THIRD PARTY INSPECTION SERVICES FOR SUPPLY, FABRICATION.ppt

Date post: 25-Sep-2015
Category:
Upload: suresh-goli
View: 229 times
Download: 3 times
Share this document with a friend
23
STAGES OF INSPECTION FOR CANOPY FOUNDATION INSPECTION MATERIAL INSPECTION FABRICATION INSPECTION. INSPECTION OF MATERIAL AFTER RECEIPT OF SITE. INSPECTION BEFORE CLOSING FALSE CEALING. FINAL INSPECTION.
Transcript
  • THIRD PARTY INSPECTION SERVICES FOR SUPPLY, FABRICATION AND ERECTION OF CANOPY UNDER APSO

    .

  • STAGES OF INSPECTION FOR CANOPY

    FOUNDATION INSPECTION MATERIAL INSPECTIONFABRICATION INSPECTION.INSPECTION OF MATERIAL AFTER RECEIPT OF SITE.INSPECTION BEFORE CLOSING FALSE CEALING.FINAL INSPECTION.

  • FOUNADTION INSPECTION POINTS TO BE COVERED:Excavation measurement as per drawing and lay out.PCC to be checked.TMT steel quantity and quality check.RCC footings and column casting to be checked as per drawing.

  • PLAIN CONCRETE CEMENT(PCC).Mixing of cement ,fine aggregate and course aggregate (1:4:8) as per drawing.Measurement of area as per drawing.

  • REINFORCEMENT Make of TMT steel. Quantity measurement.Ensuring that reinforcement as per drawing or not.

  • RCC Footings Ensuring that mechanical batch mixture used or not.Ensuring that cement make and date of manufacturing as per IOCL specification.Ensuring that vibrator used or not.Ensure that mechanical batch mixture used or not.Ensuring that concrete properly mixed or not.Supervise the footings while construction.Cubes to be casted for lab testing.

  • DATA SHEETAll the data should recorded in this format

  • RAW MATERIAL INSPECTIONEnsure raw material make whether it is approved make or not.Test certificates and Invoices review to ensure genunity of material. Ensure that raw material quantity procured by fabricator is sufficient for particular canopy.

  • FABRICATION INSPECTIONVisual inspection for welding defects.Visual inspection for surface defects.Fabrication as per drawing.

  • INSPECTION DURING ERECTIONMeasurement distance between and across the columns.Fabricated material for particular canopy reached to site or not. Plumb level to columns. Paint after erection.

  • INSPECTION BEFORE CLOSING FALSE CALINGLine and level of dummy fascia.Make of roofing, Thickness and size of roofing. Water gutter leak test. Ensure that gutter made of single aluminum sheet. Electrical cable measurement . Ensuring that no joints in cables. Lemonier as per design or not. Grid for false ceiling.

  • CIVIL WORKSHume pipe measurement. Pump Islands measurement as per drawing.Depth and size of electrical and water chambers.

  • WBMWBM-Water bound macadam.First layer 65mm 40 mm black metal+10 mm red gravel.Second layer 65mm 40 mm black metal+10 mm red gravel.Third layer 1:2:4 concrete 50 mm.Fourth layer river sand bed 50 mm Fifth layer pavers 80 mm thick

  • .Ensure that total WBM thickness 330 mmCheck for the water level of surface.

  • REFERANCE STANDERDSIS 456IS 2062IS 808

  • DOCUMENTATIONTest certificates for structural steel and TMT steel. Invoices for steel, cement, paint quantity to be matched with the quantity used in work.Inspection report for each stage. Photographs at various stages.Cube test reports.PQR and WPS of particular welder.

  • REFERANCE PHOTOGRAPHS.CANOPY ERECTION

  • CANOPY DUMMY FASCIA

  • DUMMY FASCIA SHEET

  • CANOPY 8x18 M2

  • FOUNDATION

  • WBM WORK

  • PUMP ISLANDSAND WATER CHAMBERS

  • ..

    *