
lost time%
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
59
been conducted on different stations on different seasons throughout the years. Variation
in season of the year will imply varied external effects on the travel time itself. For instance
equivalent restriction magnitudes in summer and winter have varied ultimatum effect on the
actual travel time thereby on the percentage of deviation itself. Furthermore the
topographic setup and related conditions on speed restriction zones varies along with the
stations hence it makes it difficult to conduct a consistent analysis along the line. Finally the
4% allowances added on the computed standard times had their own effect absorbing the
speed restriction effect from manifestation. On figure 38 above, this had been purely the
case for data ranges of lost time percentages lower than the 4% allowances absorbing the
effect and showing random variation. But for percentage of time lost more than 4% the
trend has been somehow an increasing curve.
With this weak or no correlation witnessed further efforts have been made to dissect the
data in to first week of imposition of the restriction. This is done as there was a tendency or
trend of increment in the first weeks of the time diagram graphs of respective zones. While
conducting the correlation analysis for this data segment it was found out that the
percentage of lost time due to speed restriction and the adjacent deviation percentage has a
correlation factor of 0.433. With this finding the percentage of deviation for the first weeks
was plotted against the adjacent percentage of time loss due to restriction. Fitting the
scatter diagram points in to a curve using the curve fitting option on Microsoft excel the
curve noted as Linear (First week basis) is obtained. This shows an increasing curve with
increased slope as shown in figure 39 below.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
60
Figure 39 scatter diagram of percentage of deviation against lost time percentage on first week basis with a correlation factor of 0.433 With this context and new finding in mind further work was done to normalize the data set
of deviation percentage and lost time due to restriction percentage. This was done in order
to reduce noise of the data and to avoid misinterpretations caused due to arbitrary data
with extremely maximum and extremely minimum values. In doing so the average deviation
for respective time losses due to restriction percentages was computed. This is done in such
a way that the deviation percentages were averaged based on their respective time losses
percentages due to the restrictions categories. This means the deviation percentages of
individual speed restrictions were averaged. After this, correlation analysis was conducted
on Microsoft excel for the average deviation percentages and the respective time losses
percentages due to restrictions. This correlation analysis yielded a correlation factor of
0.595. This is a significant number showing a tendency towards a strong correlation. With
this finding the average deviation percentage for the data set was plotted against the
adjacent percentage of time loss due to restriction on a scatter diagram. Further fitting the
scatter diagram points in to a curve using the curve fitting option on Microsoft excel the
curve noted as Linear (Average deviation) is obtained. This shows a further increasing curve
with added increased slope than the plots so far, as shown in figure 40 below.
-50%
0%
50%
100%
150%
200%
First week basisFirst week basis Linear (First week basis)Dev%
Lost time %
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
61
Figure 40 scatter diagram of average deviation percentage against lost time percentage with correlation factor of 0.595
On figure 40 the y axis represents the averaged values of the deviation for individual speed
restrictions whereas the X-axis displays the percentage of lost time for individual speed
restrictions. This graphical illustration on figure 40 and the obtained correlation factor of
0.595 from the correlation analysis shows there is somehow a positive tendency towards
correlativeness between the average deviation percentage and the lost time percentage.
(See appendix).
Further working correlation analysis was made on the average deviation percentage of the
data set for more than 4% of the time lost percentage due to restriction. From the
correlation analysis it was found out that the average deviation percentage and percentage
of time lost due to restriction are correlated by a factor of 0.603 (see appendix). The
increase in the correlation factor after the 4% is as expected the fuzzy boundary of
correlations that came in to existence due to 4% time allowances added on the standard
time. Therefore omitting the extreme values or normalizing them using averaging statistical
tool one can see there is a correlation between deviation magnitude and the associated time
loss due to restrictions.
-10%
0%
10%
20%
30%
40%
50%
Average deviationAverage deviation Linear (Average deviation)Average Dev%
Lost time
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
62
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
63
Conclusion
This conclusion part is structured in such a way that, it presents the conclusions made on the
course of addressing the research questions.
To what level of detail should such studies be done?
For data analysis involving investigation in to speed restriction care should be taken in
selecting the appropriate tools of analysis. On the course of conducting this thesis it was
found out that restriction zone mapping and statistical analysis play the major role. In
addition diagrammatical plotting of data sets on Microsoft excels and inferring implications
is of high prominence. Specifically curve fitting and line plots on will take the biggest share
of the implication deduction part enabling a clearer understanding of outputs.
The actual Travel time and standard data sets collected also plays of high significance when
it comes to the ultimate outputs of the analysis and the thesis itself. The data set should be
consistent and accommodating when it comes to different attributes that would affect travel
time or else it should be normalized to mitigate interference. Otherwise it is difficult to get
grasp of the clear image and effect of speed restrictions, as different factors such as
topography, climatic conditions, seasonal variation, travel direction and type of train might
affect and sub standardize the analysis.
In this thesis work efforts has been employed to ensure the consistency of the analysis and
data sets collected. In this virtue the analysis was done on freight 5733 with lots of
punctuality complaints history. This has enabled the manifestation of trends on speed
restrictions to greater extent. In addition to keep uniformity of the analysis similar analysis
tools has been utilized throughout the work including normalization by averaging and
percentiles.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
64
Relationship between speed reductions and delays
Trend based relationship From the analysis of most restriction zones and fitting curves of the travel times in the
restriction zone; it was found out that, for most of the restriction zones the travel time tends
to go up to reach its pick and declines again to lower magnitude towards the end. This
tendency is associated with the time based build up of learning curves of the drivers getting
accustomed to the restriction zone after a while. Furthermore progressive severity of the
reason behind the imposition of the restriction could also offer an explanation for this
phenomenon. In the restriction zone between Lundamo and Ler it have been noted that, the
speed restriction has been imposed more than a year and a half. This type of restrictions as
they long last rather than imposing them as temporary restrictions they should be
incorporated in to the standard time and should be set as a permanent restriction.
Also in some of the analyzed restriction zones cyclical variations has been noted which has
been explained by seasonal or cyclical variation on the root cause of the restriction
imposition itself and change of drivers bringing in to play different learning curves the
drivers. Most often lifting of the standard time and random shootings in travel time were
explained through imposing and revoking of restrictions ahead of time, placebo effects in
play on drivers and unbalanced special recovery times.
Looking in to the analysis done on the 13 restriction zones it was found out that as long as
there is sufficient data, uniformity and regular fluctuation of the time magnitudes on the
curves the actual time curve is lifted up above the standard line curve with a significant
margin. Visual inspection of the graphs indicated that the impact of speed restriction was
greater during the beginning of the period. This supports the premises of this thesis
assuming existence of an increasing trend in the relationship between the lost time due to
restriction and deviation for some range of data. Therefore there is an increasing effect
caused and trend displayed on the actual time taken in the presence of the speed
restrictions. This strengthens one of the research premises of speed restrictions having
effect on the actual travel time thereby causing delays.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
65
Magnitude based relationship While working on the relationship between lost times due to speed restrictions and
magnitude of the caused deviation, even if the fitting curves has directed an increasing
tendency. First it was found out that there was a weak correlation between the percentage
of the lost time and the percentage of the caused deviation for the whole data set. But for
some data sets above the 4% allowances there, tends to be a positive correlation. The
correlation analysis on first weeks based on the imposition of the speed restriction also
showed a greater correlation with a factor of 0.433. These led to conducting an average
deviation percentage analysis to normalize the data; in which the correlation analysis yielded
a correlation factor of 0.595. This showed somehow there is a positive tendency towards
correlativeness between the average deviation percentage and the lost time percentage. In
addition correlation analysis made for speed restrictions greater than 4% lost time showed
that there is an increased correlation factor of 0.603. This is an indication that the fuzzy
boundary of correlations somehow lies on the 4% zone. This fuzzy boundary might come in
to existence as a result of the added 4% allowance which is usually added by the railway
time planners on the standard time. Therefore it could be concluded that, omitting the
extreme values or normalizing them using averaging and percentile statistical tools there is a
correlation between deviation magnitude and the associated time loss due to restrictions.
Hence this depicts the fact that there needs to be further work to be done with consistent
data sets on fixed positions to clearly zoom in to the real effects displayed.
In the relationship analysis it was interesting to note that small time loses associated with
lower restrictions tend to cause higher effect of intensity compared to their magnitude.
While fitting such curves it was found out there tends to be a decreasing curve illustrating
smaller reductions having significant percentile effect than bigger ones.
The lack of the anticipated purely increasing or strongly correlated pattern between
percentage of lost time due to restriction and associated deviation magnitudes is an
opportunity for further researches in the thematic area. This could be surmounted by
studying and analyzing the restriction zones with consistent data, specific seasons and
focused areas on the restriction zones. Furthermore expanding the range of the data to
include more percentage of lost time magnitudes, differ directions along segments and
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
66
varied types of trains would lead to refined results. In addition causes of different levels of
correlations between the lost time and deviation along the route are other thematic areas
whereby supplementary researches could be conducted.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
67
Appendix
Time lost due to restriction %
Average Deviation percentage
2.50% 16.00%2.87% 15.05%4.39% -4.08%4.67% 2.90%4.81% 12.26%5.12% 42.67%5.17% 3.97%5.63% 1.42%7.50% -0.83%8.33% 33.94%8.50% 18.35%8.78% 15.69%
11.11% 8.97%13.75% 0.18%14.17% 28.96%23.12% 12.71%51.88% 43.46%59.17% 38.22% N= 20 82.81% 36.70% Correlation Factor 0.595
Time lost due to restriction %
Average Deviation percentage
4.39% -4.08%4.67% 2.90%4.81% 12.26%5.12% 42.67%5.17% 3.97%5.63% 1.42%7.50% -0.83%8.33% 33.94%8.50% 18.35%8.78% 15.69%
11.11% 8.97%13.75% 0.18%14.17% 28.96%23.12% 12.71%51.88% 43.46%59.17% 38.22%82.81% 36.70% N= 18
Correlation Factor 0.6026
18 19 20 21
18 19 20 21
67,86
64,51
62,24
59,54
57,20
53,44
49,62
46,10
44,60 *
42,22
40,30
36,38
32,28
29,80
26,94
25,18
22,76
20,95
19,83
19,05
18,92
17,93
16,42
16,17
15,50
14,15
13,09
12,10
12,09
10,50
9,30
8,72
6,87
5,85
3,89
2,28
0,27 *
1,40 *
2,29
4,38
10,50
7,33
8,72
7,33
7,33
5,85
7,33
5,26
3,89
1,97 *
1,08
Dønnum Bp
Km fraOslo S
EIDSVOLL
BØNVarud
DAL
SAND
HAUERSETER
Nordby
JESSHEIM
LANGELAND
ASPER
KLØFTA
LINDEBERG
FROGNER
Leirsund
LILLESTRØM N
General Motor s.sp.
LILLESTRØMH-sign 1214, Lillestrøm
Sagdalen
Sagdalen Bp.
STRØMMENFjellhamar
Fjellhamar Bp.
Hanaborg
LØRENSKOGHøybråten
Haugenstua Bp.
Haugenstua
GRORUDNyland
AKER
Alna
BROBEKK
BRYN
Sporv.303
OSLO S
NATIONALTHEATRET
Elisenberg Bp.A
SKØYEN
Km fraOslo S
GRORUD
ALNABRU
Km fraOslo S
AKER
ALNABRU
Km fraOslo S
ALNABRU
BROBEKK
Km fraOslo S
ALNABRU
Teisen s.sp
BRYNOslo S s.sp Kværner
LOENGA
3: 190 EVL
Kmmellomstasjon
Kryssspor-lengde
3,35
3/5: 7004: 7705: 310
2,27
DNM
5,04
2: 591 BØN
3,76
1: 536 DAL
2: 730 SAD
3,82
5,02
1: 5552: 664 HSR
2,35
1: 5473: 535 JEH
1,92
LAL
3,92
1: 711 ASE
4: 718 KLØ
4,10
2,48
1: 696 LBG
4,62
1: 321 FRO
4,23
15: 914 BRT
GMO
6: 3807: 3748: 3319: 270 LLS
1,12
0,91
SLD
0,99SLN
1,76
STN
2,02
FH1
1: 374 LØR
2,05
1,60
HG1
1,78
3: 560 GRO
2,87
AKE
1,96
BRB
3,62
BR
SP3
1,67
OSL
0,89
NTH
2,09
ELI
SKØ
Kmmellomstasjon
3,17
3: 560
Kryssspor-lengde
GRO
ALB
Kmmellomstasjon
1,39
Kryssspor-lengde
AKE
ALB
Kmmellomstasjon
Kryssspor-lengde
1,48
ALB
BRB
Kmmellomstasjon
3,44
Kryssspor-lengde
ALB
TEN
3,89
BR
KVÆ
LOE
18
18
18
18
19 20
19 20
19 20
19 20
GRORUD - ALNABRU
AKER - ALNABRU
ALNABRU - BROBEKK
LOENGA - ALNABRU
21
21
21
21
21 21 21
431)3)
1)
433 3
7)
11)
8)
12)52)
56)
8) 4328)
39)58)58)
43 43358)
2)33)
37)32)
35)
49)
53)
37
40)6)
9
6)
9
14)
17)
15)
18)46)
49)
54)29) 40)
3132
154
22) 1542) 21)42)
3 28)
17)
19)
24)
25)39) 49 52)
17)
19)
46)
52)
37
40)
37
40)6)
952)
55)41)
46)43)
46)
28)
30)
54)29) 29)15)46) 37)22)
3132
48)51
54) 3132
1539)24)
52)28)
23)
2628)
45)
57)
58)28)
17)
19)12) 36)
41)
4413
19)
54)
52)52)
24 2521 33
36)28)36)
484946
4821
57)
21
28322528) 44) 52) 2141
0) 16
1731
21) 4154
1748)47) 2)
12)
36 37)12)37)
17)58)
12)51)50)
712)
8)
484946
482425
24 33) 42) 1)46
242521
249)33)
44) 52)28
3844)
38) 4) 44)2128
6)
25
28)
4849
4855)
52) 58
415431 3)48)
4117316) 21)
36 58)37)58)37) 51 52)46
36 37)12)37)
10) 17)
54
58)5458)
32342
4 8 99
392212)
252
4 8941
429
52 2256)44) 55
17)4)
12)15)
40)4 3426
8) 29) 456
1)21)
59)
0)
7) 11)
3234 2
443
4441
4239 5246)
56)
42)10
12 3234
8 941
423922 39)45)
14)12)
18) 5249)
47)34 4
5642)
0)37)
15)34
2642)41) 44)
18)8)
23)56
23)55)12) 42) 12) 42) 12) 42) 52)37) 34)31)
28 58232 2 7)
36) 53)5)
4) 32) 3) 8)
220) 12) 52 2248)
58) 3)
18)
9 39
30)
32) 35)
48) 18)
9 14)12)
33)36)
50)28 58
32225) 4)
18)28 32
46)37)5)40)
22) 27) 58
5231) 0) 229 33)12)53)
48)
3928)
58)
21)
18)
3936)26)
8)
11 32)
48)
5250)
40)
16)15)
28)23)22) 39)
46) 16)45) 15)
21)0)
1417 26)
21) 44 1447
1721)2)
15 23 4018 388 15575451 58 18
25)
31)
57)46)
45)26)
23)
0)16) 46)
15) 45)28)
38)23)6) 36)
58)4447
24)23)
2)4)
26)14 441725)
40)21) 38)47
55)
57)
3423 2575440 5138 4231 3415 2310
4018 388 575451
19 5523 33) 11)47)
10 14)1 3425 382321
31)
3 155 11) 27 35
52575341 1
45)10 14)
8 219)
5943 49 193 155 11)
11 2323
313 31
312929
77
2727
7)37)
1145 3 31
5959
4747
77
7)15)51)
192723 23595543 3
25
49
5257
35
3823 5341 1 14) 46
27 4315
25
5 35
382321
419)
11)5955
49
52 5753
55)
2323
3145 3 3
312929 1
5959
2727
4747
11 2323
3145
312929
77
2727
4715)
7) 595947 53 54)
51)53
173 15 43
48) 12)
46)
10
15)
53
58)
58
3) 36)26)106
4516
48
1150 21
31) 15)
3131
58)
15
28)
53 55
22) 38)0)0)
4318
23)
2619 57
34
23)
263557
18
57
23)
26
5525
16 280 52
26)21)33)5)
47)24) 57)
25)23) 4)
28 3119 181230)
40 5712 40
5)
21622
5716 5)
5734 54)
5736 55)
4162
948
)
5931
59)
5935
50)
1675
1)
5933
50)
5939
51)
1678
5704
4820 18)
5254 41)5252 40)
5254 41)
57165)
5252 40)
1680 1)
5252 40)
21624 27)
1677
1682
5931
59)
4162
948
)
5077
38)
1679
1)5707
45)
5242 16)
5931
59)
5716 5)
4820 18)1675
1)
1677
5254 41)
5933
50)
5939
51)
5707
45)
531
1678
528
38)
5707
45)
21622 38)
21624 27)
545 7)
1682
5075
27)
5736 55)
533
1679
1)1680 1)
5935
50)
532
530
5704
535 6)
5716
11626
5252
529
5939
51)
4193
55)
2159
5)5)
5933
50)
4191
313
)
2150
21571)
40)
4855
17)
2152
5736
4162
948
)
5733
2161 1)
2163
5254 41)
55) 482069)
1056
4162
948
)
2165 1)
54 2)5935
50)
5704
2167
41610 4162
959)
1)
215541610 48)
4820 18)
2154
1)
2152
2154
1)57
0745
)
5931
59)
5254 41)
48)
5935
50)
2162
1)48589)
2156
5061
33)
5075
27)
5077
38)
5733
2158
1)
2158
1)
2160
48)
5931 4820 18)
4855
17)
326 1)
3776
3778
3780
3782
1026
1678
531
529
580545)
5564
46)
5566
48)
21562155
2159
5565 47)5567 49)
11626
2157 1)
5826
51)
5252 40)
5569 50)
5061
33)
5075
27)
5077
38)
2165
313
) 57041056
54 2)
4858 9)
2162
5571
2161 1)
48206 9)
3784
3786
16801)
328
1028
330 1)
3788
3790
1030
44 1)
533
51) 21632160
2165 1)
1682
3792
5828
51)
1676
2155
3776
3778
1026
1678
5564
556547) 55
66
531
528
530
1677
2156
116265)
2154
1)
46)
48)
2152
1)
3774
3780
580545)
21571)5567
49)
529
2159
21611) 21
62
2163
3782
3784
3788
3790
556950)58
26
5828
1030
16801) 16
81
2158
532
1)
5571 51)
51)
1679
1)
1)
2160
1682
51)
482069)
3786
533
1028
21651)
5716 5)
22707 45)
22913 64)
4191
313
)
4193
55)
5707
45)
5719
51)
5733
5736 55)
22253
2270922719 51)
22733
23401 13)
5709
5569
5571
5805
5826
5565 47) 5566
41610 48)
5564
46)
5931
59)
5254 41)
51)
5827 51)
4162
948
)
5252 40)
48)
5807
5935
50)
5704
45)
507738)
5567 49)
4855
17)
21546 38)
21550 27)
2167553)
50)
51)
4858 9)
4820 18) 5061
33)
5075
27)
2165
313
)
20113 9)
21672 63)
RUTEORD. NR.BLAD NR. 9 GJELDER FRA OG MED:
161.1SKØYEN - OSLO S - EIDSVOLL Søndag 11. desember 20111) 44, 56, 322, 326, 330, 334, 405, 1671, 1675, 1676, 1679, 1680, 1683, 1684, 1688, 2154, 2157,
2158, 2161, 2162, 2165, 2166, 2169, 2170, 2173, 2177 Søndager - fredager.2) 54, 4805, 4806, 5073, 5074, 5823, 21526, 21527, 21528, 21563, 21603, 21604, 21626 Lørdager.3) 306, 310, 314, 318, 505, 507, 1004, 1006, 1008, 1010, 1014, 1018, 1022, 1655, 1656, 1659,
1660, 1663, 1664, 1667, 1668, 1672, 2107, 2108, 2114, 2117, 2118, 2121, 2122, 2125, 2126, 2129, 2130, 2133, 2134, 2137, 2138, 2141, 21565 Mandager - lørdager unntatt helligdager.
4) 406, 2178, 41988 Mandager - lørdager.5) 502, 4011, 5716, 5737, 11626, 11655, 21655, 22737, 23411, 41935 Lørdager unntatt helligdager.6) 535 Mandager - torsdager og lørdager.7) 545 Fredager og søndager.8) 1038, 5572, 5708, 5730, 5732, 5936, 41906 Tirsdager - lørdager unntatt dag etter helligdag.9) 1040, 4851, 4852, 4858, 4861, 20113, 21508, 21556, 41633, 41634, 41970, 45964, 48206
Søndager.10) 1042, 5715, 11523, 11628, 22715 Helligdager.11) 1653 Skøyen - Lillestrøm Mandager - fredager unntatt helligdager. Lillestrøm - Dal Alle dager.12) 2174 Skøyen - Strømmen Søndager - fredager. Strømmen - Lillestrøm Mandager - lørdager.13) 4001, 21653, 23401, 41913 Mandager, tirsdager, onsdager og fredager unntatt helligdager.14) 4008, 21652 Onsdager - søndager unntatt dag etter helligdag.15) 4801 Loenga - Frogner Mandager. Frogner - Eidsvoll Tirsdager.16) 4802, 4824, 4835, 4862, 5241, 5242 Tirsdager.17) 4811, 4855, 4857, 4866, 5938, 21061, 41637, 41638, 41924 Mandager.18) 4813, 4820 Onsdager og fredager.19) 4817 Loenga - Frogner Tirsdager og onsdager. Frogner - Eidsvoll Onsdager og torsdager.20) 4822, 21537 Onsdager og torsdager.21) 4836, 41647, 41648 Onsdager.22) 4840 Fredager. Kjøres bare etter særskilt kunngjøring.23) 4843, 41632, 41645 Torsdager unntatt helligdager.24) 4844 Eidsvoll - Kløfta Torsdager unntatt helligdager. Kløfta - Loenga Fredager unntatt dag etter
helligdag.
25) 4865 Torsdager.26) 5003, 21533, 40964 Mandager, torsdager og fredager.27) 5005, 5075, 21535, 21548, 21550, 21624 Tirsdager og onsdager. Kjøres bare etter særskilt
kunngjøring.28) 5007, 21062 Tirsdager og onsdager.29) 5021, 5022, 5032 Tirsdager og torsdager unntatt helligdager.30) 5031 Tirsdager, torsdager og lørdager unntatt helligdager.31) 5057, 5058 Onsdager og torsdager unntatt helligdager.32) 5060 Onsdager, torsdager og fredager unntatt helligdager.33) 5061 Tirsdager, onsdager og torsdager unntatt dag før helligdag.34) 5064, 20104 Mandager unntatt helligdager.35) 5066 Tirsdager - fredager unntatt helligdager.36) 5071, 5072, 21534, 21538, 21620, 44660, 44661 Mandager - fredager.37) 5076, 21529 Onsdager og torsdager. Kjøres bare etter særskilt kunngjøring.38) 5077, 21544, 21546, 21622 Mandager, torsdager og søndager.39) 5078, 21531 Mandager, tirsdager og fredager.40) 5252 Tirsdager - fredager unntatt helligdager. Kjøres fra og med 29. mai 2012.41) 5254 Tirsdager - fredager unntatt helligdager.Kjøres til og med 25. mai 2012.42) 5256, 5816, 41630, 41631, 41676, 41677 Lørdager unntatt dag etter helligdag.43) 5261, 5262 Mandager og tirsdager unntatt helligdager.44) 5506 Tirsdager - fredager unntatt helligdager. Kjøres bare etter særskilt kunngjøring.45) 5509, 5707, 5803, 5805, 5809, 22707 Mandager - torsdager unntatt helligdager.46) 5564, 5735, 22735 Mandager - torsdager unntatt helligdager. Kjøres bare etter særskilt
kunngjøring.47) 5565 Mandager - torsdager unntatt helligdager og dag før helligdag. Kjøres bare etter særskilt
kunngjøring.48) 5566, 41610, 41629 Fredager unntatt helligdager. Kjøres bare etter særskilt kunngjøring.49) 5567 Helligdag før hverdag. Kjøres bare etter særskilt kunngjøring.50) 5569, 5933, 5935 Mandager - torsdager unntatt helligdager og dag før helligdag.
51) 5571, 5719, 5821, 5826, 5827, 5828, 5937, 5939, 21673, 22719 Helligdag før hverdag.52) 5706, 5806, 5808, 5814 Tirsdager - fredager unntatt dag etter helligdag.53) 5718, 5820, 10353, 21675, 45989 Hverdag etter helligdag.54) 5734 Onsdager, torsdager og fredager unntatt helligdager og dag etter helligdag. Kjøres bare
etter særskilt kunngjøring.55) 5736 Lørdager unntatt dag etter helligdag. Kjøres bare etter særskilt kunngjøring.56) 5738, 21567, 41910 Søndager unntatt dag etter helligdag.57) 5800, 10351, 45944, 45949, 45962, 45965 Tirsdager - fredager unntatt helligdager og dag etter
helligdag.58) 5802, 5811 Mandager - fredager unntatt helligdager. Kjøres bare etter særskilt kunngjøring.59) 5931, 48215 Fredager.60) 11654 Dal - Lillestrøm Alle dager. Lillestrøm - Skøyen Helligdager.61) 12001, 12002 Mandager og torsdager unntatt helligdager.62) 21552, 41960 Tirsdager, torsdager og lørdager unntatt dag etter helligdag.63) 21672, 41971 Fredager unntatt helligdager.64) 22913 Mandager, tirsdager, onsdager, fredager og lørdager unntatt helligdager.65) 22981, 41981 Mandager - torsdager, lørdager og søndager.66) 40965 Tirsdager, onsdager og lørdager.67) 41640, 41641 Fredager unntatt dag etter helligdag.68) 41642 Torsdager unntatt helligdager. Kjøres bare etter særskilt kunngjøring.69) 41643 Fredager unntatt dag etter helligdag. Kjøres bare etter særskilt kunngjøring.70) 41922 Torsdager, fredager og lørdager.71) 41953 Mandager, onsdager og fredager unntatt helligdager.72) 41973 Mandager - torsdager og lørdager unntatt helligdager.
Funkwerk IT TrainPlan 2.14.10.1 (Patch 10+) Side 7 of 8 Utskrift: 20.10.2011 14:39
21 22 23 24
21 22 23 24
67,86
64,51
62,24
59,54
57,20
53,44
49,62
46,10
44,60 *
42,22
40,30
36,38
32,28
29,80
26,94
25,18
22,76
20,95
19,83
19,05
18,92
17,93
16,42
16,17
15,50
14,15
13,09
12,10
12,09
10,50
9,30
8,72
6,87
5,85
3,89
2,28
0,27 *
1,40 *
2,29
4,38
10,50
7,33
8,72
7,33
7,33
5,85
7,33
5,26
3,89
1,97 *
1,08
Dønnum Bp
Km fraOslo S
EIDSVOLL
BØNVarud
DAL
SAND
HAUERSETER
Nordby
JESSHEIM
LANGELAND
ASPER
KLØFTA
LINDEBERG
FROGNER
Leirsund
LILLESTRØM N
General Motor s.sp.
LILLESTRØMH-sign 1214, Lillestrøm
Sagdalen
Sagdalen Bp.
STRØMMENFjellhamar
Fjellhamar Bp.
Hanaborg
LØRENSKOGHøybråten
Haugenstua Bp.
Haugenstua
GRORUDNyland
AKER
Alna
BROBEKK
BRYN
Sporv.303
OSLO S
NATIONALTHEATRET
Elisenberg Bp.A
SKØYEN
Km fraOslo S
GRORUD
ALNABRU
Km fraOslo S
AKER
ALNABRU
Km fraOslo S
ALNABRU
BROBEKK
Km fraOslo S
ALNABRU
Teisen s.sp
BRYNOslo S s.sp Kværner
LOENGA
3: 190 EVL
Kmmellomstasjon
Kryssspor-lengde
3,35
3/5: 7004: 7705: 310
2,27
DNM
5,04
2: 591 BØN
3,76
1: 536 DAL
2: 730 SAD
3,82
5,02
1: 5552: 664 HSR
2,35
1: 5473: 535 JEH
1,92
LAL
3,92
1: 711 ASE
4: 718 KLØ
4,10
2,48
1: 696 LBG
4,62
1: 321 FRO
4,23
15: 914 BRT
GMO
6: 3807: 3748: 3319: 270 LLS
1,12
0,91
SLD
0,99SLN
1,76
STN
2,02
FH1
1: 374 LØR
2,05
1,60
HG1
1,78
3: 560 GRO
2,87
AKE
1,96
BRB
3,62
BR
SP3
1,67
OSL
0,89
NTH
2,09
ELI
SKØ
Kmmellomstasjon
3,17
3: 560
Kryssspor-lengde
GRO
ALB
Kmmellomstasjon
1,39
Kryssspor-lengde
AKE
ALB
Kmmellomstasjon
Kryssspor-lengde
1,48
ALB
BRB
Kmmellomstasjon
3,44
Kryssspor-lengde
ALB
TEN
3,89
BR
KVÆ
LOE
22 23
22 23
22 23
22 23
21
21
21
21
GRORUD - ALNABRU
AKER - ALNABRU
ALNABRU - BROBEKK
LOENGA - ALNABRU
24
24
24
24
11
1121 21 21
17)57)34)
431 1
22)
26)
48)
52)
25)
29)4)
8)
37
40)4)
7
4)
7
29)
3437)
42)
45)
19)
22)11)
1619)
54)29) 36)12)
26121515)
3132 45
54)38)
38)
28)
17)
19)10) 42 52)
39)
52)
58)
59)35)
42)
45
242521
247)
484946
48 56)8)
2)32) 57)
21282528)4)
4)144) 52)
59)4)5)
4)17 21)2)
7)41
5431 1) 7)
11 12) 17)20)
36 1137)58)37) 5)5558)
1617
24 8
992212) 25)
32 34 24 8
941
4239 5242)
46)49)
31)
20)
434 4
26 5637)
49)45)7) 6) 9)
27)
28)12) 42) 59)
23)28 58
2 322
33)53)
42)4)35)
5)23)
26)
18)
22
48)
529 39 9
30)57)
38)0) 57) 2)19)
16)15)
23)0)22)
7)30)
46)45) 2)
1417
21)2) 24)5) 31)
4447
4)
15 2310
3634 575440 105138 8
43 433 55
27)
32)
36)24)
28)
33)
48)
52)
59)14)
2128)
33)
37
40)6)
918)
21)
42)
45)37
40)
47)
39
37
40)58)40)
45)
52)
54)
28)
29)
3132
28)
29)
313212
15
17)
19)
15
17)
19)11)
13)
15)
35)
36)
38)54)
56)
57)
50
52)
54)
54)
57)
59)
484946
48242521
2432)
242521
240)
44)52)
21
2825
28) 21283)
44)
484946
48
52)
36 37)
41 54
58)12)
17
12)
1731
37)
31
11) 20)17)
21) 5)
1012)
36 37)
41 54
58)37) 50
58)
3234 41
423922 5241)
47)15) 24)12)
25 32342
4 899 22
17)29) 41
4239 5245)
21)34 4 3426 56
26
36)50)13) 20)
28)21)
25)56
41)
12) 42) 12) 42)0)23) 29)27)
18)28 58 282 32
32)
54)16) 24)25)21)
5837)
22 5229) 22 33)29)17)
18) 48)
3919) 27) 42)
13)
15)
18)
9
31)
58)
48)
5239
16) 46)15) 45)
25) 11) 16)15)
29)3)
14 4417 47
23) 10)14
17
27)5) 44
46)45)
47
3423 40 5118 38 345 15 235754 1058 188 5440 5138
19 272311)
1 258
23219)
3 5 1511) 595543 333) 49
5257
35
38
5
5341 131)
3 317
77) 11 23
2329272715)
3145 3 3
3129 1
5959
4747
7737)
30) 38)0) 57)0
5 2)19)
5 10 25 32 5257
13
0) 22)23)
2619
7)
10
4)
114
19 275523 23
15
27 4315
17 25
49
52
35
382321
41
1959 3 15
18 2557
5
53 23121
51
54 57
5935
38
55
41
43
11 2323
3145
312929
2727
4747
11 2323
313 31
5959
312929
77
2727
47 5959
4747
4725
23) 29)
42)20
31)
12
17)
27)23)5)
30
35)
2629
2629
34)
32
42)
47
34
12 2016 4241 35
5734 54)
5709
1684 1)
1686
5256 42) 5719
51)
5733
1681
5074 2)
5256 42)
5734 54)
21624
5733
5734 54)5709
21622 38)
27)
5074 2)
1684 1)
5253
5256 42)
5719
51)
537
1681
534
2169
535 6)
545 7)
21622 38)
21624 27)
2162
1)
1)
21714001
13)
5719
51)
2162427) 57
3546
)
56 1)
48529)
2164
5253
4190
1
2166
1)
5709
2167
4466
136
)
2166
1)21622 38)
5828
51)
4852 9)
5804
582751)
2169 1)
56 1)
3794
545 7)
10322164 2167
5807
16841)
3796
3798
332
46
5809 45)
16904844 24)
1683
1)
1685
1688 1)
4844 24)5253
4164268)
5735
46)
4817
19)
4801
15)
4801
15)
541
539
1683
1)
1685
1686
1688 1)
41642 68)
538
5735
46)
536
2179
4866
5734 54)
41642 68)
4198
165
)
4817
19)
2175
5074 2)
5256 42)
21731) 2177 1)
17)
2168
4817
19)
5256 42)
2174
12)
4801
15)
5734 54)
405
1)
2170
1)
2172
2168
2170
1)
2172
4801
15)
4865
25)
5074 2) 41642 68)4817
19)
405
1)
4865
25)
4866 17)
1686
334 1)
3800
3802
3804
3806
539
1034
336
537
1036
2171
2175
2173 1)
16881)
3808
38102174
12)
2177 1)
1682
16841)
2167
21691)
3794
3796
5804
5807
535 6)
1683
1)
2164
5827 51)
2168
3792
3798
580945)535
6)
5457)
2166
1)
1032
534
4001
13)
5253
22735 46)
22901 4190
1
4466
136
)
5735
46)
5809
5828
51)
5804
45)
4852 9)
4858 9)
16881)
1685
1686
1687
2171
2174
12)2175
3800
3802
3804
3806
3808
538
539
1034
2170
1)
2172
21731)
21771)
536
537
1036
5734 54)
22981 65)
4198
165
)
5074 2)
5256 42)
41642 68)
4801
15)
4865
25)
4866 17)
5074 2)
4817
19)
5007 28)2152
72)
RUTEORD. NR.BLAD NR. 9 GJELDER FRA OG MED:
161.1SKØYEN - OSLO S - EIDSVOLL Søndag 11. desember 20111) 44, 56, 322, 326, 330, 334, 405, 1671, 1675, 1676, 1679, 1680, 1683, 1684, 1688, 2154, 2157,
2158, 2161, 2162, 2165, 2166, 2169, 2170, 2173, 2177 Søndager - fredager.2) 54, 4805, 4806, 5073, 5074, 5823, 21526, 21527, 21528, 21563, 21603, 21604, 21626 Lørdager.3) 306, 310, 314, 318, 505, 507, 1004, 1006, 1008, 1010, 1014, 1018, 1022, 1655, 1656, 1659,
1660, 1663, 1664, 1667, 1668, 1672, 2107, 2108, 2114, 2117, 2118, 2121, 2122, 2125, 2126, 2129, 2130, 2133, 2134, 2137, 2138, 2141, 21565 Mandager - lørdager unntatt helligdager.
4) 406, 2178, 41988 Mandager - lørdager.5) 502, 4011, 5716, 5737, 11626, 11655, 21655, 22737, 23411, 41935 Lørdager unntatt helligdager.6) 535 Mandager - torsdager og lørdager.7) 545 Fredager og søndager.8) 1038, 5572, 5708, 5730, 5732, 5936, 41906 Tirsdager - lørdager unntatt dag etter helligdag.9) 1040, 4851, 4852, 4858, 4861, 20113, 21508, 21556, 41633, 41634, 41970, 45964, 48206
Søndager.10) 1042, 5715, 11523, 11628, 22715 Helligdager.11) 1653 Skøyen - Lillestrøm Mandager - fredager unntatt helligdager. Lillestrøm - Dal Alle dager.12) 2174 Skøyen - Strømmen Søndager - fredager. Strømmen - Lillestrøm Mandager - lørdager.13) 4001, 21653, 23401, 41913 Mandager, tirsdager, onsdager og fredager unntatt helligdager.14) 4008, 21652 Onsdager - søndager unntatt dag etter helligdag.15) 4801 Loenga - Frogner Mandager. Frogner - Eidsvoll Tirsdager.16) 4802, 4824, 4835, 4862, 5241, 5242 Tirsdager.17) 4811, 4855, 4857, 4866, 5938, 21061, 41637, 41638, 41924 Mandager.18) 4813, 4820 Onsdager og fredager.19) 4817 Loenga - Frogner Tirsdager og onsdager. Frogner - Eidsvoll Onsdager og torsdager.20) 4822, 21537 Onsdager og torsdager.21) 4836, 41647, 41648 Onsdager.22) 4840 Fredager. Kjøres bare etter særskilt kunngjøring.23) 4843, 41632, 41645 Torsdager unntatt helligdager.24) 4844 Eidsvoll - Kløfta Torsdager unntatt helligdager. Kløfta - Loenga Fredager unntatt dag etter
helligdag.
25) 4865 Torsdager.26) 5003, 21533, 40964 Mandager, torsdager og fredager.27) 5005, 5075, 21535, 21548, 21550, 21624 Tirsdager og onsdager. Kjøres bare etter særskilt
kunngjøring.28) 5007, 21062 Tirsdager og onsdager.29) 5021, 5022, 5032 Tirsdager og torsdager unntatt helligdager.30) 5031 Tirsdager, torsdager og lørdager unntatt helligdager.31) 5057, 5058 Onsdager og torsdager unntatt helligdager.32) 5060 Onsdager, torsdager og fredager unntatt helligdager.33) 5061 Tirsdager, onsdager og torsdager unntatt dag før helligdag.34) 5064, 20104 Mandager unntatt helligdager.35) 5066 Tirsdager - fredager unntatt helligdager.36) 5071, 5072, 21534, 21538, 21620, 44660, 44661 Mandager - fredager.37) 5076, 21529 Onsdager og torsdager. Kjøres bare etter særskilt kunngjøring.38) 5077, 21544, 21546, 21622 Mandager, torsdager og søndager.39) 5078, 21531 Mandager, tirsdager og fredager.40) 5252 Tirsdager - fredager unntatt helligdager. Kjøres fra og med 29. mai 2012.41) 5254 Tirsdager - fredager unntatt helligdager.Kjøres til og med 25. mai 2012.42) 5256, 5816, 41630, 41631, 41676, 41677 Lørdager unntatt dag etter helligdag.43) 5261, 5262 Mandager og tirsdager unntatt helligdager.44) 5506 Tirsdager - fredager unntatt helligdager. Kjøres bare etter særskilt kunngjøring.45) 5509, 5707, 5803, 5805, 5809, 22707 Mandager - torsdager unntatt helligdager.46) 5564, 5735, 22735 Mandager - torsdager unntatt helligdager. Kjøres bare etter særskilt
kunngjøring.47) 5565 Mandager - torsdager unntatt helligdager og dag før helligdag. Kjøres bare etter særskilt
kunngjøring.48) 5566, 41610, 41629 Fredager unntatt helligdager. Kjøres bare etter særskilt kunngjøring.49) 5567 Helligdag før hverdag. Kjøres bare etter særskilt kunngjøring.50) 5569, 5933, 5935 Mandager - torsdager unntatt helligdager og dag før helligdag.
51) 5571, 5719, 5821, 5826, 5827, 5828, 5937, 5939, 21673, 22719 Helligdag før hverdag.52) 5706, 5806, 5808, 5814 Tirsdager - fredager unntatt dag etter helligdag.53) 5718, 5820, 10353, 21675, 45989 Hverdag etter helligdag.54) 5734 Onsdager, torsdager og fredager unntatt helligdager og dag etter helligdag. Kjøres bare
etter særskilt kunngjøring.55) 5736 Lørdager unntatt dag etter helligdag. Kjøres bare etter særskilt kunngjøring.56) 5738, 21567, 41910 Søndager unntatt dag etter helligdag.57) 5800, 10351, 45944, 45949, 45962, 45965 Tirsdager - fredager unntatt helligdager og dag etter
helligdag.58) 5802, 5811 Mandager - fredager unntatt helligdager. Kjøres bare etter særskilt kunngjøring.59) 5931, 48215 Fredager.60) 11654 Dal - Lillestrøm Alle dager. Lillestrøm - Skøyen Helligdager.61) 12001, 12002 Mandager og torsdager unntatt helligdager.62) 21552, 41960 Tirsdager, torsdager og lørdager unntatt dag etter helligdag.63) 21672, 41971 Fredager unntatt helligdager.64) 22913 Mandager, tirsdager, onsdager, fredager og lørdager unntatt helligdager.65) 22981, 41981 Mandager - torsdager, lørdager og søndager.66) 40965 Tirsdager, onsdager og lørdager.67) 41640, 41641 Fredager unntatt dag etter helligdag.68) 41642 Torsdager unntatt helligdager. Kjøres bare etter særskilt kunngjøring.69) 41643 Fredager unntatt dag etter helligdag. Kjøres bare etter særskilt kunngjøring.70) 41922 Torsdager, fredager og lørdager.71) 41953 Mandager, onsdager og fredager unntatt helligdager.72) 41973 Mandager - torsdager og lørdager unntatt helligdager.
Funkwerk IT TrainPlan 2.14.10.1 (Patch 10+) Side 8 of 8 Utskrift: 20.10.2011 14:39
20 21 22 23 24
20 21 22 23 24
343,04
337,33
330,82
321,83
315,83
307,73
302,99
297,24
291,50
286,35
280,42
276,57
271,33
266,60
259,26
252,45
246,60
242,55
237,74237,14235,35
232,19
224,15
219,32
214,35
208,08
203,21
200,09198,26196,57
191,68190,59
187,75
184,18
180,20
174,71
168,47
162,91
155,95
152,48
148,23
144,39
139,90
136,25
133,19129,79129,41
126,26
123,85123,24
119,25
114,42
110,21
107,47
101,77
96,99
93,11
89,81
84,05
79,71
75,33
71,44 *
67,86
Km fraOslo S
DOMBÅS
Skeievoll Bp
DOVRE
BRENNHAUG
Rosten Bp
SEL
Myra Bp
OTTA
Sandbu Bp
SJOA
Kjørum Bp
KVAM
Brekka Bp
VINSTRA
FRON
HUNDORP
Frya Bp
RINGEBU
Randklev BpRingebu Pukkverk s.spKvitfjell
FÅVANG
LOSNA
Potterud Bp
TRETTEN
Nordli Bp
ØYERHafjellHunderfossenHunder Bp
FÅBERGFåberg Omformerstasjons
HOVE
LILLEHAMMER
Dallerud Bp
BERGSENG
Martoddden s.sp
BRØTTUM
BERGSVIKA
MOELV
Ringsaker Bp
RUDSHØGDAVeldre Bp
BRUMUNDDAL
Langodden Bp
JESSNESFuruberget Bp
HAMARIdeal Flatbrødfabr. s.spAkersvika Bp
OTTESTAD
STANGE
SØRLISTEINSRUD
TANGEN
ESPA
Kleverud Bp
STRANDLYKKJA
MORSKOGEN
MOLYKKJA
MINNESUND
Vettalstøen Bp
EIDSVOLL
1: 300 DOM
Kmmellomstasjon
Kryssspor-lengde
5,712: 5003: 4784: 41610: 956,51
SKE
8,99
2: 568 DOV
6,00
2: 565 BRH
RO
8,10
4,74
2: 740 SEL
5,75
MRA
5,74
2: 3903: 3604: 667 OTA
5,15
SDB
5,93
2: 620 SJO
3,85
KJØ
5,24
2: 519 KVA
4,73
BKK
7,34
2: 604 VIN
6,81
1: 640 FRN
1: 690 HUN
5,85
4,05FRY
4,81
2: 550 RBU
5,55
RANRPS
8,04
2: 880 FÅV
2: 579 LOS
4,83
4,97
POT
6,27
2: 860 TRE
4,87
NOR
6,64
2: 572 ØYE
4,89
HER
3,93
2: 652 FÅBFBS
3,57
1: 665 HVE
3,98
3: 3102: 652 LHM
5,49
DRU
6,24
2: 673 BGG
2: 740 BUM
4,21
3,65
5,56
6,96
2: 810 BVK
3,47
2: 651 MLV
4,25RKR
3,842: 700 RUD
4,49
VEL
2: 690 BRD
3,06LDN
3,402: 689 JES
3,53
FUBMRS
3,02
HMR
IFS
3,99AVI
4,83
1: 703 OTT
2: 700 STG
2,743: 606
5,70
2: 694
4,78
1: 393
SRI
STE
TAN
3,88
1: 661
3,30
5,76
2: 486
2: 680
EPA
KLR
SLY
MOR
4,34
4,38
2: 377 MOL
3,89
2: 670 MSU
3,52VET
3: 1903/5: 7004: 7705: 310 EVL
4 7 15
47)
53)
47
48)
54)
6
19)
25)
13)
20)
28)
35)
15)
22)
30)
37)36)
43)
51)
58)
4)
27)
52
44)
34)
41)
46)
535)
5)
10)
15)
22)
29)
30)27 47) 45)38
12)
5)
13)
21)
15
15)
24)
32)
39)
51)
55)
3639)
49)
17)
2 5
12)
17
25)
21)
25)
30)
30)48) 39)30)
53)
19
44)44)
5217
25)
22)
32 36)
4547
3639
44)34)
3940
10) 4222)
28
3334)
30)
34)
39
52)
45)
52)16)
21)
27
15)
20
0)
7958 20)
29)
12)
14)
1821) 26)
29)19)
2529)
35)
40)11)
53
58)5558)
4) 1651
30)
35)
26)
31)
55) 13)33)
464940
47)2
546
47)
5033)
36)
55)
58)
0)
54 13)
5)
8)
12
56
53)16
19)
2123)20)
42)
45)
49)
35)
38)
42)
48
11)
23)
2812)
1723)
16
3
8)
2)
8)
1)
7)
31)2714)
19
24)
27)
17)
21)27)
32)16)
3)
8) 16
21)14)13)
40
45)40 45)
51)
36)
42)
2)
6)54)
592)
36)3336)
41)41)
48)47
50) 9)
13)
55)
0)613)58
30)
37)
42)
46
51)21)
30)
3537)
21)
27
36)
40)
19)
2426)
33)
21)
6)45)
48)
52)
57
4)
7)
12)36)
58)
3)
11
39)
4652)
57)0) 16)
19)
25)
16
2225)
29)
32)42)
45)
49)
5434)
4149)
54)
16) 29
437) 30)15 57 15 17)58)
2951)
57
88
10
21)
28)59)32)
38)
49533
10
21)
32)
58
19)
18
25)
3335
42)4142)
51)
16)
1759)
6)
14)18
40)
48)
42)
21) 4649)
57)
27)25)
32)
27)
3034)
44)
59)
3)
9
6)
11)
16)
9)
14)
40)
45)
50)
26)
33)
51)
59)
55)
2)
37)
4448)
55)
29)
36)
43)
48)
53)54)
20)21) 11)
19)
18) 12
4)
17)
20)
29)
37)
45)
21)
24)
33)
41)
49)
4)
12)
20)
55)
58)
7)
15)
59
15)
4441)
44)
53)
45)
54)
30)
33)
42)
50)
58)23)
42)1) 14)36) 53)
6)
14)1417
22 24
35 47)
55
41)
4951
47)58)
7)
27)
33
58)
4)
17
57)
27)
32) 38)
10)
16)17)
59)
5)
10)
54)
58)
3)
1038)
44)
49)
35)25)
40)
48 50)
58)30)
38)
31)
39)27)
20)
26
31)21)22)
26)
27)
16)
21
56)
37)
10)
15)
26)
31)
9)
14
449)
59)
4)
48)
53)
32)59) 23)
6102
73)
3018)
56
13)
0
917
20)
17)
35)25)
28)
48)
51
54)
13
38
38)
42)
4951)
3941)
34)47)
52)
58)
29)
24)
27)
31)
3840)2320
23
34)
37)
41)
4850)
39)
45)
48)
51)
31)
37)
22)
2629
3437)
15)
22)
29)
33)
1)
7)
11)
1722)
41
46)
42)
4346)
52)
56)
36)
6)
12)
16)
18)
57)
16
21)
24)
27)
33)57)
3)
7)
11)57)
2)
8)
46)
49)
53)
58
13)
16)
4053)
58)
1)
59)
6)
10)
14)
58)
21)
21)
24)
28)
32)53)
57)
57 15 58 27)
405
471)
5737
27)
5938 40)
5937
39)
5737
27)
5937
39)
5938 40)
5937
39)
5270 21)
5270 21)
46
334 1) 5933
36)
5939
39)
329
1)
46
331
329
1)
332
41642 45)
5707
23)
593135)
331
5734 31)
5933
36)
5939
39)
334 1)
5256 18)
5935
37)
46
332
44 1)
41642 45)5734 31)
5707
23)
5931
35)
333
1)5706 22)
5937
39)
329
1)
5936 38)
5936 38)
5706 22)
5933
36)
5939
39)
41640 44)
5931
35) 57
0723
)
5933
36) 59
3939
)
5706 22)
329
1)
5935
37)
5939
39)
5707
23)
5931
35)
5707
23)
4162
942
) 5719
29)
5733
30)
5933
36)
5938 40)
329
1)
5709
25)
5931
35)
5935
37)
5938 40)
5931
35)
4824 13)
4824 13)
5709
25)
5270 21)
4162
942
)
333
1)
5707
23)
5935
37)
5938 40)
335
5719
29)
5733
30)
526720)
5270 21)
5267
20)
5270 21)
5253
16)
5938 40)
5735
32)
5719
29)
4162
942
)
336
336
4)
5253
16)
5733
30)
41642 45)
5938 40)
4844 14)
5253
16)
5733
30)
335
5735
32)
570925)
RUTEORD. NR.BLAD NR. 10 GJELDER FRA OG MED:
161.1EIDSVOLL - DOMBÅS Søndag 11. desember 20111) 44, 47, 322, 325, 326, 329, 330, 333, 334 Søndager - fredager.2) 306, 309, 310, 313, 314, 317, 318 Mandager - lørdager unntatt helligdager.3) 308 Dombås - Lillehammer Mandager - lørdager unntatt helligdager. Lillehammer - Eidsvoll Alle
dager.4) 405 Eidsvoll - Minnesund Søndager - fredager. Minnesund - Dombås Mandager - lørdager.5) 406 Mandager - lørdager.6) 2343 Mandager - fredager unntatt helligdager. Kjøres til og med 25. mai 2012.7) 2353 Mandager - fredager unntatt helligdager. Kjøres fra og med 29. mai 2012.8) 4801, 4802, 5241, 5242, 6210, 6212 Tirsdager.9) 4805, 4806 Lørdager.10) 4811 Mandager.11) 4813, 4820 Onsdager og fredager.12) 4817, 4822 Onsdager og torsdager.13) 4824 Hove - Brøttum Mandager. Brøttum - Eidsvoll Tirsdager.14) 4843, 4844, 41645 Torsdager unntatt helligdager.15) 5252 Tirsdager - fredager unntatt helligdager. Kjøres fra og med 29. mai 2012.16) 5253 Eidsvoll - Rudshøgda Mandager - fredager unntatt helligdager. Rudshøgda - Dombås
Tirsdager - lørdager unntatt dag etter helligdag.17) 5254 Tirsdager - fredager unntatt helligdager.Kjøres til og med 25. mai 2012.
18) 5256, 41677 Lørdager unntatt dag etter helligdag.19) 5261, 5262, 20347, 20348 Mandager og tirsdager unntatt helligdager.20) 5267, 5268 Tirsdager unntatt helligdager.21) 5269, 5270 Tirsdager unntatt helligdager. Kjøres bare etter særskilt kunngjøring.22) 5706 Dombås - Ringebu Mandager - torsdager unntatt helligdager. Ringebu - Eidsvoll Tirsdager -
fredager unntatt dag etter helligdag.23) 5707 Eidsvoll - Dovre Mandager - torsdager unntatt helligdager. Dovre - Dombås Tirsdager -
fredager unntatt dag etter helligdag.24) 5708, 5730, 5732 Tirsdager - lørdager unntatt dag etter helligdag.25) 5709 Eidsvoll - Tretten Mandager - fredager unntatt helligdager. Tretten - Dombås Tirsdager -
lørdager unntatt dag etter helligdag.26) 5715 Helligdager.27) 5716, 5737 Lørdager unntatt helligdager.28) 5718, 10353 Hverdag etter helligdag.29) 5719 Eidsvoll - Tretten Helligdag før hverdag. Tretten - Dombås Hverdag etter helligdag.30) 5733 Eidsvoll - Fåvang Mandager - fredager unntatt helligdager. Fåvang - Dombås Tirsdager -
lørdager unntatt dag etter helligdag.31) 5734 Onsdager, torsdager og fredager unntatt helligdager og dag etter helligdag. Kjøres bare
etter særskilt kunngjøring.
32) 5735 Eidsvoll - Brumunddal Mandager - torsdager unntatt helligdager. Brumunddal - Dombås Tirsdager - fredager unntatt dag etter helligdag. Kjøres bare etter særskilt kunngjøring.
33) 5736, 41630 Lørdager unntatt dag etter helligdag. Kjøres bare etter særskilt kunngjøring.34) 5738 Søndager unntatt dag etter helligdag.35) 5931 Eidsvoll - Brennhaug Fredager. Brennhaug - Dombås Lørdager.36) 5933 Mandager - torsdager unntatt helligdager og dag før helligdag.37) 5935 Eidsvoll - Kvam Mandager - torsdager unntatt helligdager og dag før helligdag. Kvam -
Dombås Tirsdager - fredager unntatt helligdager og dag etter helligdag.38) 5936 Dombås - Sjoa Mandager - fredager unntatt helligdager. Sjoa - Eidsvoll Tirsdager - lørdager
unntatt dag etter helligdag.39) 5937, 5939 Helligdag før hverdag.40) 5938 Dombås - Espa Søndager. Espa - Eidsvoll Mandager.41) 10351 Tirsdager - fredager unntatt helligdager og dag etter helligdag.42) 41629 Fredager unntatt helligdager. Kjøres bare etter særskilt kunngjøring.43) 41633, 41634 Søndager.44) 41640 Otta - Fron Torsdager unntatt helligdager. Fron - Eidsvoll Fredager unntatt dag etter
helligdag.45) 41642 Torsdager unntatt helligdager. Kjøres bare etter særskilt kunngjøring.46) 41647, 41648 Onsdager.
Funkwerk IT TrainPlan 2.14.10.1 (Patch 10+) Side 6 of 6 Utskrift: 20.10.2011 14:03
00 01 02 03 04
00 01 02 03 04
343,04
337,33
330,82
321,83
315,83
307,73
302,99
297,24
291,50
286,35
280,42
276,57
271,33
266,60
259,26
252,45
246,60
242,55
237,74237,14235,35
232,19
224,15
219,32
214,35
208,08
203,21
200,09198,26196,57
191,68190,59
187,75
184,18
180,20
174,71
168,47
162,91
155,95
152,48
148,23
144,39
139,90
136,25
133,19129,79129,41
126,26
123,85123,24
119,25
114,42
110,21
107,47
101,77
96,99
93,11
89,81
84,05
79,71
75,33
71,44 *
67,86
Km fraOslo S
DOMBÅS
Skeievoll Bp
DOVRE
BRENNHAUG
Rosten Bp
SEL
Myra Bp
OTTA
Sandbu Bp
SJOA
Kjørum Bp
KVAM
Brekka Bp
VINSTRA
FRON
HUNDORP
Frya Bp
RINGEBU
Randklev BpRingebu Pukkverk s.spKvitfjell
FÅVANG
LOSNA
Potterud Bp
TRETTEN
Nordli Bp
ØYERHafjellHunderfossenHunder Bp
FÅBERGFåberg Omformerstasjons
HOVE
LILLEHAMMER
Dallerud Bp
BERGSENG
Martoddden s.sp
BRØTTUM
BERGSVIKA
MOELV
Ringsaker Bp
RUDSHØGDAVeldre Bp
BRUMUNDDAL
Langodden Bp
JESSNESFuruberget Bp
HAMARIdeal Flatbrødfabr. s.spAkersvika Bp
OTTESTAD
STANGE
SØRLISTEINSRUD
TANGEN
ESPA
Kleverud Bp
STRANDLYKKJA
MORSKOGEN
MOLYKKJA
MINNESUND
Vettalstøen Bp
EIDSVOLL
1: 300 DOM
Kmmellomstasjon
Kryssspor-lengde
5,712: 5003: 4784: 41610: 956,51
SKE
8,99
2: 568 DOV
6,00
2: 565 BRH
RO
8,10
4,74
2: 740 SEL
5,75
MRA
5,74
2: 3903: 3604: 667 OTA
5,15
SDB
5,93
2: 620 SJO
3,85
KJØ
5,24
2: 519 KVA
4,73
BKK
7,34
2: 604 VIN
6,81
1: 640 FRN
1: 690 HUN
5,85
4,05FRY
4,81
2: 550 RBU
5,55
RANRPS
8,04
2: 880 FÅV
2: 579 LOS
4,83
4,97
POT
6,27
2: 860 TRE
4,87
NOR
6,64
2: 572 ØYE
4,89
HER
3,93
2: 652 FÅBFBS
3,57
1: 665 HVE
3,98
3: 3102: 652 LHM
5,49
DRU
6,24
2: 673 BGG
2: 740 BUM
4,21
3,65
5,56
6,96
2: 810 BVK
3,47
2: 651 MLV
4,25RKR
3,842: 700 RUD
4,49
VEL
2: 690 BRD
3,06LDN
3,402: 689 JES
3,53
FUBMRS
3,02
HMR
IFS
3,99AVI
4,83
1: 703 OTT
2: 700 STG
2,743: 606
5,70
2: 694
4,78
1: 393
SRI
STE
TAN
3,88
1: 661
3,30
5,76
2: 486
2: 680
EPA
KLR
SLY
MOR
4,34
4,38
2: 377 MOL
3,89
2: 670 MSU
3,52VET
3: 1903/5: 7004: 7705: 310 EVL
59)
5)
1719 56
159
0)
6)
35)
42)
5356
442933 4
87 10
19
14
26)
11)
25)
25)
32)
11)
18)
25
18)
28)28)50)
56) 35)
36)
42)
5250844
51
2)
9)69)
18)
3033
6
19 3)50)
57)
5)
38)
45)
53)
0)
1)
9)
17)
24)
57)
9)
38)
37)
45)19)
2837)38)
13)
6)
14)
44)
11)53
56)56)
3)
53)
0) 21)
28)
19)
24)
1)
8
19)
37)
42)
4952)
31)
36)
41)29)52)
57)
2)
412)
21)1721)16)
24)
4)
12) 30)31)
39)
24)
29)
35)10)
15)
20)
8)
13)
18)54)
59)
610)
10)
17)
40)
47)1017)
26)
28
17)
24 28)
531)
8)
1618
25)38)
4446
55)
1)
2225)
34)
42)
49)
3844)
53)
8
35)
39)
4445
9
15)
19)
2627
35)36)
56)
27) 46) 41)46) 57)6)
0) 9) 21
1)
9)
2)
10)
58)
53 56)
4)27)
35)
45)
56)
33)
47)
37)
47)44
57)
41)
4657)
55)
43)
46)
55)
3)
12)
7)
15)
2532)
32)
40)
50
6)
8)
16)
21
58)
3)
912)
20)
0)
7)
12)
16)
21)
30)3)
10)
16)
21)
25)
30)
38)
37)22) 15)18
42)27)
3539
11)
1350
2225)
15
25)
26)
22)
22)
28
33)
13
18) 3033)
40)
0)
6)
11)
38 10)
40)
48)
42)
50)
58)
7)
56)
34)13)
21)
26)
30)
35)
30)
35)
40)
35)
40)
45)
50)
47)
50
53)
04
30)
32)
35)
4145
53)
5934)
4153)
2
58)
3)
10)
15
39)
46
57)
52)52)
9)14
17)
22)
2932
12)
15)
227
14)
17)
20)
15
22)
26)
29)
47)
15)
19)22)
26
15)
20)
24)
57)
1)
715)
31)
36)
40
45)28)
53)
59)
3)
16
21)
24)
58)
3)
7)
11) 21 27)
43)
46)
49)27)
32)
37)
7)22)
27)
31)
37)
41)
44)
49)
6)
11)
14)
17)
21)
29
24)
28)
56)
0)
3)
7)
13)
17)
23)
52)57) 9)
44)
47)
50)
56
47)52)
2)
8)
11)
14)
4)
15)
23)
27)
30)
59
31)
35)
39)
45)
33)
38)
42)
33)
38)
16)
20)
24)
29)
32)
36)
40)
46)
49)
52)
57)
42)
45)
50)
33)
36)
41)
50)
53)
58)
38) 50)15 3)55) 56) 46)42)
5733
5707
23)
5931
35)
405
4)
5719
29)
5733
30)
5730 24)
5709
25)
5708 24)
5709
25)
5253
16)
5718 28)
5936 38)
5935
37)
5935
37)
5735
32)
5709
25)
405
4)
406 5)
5730 24)
5735
32)
406 5)
5706 22)
41640 44)
41640 44)
30)
5719
29)
5253
16)
5718 28)
5719
29)57
3330
)
5936 38)
5708 24)
405
4)
41640
573532)
41640 44)
405
4)5253
16)
5706 22)
5709
25)
5735
32)
5936 38)
5718 28)
406 5)
5253
16)
339
405
4)
5706 22)
5735
32)
4801
8)
44)
4801
8)
5718 28)
41640 44)
5708 24)
5708 24)
5706
4824 13)
4824 13)
4817
12) 4801
8)
5936 38)
5936 38)
5938 40)
5938 40)
4167
718
)
339
405
4)
4824 13)
41640 44)4822 12)
5241
8)
22)
RUTEORD. NR.BLAD NR. 10 GJELDER FRA OG MED:
161.1EIDSVOLL - DOMBÅS Søndag 11. desember 20111) 44, 47, 322, 325, 326, 329, 330, 333, 334 Søndager - fredager.2) 306, 309, 310, 313, 314, 317, 318 Mandager - lørdager unntatt helligdager.3) 308 Dombås - Lillehammer Mandager - lørdager unntatt helligdager. Lillehammer - Eidsvoll Alle
dager.4) 405 Eidsvoll - Minnesund Søndager - fredager. Minnesund - Dombås Mandager - lørdager.5) 406 Mandager - lørdager.6) 2343 Mandager - fredager unntatt helligdager. Kjøres til og med 25. mai 2012.7) 2353 Mandager - fredager unntatt helligdager. Kjøres fra og med 29. mai 2012.8) 4801, 4802, 5241, 5242, 6210, 6212 Tirsdager.9) 4805, 4806 Lørdager.10) 4811 Mandager.11) 4813, 4820 Onsdager og fredager.12) 4817, 4822 Onsdager og torsdager.13) 4824 Hove - Brøttum Mandager. Brøttum - Eidsvoll Tirsdager.14) 4843, 4844, 41645 Torsdager unntatt helligdager.15) 5252 Tirsdager - fredager unntatt helligdager. Kjøres fra og med 29. mai 2012.16) 5253 Eidsvoll - Rudshøgda Mandager - fredager unntatt helligdager. Rudshøgda - Dombås
Tirsdager - lørdager unntatt dag etter helligdag.17) 5254 Tirsdager - fredager unntatt helligdager.Kjøres til og med 25. mai 2012.
18) 5256, 41677 Lørdager unntatt dag etter helligdag.19) 5261, 5262, 20347, 20348 Mandager og tirsdager unntatt helligdager.20) 5267, 5268 Tirsdager unntatt helligdager.21) 5269, 5270 Tirsdager unntatt helligdager. Kjøres bare etter særskilt kunngjøring.22) 5706 Dombås - Ringebu Mandager - torsdager unntatt helligdager. Ringebu - Eidsvoll Tirsdager -
fredager unntatt dag etter helligdag.23) 5707 Eidsvoll - Dovre Mandager - torsdager unntatt helligdager. Dovre - Dombås Tirsdager -
fredager unntatt dag etter helligdag.24) 5708, 5730, 5732 Tirsdager - lørdager unntatt dag etter helligdag.25) 5709 Eidsvoll - Tretten Mandager - fredager unntatt helligdager. Tretten - Dombås Tirsdager -
lørdager unntatt dag etter helligdag.26) 5715 Helligdager.27) 5716, 5737 Lørdager unntatt helligdager.28) 5718, 10353 Hverdag etter helligdag.29) 5719 Eidsvoll - Tretten Helligdag før hverdag. Tretten - Dombås Hverdag etter helligdag.30) 5733 Eidsvoll - Fåvang Mandager - fredager unntatt helligdager. Fåvang - Dombås Tirsdager -
lørdager unntatt dag etter helligdag.31) 5734 Onsdager, torsdager og fredager unntatt helligdager og dag etter helligdag. Kjøres bare
etter særskilt kunngjøring.
32) 5735 Eidsvoll - Brumunddal Mandager - torsdager unntatt helligdager. Brumunddal - Dombås Tirsdager - fredager unntatt dag etter helligdag. Kjøres bare etter særskilt kunngjøring.
33) 5736, 41630 Lørdager unntatt dag etter helligdag. Kjøres bare etter særskilt kunngjøring.34) 5738 Søndager unntatt dag etter helligdag.35) 5931 Eidsvoll - Brennhaug Fredager. Brennhaug - Dombås Lørdager.36) 5933 Mandager - torsdager unntatt helligdager og dag før helligdag.37) 5935 Eidsvoll - Kvam Mandager - torsdager unntatt helligdager og dag før helligdag. Kvam -
Dombås Tirsdager - fredager unntatt helligdager og dag etter helligdag.38) 5936 Dombås - Sjoa Mandager - fredager unntatt helligdager. Sjoa - Eidsvoll Tirsdager - lørdager
unntatt dag etter helligdag.39) 5937, 5939 Helligdag før hverdag.40) 5938 Dombås - Espa Søndager. Espa - Eidsvoll Mandager.41) 10351 Tirsdager - fredager unntatt helligdager og dag etter helligdag.42) 41629 Fredager unntatt helligdager. Kjøres bare etter særskilt kunngjøring.43) 41633, 41634 Søndager.44) 41640 Otta - Fron Torsdager unntatt helligdager. Fron - Eidsvoll Fredager unntatt dag etter
helligdag.45) 41642 Torsdager unntatt helligdager. Kjøres bare etter særskilt kunngjøring.46) 41647, 41648 Onsdager.
Funkwerk IT TrainPlan 2.14.10.1 (Patch 10+) Side 1 of 6 Utskrift: 20.10.2011 14:03
00 01 02 03 04 05 06
00 01 02 03 04 05 06
552,87
551,67
550,76
549,95
548,93
548,82
546,44
544,11
541,41
537,11
532,09
531,42
528,77
525,32
524,77
520,49
517,69
514,78
511,20
507,89
504,44
501,20
493,60
486,60
477,31
466,35
455,17
449,92
441,35
429,28
418,59
407,12
393,23
381,74
371,14
361,65
352,40
343,04
Km. fraOslo S
TRONDHEIM S
Skansen
TRONDHEIM M
Marienborg
Søndre Tilsving S
Stavne Bp
SELSBAKK
Kolstad Bp
HEIMDAL
NYPAN
MELHUS
Melhus Skysstasjon
SØBERG
Kvål
Kvål Bp
LER
Helgemo Bp
LUNDAMO
Horg Bp
HOVIN
Krogstad Bp
STØREN
Skjærli Bp
SOKNEDAL
GARLI
BERKÅK
ULSBERG
Markøya Pukkverk s.sp
FAGERHAUG
OPPDAL
Driva Bp
DRIVSTUA
KONGSVOLL
HJERKINN
Vålåsjø Bp
FOKSTUA
Gardsenden Bp
DOMBÅS
1: 470 MEL
TND
Km.mellomstasjon
Kryssings-sporlengde
SAV
2,11
1,94
7: 6788: 5579: 524 MBG
SS
2,38
2,33
1: 398 SLB
2,70
KOS
4,30
1: 6892: 6233: 270 HMD
5,02
1: 308 NYP
KST
1: 459 LER
3,32
4,00
1: 5822: 561 SØB
4,28
KÅL
2,80
2,91
HGM
3,58
1: 550 LMO
3,31
HRG
3,45
1: 524 HOI
3,24
7,60
1: 8222: 7003: 6314: 610 STØ
7,00
SÆR
9,29
2: 504 SDL
10,96
1: 780 GAL
11,18
2: 569 BÅK
13,89
13,82
2: 298 UBG
MPS
12,07
1: 702 FGH
10,69
2: 540 OPD
11,47
DRI
1: 710 DRS
1: 527 FOK
11,49
2: 322 KVL
10,60
1: 5492: 551 HJN
9,49
VÅL
9,25
9,36
GAE1: 3002: 5003: 4784: 41610: 95 DOM
15)
20
5)
10
25)
30
42)
47
0)
5 16
51)
56
12)4)
9 0
5)
4535
49)40)
57)
1)
5)
1015
21)
56)
59)
3)
7)
11)
27)
31)
35)
4055
1)
14)
18)
22)
2732
38)
50
56)
0)
6)40)
46)
50)
40)
46)
50)
10)
16)
20)
21)
27)
57)
3)
7)
32)
35)
39)
43)
47)
53)
56)
0)
4)
8)
38)
42)
46)
5055
0)9)
13)
16)
20)
54
59
23)
15)
21)
26)
37)
43)
47)31)
47)
53)
58)29)
32)
37)
55
7)
14)
11)
24)
32)114)
23)
35)
33) 16)
23)
35)
13)
20)
46)
53)
5)
57)
4)
16)
40)
52)
25
34)
40)
49)29)16)
25)
59)
8)
57)
6)38)
40)
49)
21)
51)
58)
10)32)
14) 48)
55)
3441)41)
5255)
34)
43)
57)
6)
30)
40
44)
5258
1215)
3)
1525)
0)
9)
25)
31)
42)
589)
19)
58)
6)
41)
49)
49)
0)
15)
23)
13)
24)
39)
47)
55)
6)
22)
30)
8)
1823)23)
25
3455)
31
1719
379) 40)
40)
56159 29
3353
56
16) 4751)
487
10
27)
41)
44
36)
465)
2127)
4451
51)
5)46)
522
17)
31
39
51)
612
20)
3033
50)
4)
12)
23)
39)
47)
5933
104235933
22)
5941
22)
5935
23)
5937
24)
5939
25)
5719
13)
5733
11)
5707
9)
5709
11)
5931
21)
410
1040659
3724
)
573014)
5931
21)
10406
5735
16)
5735
16)
5933
22)
5939
25)
406 3)
5707
9)
573014)
5935
23)
5719
13)
5733
11)
5935
23)
5933
22)
573014)
5709
11)
405
2)
5935
23)
5718 12) 5939
25)
405
2)
5719
13)
5730 14)
5733
11)
5707
9)
5931
21)
406 3)
5709
11)
5735
16)
5708 10)
RUTEORD. NR.BLAD NR. 11 GJELDER FRA OG MED:
161.1TRONDHEIM S - DOMBÅS Søndag 11. desember 20111) 44, 47, 446, 450, 454, 10446, 10450, 10454 Søndager - fredager.2) 405 Mandager - lørdager.3) 406 Trondheim S - Soknedal søndager - fredager, Soknedal - Dombås mandager - lørdager.4) 413, 5716, 5737, 25701 Lørdager unntatt helligdager.5) 414, 5715 Helligdager.6) 417, 10382 Lørdager og helligdager.7) 418 Helligdag før hverdag.8) 5706 Mandager - torsdager unntatt helligdager.9) 5707 Tirsdager - fredager unntatt dag etter helligdag.10) 5708 Trondheim S - Kongsvoll mandager - fredager unntatt helligdager, Kongsvoll - Dombås
tirsdager - lørdager unntatt dag etter helligdag.
11) 5709, 5732, 5733 Tirsdager - lørdager unntatt dag etter helligdag.12) 5718 Trondheim S - Kongsvoll helligdag før hverdag, Kongsvoll - Dombås
hverdag etter helligdag.13) 5719 Hverdag etter helligdag.14) 5730 Trondheim S - Lundamo mandager - fredager unntatt helligdager, Lundamo - Dombås
tirsdager - lørdager unntatt dag etter helligdag.15) 5734 Onsdager, torsdager og fredager unntatt helligdager og dag etter helligdag.
Kjøres bare etter særskilt kunngjøring.16) 5735 Tirsdager - fredager unntatt dag etter helligdag. Kjøres bare etter særskilt kunngjøring.17) 5736 Lørdager unntatt dag etter helligdag. Kjøres bare etter særskilt kunngjøring.18) 5738 Søndager unntatt dag etter helligdag.
19) 5917, 5938 Søndager.20) 5920 Tirsdager.21) 5931 Lørdager.22) 5933 Dombås - Fokstua mandager - torsdager unntatt helligdager og dag før helligdag,
Fokstua - Trondheim S tirsdager - fredager unntatt helligdager og dag etter helligdag.23) 5935 Tirsdager - fredager unntatt helligdager og dag etter helligdag.24) 5937 Dombås - Garli helligdag før hverdag, Garli - Trondheim S hverdag etter helligdag.25) 5939 Dombås - Fokstua helligdag før hverdag, Fokstua - Trondheim S hverdag etter helligdag.26) 12344, 12347 Onsdager.
Funkwerk IT TrainPlan 2.14.10.1 (Patch 10+) Side 1 of 4 Utskrift: 19.10.2011 14:11
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
73
Bibliography Bates, J., & John Polak, P. J. (2001). The valaution of relaibility for personal travel.
Transportation research part E 37 , 191-229.
Carey, M. (1999). Ex ante heuristic measures of schedule reliability. Transportation Research
Part B 33 , 473–494.
Carney and Mew, K. (2003). Airport governance reform: a strategic management
perspective. Journal of Air Transport Management, 9 , 221–232.
Carvile, M. C. (2003). Scheduling and Platforming trains at busy complex stations.
Transportation Research Part A -37 , 195-224.
Gibson, S. C. (2002). The evolution of capacity charges on the UK rail network. Journal of
Transport Economics and Policy 36 , 341-354.
Gylee, M. (1994). Punctuality analyses—a basis for monitoring and investment in a
liberalized railway systems. Proceedings of Seminars held at the 22nd European Transport
Conference P384 (9), (pp. 153-165).
H. samuel. (1961). Railway operating principle. London : stapels printers limited .
Hansen, I. A. (2001). Improving railway Punctuality by automatic piloting. Intelegent
transport systems conference proceedings (pp. 792-797). Oackland Ca USA: IEEE.
Harris, N. G. (1992). Punctuality and Performance. In N. G. Godward, Planning Passenger
Railways : a Handbook (pp. 130-142). Derbyshire England: Transport Publishing Co. Ltd.
jernbaneverket. (n.d.). jernbaneverket. Retrieved 04 14, 2012, from
http://www.jernbaneverket.no/no/Jernbanen/Jernbanen-i-tall/
Liebchen, C., & Möhring, R. (2007). The Modeling Power of the Periodic Event Scheduling
Problem: Railway Timetables — and Beyond. In Algorithmic Methods for Railway
Optimization (pp. 3-40). Heidelberg: Springer Berlin.
Nash, C. (2000). Modelling Performance Rail . In D. H. Button, Handbook of Transport
Modeling (pp. 666-675). leeds : Elsevier science ltd.
NHO. (2007). Samferdselsløftet - Næringslivets anbefalinger. Oslo: Næringslivets
Hovedorganisasjon.
Olsson, N., & Haugland, H. (2004). Influencing factors on train punctuality—results from
some. Journal of Transport Policy 11 , 387–397.
TBA49, Master Thesis Master thesis Mignote Beyene, Spring 2012
74
Pachl, J. (2002). Railway operation and Control . Rochester WA: Gorham printing.
Railway Group Standard. (2000). GK/RT0038 Signing of permisible speed and speed
restriction. London: Safety & Standards Directorate.
Rietveld, P. B. (2001). Coping with unreliability in public transportation chains: a case study
for Netherlands. Transportation Research Part A 35 , 539-559.
Rudnicki, A. (1997). Measures of regularity and punctuality in public transport operation.
Transportation systems, preprints of the Eighth International Federation of Automatic
Control 2.
Sætermo, I.-A. F., Olsson, N., & Veiseth, M. (2006). Analyser av infrastruktur-relaterte
forsinkelser på strekningen Asker- Oslo. Trondheim: SINTEF Teknologi og samfunn.
Sascha Albersa, B. K. (2005). Strategic alliances between airlines and airports—theoretical
assessment and practical evidence. Journal of Air Transport Management , 49-58.
Vatn, J. (2008). Maintenance in the Rail Industry. In J. ,. Vatn, Complex System Maintenance
Handbook (pp. 509-531). london: springer.
WEF. (2010). The Global Competitiveness Report 2010-2011. Geneva: World Economic
Forum.